IDP & BUDGET TIME-SCHEDULE FOR 2009/10 PHASE PREPARATION PHASE (May TO June’09) ACTIVITY RESPONSIBLE OUTPUT TIME FRAME Develop Draft 2010/2011 IDP/OPM Time Schedule IDP Compilation of time schedule for 10/11 budget cycle Budget 2nd week May ‘09 Circulate draft IDP & Budget time schedule for inputs by Stride & IDP Ref. Group IDP June ‘09 Tabling of Draft IDP & Budget time-schedule to All Communities & Council IDP/OPM & Budget End June ‘09 Advertisement of (website, local newspaper and notice board) of time-schedule IDP Reconstitution of Budget Committee Briefing session with Budget Committee Budget Establishment of Section 57 Evaluation Panel for 08/09 final review Analyse the report of the credibility of the 09/10 IDP OPM IDP o Approved 20010/2011 IDP/OPM & Budget Time Schedule End April ‘09 5 days after submission to Council o o o o o Assessment report of the existing level of development Priority issues / problems Understanding of causes of priority issues / problems Strategic analysis report Medium Term Revenue & Expenditure Framework (MTREF) process plan June ‘09 June – Mid July ‘ July ‘09 July ‘09 MTREF process plan to EMT and Budget Committee Analysis phase (June to sept ‘09) MTREF updated via input ex directorates (Considering peoples perception of their problems and needs, but also facts and figures) Portfolio Committee references July ‘09 Budget Aug/Sept.’09 Final review of Section 57 Employees for 08/09 OPM End Aug. ‘09 Evaluate the relevance and impact of new collated data and unexpected events on IDP IKM / IDP Aug. Sept.’09 Stakeholder Engagement Intergovernmental engagement • Engagement with Prov. & Neighbouring • Municipal Entities Analysis of the current situation (internally – organizational capacity) & (externally – service delivery backlogs, crime & unemployment) IDP / Subcouncils Aug / Sept. 09 IDP / PROV Sept. ‘09 IKM / Strat. HR Sept. – Oct.’09 Prepare strategic analysis document IKM Nov.’09 Review and revise SFA’s & objectives and Corporate Scorecard indicators with STRIDE & REF IDP / Budget Budget Hearings o Objectives (for each priority issue) o Strategic options Oct.’09 Oct. ‘09 Budget Capital Budget Briefing with Directorates Strategies PHASE (Oct. – dec. ‘09) ( Formulate solutions to address problems identified in analysis phase – relook SFA) Section 57 Performance Reviews; Completed Performance Plan MTREF outcome MTREF report submitted to MAYCO Operating Budget briefing with Directorates 1st. Strategic Planning session with • MAYCO / EMT • Portfolio Members Review Tariffs, Policies & TMS OPM Oct. ‘09 Budget Early Nov.’09 Budget Mid Nov.’09 IDP / BUDGET Nov. ‘09 Finance End Nov. ‘09 Review Service Menu IDP Nov – Dec. All draft Directorates and Department SDBIP’s and Business Plans to all committees and council IDP Nov – Dev.’09 1 Draft IDP & Capital Budget IDP & Budget S57 Mid-Year Performance Reviews; Completed Performance Plans & Evidence OPM st Review and rationalization of projects, redesigning and upgrading Projects PHASE (Jan. – March ‘10) (Project identification should have direct link to SFA and objectives) Mid Oct. ‘09 2nd Strategic Session • MAYCO / EMT • Portfolio Committee Members 1st Draft Operating Budget Alignment of Provincial and National programs Review five and one year corporate scorecards to all committees and council IDP o Project output, targets and location o Ward allocation projects o Draft Capital Budget Review proposed National and Provincial allocations to the City for incorp. Into the Draft budget for tabling (Provincial and national allocation for 3 years must be available by 20 January) Mid Jan. ‘10 End Jan’10 Jan/Feb. ‘10 IDP & Budget Jan/Feb. ‘10 Budget Feb. ‘10 IDP Feb.’10 SDBIP Beginning of March.’10 continues.../ 2 PHASE Integration Phase (jan. march’10) (Integration of information from sector department & the public in ensuring alignment to the objectives, strategies and resources as well as Prov&Nat development programmes) Approval phase (april – june ‘10) ACTIVITY RESPONSIBLE Integration of sector plans and institutional programs ALL Screening of draft IDP IDP Review Tariffs, Policies & TMA (Total Municipal Accounts) Finance OUTPUT o Intergrated Sectoral Plans o Draft IDP & Budget o Summary of Public Comments TIME FRAME March ‘10 March ‘10 March ‘10 March’10 Tabling of Draft IDP & Budget to all Committees & Council S57 Performance Reviews; Completed Performance Plans OPM Public Comment on Draft IDP & Budget IDP & Budget April ‘10 Consideration of Public Comment IDP & Budget Begin May ‘10 Approval of IDP & Budget by Council IDP & Budget End May ‘10 Submit Copy of Approved IDP to MEC Executive Mayor approves the Service delivery and budget implementation plan IDP 10 days after approved by Council IDP 28 days after the approval of the budget SDBIP noted by Council o Approved IDP & Budget Mid April IDP End June SDBIP to be made public IDP 14 days after approval by Executive Mayor Mayor to approve performance agreements within 28 days after approval of the IDP and budget. Submit to the MEC of local government and make it public within 14 days after approval IDP Office End June ‘10 09/10 Adjustment budget changes submitted to all committees and council IDP Advertisement of (website, local newspaper and notice board) of Target Adjustments IDP 09/10 First Quarter Performance Process Reports to all Committees and Council Approval of target adjustments after adjustment budget End October Promptly after approved adjustment budget Approval of first Quarter Performance Reports Beginning December 09/10 Second Quarter Performance Process Reports to all Committees and Council IDP Approval of second Quarter Performance Reports End January 09/10 January target adjustment process to all committees and council IDP Approval of target adjustments process End March Advertisement of (website, local newspaper and notice board) Targets & Adjustments IDP 09/10 Third Quarter adjustment process reports IDP Approval of third Quarter Performance Reports End May 09/10 March target adjustment process IDP Approval of target adjustments process End May Advertisement of (website, local newspaper and notice board) Targets & Adjustments IDP Fourth Quarter adjustment process reports to all Committees and Council IDP Approval of fourth Quarter Performance Reports End September First Draft Annual report forwarded to Auditor General IDP Approved 08/09 Annual Report of city and municipal entities End Sept. 08/09 Annual Report to all committees and council IDP End January Municipal Entities submit Annual Reports OPM Dec.’09 Annual Report public participation process IDP February month Advertisement of (website, local newspaper and libraries, sub-councils) of annual report IDP 7 days after submission to Council MONITORING & EVALUATION PHASE Promptly after approved adjustment budget Approval of the Oversight report Approval of annual oversight Tabling of the annual oversight report at council PREPERATION PHASE FOR 2010/11 TIMESCHEDULE FOR THE 2011/12 FINANCIAL YEAR (May - June ‘ 10) Promptly after approved adjustment budget End February End March Compilation of time-schedule for 2011/12 financial year in consultation with Budget IDP & Budget May ‘ 10 Circulate draft IDP & Budget time-schedule for inputs by Senior Management IDP & Budget May’10 Ensure that linkages of consultation of both the Budget and the IDP processes take place IDP & Budget May ‘10 Appointment of S57 Evaluation Panel to evaluate 09/10 Performance Plans OPM End May ‘ 10 Drafting of S57 Performance Agreements; Performance Plans & PDP’s OPM End May ‘10