Critical Design Report Contents Team Summary ............................................................................................................................................. 5 Introduction .................................................................................................................................................. 6 Changes Made Since PDR.............................................................................................................................. 7 Mission Criteria ............................................................................................................................................. 8 Mission Statement .................................................................................................................................... 8 Mission Requirements .............................................................................................................................. 8 Top Level Requirements ........................................................................................................................... 8 Mission Success Criteria ............................................................................................................................ 9 Critical Mission Milestones ....................................................................................................................... 9 Concept of Operations ................................................................................................................................ 10 Launch ..................................................................................................................................................... 10 Deployment & Stabilization .................................................................................................................... 11 Operations and Deorbit .......................................................................................................................... 11 Satellite Sub-system Design ........................................................................................................................ 12 Structures ................................................................................................................................................ 12 Design Selection .................................................................................................................................. 12 Interfaces ............................................................................................................................................ 14 Load Analysis....................................................................................................................................... 15 TRL ....................................................................................................................................................... 19 Risk Analysis ........................................................................................................................................ 19 Payload.................................................................................................................................................... 19 STK Models for Estimated Impacts...................................................................................................... 19 Final Design ......................................................................................................................................... 21 DRAGONS Units Deployment .............................................................................................................. 26 TRL Advancement Plan........................................................................................................................ 29 Thermal Protection ................................................................................................................................. 30 Aluminum Radiation Shield ................................................................................................................. 30 Multi-Layer Insulation ......................................................................................................................... 31 Safety and Mission Assurance............................................................................................................. 37 Risks Management.............................................................................................................................. 37 Electrical Power System .......................................................................................................................... 37 2 Design Outline ..................................................................................................................................... 38 Power Collection ................................................................................................................................. 38 Energy Storage .................................................................................................................................... 40 Power Conditioning and Distribution .................................................................................................. 40 Power Budget ...................................................................................................................................... 41 Configuration ...................................................................................................................................... 42 Risk Analysis ........................................................................................................................................ 43 Interfaces ............................................................................................................................................ 43 Orbit Attitude Determination and Control ............................................................................................. 43 Design.................................................................................................................................................. 43 Attitude Control................................................................................................................................... 48 Risk Analysis ........................................................................................................................................ 49 Technology Readiness Level ................................................................................................................ 50 Interfaces ............................................................................................................................................ 51 Command and Data Handling ................................................................................................................. 52 Hardware ............................................................................................................................................ 52 Software .............................................................................................................................................. 52 Technology Readiness Level Advancement Plan ................................................................................. 54 Communications ..................................................................................................................................... 54 Design Outline ..................................................................................................................................... 54 Technology Readiness Level ................................................................................................................ 56 Interfaces ............................................................................................................................................ 56 Safety and Mission Assurance............................................................................................................. 57 Final Product ............................................................................................................................................... 58 Operations .................................................................................................................................................. 60 Risk .............................................................................................................................................................. 61 Technology Readiness Level ....................................................................................................................... 66 Verification and Validation ......................................................................................................................... 68 Verification Matrix .................................................................................................................................. 68 System Performance Requirements Flow down Chart ........................................................................... 86 Project Management .................................................................................................................................. 88 Statement of Work ................................................................................................................................. 88 3 Team Structure ....................................................................................................................................... 89 Budget ..................................................................................................................................................... 89 Launch Services ................................................................................................................................... 89 Project Cost ......................................................................................................................................... 90 Mass .................................................................................................................................................... 93 Schedule .................................................................................................................................................. 94 References .................................................................................................................................................. 95 Appendix ..................................................................................................................................................... 97 Acronyms ................................................................................................................................................ 97 Limited Life Items List ............................................................................................................................. 98 Drawings ............................................................................................................................................... 105 EPS..................................................................................................................................................... 105 Payload.............................................................................................................................................. 107 Structures .......................................................................................................................................... 113 Communications ............................................................................................................................... 120 OADC ................................................................................................................................................. 121 Gant Chart ............................................................................................................................................. 125 4 Team Summary Bravo Aerospace Industries 800 SW 5th Ave. Gainesville, FL 32601 Phone: 954-665-6718 Email: lcnianarivera@ufl.edu Project Manager: Chief Systems Engineer: Ian Rivera Radina Dikova Members: Kathleen Hencke Lester Tuck Nicholas Hoffman Brian Lucas Chris Stewart Michael Koester Lee Silvernail Noopur Joshi Maggie Owen Bryan Maynard Joseph Levesque Chris Roda Ryan Barows Paula Pluchino Fred Ouellet Daniel Hugentugler Nathaniel Arias Tony Diaz 5 Introduction Crowding of the earth’s orbital space environment poses serious risks to space missions and creates an unpredictable environment. In 2009, a hypervelocity collision occurred between two satellites, the Iridium 33 and the inactive Cosmos-2251. This collision incapacitated the active Iridium 33 and created thousands of pieces of debris in the process, resulting in an even more hostile space environment. Analysis by both NASA and outside experts indicates that more than half of the Iridium debris will remain in orbit for at least 100 years, and much of the Cosmos debris will remain in orbit for at least twenty to thirty years.1 While the dangers of collisions between two large objects in space such as the Iridium-Cosmos collision may be obvious, there isn’t much knowledge regarding the hazards small space debris (less than 10 cm in diameter) poses. Nicholas Johnson, NASA chief scientist for orbital debris, would argue that small space debris is even more dangerous than large debris (greater than 10 cm in diameter). “The greatest risk to space missions comes from non-trackable debris.” 2 It is clear that small space debris poses some level of danger to spacecraft. This claim is supported by the damage caused to a space shuttle window due to a paint fleck. The damage was substantial enough that the window was replaced. To prevent damage caused by micro meteoroids and orbital debris (MMOD), an understanding of the dangers must be obtained. MMOD characterization allows for improved spacecraft design or maneuvering strategies. Bravo Aerospace Industries (BAI) has developed a comprehensive approach to characterizing this debris. BAI has designed the Bravo Orbital Space Satellite (BOSS) to take in situ measurements of small space debris. The BOSS project will introduce a low cost, yet reliable solution to characterizing MMOD while not contributing to the problem. BOSS has the potential to revolutionize future satellite and spacecraft design and will provide the information necessary to formulate a solution to the space debris problem. The BOSS project is of interest to all entities involved in the space industry. From protecting the International Space Station to ensuring communications satellites’ health, the mission will prove to be vital in the advancement of space technology. Since NASA possesses some of the most expensive equipment in orbit, the BOSS mission is of particular interest to NASA. The BOSS satellite is designed for the advancement of NASA’s technological capabilities, although the project’s implications will impact most space entities. BAI understands the industries’ interest in low earth orbit (LEO) missions. LEO missions are relatively cheap and simple when compared to geostationary orbit (GEO) missions. LEO debris characterization is also of interest since all missions, from LEO missions to Mars missions, must logically travel through LEO. The potential for impact in LEO is also much higher than in GEO due to a higher debris density. For this reason, the BOSS satellite will operate in a LEO environment. 6 NASA currently lacks the technology to assess small space debris with the accuracy that BOSS will be capable of. Impact test based models such as the Satellite Orbital Debris Characterization Impact Test or the NASA-Kyushu University tests have provided some models for small space debris, however these are merely attempts at duplicating unpredictable collisions which is inherently inaccurate. Analysis of test spacecraft such as NASA’s Long Duration Exposure Facility may provide insight into the damage a spacecraft may incur during a mission; however, it provides little information regarding the type of energy associated with different sized debris. Ground based systems such as the European Space Agency’s Space Situational Awareness program or the U.S. Space Surveillance Network are hardly worth mentioning since they are limited to only measuring debris of diameter larger than three millimeters.7 With the use of the innovative Debris Resistive Acoustic Grid Orbital Navy Sensor (DRAGONS) payload, BOSS will be capable of characterizing space debris as small as 50 μm. 5 The DRAGONS payload combines a control and data storage subsystem with an acoustic subsystem and a resistive grid subsystem to create an instrument designed to detect microscopic particles in polar and sunsynchronous orbits.5 Introducing this level of technology into the space environment is necessary and will open the door for further research and development of space materials. It will also increase the accuracy of current space models by allowing them to account for small space debris. Changes Made Since PDR 1. Project Management a. The schedule has been updated to reflect a more accurate time frame for the project. b. The budget has been updated to more accurately represent the cost of the project. 2. Command and Data Handling (C&DH) a. The maximum power consumed by C&DH is now 9W (previously 5W). This is due to the final computer board selection. 3. EPS a. More specific power requirements numbers from other subsystems has resulted in reduced overall power need. b. The solar array has been scaled down by 60% due to higher efficiency and updated power budget figures. c. A smaller capacity battery will be used due to updated power budget figures. d. To guarantee peak power generation, a gimbal has been added to the final solar array design. 4. OADC a. The two star trackers were removed from OADC. The star trackers were deemed unnecessary as the angular velocity and angular acceleration from the IMU provides highly accurate measurements through Kalman Filtering. b. The de-orbit module was changed to NanoSat Terminator Tape from a sail. 5. Structures a. To reduce mass while maintaining structural strength, each of the six side panels supporting the rectangular structure will now consist of an aluminum-honeycomb material as opposed to just aluminum. 7 b. It was also decided to add a shelf in the interior of the satellite in order to aid the assembly of the internal components of the satellite (specifically, the reaction wheels and modified IMU required by OADC). c. The orientation of the frame has been changed to 0.6m x 0.5m x 0.6m (length, width, height) from 0.6m x 0.6m x 0.5m. 6. TPS a. Using a phase change device to distribute heat has been deemed unnecessary. Mission Criteria Mission Statement The debris field in space is a concern for all spacecraft. The particles pose a risk for impact of spacecraft currently in space and are a concern for future spacecraft. This impact risk also poses a threat to the science missions being conducted by these spacecraft. Particles smaller than millimeter in size are non-trackable and can pose a certain risk to spacecraft.8 The BOSS mission is to characterize millimeter or smaller MMOD particles in Earth’s orbit. Insitu measurements from sensors will characterize three components of impact from particles. The three measurements include size of impact, speed of impact and direction of impact. Mission Requirements The BOSS mission has four mission requirements. These four requirements will ensure that BOSS is able to meet the mission demands of the customer. It will ensure the purpose of the mission, and the maximum cost and weight are all clearly stated and met when the satellite is complete. 01.0: BOSS shall characterize the near-Earth debris field of particles up to one millimeter in size. 2.0: BOSS shall characterize debris field using an energy detection method. 03.0: BOSS shall a have a total cost of less than 15 million dollars. 04.0: BOSS shall contain a total mass less than 180 kg. Top Level Requirements The top level requirements indicate how the mission requirements will be met. Each of the eight subsystems of the BOSS mission has a set of requirements that will ensure the mission requirements are met. Payload (05.0) - The payload instruments and sensors shall provide sufficient capabilities for millimeter size debris detection. Bus: Command and Data Handling (C&DH) (06.1) - The C&DH shall successfully collect and process data to be transmitted to the ground station. Bus: Communications (COMM ) (06.2) - The COMM shall successfully transmit “energy data” to ground station. Bus: Electrical Power Systems (EPS) (06.3) - The EPS shall store and distribute adequate power necessary for operation of all components. 8 Bus: Orbit Attitude Determination and Control (OADC) (06.4) - The OADC shall determine the relative position of the spacecraft. - The OADC shall determine motion relative to the Earth. Bus: Structures/Thermal Protection System (TPS) (06.5) - The structure shall maintain integrity and support subsystems throughout the mission life. - The TPS shall maintain satellite and subsystems temperatures within ranges of normal operation. Mission Operations (07.0) - The Mission Operation shall generate a plan which allows for the success of the mission requirements. Launch Vehicle (08.0) - The launch vehicle shall safely deliver BOSS to a 700 km polar orbit. Ground Support System (GSS) (09.0) - The GSS shall be able to downlink and uplink data to the satellite at least once per day. Mission Success Criteria The success of the BOSS mission depends on the ability for the spacecraft to utilize sensors for in-situ measurements of debris particles. There are several aspects which are critical to mission success including ability of BOSS to receive commands, measure impact, and send debris impact measurement data to ground station. The mission success criteria is outlined below. 1. 2. 3. 4. 5. 6. 7. 8. 9. COMM is able to receive commands from ground station. COMM is able to send received commands to C&DH to be sent to Payload. Payload is able to deploy and lock DRAGONS array. OADC is able to position satellite in desired direction for debris impact. DRAGONS are able to collect impact data, including size, speed and direction of impact, for particles of up to one millimeter in size. Payload is able to send impact data of size, speed and direction to C&DH. C&DH is able to send impact data to COMM system. COMM is able to send impact data to the ground station. GSS is able to receive impact data from Satellite. Critical Mission Milestones The BOSS project schedule contains several milestones which are used to assess project management. The following list displays the milestones which are of most interest: Flight Readiness Review (FRR) Launch Initiate De-Orbit Decomissioning Review (DR) Q4 2015 Q2 2016 Q1 2018 Q2 2018 9 Concept of Operations The concept of operations provides an outline for the structure of the mission beginning at and following launch. Figure 1 below provides a graphic representation of the concept of operations, and each portion therein is explained in the following sections. Launch Power Flight Computer, Torque Rods, and Reaction Wheels Detumbling Solar Panel Deployment Deorbit Operations Payload Deployment Systems Check Figure 1- Concept of Operations for the BOSS project Launch BOSS’ operations begin at launch, which is currently scheduled for Q2, 2016. SpaceX’s Falcon 9 rocket has been chosen as the launch vehicle since it is proven and cost effective. Cost analysis and comparisons to similar launch vehicles can be found in the Budget section. There are numerous Falcon 9 missions scheduled for 2016 which allows for flexibility should a launch be canceled or delayed. The Falcon 9 is also regularly launched from Vandenberg. Vandenberg launches provide access to polar orbits (90º inclination) which is the desired inclination since they intersect with all other LEO, thus providing access to space debris located outside of its own orbit. This would ultimately increase the number of collisions, thus fortifying the body of data collected. An altitude of 700 km was chosen since this is the approximate altitude in which the 2007 Chinese Anti-Satellite Missile Test (865 km) and the 2009 Iridium-Cosmos collision (792 km) occurred. These two recent events drastically increased the amount of space debris in orbit and it would be wise to search for debris near these altitudes. More information and analysis regarding orbit selection can be found in the Satellite Subsystem Design section under Payload. 10 Deployment & Stabilization When the launch vehicle has reached the desired altitude of 700 km, BOSS will be deployed. The undeployed solar panel will begin energy generation to power the flight computer, torque rods, and reaction wheels. The torque rods will be responsible for detumbling and stabilizing the satellite by interacting with the Earth’s magnetic field to slow down and eventually stop the satellite from spinning. After stabilization, the reaction wheels will be responsible for controlling the attitude of the satellite and position it in the correct orientation. Following stabilization, the solar panel will deploy for more sufficient energy generation. A full systems check by the on-board computer will follow solar panel deployment. When the satellite’s systems check is complete, the payload, consisting of six DRAGON sensors securely stowed via five hold-down mechanisms, will be deployed through the use of a spring-loaded hinge mechanism. Detailed information justifying the use of six sensors and how deployment works is discussed in the Satellite Subsystem Design section under Payload. Operations and Deorbit The operations phase will follow the deployment of the payload and is planned to last 698 days. During this time BOSS will collect and transmit data via a patch antenna to multiple NASA operated ground stations. The satellite will send payload data and system health information to the NASA ground stations which will relay the information to a central Bravo Aerospace Industries (BAI) facility. BOSS will also be able to receive commands via uplink from any authorized ground station. This is necessary to meet FCC requirements, and allows controllers to override a failing subsystem and to initiate the deorbit phase. After completion of the life cycle, GSS will signal the de-orbiting module to activate. The deorbit module for BOSS will be NanoSat Terminator Tape from Tethers Unlimited. It is a onetime deployable tape that will extend to at least 100 meters. Gravity gradient forces will align the tape with the local vertical direction to be below the satellite. The tape will increase the aerodynamic drag of the system and will generate electromagnetic drag due to passive interactions with the Earth’s magnetic field and ionospheric plasma. There will be two modules mounted by four #4-40 screws on the outside of the spacecraft. The GPS data will determine if the first has deployed. If the first module has malfunctioned, the second module will deploy. The satellite will descend from its 700km orbit in under 10 years satisfying the 25 year requirement. Figure 2 shown below provides 4 different curves at inclination angles of 28.5, 50, 75, and 98.5, with BOSS performing closely to the 98.5 curve (inclination of BOSS is 90 degrees). BOSS will continue to gather data autonomously as long as possible or until re-entry, when the majority of the spacecraft will burn up in the atmosphere. The satellite has not been deemed a threat upon re-entry. 11 Figure 2- De-orbit time versus altitude for a 180kg spacecraft with a 150m Terminator Tape as a function of inclination, for a 17cm wide tape. (from Tether Tapes Unlimited) Satellite Sub-system Design BOSS is composed of seven subsystems, which have been designed to meet their applicable system requirements. Each subsystem’s design is discussed in detail in this section. Additional information (including trade study matrices, detailed drawings, and verification/validation matrices) can be found in the appendix. Structures Design Selection The mission of the structures subsystem is to develop the support and housing of components as well as allow for the deployment and attachment of external components including solar arrays, antennas and sensors. In order to perform this, several design concepts were originally conceived and eventually those options were whittled down to a final design choice. The strength and torsional rigidity of the frame, the thermal expansion of the various structural components, the ability of each design to burn in de-orbit, and the complexity of the designs were measured either quantitatively or qualitatively. Space heritage, the mass and volume of the structure, and the cost and manufacturability of each design option were also taken into consideration. The conclusion was that the best design would be comprised of a 0.6m x 0.5m x 0.6m rectangular frame made of 6061-T6 aluminum alloy with 4 truss-like side webs on the top, bottom, and two opposite sides. The frame and webs would each have a thickness of 2 cm. Honeycombed aluminum side panels with a thickness of 7 mm would surround the frame to 12 protect the internal components of other subsystems from the harsh environments observed in lower earth orbit. These panels were chosen to reduce the mass observed from pure 6061-T6 aluminum panels while simultaneously maintaining the strength of the design. The frame is comprised of 12 rectangular rods which have a 2 cm x 2 cm cross-section. These rods are then welded together (using GTAW welding). The webs are used to support the frame on the top, bottom, front and back sides of the satellite. We chose to use these supports on the top face to support the DRAGONS sensors and on the bottom face to support the solar array and antenna. The webs on the front and back faces of the satellite are in place to aid in attaching several internal components as well as the IMU/reaction wheel shelf. A total of 32 brackets will be manufactured from 6061 T6 aluminum along with 256 M6 x 1.0 , 12 mm long screws to attach the support webs to the frame using threaded holes drilled into the frame. Also, 64 M6 x 1.0, 16 mm long screws will be used to attach the panels to the webs and frame with inserts being used to go through the panels. Pictures of key structural components and a model of the interior of the satellite, without its internal components, can be seen in figures 3-5. Figure 3 – Picture of outer frame of satellite 13 Figure 4 – Picture of web used in satellite structure Figure 5- Internal view of the frame with visible webs and fasteners present. Interfaces A critical component of the structures subsystem involves the numerous interfaces that it has with other subsystems. The structures subsystem was responsible for housing the internal 14 components of each subsystem as well as creating and maintaining a frame that would support deployable or exterior components for each subsystem. Structures will maintain physical interfaces with OADC, Payload, COMMS, EPS, TPS and CD&H. These can all be seen below in table 1. The majority of interfaces are internal. These are the IMU, reaction wheels and torque rods used for OADC; the transmitter and receiver for communications; the lithium battery and PCM/BCM for EPS; 7 internal thermistors (thermal sensors) for TPS and the software used to store data for C&DH. The external interfaces involve the deployment of the DRAGON sensors for payload, sunsensors and the de-orbit module for OADC, the solar array for EPS and a thermal coating layer (MLI) for TPS. Table 1. The different structural interfaces with other subgroups OADC Number of Interfaces 6 Interface (s) Payload 7 DRAGONS sensor deployment mechanism, control/data box supports (one for each individual sensor) Comms 3 EPS 3 Support/attachment for antenna, attachment for the receiver/transmitter Solar Panel deployment mechanism/attachment to frame, lithium battery, PCM/BCM TPS C&DH 8 1 Housing and support for de-orbit modules, gyroscope, reaction wheel, torque rod and external sun sensors MLI coating and internal thermal sensors Computer board housing Load Analysis In performing the loads analysis on the structure of the satellite, a few assumptions were made. First, it was assumed that the analysis was to be performed at launch conditions to show that the satellite could survive launch. Thus, the loads were all assumed to be at 16g. It was also assumed that the bottom of the satellite was to be attached to the fairing of the launch vehicle. Using this fact, it was assumed that the bottom of the satellite was fixed during the analysis. The final assumption is that, while folded during launch, the DRAGONS sensors would have two-thirds of their mass supported by the top panel and web and one-sixth of their mass supported by each of the side panels as the sensors latch onto the sides while folded. In order to perform the analysis, the structure of the satellite was re-created in a single SolidWorks part file to take advantage of its simulation software. In doing this, the key elements of the design were retained but a few finer details (such as some of the screw holes) were suppressed to allow the software to run. Thus the results obtained are not exact but are a good approximation. Then the loads acting on the various parts of the structure of the satellite had to be defined. These were taken to be the loads from the internal and exterior components of the satellite that were 15 supported by the structure (the DRAGONS sensors, solar arrays, reaction wheels, etc.). Table 2 below shows the load breakdown on each of the structural parts. Table 2. Mass/load breakdown for structural load analysis Part Supported Components mcomponent Fload 16mcomponent g Top Panel Front Panel Bottom Panel Back Panel Right Panel Left Panel DRAGON sensors None Solar Array, Antenna De-orbit Modules (2) Sun sensor, DRAGON sensors Sun sensor, DRAGON sensors, Torque Rods (2) 8.46 kg 0 kg 3.504 kg 3.2 kg 2.397 kg 4.049 kg 1327.9 N 0N 550 N 502.3 N 376.23 N 635.53 N Top Web Front Web DRAGONS electronics boxes Transmitter, Receiver, Torque Rod, IMU C&DH computer, EPS Battery and components, Receiver Reaction Wheels Reaction Wheels IMU 1.411 kg 4.051 kg 221.47 kg 636 N 4.07 kg 639 N 2.525 kg 7.575 kg 9 kg 397 N 1189 N 1413 N Bottom Web Back Web Bottom Shelf Top Shelf The results of the analysis (performed through SolidWorks) are presented in Figures 6 below. Figure 6. Results of stress analysis on outer panels of satellite 16 Figure 7. Results of stress analysis on shelving in satellite Figure 8. Results of stress analysis on top and front webs of satellite 17 Figure 9. Results of stress analysis on back and bottom webs of satellite The results of the study show that the maximum stress felt in the structure under these loading conditions is 143.892 MPa and that the maximum displacement of any part of the structure during launch will be 5.78 mm. The study also states that both of these maximums will occur in the interior shelving of the satellite which is understandable since the shelving was handling the largest loads during the simulation. In analyzing the results, one key point must be made. While the above pictures show that SolidWorks believes the yield strength of 6061-T6 aluminum alloy to be y 55 MPa , [20] and many other reliable sources state that 6061-T6 aluminum alloy has two values of yield strength, namely y 240 MPa and y 140 MPa (the tensile and shear strengths respectively). Looking at the above results, we see that the shear forces acting on the satellite all appear to act on the front, right, left and back panels so as long as none of these stresses reach the maximum value, we are safe. It can be seen in Figure 4 that none of the panels even leave the blue range (thus their stress is less than approximately 25 MPa) so the structure can be assumed to survive launch with a minimum factor of safety given by: FOS min y 240 MPa 1.67 max 143.892 MPa Under this assumption, the structure will be able to support the satellite once in orbit since the loads experienced there are significantly less than launch loads (the loads will be in fractions of a g-force instead of 16g). 18 TRL The structure of the satellite is fabricated out of 6061-T6 aluminum alloy with an external coating of MLI (multi-layer insulation). This alloy and coating has been used in space extensively before and thus is TRL 7+. In regards to the GTAW welding being performed to fabricate the frame, there are NASA practices that specify the process of using GTAW on spacecraft. Specifically, NASA practice No. PD-ED-1205 [21] certified GTAW for use on the space shuttle among other missions (a link to the sheet can be found in the references section). Thus it is assumed that these welds have been flown into space previously and are TRL 7+. Risk Analysis Risk analysis for the structures sub-group is crucial to the survival of the satellite. If the structure of the satellite or any of the components that are holding other components in place fails during the mission, there is an overwhelming chance that the entire mission will fail with it. The major risks that structures has to deal with are failure of the structure during launch, debris impact on the satellite puncturing the panels or fatigue from oscillating thermal stresses causing the structure to fail during the mission life. In order to minimize the chances of these risks occurring, multiple steps have been taken. First, the loads analysis performed by the team assumed that all loads acting on the satellite were launch loads. Thus, it was shown that all of the structural components of the satellite can withstand the launch process. To further minimize the chance of a launch failure, the structure will undergo vibrations testing after it is fabricated to further validate its ability to survive launch. To account for the potential of debris rupturing the panels, we have designed the satellite to have minimal loading on its panels once the DRAGONS sensors are deployed either through using webs as additional support or purely through a lack of attached components to the panels (for the side panels). This allows the panels to withstand higher impacts by allowing them to absorb more energy. Finally, in order to minimize the possibility of fatigue causing the structure to fail, the satellite structure will undergo thermal fatigue testing after fabrication to ensure its survival throughout the mission. Payload STK Models for Estimated Impacts The purpose of the mission is to provide in situ measurements of micrometeroids and orbital debris (MMOD) in Low Earth Orbit. Systems Tool Kit (STK) software was used to obtain a preliminary estimate of the amount of impacts to be expected for a given sensor area. However, successful completion of the mission will enable more accurate models to be created because actual in situ measurements will be taken. From earlier trade studies, it was determined that six 0.5 m by 0.5 m DRAGONS units, totaling a sensor area of 1.5 m2 would be used to detect the debris and take measurements. It was also 19 determined that the satellite would operate at a 700 km orbit at a 90 degree inclination for optimizing the number of impacts. A model was created for the two year mission for comparison to other possible cases of orbit size and inclination for a given sensor area. The data for four orbit sizes (700 km, 750 km, 800 km, and 850 km) and three inclinations (0°, 45°, and 90°) are provided below, along with a plot showing the trend of the results. Inclination (Degrees) 0 0 0 0 45 45 45 45 90 90 90 90 Orbit Size (km) Sensor Area (m2) Number of Impacts 700 1.5 237 750 1.5 248 800 1.5 254 850 1.5 258 700 1.5 261 750 1.5 273 800 1.5 280 850 1.5 284 700 1.5 361 750 1.5 377 800 1.5 387 850 1.5 393 Figure 10. Data collected for the number of impacts at various orbits and inclinations. Figure 11. Plot of the estimated number of impacts versus orbit size for various inclinations. 20 As can be seen from the data above, it is predicted that as the degree of inclination increased, the number of impacts increased, with the 90° inclination having more impacts by a much larger margin than the other two inclinations. The number of estimated impacts also increased as orbit size increased, but only by a small amount. For optimizing the number of hits, it can be concluded that the 90° inclination was an appropriate selection. The number of impacts relating to the altitudes between 700 and 800 km did not vary enough to say that increasing the orbit by just 100 km would provide a significant increase in the estimated number of impacts. Thus, the 700 km orbit selected will still provide sufficient data for the mission. Overall, these models provide an estimate as to what can be expected in LEO for the purposes of our mission, but it is understood that this area of study still has many unknowns. A mission of this type has never been conducted before, so the data collected during the mission will significantly improve existing models like the ones obtained from STK. Therefore, the mission will benefit users who need more accurate predictions of small MMOD and can be a factor in improving other missions in LEO in the years to come. Final Design The mission of the Bravo Orbital Space Satellite (BOSS) is to conduct in situ measurements of micrometeoroids and orbital debris that cannot be detected from ground based systems. The finalized design of the payload incorporates components that optimize the number of MMOD impacts while remaining within the constraints of mass, budget, and occupation of a minimum volume in the launch vehicle fairing. Figure 12 displays a schematic of the payload in the fully deployed position. While the payload is configured in this position, the BOSS will have the ability to collect data on the number and characteristics of impacts. Figure 12. BOSS Payload in fully deployed position. 21 Table 3. Bill of Materials of all components incorporated into the BOSS payload. Item # p01 p02 p03 p04 p05 p06 p07 p08 Name DRAGONS Shroud DRAGONS Control Box DRAGONS Sensor Honeybee Robotics Deployment Hinge Hold Down Release Mechanism Grade 8 Alloy Steel Hex Head Cap Screw Bolt Lightweight Aluminum Flat Washer Grade F Nylon-Insert Hex Flange Locknut Quantity 6 6 6 12 5 130 130 130 An overview of the components used in the payload includes the Debris Resistive Acoustic Grid Orbital Navy Sensor (DRAGONS) units, deployment hinges, hold down release mechanisms, and the hardware used for integration to the satellite. A description of each component is as follows, including any modifications to the components listed. A single DRAGONS unit consists of a sensor, a control box, and a shroud/frame. Six DRAGONS units were used on the payload of BOSS, so in total there were six sensors, six control boxes, and six shrouds that were integrated together to yield the configuration in Figure 12. The DRAGONS units were donated by NASA for the purposes of this mission and will be provided to Bravo Aerospace Industries as in Figure 13. Figure 13. Solid model of the unmodified DRAGONS unit frame as provided by NASA to BAI. 22 The frame in Figure 13 that will be provided by NASA will be modified to meet the needs of the BOSS payload. The NASA DRAGONS unit frame includes four mounting feet and vertical corner angle members. These mounting feet and vertical corner angle members will be removed because they will not be necessary to the mounting of the payload to the satellite, and will not compromise the structural integrity of the unit. The BOSS modified DRAGONS unit can be seen in Figure 14. Figure 14. Modified DRAGONS unit to meet the needs of the BOSS. Mounting feet and vertical corner angle members were removed. The purpose of the shroud is to act as a frame for the sensors while also preventing MMOD particles from impacting the sensor at shallow angles. Impacts at these shallow angles have the potential to remove an excess of sensor detection area if not prevented. The electronics box for each DRAGONS unit will be placed inside the main satellite structure and wired to the various DRAGONS units. The control box measuring ~16.51 cm × 21.59 cm × 8.89 cm is shown in Figure 15. Figure 15. Mock up version of control box. Actual control box will be provided by NASA 23 The 50 cm x 50 cm sensor of each DRAGONS unit provided by NASA consists of a resistive grid, a dual-layer Kapton film, and polyvinylidene fluoride (PVDF) acoustic impact sensors. Upon particle impact, the resistive measurements on the grid change and the size of the impact area can be measured from these resistance changes. The dual-layer Kapton film is used to measure the speed of the impacting particles by measuring the time difference between striking the two layers. The PVDF acoustic impact sensors provides data on the particle impact location. By placing the acoustic impact sensors at various locations along the sensor, the decomposition of signals received will provide data on the location. Each 50 cm x 50 cm sensor consists of four 25 cm x 25 cm quadrants of resistive grids coated with a dual-layer thin Kapton film measuring 25 µm thick. The specifications for each quadrant resistive grid include 1960 parallel lines that are 250 mm long, 62.5 µm wide, and spaced 62.5 µm apart. 3,11 The twelve Honeybee Robotics Deployment Hinges will be the main components used for payload deployment. These deployment hinges were selected because of their high stiffness, high strength, and low part count. It was also necessary for the BOSS to utilize torsion spring-driven damped deployment hinges to prevent an excess of velocity during unlatch that has the potential to spin the satellite out of control or make excess use of an attitude control system. The hinges are equipped with micro-switches that will tell BAI when the payload is fully deployed, and have a full 180° range of motion. The approximate survival temperature for the hinges is -150 °C to +150 °C, which is sufficient for the mission. The Honeybee Robotics Deployment Hinges are flight proven and have been used in the USAF STPSat-1 that was launched in 2007.13 These hinges are also contracted to be used on FORMOSAT-5 in 2014. Figure 16 displays a picture of the deployment hinges that will be utilized for the BOSS payload. Figure 16. Honeybee Robotics Deployment Hinges.[11] Due to the nature of this project, the CAD model of the BOSS payload did not utilize the exact model of the deployment hinges from the supplier. A similar model was used for the hinge components that show the overall mechanism of the hinges. Detailed features including the exact CAD model were not attainable from the supplier. 24 Five hold down release mechanisms (HDRMs) were also utilized for the payload deployment process. HDRMs, displayed in Figure 17, maintain the load of the DRAGONS units and hold the deployable sensors in place. They act as the interface between the main satellite structure and the DRAGONS units and once activated, allow movement of the hinges into the fully opened deployment position. These mechanisms are flight proven and will be supplied by Sierra Nevada Corporation Space Systems (SNC Space Systems). A picture from the supplier is seen in Figure 18. Figure 17. Hold down release mechanism. Figure 18. Hold down release mechanism.22 The hardware that will be used to secure the sensor shrouds to the hinges and the hinges to the satellite body were specifically selected to withstand the space and launch environments. The range of temperatures that the hardware will experience is -100 °C to 150 °C. All fastener hardware is rated for -150 °C to 250 °C. The bolts selected are made of grade 8 alloy steel which 25 has a 150 ksi minimum tensile strength. This rating exceeds the loads that these bolts will experience minimizing any risk of fastening failure. The nuts chosen are grade-F nylon insert locknuts. They were selected for their properties to be able to withstand heavy vibration during launch, without the nuts backing out. All fasteners are COTS parts from McMaster-Carr. The exact sizes needed to fasten the hinges are yet to be released by Honeybee Robotics, but nominal sizes are expected and easily obtainable in the selected material types. DRAGONS Units Deployment Stage 1: During launch and while the satellite is in the launch vehicle fairing, the satellite will be configured in a compact, cube-like orientation, as in Figure 19. The compact payload design minimizes fairing volume, allowing the satellite to ride as a secondary, or even tertiary payload. A minimum volume reduces the high costs associated with the launch operations for both BOSS and the fairing payload as a whole. Figure 19. Stage 1 of the Payload deployment. This figure shows the pre-deployment, most compact configuration of the DRAGONS units around the main satellite structure. The satellite is equipped with six 50 cm x 50 cm DRAGONS units, twelve Honeybee Robotics deployment hinges, and five SNC Space Systems hold down release mechanisms (HDRMs). During stage 1 of deployment, the HDRMs maintain the load of the DRAGONS units and hold the deployable sensors in place. Figure 18 displays a schematic of the hold down release mechanisms. These HDRMs are essentially the interface between the main satellite structure and the payload that allow for full deployment with minimal additional mechanical components. 26 Stage 2: During stage 2 of deployment, the first set of HDRMs release the DRAGONS units. The HDRMs are electrically activated, and once activated release a latch that allows the hinges to operate. Figure 20 provides an image of the deployment right after HDRM release. The hinges that are being used for deployment are torsion spring-driven damped hinges and provide the rotational force to deploy the payload. These Honeybee Robotics hinges have high stiffness and strength along with a low part count to minimize associated mechanical risks. The hinges are damped to reduce the velocity after release and prevent additional rotational force that could spin the satellite out of control or require maneuvers from an attitude control system. Figure 20. Stage 2 of deployment. This figure displays the payload just after HDRM release. Stage 3: Stage 3 of deployment is an intermediate phase in which the first set of three DRAGONS units are fully deployed. The next set of three DRAGONS units are released by the HDRMs and continue deploying during this stage. Figure 21 shows the first three DRAGONS units in the locked position, while the second set of sensors has not yet deployed. 27 Figure 21. Stage 3 of Deployment. Half of the DRAGONS units are fully deployed, while second set are about to deploy. Upon continued deployment, the sensors will be in a similar configuration to Figure 22 below, in which the second sets of hinges are partially deployed. Figure 22. Stage 3 of Deployment. The second set of DRAGONS units has just begun to open up. 28 Stage 4: Stage 4 is the final stage of payload deployment. In this stage, the DRAGONS units lock into place and deployment is complete. In order to be sure of full deployment from the ground, each hinge is equipped with a micro switch that sends a signal to allow Bravo Aerospace Industries to know when deployment is complete. The fully open position of the DRAGONS units payload is displayed in Figure 23. Figure 23. Stage 4 of Deployment. The payload is in the fully opened position TRL Advancement Plan The goal of this mission is to introduce a new technology—the Debris Resistive Acoustic Grid Orbital Navy Sensor into LEO that will characterize and provide data on small orbital debris. The mission is being conducted for the purpose of advancing the DRAGONS provided by NASA to a technology readiness level of 7 or higher. Bravo Aerospace Industries is depending on the supplier to test the DRAGONS units in relevant environmental settings to advance the product to a TRL 6. After successful completion of this mission, the DRAGONS units will be flight proven and will provide data on small debris in LEO that ground based systems cannot detect therefore advancing the sensor units to the appropriate TRL. All components listed in the bill of materials for the BOSS payload are commercial off the shelf (COTS) components. All components provided by the suppliers are flight proven with heritage and will be tested by the suppliers prior to delivery. The suppliers will provide this test data to BAI upon delivery of the item, ensuring that the components are at the appropriate technology readiness level. 29 Thermal Protection Aluminum Radiation Shield Subsystem components such as those from C&DH and EPS have delicate hardware whose performance can be degraded by cosmic and solar radiation. Specifically the PDM and BCM components of EPS must be protected from exposures greater than 5 kRad while the lithium-ion battery must remain under 500kRad for its lifetime. To meet these requirements, 7mm thick honeycomb aluminum panels and a radiation shield container will house these components. Figure 24. Radiation Shielding Design This shows how the total life time radiation dosage inside a spacecraft changes as the amount of aluminum shielding increases. 23 The MIR space station was maintained at a near earth orbit at an altitude of 296-421km while ISO had a highly elliptical geocentric orbit with apogee at 70600 km and perigee at 1000 km. The curves for radiation dosage relative to aluminum shielding thickness for both of these satellites are shown in figure 24. A curve similar in shape and between the curves of MIR and ISO would characterize our satellite at 700km altitude polar orbit. Yearly our satellite components should be kept to an exposure level of about 1.5kRad for its 3 year lifetime. 𝑇𝑜𝑡𝑎𝑙𝐸𝑥𝑝𝑜𝑠𝑢𝑟𝑒(𝑘𝑅𝑎𝑑) = 𝐸𝑥𝑝𝑜𝑠𝑢𝑟𝑒 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟 (𝑘𝑅𝑎𝑑) 𝑌𝑒𝑎𝑟𝑠 𝑜𝑓 𝐿𝑖𝑓𝑒 30 To maintain the satellite under 1.5kRad exposure the data presented in figure 24 shows that 6 mm of 6061-T6 aluminum alloy will suffice. The honeycomb panels of the exterior consists of a honeycomb pattern sandwiched between two layers of 1 mm thick aluminum alloy sheets. Between the exterior panels of the satellite and the radiation protection container there is also aluminum webbing and other components, which may absorb radiation. However, the coverage is not extensive throughout the structure to adequately provide protection. Therefore a box with 6 mm thick aluminum of welded sheet metal construction with a close fit lid will be used. The total mass of this container will be approximately 5 kg. Multi-Layer Insulation To test how well the Multi-Layer Insulation (MLI) protects the satellite from the harsh space environment, a number of heat transfer equations must be utilized. The space environment temperature varies depending on where the satellite is and the time of day so it is important that the MLI provides protection for a wide range of temperatures. To complete this task, the surface temperature of the satellite must be predicted using: 𝑞𝑎𝑏𝑠𝑜𝑟𝑏𝑒𝑑 = 𝑞𝑒𝑚𝑖𝑡𝑡𝑒𝑑 𝐺𝑠 𝛼𝑠 = 𝜀𝐼𝑅 𝜎𝑇 4 1 𝐺𝑠 𝛼𝑠 4 𝑇=( ) 𝜀𝐼𝑅 𝜎 (1) where, 𝐺𝑠 = Solar Flux 𝛼𝑠 = Absorptivity 𝜀𝐼𝑅 = emissivity 𝜎= Stefan-Boltzmann constant Once the outer surface temperature of the MLI is calculated, we can treat the MLI as a plane wall with each layer having its own thermo and physical properties. Because the MLI is simplified to a plane wall, the heat transfer rate through each layer is equal throughout the insulation. To put it simply: 𝑞𝑙𝑎𝑦𝑒𝑟𝑖 = 𝑞𝑙𝑎𝑦𝑒𝑟(𝑖+1) = 𝑞𝑙𝑎𝑦𝑒𝑟(𝑖+2) = 𝑞𝑙𝑎𝑦𝑒𝑟(𝑖+𝑛) Each heat transfer rate equals 𝑞 = 𝛼𝐺 − 𝜀𝜎(𝑇𝑛+1 4 − 𝑇𝑛 4 ) − 𝑘(𝑇𝑛+1 − 𝑇𝑛 ) 𝐿 (2) Where 𝑇𝑛 equals the outer temperature of the next layer (it also represents the inner temperature of the previous layer). 𝑇𝑛+1 is the inner temperature of the layer (or the outer temperature of the next layer). One can see that MLI is very versatile. The number of layers and their properties all affect how the MLI will perform. Figure 25 shows the typical makeup of MLI and Figure 26 shows the absorptivity and emissivity of common MLI materials. 31 Figure 25. Common Multilayer Insulation makeup Figure 26. Absorptivity and Emissivity of common MLI materials For the BOSS satellite design, Figure 25 was used to create a preliminary layout for the MLI and the properties from Figure 26 were used to finalize the design of the MLI. Following the format of Figure 25, the BOSS satellite’s MLI will consist of: Outer layer and inner layer of Kapton Film Beta Cloth to act as a light block Aluminized Teflon Optical Solar Reflectors which have high emissivity to block sunlight Netting Spacers and Mylar sheets to reduce conductivity (13 layers in total) All held together with Elastisol space adhesive and tape 32 The whole MLI will be attached to the structure by hook and pile connectors Here is an example photo of MLI that is very similar which will be used on the BOSS satellite Figure 27. Typical MLI makeup. The golden film on the outside represents the Kapton film backed by aluminum. The solid metallic layers represent the reflectors. The netlike materials represent the spacers, and inbetween these layers are low conductivity Mylar sheets. To confirm that this layout works, the MLI was tested when the satellite resided in the bright side of the Earth and on the dark side of the Earth. Bright side of the Earth Using the given values: 𝐺𝑠 = 1371 W/m2 𝛼𝑠 = 0.41 𝜀𝐼𝑅 = 0.75 𝜎 = 5.67 x 10-8 When the satellite is on the bright side of the Earth, the surface temperature of the satellite, using Equation 1, is: 1 𝐺𝑠 𝛼𝑠 4 𝑇=( ) = 339 𝐾 = 66°𝐶 𝜀𝐼𝑅 𝜎 Using this value and plugging into Equation 2 yields 𝑞 = 𝛼𝐺 − 𝜀𝜎(𝑇𝑛+1 4 − 𝑇𝑛 4 ) − 𝑘(𝑇𝑛+1 − 𝑇𝑛 ) 𝐿 This value will be used to find the changes in temperature when heat travels through the insulation. Substituting the given properties for each layer, the final temperature or the inside temperature of the satellite will 16°C. 33 Dark side of the Earth The final temperature of the satellite is calculated the same as the bright side, but the only difference is the solar flux value: 𝐺𝑠 = 340 W/m2. This changes the initial surface temperature of the satellite. 1 𝐺𝑠 𝛼𝑠 4 𝑇=( ) = 239𝐾 = −34°𝐶 𝜀𝐼𝑅 𝜎 Following the same procedure as above, using the same given thermal properties, the final temperature of satellite will be -16°C. With the internal heat generated by the components and the aluminum box for radiation protection, this is warm enough for the safe operation of the internal components. Internal Satellite Thermal Analysis Many of the heat generating components within the satellite are also contained within radiation protection boxes and where therefore analyzed as boxes. The thermal analysis was run at the calculated interior ambient temperatures the MLI leads to of -16ºC to +16ºC. Components with sensitive temperature ranges where considered to analyze the impact of surrounding components. Radiation was the main mode of heat transfer with most components consisting of Aluminum alloy with emissivity of 0.25 and polymers with emissivity of 0.85. Figure 28. Thermal Analysis at +16 ambient. 34 Figure 29. Thermal Analysis at -16 ambient. Thermistors To monitor the thermal health of the satellite seven thermistors will be employed, one mounted on the interior of each honeycomb aluminum alloy panel and one mounted on the lithium-ion battery radiation protection box. This placement presents the opportunity to manage components that are out of their operating thermal range by changing the individual components power mode. The thermistors chosen have a temperature range -60ºC to +160ºC with tolerance from 0 to +70ºC : ±0.35ºC. Other useful qualities: •Excellent Stability •Flight Heritage •Robust Construction •Non ITAR Restrictive •Flat Surface for Ease of Mounting •Approved by Prime Contractors •Flat Aluminum Housing These thermistors will be mounted onto the satellite using space grade tapes and adhesives. They are constructed of Matched Glass Coated NTC Thermistor Beads mounted on aluminum housing and encapsulated in Stycast 2850FT epoxy. 35 Figure 30. Thermistor dimensions. Figure 31. Thermistor resistance table Space Grade Wiring The space environment also impacts component wiring especially when exposed on the exterior of the satellite such as for the sensors payload. To counter the impact of radiation and thermal effects the conductor is silver plated copper and the insulation is flexible PTFE that has excellent outgassing behavior, reinforced mechanical resistance and a temperature range of -100ºC to +200ºC. 36 Safety and Mission Assurance There are several considerations for the safety and mission assurance of the Thermal Protective System. The following outlines how BAI will assure thermal protection remains functional throughout the mission. 1. Environmental Effects a. Throughout its time in the atmosphere, the satellite will experience fluctuations in temperature. b. Prior to launch, the materials shall be tested at the extreme temperatures of space to assure that the subsystems will remain at operational temperatures. 2. Degradation and Deformation a. Structural materials will be tested prior to launch at various temperatures and in vacuum to verify that the materials will withstand and perform at intended. 3. Contact with debris a. Multi-Layer Insulation (MLI) would degrade slightly per puncture made but will continue to function at a lesser extent b. A high energy impact can sever wires in electrical equipment for active methods such as heaters. 4. Heat Transfer a. Subsystems may receive too much heat or not enough, depending on whether or not the satellite is in the shadow of the earth or exposed to the sun. b. Radiation box protects vulnerable components like the battery 5. Maintenance a. Because the lifespan of the satellite is roughly three years, no further maintenance will be needed. Risks Management For the TPS, potential risks include breaks in the MLI, oxidation of the Aluminum Optical Solar Reflectors, outgassing. This would expose the internal components to the harsh space environment. Many of the subsystems within the satellite have to be within a temperature range to survive so to prevent any conflicts, strong insulation and material were chosen. Other risks lie in manufacturing error, testing error, and thermistor error which can be prevented before launch. The risk management chart in the “Risk” section details all of the risks and their mitigation strategies. Electrical Power System In order to give the mission a chance at success, the electrical power subsystem must provide adequate power to each component for the life of the satellite. The electrical power subsystem needs to generate power from the environment, condition and store that power, and distribute the proper amount to each component throughout the life of the BOSS two year mission. A total of 6 subsystems have power needs for their components that the electrical power subsystem must provide. The final design is one that meets all of the above success criteria while helping to stay within the mass and cost constraints. The final design is an electrical power system that draws energy from solar arrays, stores energy in a secondary battery, and uses a power conditioning a distribution unit to deliver power. 37 Design Outline The electrical power system is designed to collect energy from the sun with a Gallium Arsenide solar array. This solar array during launch is folded on the bottom side of the BOSS structure. The array is folded so that half of the total area is exposed, so it acts essentially as a body mounted panel to provide power during detumbling. After detumbling the solar array will deploy with a mechanically powered hinge and begin to provide power. The array will always be directed toward the sun using a biaxial gimbal with positioning commands coming from the command and data handling flight computer. The BOSS internal electronic components are made up of a Clyde space Lithium Ion battery and a Surrey made power unit. The Surrey power conditioning and distribution unit (PCDU) is a battery conditioning module and power distribution module in one box. The battery conditioning module regulates the incoming power from the solar array while also limiting the charge and discharge rates of the battery. The power distribution side of the unit provides the regulated power when it is needed for each component. The lithium ion battery provides the power needed for hardware components when the BOSS satellite is eclipsed by the earth. Figure 32. Above is the hardware schematic for the electrical power subsystem components. Note that everything within the PCDU is one unit within the BOSS structure. Power Collection The BOSS has a single deployable photovoltaic solar array on the bottom side of the structure. The array is made up of two a square panels 450 mm by 450 mm which fold out using a spring powered hinge. The 405 mm2 of Gallium Arsenide solar panels provide 79.5 watts of power at the end of their life. After 76.5 minutes of Sun exposure, the array captures 101.3 watt∙hours of energy. This is enough to provide the 82.9 Watt∙hours per orbit needed to charge the Lithium Ion 38 battery and provide power to electrically powered components. The solar array purchased from Clyde Space has a total efficiency of 28.3% and only has a total mass of 1.84 kg.15 The power calculation from the solar array includes all loses from cell degradation, angle to the sun loses, and inherent degradation. Figure 33. Clyde Space Solar Array with Gimbal Assembly15 In order to assure power to all subsystems, the solar array will be assembled with a biaxial gimbal purchased from MOOG.14 The command and data handling flight computer will provide input commands to the gimbal based on sun sensor readings from OADC. The result is a solar array that tracks the sun for the most power input. The gimbal itself requires 10 Watts of power to move when the array is collecting and adds an extra 1.2 kg of mass.14 The gimbaled and deployed solar array offers a better power solution than a larger area of body mounted solar arrays because of the need for the satellite core area for mounting the Dragons payload and OADC equipment. Figure 34. The Type 11 Biaxial Gimbal used to control the solar array on the BOSS.14 39 Energy Storage The battery is designed to provide power to components that need to run during the periods when the BOSS is eclipsed by the earth and no power can be drawn from the solar array. A lithium ion secondary battery was selected from Clyde space because of their experience with powering CubeSats. A lithium ion battery is the obvious choice with a strong space heritage, a high energy density, and the BOSS limitations on mass. The total energy need in the 21.5 minute dark period is 13.2 Watt-hours. The battery must be charged and discharged every orbit. Therefore to reduce damage to the battery, it must not be overcharged at all or over discharged by more than 30 percent.17 There result is a required battery capacity of 51 Watt-hours, including efficiency losses. A Clyde Space 90 Watt-hour CubeSat battery meets this requirement at a mass of 0.768 kg.17 By over sizing the battery, we assure a power positive system, meaning the BOSS will always have more power available than it needs. Figure 35. The 90 Watt∙hour Clyde Space Lithium Ion Battery used on the BOSS17 Power Conditioning and Distribution The battery and solar array give a method of collecting and storing power, but the EPS requires components to regulate and distribute this power. The Surrey made Power System 150 PCDU provides the medium between collecting and distributing. The Power System 150 is comprised of a battery conditioning module (BCM) and power distribution module (PDM). The BCM is the interface between the solar arrays and battery.16 This power system provides six battery charge regulators (BCRs) to regulate the amount of power charging the battery from the solar array. The BCRs covert the input power to the nominal 28 volt bus needed to charge the battery and interface the PDM.16 The BCM also has a battery charge monitor which protects against overcharging and discharging by supplying signals to the BCRs to turn on and off input or to the OV shunt.18 The power is distributed to the BOSS components via the PDM of the Power System 150 unit. The PDM takes commands from the command and data handling flight computer to determine if each of the 28, 28 volt switches and 16, 5 volt switches are on or off. The PDM also provides over current protection for each output switch. 40 Figure 36. The Surrey Power Unit 150 PCDU used on the BOSS.16 Power Budget It is critical to mission success that the power budget is accurate. The budget determines if the solar arrays are large enough to both provide power to components and charge the battery while the array is in the sun. The budget also includes how much energy each subsystem uses during the eclipse period to determine the size of the Lithium Ion battery. Tables 4 and 5 illustrate the overall power budget, while the third shows the power needs on the dark 22 minute period. Table 4. Power budget for BOSS. Component Command and Data Handling CPU Dragons Sensors GPS IMU Sun Sensors Torque Rod Reaction Wheel (x3) Solar Array Gimbal Communications Thermocouples Battery Charge (with losses) Total Need Normal Power Mode (W) 5 Constant Secondary Power Mode 9 for Downlink Energy Need (W∙hr) 8.61 6 Constant 1.6 Constant 5 Constant 0.2 Constant 2 As Needed 4.5 As Needed 1 Per Hit None None None None Mode 1: 8.4, Mode 3: 39 as Needed None 15 Downlink None 9.80 2.61 8.17 0.33 3.27 27.6 10 as needed 1.5 Uplink 2 Constant 1.27 4.12 3.27 13.89 82.89 The system is considered power positive because the solar array generates 101.3 watt∙hours of energy which exceeds the needed 82.9. The EPS will always generate more power than is consumed. Notice that OADC demands the most power for an active attitude and orbit control. 41 Table 5. Component energy needs. Component Battery Capacity Need (W∙hr) 1.793 Command and Data Handling CPU 2.153 Dragons Sensors 0.574 GPS 1.793 IMU 0.072 Sun Sensor 0.717 Torque Rod 4.842 Reaction Wheel 0.5378 Communications Uplink Total 13.199 The number of components running in the eclipse period is kept to a minimum to reduce the mass and cost of the battery. The 90 watt∙hour Clyde Space battery is well above the needed 51 watt∙hours needed to ensure the 30 percent depth of discharge. It also means the battery storage is power positive. The energy storage is always more than the BOSS will consume. Figure 37. Above is the wiring diagram from the power distribution module to all the powered components. A larger version of this figure is in the appendix. Configuration The two panel deployable solar array and gimbal is mounted to the bottom side of the BOSS. The single spring powered hinge is mounted to the gimbal and center of the edge of the bottom side opposite the deployed Dragons sensors. The PCDU and battery are positioned inside the structural core of the BOSS for thermal and radiation protection. The spec 80 FlexLine space grade wiring for all components is provided by TE connectivity. The wiring must be space grade and tested to avoid out gassing. The wiring runs from each power relay output of the PDM to each of the components needing power. The total mass of the assembled electrical power system 42 is 8.73 kg. Each component requiring power is wired directly to the PDM of the PCDU. The wiring diagram below provides all the components connected to the PDM. Risk Analysis Electrical power failure is not acceptable and will result in total mission failure. To avoid this, all failure modes have been considered and designed around. First is failure at the battery. Batteries inherently degrade over time. To avoid significant losses, a short satellite mission life and cyclical charge tests eliminate the risk of failure. Over charging and discharging of the battery is eliminated as a failure mode by designing a large enough battery for eclipse power and including the charge monitor and over voltage shunt in the BCM. Thermal and structural damage to the battery is designed around by the thermal and structural subsystems. Solar array failure is the most likely source of electrical power failure. Deployment and solar tests by the manufacturer reduce the risk of total failure. Debris could damage part of the array reducing the total power it can absorb. To reduce the risk associated with debris, the array is divided into 6 segments that are wired into separate BCRs. This way the loss of one segment of the array does not cause total failure. Gimbal testing by the manufacture reduces the risk of loss of mobility of the solar array. However, this loss of mobility will only result in a reduced power state. The PDM provides over current protection to all components to eliminate the risk electrical damage. Failure from electronic connections is eliminated by extensive testing and the use of space grade wiring harnesses. Interfaces The interface between the electrical power components and the command and data handling on board computer is the most critical interface. Without the commands going to and from these components, power would not be provided at the correct time and electrical components could be damaged. The PCDU interfaces with the command and data handling using an RS 422 connector through which it receives necessary commands. The interface with command and data handling is summarized in the tables in the appendix. All interfaces with other subsystems are controlled through the PDM which determines if the component is on or off and the nominal voltage. Wiring runs from each power relay output on the PDM to each of the components that require power. These relays are used to switch on and off components when power is needed or not needed for specific components. Spec 80 FlexLine Wire from TE connectivity is used to route the power from the RS 422 connectors at the PDM to the components requiring power all of which are shown in figure 6 above. The spec 80 FlexLine wire is space grade wire insulated with flexible modified radiation cross-linked ETFE polymer rated from -65 to 200 degrees Celsius. The wires will be bundled coming out of the PDM and when possible. Also a ground cable will be run to maintain electrical continuity between structural elements. Orbit Attitude Determination and Control Design An Inertial Measurement Unit (IMU) is a device that senses and calculates the spacecraft’s orientation and rates by measuring the angular acceleration and angular velocity. The angular 43 acceleration is measured using accelerometers, typically one per each axis for a total of three. The angular velocity is measured using gyroscopes, again with one for each axis, or a single, three-axis gyroscope. Normally, IMUs calculate the position of the spacecraft by integrating the measured angular rates, knowing the time-step. However, such systems will become increasingly inaccurate over time as error accumulates due to the noise and bias of the sensors, as well as the integration method. To remove such error, the IMU proposed is to use a new configuration based on a paper by Vivek Nagabhushan to reduce the bias and noise of the angular acceleration and angular velocity measurements.10 In terms of the physical configuration there are six accelerometers, with two on each axis, to allow better measurement of the angular acceleration by knowing the relative distance between the two accelerometers. The measurements are then run through a Kalman filter which will iteratively calculate more accurate (bias-free) angular rates from the measured values. The Kalman filter process and equations are described in full by Nagabhushan.10 Not mentioned specifically in the reference material is the number of iterations to use for each measurement, it has been determined that the filter will run at a rate proportional to the time step considered in the calculations and the refresh rate of the sensors. So for a refresh rate of 50 𝐻𝑧 and an internal rate of 5000 𝐻𝑧, the filter will run 100 iterations for each measurement. There will also be a dedicated 100 𝑀𝐻𝑧 CPU in the IMU itself to run the filter and send the processed data to the satellite’s main CPU to store. The specific components of the IMU referenced below can be seen in the (table or appendix). The accelerometers on the x-axis are positioned in the direction of the y-axis, the y-axis in the direction of the z-axis, and the z-axis in the direction of the x-axis. The relative distance between the accelerometers on each axis will be 130 𝑚𝑚 to provide enough distance for the filter to properly work on removing noise from the angular velocity at least. However, noise will still be present in the angular acceleration measurements for low-amplitude oscillations, which are expected. The chosen accelerometers are the QA3000-010 from Honeywell, and provide low bias and intrinsic noise. The gyroscope configuration is the same as any commercial IMU, with three ring-laser gyroscopes positioned along the three orthogonal axes. The gyroscopes may have an internal bias and may accumulate additional bias over time, the Kalman filtering acts to remove this bias. The chosen gyroscopes have a bias stability of 0.0035 𝑑𝑒𝑔/ℎ𝑟, which is within acceptable ranges for the Kalman filtering. The IMU was simulated using the above components in order to determine the optimal positioning of the accelerometers. In order to reduce the error in the angular velocity to acceptable levels, it was determined that the distance between accelerometers should be at least 10 𝑐𝑚, with additional distance reducing the error further. To fit within a certain frame based on the dimensions of COTS IMUs, the distance between accelerometers was chosen to be 13 𝑐𝑚, with one placed 2 𝑐𝑚 from the origin of the axes and the other at 15 𝑐𝑚. This configuration provides a mean error of less than 0.000005 𝑟𝑎𝑑/𝑠 in the filtered angular velocity, which corresponds to less than 0.1% error. In terms of angular acceleration, the bias is removed in the filtering, but the noise still prevails. For small angular accelerations as expected during 44 operation, the noise will be significant, however, the general form of the angular acceleration is still visible and can be determined by taking a mean of the still-noisy measurements after filtering. Kalman filtering of the measurements in this configuration provides a clear advantage in accuracy over other COTS IMUs. The physical development of the structure of the IMU and further testing are at this stage planned to be performed by University graduate students, with all components of the IMU being supplied by BAI. This IMU will be a step forward in capabilities of small satellites. However, should the new configuration not meet requirements it will still be able to function as any other IMU. Therefore, this new configuration will not pose a risk to the overall mission, and will only add a new component to the mission as a secondary objective. In determining the required positional accuracy of the system, the maximum distance of the DRAGONS payload was considered along with its provided sensitivity of 150 𝜇𝑚. Knowing the internal dimensions of the satellite and the length of the extended sensors. The length at which the sensors must be able to discern the location of impact is approximately 1.3 𝑚. Since the sensitivity was not specified total or in any direction, the given sensitivity was halved to 75 𝜇𝑚 to be safe. At a distance 𝑥 along a stationary axis from the center of the satellite, the distance 𝑥 ′ on the sensor at an angle Δ𝜃 from the initial axis is calculated by 𝑥′ = 𝑥 cos(𝛥𝜃) So, for the sensor to be able to distinguish impacts, it is required that 𝑥 − 75 𝜇𝑚 < 𝑥 ′ < 𝑥 + 75 𝜇𝑚 which can be further simplified to 𝑥 + 75 𝜇𝑚 > 𝑥 cos(𝛥𝜃) thus, 𝑥 (1 − 1 ) < 75 𝜇𝑚 cos(𝛥𝜃) Using the length of 1.3 𝑚 for 𝑥, the equation then becomes 1.3 𝑚 (1 − 1 ) < 75 𝜇𝑚 cos(𝛥𝜃) and simplifying, 45 Δ𝜃 < 0.6154° So, essentially the satellite requires a positional accuracy of less than 0.5°, and by using Modified Rodrigues Parameters to determine position, this is possible9. Figure 38.1a. The actual angular acceleration for each axis (x,y,z) in blue, with the filtered angular acceleration in red. The noise from measurements is still present, but follows the trend. 46 Figure 38.1b. The error in angular acceleration for each axis (x,y,z). The unfiltered angular acceleration is in blue and the filtered angular acceleration in red. Figure 38.2a. The actual angular velocity for each axis (x,y,z) in blue, with the filtered angular velocity in red. The filtered velocity is barely visible above, so the noise and bias have been adequately removed. 47 Figure 38.2b. The error in angular velocity for each axis (x,y,z). The unfiltered angular velocity is in blue and the filtered angular velocity in red. The error in the filtered angular velocity is much less than the unfiltered. The other attitude and orbit determination components are two sun sensors and a GPS receiver. The two sun sensors will be placed on the outside of the satellite and on sides opposite one another that face outward, perpendicular to the velocity vector. The sun sensors have an accuracy of 1° and a 90° field of view. The accuracy of the sun sensors will allow the solar panels to track the sun for the majority of the time from their data alone, and the rest of the time by extrapolating the position either from the sensors or by the power input. The GPS receiver is able to get the orbital position and velocity of the satellite with typical accuracies of 10 𝑚 and 0.15 𝑚/𝑠, respectively. Attitude Control For attitude control, it is desired for the outward normal of the DRAGONS to remain within 5° of perpendicular to the velocity vector of the satellite to achieve the maximum number of impacts on the sensors. It is also desired that the satellite have a nadir pointing accuracy of less than 5° to accommodate maximum impacts on the sensors and allow the satellite to properly communicate with ground. The chosen 100SP-O reaction wheels can provide a maximum torque of 0.11 𝑁 𝑚, which is easily capable of orienting a satellite of this size. Torque provided to the satellite can be simplified for considering the torque acting along a single axis at the center of gravity as 𝑇 = 𝐼𝑎 in which 𝐼 is the moment of inertia about an axis. Considering 𝐼 = 0.155 𝑘𝑔 𝑚2 , the maximum acceleration that can be provided to the satellite along that axis is 𝑎= 0.11 𝑁 𝑚 𝑟𝑎𝑑 = 0.7097 2 2 0.155 𝑘𝑔 𝑚 𝑠 However, operating any reaction wheel at maximum torque is very power-consuming, requiring 13 𝑊. So the goal is to operate at around 5000 𝑟𝑝𝑚 for most control instances, which requires only 2.8 𝑊, and should provide a torque roughly 20% of maximum, which gives 𝑎𝑜𝑝𝑡𝑖𝑚𝑎𝑙 = 0.1419 𝑚 𝑠2 This optimal acceleration will be sufficient for normal operation to keep the satellite aligned as desired. The actual setup will position the reaction wheels as close to the center of gravity as possible, with four reaction wheels in a tetrahedral configuration to provide three-axis control as well as redundancy from the fourth wheel. The three torque rods will be placed on three of the inner edges of the satellite to allow for momentum dumping from the reaction wheels and to avoid disturbing other systems. The torque provided by a single Andrews TQ-40 torque rod can be calculated by the equation19 𝑇𝑚 = 𝐷𝐵 48 in which 𝐷 is the dipole of the torque rod, and 𝐵 is the magnetic field of the Earth. For the chosen torque rods, the nominal dipole is given12 as 42 𝐴 𝑚2 , and the magnetic field of the Earth in a polar orbit is 𝐵= 2𝑀 𝑅3 in which 𝑀 is the magnetic moment of the Earth and 𝑅 is the radius from the center of the Earth. For a polar orbit, then 𝐵= 2(7.96 × 1015 𝑇 𝑚3 ) (7071 𝑘𝑚)3 which then gives 𝑇𝑚 = 42 2(7.96 × 1015 𝑇 𝑚3 ) = 0.0019 𝑁 𝑚 (7071 𝑘𝑚)3 This torque is two orders of magnitude less than the maximum torque provided by a reaction wheel, but only one order of magnitude less than the expected torque needed by any reaction wheel during normal operation. This will allow for sufficient momentum dumping from the reaction wheels in a relatively short amount of time compared to other torque rod options. Risk Analysis The Honeywell GG1320AN Ring Laser Gyroscopes (RLG’s) in the IMU generate some random walk and bias stability throughout its life cycle that accumulates as error and failure towards the end of its lifetime. Random walk at 0.0035deg/hour and bias stability at 0.0035deg/root-hour is typical for the gyroscope. The design of the IMU incorporates Kalman Filtering (commonly used in inertial systems) which will filter the excess noise in the system that may appear from these factors. The mission length is 2 years and the lifetime of the RLG’s is about 7 years so random walk and bias stability should not become an issue. The RLG’s may be susceptible to jitters which may skew the data but this can be tracked and should not pose a major issue to data collection. If one RLG fails, the spacecraft will lose attitude data on an axis. The IMU will consist of 6 Honeywell QA3000-010 accelerometers with two on each axis used to measure the difference between them. If one accelerometer fails, the other accelerometer will continue to take data and operate the same way a normal IMU would work. Two Surrey 2-Axis sun sensors used in this system to take data. If one sun sensor fails, the second one will continue to operate with little loss in positional data. Issues may appear with the data upon a single point failure. The spacecraft could not be facing in the direction of the sun or there could be reflection off of another satellite or space debris that could skew the data. If the Surrey SGR-20 GPS fails during the mission, direct position data for the satellite will be lost. In this case, the path of the satellite can be estimated by established data. This data will include the spacecraft’s current orbit and drag analysis based on the area affected and the spacecraft’s altitude. Accelerometer data will provide velocity, which can be integrated to 49 provide the position of the spacecraft over time. The IMU will detect collision of the spacecraft and track its position change from the impact. Failure of a Surrey 100 SP-O Microwheel (Reaction Wheel) causes a loss of one axis of control. The fourth redundant wheel will be used in place of the failed wheel to provide accurate attitude control for the spacecraft. The redundant wheel ensures that the spacecraft will maintain a pointing accuracy of 5 degrees. If one Andrews TQ-40 Dual Wound Torque Rod fails, only the momentum dump process for the reaction wheels will be affected meaning there will be less stiffness during momentum dump. The two remaining torque rods will change the attitude of the spacecraft to provide the stiffness for the momentum dump. Each torque rod is dual would so if a single winding is malfunctioning, the other winding will be used. Both windings may be used to provide greater stiffness during each momentum dump. The system may be affected from sign interference by the torque rods but they will not be used extensively so it should not pose an issue to the operation of the BOSS spacecraft. If the Tethers Unlimited Nano-Sat terminator tape should fail, a second module will be deployed. The GPS will track the altitude of the spacecraft after mission completion to ensure the deorbiting module has deployed and is working properly. Technology Readiness Level IMU Testing The in-house IMU is currently at TRL 3 as Kalman filtering is a proven method of obtaining highly accurate data from the Honeywell QA3000-010 accelerometers and the Honeywell GG1320AN gyroscopes. The advancement plan will consist of: To TRL 4: Accelerometers and gyroscopes attached to breadboard or testing circuit board to receive data Setup on turntable for controlled (known) angular acceleration/velocity Data sent to computer for processing (Kalman Filtering) Data compared to expected accuracies To TRL 5: Setup tested again and restricted to flight computer processing capabilities Include small impulses Compare with simulations To TRL 6: No longer on breadboard, but fully-functional prototype IMU configuration Test again in same conditions as previous To TRL 7: Component either fully integrated into satellite or left separate Tested in conditions closer to the actual operational environment Parabolic flight tests Compare to reported responses from reaction wheels The IMU will advance to TRL 9 with the flight of the BOSS spacecraft. 50 The Surrey 100 SP-O Small Satellite Microwheels are at TRL 7. All necessary vibration and thermal testing have been conducted and the product is ready for delivery. The TRL will advance to TRL 9 with three scheduled flights by early 2014: TDS1 (2013), KAZ MRES (2013), and DMC3 Constellation (2014). The GPS Receiver is at TRL 9. It has undergone vibration testing to NASA GEVS acceptance and undergone thermal cycling. The Surrey SGR-20 Space GPS Receiver has 65 years of total flight experience with 20 units flown.17 The Surrey 2-Axis sun sensors are at TRL 9. They have undergone vibration testing to NASA GEVS acceptance and undergone thermal cycling. The sun sensors have 63+ orbit years to include the FASAT-Bravo, Uosat-12, TopSat, and DMC-4 satellites.16 The three Andrews TQ-40 torque rods are at TRL 9. They have had all necessary testing and have flight history. They were sold and used between 2007 and 2012 by Sinclair Interplanetary until transfer to Andrews Space.14 Three units were launched in November of 2010 and 69 units have been delivered.18 The de-orbit module is at TRL 7. The CubeSat module has undergone space deployment testing and has been successful. The Tethers Unlimited Nanosat Terminator Tape works under the same concept. It has been awarded contract for delivery in Q2 of 2014.15 The advancement plan will be the use and documentation of the NanoSat Terminator Tape for flight which will advance it to TRL 9. Interfaces The OADC subsystem is primarily controlled by Electrical and Mechanical Interfaces, the electrical interface being more critical of the two. Failure of any single electrical interface could result in massive failure for the rest of the subsystem and corrupted data in the worst case scenario. The Electrical interface is run by small interactions between Attitude Control (GPS, IMU, 2 Sun Sensors), Attitude Determination (4 Reaction Wheels, 3 Torque Rods) and the flight computer. The following is a list of all the component interfaces. 1. Electrical A. Attitude Determination (GPS, IMU, and Sun Sensors) provides position, velocity, acceleration, angular velocity, angular acceleration, and attitude data to the flight computer to be sent to the proper parts of the satellite that need them. i.e. position data is received by Ground Systems. B. The flight computer provides commands to the Attitude Determination system. C. The flight computer provides commands Attitude Control (4 Reaction Wheels, and 3 Torque Rods) D. EPS – supplies monitored power to Attitude Determination and Attitude Control through the flight computer. 2. Mechanical A. Attitude Control is mounted internally within the satellite structure B. The GPS and IMU are mounted internally within the satellite structure 51 C. The Sun Sensors are mounted externally on the satellite structures in opposite directions acting along the same axis. A list of the connectors used for interfacing can be seen below. Sun Sensor: DC Connector IMU: Accels - Connected to a circuit board. Gyro’s - RS422 Interface. Also mounted on circuit board. IMU computer – RS422/485, SPI, I2C GPS: RS422 Interface Reaction Wheels: RS422 Interface option. Torque Rod: Twist-pin micro-D style connector Command and Data Handling The purpose of C&DH is to ensure that data is properly transmitted between systems onboard the satellite. This includes a method of storing data. During completion of the PDR, the C&DH system design was narrowed down to non-radiation-hardened parts, an internal data storage system, a high-performance processor, and COTS software. The design was further refined, as required for the completion of the CDR. The components which compose the C&DH system can be split into two categories, hardware and software. Hardware C&DH will utilize the Andrews Model 160 High Performance Flight Computer, which has the following specifications: 100 MHz Processor 2GB Flash Memory 64MB SD RAM Power Consumption (Nominal/Max): 5W/9W Mass: 70 grams Volume: 15x97x90 mm Operating Temperature: -30 to +65o C Input Power: 6.5V, 12V, 28V Software C&DH will purchase COTS software from Clyde Space, which will be modified to provide the following modes of operation to the flight computer: Startup: Once the EPS has provided power to C&DH, C&DH will send a signal to OADC to begin detumbling. Once successful detumbling has been verified by OADC, C&DH will signal EPS to begin providing power to the payload and solar array deployment mechanisms. Upon verification by Payload and EPS that deployment was successful, the flight computer will switch to standby mode. 52 Standby: In standby mode, C&DH will continuously receive requests from OADC to verify the satellite’s orbit and attitude. This will be done via matrix calculations by the flight computer comparing the current orbit with the desired orbit. The difference in orbits is then sent to OADC which will correct the satellite’s course and orientation. OADC data from the IMU will be saved to the flight computer’s flash memory after being converted using industry standard compression algorithms. C&DH will continuously receive, compress and record Solar Array Power Status, Solar Array Position, Battery Charge/Discharge Status, and Power/Voltage to each subsystem component, as received from EPS, to the flight computer’s flash memory. C&DH will send a true/false signal to EPS to start/stop charging the battery when EPS’s sun sensor detects the satellite is in/out of the sunlight. C&DH will also continuously provide EPS with commands to the gimbal to properly orient the solar array. C&DH will continuously receive, compress, and record temperature health data from TPS’s seven temperature sensors to the flight computer’s flash memory. Consequently, C&DH will signal EPS to stop power distribution to a particular component should that component’s temperature exceed its operating range. This will minimize damage to the component should a TPS failure occur. C&DH will wait for a signal from payload for each MMOD impact reading. The particle’s velocity vector relative to the satellite will then be numerically indexed alongside the satellite’s current orientation. This information will be compressed and stored in the flight computer’s flash memory. C&DH will then wait for a response from the COMM system signaling that the satellite is within range of a ground station, at which point the flight computer will switch to downlink mode. Downlink: C&DH will transfer all recorded data in the flight computer’s flash memory to the COMM system, and continue transferring any newly recorded data while linked to the ground station. C&DH will wait for ground commands, to be received through the COMM system, which will be executed to the applicable subsystem. Such commands may include disabling of subsystem components through EPS, or a command to initiate de-orbit, at which point the flight computer will switch to de-orbit mode. De-orbit: C&DH will signal EPS to stop power distribution to all unnecessary subsystems, and signal OADC to begin de-orbit procedures. After OADC signals that de-orbit procedures have been completed, C&DH will signal EPS to stop power distribution to all subsystems. 53 Figure 39. Telemetry flow between C&DH interfaces. Technology Readiness Level Advancement Plan The flight hardware for the on-board computer is already at a TRL 8. The system has been flight tested and will not be modified. The testing performed by the company prior to purchase of the computer includes functional, vibration, mechanical shock, thermal cycling and thermal vacuum. The flight software is at a TRL 6. This COTS software has been used previously, but slight modifications will be made for this design. To bring the computer software up to TRL 7, inhouse DITL testing will be performed by BAI to detect any bugs, which will then be fixed. Communications The responsibility of the Communications Subsystem revolves around the satellite’s capability to transmit data to the ground stations, receive commands, and successfully stay in contact with the orbiting satellite. Without successful communication from the satellite to the ground stations, the mission would be at severe risk. Loss of communications may result in a total loss of all control over the satellite. Design Outline The final design utilizes a patch antenna along with a transmitter and receiver, which will all be acquired from ISIS. The antenna, seen in figure 40, works on the s-band frequency and has an opening angle of 85 degrees. The antenna has a right-hand circular polarization pattern and a gain of 6 dB. A low antenna gain reduces the accuracy needed when directing the antenna towards the ground stations for communication. 54 Figure 40. Solid model of S-band patch antenna During downlink, the C&DH will send signals to the transmitter. The transmitter contains two circuit boards: HI-RFE (Radio Front End), HI-CTR (Controller). The Controller Module is used for whole data processing, data encoding, digital-to-analog (D/A) conversion of transmits signals, transfer of control data to/from the on-board processor and power supply of both modules. The RFE Module is the actual transmitter of the signal. Then the signal is sent to the antenna which sends the data to GSS. The data sent to GSS includes telemetry data and payload data. The transmitter has a maximum data rate of 1 Mb/s, which exceeds the minimum data rate of 0.66 Mb/s at which data will be transmitted to the ground station. A similar model of the transmitter to be acquired from ISIS can be seen in figure 41. Figure 41. Surrey S-Band Transmitter During uplink, GSS sends signals to the antenna at a maximum data rate of 1 Mb/s. The signal is transferred from the antenna to the receiver. The receiver de-modulates and decodes the data sent from GSS. These signals include emergency commands and OADC commands. A similar receiver from Surrey can be seen in figure 42. 55 Figure 42. Surrey S-Band Receiver A table of the component characteristics including power requirements, dimensions, mass and temperature range requirement can be seen in table 6. Table 6. COMM component characteristics Frequency Patch Antenna Transmitter Receiver Dimensions (mm) 50 x 50 x 3.2 Mass (g) S-band Power Requirement (W) 10 80 Temperature Range (⁰C) -120 to 120 S-band S-band 5 5 95 x 46 x 15 150 x 180 x 30 100 130 -40 to 65 -40 to 45 Technology Readiness Level The Technology Readiness Level, TRL, is inherently important because it can help to ensure that the performance demands are met by the communication system. Choosing an initial TRL of 7 provides a system that has been adequately tested in relative environments. Although a TRL of 7 is still partially a prototype, the prototype may be developed further through funded testing to reach a TRL of 8. All three components (antenna, transmitter, and receiver) are at a TRL level of 7. They have been tested in the operational environment. The proposed advancement plan to bring the TRL level to 8 is further testing of the components. Interfaces The communications system contains interfaces with structures, C&DH, and GSS. C&DH sends data via the transmitter which in turn directs it to the antenna. The antenna downlinks the data package to the ground station. When uplinking, the data from the ground station is received by the antenna which sends the data to the receiver. The receiver sends the data to be processed by C&DH. 56 The electrical interfaces discussed consist of wiring. The three components have specific connectors which allow them to transmit and receive the data. The antenna uses an SMA female connector, the transmitter used a 12 way SMC connector and the receiver uses a TNC female connector. C&DH Transmitter Receiver Antenna GSS Figure 43. COMM interface chart with GSS The system also has a physical interface with the structure. All of the components are mounted on to the structure via M4 fasteners, with the antenna being mounted on the outside. The chart below details the outline of the operational process. The Communications Subsystem primarily works with C&DH and GSS. Safety and Mission Assurance In order to assure the survival and success of the COMM system, testing will be done on several aspects of the COMM system. Testing will ensure that the COMM system will satisfy all top level requirements in the environment of space. Testing will also be done to ensure that the COMM system will operate correctly despite experiencing forces and torques during rocket launch and de-tumbling of the satellite. Testing (to be done by supplier) a.) b.) c.) d.) e.) f.) Functionality Vibration Mechanical Shock Thermal Cycling Thermal Vacuum Total Ionizing Dose 57 Functional testing will be done to ensure the COMM system will operate as designed. The data rate, frequency, and RF output power will be measured to ensure that they meet the top level requirements. Vibration testing will be done to ensure the COMM system will last the length of the mission. Vibration testing will measure the fatigue life and resonant frequencies of the COMM system. Mechanical shock testing will be done to ensure the COMM system will last through the launch of the rocket and de-tumbling of the satellite. Shock testing will be the fragility or strength of the COMM system while being loaded. Thermal cycling testing, thermal vacuum testing and total ionizing dose (TID) testing will be done to ensure the COMM system will last in the environment of space. Thermal cycling will measure the COMM system’s ability to last while subjected to very high and very low temperature experienced in space. Thermal vacuum testing will ensure the COMM system will not experience a failure, such as outgassing, due to being in a vacuum. TID testing will ensure the COMM system will not fail due to degradation from ionizing radiation. Final Product The integration of the seven subsystem designs described in Satellite Subsystem Design create the final product. Figures 44a and 44b provide front and back views of the deployed satellite, respectively. Figure 44c provides an internal view of the satellite. Figure 45 provides an overview of the interfaces between the subsystems on BOSS. Figure 44a. Front view of fully deployed satellite. A sun sensor and the front faces of the DRAGONS and solar arrays are clearly visible. 58 Figure 44b. Back view of fully deployed satellite. Visible are the terminator tape deployables and a sunsensor. Figure 44c. Internal view of BOSS. All external components have been removed to provide better visibility. 59 Figure 45. Interfaces found on BOSS Operations The process of transmitting data from the satellite to BAI facilities starts with the communications system on the satellite. When in range of one of the selected ground stations, data will be transmitted from the satellite to one of four NASA ground stations. Applicable ground stations include Kennedy, Johnson, Whitesands, and Ames. STK based analysis concluded that the satellite will provide a communications window at least twice a day. The ground station(s) that the receive data for the particular day would forward it to BAI facilities. At BAI facilities, the health data acquired will require about an hour of analysis per day to conclude the satellite’s health status. As long as the health status is good, operations will continue normally. If the health status is deemed bad, the relevant subsystem will be consulted for analysis and troubleshooting. An STK analysis determined that each ground station will have about 400 seconds of contact with BOSS during the communications window. Since it was established that there will be a communications window at least twice per day between, sending data at 1 Mb/s would yield a maximum data transfer of at least 3200 Mb per day. The daily maximum amount of expected data collected by the satellite is 528 Mb, so all stored data will be transferred from the satellite daily. The process of uplinking commands to the satellite from the BAI facilities works very similarly to the downlink process. When commands need to be sent to the satellite, the commands are sent to the applicable NASA ground station to uplink the command when the satellite is within in 60 range. Confirmation that the commands have been completed will be downlinked to the applicable NASA ground station, and forwarded to BAI facilities. The confirmation data is verified by the same engineer observing health data. The data acquired from this mission will update current MMOD models, which is of great interest to the DOD and NASA, as well as non-government aerospace agencies. Therefore, it was negotiated that NASA ground stations will be used to communicate with BOSS at no cost to BAI, and with the understanding that NASA and other agencies will have access to the space debris data. Hence, the costs associated with GSS are purely labor related. The estimated cost of labor to monitor data would be $27,920 for 698 days at an average salary of $40/hour. Considerations were made for scenarios in which analysis and troubleshooting was necessary due to bad health status, so additional funds were allocated for this contingency. Risk The risks associated with the BOSS subsystems are outlined in the risk analysis matrix. Each risk has an associated criticality based on the severity and likelihood of the event to occur. A preventative action is outlined for each risk to ensure the risk is not fatal to the mission. The risk matrix for BOSS begins on page 62. 61 Failure Mode COMM Antenna Failure Transmitter Error Tracking Error Severtity (15) Liklihood (15) Criticality Failure Cause Failure Effects Detection Debris Impact Component Failure 5 1 5 COMM to GSS Power loss Loss of GSS COMM 4 2 8 COMM to GSS Not in range of station Loss of GSS COMM 2 3 6 COMM to GSS Preventative Action Position antennas out of impact zone Backup battery Attitude/Orbit Control Attitude/Orbit Control Improper orientation Unreliable contact with GSS 1 3 3 COMM to GSS Electromagnetic Interference Poor signal 2 5 10 COMM to GSS Improper Data Rate Poor signal 2 4 8 COMM to GSS High noise Loss of contact with satellite Poor signal 2 2 4 COMM to GSS Loss of GSS COMM 4 1 4 COMM to GSS Improper Timing Loss of GSS COMM 2 3 6 COMM to GSS Thermal Deterioration Component Failure 3 2 6 COMM to GSS Depris Imact Component Failure 5 1 5 COMM to GSS (Gyro) Drift 1. Decay of Gyros and their performance over time. 2. Could be severe in a short amount of time or minor over a long period of time. 1 1 1 Software Cross-check Data V&V (Gyro) Bias Stability 1. Changes over time creating more noise in signals. 2. Could produce more work at end of life in data analysis. 3. Could skew data 1 1 1 Software Cross-check Data V&V Filtering Durability Failure Insulation C&DH Data Adjustment System Reset/Filter Attitude/Orbit Control Attitude/Orbit Control Proper Themal Protection Proper Positioning OADC IMU Failure 1. Could cause temporary malfunction (Gyro) Random Walk in the software and Environmental hardware. Conditions 2. Causes switching of bits 2 3 6 (Gyro) Jitters 1. Causes Excess Vibration on unit 2. Could skew Data 1 2 2 Manufacturing Error 1. Contamination of Unit 2. Loss or failure of Unit 3. Loss of Gyro or Accel 5 3 15 Loss of power to one Gyro Loss of Gyro on one axis 3 1 3 Software Cross-check data Feedback Control Software Cross-check Data Cross-check data Cross-check Data Software "No real preventative Action as caused by environment" 2. Program software and Hardware to expect Random Error and recover. V&V V&V Improved Quality Assurance V&V Failure Mode Failure Cause Failure Effects Severtity (1- Liklihood (15) 5) Criticality Detection Preventative Action OADC V&V Test of system with loss of power. 2nd Redundant Sun Sensor 3 Software Cross-check Data 3 15 Software Cross-check Data V&V Improved Quality Assurance 3 1 3 Software Cross-check Data V&V Test of system with loss of power 1. Failure of the part before launch. 2. No GPS position data 5 3 15 Software Cross-check Data V&V Improved Quality Assurance Sign Interference from Torque Rods 1.Cause electromagnetic Interference 2. Skew all positional data of system. 3 2 6 Hard to detect V&V Loss of Power 1. Loss of control on one axis 2. Loss of control of spacecraft 3 1 3 Software Cross-check Data V&V Redundant 4th Wheel Manufacturing Error 1. Premature loss of control on one axis 2. Loss of control of spacecraft 5 3 15 Software Cross-check Data Quality Assurance V&V Redundant 4th Wheel Torque Rod Failure Manufacturing Error 1. Loss of control of spacecraft 5 3 15 De-orbit Module Failure Manufacturing Error 1. Spacecraft will not de-orbit in 25 year deadline 5 3 15 Loss of Power No sun sensor data 3 Manufacturing/Vibe Testing Error 1. Failure of the part before launch. 2. No sun sensor data 5 Loss of Power No relative positioning data Manufacturing Error 1 Sun Sensor Failure GPS Failure Attitude Determination (System) Reaction Wheel Failure Cross-check Data GPS altitude Data V&V Improved Quality Assurance Quality Assurance V&V 2nd Module Payload Sensor Unit(s) Failure Control Box Failure Resistive grid malfunctions No data will be produced from grid Wiring from box to unit Unable to store or becomes destroyed process data from unit 5 5 1 3 5 15 Loss of data from particular sensor to electronics box Environmental testing (thermal & vibration). Careful placement of computer by TPS. No sensor data in downlink Environmental testing (thermal & vibration). Use of space grade wires carefully placed where no impacts will occur. 63 Failure Mode Failure Cause Failure Effects Detachment latch malfunctions DRAGONS Sensor is rendered useless Severtity (1- Liklihood (15) 5) Criticality 5 2 Detection Preventative Action 10 Switches placed on Verify with mechanical stop functional test 4 Verify with functional test and Switches placed on meneuver satellite to mechanical stop ensure deployment failure, not Sensor failure. Deployment Failure Locking malfunction DRAGONS Sensor is not secure, data may become skewed Temperature range is exceeded No data will be transmitted between systems 5 2 10 Environmental testing (thermal & Sudden lack of any vibration). Careful data placement of computer by TPS. No payload data 5 1 5 Data shows zero hits Failure to begin detumbling 5 1 5 OADC Data would DITL Testing prior show to flight Failure to release EPS/sensors 5 1 5 Satellite would stop DITL Testing prior transmitting to flight No data is transmittedno debris data gathered 5 1 5 No release of data 1 2 2 Software/Data from Short Mission Life C&DH 5 1 5 Ensure Mechanism Software/Data from is purchased from a C&DH reputable source 4 2 8 Software/Data from Solar Cell Testing C&DH 2 1 2 Software 2 2 C&DH Computer Hardware Failure Software error in algorithm Hardware Error Programming Error Excessive vibrations during launch DITL Testing prior to flight Vibration testing prior to flight. EPS Battery Damage/Loss Degradation over time of Battery storage capacity Battery Failure Safety Mechanism Relay Fails Solar Cell Failure Cover Glass Failure Solar Array Failure 1. Batter over discharges 2. Battery over chargers Loss of Capable Power Production Individual Solar Cell Failure Cover Glass testing Testing of Software/Data from Deployment C&DH Methods Software/Data from Simulations of C&DH Impacts Deployment Failure Loss of Capable Power Production 4 2 8 Debris Impact Solar Cell Damage/Failure 1 4 4 Loss of Power to Motor Inability to Directe Solar Arrays at Sun 4 2 8 Software/Data from Simulations with C&DH Loss of Power Loss of Range of Motion Reduced Ability to Direct Solar Arrays at the Sun 2 2 4 Software/Data from Simulations with C&DH Partial Power Loss 4 2 8 Software/Data from Back up Electronics C&DH Gimbal Failure Failed Electronics/Interconnec Electronics/Interconnec Component Failure ts ts 64 Failure Mode Severtity (1- Liklihood (15) 5) Criticality Detection Preventative Action Failure Cause Failure Effects Large Debris Impact Satellite Failure and Mission Failure 5 1 5 Excess loading Satellite Failure and mission failure 5 2 10 Panel (2) attachment failure Unable to generate energy for satellites components 5 2 10 Loss of power Environmental testing (thermal & vibration). Dragon sensor attachment failure Unable to collect data on debris impact 5 2 10 Unable to generate debris impact data Environmental testing (thermal & vibration). Antenna (2) attachment Unable to communicate failure with satellite 5 2 10 Inability to communicate with satellite Environmental testing (thermal & vibration). Thermal mirror attachment failure 5 2 10 Environmental Overheating causing testing (thermal & multiple failures vibration). Attitude sensor & IMU Unable to maintain orbit attachment failure 5 2 10 Loss of orbit Environmental testing (thermal & vibration). CD&H attachment failure Unable to record and store data 5 2 10 Loss of data communication Environmental testing (thermal & vibration). Transmitter and receiver attachment failure Unable to communicate with satellite 5 2 10 Loss of Environmental communication with testing (thermal & satellite vibration). Damage from Debris Components exposed to harsh space environment 4 1 4 .Choose strong Components are not insulation material or operational under incorporate backup certain temperatures thermal protection Absorptivity of heat increases and reflectivity decreases 4 3 12 Components are not Protect the silver operational under with nichrome certain temperatures 2 Allowing testing to run for longer Components such as periods of time to Power system seem properly vacuum to underperform and running multiple tests. 2 Testing of assembled Components such as satellite. Multiple Power system seem loops of pipe as to underperform opposed to one large pipe. Structure Frame Structure Failure Deployment attachment failure Frame attachment failure Internal attachment housing failure Unable to reflect heat from satellite Environmental Complete failure of testing (thermal & satellite vibration). Environmental Complete failure of testing (thermal & satellite vibration). TPS Break in Multilayer insulation Exposed to space Aluminum Optical environment for long Solar Reflector Oxides periods of time Temperature and Vacuum space Environment Testing Error Thermistors stop recording data Lack of accurate testing due to false simulation of environment by either failing to test thermal cycles or not reaching perfect vacuum Thermal Protection System will underperform Failed electronics/ wiring Thermal protection temperature will be collected 1 2 2 1 65 Technology Readiness Level The technology readiness level matrix seen below detailed the overall TRL of the current components. A plan for advancement has been outlined for applicable components in their respective sections. Terminator Tape Function Appropriate Scale X X X X X X X X X X X X X X X X X X X X X X X X X Overall TRL Fit X X Form Unit Description Launch Operation X Space Environment X Relevant Environment Laboratory Environment Prototype Developmental Model Brassboard Flight Qualified Payload DRAGONS Sensor Hinges Spring Loaded Hold Down Release Mechanism Software C&DH On-board Computer Software COMMS Antenna Transmitter Receiver EPS Solar Arrays Power Conditioning Unit Battery Solar Array Gimbal Space Rated Electrical Wiring Distribution Bus Interfaces OADC GPS IMU Sun Sensor Reaction Wheels Torque Rods Breadboard Concept X Technology Readiness and Technical Performance Matrix Red = Below TRL 3 Demonstration Units Environment Yellow = TRL 3, 4 & 5 Green = TRL 6 and Above White = Unknown Exists X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X 66 Structure Mechanical Components Frame Side Panels Software Housing Reflective Mirror Support Attitude Sensor Housing/Support DRAGONS box fixtures Antenna Attachment/Support Transmitter and Receiver Attachment Mechanisms Solar Panel Deployment Mechanism Payload Deployment Mechanism TPS Multi-Layer Insulation Heat Pipes Solar Reflectors GSS BAI Facilities NASA Ground Stations X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X 67 Overall TRL Appropriate Scale Function Fit X X X X X X X X X X X X X X X X X X X X X X X Form Unit Description Launch Operation Space Environment Relevant Environment Laboratory Environment Flight Qualified Prototype Brassboard Breadboard Concept X Exists Developmental Model Red = Below TRL 3 Yellow = TRL 3, 4 & 5 Green = TRL 6 and Above White = Unknown Technology Readiness and Technical Performance Matrix Demonstration Units Environment Verification and Validation The verification of requirements is needed in order to ensure that all requirements are met for a successful mission. The requirements verification matrix below shows the requirements for the BOSS mission. Each requirement can be traced to the originating document and clearly states how it is to be verified. Verification Matrix Requirement No. 05.0 Payload 05.0 Document Shall Statement Verification Success Criteria MDR Payload instruments and sensors shall provide sufficient capabilities for debris detection method. The BOSS payload shall utilize 6 DRAGONS units to detect location and particle characteristics of small space debris in the near-Earth environment. Each DRAGONS unit shall have a maximum power consumption of 810 W. The BOSS payload shall utilize framework to structurally arrange DRAGONS units. 05.1 PDR Trade Study 05.1.1 DRAGONS Specs 05.2 DRAGONS Specs Verification Method Facility or Lab Phase Acceptance Requirement Preflight Acceptance Performing Organization Sensors provide Test sufficient data when impacted by a particle. Bravo Industries Testing Lab D Yes Yes Bravo Aerospace Industries Sensors provide location and energy data after impact with particle. Bravo Industries Testing Lab D Yes Yes Bravo Aerospace Industries Bravo Industries Testing Lab C Yes No Bravo Aerospace Industries Bravo Industries Testing Lab C Yes No Bravo Aerospace Industries Test The power required Test for operation of a DRAGONS unit is between 8 and 10 W. The structure is Analysis strong enough to securely hold the DRAGONS units in place in a space environment. 05.3 PDR Trade Study 05.4 PDR Trade Study The BOSS payload shall be folded compactly around the satellite frame during vehicle launch. The BOSS payload shall utilize a deployment mechanism from the satellite main framework in order to deploy the sensor array securely. The payload fits around the 0.6 m x 0.6 m x 0.6 m securely without protruding. Inspection Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries The sensor array deploys in space environment (vacuum) securely, with acceptable vibration and dampening time. Test Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries C&DH shall successfully collect and process data to be transmitted to the ground station. The C&DH shall transmit operations data to the COMMS. The C&DH shall send command data to the OADC. Data is collected and processed without error. Test Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries Data is transmitted without error. Test C Yes Yes Bravo Aerospace Industries Command data is transmitted without error. Test C Yes Yes Bravo Aerospace Industries The C&DH shall send command data to the payload. Command data is transmitted without error. Test Bravo Industries Testing Lab Bravo Industries Testing Lab Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries 06.1 C&DH 06.1.0 CDH MDR 06.1.1 CDH MDR 06.1.2 CDH MDR 06.1.3 CDHMDR 69 06.2 COMM 06.2.0 06.2.1 06.2.2 06.2.3 COMM The COMM shall Requirements successfully transmit “energy data” to ground station. COMM The COMM shall Requirements be capable of uploading data at a range greater than 700 km. COMMRequi The COMM shall rements utilize a gain greater than 0db. COMM The COMM shall Requirements have a minimum data rate of 1 Mb/s. 06.2.4 COMM The COMM shall Requirements utilize less than 15 W of power. 06.3 EPS 06.3.0 EPSMDR.pd f The EPS shall store and distribute adequate power necessary for operation of all electrical components at peak load. Data is transmitted without error. Test Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries Minimum range of 700 km for data transfer is satisfied. Analysis Bravo Industries Testing Lab C Yes No Bravo Aerospace Industries Satellite is able to successfully transmit readable data to the ground station. The data can be sent at a rate of 1 Mb/s Inspection Bravo Industries Testing Lab D Yes No Bravo Aerospace Industries Analysis Bravo Industries Testing Lab D Yes No Bravo Aerospace Industries The required power for operation is under 15 W. Analysis, Test Bravo Industries Testing Lab D Yes No Bravo Aerospace Industries Peak power load can be provided from battery and charged during sun exposure. Test Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries 70 06.3.1 06.3.2 06.3.3 06.3.4 06.4 OADC 06.4.0.1 EPS MDR The EPS shall provide power for the satellite for the duration of the three year mission. EPS The EPS shall Requirements generate power from the environment. EPS The EPS shall Requirements provide power to the components while not exposed to the Sun. EPS The EPS shall Requirements have a distribution bus to distribute adequate power to each subsystem. OADC The OADC shall Requirements determine the relative position of the spacecraft at impact. Solar panels and battery can same power at the end of the 3 year mission. Test Manufactur C er Facility Yes No Component Manufactur er Satellite can maintain power while in orbit, without carrying fuel. Power levels are maintained during the time period of no sun exposure Test Bravo Industries Testing Lab C Yes No Bravo Aerospace Industries Test Bravo Industries Testing Lab C Yes Yes Bravo Aerospace Industries The bus distributes power that each subsystem requests Test Bravo Industries Testing Lab D Yes Yes Bravo Aerospace Industries 1. Position data received by GSS 2. Control commands produce expected attitude changes. Test NASA Testing Facility D Yes Yes NASA 71 06.4.0.2 OADC The OADC shall Requirements determine motion relative to the Earth at impact. 06.4.0.3 OADC The OADC shall Requirements transmit positional 1. Attitude rate data received from satellite and meets expected motion. Test NASA Testing Facility D Yes Yes NASA Data successfully transmitted. Test NASA Testing Facility D Yes Yes NASA 1. Position data received by GSS Test Facility Last Yes Yes Bravo Industries 1. GPS signals are initiated; seen from GSS 1. GPS operates correctly within the voltage range Test Facility Last Yes Yes NASA Inspection Facility D Yes Yes NASA 1. GPS receives sufficient power to operate correctly for the input voltage 1. GPS signals are received every 20 milliseconds Inspection Facility D Yes Yes NASA Inspection Facility D Yes Yes NASA 1. GPS remains operational within given temperature range Inspection Facility D Yes Yes NASA data to the C&DH at impact. 6.4.1 GPS 6.4.1.0 ICD 6.4.1.1 ICD 6.4.1.2 GPS Spec Sheet 6.4.1.3 GPS Spec Sheet ICD 6.4.1.4 GPS Spec Sheet 6.4.1.5 GPS Spec Sheet GPS position data shall be transmitted to C&DH GPS shall receive commands from C&DH GPS shall operate for input voltage between 18 and 38 V GPS shall receive 5.5 W at 28 V unregulated from C&DH GPS shall update position with a frequency of 50 Hz. GPS shall operate between -20° and +50° C 72 6.4.2 IMU 6.4.2.0 CDR 6.4.2.1 CDR 6.4.2.2 ICD 6.4.2.3 CDR IMU shall process accelerometer and gyroscope measurements 1. Filtered data received, bias and noise levels within tolerance of filtering IMU shall 1. Error in determine relative orientation does not satellite orientation exceed 0.5° within 0.5° Filtered IMU 1. Data is received angular rates shall from satellite be transmitted to C&DH Satellite position 1. Data is received shall be from satellite transmitted to C&DH Test Facility D Yes Yes NASA Test Facility D Yes Yes NASA Test Facility D Yes Yes NASA Test Facility D Yes Yes NASA Sun sensor position data shall be transmitted to C&DH Sun sensor shall receive commands from C&DH Sun sensor shall determine the position relative to the sun within 1° Sun sensor shall operate at ±12 V 1. Sun sensor position data received by GSS after downlink 1. Sun sensors turn on after initial command. 1. Error does not exceed 1° Test Facility Last Yes Yes NASA Test Facility Last Yes Yes NASA Test Facility D Yes Yes NASA 1. Sun sensor operates at voltage Test Facility D Yes Yes NASA 6.4.3 Sun Sensor 6.4.3.0 ICD 6.4.3.1 ICD 6.4.3.2 Sun Sensor Spec Sheet 6.4.3.3 Sun Sensor Spec Sheet 73 6.4.3.4 Sun Sensor Spec Sheet Sun sensor shall use a maximum of 0.1 W 6.4.3.5 Sun Sensor Spec Sheet Sun sensor shall operate between 20° and +50° C 6.4.4 Control 6.4.4.0 MCR 6.4.4.1 CDR 6.4.4.2 MCR 1. Sun sensors are operating within acceptable power range 1. Sun sensor operates between temperature boundaries Inspection Facility Last Yes Yes NASA Test Facility D Yes Yes NASA Spacecraft shall maintain and adjust attitude autonomously Position and rate data logs show autonomous reaction to changing attitude Test Facility Last Yes Yes NASA Satellite shall maintain an autonomous orientation within 5° from desired Spacecraft shall maintain and adjust attitude as commanded Measured deviation from desired orientation in any axis is below 5° Inspection Facility D Yes Yes NASA Spacecraft responds Test to commands and reorients itself to given command Facility Last Yes Yes NASA Reaction wheels shall receive commands from C&DH Control commands produce expected attitude changes Facility Last Yes Yes NASA 6.4.5 Reaction Wheels 6.4.5.0 ICD Test 74 6.4.5.1 ICD Reaction wheels shall send angular velocity data to C&DH 6.4.5.2 ICD Reaction wheels shall operate between 1.8 and 10 W 6.4.5.3 Reaction Wheel Spec Sheet 6.4.5.4 6.4.5.5 Reaction wheel angular velocity data received by GSS after downlink Test Facility Last Yes Yes NASA 1. Reaction wheels draw power in expected range 2. Reaction wheels remain in standby at 1.8 W Reaction wheels 1. Reaction wheels shall operate at 17- operate properly for 35 V DC given voltage range Test Facility Last Yes Yes NASA Inspection Facility D Yes Yes CDR Reaction wheels shall provide orientation control within 0.5° Inspection Facility D Yes Yes NASA Reaction Wheel Spec Sheet Reaction wheels shall operate between -20° and +50° C Inspection Facility D Yes Yes NASA 1. Measured deviation from commanded orientation in any axis is below 0.5° 1. Reaction wheels operate properly in given temperature range Yes 6.4.6 Torque Rods 6.4.6.0 ICD 6.4.6.1 ICD Torque rods shall receive commands from C&DH Torque rods shall receive power regulated by C&DH 1. Torque rods turn on after given command 1. Torque rods receive power necessary during momentum dumps Test Facility Last Yes Yes NASA Test Facility Last Yes Yes NASA 75 6.4.7 Terminator Tape CDR Terminator tape shall deploy upon command 1. Terminator tape deploys when given command at end of life Test Facility Last Yes Yes NASA 06.5.0.1 Structure MDR The structure has the adequate strength to survive in the space environment for three years. Analysis Bravo Industries Analysis Lab 1 D Yes No Bravo Aerospace Industries 06.5.0.2 TPS MDR The structure shall maintain integrity and support subsystems throughout the three year mission life. The TPS shall maintain satellite and subsystems temperatures within ranges of normal operation. Subsystems remain at constant temperatures whether or not it’s in the Earth's shadow Test Bravo Industries Testing Lab D Yes No Bravo Aerospace Industries 06.5.1 Structure The satellite Requirements structure and The satellite frame and structure remain intact after launch. Also, all components in the interior of the satellite that are fastened to the satellite remain fastened after launch. Test Bravo Industries Testing Lab D Yes No Bravo Aerospace Industries 6.4.7.0 06.5 Structure/ TPS structural attachments shall withstand all forces and vibrations endured during launch. 76 06.5.2 06.5.3 06.5.4 06.5.5 07.0 Mission Operations 07.0 Structure The structure shall Requirements have all deployment systems stowed during launch. TPS The satellite shall Requirements be protected from the space environment (radiation) throughout the three year mission life. TPS The TPS uses Requirements copper heat pipes filled with ammonia to transfer heat between satellite components. TPS The TPS shall Requirements transmit temperature data to the C&DH. Top Level The Mission Requirements Operations shall generate a plan which allows for the success of the mission requirements. All deployment systems are stowed securely. Test Bravo Industries Testing Lab D Yes Yes Bravo Aerospace Industries Thermal insulation provides adequate shield from radiation in the environment. Analysis Bravo Industries Analysis Lab D Yes No Bravo Aerospace Industries Heat pipes must not deform, degrade, or lose physical properties when put under stress of environment Test Bravo Industries Testing Lab D Yes Yes Bravo Aerospace Industries Data is successfully transmitted. Test Bravo Industries Facility D Yes Yes Bravo Aerospace Industries Plan is successfully implemented. Inspection Bravo Industries Facility C No No Bravo Aerospace Industries 77 08.0 Launch Vehicle 08.0 Top Level The launch vehicle Requirements shall safely deliver BOSS to a 700 km polar orbit. Launch vehicle safely delivers the satellite to specified orbit. Analysis, Test Facility D Yes Yes Space Exploration Technologies Corporation A ground station can communicate with the satellite at least once per day. Analysis Facility C Yes No Bravo Aerospace Industries Receive and review the health data for an hour each day. Inspection Facility D Yes No Bravo Aerospace Industries Facility D Yes No Bravo Aerospace Industries 09.0 GSS 09.0 09.1 09.2 GSS The GSS shall be Requirements able to downlink and uplink data to the satellite at least once per day. GSS The GSS shall Requirements monitor the health information (power, temperature, electrical component status) of the satellite and payload for one hour per day. GSS The GSS shall be Requirements able to send commands to ground stations for uplink to satellite at least once per day. Have ability to send Test commands to satellite once a day 78 09.3 GSS At least one Requirements NASA ground station shall be able to receive data from the satellite at least once per day. Satellite is in range and satellite antenna downlinks data to NASA ground stations at least once a day Analysis Facility D Yes No Bravo Aerospace Industries The validation table below ensures that proper testing is done and validated by the customer, NASA. The validation table states the validation parameters based on the mission’s ConOps and how each parameter is to be validated. Validation Product # 5.0 Payload 5.0 Activity Objective Validation Method Facility or Lab Phase Performing Organization NASA/ DRAGONS developers verify capability of three detections technologies function Ensure payload systems detect impacts accurately and individual detections systems are compatible with each other Tests C Bravo Aerospace Industries/ USNA 5.1 NASA will verify six DRAGONS Ensure six DRAGONS unit Expert unit layout consistent with CDR present, functioning, and in Inspection design technical drawings an acceptable debris detection layout Two-stage light gas gun facility of the University of Kent Bravo Industries Testing Lab C Bravo Aerospace Industries/ NASA 5.2 NASA validate energy consumption of individual and combination of all DRAGONS unit(s) system To ensure each DRAGONS unit is consuming at max 8-10 W of power Test Bravo Industries Testing Lab C Bravo Aerospace Industries/ NASA 5.3 NASA validate rigid and acceptable structure to arrange and contain DRAGONS units throughout mission Confirmed designed Structure will be suitable for mission requirements and lifetime Test ( Vibrations and Load testing) Bravo C Industries Testing Lab/ Vibrational Bravo Aerospace Industries/ NASA/USN 79 Analysis Lab/Compa ny A 5.4 NASA validates that’s DRAGONS compactly fold onto satellite structure. Payload system compactly fits around 0.5 x 0.6x 0.6 m^3 satellite structure Expert Inspection Bravo Industries Testing Lab C Bravo Aerospace Industries 5.5 NASA validates that payload system deploys fully and communicates via micro switches of successful deployment. Ensure system fully deploys for accurate measurements and that GSS will confirm deployment during mission Test Bravo Industries Testing Lab C Bravo Aerospace Industries Customer will evaluate computer software 1. Ensure desired modes are achieved DITL Testing Bravo Industries Testind Lab A NASA Customer will evaluate the energy Ensure quality of "energy data transferred to the ground data" is acceptable Test Bravo Industries Testing Lab C Bravo Aerospace Industries 6.2.1 Customer will evaluate the maximum range of the COMM system Ensure range of the COMM system is acceptable Analysis Bravo Industries Testing Lab C Bravo Aerospace Industries 6.2.2 Customer will evaluate the gain of the antenna Ensure the gain of the antenna is acceptable Inspection Bravo Industries Testing Lab C Bravo Aerospace Industries 6.1 C&DH 6.1 6.2 COMM 6.2.0 80 6.2.3 Customer will evaluate the data rate of the COMM system Ensure the data rate is acceptable Analysis Bravo Industries Testing Lab C Bravo Aerospace Industries 6.2.4 Customer will evaluate the power required of the COMM system Ensure the power required is acceptable Analysis, Test Bravo Industries Testing Lab C Bravo Aerospace Industries Customer will evaluate the storage capacity of the battery Ensure battery capacity is large enough for a peak power load from components Battery Storage Test Bravo Industries Testing Lab C Bravo Aerospace Industries 6.3.1 Customer will evaluate the life of the EPS subsystem components Customer will evaluate the ability of EPS to collect power from the environment Bravo Industries Testing Lab Bravo Industries Testing Lab C 6.3.2 Ensure all components will Degradalast the length of the tion Tests mission Ensure the satellite can Test maintain power without the need to carry fuel Bravo Aerospace Industries Bravo Aerospace Industries 6.3.3 Customer will evaluate the storage capacity of the battery and length of earth eclipse Customer will evaluate the success of EPS's distribution bus and voltage regulation Ensure the battery isn't over-discharged during eclipses Ensure the bus distributes correct power to different components Ammeter Test Bravo Industries Testing Lab Bravo Industries Testing Lab C Customer will evaluate the wiring used with the electrical components Ensure the wiring is space grade and will withstand space environment Vacuum Test Bravo Industries Testing Lab C 6.3 EPS 6.3.0 6.3.4 6.3.5 Ammeter Test C C Bravo Aerospace Industries Bravo Aerospace Industries Bravo Aerospace Industries OADC 81 6.4.0 Customer will evaluate spacecraft relative position determination 1. Determination system is operating properly 2. Relative position data is accurate Test Facility D NASA 6.4.1 Customer will evaluate spacecraft relative motion determination Determination system is operating properly 2. Relative motion data is accurate Test Facility D NASA Check flight computer data Flight computer is receiving position data Test Facility C Bravo Industries 6.4.2.2 Check operating voltage of the GPS Verify if the operating range is acceptable. Test Facility C Bravo Industries 6.4.2.3 Determine power draw of the GPS Verify GPS receives approximately 5.5W at 28 V unregulated Test Facility C Bravo Industries 6.4.2.4 Test and refine GPS refresh rate. GPS updates position at the Test appropriate frequency Facility C Bravo Industries 6.4.2.5 Thermal test of GPS Verify that GPS operates within the thermal boundaries Test Lab C Bravo Industries Verify the IMU flight computer correctly processes the accelerometer and gyroscope measurements Test University C University 2. Bravo Industries Verify final attitude output from the IMU is accurate to within 0.5 degrees Test University C University 2. Bravo Industries 6.4.2 GPS 6.4.2.1 6.4.3 IMU 6.4.3.0 Check filtered angular rates from IMU 6.4.3.1 Check position output from IMU 82 6.4.3.2 View data sent to C&DH Flight computer receives filtered angular rates 2. Flight computer receives position data Test Facility C Bravo Industries 6.4.4 Sun Sensor 6.4.4.0 Check flight computer data Flight computer receives sun sensor position data Test Facility C Bravo Industries 6.4.4.1 Check sun sensor commands from C&DH Verify that sun sensor receives inputs from the flight computer. Test Facility C Bravo Industries 6.4.4.2 Check position output of sun sensors Sun sensor position data is within 1 degree Test Facility C Bravo Industries 6.4.4.3 Check operating voltage of sun sensors Sun sensors operate for an acceptable voltage Test Facility C Bravo Industries 6.4.4.4 Check power draw of sun sensors Sun sensors draw acceptable power Inspection Facility C Bravo Industries 6.4.4.5 Thermal test of sun sensors Verify that the sun sensors operate within the thermal boundaries Test Lab C Bravo Industries 6.4.5 Control 6.4.5.0 Analyze satellite attitude data Verify autonomous control Test is achieved using data provided by flight computer and control system Verify active (commanded) Test control is achieved using data provided by flight computer and control system Facility D Bravo Industries Facility D Bravo Industries 6.4.5.1 Analyze satellite attitude data after commands 83 6.4.6 Reaction Wheels 6.4.6.0 Check reaction wheels' reaction to commands Verify commands are received from by the flight computer Test Facility C Bravo Industries 6.4.6.1 Check flight computer data Test Inspection Facility C Bravo Industries 6.4.6.2 Check power draw of reaction wheels Verify flight computer receives angular velocity data from the reaction wheels Verify reaction wheels receive the appropriate power Test Inspection Facility C Bravo Industries 6.4.6.3 Check operating voltage of reaction wheels Verify reaction wheels operate within advertised voltage range Test Inspection Facility C Bravo Industries 6.4.6.4 Thermal test of reaction wheels Verify that the reaction operate within the thermal boundaries Inspection Facility C Bravo Industries 6.4.7 Torque Rods 6.4.7.0 Send commands to torque rods Verify commands received from the flight computer Test Facility C Bravo Industries Determine power draw of the torque rods Power draw of torque rods is within acceptable ranges Test Facility C Bravo Industries Check commands sent by flight computer Review that the flight computer sends command to deploy the terminator tape Test Facility C Bravo Industries 6.4.7.1 6.4.8 Terminator Tape 6.4.8.0 84 6.4.8.1 6.5.0 Structure 6.5.0.1 6.5.0.2 6.5.1 TPS 6.5.1.1 6.5.1.2 6.5.1.3 6.5.1.4 6.5.1.5 Deployment of the terminator tape Terminator tape receives command and deploys Inspection N/A C NASA Customer will evaluate the response of the structure to launch conditions (loads and associated vibrations). Customer will evaluate the response of the structure and its components to high heat conditions Ensure the structure can survive launch intact. Analysis and then Test Bravo Industries Testing Lab C Bravo Aerospace Industries Ensure that the structure will burn up in de-orbit. Analysis Bravo Industries Testing Lab C Bravo Aerospace Industries Customer will evaluate that the TPS is operational passively with little electrical consumption Use of battery and electrical wiring only needed for temperature sensors Battery Test Facility C Bravo Aerospace Industries Customer will evaluate the MLI that protects a satellite with the dimensions of 0.6m x 0.6m x 0.5m from radiation Customer will evaluate the optical solar reflectors to reduce absorptivity Customer will evaluate the temperature sensors within the satellite Subsystems remain at constant temperatures whether or not it’s in the Earth's shadow Reflectivity shall be larger than 90% Radiative Heat Transfer Test Spectropho tometry Test Environme ntal Test Chambers Lab C Bravo Aerospace Industries Lab C Lab C Bravo Aerospace Industries Bravo Aerospace Industries Customer will evaluate the durability of the TPS The TPS will be functional for two years in the harsh space environment Testing Lab C The satellite must be kept between -10०C and 30०C Bravo Aerospace Industries 85 System Performance Requirements Flow down Chart Release Latch Error Sensor Deployment Incomplete Deployment Thermal Deformation Hinge Damage Switch Activation Payload Allocation Error Powe/Data Unregistered Particle Hit Impact Error Hardware C&DH Recieve data Ricochet Off Strucutre Software Transmit data Software System Performance Requirements Uplink Emergancy Commands Size/Mass Constraints Hardware Receiver Capabilities COMM SNR Hardware Transmission Range Downlink Data Rate Software Transmission Quality Orientation Error Power Generation Solar Panels Exposure Error Time of Orbit in Sun Error Solar Panel Sizing Error Battery Overcharged EPS Power Storage Storage Degredation Battery Over Distcharged Degradation Error Thermal Failure Power Distribution OADC Error C&DH Error Voltage and Current 28V Distribution Payload Error COMMS Error System Performance Requirements chart is continued on the next page. GPS Positioning Sun Sensor Sunsensors Rate IMU IMU Attitude OADC Sun sensors Three-axis control Reaction Wheels Torque rods Solar Panel Mechanism Deployment Dragon Sensors Structure System Performance Requirements Antennas Structural Integrity Electrical Housing Frame Integrity Multilayer Insulation Debris Damage Outgassing TPS Temperature Control Passive Control Degradation Heat Pipes Deformation Optical Solar Reflectors Uplink Antenna Downlink Antenna Oxidation Communication GSS Ground Station 87 Project Management Statement of Work The statement of work (SOW) contains the process management must follow during development. This allows for analysis of the work that needs to be accomplished. It also allows for accountability. The statement of work begins with a set of requirements that BAI must meet. SOW Requirements: BAI shall design a satellite capable of meeting the mission’s objectives and constraints. BAI shall develop verification methods for all system designs. BAI shall be responsible for the execution of the verification process. BAI shall be responsible for the operations of BOSS for the life of the mission. To ensure that all SOW requirements are met, a work breakdown structure (WBS) must be created. The WBS supports, manages, and oversees development of BOSS. A WBS has been developed and is shown in figure 5. BOSS Project Project Management Budget Schedule Deliverables Ground Segment Systems Engineering System Requirements Verification Ground Support Operations Launch Flight Segment Subsystem Leads Design Integration, Test, & Verification Interfaces Fig 5. Work breakdown structure. The work breakdown structure shown contains only the elements which apply to the management of the BOSS project. Subsystem leads include leads for OADC, TPS, EPS, C&DH, COMM, Payload, and Structures. Team Structure Budget Launch Services The Falcon 9 will carry BOSS to its orbit as a secondary payload to minimize costs. At approximately $4,000 per kilogram, the Falcon 9 offers the best value as a launch vehicle. Figure 2 displays costs comparisons to similar launch vehicles. Once launch services and contingency are factored into the cost of launch, BOSS will have an estimated launch price of $2.2 million. 89 Figure 2. At a maximum payload, the Falcon 9 offers a substantially lower launch price than its competitors. 6 Project Cost A cost analysis was performed for BOSS for the PDR, and has been refined and updated for the CDR to more accurately represent the actual cost. Year 1 Year 2 Year 3 Year 4 Year 5 $9,000 / mo $7,000 / mo $5,000 / mo $5,000 / mo $816,000 $505,000 $250,000 $816,000 $520,000 $250,000 $200,000 $220,000 $200,000 $200,000 $200,000 $200,000 $200,000 30% 30% 30% 30% $244,800 $151,500 $45,000 $244,800 $156,000 $75,000 $182,400 $126,200 $60,000 $60,000 $60,000 $60,000 $60,000 Salary Base Rate Senior Personnel Junior Personnel Technician Admin Personnel Fringe Benefits Senior Personnel Junior Personnel Technician Admin Personnel Materials & Supplies Structures 12 mm Screws 16 mm Screws Raw 6061 Aluminum $7.95/25 screws $8.59/25 screws $1.74/kg Honeycomb 6061 Aluminum Approx. $45 per panel COMM Transmitter $12,000 $87.45 $25.77 $65 $65 $270 $12,000 90 Receiver Antenna EPS Solar Arrays Solar Array Gimbal Lithium Ion Battery Surrey 150 Power System Wiring Payload Shroud (6) Sensor and control box (6) Hinge (12) Release mechanism (5) Bolt (130) Washer (130) Nut (130) C&DH On-Board Computer COTS Software TPS Kapton Film Aluminized Teflon Solar Reflector Mylar Sheets Elastisol Adhesive Beta Cloth Netted Spacer 6061 T6 Aluminum Sheet 4mm thick $10,000 $16,000 $10,000 $16,000 $68,300 $30,000 $68,300 $30,000 $10,650 $10,650 $12,250 $12,250 $10,000 $10,000 $0 $0 $0 $0 ~$600 $110 $7200 $550 $12.46 per pack of 100 $24.92 $5.98 per pack of 5 $2.77 per pack of 5 $155.48 $19.39 $64,350 $13,750 $176.18/m2 $11071.90/m2 $338.27 $21258.04 $26.91/m2 $0.34/mL $51.67 $153.85 $269/m2 $800/coil $110/ 840000mm2 $516 $800 $110.00 Hook and Pile Tape 25mm wide OADC $68.61/ 22860mm $68.61 Accelerometer Ring Laser Gyroscope Sun Sensor (2 $6,545 $15,550 $39,270 $46,650 $102,500 $102,500 91 unit package) GPS Reaction Wheels (4 unit package) Torque Rods IMU Computer De-orbit module(Nanosat Terminator Tape) 6061 T6 Aluminum (24mm) 6061 T6 Aluminum (6 mm) M6 #3 Machine Screws M3.5 #2 Machine Screws M5 #2 Machine Screws Subcontracts Payload Manufacturing and assembly OADC University Equipment Structures Aluminum manufacturing equipment (mill, cnc, etc) EPS Misc Electrical Equipment Verification/ Testing COMM Flight testing Payload Vibration testing Structures Vibrations Test Launch Loads Test $277,100 $374,500 $277,100 $374,500 $14,000 $34,000 $65,000 $42,000 $34,000 $130,000 $216.00 $432.04 $242.14 $484.28 $5.97 $5.97 $9.66 $9.66 $8.16 $8.16 $40 / hour $1000 $40,000 $80,000 $3,000 $8,000 $1,000 $2,000 $12,000 $500 $10,000 $40,000 92 General Strength and Fatigue testing C&DH DITL Testing Other Structures Contingency Launch Services Total Total Cost $10,000 $500/hr $2,500 $25,000 $3,396,555 $25,000 $10,000 $2,200,000 $2,171,248 $3,537,000 $10,150 k $5,000 $5,000 $525,000 $525,000 Mass Component COMM Antenna Receiver Transmitter EPS Solar Arrays Solar Array Gimbal Lithium Ion Battery Surrey 150 Power System Wiring Payload Shroud (6) Sensor and control box (6) Hinge (12) Nut (130) Bolt (130) Washer (130) Release mechanism (5) Structures 2 Side Panels (B) 2 Side Panels (A) 2 Top Panels 4 Side Webs Frame 320 Screws 32 Brackets Internal Shelf C&DH On Board Computer TPS Kapton film Mass (kg) 0.08 1.3 1.0 1.84 1.2 0.786 3.92 1 4.08 13.38 18.00 .6 .8532 .048 1.5 3.376 3.298 4.176 17.92 6.743 1.728 .296 4.51 0.07 0.46 93 Solar Reflectors Mylar Sheets Adhesive Radiation Protection Boxes OADC Accelerometer(6 units) Ring Laser Gyroscope(3 units) Sun Sensor (2 unit package) GPS Reaction Wheels (4 unit package) Torque Rods(3 units) IMU Computer Nanosat Terminator Tape (2 units) IMU Shroud IMU Mount Contingency (20%) Total 0.149 0.0312 0.581 5 0.426 1.362 0.6 0.95 10.4 3.6 0.7 1.6 2.98 8.29 25.75 154.6 Schedule To evaluate BAI’s performance, standards must be established. Since project management is intangible, a verification process may not be possible. Therefore, BOSS’s project management will be evaluated based on the execution of the established schedule and meeting the budget constraints To ensure mission success in a timely matter, a robust schedule containing a critical path to success will be followed. The schedule contains milestones which represent events such as launch, deliverables’ due dates, and end of mission. The appendix contains a gant chart which outlines the schedule for the BOSS project. Table X provides an overview of BOSS’s schedule. Table X. An overview of the BOSS project’s schedule Milestone Deadline Phase SIR 09/2014 C TRR 10/2014 D ORR 04/2015 D FRR 11/2015 D Launch Q2 2016 E PLAR 11/2016 E CERR 06/2017 E End of Operations 03/2018 DR 06/2018 F End of Mission 07/2018 - 94 The phases shown in table X represent are defined in NASA’s Systems Engineering Handbook. However, the BOSS project timeline can be split into segments defined by BAI as follows: Fabrication: Fabrication lasts approximately nine months. During this time, subsystem components will be purchased and/or manufactured and assembled. Staff will be employed for Structures, C&DH, TPS, COMM, OADC, EPS, and Payload to complete this timeline segment; with most capital being focused on Structures and OADC. Integration and Testing: Integration and testing will last approximately fourteen months. This portion of the schedule will incorporate the various subsystems assemblies into the final product. It also includes verification and testing. Staff will be employed for Structures, C&DH, TPS, COMM, OADC, EPS, and Payload to complete this timeline segment. The C&DH team will devote most of their resources towards programming, which will continue to launch. Operations: Operations begins at launch and lasts approximately 22 months. During this portion of the project, personnel for GSS and project management will be employed. Operations concludes at the initiation of de-orbit. References 1. Kelso, TS, “Analysis of the Iridium 33 and Cosmos 2251 Collision”, Advanced Maui Optical and Space Surveillance Conference, September, 2009 2. Garcia, Mark, “Space Debris and Human Spacecraft”, http://www.nasa.gov/mission_pages/station/news/orbital_debris.html#.UnHnuSeMlb4 3. Liou, JC; Adilek, Albert; Burchell, Mark; Corsaro, Robert; Giovane, Frank; “DRAGONS- A Micrometeoroid and Orbital Debris Impact Sensor” , NASA Orbital Debris Program Office , 2012 4. Kapurch, Stephen J. “NASA Systems Engineering Handbook”, DIANE Publishing, 2010 5. Tsao, Ngo, Anderson, Sadilek, Pisacane, Giovane, Corsaro, Burchell, Stansberry, Liou; “Prototyping and Testing a Debris Resistive Acoustic Grid Orbital Navy Sensor” , United States Naval Academy, 2011 6. Wang, Brian, “Upgraded Spacex Falcon 9.1.1 will launch 25% more than old Falcon 9 and bring price down to $4109 per kilogram to LEO” , http://nextbigfuture.com/2013/03/upgraded-spacex-falcon-911-will-launch.html 7. http://orbitaldebris.jsc.nasa.gov/faqs.html 8. Fitz-Coy, N. “Class Notes 8/26/13.” Aerospace Deisgn 1. Fall 2013. 9. Crassidis, John L, & Markley, Flandis (1996, May). Attitude estimation using modified Rodrigues parameters. In NASA CONFERENCE PUBLICATION (pp. 71-86). NASA. 10. Nagabhushan, Vivek; Fitz-Coy, Norman G. & Johnson, Shawn C. Estimation of spacecraft angular acceleration using linear accelerometers. 11. IN SITU MEASUREMENT ACTIVITIES AT THE NASA ORBITAL DEBRIS PROGRAM OFFICE 12. Space Mission Analysis and Design (3rd edition). Microcosm Inc. 1999. 13. http://www.honeybeerobotics.com/flight-programs/44-hinge 95 14. Type 11 biaxial gimbal. (n.d.). Retrieved from http://www.moog.com/literature/Space_Defense/Spacecraft/Spacecraft_Mechanisms_Pro duct_Catalog2.pdf 15. Small satellite solar panels datasheet. In (2012). Small Satellite Solar Panels Datasheet. Clyde Space. Retrieved from http://www.clyde-space.com/documents/2625 16. Power system 150. In (2013). Surrey Satellite Technology LTD. Retrieved from http://www.sstl.co.uk/getattachment/80c25f64-d725-4907-b942-a3df147cac16/PowerSystem-150 17. Space qualified batteries. In (2011). Clyde Space. Retrieved from http://www.clydespace.com/documents/2343 18. Levins, D. (n.d.). Protection concepts used in spacecraft power systems. Noordwijk, Netherlands. 19. http://andrews-space.com/torque-rods/ 20. F. Beer, R. Johnston, et al., Mechanics of Materials, 6th ed. Boston, MA: McGraw-Hill, 2012, App. B. 21. http://oce.jpl.nasa.gov/practices/1205.pdf 22. http://www.sncspace.com/ss_space_technologies.php 23. http://spacemath.gsfc.nasa.gov/weekly/3Page25.pdf 96 Appendix Acronyms AC – Alternating Current BAI – Bravo Aerospace Industries BOSS – Bravo Orbital Space Satellite C&DH – Command and Data Handling CMG – Control Moment Gyroscope COMM – Communications COTS – Commercial Off-the-Shelf DC – Direct Current DOD – Department of Defense DRAGONS – Debris Resistive Acoustic Grid Orbital Navy Sensor EPS – Electrical Power System GEO – Geostationary Orbit GPS – Global Positioning System GSS – Ground Support System IMU – Inertial Measurement Unit LEO – Low Earth Orbit MLI – Multi Layer Insulation OADC – Orbital Attitude Determination and Control PCDU – Power Conditioning Distribution Unit PV – Photovoltaic SOW – Statement of Work STK – Systems Tool Kit TPS – Thermal Protection System TRL – Technology Readiness Level 97 Limited Life Items List OADC Reason for selecting Item Life Requirements Potential Impact on mission parameters Item Part Number Reaction Wheel Surrey 100 SP-0 The satellite requires threeaxis control. Torque provided is sufficient for this class of satellites. At least 2 years Loss of control of two or more wheels will prevent full control of satellite’s attitude. Torque Rod Andrews TQ-40 Momentum bias that accrues from the reaction wheels must be dumped. At least 2 years Sun Sensor Surrey 2-Axis GMC Sun Sensor Orientation of satellite relative to sun will allow EPS to generate more power by orienting the solar panels. At least 2 years Complete failure of a torque rod will allow momentum bias to build along an axis, preventing accurate control of the satellite. Failure of a sun sensor will reduce knowledge of position and may hamper ability to position the solar panels for maximum power generation. Surrey SGR-20 Knowing satellite’s position relative to GPS satellites will allow for determination of orbital position. At least 2 years Accelerometers: Honeywell Knowledge of orientation is At least 2 years GPS Augmented IMU Failure of GPS will reduce onboard knowledge of orbital position; further position would need to be determined by NORAD TLEs. Failure of any accelerometer Plan Tests of accuracy of control in desired configuration for conditions more severe than expected will be performed to determine efficacy. Momentum dumping ability will be tested on the ground to determine efficacy and optimal placement on satellite. Position data during all orbits will be simulated to make sure that positions on satellite are optimal. Signal test on ground to determine accuracy and optimal placement of receivers on satellite. Test of configuration to 98 Terminator Tape QA3000-010 Gyroscopes: Honeywell GG1320 required to accurately resolve impacts on the DRAGONS sensor and orient the spacecraft; to advance the capabilities of small satellites. Nanosat Terminator Tape Satellite must deorbit within 25 years of endof-life, this method will allow for deorbiting within that time frame. At least 5 years will reduce accuracy of angular acceleration along that axis; Failure of a gyroscope will reduce angular accuracy. Complete failure of IMU will prevent accurate determination or control of satellite and will render it unable to distinguish impacts. Failure to deploy either strip will delay deorbiting of the satellite, potentially beyond the required deorbit period. determine accuracy compared to simulation and to find optimal placement inside the satellite. Sending deploy command will be simulated to ensure arrival of signal. C&DH Item Part Number High Performance Flight Computer Andrews Model 160 Reason for selecting Item Provided desired interfaces and sufficient flash memory. Life Requirements Potential Impact on mission parameters Plan 3 years Provides central processing for entire satellite. DITL testing to verify system. Life Requirements Potential Impact on mission parameters Plan Failure of transmitter will result in a loss of communication and data transmission We are going to test the transmitter at both high and low frequencies at extreme COMM Item Transmitter Part Number Reason for selecting Item The transmitter will be used to send data to the ground station at the desired At least 2 years 99 frequency and band-width Receiver The receiver will be used as a way to stay in contact with the ground station. The receiver will be used to receive emergency commands as well as normal operation instructions The patch antenna is small and flat to allow for a more aerodynamic design. It also allows for a wider beam angle Antenna At least 2 years Losing the receiver will result in complete loss of control with the satellite. At least 2 years The patch antenna is the primary way to send signals to the ground stations data rates. We will also test transmitting in hazardous weather conditions We are going to test the receiver at both high and low frequencies at extreme data rates. We will also test transmitting in hazardous weather conditions We are going to test the antenna at both high and low frequencies at extreme data rates. We will also test transmitting in hazardous weather conditions EPS Item Battery Solar Arrays Part Number Reason for selecting Item Battery is needed to store power generated from the solar arrays to be used by the components of the satellite when in the eclipse of the orbit Solar arrays are Life Requirements At least 2 years (Life of Mission) At least 2 years Potential Impact on mission parameters Failure of battery would result in inability to store power and therefore inability to power components in the eclipse of the orbit Failure of solar Plan Battery storage test along with battery degradation test along with safe positioning to avoid radiation/ interference; overcurrent protection Solar panel 100 used to collect power from the sun’s solar rays to be saved to the battery to power the satellite’s components Gimbal will be used in junction with attached hinge to orient the solar panel such that the solar cells are normal to the incoming sun rays BCM/PDM will be used to regulate and deliver desired voltages from battery to components Gimbal Battery Conditioning Module/ Power Distribution Module (Life of Mission) arrays would result in inability to generate power and prevent all components getting power degradation tests along with solar panel stress tests; radiation, vibration and thermal cycling tests At least 2 years (Life of Mission) Failure of gimbal would result in inability to aim solar arrays at the sun and would severely limit power production Perform simulations with loss or partial loss of power, vibration and thermal cycling tests At least 2 years (Life of Mission) Failure of BCM/PDM would result in incorrect voltages or no voltages making their way to components Perform ammeter test, internal redundancy, over voltage protection system Payload Item DRAGONS Sensor Part Number Reason for selecting Item The sensor will be used to collect data on MMOD and estimate the size of the impact, impact speed, and impact direction. Life Requirements At least 2 years (For the duration of the mission) Potential Impact on mission parameters Failure of a DRAGONS unit lessens the detection area necessary for characterizing the orbital debris and limits the amount of data being transmitted for the mission. Plan Because the sensors are donated, in-house tests will be conducted by the supplier to ensure that the sensors will last the duration of the mission. STK analyses will be run to ensure that the estimated number of hits will not surpass the area of the sensors during the product’s lifetime. 101 Structures Item Part Number Brackets (32) Reason for selecting Item Life Requirements Component was needed to hold the side webs to the frame of the satellite during launch/flight 2 years (Life of Mission) Potential Impact on mission parameters Failure of brackets could cause the webs to detach from the frame, resulting in potential structural collapse Screw failure could cause the webs to detach from the frames or the panels to detach from the rest of the structure, leading to structural collapse or the exposure of internal components to the space environment See above Brackets to be placed under both load analysis and also launch loads/vibrations testing to ensure survival during launch/flight. Frame components will be put through load analysis software and also through launch loads and vibrations testing to ensure structural integrity throughout the mission. Again, panels will be extensively analyzed using software and actual 12 mm M6x1.0 Screws McMaster-Carr256 Used to fasten the side webs to the brackets and frame 2 years (Life of Mission) 16 mm M6x1.0 Screws (McMaster-Carr – 64) Used to fasten the panels to the frame Used to hold the satellite together during the mission life 2 years (Life of Mission) 2 years (Life of Mission) Frame failure will lead to the webs and panels collapsing into satellite, ruining most electrical components and ending our mission. Used to shield the satellite’s internal components from the space 2 years (Life of Mission) Panel failure will expose the interior of the satellite to the space Frame Components (12) Panels (8) Plan Screws are COTS from McMasterCarr and have been tested to withstand launch loads/vibrations See above 102 environment. Honeycombed 6061 Aluminum used to reduce mass. Side Webs (4) Used to provide structural support to the satellite during mission as well as give locations to attach other components to the inside or outside of satellite 2 years (Life of Mission) environment and potentially destroy any components attached to that panel (the antenna, solar arrays, payload, etc.) Web failure will decrease structural strength at that side of the satellite and could cause the collapse of its attached panel. It could also lead to the failure of any subsystems that have components attached to it (such as the TPS sensors or the sun sensors) loads/vibrations tests to ensure integrity throughout the mission life. Webs will be placed through launch loads and vibrations tests after passing computer analysis to ensure failure does not occur during mission. TPS Item Part Number Multi-Layer Insulation Thermistors Reason for selecting Item The satellite requires overall thermal protection for interior components. Measurement Specialties, Inc. ESCC Surface Sensors Affordable, lightweight, small and space heritage. Potential Life Impact on Requirements mission parameters At least 3 Individual years components decrease in efficiency, capabilities or function when outside of its temperature range. At least 3 Feedback of years component temperatures in the event of Plan Test degassing for durability and test thermal cycles in vacuum chamber as well Momentum dumping ability will be tested on the ground to determine 103 Series Radiation Protection Shield 4mm thick 840000𝑚𝑚2 6061 T-6 Aluminum sheet (McMasterCarr) Orientation of At least 3 satellite years relative to sun will allow EPS to generate more power by orienting the solar panels. overheating they can be turned off or change mode. Lack of appropriate radiation shielding can lead to failure or malfunction of electronic components efficacy and optimal placement on satellite. Sheet metal construction. Will undergo vibrational testing when coupled with the satellite. 104 Drawings EPS Drawing of the Clyde Space lithium ion battery with dimensions [4] 105 Drawing of the MOOG Type 11 Biaxial Gimbal with dimensions [1] Drawing of the deployed solar array 106 Drawing of the folded solar array Payload 107 108 109 110 111 112 Structures 113 114 115 116 117 118 119 Communications 120 OADC 121 122 123 124 Gant Chart 125 126