Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Revision 0 (2) State FINAL DRAFT Monthly Project Status Report for ACCSYS Reporting period 2015-01-01 to 2015-01-31 Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 TABLE OF CONTENTS 1. Total ACCSYS Project Status ............................................................................ 4 1.1 Executive Summary ................................................................................................ 4 1.2 Project Wide Issues & Mitigations ............................................................................ 5 1.3 Decisions Required ................................................................................................. 5 1.4 Milestones ............................................................................................................. 5 1.4.1 Achieved Milestones during January ...................................................................... 5 1.5 Focus for the next 3 months ................................................................................... 5 2. Project Performance (EV) ................................................................................ 6 2.1 Project EV Curve .................................................................................................... 6 2.2 Variance explanation .............................................................................................. 6 2.2.1 Earned value – planned value ............................................................................... 6 2.2.2 Earned value – actual value .................................................................................. 7 3. Planning Status ................................................................................................ 7 4. Cost Status....................................................................................................... 7 4.1 Variances for at completion budget .......................................................................... 7 5. Risk Status ....................................................................................................... 7 5.1 Risks escalated present month ................................................................................ 7 5.2 Top 5 risks concerning Cost .................................................................................... 7 5.3 Top 5 risks concerning Schedule .............................................................................. 8 6. Milestones and schedule for coming 12 months .............................................. 9 7. Status on Annual Review 2013 Recommendations .......................................... 9 8. Other (examples depending on project) .......................................................... 9 8.1 Status Environment .............................................................................................. 10 8.2 Status Safety ....................................................................................................... 10 8.3 Status In-Kind ...................................................................................................... 10 8.4 Status Construction Contracts ............................................................................... 10 9. Attachments .................................................................................................. 11 9.1 Work Package Reports .......................................................................................... 11 9.1.1 WP1: Management ............................................................................................ 11 9.1.2 WP2: Beam Physics ........................................................................................... 11 9.1.3 WP3: Normal Conducting Front End .................................................................... 11 9.1.4 WP4: Spoke Cavities and Cryomodules ................................................................ 15 9.1.5 WP5: Elliptical Cavities and Cryomodules ............................................................. 16 2(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 9.1.6 WP6: Beam Delivery Systems ............................................................................. 18 9.1.7 WP7: Beam Diagnostics ..................................................................................... 19 9.1.8 WP8: RF Systems .............................................................................................. 20 9.1.9 WP10: Test Stand.............................................................................................. 20 9.1.10 WP11: Cryogenics............................................................................................ 21 9.1.11 WP12: Vacuum................................................................................................ 23 9.1.12 WP13: Safety .................................................................................................. 24 9.1.13 WP14: Accelerator Integration .......................................................................... 25 9.1.14 WP15: Electrical Support .................................................................................. 26 9.1.15 WP16: Cooling Support .................................................................................... 27 9.1.16 WP17: Power Converters .................................................................................. 29 9.1.17 WP99 Accelerator Infrastructure & Installation ................................................... 30 3(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 ACCSYS Project – Status Report for January 2015 1. TOTAL ACCSYS PROJECT STATUS 1.1 Executive Summary ACCSYS in January made significant progress in developing and finalizing InKind Contributions along as well as preparations for the upcoming Annual Review. In terms of IKC we are very close to final signature on the contract with Aarhus University on Beam Delivery Systems (final signature is expected in February). Agreement has also been reached with Wrosclaw University in Poland regarding the delivery of the majority of the Cryogenic Distribution System. The remaining portion of this system will be supplied by IPN Orsay and a meeting on the detailed technical specifications of this system was held with IPN Orsay this month. Discussions with other Polish institutions regarding the supply of the 704 MHz LLRF system were quite fruitful and it appears that such a contribution will occur. An oral agreement was reached with Daresbury Lab in the UK regarding the provision of beam instrumentation for the Linac Warm Units. Discussions with Daresbury are also underway regarding the supply of the LWU chambers and the beam line for the HEBT. Preparations for the upcoming Annual Review include replanning of the P6 schedule to reflect changes in Work Package assignments and increased IKC. The development of an integrated installation plan is an important part of this work. The updated P6 schedule will be ready in mid March. A draft agenda for the ACCSYS breakout session has been created and backup documentation is under development. ACCSYS expects have all documentation ready in time for the review. Recruiting is continuing with 4 new staff members expected to start work in January and February of 2015. The ACCSYS staff plan has been updated and will be consistent with P6 planning. The plan ensures that sufficient technicians are available for the project. The first technicians will start in 2015. There has been no additional risks added to the project during January. Some additional detailed technical risks including those associated with operations will be added to the risk registry prior to April. These will add detail but will not greatly increase the overall risk profile of the ACCSYS Project Work Package audits and design reviews have been identified for 2015. Design reviews are entered into the P6 schedule as their dates are identified. The first design review will be the CDR for the ion source and LEBT planned scheduled for February 10. Accomplishments from individual work packages include: Development of a schedule for the AD staff transition to the ESS Site offices (WP1). Successful testing of the first Double Spoke Cavity at 2 K. (WP4). Adjustment of Medium Beta klystron delivery plans to be consistent with June 2019 beam milestone (WP8). Identification of a temporary location for the the prototype modulator test lab so that work can stay on schedule (WP10 and WP17) with ESS-wide RAMI group to align approaches to reliability analysis (WP14). Review of the grounding mesh for Klystron Gallery completed (WP15). Start of development of Water Consumer Guidelines to specify design codes, standards and specifications for that water skid designers should use at ESS (WP16). Agreement with 4(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 CF on the solution to the water cooling of the Klystrons and acceptance of this approach by CCB (WP99). Internal review of Klystron Gallery layout conducted. (WP99) 1.2 1.3 Project Wide Issues & Mitigations Consistency is needed across the ESS project on the process and documentation of radiation shielding calculation. We consistently hear concerns from potential In-Kind Partners on the VAT issues. This is being addressed at the ESS-wide level. Decisions Required 1.4 1.4.1 None Milestones Achieved Milestones during January 1.5 None Focus for the next 3 months During February - April of 2015, ACCSYS will continue technical work and planning associated with the existing work packages. Work on IKCs will continue with an emphasis on the writing of detailed technical appendices and the signing of final agreements. Planned WP audits along with the CDR for the Ion Source and LEBT will be held. Placing the order for the Accelerator Cryoplant is planned for February. P6 will be updated to reflect new division of efforts and additional IKC. Planning for installation and commissioning activities will continue including the development of an installation plan. Recruitment efforts will continue and the ACCSYS staff plan will be updated. Preparations for the ESS Annual Review will be completed and presented. 5(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 2. PROJECT PERFORMANCE (EV) 2.1 Project EV Curve Grand Total Value 90,000,000 80,000,000 70,000,000 60,000,000 50,000,000 40,000,000 30,000,000 20,000,000 10,000,000 0 Earned Actuals Time-phase period Earned Actuals Scheduled 2.2 33,949,988 34,864,980 35,468,022 Variance explanation 2.2.1 Earned value – planned value The schedule variance (-1.5 Million Euro) is mainly due to: • -0.84 M€ New Vacuum plan not still in place (WP12) • -0.27 M€ New Beam Delivery system plan not still in place (WP06) • On-going actions on planning for matching the delivery date for installation (Spoke 0.17 M€ (WP04) & NC Linac -0.17 M€ (WP3)) • On-going action on resource loading to match the official staff plan (Power converter -0.17 M€ (WP17) & Installation -0.1 M€ (WP99)) 6(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 2.2.2 Earned value – actual value The cost variance (-0.9 million Euro) is mainly due to: • • 3. -0.6 M€ Uppsala University Invoice Q3 2014, coming in 2015 (Test stand WP10) Some other little fluctuations in all the WPs (mainly to salaries) PLANNING STATUS 4. After the end of 2014 the PV were normalized to the actual cost. Reassesment of klystron deliveries for medium beta shows that plan now complies with Mid 2019 target. RFQ construction is currently showing a negative total float (-36 days), but a reevaluation of the planning is on-going as following the WP03 and RFQ reviews done in November A detailed installation planning study is on-going inside the accelerator integration group with a scope of checking the delivery date of the critical components in P6. . COST STATUS 4.1 Variances for at completion budget The cost objective for ACCSYS is 510 M€. The plan until EOC now shows 510M€, including a budget reserve. This reserve will change as we replan the work packages and insert costs. The size of the reserve will be fixed by April. 5. RISK STATUS 5.1 Risks escalated present month 5.2 Top 5 risks concerning Cost None. Treatment status Expected cost (k€) 1/1/141/1/19 Started 414 Unidentified design faults are not prototyped and fail in production 1/1/1412/31/19 Started 279 Suppliers do not deliver on time with right quality/quantity, e.g. klystrons, modulators, CMs, cavities 1/1/1412/31/19 Started 264 Id Event Date 2 In-kind contributors do not meet scope and schedule requirements 5 3 7(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Treatment status Expected cost (k€) 1/1/141/1/18 Started 142 1/1/1412/31/19 Not started 113 Treatment status RP Id Event Date 8 Delay in issuing major contracts, both in-kind and others. 23 Political and financial considerations overrule technical considerations for IKC assignments 5.3 Top 5 risks concerning Schedule Id Event Date 3 Suppliers do not deliver on time with right quality/quantity, e.g. klystrons, modulators, CMs, cavities 1/1/1412/31/19 Started 16 46 cryomodule production is late 1/1/1412/31/19 Not started 16 2 In-kind contributors do not meet scope and schedule requirements 1/1/141/1/19 Started 15 8 Delay in issuing major contracts, both in-kind and others. 1/1/141/1/18 Started 12 1/1/1412/31/19 Started 12 19 Extra time spent on new systems and tools and not on technical work 8(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 6. MILESTONES AND SCHEDULE FOR COMING 12 MONTHS Top level milestones NB: Re-planning action on-going could bring to new MS action for Q1 2015 (Ready for annual review) 7. STATUS ON ANNUAL REVIEW 2013 RECOMMENDATIONS A total of 8 recommendations with 14 deliverables resulted from the annual review 10 deliverables constituting 4 recommendations are complete 4 deliverables remain: 1) Draft Beam Commissioning Plan (complete and under review) 2) IKC Plan for Beam Instrumentation (more than 75% complete) 3) Definition of Reliability Requirements - underway 4) Integration of Utility Reliability into ACCSYS Reliability Studies - underway 8. OTHER (EXAMPLES DEPENDING ON PROJECT) 9(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 8.1 Status Environment 8.2 Status Safety 8.3 Status In-Kind 8.4 Status Construction Contracts 10(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 9. ATTACHMENTS 9.1 9.1.1 Work Package Reports WP1: Management Accomplishments Preparation of documents and breakout session agenda for ESS Annual Review Replanning of various work packages to better reflect IKC and changes in scope in WP6, WP12 and WP2 Continued emphasis on finalizing IKC contracts, particularly with Arhus University. Planning for Work Package Audits and Design Reviews Developed a schedule for AD staff transition to ESS Site Offices 9.1.2 WP2: Beam Physics Accomplishments Effect of quadrupole multipole including errors being studied. DTL Design Optimization - RF simulations is on going. Housing the chopper inside a quad vs. moving the chopper out of the quads studied. Ordered two PCs for two of the group members, these PCs will be shared for studies. The LWU, HEBT and A2T magnet requirements were updated and provided to Elettra. Preliminary electromagnetic design of two types of pulsed air-cooled quadrupoles for LWU is expected by the end of February 2015. Draft version of the Preliminary study of component failures in the linac (A50080) complete, final version to be released Feb 28. Issues None As reported earlier the shortage of staff could delay some milestones and tasks 9.1.3 WP3: Normal Conducting Front End Accomplishments WP 11.3 Overall and WU 11.3.1 Management As a result of the WP 3 audit in December 2014, the WP started the new year with a clear picture of the technical status of all work units and a good understanding of priorities for 2015. Work units are now clarifying and updating their planning into ESS Primavera project plan, working back from new planning dates received from ESS for installing each of the NCFE systems into the front-end building and tunnel (ESS Bldg. G01). Prototyping and detailed design is essentially complete or nearing completion for 11(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 three of the four partner WUs, and procurement of materials and components has commenced by partner CEA for the ESS RFQ and by partner INFN LNS for ESS ISrc (Proton Source#1). This progress is necessary towards meeting the key ESS schedule milestone for 2019. However there is technical risk because requirements from ESS are still being developed, communicated and agreed with partners and interfaces with ESS site infrastructure and with systems provided by other WPs, are still being defined and communicated. WU 11.3.2 Ion Source (ISrc) and Low-Energy Beam Transport (LEBT) – IKC by INFN LNS (Catania) - - The layout area for assembly of ESS ISrc and LEBT has been established at LNS, Catania. High voltage systems, solenoid, and transformer mounting and insulation equipment for ESS Proton Source (PS)#1 has been procured and delivered. Other PS#1 components are being procured or in the process of being manufactured or delivered. The WU team worked during January to document the detailed design so that 3D CAD models, and comprehensive specifications / descriptions were ready for review at Critical Design Review (CDR), for 10 Feb 2015, and delivery to ESS. WU 11.3.3 Radio Frequency Quadrupole (RFQ) – IKC by CEA Saclay - The specification for procurement of copper is in signature and the tender for procurement will be issued according to CEA’s quality processes The call for tender for the RFQ’s coupler is in progress RFQ detailed design is being documented in reports and the CAD models WU 11.3.4 Medium-Energy Beam Transport (MEBT) – IKC by ESS Bilbao - - - - an integrated engineering model for MEBT was developed and presented to ESS. planning is being updated to provide a more detailed description of tasks and milestones for MEBT design, procurement, construction and testing, than has previously existed in Primavera. Bunchers: o Preparations for copper plating: ready to ship to GSI o Electro-Magnetic design report is in progress. o ESS RF group visited Bilbao Installations, for “simulate beam loading” measurement. Quadrupole: o a new design to adapt new BPM and APERTURE requirements is under development (T11). Diagnostics: 12(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 the design for ACCT+FCT Shielding has progressed. the design for diagnostic boxes #1 and #2 has been improved. a new configuration and layout for diagnostics was presented and is being discussed with ESS Accelerator’s Beam Instruments group. o a mechanical test of a Wire Scanner assembly in progress. o Contacts have been established with the company Feshenko for the BSM o Electronics for BCM is being evaluated. Chopper & Beam Dump: o a major workshop was organized and conducted at ESS Bilbao on 26 January. It was well attended by visiting ESS Accelerator staff from Lund and also externals specialists from CERN, SNS and STFC RAL/ISIS. The workshop resulted in a clear design direction for the technology and configuration of MEBT’s chopper and beam dump similar to a new design successfully implemented at SNS o a design report for the new configuration Conical Beam dump was presented following the workshop. o o o - WU 11.3.5 Drift Tube Linac (DTL) – IKC by INFN LNL (Legnaro) - A visit to GSI copper plating lab verified that DTL design is compliant with main copper-plating requirements, and new details in the design will be implemented. The WU is preparing for DT production tests with copper plating, ebeam welding and brazing. Planned key activities WP 11.3 Overall and WU 11.3.1 Management The work going forward must be better defined and more formally described in IKC agreements: - an In-Kind Contribution (IKC) Agreement, or at least a Heads of Agreement (HoA) between ESS and INFN, to cover at least ISrc-LEBT or DTL, or both, should be discussed as soon as possible. Note that the collaboration agreement between ESS and INFN, which included ISrc -LEBT and DTL design, expired at the end of 2014. - an IKC HoA has been signed between ESS and ESS Bilbao for MEBT, but should be considered as an interim measure only. - a HoA with CEA Saclay for a number of ESS systems, including for RFQ copper procurement and protoyping RFQ, has been negotiated and agreed in principle, but is still awaiting high-level sign-off. It should be noted that this HoA does not currently cover the scope to complete of RFQ design, procurement of components and manufacturing, testing or delivery. Consequently, the WP team is planning with the WU leaders to develop at least four (4) ‘technical annexes’ (cope / statements of work (SoW) and technical requirements and/or technical specifications needed for the three separate IKC Agreements. These should be 13(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 agreed before Q4 2015. To be able to accomplish this: - ESS is investigating options to bring additional resources into the WP team to assist with the development of technical annexes including requirements and interface definition, and for better liaison and coordination of activities and interaction between ESS and the partner WUs. - a ‘warm linac’ interfaces and integration meeting is planned for 15 May 2015. This workshop, to be held in Lund, will involve representatives from all WP 3 WUs and importantly representatives from WPs whose systems, components and infrastructure interface with the NCFE systems and components. Other uncertainties that must be resolved soon are: - whether or not an ‘injector test’ with beam for at least ISrc-LEBT-RFQ, to be conducted at CEA Saclay, will be ordered by ESS. - the scope and responsibilities between ESS and WP 3 IKCs for the transportation of NCFE systems to ESS Lund. WU 11.3.2 Ion Source (ISrc) and Low-Energy Beam Transport (LEBT) – INFN LNS (Catania) - A Critical Design Review (CDR) for both ISrc and LEBT, to be conducted 10 February 2015. WU 11.3.3 Radio Frequency Quadrupole (RFQ) – IKC by CEA Saclay - Work on the future test bench for couplers (design, building, utilities) A second CDR for RFQ, will be conducted prior to commencing tendering for RFQ manufacturing services. An initial CDR for copper procurement was successfully conducted in November 2014. This CDR#2 is scheduled for Q2 2015, to be either at the end of April or more likely early in May 2015. WU 11.3.4 Medium-Energy Beam Transport (MEBT) – IKC by ESS Bilbao - Copper plating for the buncher prototype Call for tender for quadrupole prototype. Documentation is currently being prepared. Procurement of RF Solid State Amplifier. ESS Bilbao must wait for requirements from ESS WP 8 RFS and ESS ICS before this procurement can be launched Procurement of pulser for the MEBT chopper. Waiting on ESS ICS requirements a Preliminary Design Review (PDR) for MEBT is planned to be conducted in the first half of 2015. WU 11.3.5 Drift Tube Linac (DTL) – IKC by INFN LNL (Legnaro) - drift tube prototypes to be developed CDR for DTL is scheduled for June 2015. Issues 14(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 None 9.1.4 WP4: Spoke Cavities and Cryomodules Accomplishments Prototype cavities: follow-up of prototype cavity fabrication and preparation Prototype#1 by SDMS (called “Germaine”): The cavity was successfully repaired by the SDMS company, by re-melting the precisely located defect zone with the electron beam. The leak test is successful and the cavity was sent back to IPNO. The cavity is now being carefully prepared for the vertical test, scheduled mid-march. Prototype #2 by ZANON (called “Romea”): it has been tested in vertical cryostat during the 2nd and 3rd week of January. People from Uppsala were also attending the test. The results are very good, as all specifications are met: the max achievable accelerating gradient at 2K is 11.4 MV/ (spec is 9 MV/m), not limited by a defect but by a field emission induced quench (so potentiality to go to higher gradient). The losses at nominal field are 22 W (eq. CW), more than a factor 2 better than the spec. The cavity is now being prepared for the baking (~48 hours @ 110 °C) and then will be re-tested (mid april). Prototype #3 by ZANON (called “Giulietta”): the cavity preparation (chemical etching, HPR, clean room assembly) has been achieved in end January. The test in vertical cryostat is scheduled for the 2nd week of February. Power couplers: Power coupler prototypes fabrication status. o PMB: still waiting for the delivery at IPNO. The antenna welding is under progress. No updated planning received but we hope for a delivery in early march o SCT: The two power couplers are being cleaned and prepared for the assembly on the conditioning bench. Doorknob: Fabrication is ongoing, no delay to report on. Conditioning bench: the conditioning cavity is being prepared (cleaning) for the clean room assembly with the couplers. Cold Tuning System (CTS): Nothing major to report on this month. Cryomodule: Vacuum vessel fabrication by SDMS is ongoing and is on schedule: delivery still planned in end February. The two sets of magnetic shielding are under fabrication and on time. The instrumentation is undergoing a standardization action with CEA to have as much as possible instrumentation standards for both cryomodules. 15(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Spoke Cryomodule valve box: Design work is ongoing at IPNO. The long lead time components such as the valves and heat exchanger are almost defined in order to be able to order them in the coming weeks. Extensive exchanges and face to face meeting with ESS to accurately define the specifications and schedule of the IKC linked to the spoke CDS. General: Ongoing discussion on IK Contribution of CNRS to ESS accelerator, specially on the contribution to cryomodule control/command Coordination meeting on the French/Swedish contract Meeting on Pressure Equipment Directive (PED) hold at ESS on January 15th to assess possible impacts on WP5 and WP4. Issues Issue on the cavity leakage is solved. Issue on delay with the power coupler is now under control: there will be no major consequence on the overall WP4 development plan. Current & Near Future Variances in Project Plan There is still no variance in the plan expected, and none are expected in the future 9.1.5 WP5: Elliptical Cavities and Cryomodules Accomplishments Cavity P02 from RI has been tested after heat treatment done at CERN for removing the hydrogen from the niobium sheet. The performances of this P02 cavity have been degraded in a similar way than for the P01 cavity with the same amount of Q decrease. 16(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 The cause of the degradation seems to be a pollution of the niobium during the heat treatment in the furnace. This degradation is unusual. The analysis of the RGA monitored during the heat treatment sequence is being done in order to check if some anomalous vacuum quality could be seen. A second test of the P02 cavity is scheduled after a deeper chemical treatment to try to remove the pollution from the surface of the niobium. The thickness to remove is being discussed. The helium tank of the P01 cavity has been welded at ZANON. Final machining and last fabrication operations are in progress. P01 at ZANON after the helium tank welding. The review of the manufacturing drawings of the medium beta cavities is in progress at Saclay. Some differences with our previous design are noticed concerning tolerances concentricity etc. Some machining reducing the niobium sheets of the external cells of the cavities have been also added in order to ease 17(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 the welding of the niobium. That may cause some additional flexibility. The analysis of the mechanical flexibility of the cavity as well as the tuning sensitivity needs to be performed before giving our agreement to the manufacturing drawings. The design of the assembling toolings inside the clean room is almost completed. It is in good progress for the tooling outside the clean room. We launched the order of the 6 external conductors of the couplers for the medium beta cavities. We prepared a test of assembling a HIPPI coupler in the clean room in order to check the toolings. The modification of the modulator of the 704MHz klystron is completed. Tests and conditioning have been performed up to the ESS requirements in terms of RF pulse length (4.0ms). The frequency was 16.66 Hz (higher than the ESS frequency of 14Hz). The maximum RF power was 1MW. General o IKC meeting hold in January 28th, between ESS, INFN and STFC to assess the WP5 cavity fabrication. o Meeting on Pressure Equipment Directive (PED) hold at ESS on January 15th to assess possible impacts on WP5 and WP4. Issues 9.1.6 None WP6: Beam Delivery Systems Accomplishments Contributions to two papers for the ICANS XXI conference have been produced. One paper deals with the temporal characteristics of the ESS proton and neutron pulses, specifically how the raster system affects the neutron pulse. The other paper deals with instrumentation and machine protection strategy for the ESS target station; specifically producing and analyzing a range of beam error modes and how a range of beam instrumentation can duly detect them. In an attempt to ease the process of tracking lattice changes and concatenate the linac lattice sections, an established version control system (git) has been 18(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 adopted. A common lattice file element nomenclature has also been chosen to facilitate the concatenation process. Now the WP06 contract between Aarhus University and ESS has been finalized, only signatures pending, we are working on the requirements of the raster systems. First a prototype raster scanning system with two magnets shall be built and long-term tested before production of the final system. In an attempt to prepare component specifications, non-ideal RSM field waveforms, originating from realistic magnet or power supply specifications, have been simulated. Work has also started on the procurement process, but the actual review from ESS side has to be clarified. Issues None 9.1.7 WP7: Beam Diagnostics Accomplishments Updated WP7 Planning transferred to P6 -Process variable list for all BI systems produces/updated -Planning visit to CERN to evaluate BLM electronics and test optical link reciver implementation -Verbal agreement with Daresbury on in-kind for LWU BCM and BPM. -Some progress on requirements update. -Progress on cable route planning. Collaboration with ICS on cable database. -Held several Focus meetings on diagnostics systems. -Delivered LEBT diagnostics box design to Catania -Planned design review for LEBT Allison scanner. -Planned visit from Trieste and CEA/IRFU to discuss in-kind. First discussion with Polish on possible BI in-kind -Progress on documentation of several in-kind packages. -Took delivery of new equipment and furnishing for new lab area -SLAC RTM design work almost ready for board layout review & prototyping. - Issues - BI requirements update still not completed, although work is now proceeding. Inkind discussion and other work going on with “old” requirements. Procurement process cumbersome and confusing. Need e.g. policy and thresholds for low value procurements. BI device data in LinacLego still needs to be moved to production version Cost of phase reference line for BPM missing in budget. Will resolve with WP6. Hardware interface (connector type and number of cables) with MPS needs to be agreed soon. Currently proposed solution seem overly complicated. 19(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 9.1.8 WP8: RF Systems Accomplishments 704 klystron prototypes: One contract (Toshiba) still with supplier, one project (Thales) kicked off Close to a HoA with ESS Bilbao for WP 8, NC RF Update meeting with CPI/Thales on MB IOT contract. Good progress reported Good visit from Polish in-kind partners regarding supply of 704 MHz LLRF – very good possibility to get in kind contribution here Reassesment of klystron deliveries for medium beta shows that plan now complies with Mid 2019 target. Issues LLRF cavity and phase regulation requirement continues to be very hard to satisfy for NC linac. Mitigation: extra feedback loop between power amplifier and LLRF – the concept is still under evaluation. Mitigation II: rewrite requirements for beam loss in one 1 MW-beam and one 5 MW-beam version. Mitigation III: Beam physics have issues with the calculations – ask clarification (unchanged, I know, there has been progress but I am not certain that the issue is solved – I would rather wait until I know) Cooling of klystron collectors must return 80 deg C water due to CUB issues. This represents a number of project risks including klystron warranty, reliability, and life. Mitigation: Under evaluation, I think a solution is close FREIA 352 MHz spoke RF source delayed. Mitigation: a second prototype contract has been awarded, and a third party has restarted the bankrupted company Current & Near Future Variances in Project Plan • 704 MHz klystron prototyping is about 2 months late. Mitigation: there is an offer from one of the tenderers to supply a third prototype. All offers came under the budget, so there is almost room for this, plus delivery reassessed, see above. • LLRF technical spec not possible to finalize on time due to requirements issue – see above. Impact: descoping of prototype 1, further investigations on system, see issues #1. 9.1.9 WP10: Test Stand Accomplishments - RF Lab M-house: Negotiations under way between WP17 and Akademiska Hus (AH) about renting the Southern Machine Hall of LU’s M-house for the first version of the 20(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 - - - modulator prototype lab. Costs for rent and electrical installations are known, costs for other modifications are still under investigation by AH. RF Lab (Lund): Contract negotiations between ESS and Briggen, the landlord of building at Scheelevägen, are continuing. Signature is foreseen for 2015-03-01, moving in date for 2015-05-01. RF Lab (Lund): The facility is named ‘Utgård’ and is being shared with two other ESS teams: sample environment and detectors. A coordination group including an ES&H representative is being set up. . Issues - RF Lab (Lund): WP17 has requested a second location for the lab, in the M-house of LU (where TS1 was previously planned to go) to serve as a transitional location for the lab before we can move into the Briggen location (Scheelevägen). This requires additional effort and funds from WP10, neither of which are currently planned for. The move from one location to the other will require additional manpower and money as well. Relocation of TS1 to Uppsala will require additional efforts for coordinating this work at a distance. The brunt of the additional workload will, however, have to be borne by WP8 and WP17. A new test stand engineer will have to be hired in 2016. Alternatively, a temporary position could be filled by Engineering & Integration Support Division. Additional resources for testing of elliptical CMs in Lund are required. Risks are lack of manpower for execution of testing. An evaluation of the resource needs is ongoing. First estimates of the IKC from Poland show that the risk is manageable. Current and Near Future Variances in Project Plan - The Test Readiness Review for the spoke cavity prototype has been postponed due to the delays in both cavity delivery as well as RF source delivery. The RF lab has been required to start up at an earlier date then foreseen at a different location than foreseen. This requires re-planning and additional funds. A new WU for the Lund RF Lab has been created in P6. According to ACCSYS PM, funding of 500 kEUR will be available for this WU. TS1 will be located in Uppsala. 16 MSEK of WP10’s budget will be paid to UU for the work to be done on TS1. New (later) delivery dates for the modulator and the klystrons will require an adjustment of the TS1 planning. 9.1.10 WP11: Cryogenics Accomplishments ACCP contract award justification meeting with ALAT to explain evaluation process, award decision and future projects with new business opportunities for ALAT took place. 21(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Several internal meetings regarding ACCP draft contract and negotiation approach, particularly regarding warranty, schedule, penalties and liability to place Technical and contractual clarification and discussion meetings with LKT upfront contract signature took place. There was good progress on the technical questions - LKT will update the main proposal documents. There were also constructive discussions on the draft contract with only very few items still open that will be clarified in February. The L4 requirements had been drafted and distributed to the related stakeholders. Ongoing discussions with LKT and ALAT regarding TMCP budget and technical solutions The target project is currently considering a number of options for the cold moderator design. These design options may offer significant improvements in target performance, but at the increased cost of greater cryogenic cooling required. The current estimated TMCP capacity is ~ 25 kW at 17 K. Moderator design options may increase this to >35 kW at 17K. We provided the target project with an assessment the impact of these changes on the TMCP, considering technical and schedule risk, cost and performance. A decision on the final moderator configuration should be made in February. The target project requested information on what would TMCP access requirements for installation. A summary of TMCP installation requirements was drafted and sent to Daniel Lyngh. Provided estimate of TMCP critical spare parts and estimated cost to Target division. Participated in a hydrogen safety meeting hosted by Fredrik Jörud (safety division). Reviewed and commented on two documents drafted by Dr. Hans Quack – “Circulation Pump Study” (for hydrogen circulation pumps), and “Temperature and Pressure Control in the Hydrogen Loop” Met with Mirko Menninga of the ESS procurement division to discuss options for TMCP procurement. We anticipate pursuing a “negotiated procedure” to procure the cryoplant, aiming for a better opportunity to communicate with qualified vendors, and a more competitive procurement process. Mirko committed to research how we can pursue this option, and we will draft a document to allow ESS to pre-qualify potential bidders for the TMCP. Draft SCHEDULE (SoW) to the IKC agreement between ESS and CRAS respecting the CDS for the spoke linac was provided to IPNO (it was agreed that the schedule will be the technical annex to the heads of agreement, which is going to be signed in the end of March 2015) Technical meeting on the specification of the CDS for the spoke linac was held in IPNO 22-23 Jan 2015 Negotiations with WrUT, potential Polish in-kind contributor, on providing in-kind the CDS for the elliptical linac and the CDS for Lund Test Stand 2 were successfully completed in Jan 2015 22(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 ESS-WrUT collaboration kick-off meeting was scheduled on 4 Feb 2015. Issues The end box of the CDS for the spoke linac sticks into the DTL section with a potential conflict that is not yet solved. The safety valve sizing of the CMs is still missing, i.e. the SV discharge collector line sizing is based only on rough own assumptions. Since the location of the ACCP cold box was changed the routing of the CTL shall be updated as well as the interface sheet (ESS-0011233). Due to changes in the layout/arrangement of the process lines connecting the cold boxes and warm compressor stations of the ACCP and TICP the routing of the auxiliary process liens of the CDSs for the elliptical linac and for Lund Test Stand 2 as well as the related interface sheets (ESS-0011310, ESS-0015217 and ESS-0015218) shall be modified. Unclear work split with Forschungszentrum Jülich, a probable in-kind supplier of the moderator systems including target helium cryoplant; particularly procurement needs to be sorted out Current and Near Future Variances in Project Plan Full building access (including utilities) from CF / SI is currently planned for 1-May-2017. This milestone is vital for start of the commissioning of the cryoplants. Whereas there is no conflict with ACCP and TMCP commissioning plans the TICP commissioning would be delayed with reference to the current schedule, however without any impact on the project as the TICP is not needed before end of 2017 for the acceptance testing of the CDS-LTS2 cryoline prior WP10 test stand commissioning. Future variances in P6 are hence proposed as follows: o TICP activities shifted for 2 months (delivery of main items between April and May 2017) o CDS LTS2 commissioning and SAR shifted for 2 months (July-August 2017) 9.1.11 WP12: Vacuum Accomplishments The vacuum test facilities; vacuum integration, material test and calibration test stand to be supplied by STFC Daresbury under a IKC are now in fabrication with delivery schedule for the Q2/ Q3 2015. The technical requirements for the particle test facility also being supplied by STFC were finalized in preparation for the meeting with potential supplies of the clean rooms to be held in Lund early in February 2015. This will allow these facilities to be order and delivered during Q3 of this year. 23(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Technical discussions have now started with STFC to define the first phase of work covering the supply of the LEDP, HEDP and LWU’s as apart of the planned UK IKC in the vacuum area. The second phase of work will cover the supply of the LWU’s and beam pipes for the HEBT, A2T and beam dump lines. As apart of this activity on going discussions are being held with the beam instrumentation group to define the port layout required in the diagnostic beam box of the LWU’s. This information will be required as an input to the design that will be developed by STFC over the next several months. Current plans will see the design for the prototype spoke cavity LWU completed by the end of Q2 and with construction of this unit starting during Q3 2015. In parallel with this activity, several configurations of the diagnostic beam box will be built to check BI fit and vacuum compatibility. Work continues in developing the L3 and interface requirements for the accelerator vacuum systems. Preliminary discussions were held with the WP4 and WP5 team to establish the preliminary requirements for the vacuum insulating system required for the cryomodules. On going discussion continue with CAE Saclay to finalize the vacuum layout for the RFQ. On going discussion continue with INFN on the ion source and LEBT with regard to vacuum instrumentation and the mechanical layout of the LEBT and LEBT to RFQ interface. Interconnection diagrams for the Ion source, LEBT vacuum system and Ion source LEBT control system have been prepared and forward to INFN for comment. On going discussions continue with the Bilbao vacuum team on vacuum design requirements, fabrication processes and testing requirements fro the MEBT and the vacuum layout for this system. On going work in support of the ICS VIT (vertical integration test) project continues. Work continues on cables, racks, controllers etc. for the accelerator vacuum systems. Discussions were held with the RF group on klystron integration including recommendations on ion pump controllers and klystron interlocks. Potential suppliers for the supply of the instrument venting system have been identified and meeting with them are currently being planned. Meeting was held with the TD to discuss piping of the target moderators and options for providing an active water leak detection system. Re-planning of WP12 continues. Members of the ESS vacuum team made a visit to SNS and one member of the team attend a particle accelerators training course on vacuum science. A second interview was held with a potential candidate for the vacant Vacuum System Engineer’s position. The final decision on making this candidate an offer is pending a Skype interview with a second candidate for this position scheduled for next month. Ongoing organization of AD seminars continues. Issues • None Current and Near Future Variances in Project Plan • 9.1.12 None WP13: Safety Accomplishments 24(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Lali Tchelidze back to work 50%. Need of additional resources were addressed once again. It was agreed with Gunter Muhrer that Riccardo Bevilacqua will continue working 40% of his time on AD safety related issues. Luigi Esposito was hired to join the team 50% of his time in the beginning of February. Luigi will be based in CERN most of his time, but will spend entire February and then around a week each month at ESS. Luisella Lari also joins 30% of her time from the beginning of February. Duy Phan was hired and will join the team at the end of February as a general safety engineer. AD safety representative (Lali T. or a substitute as needed) was present at every Physical Plant Working Group and Safety Advisory Group meeting. Regular internal safety bi-weekly meetings were planned starting in February. All major tasks were identified and put together in a safety plan. All of them will be tracked in JIRA, final reports will be uploaded in CHESS. The plan is in line with ES&H project plan. A number of completed tasks that are currently documented in JIRA only will be written in a form of technical notes and be reviewed and approved in CHESS. SSM requirements breakdown for AD safety is ongoing. AD representative will be included in the discussions starting in February. Information was requested about the chemical composition, density and water content of various clay materials that CF plans to use on the site. This will be used in a new, detailed radiation shielding analysis. Information was requested about the concrete chemical composition, density and water content that CF uses on the site. This will be used in a new, detailed radiation shielding analysis. AD provided input on size/shape/density/composition of stackable concrete shield blocks. Issues No approved procedure for designing shielding. The decision-making processes various from task to task. Technical shielding notes missing in some cases. The CF design, in some cases, is inconsistent with the existing technical shielding notes/”official” decisions. 9.1.13 WP14: Accelerator Integration Accomplishments Systems Engineering Continued development of L4 requirements by Lead Engineers. Review of L3 requirements for consistency, etc. Review of L2 requirements in preparation for delivery to the Annual Review Accelerator Engineering Iñigo Alonso began work as Lead Engineer for HEBT, Dump Line, & Dog Leg 25(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Selection of a single candidate for invitation to 2nd interview (LE post) Reliability/Availability Formation of ESS-wide RAMI working group by the ACCSYS Reliability Engineer has been a success, and work has started to align the various approaches and expectations of each division. Continued work on FMEA for the cryoplant, with results passed to the cryo group for consideration in relation to the purchase of the cryoplant. FMEA study on RF & vacuum systems ongoing Issues 9.1.14 Staffing remains a problem, however it is hoped that a LE post will be filled soon Some prioritization issues related to the order in which requirements are authored. This will be solved in conjunction with the Systems Engineer. WP15: Electrical Support Accomplishments Grounding system Detailing of the grounding mesh for the LINAC Front End (Level 090) has been done together with the CF designers. Karin Svedin thinks that we should take the 1 x 1 m mesh size to the CCB. Site-meeting with CF on the construction of the grounding mesh in the Klystron Gallery floor, there was some uncertainty about the requirements (mismatch between text and illustration), this was cleared up so the design could continue. Review of grounding mesh for Klystron Gallery (G02) has been performed; we had some comments on the placement and number of connection points installed in the floor: The floor grounding points were removed from the floor above the LINAC Front end (Loading/Access Hall – G02.100.5.001) as they are not required here. Electrical systems Including procurement in the project plan. The thinking is that the work package has to procure electrical cabinets, low-voltage switchgear, earthing bars and cables. The cables and electrical cabinets should be catalogue items that are ordered as needed via a framework agreement. There is still a lot of on-going discussion and design work with the routing of power cables and the entry into the electrical substations. The collisions with the cooling pipes are (probably) being resolved, of course CF-HVAC is now having a go at grabbing all available space. Discussion with CF on using their NEPLAN model to perform dimensioning of the power cables and protection circuits for WP 15. CF agrees, so we can go ahead once there is a task written up for the consultant. The Design Office (via Magnus Täcklind) will deal with the consultant via the ESS framework agreement. 26(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 The CRYO-system vendor is now known, so CF can start work on the substations for the cryoplants. The electrical requirements in DOORS should be reformulated so that CF can get their requirements directly from the vendor’s documentation. Cabling Evangelia is working with the designers on producing an estimate of the costs and amounts of “control”-cabling required for the accelerator systems (An estimate for the CNPW-cabling exists). Issues None Current and Near Future Variances in Project Plan 9.1.15 Adjustment of project plan to achieve a better match between the project plant with procurement needs and the order of installation. The purpose is to procure power cables and electrical cabinets in 2 – 3 “blocks”. Upcoming task, “11.15.2 Electrical System Modeling”, staring in Feb/March instead of Jan. The reason for that is that I have decided to use this task to extend the NEPLAN model created by CF to cover the electrical installations inside WP 15’s scope (Gallery, Front-End, CRYO) to verify the cable dimensioning form the preliminary design and to determine the requirement for overload protection. The ESS has no on-site resources that can “drive” NEPLAN. Therefore, the WP will use the ÅF-consultant that CF uses, but it will take a few weeks to contract the person. On the other hand, re-using CF’s model will shorten the task significantly so overall there will be no delay. WP16: Cooling Support Accomplishments Cooling Systems Finalized the work of the klystron collector task force. o The summary of the work was presented at CCB in 2015-01-29. The updated requirements were accepted but CF still needs to come back with cost impact. o Details and MoM concerning the work can be found on confluence. Visited SNS and met with Jim Schubert and George W Dodson. o Tour of accelerator & instrument halls o Meetings with Jim concerning accelerator cooling systems o Meetings with Lorelei Jacobs and John Denison concerning instrument cooling Discussions with Benjamin Cheymol regarding the Farday Cup and Emittance Meter Units. o These are the only water-cooled beam diagnostic tools. 27(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 o Requirements are identified and those already known are also agreed upon. o Some data is still unknown, e.g. pressure drop. Met with Tomi Pakarinen for a discussion on waste water handling. o We cannot have an outlet to the outside of FEB, all handling will have to be made on the inside. o It is foreseen to have tanks located in FEB in case a system needs to be drained. o A continuing meeting planned in February. Updated a draft of a Service Level Agreement (SLA) with NSS, and sent to Rob Connatser for review and comments. o Question regarding WP16 budget for NSS instruments still ongoing. Met with Evangelia Vaena and discussed cable inventory. o Difficult to give detailed information at this stage since the options are so numerous. E.g. Where do we install connection boxes, if any? Where will the instruments be located? Instruments for couplers still to be discussed! o Provided Evangelia with an updated spreadsheet with estimated cable types and quantities for WTRC system. Attended several Physical Plant Working Group meetings hosted by David McGinnis Attended contract meeting with Linde Kryotechnik and discussed technical requirements for the conventional cooling system. Updated Energy Inventory Spreadsheet for Erica Lindström (Energy Group) Initiated an effort to update heat loads in the “equipments summaries spreadsheet”, ESS-0007859 Continued work together with Edgar Sargsyan concerning requirements for DTL tanks and magnets. o Edgar updated heat loads (minor adjustments) o Continued discussions with Francesco Grespan concerning DTL cooling system. o Requirements for magnets and DTL are identified but some data is still only preliminary. Met with Aurelién Ponton and worked on the requirements for IS and LEBT. o Requirements are now identified but some data is still missing. Need to resolve pressure drops so that we can decide on IS/LEBT cooling concept. Participated in “process system meeting” with Ronny Sjöholm. The meeting aims at gathering all stakeholders concerning water cooling, i.e. WP16 (represents target, ACC and NSS) & CF. o WP16 will still meet with CF on separate technical meetings. Met with Markus Olsson from chopper group for further discussions on requirements. Further discussions with Xilong Wang, Philipp Arnold and Wolfgang Hees concerning water cooling for cryoplants. o It is foreseen that WP16 and WP11 collaborates regarding in compressor building piping works. 28(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 Started work on a Water Consumer Guidelines, the aim is to specify design codes, standards and regulations that designer and manufacturers of cooling skids and systems must adhere to. Reviewed ACCSYS primavera schedule for WP16 to assess compatibility between WP16 and other work packages and establish appropriate links. Will review this in February with Luisella. Selection of sustainable materials Met with Judith Freita Ramos and discussed materials used by NSS. Judith will prepare a spreadsheet with common materials together with comments regarding impact, amount of material, etc. It seems NSS has about the same type of materials as the accelerator, only a few really unique ones, e.g. large amount of wax and boron. Plans to schedule a meeting with Matthew Conlon concerning how selection of sustainable materials ties in with QA/QC as well as in kind requirements. Hopefully done in January or February. Issues No critical issues but some minor are: o The current CF pipe layout in the FEB goes into AD envelope. This will be resolved during February. o Waste water handling in FEB needs to be resolved. Risk of not meeting SSM legislation. o Hoses for accelerator cooling systems is a major reliability issue. WP16 would prefer that stainless steel tubing is used whenever possible instead of flexible hoses. This would decrease both maintenance time and the risk of leaks. o Difficult to plan work for instruments. The three first instruments are not located close to each other so they cannot share a common cooling skid. Moreover, choppers are located at various positions along the beam line. The cooling system also needs to be flexible and reliable. 9.1.16 WP17: Power Converters Accomplishments 1)- 330kVA modulator prototype – Ampegon contract The new version of the TDR has been prepared with more intensity. According to Ampegon, the High Voltage Transformer design had to be reviewed and new calculations needed to be performed. Sometime has been spent on this activity. Another aspect was the type of capacitors to be used:- ESS had specified polypropylene type and the company is willing to use electrolytic which is not in line with the specifications. According to Ampegon, these two 29(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 points have caused some delay in the delivery of the TDR and had asked for a few more weeks to deliver the TDR. A formal request for the new delivery date has been issued. 2)- Reduced Scale modulator prototype The development of controls/regulation software has advanced. The regulation of the different conversion stages on the low voltage conversion side has been successfully tested on an individual basis using dummy loads. A plan B was discussed with the accelerator division project management for the design and procurement of the High Voltage oil tank assembly. The strategy includes the design of the entire system in the framework of a collaboration with LTH followed by construction by an external company at the outcome of a new call for tender. This strategy was approved and the design and prototyping work at LTH has started. The procurement division at ESS was informed of this new initiative and agrees with it. 3)- Feasibility study on pulsed quadrupole magnets A new meeting was held with Elettra to discuss the advancement of their studies. Some progress has been made on the pulsed magnets pre-design. At the time of this meeting, it was agreed that the same kind of work would start on the feasibility studies on the power supplies. It has been agreed with Elettra that a feasibility assessment report should be prepared by Elettra and sent to ESS for distribution to the Technical Board members before the final decision is taken at the next TB to be held on March 5th. Discussions have been engaged with colleagues from the ICS division in order to check for any possible showstopper from the controls and machine protection points of view. 4)- High power laboratory at LTH A decision was made to go ahead with renting the Southern Hall in the M-building of LTH in view of testing the reduced scale modulator prototype with a HV resistive dummy load. A meeting was held with Akademiska Hus to sort out the last technical details and to agree on the next spets in view of writing and signing the contract. Akademiska Hus will prepare the renting contract that will be submitted to the WP10 for the follow up on the formalities from ESS side. 9.1.17 WP99 Accelerator Infrastructure & Installation Accomplishments Held internal review on Klystron Gallery chaired by M. Jensen Klystron Water Task Force finished generating new requirements Dump changed presented to CCB and accepted Stub Chamfer change request at CCB accepted 30(31) Document Template Document Number ESS Monthly Project Status Report Date 2015-02-17 RF Group will use portion of Cold Box Building as klystron acceptance area Hired contractor in Design Division to assist Gallery Layout Issues Lack of verification of AD-SI requirements CF not following agreed on workflow as demonstrated with electrical conduit pipes to tunnel Waste generated in Gallery may be considered activated until proven otherwise Removal of Stub Heating not resolved Current and near Future Variances in Project Plan A30760 Preliminary Integrated installation plan ready by 07-Jan-15 -> 15-Mar2015 NEW A42740 Level 3 integrated installation plan completed by 13-Jan-15 -> 15-Mar2015 NEW A48730 Technical Lab preliminary design accepted complete by 03-Nov-14 -> 03Jun-2015 A33760 Level 3. 3D model of the tunnel complete by 24 Nov-14 -> 24-Jun-2015 A42740 Level 3 Integrated installation Plan complete by 07-Nov-14 -> 07-Jun-2015 A42750 Installation Plan CDR complete by 10-Nov-14 -> 10-Jun-2015 A33780 Cable routing design Gallery complete by 26-Nov-14 -> 26-Jun-2015 A33790 Air Piping routing design tunnel complete by 27-Nov-14 -> 27-Jun-2015 A33750 Preliminary Alignment network lay-up complete by 19-Nov-2014 -> 19-Jun2015 31(31)