NEMA / MPRDA AND NWA AMENDMENTS JOINT PRESENTATION ON MINE ENVIRONMENTAL MANAGEMENT 10 SEPTEMBER 2013 1 OUTLINE • • • • • • • • • • 2 • List of Acronyms Purpose of the presentation Problem statement Introduction and Background Agreements Earlier amendments 2011 Agreement Status Quo/ Differences Inter-Departmental Project Implementation Committee (IPIC) MPRDA Bill 2013 NEMA Bill 2013 OUTLINE ...2 • • • • • • 3 Water Legislation Sub-ordinate legislation Joint initiatives by the three Departments Capacity Implications for Implementation Implementation date Additional Amendments required in terms of NEMA Outline 3 Additional Amendments required in terms of NEM:WA Additional Amendments required in terms of MPRDA Concluding Remarks 4 LIST OF ACRONYMS DEAT – Department of Environmental Affairs and Tourism DEA – Department of Environmental Affairs DME – Department of Minerals and Energy DMR – Department of Mineral Resources EA – Environmental Authorisation E&T – Environmental Affairs and Tourism EIA – Environmental Impact Assessment M&E – Minerals and Energy MPRDA – Minerals and Petroleum Resources Development Act 5 LIST OF ACRONYMS ...2 NEMA – National Environmental Management Act SEMA – Specific Environmental Management Act GN – Government Notice GG – Government Gazette 6 PURPOSE OF THE PRESENTATION To inform the Portfolio Committee's on Water and Environmental Affairs and on Mineral Resources on: the history that informed the National Environmental Management Laws Amendment Bill, 2013 and the Mineral and Petroleum Resources Development Amendment Bill, 2013, and the content of the Bills as far as it relates to environmental matters and the progress made on subordinate legislation to date. Report on the work of the three Departments, in line with the agreement on aligning the licensing systems for mine environmental management. The combined approached in line with the work of the Interdepartmental Project Implementation Committee. 7 PROBLEM STATEMENT Environmental aspects of exploration, prospecting, mining and production activities (mining activities) are currently regulated in terms of the MPRDA. Mining activities currently require a mining permit, including an EMPR (DMR) a water use licence (DWA), and, for listed activities occurring in a mining area, an environmental authorisation and/or waste management licence, and/or air emission licence (DEA). Licences may also be required in terms of the ICM Act. These laws have their own process and information requirements and there is currently a lack of integration. 8 INTRODUCTION AND BACKGROUND During the 2002 – 2008 process of amending the Mineral and Petroleum Resources Development Act, an agreement was reached between the Ministers of DEA & DMR, which intended to: • • • The agreement included the: • • • • 9 Adopt an integrated mine environmental management system. Align the MPRDA with NEMA. Repeal of all the mine environmental management provisions, through the MPRD Amendment Act; Transfer of MPRDA environmental provisions to NEMA to create a unified law and system covering environmental impact management; Provision in NEMA for an 18 month window period for the implementation of the environmental provisions relating to mining, prospecting, exploration & production. INTRODUCTION AND BACKGROUND In principle, the 2008 agreement is as follow: One system – prescribed by NEMA Minister of M&E retain mandate as designated competent authority to implement environmental system related to mining and mining areas; Minister of EA&T instated as appeal authority in mining related environmental authorisations – to enable the Minister responsible for the environment to exercise the function of custodian of the environment; Transition from the MPRDA managed system to NEMA 18 months from the date where both the NEMA and MPRDA Amendment Bills are in force. 10 INTRODUCTION AND BACKGROUND ...2 During March & April 2008, the agreement was considered and elaborated in various political fora before being submitted to a joint meeting of the then EA &T and M&E portfolio committees. The agreement was adopted by the joint portfolio committees meeting with the following addition: - After 18 months of implementation, the environmental management function related to mining will, in its entirety, be transferred to the environmental authority. 11 INTRODUCTION AND BACKGROUND ...3 In order to give effect to the agreement, the following legislative and regulatory changes were required: In terms of “one system” The MPRDA was amended by: Repealing all provisions related to environmental management; Making granting of prospecting / mining / reconnaissance applications subject to environmental authorisations (one of the granting conditions); The NEMA was amended by: Inclusion of environmental management provisions of the MPRDA currently not adequately covered by NEMA (e.g. financial provisions for rehabilitation; closure; etc.); Allowing for alignment of processes; Legislate timeframes for the review of environmental authorisations; Result – environmental management regulated by NEMA only. 12 INTRODUCTION AND BACKGROUND ...4 In terms of competent authority - NEMA was amended by: Assigning competence to the Minister of Minerals and Energy for the implementation of the environmental management system (not to formulate environmental policy, regulations, guidelines and norms & standards). Environmental management regulated by NEMA only but, for mining, implemented by DME. In terms of appeal authority - NEMA was amended by: Assigning the Minister of Environmental Affairs and Tourism as the appeal authority for all environmental authorisations that were issued for mining related activities by the Minister of Minerals and Energy. In terms of transition NEMA and MPRDA were amended to provide for transitional arrangements of an 18 month period. Within NEMA, included a provision to transfer the Minister of M&E’s environmental authorisation competence to the Minister of EA&T within 3 years. 13 INTRODUCTION AND BACKGROUND ...5 In terms of the EIA Regulations: Inclusion of content requirements for Environmental Management Programmes and Plans; community consultation; etc (previously in MPRDA); Listing of Mining (exploration, prospecting; mining, and associated activities in Mining areas) Included in Basic Assessment and Scoping and Environmental Impact Report lists to 2010 EIA Regulations Assigning Competent Authority as per NEMA provisions (section 24C) Prescribe an Appeal process 14 LEGISLATION FLOWING FROM THE 2008 AGREEMENT Legislative and Regulatory amendments to give effect to agreement were included in the: National Environmental Management Amendment Act, 2008 (Act No. 62 of 2008) (came into effect on 1 May 2009) Mineral and Petroleum Resources Development Amendment Act, (came into effect on7 June 2013) Environmental Impact Assessment Regulations, 2010 (GN R543, GG 33306, came into effect on 18 June 2010) (Entered into force on 2 August 2010) The activities lists in terms of section 24(2) of NEMA (GN R544, R 545, R546 – GG33306 of 18 June 2010. (Entered into force on 2 August 2010) 15 2011 AGREEMENT Ministers met again during 2011 to further discuss mining related matters and alignment of legislative requirements . A workshop on the amendment of the legislation was held between the Departments of DEA, Water Affairs and Mineral Resources on 26 July 2011. Resulted in an options report to the Ministers. The Ministers preferred option 2: The 2008 agreement without the final transfer of the function to Environmental Affairs Added: Different authorisation processes resulting from the agreement must be preferably integrated, if not possible, aligned Added: a last addition was to pay specific attention to mining in ecologically sensitive areas 16 INTER-DEPARTMENTAL PROJECT IMPLEMENTATION COMMITTEE (IPIC) LEGISLATION PROPOSED OPTIONS OPTION 1 RECOMMENDED OPTION OPTION 2 OPTION 3 17 Move environmental function to DEA. - Posed Constitutional challenges in that it wanted to devolve powers on regulating environmental matters to provinces as they pertain to the mining sector. - Legislative amendments needed to be done on NEMA, NWA and MPRDA. - Disintegrated licensing system. Keep the function at DMR - This will create and integrated and streamlined licensing system. - Legislative amendments required in the MPRDA, NWA and NEMA. -Timeframe alignment with Department of Water Affairs (DWA) on Water Use Licenses (WULs). Leave functions where they are in the three Departments -Legislative amendments are required in NEMA, MPRDA and the NWA. - It will not give effect to a streamlined licensing system. STATUS QUO / DIFFERENCES The current agreement between the three Departments as reflected in the two Amendment Bills currently before Parliament differs from the 2008 agreement in the following respects: The mining related environmental function will not be transferred to the Minister of DEA but implemented by the Minister of DMR in terms of the NEMA, but The Minister of Environmental Affairs will remain the appeal authority for environmental mining activities; The alignment of regulatory processes was added to the scope of the agreement; and Provides for Mining restriction in ecologically sensitive areas 18 STATUS QUO / DIFFERENCES ...2 Mining will be subjected to an Environmental Authorisation process 19 (EIA in terms of NEMA) This will replace the Environmental Management Plan or Programme (EMP or EMPR) process undertaken as a pre-condition for the Mining Permit or Right in terms of the MPRDA and the NEMA process for ancillary listed activities, The NEMA process will be authorised by Minister of DMR (competent authority). The Minister of DMR may appoint Mineral Resource Inspectors, with all the powers of an environmental management inspector to enforce environmental laws as far as it relates to mining. The mining right and mining permit will follow the MPRDA authorisation process and are issued by Minister DMR. The Environmental Authorisation and WUL processes would be triggered by the application for the mining right. Therefore, processes will run in parallel to align and streamline the issuing of various decisions. INTER-DEPARTMENTAL PROJECT IMPLEMENTATION COMMITTEE (IPIC) The IPIC in March 2012 has been tasked to elaborate the technical detail of this agreement. To date the IPIC had 7 meetings. • The IPIC comprises reps from DMR, DEA (and provinces) and DWA; • Task teams have been established; • Appeals and Legislative Amendments TT, • Co-ordinated Timeframes TT, • Capacity TT, • Enforcement TT, • Joint Planning TT, and 20 • Communication TT • INTER-DEPARTMENTAL PROJECT IMPLEMENTATION COMMITTEE (IPIC) ...2 Appeals and Legislative Amendments TT –streamline Acts, regulations and 21 appeals processes; Enforcement TT – enforceability of legislation to ensure greater compliance; Co-ordinated Timeframes TT – time frames and processes between the respective laws; Capacity TT - capacity to ensure effective implementation; Communication TT – developed a comprehensive communication strategy for the project; Joint Planning TT – sharing and co-ordination of spatial information relating to mining, protected areas, world heritage sites and other areas of possible overlaps. MPRDA BILL 2013 In 2010, the “Strategy for Sustainable Growth and Meaningful Transformation of South Africa’s Mining Industry” was adopted; • The Strategy identified amongst others fragmented licensing mechanisms as one of the key binding constraints to the global competitiveness of the industry; • Consequently, Minister of Mineral Resources and Minister Water and Environmental Affairs agreed on modalities to streamline licensing requirements for mining. • This alignment process has been given effect to in the MPRDA Amendment and NEMA Amendment Bills which are currently before Parliament. • 22 NEMA BILL 2013 The main aim of NEMLA Bill is to ensure further alignment between the MPRDA, NEMA, NEMWA, the NEMA Amendment Act, 2008, the MPRDA Amendment Act, 2008 and also to reflect the further agreements reached between the Departments. When considering the amendments, these pieces of legislation must be read together. The NEMLA Bill is summarised as follows: Minister of DMR is the competent authority to issue environmental authorisations on prospecting, mining, exploration or production activity (confined to the area for which the right has been applied for); State Departments will have to provide comments within 30 days on applications for environmental authorisations as opposed to 40 days currently stated in NEMA; 23 NEMA BILL 2013 ...2 The Minister of DMR is empowered to appoint Environmental Mineral Resources Inspectors for the compliance monitoring and enforcement of NEMA and NEMWA in relation to mining activities; The amendments to the National Environmental Management: Waste Act, 2008 (Act. No. 59 of 2008) regulate the management and control of residue deposits and residue stock piles from an environmental perspective, to be implemented by the Minister of Mineral Resources. The amendment to NEMAA provide for a transitional arrangement process on pending environmental related appeals lodged under the MPRDA to be finalised under that Act, and for appeals lodged after the commencement of the NEMLA Bill to be processed in terms of NEMA, as amended. The repeal of section 13 and Schedule to NEMAA to clarify that the environmental management function in mining areas do not transfer the environmental function as far it relates to mining activities to the Department of Environmental Affairs after 36 months. 24 WATER LEGISLATION No amendments are required to the National Water Act with respect to the licensing process. There is a policy process currently under way at DWA. Regulations have been drafted to allow the alignment of permitting systems. The amendments in this regard, do not include timeframes or processes relating to appeals. The NWA will require amendments to address amendments to the appeal process. 25 SUB-ORDINATE LEGISLATION / REGULATIONS Existing environmental impact assessment regulations and listing notices require amendments to The time frames as agreed to between the three Departments. To indicate the Minister of DMR as the competent authority Listed activities for mining Appeal procedures and timeframes The DEA has drafted the amendments. The amendments will be ready for public consultation within the next four months. The regulations need to be in force by 8 December 2014. 26 Proposed Process: S&EIR Process ito NEMA & ICM Act MPRDA Application Accepted (Optional) DWA PROCESS DMR Continues to process MPRDA application BEE Proposal Scoping Report 7 days: Acknowledge 35 days accept or reject 60 days Draft EIR & Draft EMPr 30 days Public Participation 14 days to finalise No substantive changes to Draft Review Committee GENERAL AUTHORISATION OR NWA PROCESS Review Committee GENERAL AUTHORISATION OR NEMAQA PROCESS 60 30 days days AEL PROCESS 7 days : Acknowledge & accept or reject 30 days public participation 10 days for EAP to incorporate PP comments EIR and EMPr Substantive changes to Draft NEMA EA DECISION (20 Days after acceptance of EIR & EMPR) ENVIRONMENTAL AUTHORISATION APPEAL FINALISED (60 – 90 days) APPEAL ON EA DECISION PREREQUISITE FOR MPRDA DECISION Mine Health and Safety DMR Finalises recommend ation for MWP BEE MH&S 7 days Acknowledge 50 days PP if substantially Different form Draft 30 days Accept or Reject 20 days 57 days if Non substantive 107 days if substantive WASTE PROCESS Draft Scoping Report GENERAL AUTHORISATION OR NEMWA PROCESS 14 days + 193 days 42 days 47 days Application WASTE DECISION AEL DECISION WUL DECISION EA, WASTE, AEL and WUL decisions prerequisite for MPRDA decision MPRDA DECISION 250 DAYS (Non- substantive) 300 DAYS (Substantive) Pre-application Proposed Process: BAR Process ito NEMA & ICM MPRDA Application Accepted + Draft EMPr 60 days No substantive changes to Draft Review Committee Substantive changes to Draft WASTE, AEL, DWA PROCESS DMR Continues to process MPRDA application GENERAL AUTHORISATION OR NWA PROCESS 90 DAYS 7 days : Acknowledge + 30 days public participation Final BAR, including Final EMPr BEE Proposal Mine Health and Safety 7 days Acknowledge 50 PP if substantially different from Draft 30 days Accept or Reject 20 days 57 days if Non substantive 107 days if substantive Draft Basic Assessment NEMA EA DECISION (20 Days after acceptance of BAR) ENVIRONMENTAL AUTHORISATION APPEAL FINALISED (60 -90 days) DMR Finalises recommend ation for MWP BEE MH&S Waste, AEL, WUL DECISION EA, Waste, AEL and WUL decision prerequisite for MPRDA decision Appeal on EA decision prerequisite for MPRDA decision MPRDA DECISION 197 Days (Substrantive) + 147 DAYS (Non- substantive) Applicatio n 60 days 30 days Pre-application (Optional) Participation in the Interdepartmental Project Implementation Committee (IPIC) on integrating the licensing systems Joint inspections for compliance monitoring on NWA, MPRDA and NEMA Development of the Mining and Biodiversity Guidelines Consideration of mining and sensitive areas such as World Heritage Sites Implementation of the Inter-Ministerial Committee (IMC) Report on Acid Mine Drainage (AMD) Development of relevant regulations for effective implementation of integrated licensing system Investigation of Consequences and Implications for the alignment of the licensing and 29 regulatory systems and legislative amendments CAPACITY IMPLICATIONS FOR IMPLEMENTATION No. Task Team 1. Capacity 2. 3. 4. 5. 6. SubTotal 30 Workstations & other tools Av. Finance Av. Office Space Av. Av. Av. Av. Av. Av. DWA Av. Av. Av. Av. Av. DMR - - - R 5 000 000 R 5 000 000 DEA - - - R 5 000 000 R 5 000 000 DWA - - - R 5 000 000 R 5 000 000 DMR - - - - R 44 700 000 DEA Av. Av. Av. Av. Av. DWA Av. Av. Av. Av. Av. Appeals and legislative amendments DMR Av. Av. Av. Av. Av. DEA 10 - - - R 3 089 523 DWA Av. Av. Av. Av. Av. Timeframes alignment DMR 69 - - - R 16 200 000 DEA Av. Av. Av. Av. Av. DWA Av. Av. Av. Av. Av. DMR Av. Av. Av. Av. Av. DEA Av. Av. Av. Av. Av. DWA Av. Av. Av. Av. Av. DMR 69 - - R 5 000 000 R 65 900 000 DEA 10 - - R 5 000 000 R 8 089 523 DWA - - - R 5 000 000 79 - - R 15 000 000 R 5 000 000 R 78 989 523 Communication Enforcement Joint planning Grand Total HR Training DMR Av. DEA Av. IMPLEMENTATION DATE The Mineral Petroleum Resources Development Amendment Act, 2008 entered into force on 7 June 2013 and therefore the period of the first 18 month alluded to above already commenced. The two Departments should therefore be ready to implement the legislation by 8 December 2014, which make the NEMLA amendment urgent as it is a section 76 Bill, while the MPRDA amendment Bill is a section 75 Bill. To ensure that the authorisation processes associated with mining are aligned, all four acts (NWA, NEMA/ NEMWA and MPRDA) need to be amended and aligned. The Department of Water Affairs drafted regulations to align the time frames for water use licences in line with the current agreement. The appeals process is different from those of the other two Departments and amendments to the National Water Act, 1998 is required to change the process. 31 Additional legislative amendment s required in terms of the NEMA Section 1 1 32 Issue Review definition of “applicant” – remove (b) because it is superfluous and not correct Proposed text “applicant” means a person who has submitted[-] or who intends to submit an application for an environmental authorisation; [(a) or who intends to submit an application for an environmental authorisation; or (b) an application for an environmental authorisation simultaneously with his or her application for any right or permit in terms of the Mineral and Petroleum Resources Development Act, 2002;] Environmental authorisations - Section 1 of the Principal Act is hereby amended delete latter part “and include a by the substitution for the definition of similar authorisation “environmental authorisation” of the following contemplated in a specific definition: environmental management “environmental authorisation”, when used in Act. Chapter 5, means the authorisation by a competent authority of a listed activity or specified activity in terms of this Act[, and includes a similar authorisation contemplated in a specific environmental management Act]; Additional legislative amendment s required in terms of the NEMA Section 1 33 Issue Proposed text Check definition of “community”. Include “community” interested and affected party definition. Should definition of “community” be amended. “community”─ (a) means any group of persons or a part of such a group who share common interests, and who regard themselves as a community; and (b) in relation environmental matters pertaining to prospecting, mining, exploration, production or related activity on a prospecting, mining, exploration or production area, means an interested and affected party and a group of historically disadvantaged persons with interest or rights in a particular area of land on which the members have or exercise communal rights in terms of an agreement, custom or law: Provided that where as a consequence of the provisions of this Act, negotiations or consultations with the community is required, the community shall include members or part of the community directly affected by prospecting, mining, exploration or production on land occupied by such members or part of the community; Additional legislative amendment s required in terms of the NEMA Section 1 24O(2) 34 Issue Proposed text Regional Mining Remove reference to Regional Mining Development and Development and Environmental Environmental Committee. Committee which is still used in sections 24N and 24O of the Act as it will not play any role in terms of decisions. Replace Department with “(2) The Minister, the Minister of Minerals EAP or insert EAP. and Energy, an MEC [or] identified competent authority or an environmental assessment practitioner must consult with every State department that administers a law relating to a matter affecting the environment when he or she considers an application for an environmental authorisation.” Additional legislative amendment s required in terms of the NEMA Section 43(1A) Issue Proposed text Any person may appeal to the Minister of Environmental Affairs against decision taken by the Minister of Mineral Resources. “(1A) Any person may appeal to the Minister against a decision taken by the Minister of [Minerals and Energy] Mineral Resources or any person acting under a power delegated by the Minister of Mineral Resources in respect of an environmental management programme or environmental authorisation.”. Section 12 of the National Environmental Management Amendment Act, 2008 is hereby amended by the addition of the following subsections: “(8) An environmental management programme or environmental management plan approved in terms of section 39 of the Mineral and Petroleum Resources Development Act, 2002 must be reviewed in terms of the National Environmental Management Act, 1998.”. Review of the Environmental management plan issued in terms of the MPRDA, before 8 December 2013 must be done in terms of NEMA. 35 Additional legislative amendment s required in terms of the NEMA Section 36 Issue Proposed text 43 Allow for categorising of appeals To be drafted 43 Allow for extension of To be drafted regulated appeal time frames on agreement between Ministers 43 Condonation clause: Limit Scope and time frames To be drafted Additional legislative amendment s required in terms of the NEMA Section 28(4), (5), (7), (8), (9) and (12) 37 Issue The Director-General of the Department of Mineral Resources should be given powers to issue a directive in terms of section 28(4). A contravention of a criteria or condition included an instrument adopted in terms of the new s24(5)(bB) included in the National Environmental Laws Second Amendment Bill must be included in offence provisions. Proposed text Clause 12 of NEML Second Amendment Bill: Insert the words “Director General of the Department of Mineral Resources” in section 28(4), (5), (7), (8), (9), (12) of NEMA. Clause 25 of NEML Second Amendment Bill: “(e) fails to comply with a criteria or condition specified by the Minister or MEC in any regulation made under section 24(5)(bB);” Additional legislative amendment s required in terms of the NEMWA Section 79A Issue Proposed text Delegation by Minister of Mineral Resources 79A. Delegation by Minister of Mineral Resources (1) The Minister responsible for mineral resources may delegate a function entrusted to him or her in terms of this Act to(a) the Director-General of the Department of Mineral Resources; or (b) any official or to the holder of a specific post in the Department of Mineral Resources. (2) A delegation in terms of subsection (1)(a) must be in writing; (b) may be made subject to any condition; (c) does not prevent the performance of the function by the Minister of Mineral Resources himself or herself; and (d) may be withdrawn by the Minister of Mineral Resources.”. 38 Additional legislative amendments - NEMWA Section Issue Absence of provision similar to NEML Second Amendment Bill to prohibit the undertaking of activities in specified geographical areas. Proposed text A provision similar to the newly inserted s24(2A) (clause 5(c)) in the National Environmental Management Laws Second Amendment Bill [B 13─2013] should be considered. 43 Amendment to section 43 – Align with 24C amendment. Include activities and the residue stockpiles in the listing notices. Clause 10 of the National Environmental Management Laws Amendment Bill [B 26─2013] amends section 43 to insert subsection (1A) to ensure that the Minister of Mineral Resources continues as licensing authority for those waste management activities involving residue deposits and residue stock piles. The wording proposed for the competent authority in the NEMLA (Mining) and the NEMWA should be the same. Waste information system applies to stock piles. 39 Waste information regulations are applicable to those waste management activities listed in Annexure 1 to the regulations. Mostly is the generators hazardous waste. We may need to give the Minister of Mineral Resources the power/ obligation similar to that of the MEC in s62 of the Act. Additional legislative amendments - NEMAQA Section 40 (3) 40 Issue Alignment of issuing of an Air Emission License with the time frames of the Environmental Authorisation issued by the Minister of Mineral Resources in a mining area Proposed text Where the Minister responsible for Mineral Resources is the competent authority in terms of section 24C of NEMA and an provisional Air Emission License is required in terms of this Act the Licensing Authority must decide the application within the timeframes prescribed in terms of Chapter 5 of NEMA Where the Licensing Authority fails to comply with the prescribed timeframes in terms of Chapter 5 of NEMA the MEC or Minister may intervene Additional legislative amendment s required in terms of the MPRDA Section Issue Proposed text 11 Transfer of MPRDA permit or right may also require amended EA in terms of NEMA. The written consent of the DMR Minister will be for amending the right in terms of MPRDA and the amended EA will be in terms of NEMA. Reference to submission of environmental reports required in terms of Chapter 5 of NEMA within 60 days: prospecting right will require basic assessment in terms of NEMA. No reports are submitted on day 60 in terms of NEMA. The application, draft BAR and draft EMPr are submitted with the application (day 1), and the final BAR and EMPr is submitted on day 90. What should be submitted to DMR on day 60 as required by this section? No wording change required if there is an understanding that an amendment to a right in terms of MPRDA will also require as a prerequisite the obtaining of an amended environmental authorisation. 16(4) 41 (a) to apply for an environmental authorisation and any other authorisation required in terms of a Specific Environmental Management Act and submit relevant environmental reports in terms of Chapter 5 of the National Environmental Management Act, 1998, within the prescribed period.”. Additional legislative amendment s required in terms of the MPRDA 42 Section Issue/Comment Proposed text 17(1) 23(2)(d) 27(6)(b) 75(1)(c) Should read “and an EA has been issued”. The EA being issued must be a pre-requisite before a MPRDA right can be issued – as agreed to by the respective Ministers on 20 August 2013. 17(1)(g) 23(2)(i) 27(6)(f) 80(1)(g) 32(3) How will the ability to comply with this requirement be checked or verified by DMR? “and an environmental authorisation has been issued; and where the environmental authorisation has been appealed, a decision on the appeal has been issued by the Minister of Environmental Affairs”. “the applicant has obtained permission as required in terms of the National Water Act, 1998 (Act No. 36 of 1998).”. Add the words “in terms of Chapter 5 of the National Environmental Management Act, 1998” after the words “environmental authorisation issued”. This section refers to environmental authorisation conditions remaining in place. Is it appropriate to have this in MPRDA as environmental matters should be dealt with in NEMA. Additional legislative amendment as required in terms of the MPRDA Section Issue/Comment Proposed text 43(13) Closure will require environmental authorisation in terms of NEMA. MPDRA must refer to such EA being required. 43 (4) An application for a closure certificate must be made to the Regional Manager in whose region the land in question is situated … and such Regional Manager must notify the applicant in writing to apply for an environmental authorisation in terms of the National Environmental Management Act, 1998, and submit the relevant environmental reports within the prescribed period.”. 43 (13) Insert (d): “No closure certificate may be issued unless an environmental authorisation has been issued in terms of the National Environmental Management Act, 1998.”. 43 Additional legislative amendment as required in terms of the MPRDA Section Issue/Comment Proposed text 56 Why has expiry been deleted? What will happen with the MPRDA right etc. in the instance where the EA which is a prerequisite for MPRDA permits/rights etc. is suspended/withdrawn? This refers to reports required in terms of chapter 5 of NEMA but doesn’t indicate that an EA is required for reconnaissance – this will be listed in terms of NEMA. EA must be prerequisite. The provisions should indicate that NEMA EA application should be lodged after the reconnaissance permit application is accepted by DMR (similar as in other sections). Insert (a): (a) “the environmental authorisation issued in terms of the National Environmental Management Act, 1998, lapses, is withdrawn or is suspended;” 74(4)(a) 44 Replace 74(4)(a) with the following: “(a) to apply for an environmental authorisation and submit relevant environmental reports in terms of Chapter 5 of the National Environmental Management Act, 1998, within the prescribed period.”. Additional legislative amendment as required in terms of the MPRDA Section Issue/Comment Proposed text 79(4)(b) Exploration will require S&EIR in terms of NEMA. Submission of environmental reports in terms of NEMA are submitted on application (application for and draft scoping report) followed by submission of draft EIR and EMPr on day 149 Reference to 120 days not clear what should be submitted to DMR on day 120 Production right requires S&EIR in terms of NEMA – submission of reports on day 1 and day 149. What should be submitted on day 180? to apply for an environmental authorisation and submit relevant environmental reports in terms of Chapter 5 of the National Environmental Management Act, 1998, within the prescribed period.”. 83(4)(b) 45 to apply for an environmental authorisation and submit relevant environmental reports in terms of Chapter 5 of the National Environmental Management Act, 1998, within the prescribed period.”. Additional legislative amendment as Section Issue/Comment Proposed text required in terms of the MPRDA 27(8)(a) If a production right is subject to EA, renewal thereof will also be subject to EA requirement. 27(8) “A mining permit (a) is valid…and may be renewed for three periods each of which may not exceed one year on condition that amended environmental authorisation has been issued”. 85(2) 96(1)(b) 46 Section 96 starts off by saying that this refers to a decision in terms of this Act – meaning the MPRDA. No appeal on a decision issued in terms of the MPRDA will be dealt with in terms of NEMA. Subsection (1)(b) suggests that appeals on MPRDA decisions where the appeal relates to environmental matters will also be considered by the Minister of W&EA in terms of NEMA – which is not correct. 85(2) “(e) Include an amended environmental authorisation.”. Delete 96(1)(b) Additional legislative amendment as required in terms of the MPRDA Section 102(1) 47 Issue/comment The wording suggests that the initial environmental authorisation must be obtained in terms of NEMA but that consent of the DMR Minister is sufficient to obtain an amendment thereof. An amendment of an EA process is prescribed in terms of NEMA. The written consent will be over and above that. Proposed text No wording change required if there is an understanding that an amendment to a right in terms of MPRDA will also require as a prerequisite the obtaining of an amended environmental authorisation. Additional legislative amendment as required in terms of the MPRDA, NEMLA and NWA (if applicable) Section NEW 48 Issue/comment Proposed text Extraordinary clause making To be drafted any future amendments to provisions and regulations of the above acts dealing with environmental management of mining subject to (a) agreement between the affected Ministers and (b) approval by Parliament ADVANTAGES Processes of applications of respective authorisations will run 49 parallel instead of sequential – with sequential decision making. Mining authorisation, water use licence and environmental authorisation will be issued within the allocation timeframes. Another major benefit will be the promotion of compliance through providing and better coordinating the licensing systems. Integrated environmental management promoted. Potential to restrict mining in agreed sensitive areas. CONCLUDING REMARKS Legislative amendments have been effected to both the NEMA and 50 the MPRDA. Work in the different Task Teams of the IPIC is continuing. The three Departments are putting together systems for effective implementation of the integrated permitting system NEMA, NWA and the MPRDA amendment processes are being finalised for implementation of Option 2 of the Matrix. Additional legislative amendments required in terms of DWA, DMR and DEA Acts. THANK YOU 51