HF UPGRADE PROJECT

Y. Onel PM

November 26, 2012

1

HF2013 Organization Chart

CMS HF UPGRADE 2012 ORGANIZATION CHART

P.De Barbaro

HCAL PM

Onel

*

HF UPGRADE PM

J. Nachtman

*

/ C. Tully

*

HF FE

HF Production

*

E. Gulmez / G. Alves

QIE 10

T. Shaw, J. Witmore

Calibration Unit

M. Miller, S. Los

Interface, Racks Installation

I. Schmidt

E.Gulmez

*

TR CMS L2 PM

J. Nachtman / C. Tully

HF FE

HF Production

E. Gulmez / G. Alves

QIE 10

T. Shaw, J. Witmore

Calibration Unit

M. Miller, S. Los

Interface, Racks Installation

I. Schmidt

K. Yi

*

HF Trigger

PMT Characterization

Akgun

1.1.2.1.3

T. Yetkin

*

Hf Upgrade Phase II

I. Schmidt

*

HF Integration Engineer

Neuhaus (UI)

Candidate PMT Studies

Jia (UI)

Production Testing Iowa

Funk (UI)

Batch PMT Testing

Tiras (UI)

Speciality Test

Dumanoglu (CU)

Production Testing Adana

Joshi (FNAL)

Database

Corse / Kingston (UI)

Database

Sleeves And Light Guides

*

Winn

1.1.2.1.4

ROBOX Design and Prod.

*

Schmidt

1.1.2.1.6

Kent, Debbins (UI)

Sleeve Mechanics

Cremaldi (Miss)

Scintillation Tests

Akgun (UI)

Radiation Damage

Winn (Fair)

New Sleeve Material

Cremaldi (Miss)

Sleeve Production

Schmidt (UI)

Design

Fountain (UI)

Pre-Production

Fountain (UI)

Production

Debbins (UI) *

Mechanical Testing

Los (FNAL), Neuhaus (UI) *

PMT Base Boards

S. Los (FNAL)

Design

S. Los, M. Miller (UI)

Production / Testing

Bulgarian HV

Sofia Group

Martinez (FIU) *

CAEN HV

S.Tkaczyk/T.Yetkin

*

US CMS L2 PM

G. A. Alves

*

/A.Santoro

*

Brazil CMS L2 PM

PMT Cabling

*

Terry Shaw (FNAL)

1.1.2.1.8

Terry, Shaw (FNAL)

Cable Design

Fermi Tech. TBA

Cable/Connector Test

Fermi Tech TBA

Cable Production

Demo Box, Light Guide Phi3

*

Yetkin

1.1.2.1.8

Installation And Commissioning

*

Mestvirishvili. Conkocak

1.1.2.2

Akgun, Neuhaus (UI)

Iowa Tests

Ferhat, Kaya (TR)

904 Tests

Mestvirishvili, Schmidt (UI) *

Installation in UXC

Sulak (BU-US)

Test Beam

Ozok,Bakirci,Cerci,(TR) *

Test Stands in SX5

Debbins * , Kent (UI) *

TOBOX Tesembly & Test

Cankocak * ,Kaya * (TR)

ROBOX Testing in SX5

HF CERN Team

HF Turkish Team

Fermi Tech TBA

ROBOX Cabling

HF CERN Team

ROBOX Burnin

LS1 General Planning

LS1 HF work consists of PMT replacement, HV PSU installation, and cable installation for FE electronics upgrade.

Most of the activities are off the critical path.

Installation and cabling for new FE electronics may require coordinated work with other subsystems since some space on HF were used for services and cables by them.

We are in close contact with HCAL Technical Coordinator for LS1 scheduling.

3

CABLES

We have our re-quote we have from Winchester. It is for

$370K, which is about $50K over our original estimates. We believe it is a fair quote.

The company is working on the engineering drawings and they will be sending a list of the changes to be implemented which we requested. These are all changes made to protect the cable connectors and contacts and ease the installation.

We are almost ready with the contract and the change order is already signed.

4

Cable Plan

We planned to benefit from LS1 to do as much as possible to prepare HF for the future upgrade (multi-anode readout). During LS1 we target for the following objectives:

Consolidation and clean up of cables and services. (~8 weeks)

Includes removal of existing front end signal cables

Includes the time spent on cables and services from other subsystems.

Modification, preparation of HF structures for cable storage (~2 weeks)

Prepare racks as much as possible for future electronics. (~1 week)

Could be absorbed in consolidation step above (~8 weeks)

New HV Purchase

After considering the recommendation of the CMS HF HV Micro PRR Review, we decided to purchase the CAEN main frame SY4527 model in the first opportunity and if possible by the end of this month or latest during the CERN Pool purchases using the

2012 price list .

We would also like to place an order for A1538D through CERN, even if we cannot do it directly now because there is no list price for the A1538D and the model it is not yet in the CERN-CAEN contract agreement. We will do it through an official CAEN offer for the equipment, and then CERN could negotiate with CAEN the inclusion of the model in the agreement, in a yearly based addendum.

We will initially just buy one for testing, since the CAEN could deliver the first unit by the beginning of next year. We would like to make our request now for this and sign all other agreements with CAEN and CERN Pool as soon as possible. Our current thinking is to get the first A1538 as soon as possible and after testing it to decide between the A1538D only or A1538D+A1511B solution. During the LS1 testing we should be OK using the existing CAEN supplies and/or A1535 units (3.5KV-3mA) since we are not going to test the HF + or - at the same time nor more then 1/2 of the HF+ or - until July 2013 so we have a reasonable time window before we have the final modules in hand.

6

HV Plan

We plan to finish HV power supplies installation by June 1st, 2013 latest

This is based on the estimate that mid May could be the earliest to power the first HF quadrant.

Also based on availability of CAEN PSUs.

Alexi M. and + helper will finish the installation

German M. will commission the new system with existing PVSS.

~1 week to do installation.

~1 week for commissioning.

This planning assumes that the HF HV patch panel and interlock interfaces have been produced, tested, and ready for installation (as well as CAEN

7 system).

HCAL MILESTONES

• HF PMT's are shipped to CERN 10/15/2012

• HF PMT Boards QC testing 100% at Iowa 2/1/2013

• All done, tested and delivered to CERN 2/7/2013

(Corrected a delay for the production of the base and adaptor boards which includes

20% spares. We expect that 216 will be available by January 7 to populate all of the

ROBOXes).

• 25% - at CERN by Oct.31

• 50% - by Nov 15

• 75% - by Jan. 7

• 100% - by Feb. 7

• ( Base boards will be delivered paired with Adapter boards).

8

9

Milestones 2012

HF UPGRADE PROJECT MILESTONS

PMT Testing 50% Complete

Production Readiness Review

Start Date

1/3/2012

1/12/2012

New YETS 2012 ROBOX manufactured, tested and installed in CMS 2/17/2012

New cable purchase decision 2 or 4 channel 7/2/2012

Start of CMS 2012 Shutdown

Equip ROBOX test stands at SX5

HF Plus Moved into Garages

2/11/13

1/25/13

2/25/13

HCAL INTERNAL MILESTONES

New HV system purchase decision

HF PMT characterization and testing 100% done

HF PMT's are shipped to CERN

HF PMT Boards QC testing 100% at Iowa

Start of the HF ROBOXes shipping to CERN

HF PMT's are shipped to CERN

8/15/2012

10/1/2012

10/15/2012

2/7/2013

11/1/2012

10/15/2012

10

Milestones LS1

Production Readiness Review

Equip ROBOX test stands at SX5

Start of CMS 2012 Shutdown

HF Plus ROBOX Reassembly and Testing

HF Plus Integration, Burn-in, and Commissioning

HF’s out in CMS closing sequence

HF Minus ROBOX Reassembly and Testing

Magnet Test

1/12/12

1/25/13

2/11/13

4/16/13

3/1/14

7/10/14

7/30/13

7/30/14

HF Minus Burn-in, and Commissioning 3/1/14

Final closing HF- to nominal position + install Totem T1-z 9/11/14

Bring HF Plus to nominal position 10/12/14

Bring HF Minus to nominal position

CMS ready for Beam

10/19/14

11/5/14

11

Schedule with dates

Bring CMS to full open config.

Install HFs tractions system

Remove HF strain sensor fibers

Open HF+ T2 BSC PLT

12 days

7 days

1 day

1 day

Prepare and Lower HF+ on 3 risers 1 day

Lower HF+ to on two risers 1 day

Lower HF- on two risers

Lower HF+ to ground level

1 day

1 day

Lower HF- to ground level

Move HF+ in garage

Move HF- in garage

Replace HF PMTs

HF+

HF+ burn-in, commissioning

HF-

HF- burn-in, commissioning

Bring HF+ to Nominal Position

Bring HF- to Nominal Position

CMS ready for beam

Mon 2/11/13

Mon 2/11/13

Mon 2/11/13

Mon 2/18/13

Tue 2/19/13

Wed 2/20/13

Thu 2/21/13

Mon 2/25/13

Tue 2/26/13

Tue 2/19/13

Mon 2/11/13

Mon 2/18/13

Tue 2/19/13

Wed 2/20/13

Thu 2/21/13

Mon 2/25/13

1 day

1 day

Mon 2/25/13

Tue 2/26/13

1 day Tue 2/26/13

310 days Mon 2/11/13

Mon 2/25/13

Tue 2/26/13

Tue 2/26/13

Thu 5/1/14

310 days Mon 2/11/13 Thu 5/1/14

44 days Mon 3/3/14 Thu 5/1/14

299 days Tue 2/26/13 Thu 5/1/14

45 days

8 days

9 days

Sat 3/1/14

Wed 10/12/14

Thu 10/19/14

Thu 5/1/14

Fri 10/21/14

Tue 9/31/14

1 day Wed 11/5/14 Wed 11/5/14

12

ROBOX Installation and Commissioning

ROBOX HF118 days Wed 2/27/13 Fri 8/9/13

ROBOX HF- Q1 49 days Wed 2/27/13 Mon 5/6/13

ROBOX HF- Q2 37 days Wed 4/17/13 Thu 6/6/13

Cables HF86 days Fri 4/19/13 Fri 8/16/13

Cables Q1 22 days Fri 4/19/13 Mon 5/20/13

Cables Q2 10 days Fri 5/31/13 Thu 6/13/13

ROBOX HF- Q3 37 days Mon 5/20/13 Tue 7/9/13

ROBOX HF- Q4 37 days Thu 6/20/13 Fri 8/9/13

ROBOX HF+ 106 days Tue 7/23/13 Tue 12/17/13

ROBOX HF+ Q1 37 days Tue 7/23/13 Wed 9/11/13

ROBOX HF+ Q2 37 days Fri 8/23/13 Mon 10/14/13

ROBOX HF+ Q3 37 days Wed 9/25/13 Thu 11/14/13

ROBOX HF+ Q4 37 days Mon 10/28/13 Tue 12/17/13

*Commissioning HF84 days Tue 5/21/13 Fri 9/13/13

*Commissioning HF+ 89 days Thu 9/19/13 Tue 1/21/14

Cables Q3 10 days Wed 7/3/13 Tue 7/16/13

Cables Q4 10 days Mon 8/5/13 Fri 8/16/13

Cables HF+ 79 days Thu 9/5/13 Tue 12/24/13

Cables Q1 10 days Thu 9/5/13 Wed 9/18/13

Cables Q2 10 days Tue 10/8/13 Mon 10/21/13

Cables Q3 10 days Fri 11/8/13 Thu 11/21/13

Cables Q4 10 days Wed 12/11/13 Tue 12/24/13

13

HF Schedule

14

PCB production

12x Jumper base board production/checking jumper board testing

PCB production

Board assembly/testing

Testing and QC at Iowa

First shipment of PCB's to CERN

50% board production done

All done, tested and delivered to CERN

3/1/12 --- 4/15/12

4/15/12 ---5/15/12

5/15/12—6/15/12

6/15/12– 12/1/12

6/30/12 - 7/15/12

7/31/12 (Int. Milestone)

11/15/12 (Int. Milestone)

2/7/13 (Int. Milestone)

SL

SL, IS, AM

SL

SL

MM, JC, DS, ZJ, GF, JK

ZJ

SL

SL

15

Delivery dates at CERN

Set 1 05/15/12

Set 2

Set 3

06/01/12

06/15/12

Set 4

Set 5

Set 6

Set 7

07/01/12

08/01/12

08/14/12

09/01/12

Set 8

09/14/12

PMT's

16

Test stand setup

Test new box ( set-up new ROB)

Produce and assemble test equip

Establish Testing Procedures

Produce Test stand equipment

AM Tests new Box

New ROBOX at 904- operating

Move New ROBOX to SX5

Test Stands at SX5—operating

4/23/12 - 5/15/12

3/31/12 - 6/30/12

4/23/12 - 7/31/12

4/15-6/30

IS, AM

IS, MF, PD, TK

AM, IS, AP

IS, MF, PD, TK

5/15 - 6/7/12

7/31/12 - 8/31/12

1/25/13

2/30/13

AM, HB, EB

AM, IS, AP, GA, YG

AM, IS, AP, GA, YG

AM, IS, AP, GA, YG, SD, YOz, FO,

SS, SC, NB

Adding two students Marcos and Thiago from Brazil.

17

ROB mechanics

Finalize Shield dimensions

All materials ordered

Start shipment to CERN

CERN P5 Setup

HF+ mechanics pre-assembly

ROB Completion Dates

25% completion

50% completion

75% completion

100% completion

Production contingency

04/01/12 - 05/14/12

09/15/12

11/14/12 - 12/01/12?

12/1/12 - 03/01/13

ZJ, ET, GF, JC, JK, DS

Olga, TK, PD, (+2 crews x2)

Olga, TK, PD, (+2 crews x2)

05/01/12 – 06/31/12

07/01/12 - 08/31/12

09/01/12 - 10/31/12

11/01/12 - 12/21/12

12/22/12 - 02/28/13

18

19

Assembly and Testing

Base board population learning/training

07/31/12 - 08/21/12

Populate and test baseboards

HF+ Q1 (27) 08/22/12 - 09/07/12

HF+ Q2 (54) 09/07/12 - 09/22/12

HF+ Q3 (81)

HF+ Q4 (108)

09/22/12 - 10/07/12

10/07/12 - 10/22/12

HF- Q1 (135)

HF- Q2 (162)

HF- Q3 (189)

HF- Q4 (216)

10/22/12 - 11/07/12

11/07/12 - 11/22/12

11/22/12 - 12/07/12

2/07/13 - 2/22/13

AM, IS, DK, MK, OK

AM, IS, FO, EA, MK, OK, EE, OO,

BU, MY, SD, YOz, HO, KD

20

HF Upgrade Participant List

E.Asli Albayrak, Gural Aydin, Huseyin Bahtiyar, Esra Barlas, Kerem Cankocak , Yusuf Gunaydin,

Mithat Kaya , Ozgun Kara , Cemali Kilinc, Ferhat Ozok, Marcos Martins, A.Mestvirishvili, Ozlem

Ozcelik, Umut Sen, Sevgi Tekten, Yavuz Oz, Mete Yucel

Mart-April-May-June July August September October November December

ALEXI M.

MITHAT KAYA

FERHAT OZOK

E.ASLI ALBAYRAK

KEREM CANKOCAK

THIAGO DOS REIS MARTINS

ESRA BARLAS

MARCOS M. JUNIOR

METE YUCEL

CEMALI KILINC

YAVUZ OZ

UMUT SEN

OZLEM OZCELIK

SEVGI TEKTEN

SERCAN SEN

OZLEM KAYA

HUSEYIN BAHTIYAR

OZGUN KARA

Greens are at CERN, yellows are working remotely

21

Low voltage

Power Supply

For Dynodes

Readout system

QIE

Spigot00 Spigot01

VME Create

DCC modules

High voltage

Power Supply

For PMTs(CAEN)

22

Low Voltage Power Supply for Led

High Voltage Splitter

Darkbox_00

Darkbox_01

Baseboard and PMT installation

Darkbox 1 Darkbox 2

6 BaseBoards and 48 PMTs are tested every three days

Several runs are taken for different High Voltages and different intensities

HF Upgrade Twiki side: Detailed informations can be found at https://twiki.cern.ch/twiki/bin/viewauth/CMS/HF_ROBOX_TESTS_904