Focus on the USA First Flex-Plant-10 goes into operation James Varley reports from El Segundo I n any competition for the world’s most attractive power plant locations, NRG’s El Segundo, on the Pacific Ocean coast, near Los Angeles, would have to be a contender. The new 550 MW combined cycle plant there, inaugurated on 12 September, also establishes new benchmarks for compactness, reduced emissions and noise, ultra low water use and, above all, flexibility, being the first Siemens Flex-Plant-10 to enter operation. The new power plant has two identical multi-shaft power trains, each consisting of an SGen6-1000A generator driven by an SGT6-5000F gas turbine upstream of a NEM DrumPlus HRSG, which provides steam to an SST-800 steam turbine coupled to its own SGen6-100A-2P generator. Control is via an integrated SPPA-T3000 system, with start-up and shut-down automation and stress limiting features. The single-pressure DrumPlus HRSGs (see last month’s issue), combined with a package of other measures, including full capacity steam bypass systems and innovative piping warmup strategies, allow the gas turbines to be run up to full power without restrictions, bringing 300 MW on to the grid in ten minutes, with full power achievable in a further 50 minutes or so. This is in marked contrast to the 12 hour or more start up time required by the 1950s/early 60s-vintage gas fired boiler technology that the new combined cycle facility is replacing. As well as being flexible, permitted for 200 starts per year, the new plant, being combined cycle, also achieves high baseload efficiency, around 49%. This is much better than an November 2013 aeroderivative simple cycle gas turbine peaker, but not as good as a combined cycle with three pressure HRSG. NRG opted for a singlepressure non reheat configuration, at the expense of efficiency, to achieve unrestricted gas turbine start up and maximum operational flexibility, and also to make the plant as compact as possible, as it is a congested site. The fast start technology means that the gas turbine is not held at low load, so a lowemissions power level is reached very soon, resulting in 89% (by weight) less CO per start and 95% less NOx. El Segundo is also the first full implementation of what Siemens calls Clean-Ramp, which means it is able to maintain low emissions (a remarkably low 2 ppm of NOx in the El Segundo case), while ramping steeply, both up and down – a requirement increasingly demanded by regulators as they turn their attention to controlling emissions during transients not just in steady state conditions. Clean-Ramp, which has been tested and partially installed before (eg at Long Island Energy Center, Lakeside and Marsh Landing) but never fully implemented, integrates control of the gas turbine with the SCR so that, for example, “feed forward logic” is used to trigger proactive ammonia injection in the event of an anticipated NOx excursion. Overall, says Richard Loose of Siemens, the new plant has “the operating profile of a peaker, and the emissions profile of a combined cycle”, with a conventional SCR. This makes the plant a particularly good complement for renewables. In fact it could be Surfer’s eye view of El Segundo, one of a new wave of flexible, low emissions, gas fired plants. To the right, unit 3 (retired) and 4. (photo: NEM) argued that such plants are a prerequisite for accommodating large proportions of renewables on the grid. As Michael Peevey, president of the California Public Utilities Commission, said at the 12 September El Segundo dedication ceremony, “we can’t do what we want to do with solar and wind without having plants like this, with quick start and the ability to ‘turn on a dime’ in terms of output.” When the El Segundo repowering was first proposed, back in 2000, the initial plan was to build a 630 MWe 2-on-1 baseload-oriented combined cycle plant with once-through seawater cooling. A permit for such a facility was received in 2005. But subsequently NRG decided to radically revise the design and changed to a rapid response plant with air cooling. This was “in anticipation of then future policies and regulations, such as the California State Water Resources Control Board oncethrough cooling water policy, which was approved in 2010, California Assembly Bill 32, which was adopted in 2006, and California’s associated Renewable Portfolio Standard”, www.modernpowersystems.com | MODERN POWER SYSTEMS 19 Focus on the USA notes George Piantka of NRG. The California once-through policy, and evolving federal regulations, namely §316b of the Clean Water Act, demanded reduced impact on marine life. This “attached significant risk to the economic and regulatory viability of new combined cycle ocean-cooled generation such as originally licensed in 2005 for El Segundo”, while “the Renewable Portfolio Standard placed an increased emphasis on more efficient fast start conventional generation to help integrate and complement the expected large amount of renewable generation capacity rapidly coming onto the grid.” This expectation proved well founded, with, for example, 1.8 GW of renewables added to the California grid in 2011 and 2012 – three times the fossil-fired capacity constructed. A permit application for the revised design was submitted in 2007 and the permit was received in 2010. The air cooling system at El Segundo is not the typical ACC (Air Cooled Condenser), with a number of large fans mounted on a high platform, but is described as an ACHE (Air Cooled Heat Exchanger), which is compact, with a low profile, and is also relatively quiet in operation. The ACHE performs the same function as a typical ACC, but with one major difference, explains Richard Loose: “The ACHE condenses steam exiting the steam turbine at slightly above atmospheric pressure whereas an ACC condenses steam at substantially below atmospheric pressure (vacuum conditions). Steam at higher pressure occupies a lower volume and this in turn allows the ACHE to be substantially smaller in overall size and have a lower profile than a traditional ACC. For plant sites that are space constrained, smaller equipment used for condensing steam is of great benefit.” The use of this small-footprint form of air cooling for steam condensing was an important consideration for NRG because space at the El El Segundo combined cycle plant: the main components (source: Siemens) Segundo site, crammed between a cliff and the ocean, is indeed fairly restricted, and the new plant was constructed while the existing plant continued to operate and other facilities were being demolished in parallel. Space restrictions were also an important factor in the choice of a multi-shaft, rather than single-shaft, configuration for the combined cycle plant. In the case of El Segundo the length of a single-shaft, accommodating gas turbine, generator, clutch and steam turbine, would have been problematic. Another consideration, says Richard Loose, was that “even though the ACHE used is smaller than an ACC it still would not have been practical in a single-shaft arrangement because it would not have fitted on the site without being located remotely from the steam turbine exhaust, which would have resulted in a longer a more geometrically complex exhaust duct.” Air cooling combined with the use of reclaimed waste water and water recycle results in a 90% reduction in potable water use at the site, compared with the retired units 1-3. The plant is also designed to be “zero liquid Clean-Ramp at El Segundo: low emissions while ramping (source: Siemens) 10 300 9 8 7 200 6 5 150 4 100 3 2 50 1 0 13:48 20 13:53 13:58 14:03 14:08 Time 14:13 14:18 0 14:23 14:28 14:33 MODERN POWER SYSTEMS | www.modernpowersystems.com 14:38 Stack NOx, CO (ppmvd @ 15% O2) Combined cycle MW 250 discharge”, with extensive water recycling and reuse. The new combined cycle plant has been constructed on the site of the 1950s vintage El Segundo units 1 and 2 (290 MW each). These were seawater-cooled gas-fired steam boiler units, with oil back up, retired in 2002, and subsequently demolished, with removal of two old oil tanks as well. The repowering has also included improved site landscaping, a more attractive sea wall, and better coastal views thanks to the lower profile of the new plant. Another key factor in being a “good neighbour” in the beach community, within earshot of walkers and cyclists on the Strand, and surfers, is keeping noise to the minimum. Measures have included use of low speed fans in the air cooled heat exchangers, low noise valves, acoustic enclosures, inlet and exhaust silencing baffles and acoustic lagging. Southern California Edison (whose need for new capacity has been exacerbated by premature closure of its San Onofre nuclear station (due to defective replacement steam generators)) has contracted to take the entire output of the new plant via a ten-year PPA. As well as Siemens, the other main contractor on the project was ARB, responsible for construction, while NRG acted as its own EPC contractor, with Worley Parsons providing engineering services. El Segundo is the third Siemens F class based flexible gas fired power plant to have recently entered operation in California, the other two being NRG’s Marsh Landing (open cycle) and NCPA’s Lodi, which is a multi-shaft Flex-Plant-30 with Benson threepressure reheat HRSG (see MPS, Sept 2012). With the coming on line of the new El Segundo combined cycle plant, the 335 MW unit 3, also a seawater-cooled gas-fired steam boiler unit, built in 1964, has been retired. Unit 4, of a similar vintage and capacity, continues to operate, but will close down by the end of 2015 and a second phase of the repowering programme will be implemented. In this second phase the plan is to build about 450 MW of combined cycle and peaking capacity on the sites of units 3 and 4. MPS November 2013