FAR Part 36.ppt

advertisement
FAR Part 36
Construction and Architect-Engineer
Contracts
36.000 – Scope of Part
This part pertains to policies and procedures peculiar to
contracting for construction and A-E Services. Certain
clauses and forms also apply to contracts for
dismantling, demolition, or removal of improvements
1
Subpart 36.1 – General
36.101 - Applicability
•For acquisition of construction and A-E services, Part 36 shall take
precedence if there are any inconsistencies with a requirement in
another part of the FAR; otherwise, other parts of the FAR shall be
followed when applicable.
•FAR Subpart 22.4, Labor Standards for Contracts involving
Construction discusses the applicability of Davis-Bacon Act wage
determinations in construction and non-construction contracts
involving some construction work.
•For “mixed” contracts (those involving both construction, services
or supply), contract clauses for the predominant part of work are
included; however, if contract is divisible, clauses for each type
(construction, services or supply) are included in contract.
2
36.102 – Definitions
Contract: construction or A-Engineer services
Design: defining the construction requirement including architectural,
environmental, structural, electrical, mechanical, and fire protection systems, etc;
producing the technical specifications and drawings, and preparing the
construction cost estimate
Design-bid-build: traditional acquisition method with design completed first under
one contract followed by construction completed under a different contract--two
contracts and two contractors
Design-build: one contract with one prime contractor wherein both design and
construction are included in the work scope. Considered to be a construction
contract
Firm: A-E contracts--any individual, partnership, corporation, or other legal entity
permitted by law to practice the professions of architecture or engineering
Plans and specifications: drawings, specifications, and other data related to the
construction activity
Record drawings: drawings prepared by the contractor reflecting the actual
construction once it has been completed under the contract
Two-phase design-build selection procedures: type of “down-select” procedure
(Subpart
12/18/201236.3)
3
36.103 – Methods of Contracting
•Sealed bid procedures are used for construction contracting if the
conditions in FAR 6.401(a) apply which generally means if award is to
be made on the basis of low price; discussions with offerors will not
be necessary; and expectations of more than 1 sealed bid will be
received.
•A-E services are acquired by negotiation (as opposed to sealed-bid)
in accordance with Subpart 36.6 and agency regulations (DFARS,
etc).
4
36.104 – Policy
•Generally, if not using “design-bid-build” procedures, two-phase
selection procedures must be used (see Subpart 36.3) when
entering into one contract for the design and construction of a
facility.
•Agencies are required to implement sustainable building design,
construction, renovation, repair, etc. to minimize consumption of
energy, water, and materials; reduce pollution and waste materials
from demolition, etc.
5
36.201 – Evaluation of Contractor Performance
Past performance evaluations for construction contracts is IAW FAR
42. 1502(e)--required for construction contracts ≥ $650k and in
cases of T4D.
36.202 – Specifications
•Construction specifications shall conform to the requirements in
FAR Part 11 (Describing Agency Needs).
•As much as possible, references in specifications should be to
widely recognized standards or specifications.
•When “brand name or equal” descriptions are necessary, the
essential characteristics/functions of the brand-name items must be
identified.
6
36.203 -- Government Estimate of Construction Costs
•CO shall receive an Independent Government estimate (IGE) for
each proposed contract and modification > the simplified acquisition
threshold ($150k).
•Generally IGE is only disclosed to Federal Government personnel
with a “need to know”.
7
36.204 -- Disclosure of the Magnitude of Construction
Projects
Solicitations shall state the magnitude of construction based on an
estimated price range. The following are the price ranges that are to
be used (agency-specific regulations may allow more concise ranges
at the upper level)
Less than $25,000
Between $25,000 and $100,000
Between $100,000 and $250,000
Between $250,000 and $500,000
Between $500,000 and $1,000,000
Between $1,000,000 and $5,000,000
Between $5,000,000 and $10,000,000
More than $10,000,000
8
36.206 -- Liquidated Damages
A determination must be made whether a liquidated damages
clause will be used in the construction contract. If utilized, the LD
rate is based on an estimated daily cost to the government caused
by contractor delay and may not be punitive in nature. Includes cost
for additional Government inspection; renting substitute property;
etc.
9
36.207 -- Pricing Fixed-Price Construction Contracts
•Generally, contracts shall be firm-fixed-price. They may be priced –
On a lump-sum basis for the total work performed;
On a unit-price basis for a specified quantity of work; or
A combination of the two methods.
•Lump-sum pricing is preferred method except –
when work involves a significant amount of excavation or
grading;
Work is difficult for offerors to quantify to develop adequate
estimates and could result in contractors “padding” proposed
price to cover themselves.
10
36.209 -- Construction Contracts With A-E Firms
Cannot award a construction contract to the firm that designed the
project unless approved by agency head.
36.210 -- Inspection of Site and Examination of Data
•Offerors should be allowed to inspect the work site and have access
to data regarding work to be performed, such as boring samples and
boring logs. The solicitation typically identifies time and place of an
organized site visit to allow all offerors to inspect the site in the
same manner.
•A record should be kept of the identity and affiliation of all offerors’
representatives who inspected the site or examined the data.
11
36.212 -- Preconstruction Orientation
•CO will provide the successful offeror information including –
labor standards requirements (FAR subpart 22.4):
Davis-Bacon Act--includes DOL wage determination)
Copeland (Anti-kick back) Act—unlawful to coerce
construction employee to give up part of his pay as a
condition of employment or for personal safety
Contract Work Hours and Safety Standards Act—paid
1 ½ times hourly rate for work in excess of 40
hours/week
12
36.212 -- Preconstruction Orientation (continued)
•CO will provide the successful offeror additional information
including –
subcontracting plan requirements (FAR Subpart 19.7)—
large businesses must submit subcontracting plan for
contract value > $1.5M.
Identity of federal staff who are significant for contract
performance
Other information that will facilitate the success of the
contract
•Good idea to provide this information in a preconstruction
conference for face-to-face contact and to require inclusion of
critical subcontractors.
13
36.213 -- Special Procedures for Sealed Bidding in
Construction Contracting
36.213-1 -- General
Use FAR Part 14 procedures for sealed bidding as modified by
this subpart.
36.213-2 -- Presolicitation Notices
•Issue presolicitation notices for requirements > simplified
acquisition threshold ($150k) prior to issuance of the invitation
for bid so that the greatest number of prospective bidders are
informed.
14
36.213-2 -- Presolicitation Notices (continued)
•Presolicitation notice (synopsis) must be publicized at
http://www.fedbizopps.gov for a minimum of 15 calendar
days prior to issuance of the IFB and include
Brief description of the proposed work and
performance period
Estimated price range (e.g., between $1M -$5M)
Location of the construction work
Date when IFB will be issued and bid opening date
Whether award is set aside for small businesses
Cost, if any for solicitation documents
15
36.213-3 -- Invitations for Bids
•The period of time between the issuance of solicitation and
the date set for bid opening shall be sufficient to allow for bid
preparation which includes site inspection; examining data
concerning the work; understanding the plans and
specifications; obtaining subcontract bids; and actual
calculation of bid amount based on plans and specifications.
•FAR 14.202-1: agencies shall allow at least a 30-calendar day
response time for receipt of bids from the date of issuance of a
solicitation if >$150k.
16
36.213-3 -- Invitations for Bids (continued)
• Invitations for bids (solicitation) shall be prepared either in
accordance with the Uniform Contract Format identified at FAR
Subpart 14.2 or alternative format.
•IFB includes
Applicable Davis Bacon wage determination
Performance of Work by the Contractor clause (52.236-1)
identifying % of work contractor must perform with its own
forces (usually ≥ 12%); however 52.219-14 prescribes ≥ 15%
for SB Set Aside
Magnitude of the proposed construction project
Period of performance – usually expressed in # of calendar
days.
17
36.213-3 -- Invitations for Bids (continued)
• IFB also includes
How bidders may inspect the site; examine boring logs, etc
Identification of any government furnished utilities, office
space at the construction site, etc
Pre-bid conference information, if any
Special responsibility or experience requirements
18
36.213-4 -- Notice of Award
The notice of award to the successful bidder shall –
Identify the IFB number
Identify the contractor’s bid amount
State the award price
Identify date when payment and performance bonds must
be provided to the CO
Specify when work is to commence or alternatively when
NTP will be issued
19
36.214 -- Special Procedures for Price Negotiation in
Construction Contracting
•FAR Part 15 applies when negotiating prices (RFP vs. IFB)
•Additionally (as supplemented in Part 36):
•Proposals shall be compared to the IGE
 When an element of proposed cost differs significantly
from the IGE, offeror may be required to submit cost
information concerning that element (e.g., wage rates,
significant materials or equipment and subcontractor
costs).
 When proposed price is significantly lower than the
IGE, CO shall ensure both the offeror and the
Government estimator understand the scope of work.
20
36.214 -- Special Procedures for Price Negotiation in
Construction Contracting (Continued)
•When appropriate, in addition to comparison to IGE, proposed
prices may be compared to current prices for similar types of
work, adjusted for differences in the work site and the
specifications. Parametric estimating can also be used such as
cost per linear foot for utilities, and cost per cubic yard for
excavation or concrete.
21
36.215 -- Special Procedure for Cost-Reimbursement
Contracts for Construction
Cost-reimbursement contracts to acquire construction may
only be used when consistent with FAR Subpart 16.3 and Part
15.404-4(c)(4)(i) fee limitations. Subpart 16.3 only allows a CR
type contract when requirement cannot be sufficiently defined
to allow for fixed-price contract or uncertainties in contract
performance prevent construction costs to be estimated with
sufficient accuracy to use a FP contract.
22
Subpart 36.3 – Two-Phase Design-Build Selection
Procedures
36.300 – Scope of Subpart
This part prescribes policies and procedures for use of twophase design-build selection procedures for both military and
civilian agencies (Agencies can also supplement this
information)
This is a competitive negotiated procurement in accordance
with FAR Part 15; not an IFB under FAR Part 14
23
36.301 -- Use of Two-Phase Design-Build Selection Procedures
Two-phase D-B selection procedures shall be used if:
1. 3 or more offers are anticipated
2. Design work must be performed by offerors before developing price proposals,
and offerors will incur a substantial amount of expense in preparing offers
3. Other considerations:
• Extent to which the project requirements have been adequately defined
• The time constraints for delivery of the project
• Capability/experience of potential contractors
• Suitability of the project for use of the two-phase selection method
• Capability of the agency to manage the two-phase selection process
• Any agency specific considerations
24
36.302 -- Scope of Work
A scope of work is developed that defines the project and
states the Government’s requirements. The scope may include
preliminary design, budget parameters, schedule, etc.
36.303 – Procedures
Either
•One solicitation may be issued covering both phases, or
•Two solicitations may be issued in sequence (one solicitation
for each phase).
•Phase One is a “down-select” process--proposals are
evaluated to determine which offerors may submit proposals
for Phase Two resulting in the award of one contract.
25
36.303-1 -- Phase One of the Solicitation
•Includes:
(1) The scope of work;
(2) The Phase-One evaluation factors, including -•Technical approach (but not detailed design or technical information);
•Technical qualifications, such as -• Specialized experience and technical competence;
• Capability to perform;
• Past performance of the offeror’s team (including the A-E and
construction members); and
• Other appropriate factors (excluding cost or price related factors,
which are not permitted in Phase One);
(3) Phase-Two evaluation factors (see below); and
(4) A statement of the maximum number of offerors that will be selected to
submit Phase-Two proposals. The maximum number shall not exceed 5 unless a
greater number is considered in the Government’s interest.
26
36.303-1 -- Phase One of the Solicitation (continued)
•After Phase One evaluation of the proposals is complete, CO selects the most
highly qualified offerors (not to exceed the maximum number specified in the
solicitation). These offerors are notified to submit Phase-Two proposals.
36.303-2 -- Phase Two
Phase Two of the solicitation
•is prepared in accordance with FAR Part 15
•includes Phase-Two evaluation factors, developed in accordance with FAR
PART 15.304 such as proposed technical solutions/design concepts,
management approach and key personnel
•Requires submission of technical and price proposals, which shall be
evaluated in accordance with FAR Part 15 which is very comprehensive.
27
Subpart 36.5 -- Contract Clauses
36.500 -- Scope of Subpart
Prescribes clauses for insertion in solicitations and contracts for
•construction and
•dismantling, demolition, or removal of improvements
contracts
Other provisions and clauses prescribed elsewhere in the FAR
shall also be used when applicable
FAR 52.236-1, Performance of Work by the Contractor
FAR 36.236-2, Differing Site Conditions
28
Subpart 36.5 -- Contract Clauses
FAR 52.236-3, Site Investigation and Conditions Affecting the Work
FAR 52.236-4, Physical Data
.
FAR 52.236-5, Material and Workmanship
FAR 236-6, Superintendence by the Contractor
FAR 236-7, Permits and Responsibilities
FAR 236-8, Other Contracts
FAR 236-11, Use and Possession Prior to Completion
FAR 236-13, Accident Prevention
29
Subpart 36.5 -- Contract Clauses
FAR 236-15, Schedules for Construction Contracts
Requires contractor to submit a schedule of projected start and completion dates
of salient features of the work (including acquiring materials and equipment).
This is a progress schedule which allows the government to pay against as work
progresses. If contractor falls behind schedule, contractor must get back on track
at its own expense and government may T4D if appropriate.
FAR 236-21, Specifications and Drawings for Construction
If something is mentioned in one document but not the other it will be considered
to be included in both. Specifications govern over drawings if there is a conflict
between the two.
30
Subpart 36.6 -- Architect-Engineer Services
36.601-3 -- Applicable Contracting Procedures
•The A-E contract shall require the A-E to develop designs that provide for
maximum practical use of recovered materials in the construction consistent with
the performance requirements and cost-effectiveness; and consider energy
conservation, pollution prevention, and waste reduction.
•A-E solicitation and selection procedures shall be done in accordance with FAR
36.6 procedures and not Parts 13, 14, and 15.
•If both A-E and other services are being procured in the same solicitation, FAR
36.6 is applicable if, to a dominant extent, the SOW requires performance or
approval by a registered or licensed architect or engineer. If not required,
procedures in FAR Parts 13, 14, or 15 are applicable.
31
36.601-4 – Implementation
A-E services subject to procedures of FAR Part 36.6 are:
•Professional services of an A-E nature, as defined by applicable State law and
which must be performed or approved by a registered architect or engineer.
•A-E services associated with design or construction of real property.
•Other professional services of an A-E nature or incidental services (including
studies, investigations, surveying and mapping, soils engineering, drawing
reviews, preparation of operating and maintenance manuals, etc) that logically
require performance by registered architects or engineers or their employees.
•Professional surveying and mapping services of an A-E nature. Surveying is
always considered to be an A-E service. Mapping associated with design,
construction, or alteration of real property is A-E service. Mapping not connected
to traditionally understood A-E activities are not subject to FAR 36.6 and fall under
Parts 13, 14, and 15.
32
36.602 -- Selection of Firms for Architect-Engineer Contracts
36.602-1 -- Selection Criteria
•A-E firms are evaluated in terms of:
•Professional qualifications for performance of the contracted services;
•Related specialized experience and technical competence;
•Capacity to accomplish the work in the required time;
•Past performance related to cost control, quality, and schedule compliance;
•Location in the general geographical area of the project and knowledge of
the locality of the project; and
•Acceptability under other appropriate evaluation criteria.
33
36.602-2 -- Evaluation Boards
•A-E evaluation boards are to be composed of members who, collectively, have
experience in architecture, engineering, construction, and Government. Board
members are appointed from among highly qualified professional federal
employees and, private practitioners of architecture and engineering, if
authorized by agency procedure. Chairperson must be a federal employee.
•A-E firm is not eligible for award if any of its employees are part of the evaluation
board.
34
36.602-3 -- Evaluation Board Functions
•Reviews the current data files on eligible firms and responses received to a public
notice concerning the particular project
•Evaluates the firms in accordance with the selection criteria
•Holds discussions with at least 3 of the most highly qualified firms regarding
concepts and the relative utility of alternative methods of furnishing the required
services
•Prepares a selection report for the Selection Authority recommending, in order
of preference, at least 3 firms that are considered to be the most highly qualified
to perform the required services. The report includes information regarding the
considerations upon which the recommendations are based.
35
36.602-4 --Selection Authority
•Selection decision made by agency head or a designated selection authority
•The SA reviews the board’s report and makes the final selection which is a listing,
in order of preference, of the firms considered most highly qualified to perform
the work. If the SA selects a different firm on the list as the most preferred which
differs from the one identified from the board, then the SA has to document his
rationale for the contract file.
•All firms on the final selection list are considered to be “selected firms” with
which the CO can negotiate for contract award.
36
36.602-5 -- Short Selection Process for Contracts Not to
Exceed the Simplified Acquisition Threshold
2 short processes that can be used (otherwise the previous described process
shall be used):
1.) Selection by the board. Selection board follows procedures at 36.602-3, and
there is no separate Selection Authority. The board’s selection report contains the
final selection list that is provided to CO which serves to authorize the CO to
commence negotiations.
2.) Selection by the chairperson of the board. The chairperson of the board
performs the evaluation functions at 36.602-3 which includes preparation of the
report. The SA reviews and approves the report. CO utilizes the approved report
as authorization to commence negotiations.
37
36.603 -- Collecting Data on and Appraising Firms
Qualifications
•Agencies shall receive and maintain data on firms wishing to be considered for
Government contracts.
•A-E firm must file with the appropriate agency office SF 330, “Architect-Engineer
Qualifications,” Part II (General Qualifications), and when applicable, the SF 330,
Part I (Contract Specific Qualifications).
•The agency office shall maintain an A-E qualifications data file. Based on the
information in the SF 330s, each firm shall be classified with respect to -(1) Location;
(2) Specialized experience;
(3) Professional capabilities; and
(4) Capacity, with respect to the scope of work that can be undertaken.
•Agency shall review and updated each file annually based on information
received from the A-E firms including contracts they have been awarded.
38
36.604 -- Performance Evaluation
Past performance evaluations shall be prepared for each A-E contract ≥ $30,000
or each that has been subject to T4D.
36.605 -- Government Cost Estimate for Architect-Engineer
Work
•Independent Government estimate (IGE) required for A-E work expected to
exceed the simplified acquisition threshold ($150k).
•Generally IGE is only disclosed to Federal Government personnel with a “need to
know”.
39
36.606 – Negotiations
•Upon receipt of the final selection of the highest ranked A-E firms based upon
qualifications, the CO can begin negotiations. Negotiations are conducted in
accordance with FAR Part 15 beginning with the most preferred firm in the final
selection.
•This is the first time in the selection process that the A-E firm is asked to submit
a cost proposal.
•If negotiations are unsuccessful, the CO terminates negotiations with the first
firm and proceeds down the list until successful negotiations have occurred.
40
36.607 -- Release of Information on Firm Selection
•Upon receipt of the final selection list of highest ranked firms based on
qualifications, the CO may release only the identity of the highest-ranked A-E firm
with which negotiations will commence. If negotiations are unsuccessful then the
CO may release the identity of the next ranked firm with which negotiations will
occur and so on until negotiations are successful. Once an award is made then
the CO may release award information.
•Debriefings of successful and unsuccessful firms are held after final selection has
taken place and allows release of some but not all the information specified in FAR
Part 15.
41
36.608 -- Liability for Government Costs Resulting From
Design Errors or Deficiencies
•An A-E firm may be liable for Government costs resulting from errors or
deficiencies in designs furnished under its contract. Therefore, when a
modification to a construction contract is required because of an error or
deficiency in the services provided under the associated A-E contract, the
government determines the extent to which the A-E firm may be liable.
•The CO shall issue a demand for payment from the firm if the recoverable cost
will exceed the administrative cost involved.
42
36.609 -- Contract Clauses
FAR 52.236-22, Design Within Funding Limitations
•Clause in A-E contract with a fill-in for associated estimated construction price.
The A-E contractor is required to design the facility that will be constructed such
that the government can award the construction contract at a price that does not
exceed this estimated construction price identified in this clause.
•If the proposed price in response to the construction solicitation exceeds the
construction funding limitation in the A-E contract, the firm must redesign the
project within the funding limitation. The rework is done at no cost to the
government as long as the higher proposed cost of construction is not due to
events beyond the A-E’s control (e.g., increased material costs; government delay
in issuing a construction solicitation).
43
36.609 -- Contract Clauses
FAR 52.236-23, Responsibility of the Architect-Engineer Contractor
A-E contractor is responsible for design errors or deficiencies and is
required to make necessary corrections at no cost to the Government when the
designs, drawings, specifications, or other items or services furnished contain any
errors, deficiencies, or inadequacies.
FAR 52.236-24, Work Oversight in Architect-Engineer Contracts
Work under the contract is subject to the general oversight, direction, and
approval of the CO.
FAR 52.236-25, Requirements for Registration of Designers
Registered architects or engineers are required to prepare or review and approve
the design of architectural, structural, mechanical, electrical, civil, and other
engineering features of the work.
44
Subpart 36.7 – Standard and Optional Forms for Contracting
for Construction, Architect-Engineer Services, and
Dismantling, Demolition, or Removal of Improvements
Identifies standard and optional forms, prescribed and found at FAR Part 53
SF 1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair):
shall be used for construction or dismantling, demolition, or removal of
improvements contracts > simplified acquisition threshold
Optional Form 347, Order for Supplies or Services: may be used for construction
or dismantling, demolition, or removal of improvements contracts that are at or
below the simplified acquisition threshold; or may use SF 1442
Standard Form 252, Architect-Engineer Contract: shall use for award of A-E
Services
45
Download