A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Palisade Risk & Decision Analysis Conference A REFINED APPROACH FOR DEFINING CONSTRUCTION PROJECT UNCERTAINTY Slide Slide No. No. 1 1 www.engcomp.ca “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis Palisade Risk & Decision Analysis Conference Outline • Introduction • Project Risk Analysis (PRA) Overview • The ENGCOMP PRA Process • Project Case Study • Wrap-up • Questions “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 2 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Introduction • Who am I? – 1995 U of S Grad – B.Sc. Civil eng. – Consulting Engineer in Heavy Industrial sector – Permission to consult in Saskatchewan, Alberta and British Columbia – Worked for 8 years before starting ENGCOMP in 2004 – Managing projects for over 10 years – Researching project risk for over 6 years “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 3 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 1 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference ENGCOMP Overview Slide No. 4 –Slide No. 4 www.engcomp.ca “A Refined Approach for Defining Construction Project Uncertainty” –Presenter: Jason Mewis, Mewis P.Eng. Palisade Risk & Decision Analysis Conference ENGCOMP Overview • • • • Small Firm – 15 People Founded June 2004 Conducting projects in Sask, Alta, BC and NWT Front End Project Planning (FEPP) with a focus on Cost Engineering • Estimating • Scheduling • Risk Analysis • Cost Control • Heavy Industrial Structural and Mechanical Detail Engineering Find out more about our services on our website “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 5 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Summary of Cost Engineering Services Offered • Preliminary engineering for cost estimating • Detailed Capital Cost Estimate Preparation using • • • • • • • WinEst & Modelogix Labour Rate Analysis Custom Estimate Reports to suit client’s needs Third party independent evaluation and validation Escalation Modeling Support Facilitated Project Planning & Schedule Development Facilitated Risk / Contingency Analysis Cost Control Setup / Budget Conversion “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 6 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 2 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Audience Poll • • • • Owner / Operator Representatives? Consulting Representatives? Engineering Background? Familiar with the Project Management Institute (PMI)? (PMI)? • Familiar with the Association for the Advancement of Cost Engineering (AACE)? (AACE)? • Using Monte Carlo for budgeting on Capital Construction Projects? Projects? “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 7 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Outline • Introduction • Project Risk Analysis (PRA) Overview • The ENGCOMP PRA Process • Project Case Study • Wrap-up • Questions “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 8 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Project Risk Analysis • How is Project Risk Analysis (PRA) typically done? – – – – Qualitative not Quantitative Often conducted after budget approval stage Usually sits on shelf after completion Even with a Risk Manager in place most projects are at risk of failure in terms of Budget & Schedule • Many experts concur that if you don’t do some sort of quantitative analysis, you’re not really doing risk analysis at all and in a lot of cases you may even be wasting your time. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 9 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 3 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference What is Risk Analysis • The evaluation and quantification of uncertainty on a given process where uncertainty is defined as; – “the lack of complete certainty, or the existence of more than one possibility.” – The true outcome/state/result/value is not known. (Ref. “How to Measure Anything – Finding the Value of Intangibles in Business”, Douglas Hubbard.) • Risk is a subset of uncertainty implying a negative outcome, however positive outcomes are also considered in a Project Risk Analysis “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 10 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference What is Risk Analysis To Projects • The evaluation and quantification of uncertainty on Cost and Schedule – What can adversely affect my project? – Does it impact time or money or both? – All estimates and schedules have uncertainty until the project is completed. • Quantification means statistical modeling using Monte Carlo Simulation “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 11 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Why Do Risk Analysis On Projects • An important part of the management of cost and schedule is risk analysis which includes the estimation of contingency and Risk reserve using Monte Carlo Simulation. • Although this concept has been around for many years, it is not widely used on Projects. • In cases where it is used, it is usually only applied to capital cost estimation. • Risk analysis helps you reduce uncertainty in your budget, increasing your likelihood for achieving project success. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 12 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 4 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference The Scrutiny – The process is too subjective – nothing but guesses – The real world is much more complicated – It’s too difficult or costly to accurately quantify risks • Accuracy is not the intent here. • The reality is that any level of uncertainty reduction is beneficial to your project. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 13 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference The Scrutiny • In the scientific world measurement is defined as “a set of observations that reduce uncertainty where the result is expressed as a quantity” (Ref. “How to Measure Anything – Finding the Value of Intangibles in Business”, Douglas W. Hubbard). – Exactness should never be expected – Even a simplistic approach improves your understanding of your level of project definition putting you in a much better position than if you do no analysis at all. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 14 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference The “Risk” of Qualitative (Only) • Pitfalls of not doing a Quantitative analysis; – Financial decisions won’t be as educated – Quantitative analysis usually tells you something you wouldn’t have expected (i.e. project definition is not what you thought) – A qualitative analysis does not tell you the impact of risks on your bottom line – You don’t get the collective project team knowledge of project uncertainty built into your budget. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 15 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 5 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Project Measures of Success • Need to understand what you want in order to set your parameters for project success Quality Cost Schedule “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 16 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Project Life Cycle Concept Scope Definition Design Construction Key to success: • Define the project well and execute according to PMI or similar principles “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 17 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Why Projects Go Wrong • If we know how to execute projects successfully, why do they sometimes fail to meet targets? • Pre-conceived deadlines • Deficiency in project definition • Project execution breakdown • Unusual market conditions • Etc… “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 18 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 6 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Project Definition • • • • • • • Planning & Basic Engineering Cost Estimating Capital Cost Contingency Analysis Schedule Development Project Risk Analysis Field Studies & Investigation Detailed Design / Engineering “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 19 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Typical Scope Development for Construction Projects Process Design / Conceptual Planning Facilitated Planning Session Basic Engineering Project Schedule Finalize Project Scope Evaluate Schedule vs Scope Evaluate Cost vs Scope Capital Cost Estimate Develop Risk Register Contingency Analysis Project Risk Analysis - Conceptual Drawings - Major Equipment Specifications - Engineering Scope Of Work - Cost Estimate with Confidence Level - Schedule Milestones with Confidence Level Proceed to Detailed Engineering Phase “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 20 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Outline • Introduction • Project Risk Analysis (PRA) Overview • The ENGCOMP PRA Process • Project Case Study • Wrap-up • Questions “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 21 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 7 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Budget Definition • 5 Types of Costs in Budget; – Detailed estimate - has some level of definition and its amount has some level of backback-up for its quantification. quantification. – Allowances Allowances-- can be defined but there is no detailed back--up (drawings or specifications) for it’s back quantification – Contingency - allows for all the construction items you couldn’t define or quantify at the given project stage – Risk Reserve - this portion of the budget does not account for any items that are required to be built – Escalation – Accounting for future cost of amounts estimated today “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 22 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Two Types of Analysis • ENGCOMP has developed the process into two parts – Contingency Analysis & Project Risk Analysis – Contingency Analysis accounts for the variability of cost items in the cost estimate and yields the appropriate contingency for your project • This is most often where quantitative analysis on projects stops in our industry. – Project Risk Analysis accounts for the same information as the contingency analysis but takes it to the next level by incorporating the impact of schedule variability and outside risks yielding the Risk Reserve, Schedule Contingency and Project Cash Flow. Flow. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 23 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Contingency Analysis • The objective is to determine an appropriate amount of contingency to be applied to the project with a given level of confidence that the budget will not be exceeded. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 24 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 8 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Capital Cost Contingency Analysis • Monte Carlo Simulation of Cost Estimate. – Used to establish Contingency based on a required level of confidence. • Model is based on a summary of the total cost estimate; – Usually rolled up into 20 or 30 lines. • Spreadsheet Based Model (MS Excel) – Can tailor the analysis around any existing spreadsheet based estimate / model. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 25 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Capital Cost Contingency Analysis • Process: • – Study the cost estimate (if not developed by ENGCOMP) – Develop Input Model based on summary of estimate – Calibrate Project Planning Team – Facilitate meeting with Project Team to identify Variability in the model (Triangular Distributions) – Run simulation – Generate Results Total Duration: – 1 to 4 weeks work depending on complexity. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 26 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Calibration Training • Process developed by Doug Hubbard, owner of Hubbard Decision Research • Area of research - JDM Psychology • Research has shown that most people, especially professionals, are weak at estimating uncertainty • The good news is that studies also show that measuring your own uncertainty about a quantity is a general skill that can be taught with a measurable improvement • Training can “calibrate” people so that of all the times they say they are 90% confident, they will be right 90% of the time “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 27 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 9 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Triangular Input Distributions • Triangular distributions used to simulate the input variability • Add variability to the model by using a P5/P95 estimating philosophy… • @Risk Trigen PDF “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 28 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference How a Simulation Works MARGIN Lower Bound From Class Code DESCRIPTION % Min % Max -15% -30% -23% -30% -23% -30% -10% -10% -15% -23% 20% 50% 35% 50% 35% 50% 13% 13% 20% 35% ESTIMATE Expected Value MONTE CARLO ANALYSIS Triangular Distribution Std Dev., Model Distribution Upper Bound Mean, Direct Costs A1 - Demolition SPF A2 - Restoration SPF B1 - Demolition ECF B2 - Restoration ECF C1 - Demolition CHF C2 - Restoration CHF D1 - Insulation Removal (Non-Asb) D2 - Asbestos Abatement E1 - Ash Lagoons E2 - Canals Total Direct Costs • • • • -19% $4,647,578 $5,467,738 $6,561,286 $935,598 $1,336,569 $2,004,854 $1,533,577 $1,991,658 $2,688,739 $3,220 $4,600 $6,900 $499,748 $649,023 $876,181 $70,533 $100,762 $151,143 $3,487,576 $4,103,030 $4,923,636 $15,424,667 $18,146,667 $21,776,000 $10,624,695 $13,798,305 $18,627,712 $1,120,350 $1,455,000 $1,964,250 $38,347,541 $47,053,353 $59,580,701 $5,558,869 $1,425,675 $2,071,323 $4,907 $674,984 $107,479 $4,171,415 $18,449,106 $14,350,245 $1,513,199 $48,327,201 $392,001 $220,546 $237,499 $759 $77,395 $16,627 $294,167 $1,300,984 $1,645,389 $173,504 $2,207,095 $5,558,867 $1,425,674 $2,071,325 $4,907 $674,984 $107,479 $4,171,414 $18,449,111 $14,350,237 $1,513,200 $48,327,198 Randomly generates a number from each input distribution Performs model calculations Records value for output distribution Repeats these steps for given number of iterations “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 29 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Risk Analysis Output Report Output CLIENT NAME: PROJECT NO.: PROJECT NAME: PLANT LOCATION: CASE: R es ults Simulatio n Results for Con tingen cy An alysis Contingency @ 75% Confidence = Contingency @ 80% Confidence = Contingency @ 85% Confidence = Contingency @ 90% Confidence = Distribution for TOTAL T/X57 1 .60 0 Work book Name Mea n=7.15 89 4E+07 1 .40 0 Values in 10^ -7 72 77 82 Statis tic Values in Millions 6 6 .8 6 11 9 0% 76 .33 02 Values in 10^ -7 67 72 77 82 Values in Millions 0.400 Re gr es s io n S en s itiv ity for TO T A L T/ X 57 67 72 77 82 Values in Millions 90% 66.8611 5% 76.3302 D - Contracto r I ndirects (. ../ X32 Asbestos D2 - Asbesto Abatem s Abatement ent / .. ./ X22 AshE1Lagoons - Ash Lagoo / M odel ns D. .. /X23 Contractor D - Contracto Fees (10% r Fees D.. ./ X33 .141 Dem A1 oli- tiDemol on S PF ition / Mode. SP F ../ X15 .139 Insul D1ati - Ion nsulation Remo valRem (N...oval /X 21 . 104 Dem B1 oli- tion Demol ECF itio/ n Mo E CF de... /X 17 .084 ABC - Con tractor Indi . .. /X28 rects . 078 Restorati A2 - Restoration on S PF / Mod. SP F.. /X16 . 078 E&PM D Fee E &P(4% M -Fee D&I ) / Mo. .. /X34 .062 E2 - Canals / Mo del Di stri ... /X 24 .061 En ABC g & -PEng M F ee & PM (8%Fee D&I. ../ X30 .055 Contractor ABC - ConFees tractor (10% Fees .. ./ X29 .055 Owners E - Owners Cost (7.Cost 5% D&I). ../ X37 .048 E - E &P M FPee lanni inclng.. Pl anning ./ X36 .045 D - Owners D - Owners Cost (2% Cost D&I) /.. ./ X35 . 031 -1 $66, 861,136 10% 15% $67, 949,680 $68, 654,392 $2, 829, 246 20% $69, 173,256 8.00463E+12 25% $69, 634,912 Skewnes s 0.068250638 30% $70, 025,688 Kurt osis 2.780789922 35% $70, 444,368 Median $71, 522,120 40% $70, 810,040 Mode Left X $70, 271,496 $66, 861,136 45% 50% $71, 150,264 $71, 522,120 5% 55% $71, 909,968 $76, 330,160 60% $72, 280,816 Right P 0 .0 00 62 -0.7 5 -0.5 -0 .25 0 0.2 5 S td b C oe ffi cie n ts 95% 65% $72, 690,032 Dif f X $9, 469, 024 70% $73, 105,176 Dif f P 90% 75% 0 80% Filter Min 85% Filter Max #Filt ered 0 90% 95% #Errors . 469 .46 Ra nk . 35 D - Cont ractor Indirec ts (50% Direct Labr) 0.469 D2 - As bestos Abatement E 1 - Ash Lagoons 0.459 0.290 #4 0.75 1 Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. R egr #1 #5 0.5 Se nsitiv ity Na me #2 #3 #6 “A Refined Approach for Defining Construction Project Uncertainty” Va lue 5% $81, 071,584 $71, 589,398 Variance Right X 0 .2 00 % tile $63, 366,916 Std Dev Left P 0 .4 00 5% 00:02: 45 1444223627 Max imum Mean 0 .6 00 0.000 62 24/11/2003 23:17 Summ ar y Statist ic s Value Mini mum 5% Mea n=7 .1 5894 E+07 0 .8 00 0.200 24/11/2003 23:14 Simulation Duration Random Seed 5% 0.600 Lat in Hypercube Simulation Start Time Simulation Stop Time 67 Distribution for TOTAL T/X57 0.800 1 Sampling Type 0 .40 0 1 .0 00 1.000 21 Number of Outputs 0 .80 0 0 .60 0 Mean=7.15894E+07 1.200 7.07% 8.10% 1 5000 Number of Inputs 1 .00 0 0 .00 0 62 Distribution for TOTAL T/X57 1.400 5.59% 6.30% $4, 925, 836 $5, 643, 852 Wab Dec om St udy P1 CCE (AMEC Format).xls Number of Simulations Number of Iterations 1 .20 0 0 .20 0 1.600 $3, 894, 756 $4, 385, 484 Summ ary Inform ation D - Cont ractor Fees (10% D&I) A 1 - Demolition SP F E - Owners Cost (7.5% D&I ) 0.141 0.128 0.109 $73, 530,200 $74, 020,928 $74, 561,280 $75, 279,296 $76, 330,160 C or r 0.664 0.693 0.398 0.317 0.170 0.247 #7 E - E&PM Fee incl Planning (7% D&I) 0.106 0.244 #8 #9 D1 - I ns ulation Removal (Non-Asb) A BC - Contract or Indirects (50% Direc t Labr) 0.103 0.091 0.362 0.127 #10 B 1 - Demolition ECF 0.073 0.126 #11 A BC - Eng & PM Fee (8% D&I ) 0.068 0.115 Slide No. 30 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 10 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference How to Use the Results Statistic Summary Statistics Value %tile $62,089,936 5% $66,755,652 Maximum $82,333,624 10% $67,880,376 Mean $71,911,390 15% $68,557,096 $3,143,501 20% $69,235,000 Variance 9.8816E+12 25% $69,711,912 Skewness 0.054253676 30% $70,235,208 Kurtosis 2.850267143 35% $70,668,328 Median $71,928,368 40% $71,126,992 Mode $69,448,288 45% $71,539,608 Left X $66,755,652 50% $71,928,368 Left P 5% 55% $72,297,720 $77,156,136 60% $72,696,424 Std Dev Right X Right P 95% 65% $73,075,776 Diff X $10,400,484 70% $73,502,744 Diff P 90% 75% $74,043,016 0 80% $74,559,520 Filter Min 85% $75,192,976 Filter Max 90% $75,935,504 95% $77,156,136 #Errors #Filtered 0 • Establish desired Value Minimum Level of Confidence and use the corresponding number • Review the summary statistics to establish the level of risk – Higher Std Dev = Greater risk “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 31 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Contingency Analysis • Contingencies at Varying LOC Results Contingency @ 55% Confidence = $29,494,000 22.9% Contingency @ 65% Confidence = $32,625,000 25.4% Contingency @ 75% Confidence = $36,134,000 28.1% Contingency @ 85% Confidence = $41,112,000 32.0% Contingency @ 95% Confidence = $48,942,000 38.1% “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 32 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference How to Use the Results • Use the S-Curve as a graphical representation of the possible outcomes • More usable format than the histogram Distribution for TOTAL T/X57 1.000 Mean=7.191139E+07 0.800 0.600 0.400 0.200 0.000 60 66.25 72.5 78.75 85 Values in Millions 5% 66.7557 90% “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. 77.1561 5% Slide No. 33 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 11 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference How to Use the Results • Use the Tornado Regression Sensitivity for TOTAL T/X57 E1 - Ash Lagoons / Model D.../X23 D - Contractor Indirects (.../X32 D2 - Asbestos Abatement / .../X22 D - Contractor Fees (10% D.../X33 A1 - Demolition SPF / Mode.../X15 D1 - Insulation Removal (N.../X21 B1 - Demolition ECF / Mode.../X17 ABC - Contractor Indirects.../X28 A2 - Restoration SPF / Mod.../X16 D - E&PM Fee (4% D&I) / Mo.../X34 E2 - Canals / Model Distri.../X24 ABC - Eng & PM Fee (8% D&I.../X30 ABC - Contractor Fees (10%.../X29 E - Owners Cost (7.5% D&I).../X37 E - E&PM Fee incl Planning.../X36 D - Owners Cost (2% D&I) /.../X35 -1 -0.75 -0.5 Graph to establish which variables have the greatest influence • Can be a useful tool for managing to risk or conducting further analysis .523 .422 .414 .127 .125 .094 .076 .07 .07 .056 .055 .05 .05 .043 .041 .028 -0.25 0 0.25 Std b Coefficients 0.5 0.75 1 “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 34 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Output Comparison Contingency Analysis Comparisson • Run multiple $45,000,000 17.0% 16.0% 15.0% $35,000,000 13.0% 14.0% 12.0% i Contingency simulations with different conditions and compare the results • Provides confidence in the model and helps with the decision process $40,000,000 $30,000,000 11.0% 10.0% $25,000,000 9.0% 8.0% $20,000,000 7.0% 6.0% $15,000,000 5.0% 4.0% $10,000,000 3.0% 2.0% $5,000,000 1.0% $0 0.0% P50 P60 P70 P80 P90 Level of Confidence Bars = Cost Lines = Percent No Correlations, Input PDFs @ P15 & P85 - 15,000 Iterations, 1 Simulation No Correlations, Input PDFs @ P10 & P90, 15,000 Iterations, 1 Simulation With Correlations, Input PDFs @ P15 & P85, 15,000 Iterations, 1 Simulation With Correlations, Input PDFs @ P10 & P90, 15,000 Iterations, 1 Simulation “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 35 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Contingency Breakdown Approximate Con ngenc y Br eakdown For Tot al Pr oj ect Cos t Total P rojec t Contingency @ 85% Confidenc e Level = $41,112,129 (32% of Tot al Capital Cos t) P MO & C o n su ltan t To tal 1. 2% De m o D 14 1 To tal 1 .4% In te rim M ove s T otal -3 .0% O ffice R en o s Tot al 1 8 .6% D ec o n t D1 4 1 Total 14 .2 % De m o D 1 91 B To ta l 0 .2 % W e st B ay Flo or Total 5 .7 % Cafe te r ia To tal 2 .0 % W e st B ay En c lo su re To tal 1 5 .0% De c o n t D2 13 , D2 6 4 , D2 65 Total 2 4.0 % Elec tr op la ng Tot al 1 5 .6% CA NTA SS En c los ur e To tal 4 .0 % D em o D2 1 3, D2 64 , D 26 5 Total 1 .1% “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 36 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 12 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Project Risk Analysis • Monte Carlo Simulation of Project Schedule. • – Used to develop project risk budget called Risk Reserve and schedule Contingency – Also used to establish milestone dates based on a required Level of Confidence. – Incorporates variability and uncertainty (Risk Register, cost variability & schedule variability). – Can model the effects of schedule on cost. Schedule Based Model (MS Project) – Can convert P3 schedules to MS Project for the analysis if required. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 37 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Project Risk Analysis • Process: – Study the existing schedule (if not developed by ENGCOMP) – Prepare the analysis model based on the master schedule – Calibrate Planning Team – Facilitate meeting with Project Team to identify Variability in the model (Triangular Distributions) – Facilitate Risk Brainstorming session with Project Team – Create Risk Register – Build all risk factors into the analysis model – Run simulation & Generate Results • Total Duration: – 2 to 12 weeks work depending on complexity. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 38 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Project Risk Analysis • Schedule Review & RollRoll-up Task Name Project Administration and Management (PMO) WP10: West Bay WP10 COMPLETE WP13: Cafeteria &Admin WP13.3 WP13.2: Admin. Area WP13.1: Cafeteria Fit-Up WP13 COMPLETE WP11: New Electroplating and WTP/Deconstruction and Decommissioning Duration 1360 days 1261 days 1221 days 1360 days 900 days 637 days 740 days WP9g: Deconstruct D191B 140 days WP9 COMPLETE 4/9 0 days 740 days WP9d: Deconstruct D141 PHASE IV COMPLETE 11/21 0 days WP11b: Deconstruction and Decommissioning of D213, D264, D265 WP 11 COMPLETE 8/2 1261 days 255 days WP11a: ElectroPlating &WTP Facility WP9: Deconsruction of D141 &D191B 2008 2009 2010 2011 2012 2013 O ND J F M A M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O ND J F M A M J J A S O N D J F MA M J J A S O 1182 days 0 days 0 days 11/23 0 days “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. 4/9 Slide No. 39 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 13 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Project Variability Brainstorming Group • Identify schedule variability 00 - Milestones 01 - Surface Drilling, Piling, Excavations/Materials Movement 02 - Surface Equipment/Plant/Conveyor Purchases 03 - Surface Conveyor/Sizer System Installation 04 - Surface Dewatering Installation 05 - Cat U/G Mobile Equipment Purchases 06 - U/G Drills/Ground support Equip. Purchases 07 - U/G Misc Equipment Puchases 08 - Conveyor Ramp Development 09 - Total U/G Shop Costs 10 - Access Ramp Development 11 - Bored Raises 12 - Drop Raises 13 - Level Development 14 - Watse X-Cuts 15 - Mine Contractor Indirects/Support 16 - Diamond Drilling 17 - Kimberlite Development 18 - Koala FAR #2 Vent System with Heat Recovery 19 - Misc U/G Ventilation 20 - U/G Material Handling System Purchases 21 - U/G Conveyor Installation 22 - U/G Infrastructure Purchase 23 - U/G Sump Construction 24 - U/G Misc Installation 25 - Owner's Manpower 26 - Owner's Consultant 27 - Owner's Fuel 28 - Owner's Freight 29 - Owner's Accommodation/Flights 30 - Equipment Operation & Maintenance 31 - Explosives 32 - Power 33 - Operations During Capital Period Total Duration 1377 days 822 days 1136 days 974 days 904 days 666 days 1142 days 733 days 484 days 1035 days 554 days 252 days 352 days 1078 days 873 days 1154 days 389 days 831 days 720 days 497 days 479 days 472 days 581 days 414 days 1329 days 1006 days 1338 days 273 days 1107 days 273 days 1065 days 273 days 822 days 365 days Start Date 1 Nov 04 1 Aug 05 1 Jun 05 2 Sep 05 12 Aug 05 2 May 05 2 Jan 05 3 Mar 05 5 Jan 06 16 Sep 05 1 Aug 05 24 Nov 05 17 Dec 06 3 Mar 05 1 Aug 05 2 Mar 05 13 Dec 05 6 Jan 06 4 Mar 06 4 Mar 06 4 Mar 06 27 Dec 06 2 Aug 05 1 Jun 06 1 Oct 05 1 Aug 05 1 Nov 04 1 Aug 05 2 Aug 05 1 Aug 05 31 Jul 05 1 Aug 05 1 Aug 05 1 Jul 06 “A Refined Approach for Defining Construction Project Uncertainty” Finish Date 8 Aug 08 31 Oct 07 10 Jul 08 2 May 08 1 Feb 08 26 Feb 07 17 Feb 08 5 Mar 07 3 May 07 16 Jul 08 5 Feb 07 2 Aug 06 3 Dec 07 13 Feb 08 21 Dec 07 29 Apr 08 5 Jan 07 15 Apr 08 21 Feb 08 13 Jul 07 25 Jun 07 11 Apr 08 5 Mar 07 19 Jul 07 21 May 09 2 May 08 30 Jun 08 30 Apr 06 12 Aug 08 30 Apr 06 30 Jun 08 30 Apr 06 31 Oct 07 30 Jun 07 %Under %Over -10 -5 -10 -10 n/a n/a n/a -10 -30 -10 -20 -20 -15 -15 50 20 30 50 n/a n/a n/a 25 30 25 50 50 30 30 -10 -20 -10 n/a 100 30 20 n/a -10 n/a -10 -10 30 n/a 30 30 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a Slide No. 40 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Project Risk Analysis • Risk Brainstorming – 73 risks were brainstormed but only 10 were quantified for the analysis “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 41 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference - Have historical data (But it needs to be evaluated in terms of applicability. - Also have record of days not traveled due to weather 2 L oss of Air Freight Capability 3 Cem en t Powder Availability 4 Geolog y Imp act - "GeoCatastrophy" RAN K B ACK GROUND Ice Road Availability SCORE D ESCRIPTION LIKELIHOOD 1 CONSEQUENCE ITEM NO 2 2 4 3 1 3 3 N /A 1 1 1 N /A PROBAB ILITY OF OCCURANCE Risk Register SCORING (1-Low, 3-Hig h) 9 1 0.1 Crossing the Giant Fault - Cost - 2 x cost/m affecting 100m of development per level x 2 levels - Schedule Impact - Triang(0months, 1month, 4months) Largest impact is on schedule Unstable Ground - Cost: 2 x total cost of excavation - Schedule: 1 month delay Run into "Blocky" unstable ground conditions at major excavation. - Low Probability. - May have to re-design the the mining layout, but likely will just have to spend more time and money on rock bolting and other ground support measures. Pillar Instability in Kimberlite 5 Manp ower Availability / Produ ctivity Impacts R elates to Dramatic change in productivity due to other industry demands. May result in lack of skilled resources or just qty of resources. 2 3 6 2 6 L oss / Damage of freight in tran sp ort Includes things such as truck roll-over, ship sinking, damage in transfering the load, etc. 2 1 2 N /A 7 Materials Managemen t on Site - Loss of items / stock to other operations, waste, etc. 1 3 3 N /A 8 Force Majeure Relatin g to Sup plier / Co ntracto r Delivery 3 1 3 4 9 Ekati Services no t Performing 2 1 2 N /A 3 1 3 5 10 Operations people at Ekati may be too busy with other work to provide heavy equipment support to the project as needed. If the freight doesn't make it in on the ice road the majority of the shipments can be transported using the Hercules T ransport Plane. - Max C argo = 40,000 lbs - Max D imensions = 8'H x 9'W x 52'W - Costs $1.00/kg to fly from Yellowknife and $0.14/kg to truck from Yellowknife Score is too low to consider in the analysis. The risk will be controled through mitigation measures. 0.5 3 NOTES Score is too low to consider in the analysis. The risk will be controled through mitigation measures. - Water inflows, poor ground stability, etc. 3 IMPACT - Start and End Dates will be a probability density function based on historical records. - If we miss the ice road it will add $0.84 / kg to the cost of freight and 1 month to the delivery schedule. Group decided that this would not be a significant risk during the capital period. In 2007 & 2008 (2006 productivity is f ixed); It was decided that the productivity for 2006 (rates and availability of required Apply a range to the productivity f or labour force with expertise) would be relatively constant. F or the labour in 2007, however, there will be a range of -10% to + 50 % a modification to the labour in the form of a probability density function. Score is too low to consider in the analysis. The risk will be controled through mitigation measures. --> the risk lies in the fact that BHP is not insured for the damage and the trucking company will only cover a certain dollar value per kg. Score is too low to consider in the analysis. The risk will be controled through mitigation measures. 0.05 2 month delay After discu ssio ns aroun d this risk it was decided that the probab ility and imp act were to o low to co nsider in th e project simulation. Score is too low to consider in the analysis. The risk will be controled through mitigation measures. Imp act of Pan da Op eratio ns on Issues around use of Development Equipment, Material Resources & Labour. Ko ala Project. Treat as an allow ance Task with the f ollowing duration distribution; - Triang(2weeks,4weeks,12weeks) - Cost: Duration of this task will directly increase the duration/cost of owner's and contractor's indirects. If there's a problem that affects the operations at Panda and the construction at Koala, all available resources will be given to Panda to maintain the operations. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 42 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 14 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Modeling Risk Tools within @Risk for MS Project for modeling risk; • Probabilistic Branching: Probabilistic branching lets a project branch from one task to any number of other tasks during simulation. Account for chance events in your project plans and see the impact on your outputs! • IF/THEN Conditional Branching: Build logic into your project plans. With IF/THEN Conditional Branching, if a pre-defined condition occurs during simulation, @RISK for Project will change a project value or branch to another task. Control values and branching between tasks using logic statements that you define! • Probabilistic Calendars: Often you need to model the probability of work stoppages due to weather, strikes, or other unforeseen events. By setting up Probabilistic Calendars with @RISK for Project, you can apply working and nonworking probabilities to any calendar event in Project! • Global Variables: Global variables can be used to hold values that can be referenced in @RISK for Project calculations in your project. Variables may be defined as probability distributions, single fixed values, or even IF/THEN conditions that reference other variables. Variables are not attached to a specific task or field; they are attached to the project as a whole. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 43 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Example Risk Analysis Model Triangular Input Distribution for Schedule Duration (Schedule Variability Brainstorming Session) Gantt Chart Data Type Task Description Analysis Analysis Analysis 45 Analysis W eather Risk (30 % Proba bility of Occurrin g) 90 30 60 1 20 2 40 90 60 90 1 80 30 15 30 90 90 Base Analysis 1 50 1 20 Base Analysis 60 30 15 Base Con struction Start Start Date 60 Base Detailed En ginee ring P roject Comp lete Duration (Work Days) EV Max Base P roject Ap proval Con struction Complete Min Base B udget De fin ition 60 90 1 80 Finish Date Apr 20 08 May 200 8 Apr 20 08 Jul 200 8 Schedule Cont. 38 Y Q M 2008 2009 1 Q1 2 3 4 Q2 5 6 7 Q3 8 Q4 9 10 11 12 1 Q1 2 3 4 Q2 5 6 7 Q3 8 0 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Q4 9 10 11 1 2 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 Jun 20 08 Jul 200 8 Jul 20 08 Aug 200 8 Jul 20 08 Nov 200 8 Aug 20 08 Jan 200 9 Nov 20 08 Feb 200 9 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 0 0 0 0 Jan 20 09 May 200 9 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 0 0 0 0 0 0 Feb 20 09 Mar 200 9 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 May 20 09 Jul 200 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 Mar 20 09 Jun 200 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 0 0 0 0 0 0 Jul 20 09 Nov 200 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 0 0 Base Jun 200 9 Analysis Nov 200 9 Conditional Branching for Uncertain Events (Risk Register) 15 60 14 3 –Model also incorporates project costs (Contingency Model) which allows us to determine the impact of schedule variability and outside risks on the budget “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 44 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference ENGCOMP RISC Diagram (Risk Integrated Second SS-Curve) 100% 90 % 85% 80 % 70 % Expected Project Cost Before Contingency 60 % 50 % 40 % Conti nge ncy = $41,112,000 R i sk R eser ve = $24,190,000 30 % 20 % Total Project Cost with Contingency Total Cost w ith Contingency & Project Risk Reserve 10 % 0% “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 45 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 15 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Schedule Analysis Output • Similar output format to cost contingency analysis • Output is in dates and days rather than dollars • Use same logic for calculating the required contingency for the given milestone “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 46 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Project Risk Analysis • Project Completion Statistic – With an 85% LOC the project is expected to be completed on 16 January 2014. Distribution for FMF Cape Breton - Phase IV Part II Proj... 1.000 Summary Statistics Value %tile 1/9/13 5% 25 Apr 2013 Maximum 9/30/14 10% 27 May 2013 Mean 9/30/13 15% 14 Jun 2013 Std Dev 101.6005291 20% Variance 10322.66751 25% Skewness 0.284324135 30% 31 Jul 2013 Kurtosis 2.766652842 35% 14 Aug 2013 9/24/13 40% 28 Aug 2013 45% 10 Sep 2013 50% 24 Sep 2013 Median Mode Mean=9/30/2013 Value Minimum 7/19/13 19 Jul 2013 0.800 Left X 5% 55% 0.600 Right X 3/26/14 60% 22 Oct 2013 Right P 95% 65% 06 Nov 2013 Diff X 335.109375 70% 21 Nov 2013 Diff P 90% 75% 06 Dec 2013 0 80% 25 Dec 2013 Left P 0.400 0.200 #Errors 0.000 10/18/2012 7/12/2013 5% 4/5/2014 90% 4/25/2013 12/28/2014 5% 3/26/2014 4/25/13 03 Jul 2013 08 Oct 2013 Filter Min 85% 16 Jan 2014 Filter Max 90% 14 Feb 2014 95% 26 Mar 2014 #Filtered “A Refined Approach for Defining Construction Project Uncertainty” 0 Slide No. 47 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Schedule Analysis Output • Schedule Contingency Output Summary Task Description Phase IV Total Project Schedule Demolish 191B (Under Current EA) - Planned Completion Sep 2008 TB Approval EPA(R) Phase IV – Planned Milestone Jan 2009 Construction Contract Award (WP10/11/13) – Planned Milestone Apr 2009 Data Type Start Date Duration (Work Days) 277 Apr 2008 Oct 2008 Aug 2008 Mar 2009 80 101 217 Jan 2009 Apr 2009 Feb 2009 May 2009 Analysis Apr 2009 Sep 2009 May 2009 Oct 2009 Analysis Estimate Estimate Analysis Estimate Estimate Apr 2009 Jun 2011 558 Analysis Jul 2009 Nov 2011 621 BOD Electro-Plate Shop – Planned Completion Jul 2011 Estimate Feb 2009 Dec 2010 480 Analysis Jul 2009 Jul 2011 528 BOD Cafeteria & Administration Fit-Up – Planned Completion Oct 2012 Estimate Mar 2012 Aug 2012 120 Analysis Aug 2012 Jan 2013 121 BOD West Bay – Planned Completion Jun 2011 Schedule Contingency 1360 1562 Analysis Jan 2008 Jan 2008 Finish Date Apr 2013 Jan 2014 Estimate Y Q M Gantt Chart 2008 2009 2010 2011 2012 2013 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 155 212 156 “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 48 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 16 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Outline • Introduction • Project Risk Analysis (PRA) Overview • The ENGCOMP PRA Process • Project Case Study • Wrap-up • Questions “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 49 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Case Study • Client: Department of National Defence • Project: Fleet Maintenance Facility Cape Breton Consolidation Phase IV Risk Analysis • Location: Canadian Forces Base Esquimalt, Victoria, BC “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 50 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Background – Goal: consolidate and upgrade the FMF, which are currently smaller facilities spread all over the base, into one large facility. – Project Stage: The project currently sits in the middle of Phase IV execution. DND requested evaluation of the remaining budget and schedule required to complete this phase. – Risk Management Plan: Although there has been risk assessments completed on the project in the past, a true risk analysis, using Monte Carlo simulation, had yet to be completed. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 51 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 17 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • ENGCOMP’s Mandate – Part 1 – Part 2 – Part 3 – Part 4 – Part 5 – – – – – Project Evaluation: Contingency Analysis: Action Plan: Project Risk Analysis: Project Documentation: “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 52 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Part 1 – Project Evaluation: – Information gathering mission. • project documents, toured the facilities, learned about FMF operations and interviewed major stakeholder groups for the project. – The deliverable included recommendations on improvements to project operations and policies. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 53 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Part 2 – Contingency Analysis – Site meetings • estimate review, team calibration and variability brainstorming. – Analysis included preparation of Custom reports to suit the specific requirements of DND. – The outcome was the required project Contingency including evaluation of Escalation. “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 54 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 18 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Part 3 – Action Plan – ENGCOMP provided Facilitated Project Planning Services • Delivered an appropriate schedule and action plan for the rest of Phase IV. – This was required as the basis for the project risk analysis model. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 55 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Part 4 – Project Risk Analysis: – Site meetings with the planning team • schedule variability brainstorming and risk register brainstorming. – Outcome was the project Risk Reserve and Schedule Contingency. – The results were also used to prepare the Project Cash Flow. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 56 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Part 4 – Project Risk Analysis: – Results showed a higher level of uncertainty than expected – Analysis helped to back the PM’s request for funds “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 57 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 19 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Part 5 – Project Documentation – Delivered a complete report outlining Risk analysis methodology – ENGCOMP also provided input into the preparation of an updated Project Profile Risk Assessment report. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 58 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference FMF (CB) Consolidation PRA • Successes – DND is very satisfied with the deliverables – Met with the Senior Review Board at National Defense Headquarters (NDHQ) in Ottawa to deliver the results with the Project Manager – Met with the Financial Analyst at NDHQ to support the DND Project Manager in defending the project budget. – Working with DND to prepare policy on performing this type of project risk analysis for all future DND projects. “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 59 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Outline • Introduction • Project Risk Analysis (PRA) Overview • The ENGCOMP PRA Process • Project Case Study • Wrap-up • Questions “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide No. 60 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 20 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference Measures for Validity of Process – Actual Project Success – Client perception / satisfaction on completion of deliverables? – Secondary benefits; • Congregation of stakeholders (SME) • PM Tools • Highlight areas requiring more work “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 61 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference Where are we going from here? • Alliance with Doug Hubbard – Applied Information Economics (AIE) Approaches to enhance our process – Currently using calibration • Working on concept for using Value of Information Analysis (VIA) • In the future will look into integration of Modern Portfolio Theory “A Refined Approach for Defining Construction Project Uncertainty” Slide No. 62 www.engcomp.ca Presenter: Jason Mewis, P.Eng. P.Eng. Palisade Risk & Decision Analysis Conference QUESTIONS “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide Slide No. No. 63 63 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 21 A Presentation for Palisade Risk & Decision Analysis Conference 2008 – North America 17 November 2008 Palisade Risk & Decision Analysis Conference THANK--YOU! THANK FIND US AT www.engcomp.ca “A Refined Approach for Defining Construction Project Uncertainty” Presenter: Jason Mewis, P.Eng. A Refined Approach for Defining Construction Project Uncertainty Presenter: Jason Mewis, P.Eng. Slide Slide No. No. 64 64 www.engcomp.ca ENGCOMP Copyright 2008 www.engcomp.ca 22