Appendix 4: Financial Risk Management: (Inflation) Overview: To develop an understanding of the ways in which financial risk from inflation can be minimized. Summary: A4.1 A4.2 A4.3 A4.4 A4.6 Inflation Risk Management Under Inflation Contingency Escalation Clauses Example of the Index Formula Methods 1 A4.1 Inflation 2 • Inflation can have a significant impact on an international contractor’s profits: – erode value of financial assets (cash in bank, bonds); – pay more for goods than anticipated (estimate x, pay 1.1x); – make financial liabilities more attractive (although often counteracted by high interest rates accompanying high inflation); – example inflation rates between 1980 and 1985: • • • • Argentina: 342.8% per year; Brazil 147.7% per year; Bolivia 569.1% per year; Israel 196.3% per year. • What causes inflation?: – too much money chasing too few goods, that is, demand 3 exceeds supply so prices increase to compensate. • Problems caused for international contractor by inflation: – – – – depreciation/devaluation of local currency; import restrictions; higher borrowing costs; political chaos and labor unrest. • Some approaches to mitigating inflation: – receivables must be collected as soon as possible; – keep idle cash to a minimum; – import materials from countries where prices are stable (although add in additional costs of packaging, shipping, insurance, customs duties..). 4 • Inflation occurs in different areas: – general (throughout the economy); – specific to an industry, for example, a very large project can create a shortage in resources and thus inflation in construction costs and prices: • Taipei 55 mile MRT, • London Docklands Redevelopment. – specific to resources: • high fuel prices due to shortage in oil; 5 • Three basic types of contract pricing (with implications for international contracts operating in an inflationary environment): – fixed-price: • lump-sum: a single sum is agreed in advance; • unit-price: paid a rate agreed in advance (multiply by quantity); – cost-plus contract: • paid for costs incurred plus a fee (usually stipulated limits). • owners, worldwide, prefer the fixed price approach: – if inflation is high, then good to include a a provision for cost escalation (to share inflation risks between parties); – otherwise contractor will include a large contingency to cover inflation; – however, if inflation is high, the cost-plus fee is preferable for a contractor; – even when the risk is passed to the owner, inflation will 6 still impact the contractor elsewhere (overhead, profit). A4.2 Risk Management Under Inflation • Three basic approaches to managing inflation risk in international contracts: – contracting approaches, for example: • cost-plus fee? (as discussed above); • advanced payment arrangements; • add contingency to bid (as discussed above). – construction management approaches, for example: • execute work using inflation prone items as early as possible; • careful purchasing; – countertrade approaches: • payments received in goods or materials (for example: oil). 7 Reducing Impacts of Inflation Construction Management Contracting: risk sharing? YES Countertrade NO Contract on hard currency Cost-plus contract (cost/unit and quantity) Escalation provisions Inflation contingency Advance payment arrangement Documentary proof method (cost/unit not quantity) Index formula method 8 • Reducing risk through construction management: – Planning: • review of cash flows as a defense against surprise; • use an appropriate currency; – Maintaining current information: • update control information with prices, indices and trends; – Payments: • Scrutinize payment schedules (receive early); – Design time (where you offer design as well as construction, or management of both): • expedite engineering to reduce project time; – Innovative contracting: • for example, design-build and fast-tracking allows construction to start before design completed; 9 Design then build (traditional approach): DESIGN CONSTRUCT TIME saving Design-build (eg; turn-key projects): DESIGN CONSTRUCT TIME Fast-track (where project can be phased): DESIGN CONSTRUCT 1 DESIGN DESIGN saving CONSTRUCT 2 CONSTRUCT 3 TIME 10 – Procure certain long-lead times: • identify and purchase items likely to delay the schedule or be in short supply; – Subdivide contracts: • subdividing a large risky contract into several small ones spreads the risk; 11 A4.3 Contingency • Contingency is specific provision for variable elements of cost. • Variable components can be either: – unforeseeable, for example: • ground obstructions in piling operations; – foreseeable, for example: • a prescribed increase in interest rates on a loan; – partially foreseeable: • future inflation rates (note, the further into the future, the more difficult it is to predict). 12 • Factors determining the amount of contingency added: – Magnitude of the Firm: • where there is uncertainty, a bid near the expected cost could result in either a loss or profit; • in such cases, the greater the uncertainty, then the greater the possible loss or profit; • over many projects, the uncertainties will balance out; • large companies, operating many projects, can afford the risk since they can carry losses and survive for the projects where they will make a large profit; • small companies cannot carry a large loss on a project, and so must include a LARGER contingency to minimize this risk; • so small companies will either be taking on a larger risk than large companies, or will have to bid higher; 13 – Estimate Accuracy: • a contractor will add a larger contingency when they are less sure about the accuracy of their bid; • a major determinant of the level of confidence in the accuracy of a bid is the amount of information available for producing the estimate: • overseas contracts can be subject to high levels of uncertainty due to lack of prior experience of prices, delivery efficiency, etc..; 14 – Form of Financing: • Government financed projects are sensitive to cost overruns • reimbursement requires a lot of red tape; • the incentive for a contractor, therefore, is to avoid this problem by including a large contingency; • Joint-ventures (a good approach for international projects) often include lengthy contractual procedures for evaluating cost overruns: • the incentive for a contractor, therefore, is to include a large contingency; • If a project is financed exclusively by internal sources, there is less pressure to make large short term returns, and so contingency tends to be smaller (one-off financiers want a profit this time); – Previous Experience with Inflation: • A contractor working overseas may be working in a high inflation environment: • if this is their first contract in that country, it is possible that they will have little experience of working in a high inflation environment; • in this case, it is likely that they will include a large contingency to cover 15 the uncertainty. A4.4 Escalation Clauses • Many long term contracts contain escalation (fluctuation) clauses to counter the effects of inflation. • It is a clause in a contract which automatically revises the contract price, note: – not applicable to changes in the type and quantity of work (this can be handled in other ways); 16 – is applicable to significant changes in the cost of construction (or significant changes in relevant exchange rates): • • • • • • equipment; material; labor; construction services; taxes; import tariffs; – can be used in fixed price contracts (lump-sum and unit price) (no need for this in cost-plus contracts); – The contract should specify whether prices can adjust DOWN as well as UP (if, say, oil prices fell); – usually only included for contracts that are at least 12 to 18 months in duration, though may be less in countries where inflation is very high. 17 • Advantages (from owners perspective): – significantly removes the need for contingency sums; – savings to owner if prices turn-down; – at least savings to owner if prices do not go up (compared to contingency approach); • Disadvantages (from owners perspective): – price to owner increases with inflation; – little incentive to contractor to keep costs down; – general inflation indices may not reflect increased costs to the contractor; – more owner participation is required to ensure that escalation clauses are appropriate (determination) and to ensure that they properly implemented (verification). 18 • Types of escalation clause: – Day-One-Dollar-One Clauses: • owner pays the difference in increase in cost between the date of the contract and the time of installation; – Significant Increase Clauses: • owner reimburses the difference in cost as before, but only for large increases often expressed as a percentage (risk is shared); – Delay Clauses: • owner reimburses the difference in cost (through inflation), but only increases incurred during a period of delay (the types of delay need to be stipulated, and often the contractor is responsible for the earlier part of any delay). 19 • Two types of method are used for determining Price Escalation: – Index Formula Method: • where refer to some index of inflation: • most governments produce a consumer price index (measure of general inflation); • however, governments may purposefully understate the true rate; • remember, general inflation may not reflect inflation in the type of work you are involved in; – Documentary Proof method: • here the actual costs to the owner are used in the calculation: • this can be more time consuming to compute since it requires a compilation of evidence of both: • the original expected costs of all relevant materials, equipment, labor, etc; • and the actual costs of all relevant materials, equipment, labor, etc. 20 • Index Formula Method in detail: – The method requires agreement on both: • an index to use as a measure of inflation; and • a formula for applying the index to costs: – Indices: • A price index is a statistical measure of changes in price of goods and services; • it is calculated as the ratio of prices at any point in time to prices at a base point in time (and is thus dimensionless); • for example, if the base price of a commodity in the following example is time 1, then: • • • • • time 1 = $532 time 2 = $530 time 3 = $541 time 4 = $547 time 5 = $546 index = 532/532 = 1.00000 index = 530/532 = 0.99624 index = 541/532 = 1.01692 index = 547/532 = 1.02820 index = 546/532 = 1.02632 (deflation) (inflation) (inflation) (deflation) 21 – Two broad types of indices used in escalation clauses are: • price indices (used to revise material costs); and • earnings series (used to revise labor costs). – The US Department of Labor’s Bureau of Labor Statistics publishes several indices used in escalation clauses: • Consumer Price Index; • Producer Price Index; and • Gross Average Hourly Earnings Series. – However, these are only relevant to the USA. – Use appropriate indices from the country in which the product/service etc.. is being purchased: – For example, in the UK, indices applied to escalation include: • RPI ( general inflation); • Building Cost Indices, Tender Price Indices (industry measures); • NED02 (specific work categories). 22 – Note, some countries may produce limited set of indices. – The second factor is the formula in which the indices are applied to costs: • a typical example: • • • • • • • • • • • • • • • P1 = (P0 / 100) · (a + b·M1/M0 + c ·N1/N0 + d ·W1/W0) P1 = price payable; P0 = initial price stipulated in the contract; note, a, b, c, and d specify the proportions of different components; a is the proportion of the price excluded from adjustment; b is the proportion of an index related to one category of materials; c is the proportion of an index related to another category of materials; d is the proportion of an index related to wages; note: a + b + c + d = 100; M1 = current price of comparable materials to category b; M0 = base price (at contract start) of materials in category b; N1 = current price of comparable materials to category c; N0 = base price (at contract start) of materials in category c; W1 = current price of wages; W0 = base price (at contract start) of wages; 23 • Calculate P1 for the following example: • • • • • • • • • • • P0 = $50,000; a = 10%; b = 30%; c = 30%; d = 30%; M1 = $10,600; M0 = $10,000; N1 = $10,800; N0 = 11,000; W1 = 15,000; W0 = 14,000; • Note, if the work is delayed, the contract may stipulate that the indices be calculated before the delay if the delay is the fault of the contractor. 24