STANDARD COSTING SECTION 1 Reasons for standard costing and variance analysis Historic costing is used in financial accounting and statements tend to be presented at the end of the year, therefore • corrective action is impossible • there is no yardstick by which performance can be compared. This shortcoming of financial accounting has led to the use of standard costing and variance analysis. Standard costing and variance analysis make up a predetermined costing system where • actual performance is compared with a predetermined performance so that if differences occur management can take action; • standard costing compares actual production and sales with planned production and sales; • when standards for costing are in operation they are not altered – unless a flexible budget is used; • costs are prepared to show the standard cost; actual cost and any variances, i.e. the difference between the standard or budgeted cost and the actual cost. Advantages of standard costing and variance analysis • • • • • Provide a yardstick. Help determine the price of a product. Variances can be analysed in detail. Costing is simplified. Management is encouraged to plan ahead. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 1 STANDARD COSTING Types of standard The main standards are expected standard – this merges the features of forecasting with standard setting. Expected standards usually take some account of delays and inefficiencies. They should, however, be regularly reviewed as conditions change. This sets realistic standards that both workforce and management will try to reach. current standard – for organisations which are faced with rapidly changing market conditions. Again, such standards take account of inefficiencies. They should, however, be regularly reviewed as conditions change. basic standard – here standards are left unchanged over long periods of time. It does not take account of changes in current methods of production, prices or other changing factors. Since frequent changes are necessary, basic standards are rarely used except as a basis for preparing current standards. ideal standard – this is the standard which can be attained under the most favourable conditions possible. It ignores machine breakdown and faulty materials, in fact, any waste whatsoever. This level of performance is seldom reached and is likely to demoralise staff. Perfection is impossible and for this reason this standard is not recommended. The setting of a standard cost involves every department and aims to produce a planned cost related to the product supplied by the organisation. The detailed planning that goes into producing a standard cost should make it possible to compare current actual results with the detailed cost plan. The preparation of the standard costs is typically based on either the expected standard or the current standard since these two methods more closely reflect what is happening within an organisation. Problems of setting up a standard cost system When preparing standard costs it is important to consider at what level of production the business is expected to operate. • what past performance suggests is capable of attainment – this tends to lead to management complacency; 2 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) STANDARD COSTING • what would necessitate maximum efficiency – this tends to be unrealistic but variances could stimulate management; • what is possible with normal efficiency. Standards are set to take account of • • • • • materials – usage, waste, price, output, volume labour – hours, rate of pay, strikes, output, overtime variable overheads – expense of power, cleaners fixed overheads – expense of rent and rates revenue – prices, quantity sold, profit. The information which is used to set the standard is collected by both management and work study personnel who record the relevant information on a standard cost card. This is used for every activity and it is to this that management will constantly refer to see if the standard set is being achieved. The problems associated with standard costing are: • No situation is static and in a changing situation the standard can become unrepresentative. This incurs a cost of constantly updating data. • The value of money changes. • Changes in taxation occur. • Changes occur in production methods, machinery, labour rates, efficiency, strikes. Advantages of setting up a standard cost system There are several advantages to operating a standard cost system: • Variances direct management’s attention to areas of difficulty. • The system assists in pricing the final product. • Standard costing is an effective method of determining the value of costs. • Standard costing gives a constant flow of accounting information to management without the need to constantly calculate costs. • The system assists in control by identifying variances. • Standard costing is part of the budgetary procedure. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 3 STANDARD COSTING The standard set on the standard cost card can be used for a considerable period of time. Only when the variances become constantly favourable or adverse will standards need to be changed. The standard, when set, will be near the actual cost but will tend to move as the cost of materials, labour and overheads changes. Firms who operate budgetary control have a standard costing system and so they are able to investigate any divergence from the set target. The differences between actual results and budgeted expectations are known as variances. 4 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) COST VARIANCES SECTION 2 Calculation of variances using a diagram Cost variances for materials, labour and variable overheads Variances can be expressed in two ways, either by diagram or formulae. The use of a diagram for materials, labour and variable overheads makes it unnecessary to remember the formulae since they can be calculated directly from the diagram. The difference between the standard cost and the actual cost creates the variances, which can be adverse (a) or favourable (f). It is always possible to decide whether a variance is favourable or adverse by inspection since favourable variances are below the expected cost while adverse variances are higher than the expected cost. When using the diagram it is important to ignore + or – in the calculation. The price/rate/expenditure variance and the usage/ efficiency variance when added together equal the total cost variance. The total cost variance for materials, labour and variable overheads breaks down into two parts. Total Cost Variance Material Cost Variance Labour Cost Variance Variable Overhead Cost Variance • Price Variance Price for Materials Labour Rate for Labour Expenditure for Variable Overheads • Usage Variance Usage for Materials Efficiency for Labour Efficiency for Variable Overheads The diagram is constructed using boxes. These boxes can be used to calculate all the variances for materials, labour and variable overheads. The abbreviations used in the diagram are as follows. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 5 COST VARIANCES AC = Actual Cost AP = Actual Price AR = Actual Rate AQ = Actual Quantity AH = Actual Hours SC = Standard Cost SP = Standard Price SR = Standard Rate SQ = Standard Quantity SH = Standard Hours The following diagram shows all the variances. Actual Cost (AP × AQ) AP/AR Price Variance Labour Rate Variance Expenditure Variance AQ(SP – AP) SP/SR Usage Variance Efficiency Variance SP(SQ – AQ) Standard Cost (SP × SQ) SQ/SH AQ/AH Reasons for variances Variances arise for many reasons and can be favourable (showing that actual performance was better than was budgeted) or adverse (showing that actual performance was worse than was budgeted). When variances are favourable, management is operating efficiently; when adverse, management must investigate to find out why performance is below that expected. Materials Price variances are caused by • • • • change in price of materials change in delivery costs and dates poor quality material being purchased loss of discount. 6 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) COST VARIANCES Usage variances are caused by • • • • carelessness/bad handling in use excessive scrap or waste pilferage/using non-standard materials incorrect book-keeping. Labour Labour rate variances are caused by • change in basic wage rates • poor grade of employee used on the job • excessive use of overtime. Efficiency variances are caused by • • • • • incompetent operatives/poor training poor supervision/inefficient organisation poor working conditions delays due to machine breakdown/late deliveries strikes/go-slows. Variable overheads Expenditure variances are caused by • • • • change in rent and rates increases in administrative expenses change in financial expenses – interest rates changes in the capital base of the firm. Efficiency variances are caused by • use of heat and light • appropriate use of space • volume of production, stoppages, strikes. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 7 COST VARIANCES Example 1 From the following information calculate the variances. Materials Standard Price per metre £4 Standard Usage (Quantity) per unit 5 metres Actual Price per metre £3 Actual Usage (Quantity) per unit 7 metres Material Cost Variance = (SC – AC) = £20 – £21 = £1(a) Material Price Variance = AQ(SP – AP) = 7 × £1 = £7(f) Material Usage Variance = SP(SQ – AQ) = £4 × 2 = £8(a) The values given in the question can be placed on the diagram and the variances calculated. Actual Cost £3 × 7 = £21 AP £3 Price Variance AQ(SP – AP) £1 × 7 £7(f) SP £4 Usage Variance Standard Cost £4 × 5 = £20 SP(SQ – AQ) 2 × £4 = £8(a) SQ/SH 8 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) AQ 7m COST VARIANCES Example 2 From the following information calculate the variances. Labour Standard Cost per unit Labour 3 hours @ £1.40 per hour Actual Cost of 10,000 units Labour 27,000 hours costing £30,000 Labour Cost Variance = (SC – AC) = [(3 × 10,000) × £1.40] – £30,000 = £12,000(f) Labour Rate Variance = (SR × AH) – AC = £37,800 – £30,000 = £7,800(f) Labour Efficiency Variance = SR(SH – AH) = £1.4(30,000 – 27,000) = £4,200(f) This example does not provide the actual wage rate. However, the use of the diagram provides the calculation Standard Rate × Actual Hours, the total of the Standard Cost box and the Labour Efficiency Variance box. Thus the box system provides a formula that can be used to calculate the Labour Rate Variance. The values given in the question can be placed on the diagram and the variances calculated. Actual Cost £30,000 Labour Rate Variance £7,800(f) SR £1.40 Standard Cost £42,000 Efficiency Variance SR(SH – AH) = £1.40 × 3,000 = £4,200(f) SH 30,000 AH 27,000 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 9 10 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) STANDARD COSTS AND BUDGETED COSTS SECTION 3 Standard costs and budgeted costs Because standard costing is used for both controlling costs and preparing budgeted final accounts, it is important to include all overheads so that all costs are planned for. This requires the following to be taken into account. Overhead absorption rates Overheads are usually absorbed on the basis of the budgeted labour hours and so it is necessary to calculate both the Variable Overhead Absorption Rate and the Fixed Overhead Absorption Rate so that all overhead costs are charged to the cost unit. The formula is • Variable OH Absorption Rate (VOAR) = Variable Budgeted OH/ Budgeted Hours • Fixed OH Absorption Rate (FOAR) = Fixed Budgeted OH/Budgeted Hours Standard hours production Production is usually expressed in terms of units or £s. However, when standard costing techniques are used, production can be expressed in terms common to all types of production – standard hour. This is the quantity of output or amount of work which should be produced in one hour. This is particularly useful when examining overheads because the standard hours production can be compared with the actual hours production. • Standard Hours Production (SHP) = Standard Hours × Actual Production Variable overhead variances Unlike fixed overheads there are two ways in which variable overhead variances can be calculated. The method used depends on the information given in the question. In both cases the variances are the same. • Variable Overhead Cost Variance • Variable Overhead Expenditure Variance • Variable Overhead Efficiency Variance ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 11 STANDARD COSTS AND BUDGETED COSTS Method 1 If the information presented in the question gives only actual and standard information, the variable overhead variances are calculated in the same way as in material and labour variances. Example 12,000 units are produced and result in Actual Variable Overheads of £20,000 for 10,000 hours worked. The Standard Variable Overheads expected were £1 for each hour worked. Calculate the Variable Overhead variances. Actual Cost £20,000 Expenditure Variance AH(SR – AR) = £10,000(a) SR £1.00 Standard Cost £12,000 Efficiency Variance SR(SH – AH) = £1.00 × 2,000 = £2,000(f) SH 12,000 AH 10,000 Answer Variable Overhead Cost Variance = SC – AC = £12,000 – £20,000 = £8,000 (a) Variable Overhead Expenditure Variance = AH(SR – AR) = £10,000 (a) Variable Overhead Efficiency Variance = SR(SH – AH) = £2,000 (f) 12 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) STANDARD COSTS AND BUDGETED COSTS Method 2 For factory overhead costs, the variances are calculated for the factory as a whole or for each cost centre. When the overhead costs are calculated for the factory as a whole, the information is given as a budget rather than as individual standard costs and this requires the calculation of the Overhead Absorption Rate since no Standard Rate is available. However, the box method can still be used, with modest alterations, to calculate the Variable Overhead Variances. • VOAR = Variable Overhead Absorption Rate • SHP = Standard Hours Production Actual Cost AR Expenditure Variance (VOAR × AH) – AC SR/VOAR Efficiency Variance Standard Cost SR(VOAR(SH/SHP – AH SH/SHP AH Example From the following information calculate all the Variable Overhead Variances. Budgeted: Variable Overheads £7,500 Budgeted Hours 6,000 Actual: Variable Overheads £9,000 Hours worked 5,000 Standard Hours 5,400 Answer Variable Overhead Cost Variance = SC – AC = £6,750 – £9,000 = £2,250 (a) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 13 STANDARD COSTS AND BUDGETED COSTS Variable Overhead Expenditure Variance = (VOAR × AH) – AC = £2,750 (a) Variable Overhead Efficiency Variance = VOAR(SH – AH) = £500 (f) • VOAR = Budgeted Overheads £7,500 = = £1.25 Budgeted Hours 6,000 • Standard Cost = Standard Hours × VOAR = 5,400 × £1.25 = £6,750 In this type of question the Standard Rate becomes the Variable Overhead Absorption Rate. It is important to check that the correct box layout is used when the information provided is of a budgeted nature. Actual Cost £9,000 AR £1.80 Expenditure Variance AH(VOAR – AR) = £2,750(a) SR £1.25 Efficiency Variance Standard Cost £6,750 VOAR(SH – AH) = £500(f) SH 5,400 AH 5,000 Fixed overhead variances Unlike any other cost element, fixed overheads are dealt with in a separate way since these are always budgeted for. Fixed overheads can be broken down into more than three variances and include: • Fixed Overhead Cost Variance – the total variance • Fixed Overhead Expenditure Variance – occurs when the cost of overheads is different from that allowed for • Fixed Overhead Volume Variance – occurs when the volume of production differs from that allowed for. This variance can be subdivided into: 14 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) STANDARD COSTS AND BUDGETED COSTS – Fixed Overhead Efficiency Variance – this arises due to labour being used more or less efficiently than planned – Fixed Overhead Capacity Variance – this arises when the hours worked are more or less than planned. Like the other costs, fixed overheads can be displayed using a box layout. The main difference is the use of Budgeted Hours (BH) which represents the overall total hours set for the work to be completed. Thus the Fixed Overhead Variances are: Actual Cost AR Expenditure Variance Box 2 SR/FOAR Standard Cost Volume Variance Box 1 SH/SHP BH AH Fixed Overhead Cost Variance (Box 1 – Box 3) = SC – AC Fixed Overhead Volume Variance (Box 1 – Box 2) = SC – (FOAR × BH) Fixed Overhead Expenditure Variance (Box 2 – Box 3) = (FOAR × BH) – AC • FOAR = Fixed Overhead Absorption Rate = Fixed Overheads Budgeted Hours • SH can also be SHP and SR can be FOAR. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 15 STANDARD COSTS AND BUDGETED COSTS Example Calculate all the Fixed Overhead Variances for the following: Budgeted Fixed Overheads £4,800 Hours 6,000 Actual Fixed Overheads £5,000 Hours 5,000 Standard Hours 5,400 Answer FOAR = Budgeted Fixed Overheads £4,800 = = £0.80 Budgeted Hours 6,000 Fixed Overhead Cost Variance = SC – AC = £4,320 – £5,000 = £680(a) Fixed Overhead Volume Variance = SC – (FOAR × BH) = £480(a) Fixed Overhead Expenditure Variance = (FOAR × BH) – AC = £200(a) The Standard Rate becomes the Fixed Overhead Absorption Rate in this type of question. Actual Cost £5,000 Expenditure Variance (FOAR – BH) – AC = £200(a) FOAR £0.80 Standard Cost £4,320 Volume Variance SC – (FOAR × BH) = £480(f) SH £5,400 BH 6,000 AH 5,000 The Fixed Overhead Volume Variance can be sub-divided: • Fixed Overhead Efficiency Variance • Fixed Overhead Capacity Variance. In order to calculate the last two Fixed Overhead variances, Fixed Overhead Efficiency and Fixed Overhead Capacity, alterations are required to the diagram. 16 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) STANDARD COSTS AND BUDGETED COSTS Actual Cost Expenditure Variance FOAR/SR Volume Variance Capacity Variance Efficiency Variance SH/SHP ! ! Standard Cost AH The Fixed Overhead Volume Variance is sub-divided: Fixed Overhead Efficiency Variance = FOAR(SH – AH) = £0.8(5,400 – 5,000) = £320(f) Fixed Overhead Capacity Variance = FOAR(AH – BH) = £0.8(5,000 – 6,000) = £800(a) Cost variance formulae Material variance Material Cost Variance = SC – AC Material Price Variance = AQ(SP – AP) Material Usage Variance = SP(SQ – AQ) Labour variances Labour Cost Variance = SC – AC Labour Wage Rate Variance = AH(SR – AR) Labour Efficiency Variance = SR(SH – AH) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 17 STANDARD COSTS AND BUDGETED COSTS Variable overhead variances Variable Overhead Cost Variance = SC – AC or (SH × VOAR) – AC Variable Overhead Expenditure Variance = AH(SR – AR) or (VOAR × AH) – AC Variable Overhead Efficiency Variance = SR(SH – AH) or VOAR(SH – AH) Fixed overhead variances Fixed Overhead Cost Variance = SC – AC Fixed Overhead Volume Variance = SC – (FOAR × BH) Fixed Overhead Expenditure Variance = (FOAR × BH) – AC The Fixed Overhead Volume Variance can be sub-divided into: Fixed Overhead Efficiency Variance = FOAR(SH – AH) Fixed Overhead Capacity Variance = FOAR(BH – AH) [The formulae used for standard costing are not uniform. The textbooks currently on the market provide more than one set of formulae, however the use of the diagrams will always provide a correct solution to the question set as will the formulae list provided by SQA.] 18 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) REVENUE VARIANCES SECTION 4 Revenue variances Changes in profit occur when the budgeted revenue varies from the actual revenue. Actual Revenue AP Sales Price Variance BP Budgeted Revenue Sales Volume Variance BQ AQ The Revenue Variances are = (Actual Price – Budgeted Price) × Actual Quantity Sales Volume Variance = (Actual Quantity – Budgeted Quantity) × Budgeted Price Total Sales Revenue Variance = Actual Revenue – Budgeted Revenue Sales Price Variance The same box layout that is used for the cost variances can be used for the revenue variances where standard information is replaced with budgeted information. The revenue variances can be adverse or favourable depending on whether the expected selling price and volume of sales were achieved. Remember that revenue will operate in the directly opposite way to costs. If the actual sales revenue is less than that budgeted for, the variance is adverse and if the actual sales revenue is more than that budgeted for, the variance is favourable. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 19 REVENUE VARIANCES Reasons for variances Sales price variances are caused by • • • • change in price change in demand competitors’ prices prices of similar products. Sales volume variances are caused by • • • • poor sales force low levels of production and stock cancelled orders high sales returns. Example The following information is provided by the Sales Manager: Budgeted 300 £20 Sales (in units) Selling Price Actual 310 £18 Answer Total Sales Revenue Variance = AR – BR = £5,580 – £6,000 = £420(a) Sales Price Variance = (AP – BP) × AQ = –£2 × 310 = £620(a) Sales Volume Variance = (AQ – BQ) × BP = 10 × £20 = £200(f) Actual Revenue £18 Sales Price Variance £620(a) £20 Budgeted Revenue £6,000 Sales Volume Variance £200(f) BQ 300 20 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) AQ 310 FORMULAE SECTION 5 Calculation of variances using formulae Formulae The calculation of variances can be undertaken using formulae. The disadvantages of using formulae are that: • different textbooks give different formulae; • the standard costing formulae are very similar and mistakes can be made. The SQA will provide standard cost formulae for use with the NABs but will not provide them for students in the External Examination. To avoid confusion between the many suggested formulae, the SQA have provided an authorised list that students are expected to use in their examinations. Materials Material Price Variance = (Standard Price – Actual Price) × Actual Quantity Material Usage Variance = (Standard Quantity – Actual Quantity) × Standard Price Total Material Cost Variance = (Standard Quantity × Standard Price) – (Actual Quantity × Actual Price) Labour Labour Rate Variance = (Standard Rate – Actual Rate) × Actual Hours Labour Efficiency Variance = (Standard Hours – Actual Hours) × Standard Rate Total Labour Cost Variance = (Standard Rate × Standard Hours) – (Actual Rate × Actual Hours) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 21 FORMULAE Variable overheads Variable Overhead Variance = (Variable Overhead Absorption Rate × Expenditure Actual Hours) – Actual Cost Variable Overhead Efficiency = Variable Overhead Absorption Variance Rate (Standard Hours – Actual Hours) Variable Overhead Cost Variance = (Standard Hours × Variable Overhead Absorption Rate) – Actual Cost Fixed overheads Fixed Overhead Expenditure = (Fixed Overhead Absorption Rate × Variance Budgeted Hours) – Actual Cost of Fixed Overheads Fixed Overhead Volume Variance = Standard Cost of Fixed Overheads – (Fixed Overhead Absorption Rate × Budgeted Hours) Fixed Overhead Cost Actual Variance = Standard Cost of Fixed Overhead – Cost of Fixed Overhead The Fixed Overhead Volume Variance sub-divides into: Fixed Overhead Efficiency (Productivity) Variance = Fixed Overhead Absorption Rate (Standard Hours – Actual Hours) Fixed Overhead Capacity (Production) Variance = Fixed Overhead Absorption Rate (Actual Hours – Budgeted Hours) Revenue Sales Price Variance = (Actual Price – Budgeted Price) × Actual Quantity Sales Volume Variance = (Actual Quantity – Budgeted Quantity) × Budgeted Price Total Sales Revenue Variance = Actual Revenue – Budgeted Revenue 22 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) FORMULAE The application of a formula to calculate variances will produce the same result as the box approach. The formulae used in variance analysis can be divided into three: • the formulae for materials and labour variances are very similar; • the formulae for variable and fixed overhead variances require the use of budgeted information and the calculation of overhead absorption rates; • the formulae for revenue variances require the use of budgeted information. The following worked examples show how all the variances can be calculated using the formulae. Example 1 The Greendyke Manufacturing Company manufactures Glitzi using the following standard specification. Standard direct labour: 9,600 hours at £3.80 per hour Standard direct materials: 7,000 metres at £6 per metre Actual amount of materials used was 7,500 metres costing £45,750. Actual labour hours were 9,500 costing £38,000. Using the above information calculate all the variances for both materials and labour. Answer Actual Price = £45,750 = £6.10 7,500 Actual Wage Rate = £38,000 = £4 9,500 Material Price Variance = (SP – AP) × AQ = (£6 – £6.10) × 7,500 = (–£0.1) × 7,500 = £750(a) Material Usage Variance = (SQ – AQ) × SP = (7,000 – 7,500) × £6 = (–500) × £6 = £3,000(a) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 23 FORMULAE Total Material Cost Variance = (SQ × SP) – (AQ × AP) =(7,000 × £6) – (7,500 × £6.10) = £42,000 – £45,750 = £3,750(a) Labour Rate Variance = (SR – AR) × AH = (£3.80 – £4) × 9,500 = (–£0.2) × 9,500 = £1,900(a) Labour Efficiency Variance = (SH – AH) × SR = (9,600 – 9,500) × £3.80 = (100) × £3.80 = £380(f) Total Labour Cost Variance = (SR × SH) – (AR × AH) = (£3.80 × 9,600) – (£4 × 9,500) = £36,480 – £38,000 = £1,520(a) *Note that a (–) sign indicates an adverse variance and a (+) sign indicates a favourable variance. Example 2 Jackson Manufacturer produces plugs for sale to a wide range of retail outlets. The information that they have on their overhead costs are as follows. Budgeted: Variable Overheads £8,000 Fixed Overheads £10,000 Budget Hours 5,000 Actual: Variable Overheads £8,600 Fixed Overheads £9,500 Hours worked 4,000 Standard Hours/Standard Hours Production 4,500 Calculate all the overhead variances. Answer Calculations: Variable Overhead Absorption Rate = Fixed Overhead Absorption Rate = Budgeted Overheads £8,000 = = £1.60 Budgeted Hours 5,000 Budgeted Overheads £10,000 = = £2 Budgeted Hours 5,000 (Standard Hours × Actual Production) = 4,500 Standard Hours Standard Cost = FOAR × Standard Hours = £2 × 4,500 = £9,000 Standard Cost – VOAR × Standard Hours = £1.60 × 4,500 = £7,200 Standard Hours Production = 24 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) FORMULAE Variable overheads Variable Overhead Expenditure Variance = (VOAR × AH) – AC = (£1.60 × 4,000) – £8,600 = £6,400 – £8,600 – £6,400 = £2,200(a) Variable Overhead Efficiency Variance = VOAR(SH – AH) = £1.60(4,500 – 4,000) = £800(f) Variable Overhead Cost Variance = (SH × VOAR) – AC = (4,500 × £1.60) – £8,600 = £7,200 – £8,600 = £1,400(a) Fixed overheads Fixed Overhead Expenditure Variance = (FOAR × BH) – AC = (£2 × 10,000) – 9,500 = £500(f) Fixed Overhead Volume Variance = SC – (FOAR × BH) = £9,000 – (£2 × 5,000) = £9,000 – £10,000 = £1,000(a) Fixed Overhead Cost Variance = SC – AC = £9,000 – £9,500 = £500(a) Fixed Overhead Efficiency (Productivity) Variance = FOAR(SH – AH) = £2 (4,500 – 4,000) = £1,000(f) Fixed Overhead Capacity (Production) Variance = FOAR(AH – BH) = £2 × (4,000 – 5,000) = £2,000(a) * Note that a (–) sign indicates an adverse variance and a (+) sign indicates a favourable variance. Example 3 The following information is provided by the Production Manager of PB Manufacturing. Budgeted 500 £8 Sales (in units) Selling Price Actual 480 £10 Calculate all the Revenue Variances. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 25 FORMULAE Answer Sales Price Variance = (AP – BP) × AQ = (£10 – £8) × 480 = £960(f) Sales Volume Variance = (AQ – BQ) × BP = (480 – 500) × £8 = (–20) × £8 = £160(a) Total Sales Revenue Variance = AR – BR = £4,800 – £4,000 = £800(f) 26 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) EXERCISES SECTION 6 Question 1 Calculate the material variances from the following data stating whether they are price variances or usage variances – adverse or favourable. Material Details (a) Standard price per kilo £40 Standard usage per unit 11 kilos Actual price per kilo £40 Actual usage per unit 13 kilos (b) Standard price per metre £25 Standard usage per unit 60 metres Actual price per unit £28 Actual usage per unit 60 metres (c) Standard price per kilo £3 Standard usage per unit 1,000 kilos Actual price per kilo £3 Actual usage per unit 973 kilos (d) Standard price per gram £17 Standard usage per unit 440 grams Actual price per gram £14 Actual usage per unit 440 grams (e) Standard price per metre £6 Standard usage per unit 88 metres Actual price per metre £4 Actual usage per unit 85 metres (f) Standard price per kilo £117 Standard usage per unit 30 kilos Actual price per kilo £123 Actual usage per unit 20 kilos (g) Standard price per litre £15 Standard usage per unit 158 litres Actual price per litre £16 Actual usage per unit 165 litres ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 27 EXERCISES Question 2 Calculate as many variances as you can from the following information. 1. 2. 3. 4. 5. 28 Standard cost per unit Actual cost of 5,000 units produced Material 5 kilos @ £0.60 per kilo Labour 1 hr @ £1.10 per hr Material 26,500 kilos costing £13,000 Labour 4,800 hrs costing £5,000 Standard cost per unit Actual cost of 7,500 units produced Material 3 m @ £2.50 per m Labour 4 hrs @ £1.20 per hr Material 21,000 m costing £50,000 Labour 28,000 hrs costing £30,000 Standard cost per unit Actual cost of 10,000 units produced Material 5 kilos @ £0.50 per kilo Labour 2 hrs @ £2 per hr Variable Overheads 1 hr @ £1/hr Material 54,000 kilos costing £26,000 Labour 19,000 hrs costing £30,000 Variable overhead 10,000 hrs costing £15,000 Standard cost per unit Actual cost of 1,000 units produced Material 2 m @ £1.50 per m Labour 6 hrs @ £0.8 per hr Material 2,000 m costing £4,000 Labour 7,000 hrs costing £7,000 Standard cost per unit Actual cost of 3,000 units produced Material 1 g @ £3 per g Labour 2 hrs @ £1.20 per hr Material 4,000 g costing £15,000 Labour 6,000 hrs costing £8,000 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) EXERCISES Question 3 Calculate the standard cost of materials, labour and variable overheads for each of the following products and related outputs. 1. 2,000 units were produced of product Z where: Actual costs: Direct materials £800; Direct labour £300; Variable overheads £200 Favourable variances: Material usage £20; Overhead volume £50 Adverse variances: Material price £40; Labour efficiency £10; Labour rate £20; Overhead expenditure £30. 2. 1,000 units were produced of product S where: Actual cost: Direct materials £1,000; Direct labour £400; Variable overheads £200 Favourable variances: Material usage £10; Overhead volume £40; Material price £10 Adverse variances: Labour efficiency £20; Labour rate £30; Overhead expenditure £10. 3. 5,000 units were produced of product A where: Actual costs: Direct materials £900; Direct labour £200; Variable overheads £100 Favourable variances: Material usage £20; Overhead volume £20; Material price £10 Adverse variances: Labour efficiency £20; Labour rate £20; Overhead expenditure £10 4. 2,000 units were produced of product B where: Actual costs: Direct material £300; Direct labour £600; Variable overheads £100 Favourable variances: Material usage £30; Overhead volume £40 Adverse variances: Material price £20; Labour efficiency £20; Labour rate £10; Overhead expenditure £30. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 29 EXERCISES Question 4 Calculate as many variances as you can from the following information. 1. 2. 3. 4. 5. 6. 30 Standard Cost per unit Actual Cost of 10,000 units produced Material 4 m @ £0.50 per m Labour 3 hrs @ £1.40 per hr Material 16,000 m costing £18,000 Labour 27,000 hrs costing £40,000 Standard Cost per unit Actual Cost of 4,000 units produced Material 2 kilos @ £4.00 per kilo Labour 6 hrs @ £1.00 per hr Material 10,000 kilos costing £20,000 Labour 40,000 hrs costing £38,000 Standard Cost per unit Actual Cost of 2,000 units produced Material 2 m @ £2.50 per m Labour 1 hr @ £1.00 per hr Material 6,000 m costing £12,000 Labour 5,000 hrs costing £4,000 Standard Cost per unit Actual Cost of 1,000 units produced Material 1 kilo @ £1 per kilo Labour 2 hrs @ £2 per hr Material 1,000 kilos costing £1,000 Labour 2,000 hrs costing £4,000 Standard Cost per unit Actual Cost of 500 units produced Material 3 kilos @ £0.80 per kilo Labour 1 hr @ £0.50 per hr Variable Overheads 2 hrs @ £1/hr Material 1,400 kilos costing £1,000 Labour 350 hrs costing £400 Variable Overheads 800 hrs costing £1,500 Standard Cost per unit Actual Cost of 2,000 units produced Material 8 kilos @ £0.75 per kilo Labour 20 hrs @ £0.30 per hr Variable Overheads1 hr @ £0.70/hr Material 15,000 kilos costing £14,000 Labour 17,000 hrs costing £20,000 Variable Overheads 5,000 hrs costing £3,000 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) EXERCISES Question 5 Calculate the standard cost of materials, labour and variable overheads for each of the following products and related outputs. 1. 400 units were produced of product S where: Actual costs: Direct materials £400; Direct labour £100; Variable overheads £100 Favourable variances: Material usage £5; Overhead volume £60 Adverse variances: Material price £60; Labour efficiency £20, Labour rate £8. 2. 4,500 units were produced of product A where: Actual costs: Direct materials £700; Direct labour £1,000; Variable overheads £300 Favourable variances: Material price £60 Adverse variances: Material usage £30; Labour efficiency £10; Labour rate £5; Overhead volume £4; Overhead expenditure £6. 3. 8,000 units were produced of product B where: Actual costs: Direct materials £400; Direct labour £6,000; Variable overheads £350 Favourable variances: Material usage £4.50; Labour efficiency £3 Adverse variances: Material price £22; Labour rate £37; Overhead expenditure £64. 4. 2,000 units were produced of product G where: Actual costs: Direct materials £8,000; Direct labour £300; Variable overheads £1,200 Favourable variances: Material price £55; Labour rate £40; Overhead expenditure £23 Adverse variances: Material usage £4.20; Labour efficiency £7.50. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 31 EXERCISES 5. 500 units were produced of product T where: Actual costs: Direct material £3,000; Direct labour £1,500; Variable overheads £3,500 Favourable variances: Materials usage £38; Material price £30; Labour rate £40; Overhead spending £40. 32 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) EXERCISES Question 6 (a) Green Manufacturing Co Ltd uses a Standard Costing system. The following details relate to the current month during which 1,500 units were produced. Material Labour Standard cost per unit 2 kg @ £3 per kg 3 hours @ £10 per hour Actual cost of 1,500 units produced 2,800 kg @ £2.50 per kg 4,000 hours @ £11 per hour You are required to calculate the cost variances relating to materials and labour. (b) The Greenend Manufacturing Co Ltd produces a unit for the computer industry. The following is the information relating to the production of this unit during the first quarter of the current year when 10,000 units were produced. Material Labour Standard cost per unit Actual cost of producing 10,000 units 10 kg @ 50p per kg 195,000 kg @ 60p per kg 4 hours @ £1.80 per hour 40,500 hours @ £1.60 per hour You are required to calculate the cost variances relating to materials and labour. (c) Macrae Manufacturing Co Ltd operates a Standard Costing system. The following details relate to this month. Materials Labour Standard cost per unit 5 kg @ £3 per kg 1 hour @ £10 per hour Actual cost of producing 3,000 units 15,100 kg @ £2.90 per kg 1,450 hours @ £9 per hour You are required to calculate the cost variances relating to materials and labour. (d) The following data relates to Product Z which MacIntosh Manufacturing Co Ltd makes. This month 5,000 units were produced. Materials Labour Standard cost per unit 10 kg @ £0.5 per kg 5 hours @ £0.8 per hour Actual cost of 5,000 units produced 49,500 kg @ £0.70 per kg 25,200 hours @ £1.10 per hour You are required to calculate the cost variances relating to materials and labour. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 33 EXERCISES Question 7 (a) Applewhite Manufacturing plc uses a Standard Costing system. The levels of output for the current month are as follows: Actual output 2,000 units Budgeted output 1,800 units The following details relate to the current month: Material Labour Standard cost per unit Actual cost of 2,000 units 2 m @ £2 per m 4,600 m @ £1.60 per m 2 hours @ £12.50 per hour 5,000 hours @ £12 per hr The overheads are recovered on the basis of direct labour hours. Budgeted output 1,800 Variable overheads £2 per labour hour Fixed overheads £3 per labour hour Actual cost of 2,000 units £8,000 £20,000 You are required to calculate the cost variances relating to materials, labour, variable and fixed overheads. (b) Brown Manufacturing uses a Standard Costing system. The levels of output for the current month are as follows: Actual output Budgeted output 5,000 units 4,500 units The following details relate to the current month: Material Labour Standard cost per unit 3 kg @ £3 per kg 2 hours @ £6 per hour Actual cost of 5,200 units 15,000 kg @ £3.10 per kg 20,000 hours @ £7 per hour The overheads are recovered on the basis of direct labour hours. Budgeted output 4,500 Variable overheads £1 per labour hour Fixed overheads £2 per labour hour Actual cost of 5,200 units £5,000 £30,000 You are required to calculate the cost variances relating to materials, labour, variable and fixed overheads. 34 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) EXERCISES Question 8 (a) Zoda Manufacturing plc has difficulty in identifying its overhead variances. The information below shows the budgeted and actual details collected for the past month. Variable overheads Fixed overheads Budgeted £8,000 £5,000 Actual £7,000 £5,600 Zoda Manufacturing plc operates a Standard Costing system and has identified the following hourly details: Budgeted hours Standard hours Actual hours 5,000 5,200 5,600 Using the information above calculate all the overhead variances. (b) Yell Manufacturing plc has identified its overhead expenses. The information below shows the budgeted and actual details they have collected for the past month. Variable overheads Fixed overheads Budgeted £20,000 £18,000 Actual £22,000 £16,000 Yell Manufacturing plc operates a Standard Costing system and has identified the following hourly details: Budgeted hours Standard hours Actual hours 5,000 4,500 4,000 Using the information above calculate the overhead variances. ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 35 EXERCISES Question 9 (a) Cameron Co Ltd has calculated the cost variances and are now preparing their revenue variances from the following information: Sales (in units) Sales (price per unit) (b) Actual data for July 4,500 £13 Duffy Co Ltd has calculated cost variances and is now preparing its revenue variances from the following information: Sales (in units) Sales (price per unit) (c) Budgeted data for July 5,000 £12 Budgeted data for August 10,000 £20 Actual data for August 9,000 £18 Edwards Co Ltd has calculated cost variances and is now preparing its revenue variances from the following information: Sales (in units) Sales (price per unit) Budgeted data for 3 months to January 12,500 £30 Actual data for 3 months to January 15,000 £35 (d) Ferguson Co Ltd has calculated cost variances and is now preparing its revenue variances from the following information: Sales (in units) Sales (price per unit) 36 Budgeted data for current month 1,000 £6 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) Actual data for current month 1,500 £5 SOLUTIONS SECTION 7 Answer 1 Material Calculations (a) Total Material Cost Variance = (SC – AC) = £440 – £520 = £80 (A) Material Price Variance = (SP – AP)AQ = (£40 – £40)13 = £0 × 13 = 0 Material Usage Variance = (SQ – AQ)SP = (11 – 13)£40 = –2 × £40 = £80 (A) (b) Total Material Cost Variance = (SC – AC) = £1,500 – £1,680 = £180 (A) Material Price Variance = (SP – AP)AQ = (£25 – £28)60 = –£3 × £60 = £180 (A) Material Usage Variance = (SQ – AQ)SP = (60 – 60)£25 = 0 × £25 = 0 (c) Total Material Cost Variance = (SC – AC) = £3,000 – £2,919 = £81 (F) Material Price Variance = (SP – AP)AQ = (£3 – £3)973 = £0 × 973 = 0 Material Usage Variance = (SQ – AQ)SP = (1,000 – 973)£3 = 27 × £3 = £81 (F) (d) Total Material Cost Variance = (SC – AC) = £7,480 – £6,160 = £1,320 (F) Material Price Variance = (SP – AP)AQ = (£17 – £14)440 = £3 × 440 = £1,320 (F) Material Usage Variance = (SQ – AQ)SP = (440 – 440)£17 = 0 × £17 = 0 (e) Total Material Cost Variance = (SC – AC) = £528 – £340 = £188 (F) Material Price Variance = (SP – AP)AQ = (£6 – £4)85 = £2 × 85 = £170 (F) Material Usage Variance = (SQ – AQ)SP = (88 – 85)£6 = 3 × £6 = £18 (F) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 37 SOLUTIONS (f) Total Material Cost Variance = (SC – AC) = £3,510 – £2,460 = £1,050 (F) Material Price Variance = (SP – AP)AQ = (£117 – £123)20 = –£6 × 20 = £120 (A) Material Usage Variance = (SQ – AQ)SP = (30 –20)£117 = 10 × £117 = £1,170 (F) (g) Total Material Cost Variance = (SC – AC) = £2,370 – £2,640 = £270 (A) Material Price Variance = (SP – AP)AQ = (£15 – £16)165 = –£1 × 165 = £165 (A) Material Usage Variance = (SQ – AQ)SP = (158 –165)£15 = –£7 × 15 = £105 (A) 38 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Answer 2 1. Materials AC = £13,000 SC = £0.60 × 5 × 5,000 = £15,000 Total Material Cost Variance = (SC – AC) = £15,000 – £13,000 = £2,000 (F) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£0.60 × 26,500) – £13,000 = £15,900 – £13,000 = £2,900 (F) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £15,000 – (26,500 × £0.60) = £15,000 – £15,900 = £900 (A) Labour AC = £5,000 SC = £1.10 × 1 × 5,000 = £5,500 Total Labour Cost Variance = (SC – AC) = £5,500 – £5,000 = £500 (F) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1.10 × 4,800) – £5,000 = £5,280 – £5,000 = £280 (F) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £5,500 – (4,800 × £1.10) = £5,500 – £5,280 = £220 (F) 2. Materials AC = £50,000 SC = £2.50 × 3 × 7,500 = £56,250 Total Material Cost Variance = (SC – AC) = £56,250 – £50,000 = £6,250 (F) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£2.50 × 21,000) – £50,000 = £52,500 – £50,000 = £2,500 (F) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £56,250 – (21,000 × £2.50) = £56,250 – £52,500 = £3,750 (F) Labour AC = £30,000 SC = £1.20 × 4 × 7,500 = £36,000 Total Labour Cost Variance = (SC – AC) = £36,000 – £30,000 = £6,000 (F) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1.20 × 28,000) – £30,000 = £33,600 – £30,000 = £3,600 (F) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £36,000 – (28,000 × £1.20) = £36,000 – £33,600 = £2,400 (F) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 39 SOLUTIONS 3. Materials AC = £26,000 SC = £0.50 × 5 × 10,000 = £25,000 Total Material Cost Variance = (SC – AC) = £25,000 – £26,000 = £1,000 (A) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£0.50 × 54,000) – £26,000 = £27,000 – £26,000 = £1,000 (F) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £25,000 – (54,000 × £0.50) = £25,000 – £27,000 = £2,000 (A) Labour AC = £30,000 SC = £2 × 2 × 10,000 = £40,000 Total Labour Cost Variance = (SC – AC) = £40,000 – £30,000 = £10,000 (F) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£2 × 19,000) – £30,000 = £38,000 – £30,000 = £8,000 (F) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £40,000 – (19,000 × £2) = £40,000 – £38,000 = £2,000 (F) Variable Overheads AC = £15,000 SC = £1 × 1 × 10,000 = £10,000 Variable Overhead Cost Variance = (SC – AC) = £10,000 – £15,000 = £5,000 (A) Variable Overhead Expenditure Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1 × 10,000) – £15,000 = £10,000 – £15,000 = £5,000 (A) Variable Overhead Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £10,000 – (10,000 × £1) = £10,000 – £10,000 = 0 4. 40 Materials AC = £4,000 SC = £1.50 × 2 × 1,000 = £3,000 Total Material Cost Variance = (SC – AC) = £3,000 – £4,000 = £1,000 a Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£1.5 × 2,000) – £4,000 = £3,000 – £4,000 = £1,000 (A) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £3,000 – (2,000 × £1.5) = £3,000 – £3,000 = 0 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Labour AC = £7,000 SC = £0.80 × 6 × 1,000 = £4,800 Total Labour Cost Variance = (SC – AC) = £4,800 – £7,000 = £2,200 (A) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£0.8 × 7,000) – £7,000 = £5,600 – £7,000 = £1,400 (A) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £4,800 – (7,000 × £0.80) = £4,800 – £5,600 = £800 (A) 5. Materials AC = £15,000 SC = £3 × 1 × 3,000 = £9,000 Total Material Cost Variance = (SC – AC) = £9,000 – £15,000 = £6,000 (A) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£3 × 4,000) – £15,000 = £12,000 – £15,000 = £3,000 (A) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £9,000 – (£4,000 × £3) = £9,000 – £12,000 = £3,000 (A) Labour AC = £8,000 SC = £1.20 × 2 × 3,000 = £7,200 Total Labour Cost Variance = (SC – AC) = £7,200 – £8,000 = £800 (A) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1.20 × 6,000) –£8,000 = £7,200 – £8,000 = £800 (A) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £7,200 – (6,000 × £1.20) = £7,200 – £7,200 = 0 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 41 SOLUTIONS Answer 3 1. Materials Actual Cost £800; Price Variance £40 (A); Usage Variance £20 (F) Standard Cost = £800 – £40 + £20 = £780 Labour Actual Cost £300; Wage Rate Variance £20 (A); Efficiency Variance £10 (A) Standard Cost = £300 – £20 – £10 = £270 Variable Overheads Actual Cost £200; Spending Variance £30 (A); Efficiency Variance £50 (F) Standard Cost = £200 – £30 + £50 = £220 2. Materials Actual Cost £1,000; Price Variance £10 (F); Usage Variance £10 (F) Standard Cost = £1,000 + £10 + £10 = £1,020 Labour Actual Cost £400; Wage Rate Variance £30 (A); Efficiency Variance £20 (A) Standard Cost = £400 – £30 – £20 = £350 Variable Overheads Actual Cost £200; Spending Variance £10 (A); Efficiency Variance £40 (F) Standard Cost = £200 – £10 + £40 = £230 3. Materials Actual Cost £900; Price Variance £10 (F); Usage Variance £20 (F) Standard Cost = £900 + £10 + £20 = £930 Labour Actual Cost £200; Wage Rate Variance £20 (A); Efficiency Variance £20 (A) Standard Cost = £200 – £20 – £20 = £160 Variable Overheads Actual Cost £100; Spending Variance £10 (A); Efficiency Variance £20 (F) Standard Cost = £100 – £10 + £20 = £110 4. 42 Materials Actual Cost £300; Price Variance £20 (A); Usage Variance £30 (F) Standard Cost = £300 – £20 + £30 = £310 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Labour Actual Cost £600; Wage Rate Variance £10 (A); Efficiency Variance £20 (A) Standard Cost = £600 – £10 – £20 = £570 Variable Overheads Actual Cost £100; Spending Variance £30 (A); Efficiency Variance £40 (F) Standard Cost = £100 – £30 + £40 = £110 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 43 SOLUTIONS Answer 4 1. Materials AC = £18,000 SC = £0.50 × 4 × 10,000 = £20,000 Total Material Cost Variance = (SC – AC) = £20,000 – £18,000 = £2,000 (F) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£0.5 × 16,000) – £18,000 = £8,000 – £18,000 = £10,000 (A) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £20,000 – (16,000 × £0.5) = £20,000 – £8,000 = £12,000 (F) Labour AC = £40,000 SC = £1.40 × 3 × 10,000 = £42,000 Total Labour Cost Variance = (SC – AC) = £42,000 – £40,000 = £2,000 (F) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1.4 × 27,000) – £40,000 = £37,800 – £40,000 = £2,200 (A) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £42,000 – (27,000 × £1.40) = £42,000 – £37,800 = £4,200 (F) 2. Materials AC = £20,000 SC = £4 × 2 × 4,000 = £32,000 Total Material Cost Variance = (SC – AC) = £32,000 – £20,000 = £12,000 (F) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£4 × 10,000) – £20,000 = £40,000 – £20,000 = £20,000 (F) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £32,000 – (10,000 × £4) = £32,000 – £40,000 = £8,000 (A) Labour AC = £38,000 SC = £1.00 × 6 × 4,000 = £24,000 Total Labour Cost Variance = (SC – AC) = £24,000 – £38,000 = £14,000 (A) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1 × 40,000) – £38,000 = £40,000 – £38,000 = £2,000 (F) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £24,000 – (40,000 × £1) = £24,000 – £40,000 = £16,000 (A) 44 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS 3. Materials AC = £12,000 SC = £2.50 × 2 × 2,000 = £10,000 Total Material Cost Variance = (SC – AC) = £10,000 – £12,000 = £2,000 (A) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£2.50 × 6,000) – £12,000 = £15,000 – £12,000 = £3,000 (F) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £10,000 – (6,000 × £2.50) = £10,000 – £15,000 = £5,000 (A) Labour AC = £4,000 SC = £1 × 1 × 2,000 = £2,000 Total Labour Cost Variance = (SC – AC) = £2,000 – £4,000 = £2,000 (A) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1 × 5,000) – £4,000 = £5,000 – £4,000 = £1,000 (F) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £2,000 – (5,000 × £1) = £2,000 – £5,000 = £3,000 (A) 4. Material AC = £1,000 SC = £1 × 1 × 1,000 = £1,000 Total Material Cost Variance = (SC – AC) = £1,000 – £1,000 = 0 Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = £1 × 1,000) – £1,000 = £1,000 – £1,000 = 0 Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £1,000 – (1,000 × £1) = £1,000 – £1,000 0 Labour AC = £4,000 SC = £2 × 2 × 1,000 = £4,000 Total Labour Cost Variance = (SC – AC) = £4,000 – £4,000 = 0 Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£2 × 2,000) – £4,000 = £4,000 – £4,000 = 0 Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £4,000 – (2,000 × £2) = £4,000 – £4,000 = 0 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 45 SOLUTIONS 5. Material AC = £1,000 SC = £0.80 × 3 × 500 = £1,200 Total Material Cost Variance = (SC – AC) = £1,200 – £1,000 = £200 (F) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£0.8 × 1,400) – £1,000 = £1,120 – £1,000 = £120 (F) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £1,200 – (1,400 × £0.8) = £1,200 – £1,120 = £80 (F) Labour AC = £400 SC = £0.50 × 1 × 500 = £250 Total Labour Cost Variance = (SC – AC) = £250 – £400 = £150 (A) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£0.5 × 350) – £400 = £175 – £400 = £225 (A) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £250 – (350 × £0.5) = £250 – £175 = £75 (F) Variable Overheads AC = £1,500 SC = £1 × 2 × 500 = £1,000 Variable Overhead Cost Variance = (SC – AC) = £1,000 – £1,500 = £500 (A) Variable Overhead Expenditure Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£1 × 800) – £1,500 = £800 – £1,500 = £700 (A) Variable Overhead Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £1,000 – (800 × £1) = £1,000 – £800 = £200 (F) 6. 46 Material AC = £14,000 SC = £0.75 × 8 × 2,000 = £12,000 Total Material Cost Variance = (SC – AC) = £12,000 – £14,000 = £2,000 (A) Material Price Variance = (SP – AP)AQ = (SP × AQ) – (AP × AQ) = (£0.75 × 15,000) – £14,000 = £11,250 – £14,000 = £2,750 (A) Material Usage Variance = (SQ – AQ)SP = (SQ × SP) – (AQ × SP) = £12,000 – (15,000 × £0.75) = £12,000 – £11,250 = £750 (F) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Labour AC = £20,000 SC = £0.30 × 20 × 2,000 = £12,000 Total Labour Cost Variance = (SC – AC) = £12,000 – £20,000 = £8,000 (A) Labour Rate Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£0.3 × 17,000) – £20,000 = £5,100 – £20,000 = £14,900 (A) Labour Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £12,000 – (17,000 × £0.3) = £12,000 – £5,100 = £6,900 (F) Variable Overheads AC = £3,000 SC = £0.70 × 1 × 2,000 = £1,400 Variable Overhead Cost Variance = (SC – AC) = £1,400 – £3,000 = £1,600 (A) Variable Overhead Expenditure Variance = (SR – AR)AH = (SR × AH) – (AR × AH) = (£0.7 × 5,000) – £3,000 = £3,500 – £3,000 = £500 (F) Variable Overhead Efficiency Variance = (SH – AH)SR = (SH × SP) – (AH × SR) = £1,400 – (5,000 × £0.7) = £1,400 – £3,500 = £2,100 (A) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 47 SOLUTIONS Answer 5 1. Materials Actual Cost £400; Price Variance £60 (A); Usage Variance £5 (F) Standard Cost = £400 – £60 + £5 = £345 Labour Actual Cost £100; Wage Rate Variance £80 (A); Efficiency Variance £20 (A) Standard Cost = £100 – £8 – £20 = £72 Variable Overheads Actual Cost £100; Spending Variance £0; Efficiency Variance £60 (F) Standard Cost = £100 + £60 = £160 2. Materials Actual Cost £700; Price Variance £60 (F); Usage Variance £30 (A) Standard Cost = £700 + £60 – £30 = £730 Labour Actual Cost £1,000; Wage Rate Variance £5 (A); Efficiency Variance £10 (A) Standard Cost = £1,000 – £5 – £10 = £985 Variable Overheads Actual Cost £300; Spending Variance £6 (A); Efficiency Variance £4 (A) Standard Cost = £300 – £6 – £4 = £290 3. Materials Actual Cost £400; Price Variance £22 (A); Usage Variance £4.5 (F) Standard Cost = £400 – £22 + £4.5 = £382.5 Labour Actual Cost £6,000; Wage Rate Variance £37 (A); Efficiency Variance £3 (F) Standard Cost = £6,000 – £37 + £3 = £5,966 Variable Overheads Actual Cost £350; Spending Variance £64 (A); Efficiency Variance £0 Standard Cost = £350 – £64 = £286 4. 48 Materials Actual Cost £8,000; Price Variance £55 (F); Usage Variance £4.2 (A) Standard Cost = £8,000 + £55 – £4.2 = £8,050.8 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Labour Actual Cost £300; Wage Rate Variance £40 (F); Efficiency Variance £7.5 (A) Standard Cost = £300 + £40 – £7.5 = £332.5 Variable Overheads Actual Cost £1,200; Spending Variance £23 (F); Efficiency Variance £0 Standard Cost = £1,200 + £23 = £1,223 5. Materials Actual Cost £3,000; Price Variance £30 (F); Usage Variance £38 (F) Standard Cost = £3,000 + £30 + £38 = £3,068 Labour Actual Cost £1,500; Wage Rate Variance £40 (F); Efficiency Variance £0 Standard Cost = £1,500 + £40 = £1,540 Variable Overheads Actual Cost £3,500; Spending Variance £40 (F); Efficiency Variance £0 Standard Cost = £3,500 + £40 = £3,540 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 49 SOLUTIONS Answer 6 (a) Material AC = 2,800 × £2.5 = £7,000 SC = 2 × £3 × 1,500 = £9,000 Total Material Cost Variance = (SC – AC) = £9,000 – £7,000 = £2,000 (F) Material Price Variance = (SP – AP)AQ = (£3 – £2.5)2,800 = £0.5 × 2,800 = £1,400 (F) Material Usage Variance = (SQ – AQ)SP = [(2 × 1,500) – 2,800]£3 = 200 × £3 = £600 (F) Labour AC = 4,000 × £11 = £44,000 SC = 3 × £10 × 1,500 = £45,000 Total Labour Cost Variance = (SC – AC) = £45,000 – £44,000 = £1,000 (F) Labour Rate Variance = (SR – AR)AH = (£10 – £11)4,000 = £1 × 4,000 = £4,000 (A) Labour Efficiency Variance = (SH – AH)SR = [(3 × 1,500) – 4,000]£10 = 500 × £10 = £5,000 (F) (b) Materials AC = 195,000 × £0.60 = £117,000 SC = 10 × £0.5 × 10,000 = £50,000 Total Material Cost Variance = (SC – AC) = £50,000 – £117,000 = £67,000 (A) Material Price Variance = (SP – AP)AQ = (£0.5 – £0.6)195,000 = £0.1 × 195,000 = £19,500 (A) Material Usage Variance = (SQ – AQ)SP = [(10 × 10,000) – 195,000]£0.5 = 95,000 × £0.5 =£47,500 (A) Labour AC = 40,500 × £1.6 = £64,800 SC = 4 × £1.8 × 10,000 = £72,000 Total Labour Cost Variance = (SC – AC) = £72,000 – £64,800 = £7,200 (F) Labour Rate Variance = (SR – AR)AH = (£1.80 – £1.60) 40,500 = £0.20 × 40,500 = £8,100 (F) Labour Efficiency Variance = (SH – AH)SR = [(4 × 10,000) – 40,500]£1.80 = 500 × £1.80 = £900 (A) 50 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS (c) Materials AC = 15,100 × £2.90 = £43,790 SC = 5 × £3 × 3,000 = £45,000 Total Material Cost Variance = (SC – AC) = £45,000 – £43,790 = £1,210 (F) Material Price Variance = (SP – AP)AQ = (£3 – £2.90)15,100 = £0.10 × 15,100 = £1,510 (F) Material Usage Variance = (SQ – AQ)SP = [(5 × 3,000) – 15,100]£3 = 100 × £3 = £300 (A) Labour AC = 1,450 × £9 = £13,050 SC = 1 × £10 × 3,000 = £30,000 Total Labour Cost Variance = (SC – AC) = £30,000 – £13,050 = £16,950 (F) Labour Rate Variance = (SR – AR)AH = (£10 – £9)1,450 = £1 × 1,450 = £1,450 (F) Labour Efficiency Variance = (SH – AH)SR = [(1 × 3,000) – 1,450]£10 = 1,550 × £10 = £15,500 (F) (d) Materials AC = 49,500 × £0.70 = £34,650 SC = 10 × £0.5 × 5,000 = £25,000 Total Material Cost Variance = (SC – AC) = £25,000 – £34,650 = £9,650 (A) Material Price Variance = (SP – AP)AQ = (£0.50 – £0.70)49,500 = £0.20 × 49,500 = £9,900 (A) Material Usage Variance = (SQ – AQ)SP = [(10 × 5,000) – 49,500]£0.50 = 500 × £0.50 = £250 (F) Labour AC = 25,200 × £1.10 = £27,720 SC = 5 × £0.8 × 5,000 = £20,000 Total Labour Cost Variance = (SC – AC) = £20,000 – £27,720 = £7,720 (A) Labour Rate Variance = (SR – AR)AH = (£0.8 – £1.1)25,200 = £0.30 × 25,200 = £7,560 (A) Labour Efficiency Variance = (SH – AH)SR = [(5 × 5,000) – 25,200]£0.80 = 200 × £0.80 =£160 (A) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 51 SOLUTIONS Answer 7 (a) Materials AC = 4,600 × £1.60 = £7,360 SC = 2 × £2.0 × 2,000 = £8,000 Total Material Cost Variance = (SC – AC) = £8,000 – £7,360 = £640 (F) Material Price Variance = (SP – AP)AQ = (£2 – £1.60)4,600 = £0.40 × 4,600 = £1,840 (F) Material Usage Variance = (SQ – AQ)SP = [(2 × 2,000) – 4,600]£2 = 600 × £2 = £1,200 (A) Labour AC = 5,000 × £12.00 = £60,000 SC = 2 × £12.50 × 2,000 = £50,000 Total Labour Cost Variance = (SC – AC) = £50,000 – £60,000 = £10,000 (A) Labour Rate Variance = (SR – AR)AH = (£12.50 – £12)5,000 =£.5 × 5,000 = £2,500 (F) Labour Efficiency Variance = (SH – AH)SR = [(2 × 2,000) – 5,000]£12.5 = 1,000 × £12.5 = £12,500 (A) Variable Overheads AC =£8,000 SC = 2 × £2 × 2,000 = £8,000 Total Overhead Cost Variance = SC – AC = £8,000 – £8,000 = £0 (A) Variable Overhead Expenditure Variance = (VOAR × AH) – AC = (£2 × 5,000) – £8,000 = £2,000 (F) Variable Overhead Efficiency Variance = VOAR/(SH–AH) = £2(4,000 – 5,000) = £2,000 (A) Fixed Overheads AC = £20,000 SC = 2 × £3 × 2,000 = £12,000 BH = 2 × 1,800 = 3,600 hrs SH = 2 × 2,000 = 4,000 hrs AH = 5,000 hrs Fixed Overhead Cost Variance Fixed Overhead Expenditure Variance = SC – AC = £12,000 – £20,000 = £8,000 (A) = (FOAR × BH) – AC = (£3 × 3,600) – £20,000 = £9,200 (A) Fixed Overhead Volume Variance = SC – (FOAR × BH) = £12,000 – (£3 × 3,600) = £1,200 (F) 52 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Fixed Overhead Efficiency Variance Fixed Overhead Capacity Variance (b) = FOAR/(SH – AH) = £3(4,000 – 5,000) = £3,000 (A) = FOAR/(AH – BH) = £3(5,000 – 3,600) = £4,200 (A) Materials AC = 15,000 × £3.10 = £46,500 SC = 3 × £3.0 × 5,200 = £46,800 Total Material Cost Variance = (SC – AC) = £46,800 – £46,500 = £300 (F) Material Price Variance = (SP – AP)AQ = (£3 – £3.10)15,000 = £0.10 × 15,000 = £1,500 (A) Material Usage Variance = (SQ – AQ)SP = [(3 × 5,200) – 15,000]£3 = 600 × £3 = £1,800 (F) Labour AC = 20,000 × £7 = £140,000 SC = 2 × £6 × 5,200 = £62,400 Total Labour Cost Variance = (SC – AC) = £62,400 – £140,000 = £77,600 (A) Labour Rate Variance = (SR – AR)AH = (£6 – £7)20,000 = 20,000 × £1 = £20,000 (A) Labour Efficiency Variance = (SH – AH)SR = (10,400 – 20,000) £6 = £57,600 (A) Variable Overheads AC = £5,000 SC = 2 × £1 × 5,200 = £10,400 Total Overhead Cost Variance = (SC – AC) = £10,400 – £5,000 = £5,400 (F) Variable Overhead Expenditure Variance = (VOAR × AH) – AC = (£1 × 20,000) – £5,000 = £15,000 (F) Variable Overhead Efficiency Variance = (SH – AH)VOAR = (10,400 – 20,000)£1 = £9,600 (A) Fixed Overheads AC = £30,000 SC = 2 × £2 × 5,200 = £20,800 BH = 2 × 4,500 = 9,000 hrs SH = 2 × 5,200 = 10,400 hrs AH = 20,000 hrs ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 53 SOLUTIONS Fixed Overhead Cost Variance Fixed Overhead Expenditure Variance = SC – AC = £20,800 – £30,000 = £9,200 (A) = (FOAR × BH) – AC = (£2 × 9,000) – £30,000 = £12,000 (A) Fixed Overhead Volume Variance = SC – (FOAR × BH) = £20,800 – (£2 × 9,000) = £2,800 (F) Fixed Overhead Efficiency Variance = FOAR/(SH – AH) = £2(10,400 – 20,000) = £19,200 (A) Fixed Overhead Capacity Variance = FOAR/(AH – BH) = £2(20,000 – 9,000) = £22,000 (A) 54 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Answer 8 (a) Variable Overheads VOAR = BO/BH = £8,000/5,000 = £1.60 SC = SH × VOAR = 5,200 × £1.60 = £8,320 Total Overhead Cost Variance = SC – AC = £8,320 – £7,000 = £1,320 (F) Variable Overhead Expenditure Variance = (VOAR/SR × AH) – AC = (£1.6 × 5,600) – £7,000 = £1,960 (F) Variable Overhead Efficiency Variance = VOAR/SR(SH–AH) = £1.6 (5,200 – 5,600) = £640 (A) Fixed Overheads FOAR =BO/BH = £5,000/5,000 = £1 SC = SH × FOAR = 5,200 × £1 = £5,200 Fixed Overhead Cost Variance = SC – AC = £5,200 – £5,600 = £400 (A) Fixed Overhead Expenditure Variance = (FOAR/SR × BH) – AC = (£1 × 5,000) – £5,600 = £600 (A) Fixed Overhead Volume Variance = SC – (FOAR/SR × BH) = £5,200 – (£1 × 5,000) = £200 (F) Fixed Overhead Efficiency Variance = FOAR/SR(SH – AH) = £1(5,200 – 5,600) = £400 (A) Fixed Overhead Capacity Variance = FOAR/SR(AH – BH) = £1(5,600 – 5,000) = £600 (A) (b) Variable Overheads VOAR = BO/BH = £20,000/5,000 = £4 SC = SH × VOAR = 4,500 × £4 = £18,000 Total Overhead Cost Variance = SC – AC = £18,000 – £22,000 = £4,000 (A) Variable Overhead Expenditure Variance = (VOAR/SR × AH) – AC = (£4 × 4,000) – £22,000 = £6,000 (A) Variable Overhead Efficiency Variance = VOAR/SR(SH–AH) = £4(4,500 – 4,000) = £2,000 (F) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 55 SOLUTIONS Fixed Overheads FOAR =BO/BH = £18,000/5,000 = £3.60 SC = SH × FOAR = 4,500 × £3.60 = £16,200 Fixed Overhead Cost Variance = SC – AC = £16,200 – £16,000 = £200 (F) Fixed Overhead Expenditure Variance = (FOAR/SR × BH) – AC = (£3.60 × 5,000) – £16,000 = £2,000 (F) Fixed Overhead Volume Variance = SC – (FOAR/SR × BH) = £16,200 – (£3.60 × 5,000) = £1,800 (A) Fixed Overhead Efficiency Variance = FOAR/SR(SH – AH) = £3.60(4,500 – 4,000) = £1,800 (F) Fixed Overhead Capacity Variance = FOAR/SR(AH – BH) = £3.60(4,000 – 5,000) = £3,600 (F) 56 ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) SOLUTIONS Answer 9 (a) Budgeted Revenue = £12 × 5,000 = £60,000 Actual Revenue = £13 × 4,500 = £58,500 Total Sales Revenue Variance = AR – BR = £58,500 – £60,000 = £1,500 (A) Sales Price Variance = (AP – BP)AQ = (£13 – £12) × 4,500 = £4,500 (F) Sales Volume Variance = (AQ – BQ)BP = (4,500 – 5,000) × £12 = £6,000 (A) (b) Budgeted Revenue = £20 × 10,000 = £200,000 Actual Revenue = £18 × 9,000 = £162,000 Total Sales Revenue Variance = AR – BR = £162,000 – £200,000 = £38,000 (A) Sales Price Variance = (AP – BP)AQ = (£18 – £20) × 9,000 = £18,000 (A) Sales Volume Variance = (AQ – BQ)BP = (9,000 – 10,000) × £20 = £20,000 (A) (c) Budgeted Revenue = £30 × 12,500 = £375,000 Actual Revenue = £35 × 15,000 = £525,000 Total Sales Revenue Variance = AR – BR = £525,000 – £375,000 = £150,000 (F) Sales Price Variance = (AP – BP)AQ = (£35 – £30) × 15,000 = £75,000 (F) Sales Volume Variance = (AQ – BQ)BP = (15,000 – 12,500) × £30 = £75,000 (F) (d) Budgeted Revenue = £6 × 1,000 = £6,000 Actual Revenue = £5 × 1,500 = £7,500 Total Sales Revenue Variance = AR – BR = £7,500 – £6,000 = £1,500 (F) Sales Price Variance = (AP – BP)AQ = (£5 – £6) × 1,500 = £1,500 (A) Sales Volume Variance = (AQ – BQ)BP = (1,500 – 1,000) × £6 = £3,000 (F) ACCOUNTING AND FINANCE – VARIANCE ANALYSIS (AH) 57