IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES SOUTHWESTERN CROWN OF THE CONTINENT COLLABORATIVE 1. Describe the case studies that reflect large scale/cross boundary activities (landscape level) or how the authority allowed for program integration that may not have been available in the past. What were the issues and goals? The Southwestern Crown of the Continent (SW Crown) is a 1.5 million acre trans-boundary landscape selected for Collaborative Landscape Restoration (CFLR) funding. Both the financial benefits and the financial obligations of being a CFLR project are borne by three National Forests and three different Ranger Districts, which adds to fiscal complexity. The goals of the SWCC are elaborated in the Southwestern Crown of the Continent Landscape Restoration Strategy prepared by the SWCC in 2010. The goals include a variety of fuel reduction, restoration and monitoring objectives that will contribute toward ecological, economic and social sustainability. The restoration goals span the resource spectrum, including forest health, invasives and exotics treatments, fish and wildlife habitat restoration, and watershed improvements through road, trails and site restoration work. The NFRR authority is an ideal and efficient means to address these integrated goals. 2. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? In FY12 the Southwestern Crown Collaborative (SWCC) received $3,093,950 from the Washington Office (WO) for completing high priority fuel reduction, restoration and monitoring work. After consultation with SWCC partners the WO allocated a “special” $906,050 in the budget line item of NFRR with instructions to use these funds as if they were CFLR/CFLN dollars. The flexibility of NFRR use was critical to the success of this special allocation, and it effectively brought the total SWCC CFLR funding to the requested $4 million. The special allocation enabled six different restoration monitoring projects and 24 different restoration projects effectively putting local contractors to work and improving fuel and watershed conditions. For each CFLR dollar the SWCC receives we must match the investment with another dollar. In FY12 $402,140 of NFRR funds were invested by the three national forests contributing to the 1:1 match. CFLR funds and CFLR matching dollars cannot be used for planning. NFRR dollars, however, can be, and in FY12 NFRR funds were critical to advancing a variety of NEPA planning efforts critical to for fuel reduction and restoration needs. 3. Describe the outcomes or on-going status. Did the activity lead to an improved watershed condition within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. In FY12 NFRR contributed to a wide variety of restoration and fuel reduction work as displayed in the following table. Additionally, NFRR funds were invested in six different restoration monitoring projects with five different partners. The projects include socioeconomic monitoring that assesses local contract capture, and fire manager’s perspectives on reduced suppression costs due to fuel reduction; aquatic monitoring including nutrient, total suspended sediment and trout genetic assessments; road restoration vegetation and soils monitoring; and, bird monitoring. This investment leveraged an additional $86,250 of partnership cash or non-cash, in-kind contributions and other federal allocations. USDA FOREST SERVICE Page 1 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES Performance Measure NFRR Funds Contributed To Acres of forest vegetation established Manage noxious weeds and invasive plants Acres of water or soil resources protected, maintained or improved to achieve desired watershed conditions. Acres of lake habitat restored or enhanced Miles of stream habitat restored or enhanced Acres of terrestrial habitat restored or enhanced Unit of measure Acres Acre Units Accomplished That NFRR Contributed To 120 2,899 Acres 231 Acres Miles Acres 3,000 25 3,100 Number of stream crossings constructed or reconstructed to provide for aquatic organism passage Number Miles of property line marked/maintained to standard Miles 36.3 Acres of hazardous fuels treated outside the wildland/urban interface (WUI) to reduce the risk of catastrophic wildland fire Acre 641 Acres of wildland/urban interface (WUI) high priority hazardous fuels treated to reduce the risk of catastrophic wildland fire Acres 875 8 4. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? No 5. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? It was extremely efficient to receive NFRR funds to make up the difference in the SWCC’s CFLR request because the NFRR funds came in one lump sum, but were able to be used for the full range of restoration and monitoring efforts envisioned under the CFLR program. 6. How did the IRR authority change the way activities were selected? The IRR authority did not change the way activities were selected, however, its broad scope and flexibility fit very well with the priority fuel reduction, restoration and monitoring activities selected to implement within the SW Crown. 7. Suggest ways the use of this authority can be improved. No Comment. 8. A GIS map showing specific treatment areas and submit geodatabase files/shapefiles. Spatial data must also be recorded in the FACTS spatial data engine (SDE) and meet existing data dictionary standards. All data reported in FACTS will be recorded in the FACTS spatial data engine by April 15th as required (the majority is already entered). 9. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. NFRR is an efficient tool for implementing integrated restoration and monitoring projects across forest boundaries. 10. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. The following table lists 19 different organizations who directly contributed to the successes of the FY12 SWCC program. USDA FOREST SERVICE Page 2 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES Performance Measure NFRR Funds Contributed To Acres of forest vegetation established Manage noxious weeds and invasive plants Acres of water or soil resources protected, maintained or improved to achieve desired watershed conditions. Acres of lake habitat restored or enhanced Miles of stream habitat restored or enhanced Acres of terrestrial habitat restored or enhanced Number of stream crossings constructed or reconstructed to provide for aquatic organism passage Miles of system trail maintained to standard Miles of system trail improved to standard Acres of hazardous fuels treated outside the wildland/urban interface (WUI) to reduce the risk of catastrophic wildland fire Monitoring Partners Partner Match Swan Ecosystem Center, Montana Conservation Corps Ponderosa Snow Warriors, Blackfoot Challenge, Montana Conservation Corps, Bob Marshall Wilderness Foundation, Clearwater Resource Council $24,000 $76,200 Montana Wilderness Association $2,000 Montana Fish, Wildlife and Parks $70,000 Big Blackfoot Chapter of Trout Unlimited $45,000 Blackfoot Challenge $6,000 Big Blackfoot Chapter of Trout Unlimited $45,000 Back Country Horseman, Ponderosa Snow Warriors, Bob Marshall Wilderness Foundation, Montana Wilderness Association $144,541 National Off Highway Vehicle Conservation Council $16,205 Rocky Mountain Elk Foundation $6,000 Swan Ecosystem Center, University of Montana Biological Station, University of Montana, Ecosystem Management Research Institute, Northwest Connections, Clearwater Resource Council, Montana Fish, Wildlife and Parks, Wildlands CPR $234,610 The Wilderness Society $22,570 Planning – CFLR Coordinator USDA FOREST SERVICE Page 3 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES FLATHEAD NATIONAL FOREST RED BENCH ROAD STORAGE 1. Describe the case studies that reflect large scale/cross boundary activities (landscape level) or how the authority allowed for program integration that may not have been available in the past. What were the issues and goals? This project was relatively small and confined to one tributary watershed in the North Fork of the Flathead River drainage. Some additional flexibility was achieved in the ability to fund this project from a larger combined funding source but the total cost of $23,000 was not out of reach of even the previous traditional funding codes (referred to as BLIs). 2. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? Comparison of this project in respect to its former status prior to NFRR is somewhat misleading as it was in the process of receiving funding as a Legacy Roads and Trails (CMLG) project. See response to question #4 below. 3. Describe the outcomes or on-going status. Did the activity lead to an improved watershed condition within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. The implementation of this work has significantly reduced the risk of culvert and road failure in the future and eliminated several fish barriers. 4. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? This project does not accurately reflect the integration possible through the BLI consolidation as it would have been previously funded with CMLG as a proposed project selected for funding in the Regional CMLG prioritization process. 5. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? NA- See response to #4 above 6. How did the IRR authority change the way activities were selected? We are continuing to develop and refine improvements to our present system for proposing and prioritizing projects for funding in NFRR that address several additional factors beyond accomplishment of targets. 7. Suggest ways the use of this authority can be improved. Traditional targets brought forward into NFRR as well as continued emphasis of additional “soft” targets from Regional programs have reduced effectiveness of the use of this authority. When most of the available NFRR funding needs to be directed toward these targets, it limits our flexibility and ability to address the highest priorities. There is also no assurance that if these targets are not met and funding is applied to other higher priority restoration projects, that NFRR funding levels will remain constant or even what level of decrease would result. There may be a way to balance NFRR and other “soft” or USDA FOREST SERVICE Page 4 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES non-accountable, non-quantitative targets more effectively at the regional level so that Forests can have some variance in target accomplishment from year to year to implement non-traditional restoration projects not reflected in existing NFRR targets. 8. A GIS map showing specific treatment areas and submit geodatabase files/shapefiles. Spatial data must also be recorded in the Forest Service Activity Tracking System (FACTS) spatial data engine (SDE) and meet existing data dictionary standards. Available on request. 9. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. The Forest Aquatics Program Manager can be contacted for more detailed team perspectives on this project. Be aware that this project was very limited in scope and was not a thorough test of the pros/cons of the NFRR pilot. 10. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. No partners were involved with this project. Brief Description of the Red Bench Road Storage Project: Several projects completed on the Flathead National Forest in FY12 exemplify the flexibility and multiple resource benefits of the NFRR Budget Line Item. For example, the Red Bench Road Storage Project will improve 9.9 miles of road, with benefits for fish, wildlife, recreation, and watershed health, while maintaining long-term access for land management. The project is located in the Red Meadow watershed, a tributary to the North Fork Flathead River. Red Meadow Creek and the larger North Fork area provide key habitat grizzly bear and bull trout, both Threatened species. Red Meadow Creek provides important spawning and rearing habitat for migratory bull trout and resident westslope cutthroat trout. Current habitat is exceptional but at risk due to potential culvert failures on the Red Bench Road. This area is also very popular for hiking, hunting, camping, fishing, rafting, huckleberry picking, and a variety of other recreational pursuits. To balance the wide range of resource concerns and uses, the Forest Service is putting the Red Bench Road into long term storage, or Maintenance Level 1 status. This will provide for long term resource protection, but will leave the road prism in place for future management. NFRR provided the flexibility to implement this important project and will help the forest achieve multiple targets. Project Details: Cost: $23,000 Miles of road waterproofed: 9.9 Culverts upgraded to AOP standards: 4 Culverts removed: 2 Berms constructed: 1 Fish barriers removed: 6 USDA FOREST SERVICE Page 5 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES IDAHO PANHANDLE NF, KOOTENAI VALLEY RESOURCE INITIATIVE PROJECT 1. Describe the case studies that reflect large scale/cross boundary activities (landscape level) or how the authority allowed for program integration that may not have been available in the past. What were the issues and goals? The Kootenai Valley Resource Initiative (KVRI), a local collaborative with broad membership and partners, is working with the Idaho Panhandle National Forests to implement the Lower Kootenai River Watershed CFLRP project (KVRI 2011). The treatments proposed are expected to improve water quality and wildlife habitat, improve economic opportunities for local communities, and enhance landscape resistance to severe wildfire, insects, disease, and the effects of climate change. The project will treat nearly 40,000 acres and is expected to create approximately 144 jobs. Forest staff anticipates that the NFRR Authority will fund tangible on-the-ground results as the forest incorporates the authority into out-years. Beginning in fiscal year 2013, the forest expects that the combination of the NFRR Authority with the forest’s Five Year Action Plan, CFLR project, Treasured Landscapes, WCF priorities, and ongoing program of work will result in improvements in specific areas including TS Acres, TSI, Reforestation Acres, Range Vegetation Improved, Soil and Water, Invasive Weeds, Wildlife Habitat, Stream Enhancement, Road Decommissioning, and non-WUI Treatments. 2. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? Though the NFRR Authority did not influence the planning or implementation of the project this year, we expect it will in the future. The flexible nature of NFRR funding means the forest will be able to match CFLN funding in a manner that targets the most-needed work. In the past, for instance, the noxious weeds portion of the NFRW BLI had been low – perhaps lower than needed to treat a particular area. With NFRR funding, the right amount could be allocated to effectively meet the target. Allocating funding to one resource – such as noxious weeds as just described - could come at the expense of other restoration activities, including timber outputs. The table below shows how NFRR funding was used in the Lower Kootenai River Watershed project area to meet the project’s objectives. Project NFRR Funding CFLN Funding Silver Crescent Road Construction and Reconstruction $6,296 $99,500 East Fork Stewardship & Meadow Creek Timber Sales $41,422 0 $37,000 $38,000 $22,584 $40,000 $10,554 $21,022 Timber Stand Improvement Thinning Road Decommissioning Invasive Plant Treatments 3. Describe the outcomes or on-going status. Did the activity lead to an improved watershed condition USDA FOREST SERVICE Page 6 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. This table shows the accomplishments met in the Lower Kootenai River Watershed project area using NFRR funding. The target outputs were achieved in fiscal year 2012. Performance Measure Units Accomplished With NFRR Funds Acres of forest vegetation improved 119 Manage noxious weeds and invasive plants 120.8 Acres of water or soil resources protected, maintained or improved to achieve desired watershed conditions 3 Miles of stream habitat restored or enhanced 1.25 Acres of terrestrial habitat restored or enhanced 10 Acres of rangeland vegetation improved 41.4 Miles of road decommissioned 1.0 Number of stream crossings constructed or reconstructed to provide for aquatic organism passage 2 Acres of wildland/urban interface (WUI) high priority hazardous fuels treated to reduce the risk of catastrophic wildland fire 116.5 4. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? No. 5. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? The advantage of having a single BLI is that funding can be directed and targets set based on what work is needed on the ground. The disadvantage of having a single BLI is that under-funded programs may lose their “protected” funding altogether if other objectives are perceived as being more important, and NFRR funds are diverted to those objectives. This could be especially true if the secondary objectives are not in the same geographic location as larger NFRR projects. 6. How did the IRR authority change the way activities were selected? No change for fiscal year 2012. USDA FOREST SERVICE Page 7 IRR 2012 REPORT | APPENDIX 2 | R1 CASE STUDIES 7. Suggest ways the use of this authority can be improved. 8. A GIS map showing specific treatment areas and submit geodatabase files/shapefiles. Spatial data must also be recorded in the FACTS spatial data engine (SDE) and meet existing data dictionary standards. This will be done as part of the CFLRP Annual Report for the Lower Kootenai River Watershed project. 9. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. Comments and input throughout this report for the IPNF are compilations of thoughts from several employees. The Forest will provide team members’ contact information upon request. We have described the expected benefits of the NFRR Authority above. As a point of discussion with respect to this authority was the potential for the impact that allocating funding to one resource – such as noxious weeds as just described – and how those target accomplishments could come at the expense of other restoration activities, such as timber outputs. While the obvious advantage of having a single BLI is that funding can be directed and targets set based on what work is needed on the ground, the perception is that under-funded programs may lose their “protected” funding altogether if other objectives are perceived as being more important. For example, to meet the standards in the forest plan’s Grizzly Bear Access Amendment, roads need to be decommissioned. If large vegetation management projects do not occur in grizzly bear habitat, funding to decommission roads may not be available. As the Forest realized through the limited implantation of this authority, however, NFRR does not drive targets or accomplishments, and as such the perception is a cultural hold-over from single-item BLI issues. We realize that NFRR authority is designed to eliminate the fencing of funds and provide better application of funding and resources to meet targets across the Forest in a more efficient and timely manner. 10. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. Kootenai Tribe of Idaho Boundary County City of Bonners Ferry Private citizens Landowners Federal and state agencies Conservation/environmental advocacy groups Representatives of business and industry USDA FOREST SERVICE Page 8 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES CORONADO NF INTEGRATED VEGETATION MANAGEMENT PLANNING TEAM The Coronado National Forest utilizes an integrated team to set the Forest’s priorities for vegetation management projects such as prescribed fires and mechanical treatments (e.g. chainsaw thinning and mastication). All vegetation management projects are intended to be included regardless of what the primary purpose(s) of the treatment are. This team consists of representatives from each district as well as forest level specialists. The team evaluates project proposals and makes recommendations to the Forest Leadership Team. The team was established in order to have a planning system to develop projects that are of high quality and integrated across resource boundaries and foster a forest-wide ownership in the program of work. Projects are evaluated on a wide variety of factors including, but not limited to, the watershed condition (as determined by the watershed condition framework), the values at risk, the status of landscape scale analysis, the number and types of treatments and benefits, the partners involved, and their contributions. The implementation of IRR helped to facilitate IVMPT project planning and implementation by essentially removing real or perceived barriers previously imposed by separate fund codes for watershed, wildlife, timber and fuels projects. It did not did not change the mix of outcomes, primarily because the Coronado NF historically had a very little funding in NFTM. The single BLI has advantages in that it encourages integration of natural resource management programs (i.e., vegetation management, wildlife, timber and fuels) from initial program of work planning through implementation and accomplishment. The single BLI increases efficiency. Because of the timing of development of the Forest program of work prior to the beginning of FY12, the IRR authority did not change the way activities were selected in FY’12. In FY ’13 it may increase the number of activities with wildlife habitat benefits. The Coronado began implementing an integrated approach for planning and prioritizing vegetation management projects a few years prior to the IRR Pilot Program. This allowed for a seamless transition to the IRR Program from the planning and implementation standpoint. The Forest Fuels Specialist felt that challenges came with reporting year end accomplishments. Consolidating several BLIs into NFRR created challenges when it came to accomplishment reporting. With individual BLIs for each program (NFVW, NFTM, NFWF) it was easier to filter out core vs. integrated accomplishments, as well as proportion of acres accomplished by performance measure. Consistency between reporting databases also created some challenges (FACTS, WFRP, Workplan, etc.). USDA FOREST SERVICE Page 9 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES This project has a variety of partners that brought different expertise to the table. National Wild Turkey Federation – Stewardship Partner for Pinaleño Ecosystem Restoration Project (PERP) Eastern Arizona College Small Business Development Center – Key in small wood products workshops USFS State and Private Forestry- Partner in small wood market development Northern Arizona Wood Products Association –Partner in small wood market development Gila WoodNet/Restoration Technologies – Partner in small wood market development Center for Cooperative Forest Enterprises/National Network of Forest Practitioners- Lead for economic o Feasibility study of PERP products Graham County - Partner City of Safford - Partner Pinaleño Partnership o (includes: Sky Island Alliance, San Carlos Apache Tribe Elders Council, White Mountain Apache Tribe Heritage Program, FWS, AZG&FD, Gila Watershed Partnership, Old Columbine Summer Home Owners, Turkey Flat Summer home Owners, lots of individual public members, Maricopa Audubon, RMRS)- Small business workshops US Fish &Wildlife Service -Partner AZG&FD- Partner San Carlos Apache Tribe- Participant in the PERP Stewardship Freeport McMoRan – Small business working group Rocky Mountain Research Station - Partner UA/LTRR/Fire Ecology Lab/Biology Lab - Partner Safford BLM – Provided crews for Turkey Flat implementation Arizona Department of Corrections – Provided crews for PERP and Spencer/Bigelow implementation Prescott NF – Provided crews for implementation Spencer/Bigelow Sky Island Alliance - Partner USDA FOREST SERVICE Page 10 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES BLACK HILLS VEGETATION MANAGEMENT PROJECT ON THE PRESCOTT NF The Black Hills Vegetation Management Project area is 185,525 acres located on the Verde and Chino Valley Ranger Districts on the Prescott National Forest. Of this, 163,139 acres are management by the Prescott National Forest (PNF) with the remaining acres in private ownership or managed by other Federal, State or local agencies or municipalities. The assessment evaluated the area for opportunities to manage the vegetation in a manner that would promote conditions more closely resembling the natural range of variability in vegetative structure, species composition, and species distribution. It also provided an opportunity to manage vegetation and fuels at a landscape level to reduce the potential for and risks associated with large, high-severity wildfire. The Forest currently has two Watershed Restoration Action Plans (WRAPs) completed for watersheds within the Black Hills Vegetation Management area, with a two additional WRAPs expected within the next fiscal year. Other planning was also complete in this multi-watershed area, addressing management of rangeland resources (i.e. Bottle and Goat Peak Livestock Grazing Management EAs), allowing for the opportunity to implement additional resource improvement projects to address multiple indicators. Many of the management activities designed to address resource issues and concerns within the prioritized watersheds were based on planned forest projects which were implementable over the next three to five years, as identified in the recent NEPA analysis and the WRAP. Other identified essential projects proposed and implemented to improve watershed indicators were also considered to address existing resource maintenance issues, including road maintenance, unmanaged dispersed recreation activities, development and implementation of Best Management Practices (BMPs), and obliteration of user created routes to implement the Forest Motor Vehicle Use Map (MVUM). Public involvement and outreach which occurred as part of the Planning and Analysis processes provided a base for project implementation and partner development. Additional partner development and work with adjacent land owners is still to be developed and implemented for watershed restoration across jurisdictional boundaries; however, this work is trailing behind project implementation. One integrated BLI resulted in efficiencies for prioritization and implementation of project work on the Forest; incorporating multiple program areas into focusing planned management activities in priority watersheds. Employees began working across program boundaries for implementation of essential projects, regardless of their primary functionality. Concentration of multiple Forest management activities within a single watershed or at a smaller landscape scale in two or three watersheds is not the traditional way of doing business for the Forest. The change in approach has yet to be well communicated with communities associated with priority watersheds and with many of our partners. In order to change public perception and understanding the Forest is planning a communication strategy to increase community involvement and improve public engagement in restoration activities. The Forest did not plan completion of all essential projects within the first year of implementation of the Watershed Action Plan. The number of concurrent stressors that would be placed on a watershed as a result of completion of an overwhelming number of projects within such a short timeframe could potentially result in a decline in watershed function and condition, at least short-term. However, planned implementation over the next 1-3 years, project design and preparation, partner and community coordination, and inventorying and monitoring is ongoing and is expected to result in an USDA FOREST SERVICE Page 11 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES improved watershed condition within the context of the Watershed Condition Framework (WCF). Tracking targets and accomplishments for the consolidated BLI has increased the complexity of reporting (i.e. multiple reporting databases and levels of accomplishment for each outcome). Accomplishments are more integrated, resulting in a decrease in forest accomplishments if one or more resource programs accomplishes less than projected, causing a ripple effect. In addition, some accomplishments are reported as being met when a contract is awarded. However, the same outputs cannot be reported as accomplishments in WIT until the project work is completed, sometimes in a timeframe difference of one or three years. The combination of multiple BLIs into NFRR has resulted in many advantages to improving operational efficiency at the Forest level. For example, focus based planning for project implementation has significantly improved, resulting in increased dialogue between resource functions. The Forest is moving away from funding small scale, single resource related projects to prioritizing larger landscape or watershed related projects for funding and implementation based on multi-resource related benefits. Coordination for planning and implementation of project work has also improved across program boundaries, incorporating employees from a diverse perspective and background into ongoing discussions and on-the-ground project work. The combination of multiple BLIs into NFRR has also resulted in some challenges that are perceived as having negative consequences to efficiency. For example, adding NFN3 funds to the combined BLI creates on Forest competition against essential projects for watershed restoration as well as for dollars which fund primary Forest organizations. The Forest roads and engineering program has effectively realigned legacy roads funding to address resource issues within priority watersheds, however trails related projects are less effective in addressing primary resource concerns within priority watersheds and therefore less likely to compete well for limited funding. Lastly, the Forest fuels program has been effective in implementing projects in priority watersheds, however continues to struggle with competing for funds at a forest level for project implementation without full recognition of the need to fund the basic program or organization. The Prescott NF used an interdisciplinary team approach to select specific areas within the priority watersheds where management activities could influence watershed indicator scores. The IRR authority effectively improved dialogue between resource specialists and focused discussions on essential projects to improve watershed function. Resource specialists designed and proposed projects for implementation and the Forest Leadership Team prioritized the Forest program of work. Additional criteria were added for the Forest Leadership Team to emphasize work in priority watersheds. Timing or scheduling implementation for each project is then leveled based on Forest capacity, Forest commitments, partner involvement or relationships, responsiveness to meeting multi-functional resource objectives, addressing health and safety issues, and/or meeting projected reporting measures. Timing and scheduling for project selection may also be based on funding availability and program flexibility for successful implementation. The use of a single BLI has emphasized implementation of Forest management activities within the priority watersheds. The Forest has added additional criteria for consideration by the Forest Leadership Team to help prioritize the Forest Program of Work each year. Out-year project work is coordinated across resource programs and out-year implementation planning involves multiple resource functions. Consideration is given to proposed projects which have the highest likelihood of addressing resource issues and concerns within priority watersheds and which will produce outcomes to improve watershed function. Forest emphasis focus on activities to be performed has broadened and now includes essential projects USDA FOREST SERVICE Page 12 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES for implementation that in the past may only have been implemented as additional funding allowed; such as prioritizing mine assessments for resource impacts and review of existing permits to assess unauthorized water diversion and use. Selection of priority watersheds encourages multiple resource programs to coordinate and identify projects that traditionally may not have been selected for implementation or emphasized in the forest program of work. The cumulative selection of a diversity of projects for implementation is expected to have tangible benefits from collaborative dialogue, community and partner involvement, and result in improved watershed function and resiliency. According to the Forest Engineer, a benefit of NFRR is that the funds can be used for any type of work across the former BLI’s. This opened his eyes as to how the dollars could be “shared” and put toward a priority project within the watershed. The Primary Purpose barrier went away. Savings from road maintenance/ decommissioning projects could be used for other projects in the watershed. Projects that identified in the WRAP were actually funded and were aligned with the MVUM. This was not an unfunded mandate or exercise. One of the disadvantages is that it is a large BLI and a challenge to track. The Forest Fire Management Officer found that the intent to collaborate among traditionally separate functions on the unit toward common priority land management work is commendable and desired. He felt that a common BLI for multi-resource projects is more readily identifiable or traceable at some financial levels. The combination of previous BLIs into one BLI did introduce challenges and negative outcomes to the out-year planning process since it forced separate organizations within a single unit to compete for dollars to fund organizations. He felt this introduced bias into prioritizing annual programsof-work; that bias being choosing projects that would fund organizations vs. choosing projects that are a priority for the ecosystem. The partners on Black Hills WRAP are the Boy Scouts of America (recreation signing and work on erosion control projects to address resource impacts from unmanaged dispersed recreation activities), Arizona Game and Fish Department and National Wild Turkey Federation (spring management and improvement), and the grazing permittee and the Natural Resource Conservation Service (changes in livestock management to address resources issues and concerns, project work to treat invasive plants within the watershed, fencing to improve riparian vegetation condition). USDA FOREST SERVICE Page 13 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES SANTA FE NF - LAS CONCHAS FIRE LONG-TERM RESTORATION The Las Conchas fire burned approximately 156,000 acres across the Santa Fe National Forest, Bandolier National Monument, Los Alamos National Laboratory, tribal, county, and private lands, including nearly 79,000 acres on Santa Fe National Forest. Post-fire effects include flooding and debris flows downstream that affect additional stakeholders outside of the burn scar. The primary concern with post-fire response is for protecting human health and safety. Stabilization of resources within the fire-affected landscape is also a high priority. Goals of post-fire treatments include reducing the amount of and human exposure to debris flows and hazard trees, stabilizing soils to reduce loss of productivity as well as damage or loss of roads and cultural resources, repairing structural improvements used for range and wildlife management, and providing safe access for private inholdings and public visitation. The rehabilitation goals mentioned have benefits to the integrated natural resource areas as well as to recreation, heritage, and engineering resource areas. Most of the activities planned for Las Conchas restoration and rehabilitation were identified in interdisciplinary settings including the BAER support and a subsequent Resource Allocation Team using resources from off-Forest prior to implementation of Integrated Resource Restoration program. Most of the activities are driven by one or two primary resource areas but deliver benefits to many resources. The primary benefit of IRR was expanding the primary purpose to include all 6 BLIs it incorporated, therefore increasing flexibility for activities that could be funded. For example: Nearly 2,000 acres of reforestation were designated on the ground in consideration of timber suitability, habitat for threatened, endangered, or proposed species, and in response to pueblo concerns without having to be driven by multiple funding sources. Planting in FY13 will include a volunteer component including Los Alamos County government, local communities and pueblos, and local recreation, conservation and civic groups. Project preparation in FY12 was funded by NFRR and RTRT. Nine earthen tanks were cleaned of ash and sediment and dams were repaired; materials were purchased to repair nine spring developments; and materials were purchased to replace 24 miles of range allotment and Forest boundary fences damaged in the fire. In addition, NFRR funded planning and preparation work for one new wildlife trick tank that was provided by Rocky Mountain Elk Foundation and the FY 13 installation will be funded by Secure Rural Schools program funds. These efforts improve wildlife habitat and will restore the ability to manage permitted grazing on the affected allotments. Approximately 16 miles of trail repair and maintenance was funded by NFRR. Of that, 15 miles are funded with a 50% match challenge cost-share agreement to protect improvements as well as to direct runoff to reduce additional soil loss downslope of trails which are often located parallel to drainages. Public engagement for this project is high, with more than 1,000 volunteer hours accrued and 2,300 more hours committed. Heritage resource surveys have been funded to locate and identify heritage resources threatened by post-fire erosion as well as to protect them from damage during continued implementation of hazard tree removal projects. Some of the surveys are complete, more USDA FOREST SERVICE Page 14 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES are planned for FY13. Surveys for Mexican spotted owls and Jemez Mountains Salamanders are ongoing to monitor effects from the wildfire as well as to meet requirements to implement planned hazard tree removal and harvest activities. These surveys are designed to efficiently meet both needs since they were funded together. Noxious weed surveys and treatments were continued with no change in program from previous years. More than 200 additional acres of occurrence were mapped within the fire area. The landscape is severely altered from its prior functioning condition as a result of wildfire. The watersheds in the Las Conchas fire area were not assessed under the WCF following the fire. However, outcomes of prescribed activities have improved watershed conditions from the post-fire status. Ongoing activities coupled with natural recovery will lead to improved watershed condition over the long term. Integrated activities completed and ongoing will improve nearly all watershed condition indicators including: water quality, aquatic habitat, aquatic biota, riparian vegetation, roads and trails, soils, forest cover, rangeland vegetation, and forest health. The consolidation of BLIs potentially increased the integrated benefits of individual activities by increasing collaboration among resource areas. It also allowed the Forest to evaluate and approve what post-fire rehabilitation activities to fund rather than competing for activity-specific NFN3 funds at the regional level as in years past. The pooling of so many funds into the single BLI requires more coordination than was already occurring; reaching out to engineering as well as the previously-integrated ecosystem resources. The increased coordination may have a positive effect on resources by trying to maximize benefits to all resources. The increased coordination definitely requires more time and energy from personnel in developing, prioritizing, and tracking projects to ensure the program is fully implemented. More time for adjustment and coordination is needed to fully realize the impacts to efficiency. To the Forestry Program Manager IRR meant fewer BLIs to keep track of, but more difficulty in tracking because several programs are funded from the same pot of money. Since Las Conchas rehabilitation projects were already identified at the start of the IRR implementation, it was simple to fund a large mix of projects from the single BLI. For his employees directly involved in projects such as reforestation layout and hazard tree mitigation, it made no difference. Partners on this project include the Rocky Mountain Elk Foundation, who donated trick tank materials, and the Southwest Nordic Ski Club who provided a 50% cost share for trail rehabilitation on 15.7 miles of trail. USDA FOREST SERVICE Page 15 IRR 2012 REPORT | APPENDIX 2 | R3 CASE STUDIES POST FIRE RESTORATION PROJECTS In the summer of 2011, the Region had numerous large fires that resulted in over $50 million in fire rehabilitation needs, both short term and long term. There were additional large fires during 2012 which added to the regional fire rehabilitation need. IRR proved instrumental with regards to post fire restoration work across the Southwestern Region’s Forests in FY 2012. Restoration and stabilization needs were so diverse as well as extensive that the IRR concept reduced significant “process” time constraints in terms of fund allocations and interdisciplinary participation. IRR allowed the forests to jump directly into restoration work assessed and planned the previous year. The forests literally shifted on the fly into 2012 burn assessments and restoration planning. Implementation was in full swing by the end of FY 2012. Coupled with the Region’s plan for forests to complete a fiveyear restoration plan, short-term stabilization efforts will mesh into long-term restoration goals. Long term efforts such as reforestation, vegetation, habitat, water quality and other issues will then be addressed. In addition to the BAER (Burn Area Emergency Rehabilitation) work, most Forests pursued hazard tree removal and range fence reconstruction as well as repairs to other damaged watershed infrastructure as initial restoration priority needs. Strategic road closures were installed in order to protect watershed resources as well as the public during the upcoming monsoon season. The Coronado NF began trail repairs that were causing excessive erosion. The forest relied on previously funded, standing agreements with the Department of Corrections to clean and stabilize trails, repair erosion control devices, and reconstruct stock tanks. Volunteers were used to inventory and monitor fire affected range and watershed infrastructure. In 2012, the Gila NF utilized various partners from other forests and agencies to layout, mark, and cruise roadside hazard tree salvage and salvage in areas of high natural regeneration potential. These salvage sales are active and on-going. Use of a crew from the Alamo Navajo Band, trained by the Forest Service, was completely successful in assisting with the marking and cruising of hazard trees. Fencing supplies and an installation contracts worth $90,000 was awarded with NFRR. This work completed over 72 miles of fence reconstruction on the Wallow (Gila side) Fire. Additional contracts for fence replacement and repair were awarded on the Apache-Sitgreaves NF. This work was critical to the restocking of the livestock allotments on the forests. Fire affected forests contracted out Mexican Spotted Owl (MSO) survey teams with NFRR in FY 2012. Partners and volunteers worked to repair wildlife water features (ponds and drinkers). Chiricahua Leopard Frog habitat is being restored on the Coronado NF with cooperative effort from partners like Bat Conservation International. Forest Service crews replaced drainage pipes, cleared roads of fire flows, riprapped drainage inlets, installed rolling grade dips, and replaced spot surfacing around washouts using a combination of NFRR and CMRD funds. USDA FOREST SERVICE Page 16 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES STOLLE CREEK –SOUTH FORK SALMON RIVER PRIORITY WATERSHED BOISE NF Watershed Description Ecologically important, the Stolle Creek watershed is nested in the upper South Fork Salmon River (SFSR) Subbasin, which historically produced up to 60% of the anadromous fish in the Snake River Basin. High-value aquatic species include: Federallylisted Chinook salmon (Threatened), steelhead trout (Threatened), bull trout (Threatened); westslope cutthroat trout (R4 Sensitive); and several amphibian species such as the Idaho giant salamander. Stolle Meadows is one of Stolle Meadows Chinook Salmon 2012 five major areas in the watershed that provides critical spawning habitat for Chinook salmon and steelhead trout, which is key to the viability of the SFSR populations. Additionally, the SFSR is considered suitable for Wild and Scenic River status because of it outstandingly remarkable scenic, recreational, geologic, fisheries, cultural resources, and ecological/botanical values. WCF Status Functioning at Risk (WCF Rating of 2.13) The current conditions contributing to the WCF rating are summarized as: Impaired Water Quality. SFSR was 303(d) listed in 1998 and has had a TMDL for sediment since 1991. The Idaho Department of Environmental Quality (IDEQ) proposed developing a stream temperature TMDL in 2011. Accelerated sediment, altered streambanks, increased width-to-depth ratios, and reduced stream channel-floodplain connectivity from historic and current road-related and dispersed recreation uses have substantially impacted aquatic habitat (Forest Service 2011, Forest Service 2009). The 2007 Cascade Wildfire Complex burned 268,000 acres, 85% of the watershed. Post-fire effects include extensive loss of forested vegetation and chronic soil erosion that will take many decades into the future to recover (Forest Service 2007). Stolle Creek-S.F. Salmon River Watershed Issues Open road density of approximately 2.0 mi/mi2; with an RCA road density of 1.8 mi/mi2. Identified road segments on unstable landtypes, with some landslide-related road failures. Forested vegetation largely removed by recent wildfire thereby reducing stream shading and leading to the increased landslide risk from reduced tree root/soil strength. Although large woody debris (LWD) is currently high due to recent stand replacing wildfire, a longterm deficit in large diameter material is expected as the existing LWD naturally decomposes prior to the availability of new LWD (>100 years). The GRAIP1 Inventory estimated 540 tons/year of road-related sediment is being delivered to streams from authorized and unauthorized roads having high surface erosion rates. 1 Geomorphic Road Assessment and Inventory Package (GRAIP) combines a detailed road inventory with GIS analysis to predict road sediment production and delivery, mass wasting risk from gullies and landslides, and road hydrologic connectivity (Black et al 2009). USDA FOREST SERVICE Page 17 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES Stream Crossing Road 473B Before Treatment Stream Crossing After Treatment Restoration Objectives The Stolle Creek-South Fork Salmon River Priority Watershed Restoration Action Plan includes three restoration objectives: 1. Reduce road-related impacts and risks to water quality and fisheries resources according to the SFSR sediment TMDL while retaining a safe and efficient transportation system to meet current and future management, public access, and recreational needs. 2. Reduce recreation impacts and risks by improving the trail system to provide public access and recreation opportunities while reducing unintended impacts to the environment. 3. Enhance recreational experience by providing educational and interpretive exhibits describing unique natural features in the upper South Fork Salmon River. The following essential projects were identified to achieve the objectives: Road decommissioning. Road reconstruction. Unauthorized route decommissioning. Motorized trail reconstruction. Post-wildfire reforestation. USDA FOREST SERVICE Page 18 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES IRR Accomplishments NFRR Performance Measure Planned WTRSHD-CLS-IMP-NUM: WTRSHD-RSTR-ANN (acres): HBT-ENH-TERR (acres): S&W-RSRC-IMP (acres): FOR-VEG-EST (acres): HBT-ENH-STRM (miles): RD-DECOM (miles): 0 4,540 4,400 140 0 12 35 Actual 0 10,424 10,144 140 140 12 36 Comments Not all essential projects have been implemented Restoration activities implemented to achieve the accomplishments include: Decommission by recontouring 24 miles of Maintenance Level 1 roads, including restoration of 46 stream crossings. Obliteration by recontouring 12 miles of unauthorized routes. Construction of three trail bridges, installation of one metal culvert, and reconstruction of trail segments adjacent to streams. Funding (to date) Approximately $362,317 ($262,317 Forest Service and $100,000 Partnership) Excavator Decommissioning Road Obliterated Road 483B Partners For this project $100,000 was contributed by the Nez Perce Tribe for the purpose of restoring anadromous fish habitat. The source of this funding was the Bonneville Power Administration salmon recovery efforts. Representatives of the Nez Perce Tribe also assisted in monitoring the implementation of the road decommissioning/obliteration contracts. Additional partners that have contributed to the planning and implementation of water quality improvement projects or recreation projects by providing funding, grants, or volunteers include: Idaho Department of Environmental Quality (IDEQ), Idaho Department of Parks and Recreation (IDPR), Southwest Idaho Mountain Biking Association (SWIMBA), Back Country Horsemen, and McCall Hiking Club. USDA FOREST SERVICE Page 19 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES IRR Conclusions 1. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? For the Stolle Creek-S.F. Salmon River Priority Watershed, the IRR process decreased the level of internal coordination across the fish/wildlife, contracting, engineering, and watershed program areas that would be needed when using the traditional BLIs. Using IRR funds reduced the effort required to designate various fund codes to portions of this project (CMLG, CMRD, NFWF, and NFVW). The integrated process decreased complexity often associated with creating the proper “mix” of BLIs/funding when collaborating with partners and coordinating agencies to use contributing funds. 2. Describe the outcomes or on-going status. Did the activity lead to an improved watershed condition within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. By definition, once all essential projects have been implemented, or the Forest Service has addressed the stressors limiting functioning status of the WCF indicators within its authority as the land management agency, watershed condition should improve. For the Stolle Priority Watershed all essential projects with the exception of reforestation have been implemented. Currently, the watershed remains in the “Functioning at Risk” category. Completing reforestation activities remains a priority with funding (NFRR and NFVW) designated over the next two years. Additional road decommissioning and reconstruction activities will be implemented as additional NFRR funding becomes available, while recognizing competing priorities across the Forest. 3. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? With the exception of NFRW, the traditional BLIs needed to implement the essential projects were consolidated into NFRR. Some NFRW funds were combined with NFRR in project planning. The NFRR mix alleviated functional funding that would traditionally provide partial funding for a resource activity and facilitated accomplishment of integrated restoration targets, sometimes exceeding planned levels. 4. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? Advantages – less effort needed to coordinate across multiple resource areas/BLIs. Disadvantage – project managers must continually monitor spending or it is difficult to track actual project costs. 5. How did the IRR authority change the way activities were selected? The authority did not necessarily change the way activities were selected. Prior to the wildfires many restoration opportunities were already identified but lacked funding under a functional BLI to implement. The post-fire rehabilitation efforts supported with NFN3/WFW3 provided some flexibility to combine previously identified restoration activities and establish the foundation for an integrated restoration program. The IRR authority enabled the Forest to prioritize and more USDA FOREST SERVICE Page 20 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES efficiently implement a range of restoration projects involving multiple resource areas with integrated accomplishments. 6. Suggest ways the use of this authority can be improved. Likely no recommendations specific to this project. With respect to reporting all restoration accomplishments, there are some glitches that need to be worked out to capture potential integrated activities funded under other BLIs. 7. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. The District Hydrologist states: “Internally, the NFRR approach improved project integration (“BLI cost-sharing”) by making it easier for program areas to capture respective accomplishments (integrated targets) while reducing the level of coordination to agree on funding percentages under the traditional BLIs. Externally, using NFRR increased efficiency to implement integrated projects with partnership funds– which contributes to opening up new or additional partnerships”. 8. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. For this project $100,000 was contributed by the Nez Perce Tribe for the purpose of restoring anadromous fish habitat. The source of this funding was the Bonneville Power Administration salmon recovery efforts. Representatives of the Nez Perce Tribe also assisted in monitoring the implementation of the road decommissioning/obliteration contracts. Additional partners that have contributed to the planning and implementation of water quality improvement projects or recreation projects by providing funding, grants, or volunteers include: Idaho Department of Environmental Quality (IDEQ), Idaho Department of Parks and Recreation (IDPR), Southwest Idaho Mountain Biking Association (SWIMBA), Back Country Horsemen, and McCall Hiking Club. References Black, T.A., Cissel, R.M., and C.H. Luce. 2009. The Geomorphic Road Analysis and Inventory Package (GRAIP) Data Collection Method. USDA Forest Service Rocky Mountain Research Station, Boise Aquatic Science Lab. http://www.fs.fed.us/ GRAIP/downloads/manuals/GRAIP_Field_Manual_2009.pdf. Forest Service. 2011. Environmental Assessment, South Fork Salmon River Resource Management Project. Cascade Ranger District, Boise National Forest. Forest Service. 2009. Environmental Assessment, South Fork Salmon River Recreation Access Management Project (RAMP). Cascade Ranger District, Boise National Forest. Forest Service. 2007. Burned Area Emergency Response (BAER) Reports, Cascade Complex South and Cascade Complex North. USDA FOREST SERVICE Page 21 Figure 6. Stolle Creek-South Fork Salmon River Priority Watershed Restoration Activities. IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES USDA FOREST SERVICE Page 22 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES BIRCH CREEK – ESCALANTE RIVER PRIORITY WATERSHED | DIXIE NF Watershed Description The Dixie National Forest has entered into a collaborative initiative with a range of governmental and non-governmental entities aimed at a multi-year, multi-dimensional restoration of ecological functions within the Escalante River Watershed. The intent is to integrate Motorized Travel Plan, Restoration of Upland Forest Vegetation, Riparian Restoration, and Rural Community Stability and Protection into one seamless initiative, with all four themes being considered in all projects. The Escalante Watershed is a highly significant natural, cultural, visual and recreational resource. It contains worldclass geological features including steep exposed rock canyons and the Aquarius Plateau, one of the largest of its type in the world. It possesses some of the best examples of Escalante River Watershed pre-historic cultural resources in the southwest. Excellent habitat exists or could be restored for important native fish and wildlife resources. Visitors come from throughout the nation and world to experience the watershed’s spectacular views and recreational opportunities. The focus in FY12 was in the Birch Creek watershed in the Escalante River drainage. Emphasis in this watershed contributed to outputs relating to Colorado Cutthroat Trout stream habitat improvements, road decommissioning, road improvements relating to road drainage and surfacing and removal of an aquatic passage concerns. Vegetation management objectives in this watershed where advanced with riparian vegetation thinning objectives being implemented and the accelerated advancement of spruce/sub alpine and aspen timber sale offers. This project has implemented a more diverse mix or outputs in one focus area than any other project over the last five years on the forest. IRR Conclusions 1. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? By utilizing the watershed condition framework analysis, the forest recognized the efficiency of combining implementation efforts involved in more cohesive watershed condition improvement. Internal collaboration with all specialists included a diverse mix of implementation goals necessary to improve the watershed condition class in our IRR focus area. 2. Describe the outcomes or on-going status. Did the activity lead to an improved watershed USDA FOREST SERVICE Page 23 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES condition within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. Three major actions were implemented to improve watershed conditions: • Stream Miles Enhanced – for aquatic passage and riparian vegetation encroachment. Over five miles of stream habitat improvement was improved on two road/ stream crossings. This included the construction of step pool habitat in two stream segments and the removal of vegetation in riparian areas to move the vegetative condition back to a properly functioning condition class. • Road Miles Decommissioned – for reduction of sedimentation and terrestrial wildlife habitat improvement. Ten miles of road was decommissioned and over one thousand acres of terrestrial habitat improvement was realized. • Road Miles Improved – two miles improved with aggregate surfacing and ten miles of maintenance to lessen sedimentation impacts to nearby aquatic habitat. Following the completion of all these on–going projects the Birch Creek watershed will be improved in condition class. Selected Forest Outcome: To restore Aquatic Organism Passage and improve habitat connectivity for remnant populations of R4 Sensitive Colorado River cutthroat trout by replacing Stream Erosion Check Dams with grade control structures passable to fish. Existing Birch Creek Check Dam. Erosion log check dams constructed over 60 years ago were impairing stream habitat connectivity. Old Check Dam with New Stream Channel and Step Pool Structures Work Performed: Lowered Existing Log Erosion Check Dam Constructed 13 log/rock step structures to create a step-pool cascade stream channel to cross over existing check dam. USDA FOREST SERVICE Page 24 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES Expected Benefits: Re-established Aquatic Passage for R4 Sensitive Colorado River cutthroat trout (CRCT) over Check Dam Maintained grade control of original check dam to prevent upstream head cut migration Access to additional 1.7 miles of stream habitat upstream of check dam. Part of a larger project to restore connectivity between Birch Creek and two tributary streams for remnant populations of CRCT 3. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? All of the consolidation of BLIs increased the outputs in one area; to accomplish this much work with 5 or 6 BLIs with competing emphasis would not have been possible in previous years. 4. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? Advantages: More defined projects at a watershed scale. Less budget work. More cooperation in analyzing projects. Fewer larger size projects with multiple target attainment. Disadvantages: Less projects overall. Implementation may take more than one year. 5. How did the IRR authority change the way activities were selected? The forest is moving toward larger scale watershed evaluations with multiple target attainment. This likely lowers the overall number of projects we implement but focuses our investment in focused areas. 6. Suggest ways the use of this authority can be improved. Allow NFRR funding to be utilized for range vegetation improved acres. This resource improvement is under-represented in the new IRR emphasis due to this restriction. 7. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. One hydrologist states: ”IRR enabled using the Good Neighbor Agreement and “Schedule A” Authorities to award implementation work quickly. IRR also facilitated the implementation team of multiple specialists working together to allocate funding for restoration projects. On the downside we did not invest in the vegetative management NFMA/NEPA process in the initial fiscal year that the pilot project was initiated, slowing down large scale vegetation restoration.” 8. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. Garfield County has accepted the implementation work of 10 miles of road maintenance, 2 miles or road reconstruction and the construction of a bridge and a low-water crossing that meets aquatic passage standards. The Utah Division of Wildlife Resources has completed the implementation of stream gradient restoration project that saved the forest over $20,000 in cost. The Utah Department of Forestry, Fire, and Lands have accepted riparian area improvement through thinning. This will result in protecting and restoring these systems to a properly functioning condition. USDA FOREST SERVICE Page 25 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES Escalante River-Birch Creek Restoration USDA FOREST SERVICE Page 26 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES WEISER AND LITTLE SALMON RIVERS PRIORITY WATERSHED | PAYETTE NF Watershed Description The headwaters of the Weiser and Little Salmon Rivers (WLSR) encompass working forests of westcentral Idaho. Long considered the breadbasket of the Payette National Forest (PNF), these productive forests provided resource benefits for fish, wildlife, timber, grazing and recreation. The Weiser River flows south through the PNF which forms a large semi-circle around the predominately agricultural communities of Council, Cambridge and Indian Valley. The river flows out of the headwaters to wind through these ranchlands, to join the Snake River 100 miles away at the Oregon border. Weiser-Little Salmon River Watershed The Payette National Forest was selected as a CFLR Project in February 2012 and adjusted our FY 2012 program of work to meet annual commitments made in the CFLRP Proposal. This resulted in numerous shifts in dollars and tasks to make sure the CFLRP requirement of matching funds dollar per dollar were achieved. The CFLR landscape is 972,000 acres and includes the Council RD, New Meadows RD and portions of the McCall RD. NFRR funding was the primary source of matching. One significant accomplishment was the completion of the NEPA document for the Mill Creek Council Mountain area (MCCM) project. The MCCM project area is approximately 50,000 acres and includes forested areas rated high priority for terrestrial wildlife habitat restoration as well as a high priority Aquatic Conservation Strategy (ACS) subwatershed (East Fork of the Weiser River). The MCCM FEIS and ROD set the stage for three to five years of restoration work on the ground that will contribute to IRR performance measures. IRR Conclusions: 1. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? The concepts of IRR and CFLRP encourage project planning at much larger scales. The Forest has embraced this concept and has increased the project area size to around 50,000–80,000 acres. Completing one EIS for this large a landscape results in numerous restoration activities that can be implemented over several years. External collaboration and public engagement has been emphasized over the past three years working with the Payette Forest Coalition (PFC). The Forest believes the collaboration and integration of these large landscape planning efforts results in better decisions that lead to better resource outcomes when measured in terms of acres of habitat restored, acres of vegetation restored, or miles of stream habitat improved. USDA FOREST SERVICE Page 27 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES Dewey Creek culvert before AOP project Dewey Creek bridge after AOP project 2. Describe the outcomes or on-going status. Did the activity lead to an improved watershed condition within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. The FY 2012 accomplishments contributed to improvements to WCF watershed conditions, but they did not result in a shift from functioning at unacceptable risk to a better class. It will take several years before that shift occurs in the WSLR. One aquatic organism passage (AOP) structure was installed within the Forest Plans Aquatic Conservation Strategy high priority watershed (East Fork of the Weiser River) and the completion of the EIS will lead to numerous watershed improvements implemented in FY 2013 through FY 2015. These activities include road decommissioning, more AOPs, and road improvements. In FY 2013, the Forest will complete the final watershed improvement activities in the Kennelly Creek Watershed (Paddy Flat Area) which will move this high priority watershed into a functioning acceptable rating. 3. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? The consolidation of BLIs did not change the mix of outcomes and outputs other than the hazardous fuels situation where only 25 percent of the fuels funding contribute to planning of integrated fuel reduction projects. In the past, hazardous fuels often funded up to 50 percent of the planning. 4. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? NFRR as a single BLI gives the Forest more flexibility and may increase some internal efficiency because we will no longer spend as much time tracking and allocating funding from the separate BLI’s. There is also a potential disadvantage. The responsibility to maintain programs such as the stewardship or timber sale program that contribute outputs tied to jobs in our local communities could be overlooked with the lumping of BLI’s. Each Forest Leadership Team should ensure the outputs derived from NFRR maintain the right mix of commodity outputs. USDA FOREST SERVICE Page 28 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES 5. How did the IRR authority change the way activities were selected? For us it was the combination of IRR authority and the CFLRP authority. Combined, these two funding authorities resulted in more restoration work focused within the CLFRP landscape and were selected to match the commitments outlined in our original CFLRP Proposal. 6. Suggest ways the use of this authority can be improved. The Forest faced two major challenges in 2012 in relation to planning work and accomplishments. First, we received authority for NFRR when we were 25% into the new fiscal year. This caused a lot of work for Program Managers as we had to reassign activities from “old” work codes to the NFRR code. Shortly after we received NFRR authority we were told we received funding as a CFLRP Forest. We then had to completely re-do the forest budget to find sufficient funds to “match” the influx of CFLN funds. As mentioned previously, in many cases we were already positioned to complete integrated projects, so switching from many EBLIs to one (NFRR) was not too difficult, but we were not positioned to fully utilize CFLRP funds without moving funds from projects planned for outside the CFLRP boundary, to projects within the CFLRP area. It would also be beneficial to change the distribution of WFHF funds attributed to NFRR, based on the average amount of treatments in WUI versus non WUI areas. Currently, 25% of WFHF funds are included in NFRR, but on our Forest a much larger percentage is considered integrated restoration work. Conversely, fuel specialists have expressed concern at having more of their funds “lumped” into the “big” NFRR code. 7. A GIS map showing specific treatment areas and submit geodatabase files/shapefiles. Spatial data must also be recorded in the FACTS spatial data engine (SDE) and meet existing data dictionary standards. The Forest is working on our spatial data in FACTS and will not be able to produce this layer until spring 2013. 8. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. A team member states: “One of the biggest advantages of IRR is that our partners are told that we all need to play in the sandbox together – harvesting timber is as important as decommissioning roads; ecological benefits and economic benefits are equally important. The disadvantage is partners that represent a specific interest, be it wilderness or motorized recreation or logging, are concerned that one strong personality or belief system may “hijack” a disproportionate amount of the NFRR funds.” 9. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. The Payette Forest Coalition was our collaborative partner for this project. This group will be recognized by the Regional Forester in late November for the Regional Partnership Award. The Nez Perce Tribe contributed to one large AOP structure that was installed in the headwaters of the Secesch River near Burgdorf. USDA FOREST SERVICE Page 29 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES SWIFT CREEK PRIORITY WATERSHED | ASHLEY NF Watershed Description The restoration goal for the Swift/Cart Creek watershed was to correct remaining resource issues (i.e., erosion, soil productivity, stream sedimentation, wet meadow braiding) associated with system trails in the watershed. The major trail identified with resource issues was a trail created by bulldozer in the 1950’s during dam construction in what is now designated wilderness. Sections of this trail had severe erosion and gullying associated with it. Other sections of trail in the watershed identified for restoration or relocation involved eroding trail beds near streams, fords, wet meadows, seeps, and overly steep terrain. Completions of these projects were the only actions need to move the watershed from condition class II to class I. Swift/Cart Creek Watershed Restoration 1. Describe how IRR helped to facilitate project planning and implementation. Was the action or activity implemented/completed more efficiently or effectively, including information on internal and external collaboration and public engagement? Did the activities have a greater impact to resource outcomes? Pilot authority and awarded Regional funding for this focus watershed raised the priority for this work to be implemented in FY 2012. The interdisciplinary WCF assessment process identified watershed as a candidate for focused restoration effort. A large-scale restoration project had just been completed in the watershed involving the Forest Service, local county partners, federal agencies, and state of Utah, to decommission 5 dams in the Swift Creek Watershed which resulted in restoring natural hydrologic function of streams. In FY 2012 the authority allowed for close integration between recreation and hydrology specialists on remaining trail system issues within this wilderness watershed. NFRR funding was also used to employ and oversee Utah Conservation Corps trail crews to assist in the workload of trail restoration for this project. USDA FOREST SERVICE Page 30 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES 2. Describe the outcomes or on-going status. Did the activity lead to an improved watershed condition within the context of WCF? If so, how? If not, why? Reports should provide qualitative as well as quantitative data. Fiscal year 2012 activity Trail restoration work was completed at the majority of the locations planned. Specific work resulted in 16 improved channel crossings and their approaches, 25 water bars, 35 check dams, 2 French drains, over 250 feet of raised turnpike, and over 1,300 feet of braided trail restored at individual sites throughout the watershed. Plans for FY 2013/14 Delays in attaining archaeology clearance for six trail reroutes have postponed some relocation work to FY13/14. Due to weather and logistic delays encountered late in the field season, one remaining section of trail targeted for restoration in FY12 has also been delayed until FY13/14, when the remaining reroutes will be completed. With completion of these final sections of trail all essential projects identified for the watershed will have been completed and will result in an improvement watershed condition class in the context of the WCF. Work completed since 2007 will have resulted in improvements to framework items: 7.1 Soil Productivity, 7.2 Soil Erosion, 6.2 Road Maintenance, 6.3 Proximity to Water, 6.4 Mass wasting, 2.1 Flow characteristics, and 3.2 Channel Shape and Function. Trail 055 near Owl Creek Meadow before and after FY12 trail work 3. Describe if the consolidation of BLIs (NFRR) changed the mix of outcomes and outputs. If so, how? In the case of the Swift Creek project, the mix of outcomes and outputs were probably similar to the scenario if the BLI’s were separate. The scope of the project was more focused on correcting the remaining resource issue (trail impacts) within the watershed and funding would have come from watershed NFVW and trails NFRW/CMTL. However, combining the BLI’s and the designating the area as a focus watershed allowed the work to occur more quickly because more funding was available for the project. USDA FOREST SERVICE Page 31 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES In the case of the Cart Creek focus watershed, the consolidation of BLI’s has changed the mix of outcome and output/goals for projects within the watershed. The issues and restoration opportunities cover a wider range of disciplines. Specialist’s time in NFRR was budgeted in FY 2012 to participate in an ID team that included making coordinated field visits to the watershed to identify watershed issues and to discuss restoration ideas as a group. While NEPA analysis acts in a similar interdisciplinary manner, the level of integration and on-the-ground discussion of ideas for projects seems to be greater than the past way of doing business under separate BLI’s. Through our FY 2012 planning efforts, partnership funding from the EPA and the State of Utah has been awarded for restoration projects in the Cart Creek Watershed. Implementation of projects will begin in FY 2013 and continue for several years. 4. Describe the advantages and disadvantages of the single BLI (NFRR). How NFRR has impacted efficiency? The disadvantage of the NFRR BLI is trying to manage the complexity of a BLI that incorporates multiple program areas and associated targets and program elements, especially when it comes to tracking spending. The advantages of the NFRR BLI is the transparency and integration among program areas, the ability to leverage a large amount of funding and resources for a particular project, the flexibility to plan projects without the constraints of numerous specific targets, limited primary purpose, or territorialism of program areas. 5. How did the IRR authority change the way activities were selected? With the Swift Creek Watershed, potential activities were reviewed in a multidisciplinary manner (i.e., Watershed Condition Framework). Due to the wilderness setting and the large-scale project recently completed in the watershed, all the remaining resource issues and restoration opportunities identified in the framework related to the trail system. As such, activities and implementation was more limited to watershed and trails personnel. As demonstrated in the planning process of projects in the Cart Creek Focus watershed, the IRR mode of operating has fostered greater on the ground interdisciplinary discussion and input in issue identification and designing solutions (e.g., left side of the NEPA triangle planning). 6. Suggest ways the use of this authority can be improved. Not sure yet. 7. A GIS map showing specific treatment areas and submit geodatabase files/shapefiles. Spatial data must also be recorded in the FACTS spatial data engine (SDE) and meet existing data dictionary standards. Swift Creek Watershed restoration planning and accomplishments have been entered into WIT. Trail improvement/maintenance is also documented by the recreation program under INFRA. USDA FOREST SERVICE Page 32 IRR 2012 REPORT | APPENDIX 2 | R4 CASE STUDIES 8. Illustrate the pros/cons of the pilot from the team member perspective, with contact information for a team member who worked on the project. The hydrologist on the project states: “Internally, IRR provided an advantage in setting goals and priorities among program areas because we concentrated our efforts on projects associated with the Forest’s focus watersheds. This seemed to encourage a lot more integration among program areas than occurred historically. Because of the flexibility and integration, there were more opportunities to fund projects associated with partners.” 9. List of partners, their contributions (if any) that were involved in the planning and/or implementation of your project. Utah Conservation Corps crews were employed to handle the additional trail restoration workload in Swift Creek FY2012. Partners involved in the recently completed High Lakes Dam Stabilization Project (2007-2010) included: the Duchesne County Water Conservancy District, Bureau of Reclamation, State of Utah Engineers Office, the Central Utah Project, and the Utah Conservation Corps. USDA FOREST SERVICE Page 33