Integration and Installation Outline: • • Status and overview of activities: – Platforms and staircases – Muon Filters and beam plugs – Support Structures – Nacelles – Chamber support panels – Services Schedule February 14, 2006 Comprehensive Review B. Schmidt 1 Platforms and staircases behind M5 (US-side) February 14, 2006 Comprehensive Review B. Schmidt 2 Due to work on cryoline, installation could take place only in October 2005 Platforms and staircases behind M5 (PZ-side) February 14, 2006 Comprehensive Review B. Schmidt Installation scheduled for February 2006 3 Muon Filters and Beam Plugs Muon Filters: • • • MF4 was completed in April 2005 Traction systems are installed Filter on US-side in its final position Beam Plugs: • • To be delivered in February 2006 Installation scheduled for March 2006 February 14, 2006 Comprehensive Review B. Schmidt 4 General Support Structure • Installation of both towers finished in Nov/Dec 2005 • Top beams for chamber support Gas racks Electronics racks panels will be mounted this week February 14, 2006 Comprehensive Review B. Schmidt 5 Suspended Platforms • Order placed with ALCLIC (CH) • Two suspended platforms will be delivered (with CE-certificate) end of February 2006. • Acceptance by SC hopefully early March 2006 • Work on their integration (guiding and suspension) in the muon system currently ongoing. • To speed up installation of services (cables, gas pipes, etc.), ordering of a 3rd platform is foreseen. February 14, 2006 Comprehensive Review B. Schmidt 6 Chamber Support Walls • Production for M4+M5 panels finished, for M2+M3 ongoing in COSPAL (IT) • Panels have precision holes for ‘balconies’ • A prototype wall has been extensively tested in LNF with a load of 1.8tons • Installation in LHCb from March-May 2006 February 14, 2006 Comprehensive Review B. Schmidt 7 Chamber Support Walls Installation sequence for each half station: • Lifting tool installation • Panel installation 1. 2. 3. 4. 5. 6. 7. 8. 9. Panel in vertical position Installation of ~30 ‘balconies’ Fixation of 30m copper braid Mounting of ~100 cable supports Panel lifting Positioning of the following panel Gluing & riveting Soldering for electrical safety Check of ‘balcony’ alignment (with ruler) -> Less than one working day for each panel: -> One half-station a week February 14, 2006 Comprehensive Review B. Schmidt 8 Services: Cabling Concept: Horizontal routing for cables between and behind chambers Confection and testing of cables for stations M4+M5 ongoing at CERN, using prototype cables. -> The rest to be done in Italy. February 14, 2006 Comprehensive Review B. Schmidt 9 Services: Gas System Overall design: • Described in EDMS document 463077. • Distribution racks for M2-M5 with 18 ch. manifolds have been installed. Internal Gas Piping: • After the ageing test we decided to connect chambers in parallel -> Impedance adjustment will be done using capillaries ( 0.5mm, 2.5cm long) Gas connector T-piece with Copper Capillary Lin e1 Chamber Rilsan tube Distribution box February 14, 2006 Comprehensive Review B. Schmidt 10 Services: Cooling Cooling for FE-boards: • In order to avoid hot spots close to the beam pipe in M2/M3, air blowers are foreseen for both sides, providing an airflow of about 400m3/h (enough to remove about 2.5kW of dissipated power by air). • Distribution principle: Temperature reduction due to cooling: ΔT2,3 ~ 7.5oC Hoses have 30mm diameter • Something similar is planned for M1 • Schedule: Blowers for M2-M3 ready for installation in April 2006 February 14, 2006 Comprehensive Review B. Schmidt 11 Chamber Positioning • The chambers will be correctly positioned on the walls (~1mm precision), using the precise positioning of chamber supports (‘balconies’) as starting point. • The position of each chamber will be measured with respect to reference points placed on the border of the half station support panels by means of a laser distance meter. Reference point chamber Chamber fixation “balcony” Half station 12 Installation Overview Schedule: 1. Refurbishing of zone behind M5 and mounting of general support structures Completed by Feb 2006 2. Integration of nacelles and guiding system Feb 2006 3. Installation chamber support panels US-side: PZ-side: On detector cabling, gas piping etc US-side: PZ-side: M2-M5 Chamber installation US-side: PZ-side: Installation of M1 station March 2006 April 2006 April-June 2006 July-Sept 2006 May-August 2006 Sep. 2006 - Jan 2007 Jan-March 2007 4. 5. 6. February 14, 2006 Comprehensive Review B. Schmidt 13 Muon System Installation schedule • Chamber support panels and services will be installed by technicians of the collaborating institutes -> 104 man weeks • Chambers and electronics will be installed and commissioned by 2 teams of 3-4 people of the muon group -> 220 man weeks February 14, 2006 Comprehensive Review B. Schmidt 14 Conclusions • Despite the delay caused by the installation/commissioning of the cryoline, good progress has been made with the muon system infrastructure in 2005. • The schedule for the installation of the M2-M5 infrastructure, services and chambers remains tight and requires close monitoring. • We are aiming at having M2-M5 completed and as much as possible of M1 installed at the LHC start-up in 2007. February 14, 2006 Comprehensive Review B. Schmidt 15 Installation and Maintenance Positions Old and New Installation scenarios: February 14, 2006 Comprehensive Review B. Schmidt 16 Muon System Installation schedule February 14, 2006 Comprehensive Review B. Schmidt 17 Muon System Installation schedule February 14, 2006 Comprehensive Review B. Schmidt 18 M1 Integration Status: • Work on M1 integration has been resumed in 11/2004 (M2-M5 integration had and has priority) Issues which have to addressed: • • • • • • Gantry design and impact on M1 -> done Constraints from neighbouring detectors -> established Attachment of M1 on the top and guiding on the bottom -> ideas exist Racks for M1 in the ‘bunker’ -> ok Cable routing -> extensive studies required Cooling issues -> study has to be resumed Plans: • Solve outstanding issues in 2005. •February Implement infrastructure for M1B. Schmidt in 2006 14, 2006 Comprehensive Review 19 M1 Integration Conceptually could be done this way: February 14, 2006 It is not easy to fit a cablechain and fixations into the space available (1100 cables each side !) Comprehensive Review on B. Schmidt 20