imacVII_infrastructure

advertisement
Status of Infrastructure
Emre Kazancı
On Behalf of TARLA Team
IMAC VII Meeting
Outline
• Completed Construction Works
• New constructions
• Modifications
• Experimental Stations and Clean Room
• Electricity
• Ionized Air Conditioning
• Radiation Shielding Doors
• Compressed Air
• Water Cooling System
• Segmentation of Laboratory Rooms
• Conclusion
07-08/09/2015
IMAC VII Meeting
2
Construction Works
New Construction
•
•
•
•
•
A,B Administrative Building
C Accelerator Building
D Water Cooling Building
E Security
F Generator and main
transformer room
• G UPS room
• H Mechanical Workshop
• I Contamination Storage
07-08/09/2015
IMAC VII Meeting
3
New Constructions
• Water cooling building and piping tunnel
Houses pumps, tanks, circulators, heat exchangers etc.
• Mechanical workshop
Production and repair of mechanical systems up to a certain level
• Contaminated material storage
To safely store activated equipment (solid)
• Security office
Controlled, single entrance to facility site for human and machine safety
• Waste-water storage (planned, in tender progress)
• To safely store activated water produced by water cooling system
07-08/09/2015
IMAC VII Meeting
4
Water Cooling Building
The building is dedicated for water
cooling plant
Connected to the laboratory by a 2x2m
wide tunnel beneath road level
Total height 5.5 m (2m below road level)
07-08/09/2015
IMAC VII Meeting
5
Mechanical Workshop
A two story workshop with gross
area of 200 m2 for manufacturing
and maintenance
•
•
•
•
•
•
•
Crane 5ton
Driller
Cold Saw
Compressor
Band Saw
Guillotine shear
Hand Tools
•
•
•
•
•
•
•
•
CNC milling machine
CNC turning machine
Turning machine
Milling machine
3 Axis goniometer
Hydraulic Press
Pipe bending machine
TIG welding machine
07-08/09/2015
IMAC VII Meeting
6
Contaminated Material Storage, Security Office
07-08/09/2015
IMAC VII Meeting
7
Waste-water storage
• Automatic activated water draining and tank to tank transfer via dedicated piping
and pump
• Human contact to water only at clearance volume of piping tunnels between caves
• Designed, in tender progress
• Will be located next to water cooling building, buried underground
• Trapped access without radiation shielding door from water cooling building
• Total volume of circulating water in radiation area is 1.8 tones. (beamline and three
dumps)
• 3x2 tones all metal modular SS tanks plus 2 tones dispose chamber
07-08/09/2015
IMAC VII Meeting
8
Modifications
Switched position of CB2 and one layer of
radiation shielding blocks
A small control office is built inside He
cooling room
Door position of He cooling room is
changed because CB1 and dewar is
located at the entrance hall of former one
Location and size of former sectional door
is changed to allow entrance of CB1 and
WWP
07-08/09/2015
IMAC VII Meeting
9
Ionized air ducts are reorganized regarding
radiation security
Before
• Former distribution was covering almost whole
area on the roof
• No trespassing was allowed
• Foam duct material, unsafe for radiation
• Glued to the ground, no maintenance without
damaging neighboring ducts
• Input and exhaust ports were at the same
elevation with beamline
After
07-08/09/2015
IMAC VII Meeting
10
Air conditioning units located at corridor are
Before
After
moved to terrace
• Gained a larger working area
• Ease of maintenance
• Reduce mechanical vibrations near RF amplifiers and
LLRF
• Less complex air duct distribution and homogeneous air
flow
07-08/09/2015
IMAC VII Meeting
11
• UPS units are moved to former e-gun building
•
•
•
•
•
Reduced cooling costs
Increased number of UPS units
More organized and simpler cabling for electricity grid
Gained more working area inside laboratory
Reduced electricity related security risks
• Power distribution inside laboratory building is
reorganized accordingly
Before
07-08/09/2015
After
IMAC VII Meeting
12
• Trapped entrance to radiation halls are removed in order to use
concrete doors instead of lead doors
•
•
•
•
A cheaper solution
More working area
Easier access for big systems
Better radiation security
07-08/09/2015
IMAC VII Meeting
13
Additional cable halls are drilled to radiation area roof
(31 in total)
Two stairs are built to radiation area roof
Terrace of laboratory is reorganized as ionized/nonionized air ventilation plant and storage
07-08/09/2015
IMAC VII Meeting
14
Experiment Stations and Clean Room
• Former two-story, 6 room experiment station area is demolished in
order to build 5 new stations in a single story with elevated height
and a clean room according to demands of experiment community
07-08/09/2015
IMAC VII Meeting
15
Electricity
• One of the main parts
of TARLA
infrastructure
• Electricity system is
totally reorganized
during modifications
• 2MVA + 1MVA backup
• 3 x 1000kVA Transformers
• 3 x 1100kVA Generator
• 6 x 300kVA UPS
• Busbar Distribution
07-08/09/2015
IMAC VII Meeting
16
• Coupled grounding for facility and
• Load and voltage fluctuation
electricity system
±5%
• Grounding trays furnished to
• Frequency fluctuation ±1 Hz
caves
• Harmonic distortion isolation
• No ungrounded power panel or
for RF system feed (under
plug.
development)
• Average grounding resistance
throughout facility of 0.06 Ω
• Local PLC system for
generator synchronization to
UPS phase
• Local controller for UPS
switching
• SCADA system for grid
monitoring and shutter control
(under development)
• Synchronized loading of
generators <1 min.
• UPS feed duration under
Three distinct busbar installations for power
%125 load >10 min.
distribution of 1kA, 1.6kA and 4kA carrying
capacity which are connected in parallel to UPS
07-08/09/2015
IMAC VII Meeting
17
Ionized Air Conditioning
• Air ducts, inlet coil, exhaust port
and dampers are installed
• Design of chimney and filter
unit is ongoing
• Design and installation of PLC
controller for dampers, motors
and valves will be done
according to safety and hazard
analysis which is under the
scope of PSS contractor
• Single inlet and outlet coupled to distribution ducts via air dampers.
• Distinct air ducts for each hall, no risk of air mixing during operation.
• Staff may freely be present in any hall even if the rest of halls are in operation
07-08/09/2015
IMAC VII Meeting
18
• 40500 m3/h total air flow rate which
corresponds to 25 circulations/hour.
• Combination of bag/HEPA
(H14)/carbon filters for exhaust
• 5m chimney height above highest
point of roof (17.5m above ground
level)
• 900 mbar pressure inside caves
(~950 mbar outside)
• Frequency driven suction motor at
exhaust port to enable different
operation modes
07-08/09/2015
IMAC VII Meeting
19
Radiation Shielded Doors
• Instead of lead composite
doors, concrete doors in
same thickness with walls are
decided.
• Better radiation security
• Easier access for big
machines like SRF modules
• Cheaper construction
07-08/09/2015
IMAC VII Meeting
20
• General design is complete
• Total weight is about 130
ton/door
• Detailed design including
static calculations,
mechanical design and
actuator system design will
be done by contractor
• Dimensions are
3.30x2.25x4.35m
• Construction department
approved static calculations
for basement
• A hole of 40 cm depth will be
dig for traction and actuator
system
07-08/09/2015
• PLC based controller will be
done according to the
«hazard and risk
assessment» of PSS
contractor
IMAC VII Meeting
21
Compressed Air
• ATLAS Copco GA 7 VSD+
• 5.5-12.5 bar pressure
• 7.2-14.2 l/s flow rate
• Screw type, frequency controlled
• FD15 drier
• Dew point of -400C
• Operating pressure up to 16 bar
• 15 l/s flow rate
• Tank
• 500liters
Installed for He plant primarily but
capable of feeding enough
pressure/flow for whole facility
Cu piping is installed for He plant
Al piping will be used for radiation
halls due to lesser contamination
07-08/09/2015
IMAC VII Meeting
22
Water Cooling System
• Water cooling system is
composed of;
• Installation is divided into two
stages;
• a central cooling plant which
provides cooling capacity
• three separate circulations;
beamline components, beam
dumps and radiation nonrelated systems
• support systems
07-08/09/2015
• First stage covers central cooling
plant, majority of support systems
and radiation non-related
circulations
Commissioning phase
• Second stage covers beamline
/beamdump cooling circulations
and waste-water treatment
Design complete/in tender progress
IMAC VII Meeting
23
07-08/09/2015
IMAC VII Meeting
24
• First Stage Covers;
• 1 Hybrid type closed cycle
cooling tower, 850.000kcal/h
• 3 Chiller Units 425.000kcal/h
each
• 2 Main heat exchangers
(1 backup)
• 4 storage tanks
•
•
•
•
1x15 ton feed water
1x1 ton filtered water
1x5 ton 7/120C chiller buffer
1x2 ton conditioned water
• 4 frequency driven circulation
pumps
• 3 fixed speed mixing pumps
• 2 main 3-way mixing valves
• 2 2-way by-pass valves
• Automation and control system
07-08/09/2015
IMAC VII Meeting
25
07-08/09/2015
IMAC VII Meeting
26
Flow rate
Nom. Input
Temp
Temp rise
Conductivity
pH
Nom. Input
pressure
Pressure
drop
Radiation
non-related
systems
~3-30 m3/h
22+/-30C
<150C
--
--
6+/-1bar
<3 bar
Beamline
~0.2-2.7 m3/h
29+/-10C
<150C
1-5 MΩ
8-8.5
6+/-0.5bar
<3 bar
Beamdumps
2x4.6 m3/h
29+/-30C
<150C
6+/-0.5bar
<4 bar
07-08/09/2015
IMAC VII Meeting
1-5 MΩ
8-8.5
27
Segmentation of Laboratory Rooms
RF and electronic
Small
workshop rooms
Acc Hall
Brems. Hall
FEL Hall
Clean room
He Plant
Sample
preperation
room
Proposed area for exp.
Stations and clean room
Tr
room
07-08/09/2015
1st floor
IMAC VII Meeting
28
System roomservers
Electronic storage
Electronic workshop
Diagnostic lab
Control room
2nd floor
07-08/09/2015
IMAC VII Meeting
29
Conclusions
• Infrastructure is the key point of an accelerator facility
• Without proper and reliable infrastructure actual progress can
not be met
• Late 2014 and majority of 2015 is spent on infrastructure
studies
• Complete missing parts
• Fix problems
• Infrastructure studies are almost completed.
• Technical specification documents are prepared for the rest, we
are waiting for the tender procedures to be completed
07-08/09/2015
IMAC VII Meeting
30
Thank You
IMAC VII Meeting
Download