Project 043-11 PTSS Conduit & Cabling Specifications as of 2013-07-24 PART 1 GENERAL 1.1 General Requirements .1 Wherever practical and reasonable, all cabinets and electrical boxes shall be installed in the locations shown on the attached floor plans. .2 Drawings show conduit connection requirements. Actual conduit runs shall run parallel to building lines. .3 All conduits shall be EMT unless specified otherwise. .4 All outlet, device and pull boxes shall be steel unless specified otherwise. .5 All conduits shall be sized according to the number of cables in the run. Maximum conduit fill is 50%. .6 All junction boxes (J1, J2, J3, etc.) shall be steel and sized according to the number of conduits they must accommodate. .7 All cables pulled to a 'T' Type cabinet (T1, T2, T3, etc.) shall have no less than 4500mm of cable slack in the ‘T’ cabinet. .8 All cables in a device or outlet box shall have no less than 600mm of cable slack at the device/outlet box. .9 All cables in a cabinet, a device box, a utility box or an outlet box shall be labelled. .10 The contractor shall test all cables for opens, grounds and shorts. The contractor shall replace any cables found to be defective by the owner. file: 26 PART 2 1. 2. 3. - 4. - file: MATERIALS & PRODUCTS Conduit All conduits shall be EMT. Junction, Outlet and Pull Boxes All outlet, device and pull boxes shall be steel. Cable All telephone type (Cat3) cables shall be NORDX D-INSIDE CABLE, 24 AWG, CMR, Category 3 solid copper with a grey jacket (or equivalent). Pull Cord/Tape Polypropylene type, 200 lb tensile strength minimum. 36 PART 3 A1 Junction Box (450H X 450W X 100D) - - - J1 - - Supply and install one 300H X 300W X 100Dmm Type 1 Telephone cabinet, complete with 3/4" wood back, mounted 600mm below suspended ceiling in Room 162 (as per floor plan). Supply and install two structured wiring/data outlets 100mm to the left of the T3 cabinet. Provide Cat5E cabling from wiring/data outlets to patch panel in the LAN Room. Provide patch cords and cross connected from patch panel to data switch. Square Outlet Box - file: Supply and install one junction box above the suspended ceiling. If the ceiling is finished the junction box should be mounted on a wall 100mm below finished ceiling but no higher than 2400mm A.F.F.. Junction box shall be sized according to the number of conduits that must be accommodated. Supply and install conduit, sized to fit cables, from this junction box to the A1 junction box in Room 116 (as per floor plan). “T” Cabinet (300H X 300W X 100D) - 01 Supply and install one surface mounted 450H X 450W X 100Dmm junction box, complete with 3/4" wood back, on the slab above the suspended ceiling. This junction box is to be located at the entrance to Room 116 (as per floor plan) to make it accessible and serviceable. Remove existing 900H x 600W x 150D cabinet in the southeast corner of Room 116 and reroute all the conduit which had terminated in this cabinet to the new 450H X 450W X 100Dmm junction box. Supply and install two 38mm conduits from this junction box to the T3 cabinet in Room 162 (as per floor plan). Supply pull cord in each conduit. Junction Box - T3 EXECUTION Supply and install one 4" square outlet box (2-1/8" deep) c/w blank cover plate 150mm below finished ceiling but no higher than 2400mm A.F.F.. Supply and install conduit from this outlet box to a J1 junction box in the area (as per floor plans). Supply, install and label two 4 pair telephone (Cat3) cables in the conduit from the outlet box to the A1 junction box in Room 116. 46 11 Square Outlet Box - - - 21 Device Box - 41 - file: Supply and install one recessed 100 X 150 X 63mm three gang device box c/w blank cover plate centered 1500mm A.F.F.. Supply and install conduit from this device box to a J1 junction box in the area (as per floor plans). Supply, install and label one 4 pair telephone (Cat3) cable in the conduit from the device box to the A1 junction box in Room 116. Octagon Outlet Box - Supply and have door-frame fabricator spot weld one 100 X 100 X 40mm outlet box on top of the frame as per attached detail drawing “PROTECTED DOOR ELEVATION OF SINGLE DOOR WITH DOOR CONTACT”. Drill a 19mm hole 75mm (center point) from the edge of the door casing to allow for door switch installation and access to frame mounted outlet box. Supply and install conduit from the outlet box in the door frame to a 100 X 50 X 63mm pull box mounted above the door on the protected side of the wall. This pull box shall have a blank cover plate installed and shall be mounted above the suspended ceiling OR 100mm below the ceiling if the ceiling is finished. Supply and install conduit from the pull box to a J1 junction box in the area (as per floor plans). Supply, install and label one 4 pair telephone (Cat3) cable in the conduit from the outlet box in the door frame to the A1 junction box in Room 116. The cable slack at the outlet box in the door frame shall be tucked into the outlet box to protect the cable from damage. Supply and install one 4" octagon outlet box c/w blank cover plate on the ceiling. If ceiling is suspended, the octagon outlet box shall be located 300mm above the suspended ceiling. Supply and install conduit from the outlet box to a J1 junction box in the (as per floor plans). Supply, install and label one 4 pair telephone (Cat3) cable in the conduit from the outlet box to the A1 junction box in Room 116. Note: 1. Supply no less than 3600mm of cable slack at the outlet box. 56 Attachments: file: 1. DETAIL DRAWING - PROTECTED DOOR - ELEVATION OF SINGLE DOOR WITH DOOR CONTACT 2. Project 043-11 - PTSS Floor Plan as of 2013-07-24 66