@RISK 6.0 for Project Management with Excel Integration Javier Ordonez, Ph.D., PMP

advertisement

@RISK 6.0 for Project Management

with Excel Integration

Javier Ordonez, Ph.D., PMP jordonez@palisade.com

Definitions:

Project Risk & Uncertainty

» Project risk is defined as the possibility that the outcome of an uncertain event affects negatively or positively the cost and time performance of project activities and/or their planned execution

Risk = Consequence x Probability of Occurrence

» Uncertainty is defined as the lack of knowledge about the parameters that characterize the system

Project Risk Analysis

» Schedule Risk Analysis :

• Quantification of uncertainty in activity durations

• Quantification of uncertainty in project duration

• Quantifying the impact of risk events and opportunities

• Allocation and management of contingencies

» Simulation:

• Overcome the limitations of CPM/PERT

• Generates scenarios involving a random set of durations. Each scenario produce a deterministic CPM deterministic schedule.

• At the end, analyze the results of the scenarios to understand the range of variability in project duration

• It requires activity information and distributions

• Can model correlations among activities’ durations

• Can obtain information of how critical is an activity

• Can make use of probabilistic or conditional branching

Risks Events vs. Uncertainty

Uncertainty

$ o Time

Risk Events’ Impacts

Qualitative Risk Analysis

Likelihood

Not Likely

Low

Likelihood

Likely

High Likely

Near

Certainty

Score

1

2

3

4

5

Schedule

Minimal or no impact

Additional activities required; able to meet key dates

Minor schedule slip; will miss need date

Project critical path affected

Cannot achieve key project milestone

Risk Register

Priority Descript ion

Activities

Affected

Cost /

Time

Impact

1

… n

1 2 3 4 5

Consequence

Cost

Minimal or no impact

Budget increase <1%

Budget increase <5%

Budget increase <10%

Budget increase >10%

Technical

Minimal or no impact

Minor performance shortfall, same approach retained

Moderate performance shortfall, but workarounds available

Unacceptable, but workaround available

Unacceptable, no alternatives exist

Score

1

2

3

4

5

The New “@RISK for Project”

» Allows simulation of project schedules using @RISK for Excel

» Modeling is done in Excel vs earlier versions of @RISK for Project where all modeling was done in Microsoft Project

» All scheduling calculations are still done in

Project

» How does this happen?

Excel is a New “View” of a

Project

» A new communication layer between Excel and Project was built

» This allows live updating of schedules in

Project when changes are made in Excel

» Combines the best of two worlds – Excel formulas, functions, graphs and the

Microsoft Project scheduling engine

What does a User Need?

» An installed copy of Excel and the new version of @RISK for Excel that supports project schedules

» An installed copy of Microsoft Project 2003 or higher

» Project schedules in MPP format that they want to analyze for risk

Modeling in the New @RISK

» It’s @RISK for Excel for entering distributions, simulating, fitting, sensitivity analysis, etc.

» Formulas can be used in schedules to link to other calculations in Excel and perform calculations that are very difficult to do in

Project

» Some new modeling tools are available in

Excel that support project-specific functions

(probabilistic branching and calendars, categories, parameter entry tables)

New Project-Specific Features

» Probabilistic Time-Scaled Reports and

Graphs

» Schedule Auditing

» Excel integration will make it much easier to combine cost and schedule risk analysis

» Cost data (typically modeled in Excel) can be easily linked with formulas to the Excel view of the project schedule

@RISK for Excel Capabilities that Were

Missing from @RISK for Project

» Users will now have access to many important capabilities that were not available in earlier versions of @RISK for

Project, including:

- Alternate Parameters

- Improved @RISK 5.x graphing

- Browsing

- Automation API

- @RISK statistics functions

Compatibility with Earlier Versions of @RISK for Project

» When a project that was used with earlier versions of @RISK for Project is opened in

@RISK for Excel:

- All distributions are converted to equivalent

@RISK for Excel functions

- Probabilistic Branching, If-Then conditions,

Variables and Probabilistic Calendars are converted to their Excel equivalents

» Goal is 100% backward compatibility

Simulation – How’s it Done?

» Project takes the values sampled in @RISK for

Excel or calculated with Excel formulas

» Values are sent to Project and the schedule is recalculated using those values

» Results go back to @RISK for Excel

» Thus, all schedule calculations during simulations are done in Project

» This ensures that results are calculated just as an add-in to Project would do

» We did not build our own scheduling engine to replace Project’s

Technical FAQs

» Speed – Many models will simulate faster, some run at same speed

» Linking Workbook to MPP – when a workbook / MPP combo is opened,

@RISK syncs changed values in Project to the workbook in Excel

» Thus, if a schedule is updated in Project without @RISK, Excel will show the updated values

@RISK for Project

15

Working with a Project in Excel

» First, the .MPP file is opened in Excel using the

Open command on the new Project menu in

@RISK for Excel. The schedule, Gantt chart, etc. are imported into Excel.

» Once the schedule is displayed in Excel, the new workbook can be saved

» If the workbook is opened later, the associated

MPP file is automatically opened and linked to the workbook

» You still build your schedules in Project – then use

@RISK for Excel for risk analysis

Benefits of the New @RISK

» Companies can standardize on @RISK for

Excel, and get risk analysis for project schedules too

» One interface, lower learning curve for users

» Easy access to modeling in Excel when working with projects (formulas, charts, functions, etc.)

» Modeling is done better in Excel, not Project

More Benefits

» Localized in Spanish, Portuguese, French,

German, Japanese, and Chinese

» Provides access to other add-ins in Excel

(such as optimizers) for schedules

» Enables combined analysis with other

DecisionTools Suite products

Demo

Download