New Version of SICB - Indico

advertisement
Integration and Installation
Outline:
•
•
Status and overview of activities:
–
Platforms and staircases
–
Muon Filters and beam plugs
–
Support Structures
–
Nacelles
–
Chamber support panels
–
Services
Schedule
February 14, 2006
Comprehensive Review
B. Schmidt
1
Platforms and staircases behind M5 (US-side)
February 14, 2006
Comprehensive Review
B. Schmidt
2
Due to work on cryoline, installation could take place only in October 2005
Platforms and staircases behind M5 (PZ-side)
February 14, 2006
Comprehensive Review
B. Schmidt
Installation scheduled for February 2006
3
Muon Filters and Beam Plugs
Muon Filters:
•
•
•
MF4 was completed in April 2005
Traction systems are installed
Filter on US-side in its final position
Beam Plugs:
•
•
To be delivered in February 2006
Installation scheduled for March 2006
February 14, 2006
Comprehensive Review
B. Schmidt
4
General Support Structure
•
Installation of both towers finished in Nov/Dec 2005
•
Top beams for chamber support
Gas racks
Electronics racks
panels will be mounted this week
February 14, 2006
Comprehensive Review
B. Schmidt
5
Suspended Platforms
• Order placed with ALCLIC (CH)
• Two suspended platforms will be delivered (with CE-certificate) end of
February 2006.
• Acceptance by SC hopefully early March 2006
• Work on their integration
(guiding and suspension) in
the muon system currently
ongoing.
• To speed up installation of
services (cables, gas pipes,
etc.), ordering of a 3rd
platform is foreseen.
February 14, 2006
Comprehensive Review
B. Schmidt
6
Chamber Support Walls
• Production for M4+M5 panels finished,
for M2+M3 ongoing in COSPAL (IT)
• Panels have precision holes for ‘balconies’
• A prototype wall has been extensively
tested in LNF with a load of 1.8tons
• Installation in LHCb from March-May 2006
February 14, 2006
Comprehensive Review
B. Schmidt
7
Chamber Support Walls
Installation sequence for each half station:
•
Lifting tool installation
•
Panel installation
1.
2.
3.
4.
5.
6.
7.
8.
9.
Panel in vertical position
Installation of ~30 ‘balconies’
Fixation of 30m copper braid
Mounting of ~100 cable supports
Panel lifting
Positioning of the following panel
Gluing & riveting
Soldering for electrical safety
Check of ‘balcony’ alignment (with ruler)
-> Less than one working day for each panel:
-> One half-station a week
February 14, 2006
Comprehensive Review
B. Schmidt
8
Services: Cabling
Concept:
Horizontal routing
for cables between
and behind chambers
Confection and testing of cables for
stations M4+M5 ongoing at CERN,
using prototype cables.
-> The rest to be done in Italy.
February 14, 2006
Comprehensive Review
B. Schmidt
9
Services: Gas System
Overall design:
• Described in EDMS document 463077.
• Distribution racks for M2-M5 with 18 ch. manifolds have been installed.
Internal Gas Piping:
• After the ageing test we decided
to connect chambers in parallel
-> Impedance adjustment will be done
using capillaries ( 0.5mm,
2.5cm long)
Gas connector
T-piece with
Copper
Capillary
Lin
e1
Chamber
Rilsan
tube
Distribution box
February 14, 2006
Comprehensive Review
B. Schmidt
10
Services: Cooling
Cooling for FE-boards:
• In order to avoid hot spots close to the beam pipe in M2/M3, air
blowers are foreseen for both sides, providing an airflow of about
400m3/h (enough to remove about 2.5kW of dissipated power by air).
• Distribution principle:
Temperature reduction
due to cooling:
ΔT2,3 ~ 7.5oC
Hoses have 30mm diameter
• Something similar is planned for M1
• Schedule: Blowers for M2-M3 ready for installation in April 2006
February 14, 2006
Comprehensive Review
B. Schmidt
11
Chamber Positioning
• The chambers will be correctly
positioned on the walls (~1mm
precision), using the precise positioning
of chamber supports (‘balconies’) as
starting point.
• The position of each chamber will be
measured with respect to reference
points placed on the border of the half
station support panels by means of a
laser distance meter.
Reference
point
chamber
Chamber fixation
“balcony”
Half station
12
Installation Overview
Schedule:
1.
Refurbishing of zone behind M5 and mounting
of general support structures
Completed by
Feb 2006
2.
Integration of nacelles and guiding system
Feb 2006
3.
Installation chamber support panels US-side:
PZ-side:
On detector cabling, gas piping etc US-side:
PZ-side:
M2-M5 Chamber installation
US-side:
PZ-side:
Installation of M1 station
March 2006
April 2006
April-June 2006
July-Sept 2006
May-August 2006
Sep. 2006 - Jan 2007
Jan-March 2007
4.
5.
6.
February 14, 2006
Comprehensive Review
B. Schmidt
13
Muon System Installation schedule
• Chamber support panels and services will be installed by technicians
of the collaborating institutes
-> 104 man weeks
• Chambers and electronics will be installed and commissioned
by 2 teams of 3-4 people of the muon group -> 220 man weeks
February 14, 2006
Comprehensive Review
B. Schmidt
14
Conclusions
•
Despite the delay caused by the installation/commissioning
of the cryoline, good progress has been made with the
muon system infrastructure in 2005.
•
The schedule for the installation of the M2-M5
infrastructure, services and chambers remains tight and
requires close monitoring.
•
We are aiming at having M2-M5 completed and as much as
possible of M1 installed at the LHC start-up in 2007.
February 14, 2006
Comprehensive Review
B. Schmidt
15
Installation and Maintenance Positions
Old and New Installation scenarios:
February 14, 2006
Comprehensive Review
B. Schmidt
16
Muon System Installation schedule
February 14, 2006
Comprehensive Review
B. Schmidt
17
Muon System Installation schedule
February 14, 2006
Comprehensive Review
B. Schmidt
18
M1 Integration
Status:
•
Work on M1 integration has been resumed in 11/2004
(M2-M5 integration had and has priority)
Issues which have to addressed:
•
•
•
•
•
•
Gantry design and impact on M1
-> done
Constraints from neighbouring detectors -> established
Attachment of M1 on the top
and guiding on the bottom
-> ideas exist
Racks for M1 in the ‘bunker’
-> ok
Cable routing
-> extensive studies required
Cooling issues
-> study has to be resumed
Plans:
•
Solve outstanding issues in 2005.
•February
Implement
infrastructure
for M1B. Schmidt
in 2006
14, 2006
Comprehensive Review
19
M1 Integration
Conceptually could be done this way:
February 14, 2006
It is not easy to fit a cablechain and fixations into the
space available
(1100 cables
each side !)
Comprehensive
Review on
B. Schmidt
20
Download