1682 IEEE Transactions on Power Delivery, Vol. 6, No. 4, October 1991 COMPACT RIGHT-OF-WAYSWITH MULTI-VOLTAGE TOWERS R.H. Brierley Member A.S. Morched Senior Member T.E. Grainger Non-member ONTARIO HYDRO Toronto, Ontario, Canada ABSTRACT: With increasing transmissior. requirements, and increasing public pressure to minimize new right-of-ways, utilities are increasing the circuit density to maximize the u s e of e x i s t i n g right-of-ways. Reduced c l e a r a n c e s between circuits, and the arrangement of various voltagelevel circuits on the same tower have resulted in a serious increase i n induction effects. Problems with voltage unbalance, residual load voltage, ferroresonance, breaker recovery voltage, ground switch duty, a n d line m a i n t e n a n c e have been identified, a n d solutions presented. 1.0 INTRODUCTION: In recent years, the public has become more sensitive to the proliferation of overhead transmission right-of-ways. There h a s been a n increasing pressure to provide t h e required transmission capability by increasing the voltage level of existing lines, and by adding more circuits onto existing right-of-ways. One solution to this problem, used by Ontario Hydro and others, is to restring existing lower voltage transmission or distribution circuits onto new towers with new high-voltage circuits. Several configurations have been s t u d i e d , with u p to t h r e e circuits, each of different voltage, on t h e same tower. Typical tower configurations are shown in Figure 1.The following i s a d e s c r i p t i o n of p r o b l e m s i d e n t i f i e d , alternatives considered, and solutions developed for such circuit arrangements. Although these problems are not new to power systems, t h e i r severity h a s increased, frequently beyond t h e tolerable level, a s compared to those experienced with conventional double circuit towers or multi-circuit right-of-ways. 2.0 POTENTIAL PROBLEMS: 2.1 Voltage Unbalance: contain various proportions of positive, negative, and zero sequence components. The positive sequence components a r e not likely to c a u s e a problem, with t h e possible exception of voltage level control. The zero sequence c o m p o n e n t s a r e e i t h e r blocked by d e l t a connected transformer primary windings, or shorted by transformer delta-connected secondary windings. I n t h e latter case, minor additional transformer heating could be expected due to the delta winding loading. The negative sequence components a r e passed through transformers, and can cause serious overheating problems for rotating loads, or local generation. Line unbalance effects have traditionally been solved by regularly spaced phase conductor transpositions. With s y s t e m e x p a n s i o n , t h e t r a n s p o s i t i o n cycles w e r e interrupted by new load or switching stations, until they no longer served t h e i r purpose. New lines were built w i t h o u t transpositions; a practice which eventually resulted i n a n increase i n voltage unbalance causing difficulty in motor starting, and increased motor heating. Steps were taken to rebalance the system voltage, on a n ad-hock basis, by modifying the phase arrangements of selected circuits. FIG. 1 Multi-Voltage Towers The close coupling of extra-high-voltage circuits, with lower voltage circuits, can result in significant voltages being induced on the lower voltage circuits and appearing at the load buses. Depending on the tower configuration, and on the phase arrangement, the induced voltages can 91 WM 096-8 PWRD A paper recommended and approved by the IEEE Transmission and Distribution Committee of the IEEE Power Engineering Society for presentation at the IEEE/PES 1991 Winter Meeting, New York, New York, February 3-7, 1991. Manuscript submitted August 30, 1990; made available for printing January 3 , 1991. I n t h e mid-seventies t h e O n t a r i o Hydro bulk power transmission system consisted, predominantly, of doublec i r c u i t 230 kV tower l i n e s , w i t h only a few 500 kV circuits. Now, a significant portion of a 500 kV overlay system exists. Some additions to this overlay a r e being built on existing right-of-ways. The existing lower voltage circuits a r e frequently retained, sometimes t o radially supply local loads a s shown in Figure 2. Under system contingencies, the 500 kV circuits a r e expected to carry very high c u r r e n t s . T h e negative sequence voltages induced i n t h e lower voktage circuits by t h e s e l a r g e currents can cause a n unacceptable voltage unbalance on local loads. 0885-8977/91$01.ooO1991 IEEE 1683 Figure 1A shows a multi-voltage tower configuration which, w i t h t h e 500 kV circuit c a r r y i n g load at i t s t h e r m a l limit of 2300 amps, produces 5.5970 negative sequence voltage at radially supplied loads. I n t h i s configuration, two phases of the higher voltage circuit are in close proximity to phases of t h e lower voltage circuit, while t h e third phase is remote. Both capacitively and inductively induced voltage u n b a l a n c e s c a n r e s u l t . Figure 1B shows a more acceptable tower configuration. Induced voltages on t h e lower voltage circuit can be mostly positive sequence for this configuration. However, i n a particular system arrangement, with t h e phasing selected so a s to minimize the electromagnetic field at the edge of the right-of-way, and with thermal limit loading of t h e 500 kV circuit, t h i s arrangement would produce a negative sequence voltage of approximately 1.25%. stationary, this residual voltage i s approximately t h e maximum allowable. However, values greater than 20% have been calculated for multi-voltage tower configurations. With voltages in this range, large motors will be tripped by undervoltage relays. Small motors, and household a p p l i a n c e s will l i k e l y stop, a n d will b e subjected to locked-rotor currents high enough to cause damage in a short time. DSB DSA b\ " , o_sL I I BUCHANAN TS ALLANBURG TS ST ' THOMAS TS . . 1 i ," 8 i v 500kV Y -2000 y15kV7 -1000 r15lrV 2( 0 1000 POWER FLOW- MW. A A A FIG. 3 Voltage Unbalance Variation with 500kV Power Flow DS A DSB DS C FIG. 2 Bulk Transmissionand Distribution Circuits on a Combined Right-of-way The tower arrangement shown i n Figure lC, used with t h e system of Figure 2, produces a variation i n load negative sequence voltage unbalance with power transfer in the 500 kV circuit a s shown in Figure 3. Through most of the normal operating range, the unbalance is below the acceptable NEMA Standard MG1-12.45a limit of 1.0%. However, a system contingency resulting i n increased power flow i n the 500 kV circuit will result in potential damage to r o t a t i n g loads fed from t h e lower voltage circuits. Overheating, and difficulty with motor starting h a s been experienced with voltage unbalance a s low a s 2.%. 2.2 2.3 Ferroresonance: If a n u n l o a d e d t r a n s f o r m e r i s de-energized w i t h a transmission line of sufficient length, coupled to another t r a n s m i s s i o n l i n e , f e r r o r e s o n a n c e m a y occur [ 11. Essentially t h e nonlinear magnetizing impedance of the transformer oscillates with t h e line capacitances. With sufficient energy transmitted across t h e inter-circuit capacitance to supply the losses, these oscillations can be sustained. Ferroresonant oscillations normally 'lock in' at either 60 Hz or at a subharmonic. A fixed relationship exists b e t w e e n t h e f r e q u e n c y a n d t h e v o l t a g e of t h e ferroresonant oscillation. This relationship is due to the Residual Load Voltage: Step-down transformers supplying loads a r e frequently t a p p e d from a circuit without individual switching capability, for example the 115 kV DS's shown in Figure 4. De-energization of the circuit-transformer combination may not result in zero load voltage if the circuit is closely coupled with another circuit. The residual voltage can be considerable, and will likely be unbalanced a s shown in Figure 5. The effect is caused, almost exclusively, by the capacitive coupling between the circuits. Therefore the residual voltage is dependent on the length of the coupled section, and the size of the connected load. Residual voltage resulting from coupling on double circuit towers, with circuits of the same voltage, is of the order of 5%. Considering the normal range of motor locked rotor i m p e d a n c e s , a n d t h e poor h e a t d i s s i p a t i o n w h e n STATION A m STATION B DS DS 3tz FIG. 4 Multi-Voltage Right-of-way 1684 switching and fault conditions. Increasing or decreasing a n y p a r a m e t e r m a y r e s u l t i n t u n i n g or d e t u n i n g t h e s y s t e m . T h e s i t u a t i o n w i t h f e r r o r e s o n a n c e i s more c o m p l i c a t e d s i n c e t h e n o n l i n e a r b e h a v i o r of t h e transformer magnetizing reactance permits i t to t u n e itself to the applied frequency, or its subharmonics, over a wide r a n g e of s y s t e m conditions. This increases t h e likelihood for ferroresonance, and makes it difficult, if not impossible, to predict ferroresonant conditions from system parameters. Simulation of the system, in the time domain, appears a s t h e only reliable tool; but even this tool suffers from a number of short-comings. . . . . ................................... , -8.001....,....l 0 . 0 0 0.10 0.20 0 . 3 0 O.’tO . , . 0.50 0.60 0.70 0.80 0.90 Time ( in Sec.) x 1.00 16’ FIG. 5 Residual Load Voltage on De-energization need to drive the flux in t h e transformer core from one saturation point to t h a t of t h e opposite polarity. As the voltage decreases, t h e frequency of t h e ferromagnetic oscillation decreases. Conversely, if a switching surge were t o s t a r t t h e process at a high enough voltage, t h e o s c i l l a t i o n s could conceivably be m a i n t a i n e d a t a harmonic frequency and at a voltage well above normal. Close coupling to a h i g h e r voltage line increases t h e p o s s i b i l i t y of s u c h h i g h v o l t a g e h i g h f r e q u e n c y oscillations. A situation conducive to ferroresonance may be created inadvertently by a stuck breaker, where a transformer a n d a transmission line a r e i n adjacent positions i n a switch yard. Modern air blast a n d SF6 breakers a r e not mechanically ganged between poles. Consequently, the independent pole mechanisms can be expected to stick with a higher frequency than the three phases together. S u c h a s i n g l e p h a s e connection b e t w e e n a coupled transmission line a n d a transformer can result i n ferroresonz ice. T h e s i t u a t i o n m a y also r e s u l t from t h e omission of transformer high-voltage breakers as in the Dual Element Source Network (DESN) arrangement used by Ontario Hydro. I n t h i s a r r a n g e m e n t , two circuits, with two attached transformers, feed a load bus as shown in Figure 4. On occurrence of a fault, the faulted circuit-transformer combination i s disconnected, leaving t h e load continuously supplied. This system achieves high reliability by providing continuous voltage to t h e load during the clearing of line faults. However, the switching of t h e circuit-transformer combination without a load, combined with the close coupling of the switched circuit to a circuit of higher voltage, increases the probability of ferroresonance. Identifying resonant conditions in transmission systems is I] t straight forward due to the complexity of the interphase a n d inter-circuit capacitances a n d inductances involved, and their distributed nature. Linear resonant c o n d i t i o n s , as i n t h e c a s e of l i n e r e a c t o r s , c a n b e accurately identified by frequency scans under different Studies with the EMTP program are somewhat limited by t h e lack of information on t h e transformer s a t u r a t i o n characteristics a n d t h e accuracy of t h e t r a n s f o r m e r models. EMTP studies, with d a t a varied over a reasonable range, have almost invariably shown some possibility of ferroresonance if the line was coupled to one of higher voltage. The higher saturation kneepoint of the ’quiet’ transformers now being specified has, on occasion, appeared to aggravate t h e situation by increasing t h e voltage at which t h e ferroresonance c a n occur. T h e calculated oscillation has been at extremely high voltage i n some instances a s shown i n Figure 6. This type of oscillation creates a risk of transformer damage, a n d of breaker restrike. 2.4 Breaker Recovery Voltage: The duty on existing breakers may be increased by t h e close coupling of a circuit with higher voltage circuits in two ways: by increasing the trapped charge voltage, and by increasing t h e ferroresonant oscillation voltage if a transformer is attached to the circuit. The trapped charge voltage on a double circuit tower will have a crest of about 1.5 per unit of normal crest voltage. With close coupling to a higher voltage circuit, voltages u p t o 2.1 per unit have been calculated. F i g u r e 7 shows t h e r e s u l t s of s u c h calculations. The breaker stress is especially high when t h e coupled voltage i s not i n p h a s e with t h e s y s t e m voltage on the live side of the breaker. A maximum recovery voltage (1.76 x maximum voltage for equipment) i s given i n s t a n d a r d s [21 for AC highvoltage circuit breakers. This recovery voltage refers to the fast transient peak which, in the first few tenths of a millisecond, follows fault current interruption. Standards allow for a n increase in this breaker recovery voltage, by a factor of 1.17, for interruption of small currents. An e v e n h i g h e r w i t h s t a n d voltage i s applicable t o t h e longitudinal insulation with t h e breaker i n t h e open position, fully deionized. However a value is not given specifically for the very slow recovery voltages involved in switching closely coupled circuits. Provided the standard recovery voltage value, augmented by the low current allowance, (1.76 x 1.17 of maximum voltage for the equipment) is not exceeded, t h e breaker can be assumed adequate. Its operation may, however, be accompanied by an occasional restrike. 1685 ................. : (7.a) N . . . . . . ............... 1 ....................... 3 00 3.00 2.00 1.00 0.00 .......... .. -5.00: . . . . 0.00 I . . . . , . . . . ; . . . . I 0.10 0.20 0.30 0.00 0.110 0.10 Time ( in Sec.) - N0 6 0.30 0.116 Time ( in Sec.) x 10 -' 0.50 0.60 0.50 0.60 ..--, a. oo- I (6.b) 00- . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . c 2 . 9 0 p.u. N 0 r n: X 0.20 -lz x 0.00-- - 8 5c -1.00-.- ... v m 4 3 -2.00-. ... 8 3. r .......... -6.001.. 0.00 . . i 0.10 . . . . i n . . 0.20 . r n , . . . . 1 0.30 0.00 0.110 Time ( in Sec.) FIG. 6 230kV Transformer Ferroresonance (a) Terminal Voltage (b) Breaker Recovery Voltage 2.5 Ground Switch Duty: When a transmission circuit i s taken out of service for maintenance, i t is usually grounded at both ends using permanently installed ground switches. O n multiple circuit right-of-ways, t h e power flow in t h e live circuits induces currents in t h e grounded circuit. The second to l a s t ground switch to open may h a v e difficulty interrupting this circulating current. I n addition, t h e inter-circuit capacitance can induce charging current in the last ground switch to open, and can result i n a high recovery voltage across it. G r o u n d s w i t c h e s i n common u s e h a v e no r a t e d interrupting capability. However, over the years, i t has been obvious t h a t t h e s e switches h a v e successfully interrupted appreciable currents and withstood significant recovery voltages. The close coupling of HV circuits with EHV bulk transmission circuits on the same tower h a s created a condition where t h e circulating c u r r e n t a n d r e c o v e r y v o l t a g e c a p a b i l i t y of t h e conventional g r o u n d s w i t c h e s m a y be exceeded. Circulating c u r r e n t s i n excess of 300 a m p s rms, a n d ground switch recovery voltages in excess of 160 kV crest, on a 115 kV circuit have been calculated. 0.10 0.20 0.30 0.110 Time ( in Sec.)x lo-' FIG. 7 De-energizationof an Untapped Coupled Circuit (a) Line Side Voltage (b) Breaker Recovery Voltage 2.6 Working Grounds: I n addition to permanent grounds at station entrances, working grounds a r e usually applied i n t h e vicinity of maintenance work on transmission circuits to protect workers from operating errors and from induction effects. It i s generally expected t h a t negligible currents will flow in the working grounds since the induced currents on both sides are almost identical. Working grounds at a transposition location carry t h e difference of t h e induced currents i n t h e two adjacent sections, which a r e approximately 120 degrees out of phase. The result can be a ground current a t i m e s t h e normal circulating current. Similarly, high currents can be experienced at other discontinuities, such as locations w h e r e circuits join o r leave the right-of-way. These c u r r e n t s m a y be too high for t h e continuous c u r r e n t capability of the grounding equipment,and may cause too long arcs for the working grounds to be safely removed. I n some arrangements, t h e lower voltage circuits form major p a r t s of t h e bulk power transmission system. A maintenance outage to the EHV circuit can result in the loading of t h e low voltage circuits to t h e e x t e n t t h a t unacceptably high circulating currents can be induced in the closely coupled EHV circuit. POSSIBLE SOLUTIONS: 3.0 A complicating difficulty in finding proper solutions to the above problems is t h a t a solution t o one may aggravate another. The accepted solutions must aim at control of all problems, at minimum cost. Possible solutions to specific problems are given below. 3.1 Solutions for Voltage Unbalance Problems: 3.1.1 Transpositions: which will not appear at the load due t o delta connected transformer windings. 3.3.2 Secondary Side Load Switching: On detection of unacceptably high residual voltage, i t would be possible to open secondary feeder breakers t o protect the load. The major risk of such a n arrangement is t h a t i t leaves t h e unloaded transformer connected t o a circuit with high coupled voltages, a n d could lead to ferroresonance. 3.2.3 Primary Side Load Switching: By transposing the high voltage circuit, voltage unbalance i n t h e low voltage circuit from line coupling c a n be eliminated. This can be impractical with short lengths of coupling, and expensive in any situation. Somewhat less effective is transposition of the lower voltage circuit so a s to create three equal sections over the coupled range. This will result in the conversion of the voltage unbalance into zero sequence. Zero sequence voltage unbalance may not reach t h e load because of delta connected transformer windings. Transpositions can result in unexpectedly high currents in working grounds during maintenance. O n d e t e c t i o n of r e s i d u a l v o l t a g e , t h e s t e p - d o w n transformer and its attached load could be switched by a load switcher. The circuit will be subsequently r e energized without t h e transformer. I n t h e case of a s u c c e s s f u l r e - e n e r g i z a t i o n , t h e load will s u f f e r a somewhat prolonged outage until the load interruptor is closed by control. If the re-energization is not successful, t h e line b r e a k e r s m a y e n c o u n t e r t h e high recovery voltages associated with clearing a coupled, unloaded circuit. 3.1.2 3.3 Solutions for Ferroresonance Problems: 3.3.1 Damping Resistors: Tower Config-uration: Voltage u n b a l a n c e m a y be r e d u c e d by t o w e r configuration, and phase arrangements. The objective is to provide equal coupling of each phase of the low voltage circuit with the corresponding phase of the high voltage circuit. The coupling will t h e n cause predominantly positive sequence voltages. Close coupling of all phases of the low voltage circuit with a single high voltage phase will result in a predominantly zero sequence coupled voltage, which may be tolerable with some transformer configurations. Other tower o r phase arrangements can result in a strong negative sequence component, which will pass unmodified through transformers, and damage rotating loads. 3.1.3 Adding damping resistors, switched on t h e low voltage bus by a fast device, instigated by the same relaying used t o t r i p t h e HV circuit, m a y provide a solution t o t h e problem. The high speed is necessary to reduce the high voltage levels which may accompany the earlier stages of the ferroresonant oscillation. The fastest switching device, on closing, is believed to be a vacuum switch. Breakers have been used, with some delay being introduced in the line breaker opening s o t h a t t h e r e s i s t e r s will be i n service when the breakers clear. Damping resisters, in two independantly switched banks for reliability, with ratings up t o 400 kW per phase have been suggested. Voltage Balancing Devices: 3.3.2 Load Break Switches: T h e voltage of a m u l t i - p h a s e power s y s t e m m a y be balanced at a point by use of independent phase voltage control. This may consist of single phase transformer-type voltage regulators, a series of small single phase switched shunt capacitors, o r single phase static var compensators. Although these devices are standard system components, their use to balance rather than maintain a voltage level is less common. The logic to decide on t h e amount and p h a s e of t h e a d j u s t m e n t m u s t be based on t h e small differences of the bus voltages. Measurement accuracy is, therefore, a concern. In circumstances where the transformer is connected t o a coupled line through a disconnect switch, a n d ferroresonance is expected, i t may be economic to replace the disconnect with a load switcher which can successfully de-energize a ferroresonating transformer, a s well a s provide the isolation duty of a disconnect. Although the currents involved in ferroresonance do not approach fault currents, t h e recovery voltages may be high, a n d t h e capability of t h e load s w i t c h e r s h o u l d be carefully checked. 3.2 Solutions for Residual Load Voltage Problems: 3.3.3 3.2.1. Transpositions: As in the voltage unbalance problem, the residual voltage may be eliminated by complete transposition of the high volt,age circuits. Transposition of the low voltage circuit orily can convert the residual voltage to zero sequence, I Ground Switches: Ferroresonance h a s been stopped, on occasion, by t h e closing of ground switches. This solution has the handicap of being very slow. It will not suffice if t h e oscillating voltage is high enough to threaten equipment insulation. Further, the ground switch must eventually be removed, and i t is quite possible t h a t the associated transient will once more i n i t i a t e t h e oscillation. Separation of t h e 1687 transformer and line prior to opening the ground switch could create a need for special relaying or communications. 3.3.4 Cross Tripping of Companion Circuit: For a stuck breaker condition leading to ferroresonance, a scheme to cross trip the live circuit is under consideration. Stuck breaker conditions occur very infrequently. If the system is designed to tolerate a double circuit fault, the cross tripping will only marginally increase the frequency of the simultaneous loss of two circuits. 3.4 3.4.1 Solutions for Breaker Recovery Voltage Problems: Selection of Optimum Phase Arrangement: By selecting t h e p h a s i n g of t h e low voltage circuit, relative to t h e high voltage circuit, so t h a t the induced voltage i s i n p h a s e with t h e low voltage system, t h e voltage across t h e opening b r e a k e r will be reduced. However, a phase shift between t h e voltage levels, or other requirements, such a s a need to minimize t h e electromagnetic field strength at the edge of the right-ofway, may preclude this approach. 3.4.2 Application of Surge Arresters: I t may be possible to select metal oxide arresters, with a n adequate continuous operating voltage, and with a low enough protective level that the breaker recovery voltage can be limited. The arrester would be installed, on t h e line side of t h e breaker, to discharge a portion of t h e t r a p p e d charge voltage d u r i n g line de-energization. However, in selecting such a n arrester, margins are much tighter than normal. Consideration must be given to the temporary overvoltages that may occur on healthy phases during the fault. Also, following line de-energization, a n attached rotating load may maintain both the fault and the system voltage, increasing the arrester thermal duty. 3.4.3 Replacement of Breakers: If studies indicate t h a t , in spite of stratagems such as p h a s e a r r a n g e m e n t selection, t h e s t a n d a r d recovery voltage value for breakers is exceeded, or if a n occasional restrike is not tolerable, the breaker must be assumed inadequate. It must then be tested for capacitor switching d u t y at appropriately high voltages, or replaced by a breaker of adequate rating. Consideration should be given to the use of SF6 breakers, which appear to inherently have a capacitive switching ability much above t h a t of other types of breakers. 3.5 Solutions for Ground Switch Duty Problems: 3.5.1 Determination of Capability of Conventional Ground Switches: The i n t e r r u p t i n g capability of conventional ground switches is usually expressed a s a current limit, and a s a length of circuit corresponding to conditions at which successful operation h a s been demonstrated. The increasingly close coupling, particularly with circuits of higher voltage rating, h a s made this experience-based data obsolete. A method outlined i n a 1950 NEE paper by F.E. Andrews et a1 [3] permits the calculation of arc reach as a function of current and open circuit voltage. If such arcs are limited to approximately one half of the available clearance, a basis for evaluation of existing equipment can be established. 3.5.2 Development of Higher Capability Ground Switches: A ground switch with suitable interrupting capability has been developed for use by Ontario Hydro [4], consisting of a n SF6 i n t e r r u p t o r , w i t h a disconnect s w i t c h t y p e isolator. Other desirable features have been included, such a s remote operation capability and a visible by-pass of the interruptor in the closed position. Ground switches with proven interrupting capability have also been developed for gas insulated substations [51. 3.6 Solution for Workinv Ground Problems: The compact right-of-ways presently being planned show numerous locations and conditions where conventional w o r k i n g g r o u n d s c a n n o t b e u s e d . I n s t a l l a t i o n of p e r m a n e n t ground switches, with or without special interruption capability, in these locations, is the present practice, b u t m a y n o t be a n economic solution. It i s desirable t h a t a portable ground switch be developed, capable of easy application in the field. 4.0 CONCLUSIONS: The addition of more circuits onto existing right-of-ways, and particularly the use of multi-voltage towers, is adding a new dimension to problems resulting from electromagnetic and electrostatic induction. Although none of the problems are new, and although solutions are usually possible, the costs can be significant and must be anticipated in the early planning stages. Problems with voltage unbalance, residual voltage, ferroresonance, breaker recovery voltage, ground switch duty, and line m a i n t e n a n c e have been identified, a n d solutions presented. Although implemented solutions depend on the s y s t e m configuration, t h e following conclusions a r e generally valid: 1. The use of transpositions to minimize induction effects i s expensive, a n d r e s u l t s i n severe working ground problems. 2 . T h e n u m b e r of locations w h e r e coupled c i r c u i t s converge o r diverge should be minimized. 3. Careful selection of circuit p h a s i n g i s required to minimize negative sequence unbalance, to reduce breaker recovery voltage, and to reduce ground switch duty. 4.Use of independent phase switched capacitors, or static var compensators, may be required to compensate load 1688 voltage unbalance i n systems where optimum phase arrangement is not enough. 5. Breakers with limited recovery voltage capability may have to be protected with arresters, or be replaced with SF6 breakers of higher capability. 6. Special m e a s u r e s , s u c h a s d a m p i n g r e s i s t o r s , or individual transformer switching capability, m a y be r e q u i r e d t o r e d u c e i n c i d e n t s of t r a n s f o r m e r ferroresonance. 7. Special high-voltage switching devices may be required to disconnect loads u n d e r t h e condition of s u s t a i n e d under-voltage. REFERENCES: [ l ] E . J . D o l a n , D.A. G i l l i e s , E . W . K i m b a r k Ferroresonance i n a Transformer with a n EHV Line IEEE Transactions (PAS-91) pp. 1273, May/June 1972 [21 ANSI Standard C37.06 - 1979 Preferred Ratings and Related Required Capabilities for AC High-Voltage Circuit Breakers [31 F . E . A n d r e w s , L . R . J a n e s , M.A. A n d e r s o n Interrupting Ability of Horn-Gap Switches AIEE Transactions 1950, pp. 1016 [4] G. Handfield, L. L a m - I n t e r r u p t e r Type Ground Switch for 550 kV Parallel Transmission Lines CEA Spring Meeting, 1989 [5] R. Kugler, H.M. Luehrmann, F. Veuhoff - Switching T e s t s on GroundinP Switches for G a s I n s u l a t e d Substations IEEE Transactions (PAS-103) pp. 3569, Dec. 1984 BIOGRAPHIES: Russell H. Brierley (M'73) was born i n 1930 in Hamilton, Ontario. H e received his electrical engineering degree from Queens University in Kingston, Ont., in 1953. He worked for six years for CGE in Peterborough, Ont., in the design of Hydraulic Generators; a n d t h r e e years for Ontario Hydro's Research Division, field testing electrical equipment. Since 1963 he has worked in various positions in Ontario Hydro, System Planning Division. He h a s been involved i n s y s t e m s t u d i e s u s i n g t h e Electromagnetic Transients Program, since 1969. Mr. Brierley i s a Professional Engineer in the Province of O n t a r i o . H e i s a m e m b e r of t h e C a n a d i a n N a t i o n a l Committee of IEC TC28 on Insulation Coordination, and a co-author of CSA Publication on t h e Principles a n d Practice of Insulation Coordination - C308. Atef S.Morched (M'77-SM790)was born i n Cairo, Egypt i n 1942. He o b t a i n e d a B.Sc. i n E l e c t r i c a l Engineering from Cairo University in 1964, a Ph.D. a n d a D.Sc. from t h e N o r w e g i a n I n s t i t u t e of Technology i n Trondheim i n 1970 and 1972. He worked for t h e E g y p t i a n Electricity Corporation between 1964-1967 and 1972-1974. H e was a Research Associate w i t h t h e U n i v e r s i t y of Toronto during 1974-1975. Since 1975 h e h a s been with O n t a r i o Hydro; initially with t h e S t a t i o n s Design Department, and subsequently with the System Planning Division where he currently holds the position of Head of the Electromagnetic Transients Section. Dr. Morched is a Professional Engineer in the Province of Ontario. He has authored and co-authored a number of technical papers. His paper on Network Equivalents for Electromagnetic Transient Studies won a 1985 PES Prize Paper Award . Tom E . Grainger was born in North Bay, Ontario in 1958. I n 1980 he received a diploma i n E l e c t r i c a l Engineering Technology from t h e Ryerson Polytechnical Institute, in Toronto, Ont. He i s presently completing t h e r e q u i r e m e n t s for membership i n t h e Association of Professional Engineers of Ontario. I n 1980 Mr. Grainger joined the System Planning Division of O n t a r i o H y d r o , a n d i s c u r r e n t l y w o r k i n g i n t h e Electromagnetic Transients Section. 1689 DISCUSSION GEORGE GELA, HVTRC, LENOX, MA: The paper provides a broad overview o f many questions t h a t could a r i s e when one t r i e s t o minimize t h e r i g h t - o f - w a y through t h e use o f compact l i n e designs, o r when one t r i e s t o maximize t h e u t i l i z a t i o n o f t h e r i g h t - o f - w a y through t h e use o f m u l t i - v o l tage towers. The paper concentrates mainly on t h e o p e r a t i o n a l c h a r a c t e r i s t i c s o f t h e o p t i m i z e d t r a n s m i s s i o n c o r r i d o r s , and presents as conclusions some f a i r l y generic statements as t o what might be expected. The d i s c u s s e r would f i r s t l i k e t o e x p l o r e t h e poss i b i l i t y o f d e r i v i n g some more d e f i n i t e statements o r g u i d e l i n e s . For example, w i t h t h e "more crowded" c o r r i d o r s and towers (i.e., smaller a i r distances, o r a m i x t u r e o f voltage l e v e l s ) , would t h e outage r a t e be higher, and could t h e t r a d i t i o n a l l y low outage r a t e s be recovered a t a reasonable c o s t o f s w i t c h i n g and p r o t e c t i v e equipment? Would t h e overvoltage charact e r i s t i c s be a l t e r e d t o t h e p o i n t where t h e v a s t amount o f experience accumulated t o date would need t o be r e v i s e d ? With t h i s l a s t question, t h e d i s c u s s e r would l i k e t o address n o t so much t h e general area o f electromagnetic t r a n s i e n t s , b u t r a t h e r more s p e c i f i c a l l y t h e t o p i c o f l i v e - l i n e maintenance. The authors address t h e question o f working grounds, i . e . , o f grounding temporarily the de-energized l i n e f o r t h e purpose o f p r o t e c t i n g workers from e l e c t r o c u t i o n due t o a c c i d e n t a l 1 i n e r e - e n e r g i z a t i o n [ A ] . However, de-energizing a l i n e t o perform maintenance r e p r e s e n t s a l o s s o f revenue, which may be a s i g n i f i c a n t consideration. Performing t h e work w i t h t h e l i n e energized, i.e., l i v e - l i n e maintenance, o f course i s an o p t i o n which avoids t h e problem, b u t t h e s a f e t y o f t h e worker must take p r i o r i t y . Worker's s a f e t y i s assumed b a s i c a l l y by r e t a i n i n g proper a i r distances t o grounded and energized e l e c t r o d e s [ B ] . These d i s tances must i n c l u d e several l a y e r s o f " s a f e t y f a c t o r s " o r "adders" t o account f o r v a r i o u s working and engonomic issues, and t o b r i n g t h e p r o b a b i l i t y o f a i r breakdown t o very, very low values. I n o t h e r words, t h e distance needed t o perform l i v e - 1 i n e maintenance s a f e l y i s always considerably greater than t h a t c o r responding t o t h e 50% breakdown, f o r a given t r a n s i e n t overvoltage l e v e l . For compact l i n e s and m u l t i voltage towers, t h e a v a i l a b l e physical distances may not be s u f f i c i e n t due t o compaction, t o perform l i v e 1 i n e maintenance, unless a d d i t i o n a l remedial steps are taken. The r e m e d i a l s t e p s may range f r o m dee n e r g i z i n g t h e l i n e a l t o g e t h e r , through t e m p o r a r i l y c o n t r o l l i n g t h e overvoltages l o c a l l y a t t h e w o r k s i t e o r p l a c i n g t h e worker on t h e l i n e using, say, h e l i c o p t e r s , t o developing new work methods i n c l u d i n g automat i o n . The thorough understanding o f overvoltages and o f t h e i m p l i c a t i o n s o f reduced distances i n optimized c o r r i d o r s , i s e s s e n t i a l i n making decisions r e l a t e d t o l i n e maintenance. Above a l l , t h e broad q u e s t i o n o f l i v e - l i n e maintenance should be included e a r l y i n t h e d i s c u s s i o n o f compact r i g h t - o f - w a y s , as t h e authors have attempted i n p a r t , so t h a t t h e apparent advantages are n o t b l u n t e d by t h e need t o de-energize t h e l i n e due t o i n s u f f i c i e n t distances even f o r such operations as replacement o f bundle spacers o r i n s t a l l a t i o n o f marker b a l l s . The authors' comments i n t h i s area a r e appreciated. REFERENCES A. ANSI/IEEE Std 1048-1990, " I E E E Guide f o r Protect i v e Grounding o f Power ines" B. ANSI/IEEE S t d 516-1987, " I E E E Guide f o r Maintenance Methods on Energ zed Power-Li nes" . . Manuscript received February 20, 1991. R.H. BRIERLEY, A.S. MORCHED, T.E. GRAINGER The Authors would like to thank Dr. Gela for his interest in t h i s paper, a n d for pointing out t h e similarities of problems associated with t h e topic of t h i s paper, and Compact Line Design. The increased coupling effects of the multi-voltage tower h a v e r e s u l t e d i n w h a t m i g h t be called 'bothersome' overvoltages. Although a concern for terminal equipment, they do not appear to threaten t h e line insulation itself. Consequently, higher outage rates are not expected if the terminal effects have been properly considered. These terminal effects do represent a modification in 'experience based' knowledge which will have to be assimilated. Live-line maintenance is indeed a n important consideration in the design of multi-voltage towers. In the p a r t i c u l a r t o w e r d e s i g n s of F i g u r e 1, c l e a r a n c e s commensurate w i t h t h e maximum s w i t c h i n g s u r g e a s s o c i a t e d w i t h n o m i n a l 2 3 0 kV c i r c u i t s a n d t h e 'envelope' required for workers and equipment have been maintained. The maximum switching surge results from re-energizing a line with a trapped charge, and since the trapped charge voltage may be increased by t h e multivoltage tower arrangement, so t h e maximum switching surge may be increased. Several of the circuits described are actually insulated for 230 kV, while operating at 115 kV. This was done because of t h e expected high o u t a g e r a t e of 115 kV insulator s t r i n g s on a high 500 kV t o w e r , a n d b e c a u s e of a n anticipated need to reconnect t h e circuits for 230 kV operation in t h e f u t u r e . As a consequence, live-line maintenance on these circuits, using 230 kV tools a n d clearances, should pose no problem. The circuits operating a t 230 kV have been checked to ascertain that switching s u r g e s h i g h e r t h a n t h e a s s u m e d maximum a r e n o t possible. Such switching s u r g e s a r e unlikely in t h e discussed a r r a n g e m e n t , because t h e presence of the DESN transformers ensures t h a t the trapped charge will be dissipated prior to reclosure. I t may be necessary, in other locations, to restrict switching surges using line mounted arrestors, r a t h e r t h a n increase standardized safety clearances. Manuscript received June 30, 1991.