Numericals Topic Formula RoI ARR PV Benefit-Cost Analysis; Project Selection criteria FV (1 r ) N N NPV i 0 CFi (1 r ) i IRR 𝐵𝐶𝑅 = Time Management I 𝑃𝑉 𝑜𝑓 𝐵𝑒𝑛𝑒𝑓𝑖𝑡𝑠 𝑃𝑉 𝑜𝑓 𝐶𝑜𝑠𝑡𝑠 Total Float = LS – ES = LF – EF 𝜇 = (𝑂 + 4𝑀 + 𝑃)/6 σ = (P – O)/6 Earned Value Management Channels of communication Risk Management CV = EV – AC SV = EV – PV CPI = EV/AC SPI = EV/PV 𝐵𝐴𝐶 − 𝐸𝑉 𝐸𝐴𝐶 = 𝐴𝐶 + 𝐶𝑃𝐼𝑒𝑠𝑡 VAC = BAC – EAC (𝐵𝐴𝐶 − 𝐸𝑉) 𝑇𝐶𝑃𝐼 = (𝑇𝑎𝑟𝑔𝑒𝑡 − 𝐴𝐶) 𝐶 =𝑛∗ (𝑛 + 1) 2 𝐸𝑀𝑉 = ∑(𝑃 ∗ 𝐼)𝑖 Description RoI = Return on Investment ARR = Average Rate of Return I = Initial Investment PV = Present Value FV = Future Value R = Rate of discounting N = Number of years NPV = Net Present Value CFi = Cash flow for year I r = Rate of discounting N = Number of years IRR = Internal rate of return; Rate of discount at which the Present Value of benefits = Present Value of costs; i.e. In the NPV formula; treat “r” as a variable and equate NPV to zero BCR = Benefit/Cost Ratio LS = Latest Start Time; LF = Latest Finish Time ES = Earliest Start Time; EF = Earliest Finish Time μ = Expected time σ = Standard deviation O = Optimistic Time estimate P = Pessimistic Time estimate M = Most likely Time estimate CV = Cost Variance; SV = Schedule Variance CPI = Cost Performance Index; SPI = Schedule Performance Index EV = Earned Value; PV = Planned Value; AC = Actual Cost EAC = Estimate at Complete; BAC = Budget at Complete ETC = Estimate to Complete CPIest = Estimated CPI for the remaining period VAC = Variance at Completion TCPI = To-complete cost performance index ; to manage overall spent to Target C = Number of channels of communication N = Number of team members EMV = Expected Monetary Value P = Probability of event i I = Impact of event i Definitions/Concepts Term Project Program Portfolios Stakeholder Payback period Opportunity cost Configuration management systems Product scope Project scope Control account Work package Rolling wave planning Leads and Lags Critical path Crashing Fast tracking Resource optimization Depreciation Quality Grade Cost of quality RACI Definition Temporary endeavor undertaken to create a unique product, service or result A group of projects managed in a coordinated way to obtain benefits or control not available from managing them individually A collection of projects, programs, sub-portfolios and operations managed as a group to achieve strategic objectives An individual, group or organization who may affect, be affected by or perceive itself to be affected by a decision, activity or outcome of a project Number of time periods it takes to recover the initial investment The value of the opportunity that was available but had to be given up in order to pursue another opportunity A set of procedures used to apply technical and administrative direction and surveillance to identify and document the functional and physical characteristics of a product, service or a result component Features and functions that characterize a product The work that must be done to deliver a product, service or result with the specified features and functions The level of work at which the management wishes to exercise control A unit of work or deliverable at the leaf node of a work package An iterative planning technique in which the work to be accomplished in the near term is planned in greater detail while the work to be done in the future is planned at a higher level A successor activity is said to have a lead when it can start in advance of the predecessor; it is said to have a lag when it has to wait for a certain period after the predecessor Longest path from start to finish in a project network diagram; All activities on the critical path have zero float Achieving reduction in time taken by increasing the cost Achieving reduction in time taken by increasing the work being done in parallel Applying optimization techniques to achieve the desired level of utilization of resources An accounting practice or entry that takes into consideration the reduction in the value of an asset over time The degree to which a set of inherent characteristics fulfills requirements A category assigned to deliverables having the same functional use but different technical characteristics All the costs incurred over the life of a product to ensure that it conforms to the requirements A common type of responsibility assignment matrix that uses responsible, accountable, consult and inform statuses to define the involvement of stakeholders Risk Contract Cost reimbursable contract Fixed price contract An uncertain event or condition that, if it occurs can have a positive or negative effect on a project’s objectives A mutually binding agreement that obligates the seller to provide the specified products or services or results and the buyer to provide the monetary or other valuable consideration A form of contract that requires the buyer to pay the seller for all the costs incurred, plus a fee representing the seller’s profit A form of contract that sets the fee to be paid for a defined scope of work regardless of the cost of effort to deliver it Mind-Maps Knowledge areas of project management Scope Time HR Integration Quality Cost Risk Procure ment Stakeho lder Communic ation Process groups of project management Initiating Processes Planning Processes Controlling Processes Executing Processes Closing Processes Influence of organizational structure on projects Organisation Type Project Characteristics Matrix Functional Weak Matrix Balanced Matrix Strong Matrix Projectized Little or Project Manager's Authority None Percent of Performing Organization's Personnel Assigned Full Time to Project Work Project Manager's Role Common Titles for Project Manager's Role Project Management Administrative staff Virtually None Part-time Project Coordinat or / Project Leader Limited Moderate to Low or Moderate Hogh High to almost total 0-25% 15-60% 50-95% 85-100% Part-time Full-time Full-time Full-time Project Manager / Program Manager Project Manager / Program Manager Full-time Full-time Project Coordinator Project Manager / Project / Project officer Leader Part-time Part-time Part-time Change management steps: • Determine that a change is “necessary” or has occurred • Evaluate the impact of the change • Come up with alternatives • Discuss internally • Discuss externally Group creativity techniques: • Brainstorming • Nominal group technique • Idea/Mind mapping • Affinity diagram • Multi-criteria decision analysis Group decision making techniques: • Unanimity • Majority • Plurality • Dictatorship Time management concepts: • Relationship types o Finish to Start o Start to Start o Finish to Finish o Start to Finish • Dependency types o Internal vs. External o Mandatory vs. Discretionary • Network diagramming techniques o PDM or AON: Activities on the node; arrows indicate relationships o ADM or AOA: Activities on arrows; direction indicates relationships • Types of estimation o Top-down Expert Analogous Parametric o Bottom up or detailed • Critical chain method: Including logical and resource dependencies simultaneously to produce a critical path • • • Properties of normal distributions o 68% observations between 1 std deviation of the mean o 95% observations between 2 std deviation of the mean o 99.73% observations between 3 std deviation of the mean o 99.999966% observations between 6 std deviation of the mean Float or Slack: The amount of time that an activity can be delayed without delaying the project Schedule compression techniques o Crashing: Increasing cost to save time o Fast tracking: Performing activities in parallel to save time Quality management concepts: • Marginal quality (optimal quality) is reached when the cost of achieving additional quality is matched by the additional revenue it fetches • Philosophies for quality management: o Total quality management (TQM): Integrated management philosophy o Kaizen: Small improvements to make things better o Deming cycle: PDCA (Plan-Do-Check-Act) o Kanban: A pull based system for management of inventory that operates on JIT (just-intime) principles • Quality Assurance o Is ongoing during execution o Focuses on the process o Audits, reviews, etc. • Quality Control o Inspects specific results or deliverables o Focuses on the product or results o Testing, Inspection, etc. • Cost of quality = Cost of conformance + Cost of non-conformance o Cost of conformance = Prevention costs (Training, Documentation, etc.) + Appraisal costs (Testing, etc.) o Cost of non-conformance = Internal failure costs (Rework, scrap, etc.) + External failure costs (Warranty, recall, etc.) • 7-basic quality tools o Control charts: Observe variation in a process to make sure it is in control o Cause and effect (or Ishikawa or Fish-bone) diagram: For root cause analysis o Flowcharting: Visualizing the flow in a process o Histogram: To assess frequency for a certain category o Pareto diagram: Based on 80-20 rule; used for prioritization o Scatter diagram: To assess the correlation between two variables o Checksheets: To organize data for inspection or presentation HR management concepts: • Stages of team formation: Forming, Storming, Norming, Performing and Adjourning • Sources of conflict: Resources, Scheduling, Personality • Conflict resolution techniques: o Withdraw/Avoid o Smooth/Accommodate o Compromise/Reconcile o Force/Direct o Collaborate/Problem solve • Forms of authority for the manager: Formal, Expert, Reward, Penalty, Referent • Maslow’s hierarchy: Physiological, Safety, Social, Esteem, Self Actualization • Herzberg’s theory: Hygiene factors, Motivating agents • Mcgregor’s theory: X theory (people want to avoid work) and Y theory (people are self motivated) • Leadership styles: Autocratic/Authoritarian, Participative/Democratic, Delegative/Laissez Faire • McKinsey’s 7-S: Hard elements – Strategy, Structure, Systems; Soft elements: Shared values, Skills, Style, Staff Risk management concepts: • Contingency reserves are for known unknowns, management reserves for unknown unknowns • Strategies for responding to pure risks or threats: o Avoid o Transfer o Mitigate o Accept • Strategies for responding to positive risks or opportunities: o Exploit o Share o Enhance o Accept Procurement management concepts: • Contract types: o Cost reimbursable: Buyer pays all costs plus a profit Cost risk lies with the buyer Used when the scope and duration is uncertain o Time and Material: Buyer pays at a certain rate Seller doesn’t have to worry about scope – buyer is in control Used for small assignments or to get started or staff augmentation o Fixed price: Buyer pays a fixed fee Cost risk lies with the seller Used when the scope is well known and stable Data flows in project management Project Initiator Project SoW Business Case Agreeme Initiatin nts g Enterpri se or Organizational Process Assets Enterprise Environmental Procurement Factors documents Plannin g Project Charter Stakeholder register Stakeholder management strategy o Custom er Require ments Project Docume Teamin g Agreem ents Final Product , Service Seller or Propo Result sals Executi ng Resour ce Calend Management Project ars Plan Make or buy decisions Approved Source selection change requests criteria Quality control measurements Monitoring and Controlling Process Group Performance reports Sellers Contr act Awar d Closing Process Accepted Deliverables Procurement documentation Deliverables Change requests Work performance information Selected Sellers