Cassidian Systems SAP based Programme Risk Analysis John Ducker March 2011 April 11 Content • EADS Cassidian Systems - An Overview • The need for a new approach - developing the Solution • Standard Production Models • Source Data • Cost, Effort and Duration Distributions • Cumulative Probabilities • Tracking Planned / Actuals • Understanding the Results • Summary – Closed Loop Model • Conclusion – Comparitive SWOT • Questions. Page 2 April 11 EADS at a glance: A Global Leader • EADS is a global leader in aerospace, defence and related services • €43 billion revenue in 2009 • Workforce of 118,000 Page 3 April 11 EADS Divisions - The Four Firm Walls EADS is built on •A380 Double-Decker Aircraft •A350 extra wide body is the latest addition to the fleet •Airbus Military designs and manufactures special mission aircraft for military and security tasks •Is the world leader in the design and manufacture of satellite systems •Prime contractor to ESA for its major space exploration programme Page 4 •The world’s No.1 manufacturer of civil and parapublic helicopters •Strong worldwide presence through its 18 subsidiaries on 5 continents •Integrated system solutions to meet its customers’ needs for Network Enhanced Capabilities April 11 EADS Employees by Country as of December 31, 2009 France Germany Spain United Kingdom Other Countries 44,760 (37 %) 43,814 (37 %) 10,469 (9 %) 12,733 (11 %) USA 2,512 (2 %) Rest of World 5,218 (4 %) Total Number of Employees: 119,506 Standard Presentation Page 5 17.09.2010 5 April 11 The Cassidian Organisation Page 6 April 11 Cassidian at Newport Merged 3 sites into Newport Campus in 2008. Delivering large scale Change Programmes. Service operation centre supporting operational networks. Hosting critical data centre. EADS centre for Innovation & Research. • Joint venture with Welsh Assembly Government & universities Page 7 April 11 Cassidian at Newport Ectocryp New generation network encryption device EADS PI initiative Transparent operation & HAIPE compliant Varying levels of security for Government and industry Accredited to Top Secret over the internet. Page 8 April 11 Cassidian at Newport Skynet 5 £3.6bn project for Ministry of Defence. Led by Paradigm Secure Communications Ltd with Cassidian (Systems) as a major partner. Page 9 April 11 Cassidian at Newport Cyber Security Growing need for new solutions and products to face cyber threats International Cyber Security Customer Solution Centre opening 2010. Centre will meet the needs of operators of critical IT infrastructure Provides expertise and solutions to detect and respond to complex cyber threats. Page 10 April 11 Cassidian at Newport Defence Information Infrastructure (DII) DII is a key MOD Change Programme EADS part of the ATLAS Consortium providing the providing MoD with an upgraded secure IT infrastructure. Provides 300,000 users in 2,000 locations with a single information network. Page 11 April 11 SAP Based Programme Risk Analysis Note : All numeric data used in this presentation is fictitious and is used only for the purpose of illustrating the general method of analysis. Page 12 April 11 Developing the Solution 1 • Managed Services - Production, Build or Implementation element of the work requires significantly more effort and is riskier than the Design or Support elements. • Client Defined High Level Schedule – Dynamic planning environment due to site readiness factors. • Traditional Gantt based Monte Carlo simulations – difficult to respond to rapidly changing plans. Page 13 April 11 Developing the Solution 2 Contains the cost model, first Extracts SAP areWork analysed in Excel using @Risk Site from Deployment completed according to developed asis the Bid position and Prothe for plan Excel. Output from this analysis feeds both The Site Deployment Plan contains the detailed Classic closed control loop, therefore any and thedeveloped cost other metrics then as the contract The High Level Planand determines, withrecorded client Montein Carlo Simulations ( distribution curves ) and planning information for individual Sites or the perturbations resulting from adjustments to estimates SAP ( SAP Time Bookings ) against the matures with workschedule extensions and input, the production for the(WBS Cost to Complete ( EAC ) process. production units ). Estimated Cost, Effort, are automatically smoothed by feedback established at the previous stage. refined estimates. Thecase Business deliverable elements. Inconstant the of this Duration and Start / Finish dates are included. from the analysis process resulting in automatic Model example takes closed loop ‘ Sites ‘. feedback This data is input into improvement. SAP also baselined continuous from Monte Carloand Simulations and into Excel for futurethe reference and comparison with SAP based analysis actual work performance data. Page 14 April 11 Standardised Unit Production Model Page 15 April 11 Standardised Unit Production Types Page 16 April 11 Example SAP Data Extract Page 17 April 11 Completion Cost Distribution Page 18 April 11 ( Other Distributions ) Normal / Pert Fit 3 Point / Triangular Fit Page 19 April 11 Effort and Duration Distributions Effort Duration Page 20 April 11 Cost to Complete – Cumulative Probability Page 21 April 11 Effort and Duration – Cumulative Probabilities Effort Duration Page 22 April 11 Comparing Actual and Planned Probabilities Page 23 April 11 Tracking Program Performance Page 24 April 11 Tracking Actual / Planned Ratios Page 25 April 11 Understanding the Result ( 1 ) •Sample Size / Early Optimism – Quick Win bias a threat. •Risk and Opportunity Impacts – Actual measured results, no simulations. – Independent of Schedule quality and constraints. – Visible effects on Cost and Effort as well as Duration. •Fitted Distribution – Process Maturity – Correlation of performance figures. – Decreasing Deviation with maturity. •Error Detection – Exceptions readily apparent from unexpected deviation. •Most likely and Statistical Mean – Simple distinction from elementary symmetrical distributions. Page 26 Understanding the Result ( 2 ) •Confidence Intervals – Confidence based on past actual performance. – 3 point estimates readily determined for future applications. •Earned Value Indications – Ratios of Actual / Planned statistical Means provide strong indicators. •Resource Planning – Probability weighted Measures of completion effort and utilisation optimise resource planning. •Estimated Completion Cost – Simple extrapolation and scaling of cost curves provide probability weighted completion estimates. •Trend Analysis – Routine analysis reveals program performance trends in all key domains. Page 27 April 11 DII LARGE SCALE SITE INSTALLATION CONTROL MODEL BAFO Position RFCs Delay Claims( ICDN ) Sequence Changes Labour Rate Changes Contract Increments April 11 Delivered Sites. NS Handover. RFCs Delay Notices ( ICDN ) Network Services ( NS ) Design & Integration ( D & I ) Business Model ATLAS High Level Plan ( Sequence / HLP ) Site IMPL Plans Site IMPL Work Cumulative probability of delivery dates ( ‘ S ‘ Curves ) DII – Closed Loop Process Control. Business Model DII Project Risk Predictive Monte Carlo Register Simulations ( Delay Impacts ) Generates Cost Baseline for given Work - Estimation, Costing, Planning and Estimates calibrated Sequences. against Actuals Risk Management. achieved Costing of Change (RFC Mean &Process). Mode Effort, ‘ Actuals -statistical Using ‘ Probability metrics to calibrate Duration Duration and Distribution Functions Flexible Modelling Assumptions. Utilisation estimates and schedules. values Effort-Driven Model. completion by Site Type Consolidates by Client WBS and EADS @Risk Analysis. Probability Workstream. Cost to Complete. Distributions for Estimation Metrics. Site Effort / Generates Model Cost Form. completed Time metrics Provides Input to the Pricing Workmodels. in Progress Page 28 John Ducker March 2007 SAP Time Bookings ( completed Sites ) Copyright EADS DS UK 2007 v2 Jul 07 April 11 Conclusion - SWOT Analysis 1 Page 29 April 11 Conclusion - SWOT Analysis 2 Page 30 April 11 Conclusion - Overall • Where ‘ Actual ‘ data is available the described method will provide superior accuracy. • Where only ‘ Planned ‘ data is available, Monte Carlo simulation is the best solution. • The ‘ @Risk ‘ Toolset may be used for both types of analysis Page 31 April 11 Risk Management Awards 2010 Best Use of Technology in Risk Management Winner Cassidian Systems ( UK ) ( DII Programme ) Page 32 April 11 QUESTIONS ? Page 33