Risk Management Capability The Critical Link between Quantitative Risk Analysis and Project Approvals - improving the performance of UK MoD equipment procurement projects Martin Hopkinson © Risk Management Capability Limited 2012 UK MoD Equipment Procurement © Risk Management Capability Limited 2012 Slide No: 2 CADMID Project Cycle Equipment Procurement Initial Gate Main Gate Demonstration and Concept Assessment Manufacture In-service Disposal Equipment Support © Risk Management Capability Limited 2012 Slide No: 3 Historic Schedule Performance Project Main Gate Slip Typhoon Nov-87 41% Brimstone Mar-96 64% Jul-96 141% Astute Mar-97 62% ASTOR Jun-99 51% A400M May-00 69% BVRAAM May-00 17% Type 45 Jul-00 46% Typhoon ASTA Oct-00 27% Nimrod MRA4 0 -20% 20% 40% 60% 80% 100% 120% 140% 160% Schedule Slip Moving average of 10 projects Source data: National Audit Office Major Projects Reports 2005 - 2010 © Risk Management Capability Limited 2012 Slide No: 4 Monte Carlo Schedule Risk Models Uncertain outcome of activity durations estimated with probability distributions Min Mode Max Models generally have <200 activities Uncertain effects of risk events estimated with probabilities and impact probability distributions Min Mode Max Variation of milestone dates is driven by Monte Carlo simulation, with results typically shown using s-curves X% Typically, probability distributions are defined using a shape (e.g. Beta Pert) and a three-point estimate © Risk Management Capability Limited 2012 Slide No: 5 Assessment Phase - Risk Reduction Cumulative Probability 100% 90% Main Gate Forecast Initial Gate Forecast 50% 10% Overall Project Cost (£M) or Time (In-service date) © Risk Management Capability Limited 2012 Slide No: 6 Three Point Confidence Forecasts Confidence Forecasts (Percentiles) P10 P50 P90 Cumulative Probability 100% 90% 50% 10% Overall Project Cost (£M) or Time (in-service date) © Risk Management Capability Limited 2012 Slide No: 7 Risk Differentials Risk Differential Consumed = P50C – P50MG P90MG – P50MG Risk Differential 100% 90% Current Forecast 50% Forecast at Main Gate 10% Completion Date © Risk Management Capability Limited 2012 Slide No: 8 Projects Passing Main Gate 2000-04 Project Main Gate RDC A400M May-00 7.3 BVRAAM May-00 2.1 Type 45 Jul-00 6.3 Typhoon ASTA Oct-00 4.0 Tojan & Titan Jan-01 0.9 Bowman Aug-01 0.0 Support Vehicle Nov-01 4.2 NLAW May-02 3.6 Terrier Jul-02 18.4 CIP Oct-02 2.3 LF Anti-tank GW Jan-03 -0.5 Precision Guided Bomb Jun-03 0.5 Panther Jul-03 0.8 GMLRS Aug-03 0.0 Naval EHF/SHF Sat Coms Aug-03 31.0 Soothsayer Aug-03 5.0 C-Vehicle Capability Dec-03 0.8 -4 0 4 8 12 16 20 24 28 32 Risk differential consumed (RDC) -4 0 4 8 © Risk Management Capability Limited 2012 12 16 20 24 28 32 Slide No: 9 Addressing Schedule Performance Risk April 1999 Introduction of Smart Procurement and risk-based confidence forecasts at Main Gate April 2003 Measurements of Risk Management Process Capability These measurements were made by auditing projects using the Project Risk Maturity Model © Risk Management Capability Limited 2012 Slide No: 10 Project Risk Maturity Model Example of a Project at RMM Level 2 100% Level 4 75% Level 3 50% Level 2 25% Level 1 Stakeholders Risk Identification Risk Analysis Risk Responses Project Management © Risk Management Capability Limited 2012 Culture Slide No: 11 Process Capability 2004 - 2004 In the period April 2003 – March 2004, the Project Risk Maturity Model (RMM) was used to measure process capability on 29 of the MoD’s 30 Major Projects RMM Level No. of Projects Level 4 - Natural 3 Level 3 - Normalised 4 Level 2 - Novice 16 Level 1 - Naive 1 © Risk Management Capability Limited 2012 Slide No: 12 Addressing Schedule Performance Risk April 1999 Introduction of Smart Procurement and risk-based confidence forecasts at Main Gate April 2003 Measurements of Risk Management Process Capability April 2004 Main gate approvals conditional upon demonstration of Project Risk Maturity Model Level 3 or greater April 2008 Project Risk Maturity Model demonstrations substituted by Verification and Validation audit of risk models © Risk Management Capability Limited 2012 Slide No: 13 Project Risk Maturity Model From April 2004, projects with a value >£25m had to demonstrate a process capability of RMM Level 3 or greater 100% Level 4 75% Level 3 50% Level 2 25% Level 1 Stakeholders Risk Identification Risk Analysis Risk Responses Project Management © Risk Management Capability Limited 2012 Culture Slide No: 14 Did It Work? Did projects with a higher risk management capability at Main Gate Approval have better outcomes than their predecessors? © Risk Management Capability Limited 2012 Slide No: 15 Trend in Risk Differential Consumed Project Main Gate RDC A400M May-00 7.3 BVRAAM May-00 2.1 Jul-00 6.3 Typhoon ASTA Oct-00 4.0 Tojan & Titan Jan-01 0.9 Bowman Aug-01 0.0 Support Vehicle Nov-01 4.2 NLAW May-02 3.6 Terrier Jul-02 18.4 CIP Oct-02 2.3 LF Anti-tank GW Jan-03 -0.5 Precision Guided Bomb Type 45 Jun-03 0.5 Panther Jul-03 0.8 GMLRS Aug-03 0.0 Naval EHF/SHF Sat Coms Aug-03 31.0 Soothsayer Aug-03 5.0 C-Vehicle Capability Dec-03 0.8 MTADS/PNVS Sep-04 0.3 Watchkeeper Jul-05 0.7 Falcon Mar-06 0.7 Merlin Sustainment Mar-06 0.0 Future Lynx Jun-06 0.0 Advanced Jet Trainer Aug-06 0.7 Future Strat' Tanker Aircraft May-07 0.0 Jul-07 1.3 Feb-08 0.7 Queen Elizabeth Class UK MFS Increment C -4 0 4 8 12 16 20 24 28 32 Risk differential consumed (RDC) Moving average of 10 projects RMM "Level 3+" required Source data: National Audit Office Major Projects Reports up to 2010 -4 0 4 8 12 © Risk Management Capability Limited 2012 16 20 24 28 32 Slide No: 16 Trend in Percentage Delay Project Main Gate Slip Typhoon Nov-87 41% Brimstone Mar-96 64% Nimrod MRA4 Jul-96 141% Astute Mar-97 62% ASTOR Jun-99 51% A400M May-00 69% BVRAAM May-00 17% Type 45 Jul-00 46% Typhoon ASTA Oct-00 27% Tojan & Titan Jan-01 21% Bowman Aug-01 0% Support Vehicle Nov-01 63% NLAW May-02 54% Terrier Jul-02 74% CIP Oct-02 124% LF Anti-tank GW Jan-03 -12% Precision Guided Bomb Jun-03 6% Panther Jul-03 25% GMLRS Aug-03 0% Naval EHF/SHF Sat Coms Aug-03 42% Soothsayer Aug-03 75% C-Vehicle Capability Dec-03 23% MTADS/PNVS Sep-04 8% Watchkeeper Jul-05 10% Falcon Mar-06 12% Merlin Sustainment Mar-06 0% Future Lynx Jun-06 0% Advanced Jet Trainer Aug-06 20% Typhoon Future Capabilty Jan-07 0% Future Strat' Tanker Aircraft May-07 0% Jul-07 10% Feb-08 65% Queen Elizabeth Class UK MFS Increment C -20% 0 20% 40% 60% 80% 100% 120% 140% 160% Schedule Slip Risk-based forecasts introduced Moving average of 10 projects April 04: RMM "Level 3+" required Source data: National Audit Office Major Projects Reports up to 2010 -20% 0 20% 40% 60% 80% © Risk Management Capability Limited 2012 100% 120% 140% 160% Slide No: 17 Conclusions 1. Project risk management can be demonstrated to work 2. Quantitative Risk Analysis can help an organisation to improve its record for achieving project objectives. 3. However, the organisation may also need to implement a process for measuring and improving process capability 4. Setting realistic objectives at the main project approval point is important (projects that missed their schedule objectives continued to underperform) © Risk Management Capability Limited 2012 Slide No: 18 Risk Management Capability Ltd www.rmcapability.com Free pdf downloads of papers and risk management capability sheets © Risk Management Capability Limited 2012 Slide No: 19