062 Workplace Standards Tasmania, Department of Justice Tasmania Draft model WHS Third Set Codes of Practice - Public Comment Response Form Complete and submit this form by 5PM AEST FRIDAY 22 JUNE 2012 to codes@safeworkaustralia.gov.au 1. Safe Design, Manufacture, Import and Supply of Plant Section/page no. Comment Impacts: Do you anticipate any potential costs or safety benefits of complying with this code that are different to current requirements in your jurisdiction? If so, what are they? 2. Working in the Vicinity of Overhead and Underground Electrical Lines Section/page no. Comment Section 1.4 The section on ‘Safe work method statements’ merely restates the circumstances under which they are required (by the WHS Regulations). We suggest consideration be given to expanding this section by explaining their purpose and role in the context of this type of work, and that safe work method statements be presented as one of the suite of measures that can be considered (together with an explanation of the circumstances under which they are mandated). Section 2.1 on page 9 This section refers to the ‘National Guidelines for Safe Approach Distances to Electrical Apparatus’. It may assist the reader if a cross reference is made to Appendix E, where the full reference is listed. Section 2.1, the dot point between the diagrams on page 10 This dot point refers to ‘… and/or excessive electrical load current passing through the conductors.’ We submit that the use of the word ‘excessive’ is incorrect in this context, as the distribution network service provider (the electricity supply authority) must operate the system within design constraints and ‘excessive’ would be outside such constraints. Alternative wording is suggested, for example, ‘… and/or excessive the changing electrical load current passing through the conductors.’ Section 2.1 page 11 We recommend deletion of the text on ‘Increase to approach distances’. We note that the question of approach distances was raised in the Issues Paper and WST supports Option 1 or 4 (our comments on the options are provided later in this document), neither of which would require this text. Section 2.1 figure 3 page 11 For clarity and ease of application, we recommend pictorial differentiation between poles and towers. Therefore an additional figure is needed to cover towers. For example, see pages 2 and 3 of WST’s document called a Guide to working safely near overhead power lines (GB 137) (available at www.wst.tas.gov.au ) for depictions of poles and towers. Section 2.2, 2.3 and 2.4 These sections should include reference to the 4.0 metre approach distance for metal scaffolding near live electrical lines, as per section 5 and also Table 4 in section 7 (on page 41). We also suggest that Table 4 (where it mentions ‘scaffolding’) include a note cross-referencing the COP on Scaffolding Work. Section 2.4 on pages 13 & 14 The text on ‘About no go zones’ needs to support the requirements in the preceding paragraphs in 2.4. for the electricity supply authority’s written approval. This might be easily covered by rewriting the 1st paragraph on page 14 as follows (changes marked): Page 1 of 7 062 Workplace Standards Tasmania, Department of Justice Tasmania ‘In planning the work, Tto decide the correct no go zone in the circumstances, you should consider contacting the electricity supply authority or owner, and: verify the voltage of the electric line, and verify if it is insulated or bare.’ Then the next line ‘ if you don’t know these facts, you …’ could be removed. This puts preference to making contact with the electricity supply authority, which adds to the safety aspects, as well as notifying electricity supply authority so they can also make a judgement as to whether or not it is safe to perform the work with the lines energised, even though the work may be outside the ‘no go zone’. Section 2.5 The current design envelope in Tasmania covers a 4.3 metre height, not the 4.6 metres as mentioned in this section. There are some exemptions to this under the Vehicle and Traffic (Vehicle Operations) Regulations 2001 and the associated Heavy vehicle general Access Mass and Dimension limits – vehicle information bulletin. This comment is also relevant to the categories of maximum transport height above road in section 8 of this COP, see category 1 page 45. We submit that it is outside the scope of this code of practice to change jurisdictional requirements, which are established by authorities other than WHS Regulators. This need not preclude future consideration, in consultation with appropriate agencies, of whether there are prospects for harmonising this area. Available options for this COP include: listing the requirements in each jurisdiction (perhaps as an appendix); or making a general statement that the design envelope varies across jurisdictions and is generally in the vicinity of 4.3 to 4.6 metres in height (we note that there is more information in Appendix D, which is not referred to in Section 2.5). WST does not support the current approach of merely referring to 4.6 metres in Section 2.5. Section 2.6 We suggest that this section include text that explains that the requirement to ‘ … have successfully completed an appropriate course of training …’ is in addition to the requirements under the Act and Regulations for plant operators to be competent and, in the case of high risk plant, licensed. Similarly there are requirements for safety observers under the Regulations that we recommend be referenced. Section 3 We suggest the number of terms used to refer to plant, especially mobile plant, be rationalised. The COP variously uses ‘crane or operating plant’, ‘crane or other operating plant’, ‘cranes and mobile plant’, ‘crane or other plant’, ‘crane or plant’, ‘crane or item of mobile plant’, and ‘crane, mobile plant, machinery and equipment’, all within the chapter dealing with cranes and mobile plant. Section 3.2 We submit that the risk assessment should be documented and available on site when the work is be performed. Section 3.3 on page 19 We submit that there should be reference to the earthing of the crane, or mobile plant or load etc., when in the authorised person zone, and possibly even outside the zones when working in the vicinity of energised electric lines, whether overhead or underground. This would then link the earthing aspects in the risk assessment to section 3.7 of this COP. Section 4 We suggest the text of the second dot point of the second paragraph be amended as follows (changes shown): Page 2 of 7 062 Workplace Standards Tasmania, Department of Justice Tasmania ‘ a local government work crew (other than those who are authorised persons for clearing of vegetation around electricity supply authority and private owner distribution electric lines and assets) performing vegetation clearing or planting or vegetation treatment’. This emphasises that the owner of the electrical lines or asset has the role of authorising the work around such assets. Section 4.1 The text under ‘unauthorised persons carrying out tree and vegetation management’ is only appropriate for the safe access to voltage up to 132kV, say on poles. The text also needs to cover the safe access no go zone for transmission lines. Additionally, there would need to be a figure showing the work zones for towers (in addition to the diagram showing poles). Section 4.1 Consistent with our response later in this submission to the question in the issues paper on training, we submit that the ‘current competency’ under ‘Authorised persons carrying out tree and vegetation management’, on page 27, be spelt out as being (as a minimum) the UET20312 – Certificate II in ESI – Powerline Vegetation Control, or a person enrolled in that cert II course of training whilst being supervised by a competent person who holds that cert II qualification. Section 4.4 We submit that the text on ‘Minimise the risk’ section on page 29 should include reference to the earthing of mobile plant (as we have also recommended in our comments above on section 3.3). Section 5 We submit that the introduction on page 31 should cross reference the COP on Scaffolding Work for guidance on scaffolding work (in the same way that the Scaffolding Work COP references this COP in section 4.5). Additional examples for inclusion in the introduction to this section could include transportable/movable structures such as grain silos. Section 6 on page 36 Section 7.1 We suggest you include ladders in the list of the examples of handling of metal materials in table 4 on page 41. Section 7.4 We suggest the inclusion of a note on figure 15 stating that insulated matting and tiger tails are only to be installed/fitted by appropriately competent and licensed (where appropriate) persons. Section 8, pages 44, 45, 46 and 47 As mentioned in our comments on Section 2.5, references to a vehicle load height of 4.6 metres does not line up with the 4.3 overall height dimension limits in Tasmania. We acknowledge the note on page 47 that indicates the information in Table 5 pertains to Queensland, and the reference to Appendix D. WST does not support basing Table 5 on a single jurisdiction. Pending any work to harmonise these requirements, and given that the responsibility for these limits does not rest with WHS Regulators, we suggest that, the COP should include appendices detailing the requirements in all jurisdictions (developed in consultation with the responsible agencies in each jurisdiction). On a related issue, we are advised that the term ‘escort vehicle’ is defined in each jurisdiction’s road and traffic legislation. To prevent confusion, we suggest that similar terms of ‘escorting’ and ‘escort service providers’ not be assigned different meanings. We suggest a cross reference to the relevant laws be considered if the scope is sufficiently similar. Section 9 We recommend you add the following examples to the examples of work on page 48: A person drilling or nailing into a wall, where electrical cables are Page 3 of 7 062 Workplace Standards Tasmania, Department of Justice Tasmania installed behind the plaster board or masonry etc. (this is partly covered in the 3rd dot point of the hazard examples of 9.1); A plumber cutting a conductive water pipe that is part of the site’s electrical installation’s earthing system. Section 9 We suggest that consideration be given to including reference to safe approach distances for cables, depending on their voltage, in a similar system to that for overhead electric lines identified in section 2, with no go zones, authorised person zones and unauthorised person zones. Many electricity supply authorities do not allow mechanical excavations within 1 metre of their high voltage cables. The safe approach distances to energised cables is heavily reliant on the type of cable, its location and it’s condition etc. (in Tasmania, the cables range from 110/240/415 volts up to 110kV AC and 400kV DC). Section 9.2 As per our comment on section 3.2, we submit that the risk assessment should be documented and available on site when the work is be performed. Section 9.3 With respect to the reference to digging by hand in the second paragraph we note that this may not be safe either, as crow bars, picks and shovels can cut and expose electrical conductors. We suggest the following modified text to cover this concern (changes shown): ‘… For example, if you cannot determine exactly where an underground cable is, you should dig carefully to use ‘pot holing’ to carefully identify the cable location and avoid accidental damage contact with the cable. This may mean digging only by hand using insulated hand digging tools (appropriate for the voltage concerned) when pot holing, or the use of vacuum pumping in the pot holing process to locate the underground cable/s. …’. Doing this could also remove need for the last sentence in this paragraph, ‘This may mean using hands tools instead of power tools.’ The introduction of the term ‘pot holing’ would be appropriate, as it is an industry identifiable term (and it would be appropriate to add the definition of ‘pot holing’ to appendix A). Appendix A We suggest that a definition of ‘isolated’ be added in Appendix A, as the term is used in 9.3 and elsewhere in the COP; and persons with no industry experience may not understand that ‘isolated’ is not merely de-energised/switched off. Appendix A We have three matters to raise with the definition of ‘Electricity Supply Authority’. The first is that the definition as it stands does not appear to include the transmission of electricity (predominantly on towers) between the Generator and the Distributor (unless ‘distribution’ is read to include ‘transmission’). This could be addressed by adding ‘or transmission’ after ‘distribution’. Secondly we suggest that ‘or network service provider’ be added after ‘network operator’. Thirdly, we note that the definition of ‘electricity supply authority’ in the Model WHS Regulations is subject to a jurisdictional note which requires jurisdictions to insert the relevant person or body into the definition. This means that the definition may possibly be different between the regulations and the COP, and we consider this to be problematic. Cross-referencing to the definition in the regulations may resolve the issue if the scope is the same. However, if it is not (and noting our comment that ‘transmission’ needs to be included), another option will be required. A simple solution may be to use a different term in the code of practice (such as the alternative of ‘network operator’) and include a definition along the lines of: ‘Network operator means a person or body engaged in the distribution or transmission of electricity to the public or in the generation of electricity for supply, directly or indirectly, to the public. An electricity supply authority as Page 4 of 7 062 Workplace Standards Tasmania, Department of Justice Tasmania defined in the Work Health and Safety Regulations is a network operator. A network operator may also be known as a network service provider.’ Page 5 of 7 062 Workplace Standards Tasmania, Department of Justice Tasmania Appendix C Comment on three options posed on pages 8 and 9 of the Issues Paper We submit that the word ‘shall’ in the first sentence should be replaced with ‘should’ because it is not relating to a legislative requirement. We submit that words to the effect of ‘only if it is safe to do so’ be added to the beginning of the first dot point on page 56. 1. Option 1: WST conditionally supports this option, subject to Tasmania’s electricity supply authorities raising no safety concerns regarding a reduction of the distance applicable to lines greater than 132kV (and up to 330kV) from 8 metres to 6.4 metres. This option is consistent with AS 2550.5 – 2002, and aligns the distances to voltages that are expressed numerically. By way of background, in Tasmania, a number of electricity supply bodies utilise the ‘no go zones’ published by Workplace Standards Tasmania (available at www.wst.tas.gov.au in publication no. GB137, page 2 & 3) within which written authorisation to work is required. GB137 accommodates and aligns with the dimensions in option 1, however there are only two specifications: less than 132kV - 3 metres and greater than 132kV - 8 metres. Please note, the maximum nominal operating voltage in Tasmania currently is 220kV (with the exception of the Basslink line which operates at 400kV DC). 2. Option 2. Not supported. Wherever possible, we should seek to have consistency with other standards and codes. 3. Option 3. Not supported. Removal of the table does nothing to advance national harmonisation. 4. Option 4. WST notes that the issues paper does not specify what distances would apply. WST conditionally supports this option, subject to the distances specified. Comment on question posed on training on page9 of the Issues Paper With regard to training and competence requirements for authorised persons to work in the authorised person/no go zones; to provide harmonisation and portability, we submit that this should be; Provided by registered training organisations; Involve the application of not only the ENA NENS 04 document – Safe Approach Distance to Electrical and Mechanical Apparatus, but also i. ENA NENS 03 – National Guidelines for Safe Access to Electrical and Mechanical Apparatus; and ii. The Australian Energy Supply Industry (ESI) Skill Passport, which was an ENA initiative, that is currently being implemented with over 21,000 already issued nationally. To nationally recognised units of competence for endorsed training packages, where appropriate. This should include as a minimum the; i. appropriate high risk licences, as appropriate, ii. appropriate national occupational licence (NOLA) for the type of prescribed work, as appropriate e.g. Electrician, Cable Jointer, Lineworker, Plumber, etc. iii. competence requirements for the work activity, e.g. UET20312 – Certificate II in ESI – Powerline Vegetation Control, for vegetation management, Safety Observer Page 6 of 7 062 Workplace Standards Tasmania, Department of Justice Tasmania training and registration/authorisation, iv. set of Refresher Training Units for the ESI as endorsed under the Transmission, Distribution and Rail Training Package UET11, and v. competence in the application of ENA NENS 03 and ENA NENS 04, as appropriate for the work activity. Impacts: Do you anticipate any potential costs or safety benefits of complying with this code that are different to current requirements in your jurisdiction? If so, what are they? Depending on the distances proposed Option 4 may impose some additional cost on PCBUs in changing existing work practices in working in the vicinity of overhead or electrical lines. We also note the potential for costs if Tasmania were to align with the vehicle load heights specified in Section 8. 3. Traffic Management in Workplaces Section/page no. Comment Impacts: Do you anticipate any potential costs or safety benefits of complying with this code that are different to current requirements in your jurisdiction? If so, what are they? 4. Scaffolding Work Section/page no. Comment Impacts: Do you anticipate any potential costs or safety benefits of complying with this code that are different to current requirements in your jurisdiction? If so, what are they? 5. Formwork and Falsework Section/page no. Comment Impacts: Do you anticipate any potential costs or safety benefits of complying with this code that are different to current requirements in your jurisdiction? If so, what are they? Other comments Page 7 of 7