1 - DWA

advertisement
REPUBLIC OF SOUTH AFRICA
District
Municipality Logo
DISTRICT MUNICIPALITY NAME …….
TENDER No ……..
DUE AT …………. ON
……………………….
Programme Implementing Agent
(Improved BoTT)
for the
Community Water Supply And Sanitation
Capital Programme
in
[DISTRICT MUNICIPALITY NAME]
SUBMIT TENDER DOCUMENTS
TO
TENDERER
COMPILED BY:
Generic Documentation prepared by
DIRECTORATE: PROJECT DEVELOPMENT SUPPORT
DEPARTMENT OF WATER AFFAIRS AND FORESTRY
PRIVATE BAG X313
PRETORIA, 0001
REPUBLIC OF SOUTH AFRICA
District Municipality Document prepared by
Documentation Prepared for
DISTRICT MUNICIPALITY(S) DETAILS
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
INVITATION TO SUBMIT TENDER
for the
Programme Implementing Agent
(Improved BoTT)
The ___________________ District Municipality hereby calls for proposals from suitably qualified
tenderers to undertake work as a Programme Implementing Agent for the Community Water Supply
and Sanitation Capital Programme (CWSSCP) for _____________________.
This tender is for the provision of planning, design, construction, operations and maintenance of water
services as well as such institutional and social development as may be required, following a
prescribed business planning process. It focuses on the process of sustainable infrastructure
development to address backlogs in the water services sector.
The document has the FIDIC Conditions of Contract for Plant and Design – Build for Electrical and
Mechanical Plant and for Building and Engineering Works, Designed by the Contractor, First Edition
1999 (The Yellow Book), as a basis and will be under the jurisdiction of the District Municipality.
The envisaged Works have three main parts:

Infrastructure Development, comprising:

Business Planning

Design

Construction

Sustainability, comprising:

Operations and Maintenance

Institution and Social Development

Sanitation, comprising:

Basic Hygiene and Health Training

Provision of Sustainable Sanitation Systems
The Employer’s Requirements in the separate parts will provide details of the Works.
A compulsory site inspection will be held in ______________________ at ____________ on
______________ 200___.
Interested parties may obtain a complete set of Tender Documents upon payment of R200,00 from
the ______________________. The tender documents will be available from the day the invitation for
tenders is placed.
Tenders must be submitted to the __________________ or deposited in the Tender box in the
__________________ not later than _________ on _______________
Improved BoTT: Version 1: June 2001
TABLE OF CONTENTS
VOLUME 1:
GENERAL REQUIREMENTS
(i)
NOTICE TO TENDERERS ............................................... i (1)
PART A: FORM OF CONTRACT AGREEMENT ........................... A (1)
PART B: CONDITIONS OF CONTRACT ....................................... B (1)
PART C: APPENDIX TO TENDER ................................................ C (1)
PART D: EMPLOYER’S REQUIREMENTS ................................... D (1)
PART E: GENERAL SPECIFICATIONS AND
PRELIMINARY AND GENERAL ITEMS .......................................... E (1)
VOLUME 2:
INFRASTRUCTURE DEVELOPMENT
PART 1: BUSINESS PLANNING AND DESIGN ........................... 1 (1)
PART 2: CONSTRUCTION ........................................................... 2 (1)
PART 3: DRAWINGS .................................................................... 3 (1)
VOLUME 3:
SUSTAINABILITY
PART 1: OPERATIONS AND MAINTENANCE ............................. 1 (1)
PART 2: INSTITUTIONAL AND SOCIAL DEVELOPMENT .... 2 (1)
VOLUME 4:
SANITATION ................................................................................... iv (1)
VOLUME 5:
PROPOSAL AND TENDER FORMS
PART 1: PROPOSAL .................................................................... 1 (1)
PART 2: TENDER FORMS ........................................................... 2 (1)
PART 3: SCHEDULE OF QUANTITIES ........................................ 3 (1)
PART 4: CORRESPONDENCE .................................................... 4 (1)
Improved BoTT: Version 1: June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
General Requirements
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page (i)
General
TABLE OF CONTENTS
PAGE(S)
(i)
NOTICE TO TENDERS .................................................................................................. i (1)
PART A:
FORM OF CONTRACT AGREEMENT ........................................................................ A (1)
PART B:
CONDITIONS OF CONTRACT .................................................................................... B (1)
PART C:
APPENDIX TO TENDER .............................................................................................. C (1)
PART D:
EMPLOYER’S REQUIREMENTS ................................................................................. D (1)
PART E:
GENERAL SPECIFICATIONS AND PRELIMINARY AND GENERAL ITEMS ............. E (1)
106762682 / 7/6/01
Improved BoTT: Version 1:June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
General Requirements
Notice to Tenderers
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Notice to Tenderers
TABLE OF CONTENTS
PAGE(S)
1.
GENERAL NOTES .................................................................................................................... 1
1.1
Basic Information ....................................................................................................................... 1
1.2
Tenderers to Comply with Documents ...................................................................................... 2
1.3
Timetable ................................................................................................................................... 2
1.4
Process ...................................................................................................................................... 2
2.
CONDITIONS OF TENDER ...................................................................................................... 4
2.1
DM Tender Board Conditions And Procedures ......................................................................... 4
2.2
Document to be completed and returned .................................................................................. 4
2.3
Item Rates and Forms ............................................................................................................... 4
2.4
Authority For Signatory .............................................................................................................. 4
2.5
Joint Venture or Consortium Agreement ................................................................................... 4
2.6
HDI and HDC Involvement ........................................................................................................ 5
2.7
Tax Certificate ........................................................................................................................... 5
2.8
Acceptance or Rejection ............................................................................................................ 5
2.9
Sub-Contractors ........................................................................................................................ 5
2.10
Electronic Transmission of Tenders .......................................................................................... 5
2.11
Costs Incurred by Tenderer ....................................................................................................... 5
2.12
Results of Tenders .................................................................................................................... 5
2.13
Alternative Tenders.................................................................................................................... 5
3.
DOCUMENT STRUCTURE....................................................................................................... 6
4.
PROPOSAL TO BE SUBMITTED WITH TENDER ................................................................... 6
106762682 / 7/6/01
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
1.
GENERAL NOTES
1.1
Basic Information
6
E
Page i (1)
Notice to Tenderers
Tenderers shall note the following general points:
(a)
This document, comprising Volumes 1 to 5 inclusive, sets out the tender requirements
and framework for the appointment of a Programme Implementing Agent (PIA) in the
[……….………………………………….…… District Municipality (DM)] to support the
[…………………………………………………………………………………. Programme].
(b)
Tenderers shall note that it is the intention of this tender to obtain competitive bids for
the provision of a PIA to the DM on the basis of the tenderer’s experience, workplan,
staff, price and proposal.
(c)
This document will form the basis of the Contract entered into between the DM and the
successful tenderer.
(d)
Tender documents will be issued according to the following details:
Issuing Authority
Date of Issue
Place of Issue
Tender Period
6 weeks
and shall be posted in time to ensure delivery before the closing time for tenders to:
Tender Submitted to:
[Insert name of DM]
Closing Time and Date:
Street Address:
Postal Address:
The tenderer has the sole responsibility for ensuring that the tender documents are
received before tender closing time. Late tenders will not be considered.
(e)
The successful tenderer will be required to enter into a Contract Agreement which is
included in the tender document.
(f)
Inquiries during the tender period to be addressed to:
Attention:
Tel.:
Fax.:
It should be noted that only written clarifications and addenda issued during the tender
period by the DM will be valid.
(g)
This Tender shall remain valid for 120 calendar days from the date of tender closing.
Should the tender validity expire on a Saturday, Sunday or public holiday, the tender
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i
3
B
4
C
5
D
6
E
Page i (2)
Notice to Tenderers
shall remain valid and open for acceptance until the close of business on the following
working day.
1.2
(h)
The pages in each of the volumes of these tender documents are numbered.
Tenderers must satisfy themselves that their documents are complete. Should any
pages in this document be missing or indistinct then the Tenderer must advise the DM
immediately and request the missing pages.
(i)
Should the Tenderer note any obvious errors or omissions, the DM should be notified
immediately in order to have the discrepancy rectified before tender closing.
Tenderers to Comply with Documents
Tenderers must allow in their Tenders for all labour, materials, machinery and everything
necessary for the execution and completion of the Contract in accordance with the tender
documents.
1.3
Timetable
The following is a brief listing of the timetable relevant to this tender.
Number
1.4
Event
1.
Tender Advertisement
2.
Tender Issue
3.
Compulsory Site Inspection
4.
Tender Closure
5.
Tender Award (Approximate Date)
Date
Process
The process that has given rise to this tender enquiry and that will be followed until tender
award, is illustrated below.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
DM = District Municipality
2
A
3
B
4
C
5
D
6
E
Page i (3)
Notice to Tenderers
FIGURE 1
TENDER ENQUIRY PROCESS
DM assisted by DWAF region through
Regional TAC
Procurement and Appointment of DM
Engineer
DM Engineer prepares DM specific
Tender
document
–
estimates
quantities for works to equal budget
with
projects
using
generic
documents and WSDPs
Budget
Info. flow +
WSDPs
Approval of Document by DM
Tender Advert for PIA Contract
Issue of Tender Documents
Site Inspection Session
Tender Closure and Evaluation
PIA Tender Award
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
2.
CONDITIONS OF TENDER
2.1
DM Tender Board Conditions And Procedures
Page i (4)
Notice to Tenderers
The relevant conditions and procedures of DM will apply and the DM must insert the
relevant conditions and procedures here.
2.2
2.3
2.4
Document to be completed and returned

The Tenderer is required to complete all the forms and schedules included in
Volume 5 and to prepare the proposal as required in Volume 5 and to return these with
the tender. Failure to do so may invalidate the tender.

The Tenderer is required to price in full the Schedules of Quantities, Fees and Tariffs
included in Volume 5 of this document. The original and two copies of Volume 5 shall
be submitted.

The Tenderer is required to provide all the supporting information requested in the
document with the tender. The adjudication will take into account all aspects and not
just the rates submitted and failure to provide full and detailed information could affect
this adjudication.
Item Rates and Forms

All Item Rates quoted shall be in South African currency and are to exclude Value
Added Tax.

The tender must be signed and witnessed on the Letter to Tender annexed hereto with
all blanks in the tender and appendix filled in.

All spaces in the Tender forms and other annexures shall be completed in full.

The Schedule of Quantities must be fully priced and items may not be grouped into a
single rate.

The District Municipality reserves the right to renegotiate, prior to award, any rates in
the Schedules of Quantities, Fees and Tariffs which are, in the opinion of the DM,
unreasonable or out of proportion.
Authority For Signatory

2.5
A certified copy of the Company Board Resolution or of the resolution of the
Consortium Members must be submitted with the tender. This resolution shall
authorize the person who signs this tender, as well as any Contract resulting from this
tender and any other documents and correspondence in connection with this tender
and/or Contract requiring such signature, to do so on behalf of the company or
consortium.
Joint Venture or Consortium Agreement

If the Tender is submitted by a joint venture or consortium of more than one person(s)
and/or companies and/or firms, it shall be accompanied by the original, or a certified
copy of the agreement or other document, under which such joint venture or
consortium will be constituted, which must define precisely inter alia the conditions
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page i (5)
Notice to Tenderers
under which the joint venture or consortium will function, its period of duration and the
participation of the several constituent persons and/or companies and/or firms;
2.6
HDI and HDC Involvement
Tenderers shall note that it is requirement of this tender that all offers shall include the
involvement of Historically Disadvantaged Individuals (HDIs) and Historically Disadvantaged
Companies (HDCs), as outlined in the Employer’s Requirements.
2.7
Tax Certificate
An original or certified copy of a valid tax clearance certificate issued by SARS must be
submitted.
2.8
Acceptance or Rejection
Tenders may be rejected if they show any departure from the conditions or specifications
contained in the tender documents or are incomplete in any way. The District Municipality
does not bind itself to accept the lowest or any tender and reserves the right to accept any
tender it may deem expedient, nor will it assign any reason for the acceptance or rejection of
any tender.
2.9
Sub-Contractors
Tenderers must submit with their Tenders the names and addresses of the Sub-Contractors
which they propose to employ and the section of the works on which they would be employed.
2.10
Electronic Transmission of Tenders
Telegraphic, faxed or e-mailed tenders will not be considered.
2.11
Costs Incurred by Tenderer
The District Municipality will not be responsible for any expenses which may be incurred by any
tenderer in the preparation and submission of the tender or visiting the site in connection
therewith.
2.12
Results of Tenders
Notice of acceptance or non-acceptance of tenders will be sent to all tenderers.
2.13
Alternative Tenders

A Tenderer who has duly submitted an offer, which in all respects complies with the
specification, may, at his own initiative, also submit an alternative offer at the same
time or any time prior to the closing time of tenders. Any deviation from specification or
alternative condition of tender must be clearly stated. Any saving or additional
expenditure for the DM brought about by each deviation or alternative proposal must
be quantified in the tender documents.

Should the Tenderer wish to offer any alternatives, he shall include with his tender a
complete schedule of rates, preliminary technical proposals, organizational
development details, etc. and all other documents required in terms of this tender
enquiry as well as all other relevant details pertaining to such alternative(s).
Improved BoTT: Version 1: June 2001
Volume
Part

3.
1
i
2
A
3
B
4
C
5
D
6
E
Page i (6)
Notice to Tenderers
Failure to comply with this clause may disqualify the alternative offered from further
consideration.
DOCUMENT STRUCTURE
This tender document consists of the volumes as follows:
Volume
Description
1
General Requirements
2
Infrastructure Development
3
Sustainability
4
Sanitation
5
Proposal and Tender forms
The volumes of this document form a single contractual document and must be read as one.
The document has been divided into separate volumes for convenience only and all clauses
are mutually applicable. Where a conflict occurs in the information, the order of precedence
as described in the conditions of the contract shall apply.
4.
PROPOSAL TO BE SUBMITTED WITH TENDER
It is a tender requirement that tenderers compile a proposal as part of Volume 5. This
proposal shall contain all necessary information as requested in the various Parts of the
Employer’s Requirements.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page i (7)
Notice to Tenderers
PROGRAMME IMPLEMENTING AGENT
(Improved BoTT)
TENDER DOCUMENT
VOLUME 1
VOLUME 2
GENERAL REQUIREMENTS
Part
Description
(i)
A
B
Notice to Tenderers
Form of Contract Agreement
Conditions of Contract
Part 1: General
Part 2: Particular
Appendix to Tender
Employer’s Requirements
General Specifications and
Preliminary & General Items
C
D
E
INFRASTRUCTURE DEVELOPMENT
Part 1
Business Planning and Design
Part 2
Construction
Part 3
Typical Drawings
VOLUME 4
SANITATION
VOLUME 3
VOLUME 5
SUSTAINABILITY
PROPOSAL AND TENDER FORMS
Part 1
Operations & Maintenance
Part 1
Tender Forms and Schedules
Part 2
Institutional & Social Development
Part 2
Proposal
Part 3
Schedule of Quantities
Part 4
Correspondence
---- END OF SECTION ----
Improved BoTT: Version 1: June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
Part A
Form of Contract Agreement
Improved BoTT: Version 1: June 2001
Contract
Volume
Part
5.
1
i
2
A
3
B
4
C
5
D
6
E
Page A (1)
Form of Contract Agreement
CONTRACT AGREEMENT
This Agreement is made this _______ day of ___________________ 20 ____ between
__________________ of _________ (hereinafter called “the Employer”) of the one part, and
__________________ of _________ (hereinafter called “the Contractor” of the other part.
WHEREAS
the
Employer
desires
that
the
Works
known
as
_________________________________ should be executed by the Contractor, and has
accepted a Tender by the Contractor for the execution and completion of these Works and the
remedying of any defects therein.
The Employer and the Contractor agree as follows:
1.
In this Agreement words and expressions shall have the same meaning as are
respectively assigned to them in the Conditions of Contract hereinafter referred to.
2.
The following documents shall be deemed to form and be read and construed as part
of this Agreement:
(a)
The Letter of Acceptance
________________________
(b)
The Letter of Tender dated
________________________
(c)
The Addenda Nos.
________________________
(d)
The following Contract Documents:
VOLUME 1:
GENERAL:
NOTICE TO TENDERERS
PART A:
FORM OF CONTRACT AGREEMENT
PART B:
CONDITIONS OF CONTRACT
PART C:
APPENDIX TO TENDER
PART D:
EMPLOYER’S REQUIREMENTS
PART E:
GENERAL SPECIFICATIONS AND PRELIMINARY
AND GENERAL ITEMS
VOLUME 2:
INFRASTRUCTURE DEVELOPMENT:
PART 1: BUSINESS PLANNING AND DESIGN
PART 2:
CONSTRUCTION
PART 3:
DRAWINGS
VOLUME 3:
SUSTAINABILITY:
PART 1:
OPERATIONS AND MAINTENANCE
PART 2:
INSTITUTIONAL AND SOCIAL DEVELOPMENT
VOLUME 4:
SANITATION
Improved BoTT: Version 1: June 2001
Contract
Volume
Part
1
i
2
A
3
B
4
C
VOLUME 5:
5
D
6
E
Page A (2)
Form of Contract Agreement
PROPOSAL AND TENDER FORMS:
PART 1:
PROPOSAL
PART 2:
TENDER FORMS
PART 3:
SCHEDULE OF QUANTITIES
PART 4:
CORRESPONDENCE
3.
In consideration of the payments to be made by the Employer to the Contractor as
hereinafter mentioned, the Contractor hereby agrees with the Employer to design,
execute and complete the Works and append to maintain and operate the Works and
remedy any defects therein, in conformity with the provisions of the Contract.
4.
The Employer hereby agrees to pay the Contractor, in consideration of the execution
and completion of the Works and the remedying of defects therein, the Contract Price
at the times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed the day and year
first before written in accordance with their respective laws.
SIGNED by: _____________________________
SIGNED by: ____________________
for and on behalf of the Employer
For and on behalf of the Contractor
In the presence of
in the presence of
Witness:
_________________________
Witness:
______________________
Name:
_________________________
Name:
______________________
Address:
_________________________
Address:
______________________
Date:
_________________________
Date:
______________________
---- END OF SECTION ----
Improved BoTT: Version 1: June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
Part B
Conditions of Contract
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page B (i)
Conditions of Contract
TABLE OF CONTENTS
PAGE(S)
SECTION 1: GENERAL CONDITIONS OF CONTRACT.................................................................... B 1
SECTION 2: PARTICULAR CONDITIONS OF CONTRACT .............................................................. B 2
106762682 / 7/6/01
Improved BoTT Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page B (1)
Conditions of Contract
SECTION 1: GENERAL CONDITIONS OF CONTRACT
The FIDIC Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant
and for Building and Engineering Works, designed by the Contractor, First Edition 1999 (FIDIC
Contract Conditions)1, apply to the Works of this Contract. All clauses of these FIDIC Contract
Conditions shall apply unaltered except where replaced in Section 2: Particular Conditions of Contract.
1
This contract document may be obtained from FIDIC which may be contacted at the following web address:
http://www.fidic.org; e-mail address: fidic@pobox.com
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page B (2)
Conditions of Contract
SECTION 2: PARTICULAR CONDITIONS OF CONTRACT
The following Particular Conditions of Contract refer to the provisions of the General Conditions of
Contract specified in Section 1 of this Contract.
Clause
Description
1.
General Provisions
1.1
Definitions
Add the following definitions:
“Accepted Section Amount” shall mean the agreed lump sum for the execution of the
Section of the Works under consideration as stated in the Section 8.1A notice.
“Business Plan” shall mean a Section of the Works, which is prepared in terms of Volume 2
Part 1.
“Project” means a sub-set of the Works comprising a number of Sections.
“PEP” shall mean a concise document which sets down the requirements noted in Volume 2
Part 1.
“Section 8.1A Notice” shall mean the notice described in terms of Section 8.1A.
Replace the following definitions in the General Conditions of Contract:
1.1.2.3
“Contractor” means the person(s) named as the Programme Implementing Agent in the
Letter of Tender accepted by the Employer and the legal successors in title to this person(s).
1.2
Interpretation
At the end of sub-clause 1.2 insert:
“In these Conditions, provisions including the expression “Cost plus reasonable profit”
requires this profit to be ten per cent (10%) of this Cost”.
4.
The Contractor
At the end of the second paragraph of Sub-Clause 4.2 Performance Security, insert:
“If the Performance Security is in the form of a bank guarantee, it shall be issued by a bank
registered in South Africa. If the Performance Security is not in the form of a bank
guarantee, it shall be furnished by a financial entity registered, or licensed to do business, in
South Africa”.
At the end of sub-paragraph (b) of Sub-Clause 4.4 Sub-Contractors insert:
“Prior consent shall not be required if the value of the subcontract is less than two percent
(2%) of the Accepted Contract Amount”.
4.1
Contractor’s General Obligations
Add after the first paragraph of this clause:
“The Works shall consist of a number of Projects as well as a number of individual
Sections.”
Add the following words in the second paragraph after the word “execution” – “including
operation and maintenance”
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Clause
Page B (3)
Conditions of Contract
Description
8.
Commencement, Delays and Suspension
8.1
Commencement of Work
Replace the word “42 days” with “28 days” in this Clause.
Insert the following clause:
8.1A
Commencement of each Section of the Works
“The Employer shall issue a notice to the Contractor instructing him to commence activities
for each Section of the Works. Such notice shall include the Time for Completion (SubClause 1.1.3.3), Accepted Section Amount, and reference to the numbered Business Plan
for all Sections except for Volume 2 Part 1 where the document shall be a PEP.
10.
Employer’s taking over
Add the following paragraph at the end of Clause 10.1.
10.1A
“Where the Contractor’s obligations in a Section consist of the production of a report for the
Employer’s approval, the taking over of such a Section shall consist of the Employer’s
written acceptance of the report.”
14.
Contract Price and Payment
14.1
Contract Price
Replace sub-paragraph (a) with the following:
(a)
The Contract Price shall be the Sum of the Accepted Section Amounts, which shall be
contained in the Section 8.1A Notices issued, plus the Preliminary and General items stated
in the Schedule to Volume 1 Part E.
Insert the following sub-clause:
14.1A
“The Engineer shall agree or determine the value of those parts of the Works which are to
be measured, in accordance with Sub-Clause 3.5. Measurement shall be made of the net
actual quantities of those parts, notwithstanding local practice.
Whenever the Engineer requires any part of the Works to be measured, reasonable notice
shall be given to the Contractor’s Representative, who shall:
(a)
promptly either attend or send another qualified representative to assist the Engineer in
making the measurement, and
(b)
supply any particulars requested by the Engineer.
If the Contractor fails to attend or send a representative, the measurement made by (or on
behalf of) the Engineer shall be accepted as accurate.
Except as otherwise stated in the Contract, whenever any Permanent Works are to be
measured by records, they shall be prepared by the Engineer. The Contractor shall, as and
when requested, attend to examine and agree the records with the Engineer, and shall sign
the same when agreed. If the Contractor does not attend to examine and agree these
records, they shall be accepted as accurate.
If the Contractor examines and disagrees the records, and/or does not sign them as agreed,
then the Contractor shall notify the Engineer of the respects in which the records are
asserted to be inaccurate. After receiving this notice, the Engineer shall review the records
and either confirm or vary them. If the Contractor does not so notify the Engineer within 14
days after being requested to examine the records, they shall be accepted as accurate”.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page B (4)
Conditions of Contract
Clause
17.
Description
Risk and Responsibility
Sub-clause 17.6
Limitation of Liability
In Sub-Clause 17.6, the sum referred to in the penultimate sentence shall be one third of
the Accepted Contract Amount.
18.
Insurance
18.1A
Professional Indemnity Insurance
The Contractor shall submit proof of professional indemnity insurance carried by all
professional service providers used on the Contract. The total value of all the insurance
shall not be less than twice the value of the professional services tendered.
20.
Claims, Disputes and Arbitration
20.6
Arbitration

In the second line of this clause delete the word “international”.

Under sub-point (a) delete the words “International Chamber of Commerce” and
substitute the words “South African Association of Arbitrators”.

Under sub-point (b) delete the word “three arbitrators” and substitute the word “one
arbitrator”.
---- END OF SECTION ----
Improved BoTT: Version 1: June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
Part C
Appendix to Tender
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page C (1)
Appendix to Tender
APPENDIX TO TENDER
[Note: with the exception of the items for which the Employer’s Requirements have been
inserted, the following information must be completed before the Tender is submitted]. Items *
are to be completed by the DM before tender issue.
Item
Sub-Clause
Entry
* Employer’s name and address ...............
1.1.2.2 & 1.3 ........................................................................
Contractor’s name and address ...............
1.1.2.3 & 1.3 ........................................................................
* Engineer’s name and address ...............
1.1.2.4 & 1.3 ........................................................................
* Time for Completion of the Works .........
1.1.3.3..................................................................................
_____ days
Defects Notification Period .......................
1.1.3.7..................................................................................
365 days
* Electronic Transmission Systems ..........
1.3........................................................................................
Governing Law..........................................
1.4........................................................................................
South African
Ruling language ........................................
1.4........................................................................................
English
Language for communications .................
1.4........................................................................................
English
* Time for access to the Site.....................
2.1........................................................................................
______ days after Commencement
Date
* Amount of Performance Security ...........
4.2........................................................................................
______ % of the Accepted Contract
Amount, in the currencies and
proportions in which the Contract Price
is payable
Period for notifying unforeseeable errors,
faults and defects in the Employer’s
Requirements ...........................................
5.1........................................................................................
Initials of Signatory of Tender ________________________________
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Item
Page C (2)
Appendix to Tender
Sub-Clause
Entry
Normal working hours ...............................
6.5........................................................................................
No work shall be carried out after
sunset or before sunrise
Delay damages for the Works ..................
8.7 & 14.15(b) ......................................................................
_______ % of the value of the relevant
Section of the Works per day, in the
currencies and proportions in which the
Contract Price is payable
Maximum amount of Delay damages .......
8.7........................................................................................
_______ % of the value of the relevant
Section of the Works
If there are Provisional Sums:
Percentage for adjustment of
Provisional Sums .........................
13.5(b) .................................................................................
_______ %
If Sub-Clause 13.8 applies:
Adjustments for Changes in Cost:
.....................................................
Tables of adjustment data ...........
13.8......................................................................................
for payments each Month/[YEAR] in
South African Rands (currency)
*These values and dates confirm the definition of each index, but do not define Base Date indices
Total advance payment ............................
14.2......................................................................................
None
Number and timing of instalments ............
14.2......................................................................................
Not Applicable
Start repayment of advance payment .......
14.2(a) .................................................................................
Not Applicable
Repayment amortisation of advance
payment ....................................................
14.2(b) .................................................................................
Not Applicable
Percentage of retention ............................
14.3......................................................................................
Cumulative 5% of the Accepted Section
Amounts
Limit of Retention Money ..........................
14.3......................................................................................
2,5 % of the Accepted Contract Amount
Plant and Materials for payment when
shipped en route to the Site .....................
14.5(b) .................................................................................
Not Applicable
Initials of Signatory of Tender ________________________________
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Item
Page C (3)
Appendix to Tender
Sub-Clause
Entry
Plant and Materials for payment when
delivered to the Site ..................................
14.5(c) .................................................................................
Plant and Materials listed in Schedule
of Quantities on which lump sum
Sections are based
Minimum amount of Interim Payment
Certificates ................................................
14.6......................................................................................
R50 000.00
Periods for submission of insurance:
(a) evidence of insurance ........................
18.1 & 18.5A ........................................................................
21 days
(b) relevant policies..................................
18.1 & 18.5A ........................................................................
30 days
Maximum amount of deductibles for
insurance of the Employer’s risks .............
18.2(d) .................................................................................
Sum of the value of all Sections of the
Works of which first delivery has been
taken by the Employer
Minimum
amount
of third party
insurance ..................................................
18.3......................................................................................
R10 million
The DAB shall be ......................................
20.2......................................................................................
One sole Member/adjudicator
Appointment (if not agreed) to be made
by ..............................................................
20.3......................................................................................
The President of SAICE or a person
appointed by the President
Initials of Signatory of Tender ________________________________
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page C (4)
Appendix to Tender
If there are Sections:
Definition of Sections:
Description
(Sub-Clause 1.1.5.6)
Accepted Section
Amount
Time for
Completion
(Sub-Clause
1.1.3.3)
Delay Damages
(Sub-Clause 8.7)
Sections
of
the
Works
comprise various activities as
described
under
the
Employer’s Requirements
As
per
Notice
according to Clause
8.1A
As per Notice
according
to
Clause 8.1A
As per Notice
according
to
Clause 8.1A
Business Planning and Design
Construction
Operations and Maintenance
Sanitation
Note: Appropriate ISD is to be
included in all the above
Sections

These percentages shall also be applied to each half of the Retention Money under
Sub-Clause 14.9.
[In the above Appendix, the text shown in italics is intended to assist the drafter of a
particular contract by providing guidance on which provisions are relevant to the particular
contract. This italicised text should not be included in the tender documents, as it will
generally appear inappropriate to tenderers.]
---- END OF SECTION ----
Improved BoTT: Version 1: June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
Part D
Employer’s Requirements
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (i)
Employer’s Requirements
TABLE OF CONTENTS
PAGE(S)
1.
BACKGROUND ......................................................................................................................... 1
2.
SCOPE AND OBJECTIVES ...................................................................................................... 2
3.
CONTRACTUAL PROCESS AND STRUCTURE ..................................................................... 2
4.
EMPLOYER’S GENERAL REQUIREMENTS ........................................................................... 9
4.1
Exclusive rights with geographical area of DM .......................................................................... 9
4.2
Community liaison ..................................................................................................................... 9
4.3
Minimum and Maximum Values ................................................................................................ 9
4.4
Additional Information ................................................................................................................ 9
4.5
Quality Assurance System ......................................................................................................... 9
4.6
Institutional Support to Local Authorities ................................................................................... 9
4.7
Other parties .............................................................................................................................. 9
4.8
Design Requirements .............................................................................................................. 10
4.9
Operation and Maintenance Requirements ............................................................................. 10
4.10
Institutional and Social Requirements ..................................................................................... 10
4.11
The Contract shall be based on the following principles ......................................................... 10
4.12
Safety and Security .................................................................................................................. 10
4.13
Key Performance Indicators (KPIs) and Monitoring and Evaluation (M&E) ............................ 10
5.
INTERFACES .......................................................................................................................... 11
6.
STAFFING ............................................................................................................................... 12
6.1
Period .................................................................................................................................... 12
6.2
Conduct ................................................................................................................................... 12
6.3
Additional Skills ........................................................................................................................ 12
6.4
Empowerment ......................................................................................................................... 12
6.5
Experience ............................................................................................................................... 12
7.
PROPOSAL ............................................................................................................................. 13
106762682 / 7/6/01
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (ii)
Employer’s Requirements
7.1
Technical Section .................................................................................................................... 13
7.2
Financial Section ..................................................................................................................... 14
8.
EVALUATION CRITERIA ........................................................................................................ 15
8.1
Evaluation of Technical Sections ............................................................................................. 15
8.3
Right of DM to Investigate and Seek Clarification ................................................................... 16
APPENDIX A ........................................................................................................................................ 17
APPENDIX B ........................................................................................................................................ 19
106762682 / 7/6/01
Improved BoTT: Version 1: June 2001
Volume
Part
6.
1
i
2
A
3
B
4
C
5
D
6
E
Page D (1)
Employer’s Requirements
BACKGROUND
It is the Government of South Africa’s stated intention to provide water services for all of its
citizens. To this end DWAF has been mandated to facilitate water service delivery to the rural
poor and others who do not have water services. This has resulted in the creation of a multimillion Community Water Supply and Sanitation Capital Programme (CWSSCP) through which
DWAF channels central government and other donor funds to capital projects.
The Government of South Africa has also embarked upon an extensive multi-faceted Water
Services Sector Support Programme (WS-SSP) to provide water and sanitation services to
improve the quality of life of poor rural communities. This programme is being supported by
funding from the European Community (EC) through the Commission of the European
Communities in terms of a financing agreement. The work will be focused in the provinces
where the greatest backlog exists namely Northern Province, KwaZulu Natal and Eastern
Cape and it is called the Masibambane Programme. These provinces are referred to as the
Masibambane Provinces. It is expected to provide sustainable services to approximately 2,4
million people.
The programme involves the expenditure of some R2 220 million over three years in the
Masibambane provinces. At present this amount includes donor support of some R600
million, of which R500 million is from the European Community, while the United Kingdom,
Netherlands and France provide the remainder.
The Water Services Act (Act No. 108 of 1997), identifies local government as having the
ultimate responsibility for water service delivery and the Division of Revenue Act,(Act No 16 of
2000) specifies that no capital funds will be spent without agreements being in place to ensure
long-term sustainability of the envisaged service. Therefore the implementation of the
programme requires close co-operation between DWAF and local authorities to ensure that
the capital programme is in line with local authority expectations and their ability to provide the
service over the long term.
The recent local authority demarcation process (Municipal Demarcation Act (Act No 27 of
1998 ) of has also created new authorities, in addition to some existing authorities, that have
limited institutional capacity to provide the above service. Hence, the programme is being
undertaken in an environment in which democratic local government structures have only
recently been put into place and new legislation places the responsibility for sustainable
service provision on these new institutions.
In view of the increased demands on these new institutions to undertake such a rapidly
deployed multi-sectoral programme, the Department of Water Affairs and Forestry (DWAF) is
responsible for facilitating the provision of water and sanitation services. DWAF also has to
ensure that this work is integrated with other works that are being co-ordinated by the
Department of Provincial and Local Government (DPLG). In addition, the other aspects of the
programme aimed at providing institutional and social development to ensure sustainability of
water and sanitation services are also being channelled through DWAF.
In view of the above situation, this document has been compiled to provide support to District
Municipalities through a holistic project lifecycle contract under the District Municipalities
control. The Programme Implementing Agent (PIA) appointed under this contract will be
expected to work together with all other service providers to ensure the successful
implementation of the CWSSCP and the sustainable operation of the works and delivery of
water to the communities involved.
The services are to be provided by means of defined projects to be executed from inception
through business planning, institutional and social development (ISD), design, construction,
operation and maintenance (O&M). All of these services are to ensure sustainability, cost
effectiveness, job creation and the elimination of backlogs inherent in the country.
Improved BoTT: Version 1: June 2001
Volume
Part
7.
1
i
2
A
3
B
4
C
5
D
6
E
Page D (2)
Employer’s Requirements
SCOPE AND OBJECTIVES
The goal of this contract is to obtain adequate technical, construction, O&M and ISD
resources for the District Municipality (DM) to ensure the successful delivery of water services
as described above. The Works to be executed under this Contract involved the design and
implementation of Capital Works for water services provision as well as the initial operations
and maintenance until such time as these can be undertaken by the DM or its preferred Water
Service Provider.
This will be achieved through the following objectives:

the provision of a PIA team to the DM to assist to plan and implement capital works
inclusive of a senior manager to oversee the work of the team and to liase as required
at a senior level.

to access specialist staff and other personnel resources as required on an ad-hoc
basis.
The scope of work envisaged for the staff will be determined as the work progresses
and delivery takes place within the District Municipality. However, in broad terms the
scope of work entails the following:
8.

Business planning, design and technical assistance of designated projects in the DM;

Overall co-ordination, management and construction of the designated Water and
Sanitation Projects in the DM;

Consultation with local authorities, communities as well as all other parties, or any
other parties involved in the delivery of water services and building good working
relationships with such parties;

Assist and advise District Municipalities with its arrangements in regard to developing
its capacity to fulfil its role as Water Services Authority (WSA) and other sustainability
issues;

Assist WSA’s in respect of their options, arrangements and choices regarding Water
Service Providers (WSP) and linking such arrangements to the execution and
utilisation of capital works;

Transfer technical, contractual and administrative skills to DM and other parties
involved in the process.

Consult with and involve communities during the planning, construction and O&M
section of a Project(s) during the course of the contract.
CONTRACTUAL PROCESS AND STRUCTURE
The contractual processes and structure of the contract are depicted in the following figures.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (3)
Employer’s Requirements
FIGURE 3
Overall Diagram for Works
Issue of the Submission Issue of the 8.1
Tender
Letter of
of the
Commencement
Documents Tender
Acceptance Date
Base
Date
< 28d >
Tender
period
<
<
28d
11.9 Issue of
Performance
Certificate
See Detailed Diagrams for Works 3A and
Projects – Figure 4
>
28d
10.1 Issue of
Taking-Over
Certificate
Defects
Notification
Period
>
4.2 Issue of the
Performance Security
11 Notifying
of Defects
9.1 Tests on
Completion
Remedying
of Defects
Improved BoTT: Version 1: June 2001
< 21d >
4.2 Return of
the
Performance
Security
Volume
Part
2
A
1
i
3
B
4
C
5
6
E
D
Page D (4)
Employer’s Requirements
FIGURE 3A
Process Diagram for Works
Sections of the Works are defined as:
Commencement
Date
1.
2.
3.
Section of the Works
Business Planning
Construction
Operations
Maintenance
Sanitation
4.
Sanitation
4
Contract
Completion
Date
and
NOTE:
Issue of 8.1.A Notice
Project(s) A
Business Planning
and design
Construction
Operations and Maintenance
1
2
3
Sections of the Works
Operations and Maintenance
Defects
Liability
Section of the Works
Section of the Works
Business Plan
1
Project(s) B
Construction
Section
2
Operations and
Maintenance
3
Defects
Liability
Construction
2
Sections of the Works
ISD Input in all Sections
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (5)
Employer’s Requirements
FIGURE 4
Process Diagram for Projects
PROJECT
Issue of 8.1.A
Notice
Submission of
Business Plan
Approval of
Business Plan
by Appraisal
Committee
Issue of 8.1.A
Notice
Commencement
of section
2d
9.1 Tests for
completion
14d
Business Plan –
see Figure 5
Delays
attributable to
the Contractor
Agreement of
Lump Sum
for
Construction
10.1 Issue of
Take over
Certificate
8.2 Time for Completion
Defects liability
period
Only if no
O&M
Section
Defects
Liability
Period
Issue of 8.1.A
Notice for
Operations
and
Maintenance
Section of the Works
Section of the Works
Section of the Works
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (6)
Employer’s Requirements
FIGURE 5
Business Plan Process
Section of the Works
Engineer evaluates
or asks for additional
info
Instruction
by Employer
Agreement
of
PEP
Business
Plan
Approval by
Appraisal
Committee
Engineer
Review and
Agreement
Final Negotiation
on lump sum
Variable
Draft PEP
21 Days
1 day
Conceptual
Report
Provisional
lump sum
agreement
Business Plan
completed and
submitted
to
DM
for
approval
Issue 8.1.A
notice to
Commence
Section
NOTE:
Conversion
lump sum
construction
Business Plan – See Note
PIA does preliminary design, quantities and price i.e. Section Bill
of Principle Quantities for Permanent Works (using tender rates)
and other work as defined in PEP.
Improved BoTT: Version 1: June 2001
to
for
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (7)
Employer’s Requirements
FIGURE 6A
Payment Events – Process for monthly payment
14.3 Contractor
submits Statement
to the Engineer
Each of the
monthly (or
otherwise)
interim
payments
14.6 Engineer
issues Interim
Payment
Certificate
14.7 Employer makes
the payment to the
Contractor
<56d
<28d
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (8)
Employer’s Requirements
FIGURE 6B
Payment Events – Process for final payment
The final
payment
Engineer verifies
statement,
Contractor submits
information
<56d
<28d
14.11 Contractor submits14.11 Contractor submits
draft final statement to Final Statement and the
14.12 discharge
the Engineer
14.13 Engineer
issues Final Payment
Certificate
14.7 Employer
makes payment
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (9)
Employer’s Requirements
9.
EMPLOYER’S GENERAL REQUIREMENTS
9.1
Exclusive rights with geographical area of DM
The successful tenderer will not have exclusive rights as the PIA in the DM and the DM
reserves the right to appoint more than one PIA Team.
9.2
Community liaison
Liaison with communities will be through the Area or District Planning Forums, Project Steering
Committees, Village Water Committees or Local Authorities or other structures as may be
designated by the Employer. The particular structure of the liaison with the community may be
unique to each Project(s) and clarification of these structures and relationships will form part of
the Business Plan preparation process.
9.3
Minimum and Maximum Values
There is no guarantee as to the minimum or maximum value of the final Contract. While an
order of magnitude Contract Schedule of Quantities is provided in his document this is
indicative only and the DM does not bind itself to this, or any, scope of works. No claims will
be entertained from the PIA as a result of the Contract not meeting expectations.
9.4
Additional Information
The following documents shall be read for information by tenderers:
[The DM may want to list particular info of a non-contractual nature here].
9.5
Quality Assurance System
The PIA shall prepare a quality assurance system for the Works and Sections of the Works in
accordance with ISO9000:2000 and ISO14000:1994. This system shall be submitted to the
Engineer for approval before any design or execution section is commenced.
9.6
Institutional Support to Local Authorities
The PIA may be required to provide certain institutional support functions. However it is
expected that the primary institutional support will be provided though other appointments.
During the course of the Contract the PIA is expected to formalise the scope of Works and
Sections of the Works within the Contract using the Business Plan procedures.
9.7
Other parties
The other works which may be in progress or which may start on some sites forming part of
this Contract are likely to include, but are not limited to the following:

Maintenance services done by ESKOM and/or Telkom.

Activities by the Department of Water Affairs and Forestry or other Water Supply
Authorities regarding existing water infrastructure.

Drilling and Test pumping of boreholes by teams of other Contractors.

Testing of boreholes in all the regions, districts and villages.
Improved BoTT: Version 1: June 2001
Volume
Part

9.8
1
i
2
A
3
B
4
C
5
D
6
E
Page D (10)
Employer’s Requirements
[DM can add other parties here]
Design Requirements
The specific design requirements are listed in the relevant project specifications listed in the
Contract.
In addition the DM has the following general design requirements [DM to list specific design
requirements].
9.9
9.10
Operation and Maintenance Requirements

The PIA may be required to operate and maintain the systems as detailed in the
Business Plan for the Section of the Works. The PIA may then provide a mentorship
service to the DM for a period as determined after transfer if contained in the Business
Plan.

If the DM does not yet have the capacity to operate the systems (i.e. maintenance
capability) then the DM must include Specifications for the O&M. It is a requirement of
this document that the PIA operates and maintains the system while building capacity
in the DM to the point that the system can be transferred. The Business Plan shall set
out clearly how this is to be achieved.
Institutional and Social Requirements

9.11
9.12
Wherever the Community requirements conflict with any of the DM requirements, the
DM approval for any such deviation from its requirements shall be obtained.
The Contract shall be based on the following principles

The provision of the basic RDP water requirements (i.e. 25. litres per capita within 200
metres).

The provision of sanitation in accordance with the National Sanitation Policy (currently
a household subsidy of R600.00 each with a possible extra allowance in the case of
difficult ground conditions).

The funding for these basic requirements will be provided by the Department of Water
Affairs and Forestry.
Safety and Security
The PIA shall take particular note of the safety and security precautions which are essential for
a Contract of this nature with widely dispersed sites and where it may not be possible to fence
the sites to make them secure. Full allowance for the provision of the necessary safety and
security provisions shall be made in the rates tendered in the Schedule of Quantities.
9.13
Key Performance Indicators (KPIs) and Monitoring and Evaluation (M&E)

An outline of envisaged KPIs is given in various volumes of the contract document.
These KPIs and others will be developed with the PIA independently during the
currency of this contract.

KPIs are an important and integral part of the national reporting system and shall be
the means of measuring performance. The measurement of performance shall
provide all stakeholders with objective information on project status and progress i.e.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (11)
Employer’s Requirements
physical and financial compliance with RDP objectives including policy and strategic
objectives, sustainability, etc.

10.
The Department of Water Affairs and Forestry has a Monitoring and Evaluation (M&E)
system for KPIs. The PIA shall provide information required in the specified reporting
format to the DM for inclusion in the national reporting system. It shall be noted that
some KPIs will be interpreted by the Department of Water Affairs and Forestry from
information provided by the PIA e.g. from milestones or targets of physical, financial,
and capacity building aspects of the programme. Other information will be utilised
from the reporting by the PIA of achievement against a specific KPI as a quantitative
value.
INTERFACES
The PIA will report directly to the:
[……………………………….. Insert Name]
or the responsible official as designated in writing.
The DM’s structure consists of the following:
[……………………………….. Insert Structure]
In addition to communicating within the DM, the PIA will also be expected to communicate with
the following:
[……………………………….. Insert list]
and various other stakeholders at national level and in the regions.
The PIA will need to work with the DWAF: Monitoring and Evaluation units in the regions and
at national level.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (12)
Employer’s Requirements
The PIA will also be expected to interface with the:
[……………………………….. Insert other ]

EU ambassador or officials designated in writing.

All donor organisations as well as other industry role players when required to assist in
expediting the Masibambane Programme.
The PIA should note that several other consultants are currently assisting in related areas and
programmes. The PIA shall ensure that all relevant information is obtained from these
consultants and that smooth interfaces are developed to avoid duplication of effort.
11.
STAFFING
11.1
Period
The DM requires the PIA to establish resources to provide the services related to this Contract
to the DM for the period of the Contract as detailed in the Appendix to Tender. An extension to
the contract may be negotiated upon mutual agreement by the parties.
11.2
Conduct
The PIA staff shall at all times act professionally and with integrity, objectivity and
independence. The PIA team shall have the necessary professional knowledge and skill to
undertake the activities assigned to them.
11.3
Additional Skills
In addition, personnel with specific skills will be required by the DM. These skills shall be
provided on a draw down basis using the rates set out in the Schedules of Quantities. The PIA
shall demonstrate to the DM that they have the range of skills and resources necessary to
meet the core requirements of this contract while also having the resources and skills to meet
possible ad hoc requirements for specialist personnel.
11.4
Empowerment
The commitment of the DM to the Government’s policy concerning the empowerment of
historically disadvantaged individuals and companies (HDI/HDC) shall be noted and adhered
to by the PIA. The minimum HDI/HDC participation goal for this project is 25% in work and
equity sharing respectively.
11.5
Experience
The PIA shall demonstrate experience in management and administration, not only of large
infrastructure developments but also of smaller community water developments, which require
greater sensitivity within a multi skilled, multi project environment. The PIA shall have
knowledge of, inter alia:
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i
3
B
4
C
5
D
6
E
Page D (13)
Employer’s Requirements

Legal requirements generally and the Water Services Act, the Division of Revenue Act
and the Municipal Systems Act specifically

RDP requirements

Water services

Government procedures, policies and systems

Organizational development

Sustainability issues

Institutional and social issues

Capacity building

Operations and maintenance of rural and urban water systems

Rural sanitation

Financial management of projects and programmes and related issues

Contractual administration and supervision

Programme and project management

Word processing, spreadsheets, database programmes and project planning software

Construction, building, engineering, consulting and service provision contracts
12.
PROPOSAL
12.1
Technical Section
The tenderer shall submit a short technical proposal indicating its understanding of the
contract as well as:
7.7.1
7.7.2
Firm’s Experience

Overall competence and track record

Specific project applicable expertise
Approach and methodology and Project Management
The tenderer shall submit a brief (10 page maximum) workplan stating his understanding of
the challenges faced and a strategy for DM co-operation. The following factors will enhance
the workplan score:

Clarity, comprehensiveness and level of detail

Soundness of approach and methodology

Understanding of local conditions

Robustness of approach

Relevant examples

A brief description of a strategy for SMME’s, job creation and labour intensive
construction.
The following factors will detract from the workplan score:

Inclusion of inappropriate focus on non-critical issues

Inappropriate detail
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i


3
B
4
C
5
D
6
E
Page D (14)
Employer’s Requirements
Proposals that are not appropriate for the local environment and in the
interests of the District Municipality
Qualifications of Key Personnel
[……………………………….. Insert other issues as required]
The evaluation of this section shall include but not be limited to, the following:

The extent of the resources of the bidder or consortium to undertake the full range of
services.

The qualifications and experience of four key staff from the Core team in categories:


Business Planning Design

Construction Experience in Water Related Projects

Operations and Maintenance

Institutional and Social Development

Sanitation
Experience in similar environments
The PIA should include sufficient technical details in its proposal to enable the Evaluation
Committee to assess whether these objectives will be met. The tenderer shall provide details
of the proposed organisation structure of the team and shall provide an outline of the
methodology that will be used. The breakdown and points as detailed in the evaluation tables
will be used to determine the technical scores.
CV’s will be in the format given at the end of this document.

Employment Equity
The following will be taken into account in the evaluation:
Historically Disadvantaged Principles in the Consortium
A minimum involvement of 25% is required to achieve the minimum points to be
considered for the project. Other values of involvement will be rated pro-rata. The
utilization of Historically Disadvantaged Individuals (HDI’s) on the programme will be
evaluated relative to the total staff cost. Points will be pro rata-ed up to a maximum
value of 40%.
12.2
Financial Section
The tenderer shall submit a price based on the completion of the Schedules of Quantities in
Volume 5. All schedules are in this volume and the relevant tender forms are also included.
This volume and separate tenderer’s proposal are the only documents to be returned.
Improved BoTT: Version 1: June 2001
Volume
Part
13.
1
i
2
A
3
B
4
C
5
6
E
D
Page D (15)
Employer’s Requirements
EVALUATION CRITERIA
The tenders will be evaluated as a two-stage process in accordance with the following criteria:
The Technical Proposal will be opened first and evaluated as follows:
Technical Proposal

Overall Competence and Track Record
25%

Approach and methodology including understanding of the Contract document
25%

Employment Equity
20%

Qualifications of key personnel
30%

Total
100%
Pass/Fail
After the Technical Proposal has been evaluated, Financial Proposal of the Tenderer attained
at least the minimum technical score will be opened.

13.1
Price
Evaluation of Technical Sections
The DM shall evaluate the Technical Proposals received at Tender Closure, and opened in
accordance with the approved procedures, in accordance with the following process.
8.1.1
In Step 1, the Evaluation Committee shall examine each Technical Proposal submitted
to determine whether the Technical Proposal is complete and substantially responsive.
8.1.2
In Step 2, the Evaluation Committee shall evaluate the Technical Proposals that are
substantially responsive based on the following criteria and marking system:
Criteria
Firm’s Experience

Overall Competency and track record

Specific project applicable expertise
Approach and Methodology and Project Management

Understanding of ToR

Problem Conceptualisation

Innovation in approach

Project management
Qualifications of key personnel

Business Planning and Design

Construction Experience

Operations and Maintenance

ISD

Sanitation
Employment Equity
Minimum
Score
Weighting
5
6
12
13
10
25
15
30
10
20
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i
3
B
4
C
5
6
E
D
Criteria

Previously Marginalised Principals

Woman Principals

Affirmative Career Development

Social Responsibility
Sub total
Page D (16)
Employer’s Requirements
Minimum
Score
Weighting
46
100
Pass/Fail
13.1.1 To qualify to be considered further, a Technical Proposal must receive at least:
(a)
a total score of 70 points; and
(b)
a minimum score in each section
Each Tenderer of a Technical Proposal that meets the criteria shall be a Qualified
Tenderer.
13.1.2 Technical Proposals that,
(a)
receive fewer than 70 points;
(b)
a minimum score in each section
shall not be considered further.
13.2
Evaluation of the Financial Proposal
For each qualified tenderer the Evaluation Committee shall examine each such Financial
Proposal to determine whether such Financial Proposal is complete and substantially
responsive.
The lowest financial tenderer shall be deemed then as the winner after an arithmetic check of
the documentation and an evaluation of any criteria that may alter the price. This shall include
an evaluation of any Alternative tenders, Qualifications, omissions and other factors.
13.3
Right of DM to Investigate and Seek Clarification during the Evaluation Process
8.1.1
The DM may, in its sole discretion, seek clarification, during the process. In the
process of clarification, no change in the substance of the Technical Proposal or in the
Financial Proposal shall be sought, offered or permitted.
8.1.2
DM shall seek all clarifications in writing and the Tenderers’ responses shall also be in
writing.
8.1.3
Without limiting the generality above, DM may, in its sole discretion:
(a)
investigate evidence of the ability and experience of a Tenderer under consideration,
including joint venture partners, proposed subcontractors, and parties otherwise
related to the Tenderer or the Tenderer’s Proposal; and
(b)
require or seek out confirmation from other parties of information furnished by a
Tenderer.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (17)
Employer’s Requirements
APPENDIX A
FORMAT OF CURRICULUM
PROFESSIONAL STAFF
VITAE
(CV)
FOR
PROPOSED
Proposed Position:
Name of Firm:
Name of Staff:
Profession:
Date of Birth:
Years with Firm/Entity:
Nationality:
Membership in Professional Societies:
Detailed Tasks Assigned:
Key Qualifications:
[Give an outline of staff member’s experience and training most pertinent to tasks on
assignment. Describe degree of responsibility held by staff member on relevant previous
assignments and give dates and locations. Use about half a page.]
Education:
[Summarise college/university and other specialised education of staff member, give names of
schools, dates attended, and degrees obtained. Use about one quarter of a page.]
Employment Record:
[Starting with present position, list in reverse order every employment held. List all positions
held by staff member since graduation, giving dates, names of employment organisations,
titles of positions held, and locations of assignments. For experience in last ten years, also
give types of activities performed and client references, where appropriate. Use about two
pages.]
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page D (18)
Employer’s Requirements
Languages:
[For each language indicate proficiency: excellent, good, fair or poor in speaking, reading and
writing.]
Certification:
I, the undersigned, certify that to the best of my knowledge and belief, these data correctly
describe my qualifications, my experience, and me. I also certify that I have only given
permission for my CV to be included in the Proposal submitted by
[Fill in name of Bidder here.]
Date:
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i
3
B
4
C
5
D
6
E
Page D (19)
Employer’s Requirements
APPENDIX B
Procedure for preparing and updating a PEP
Introduction
PEPs represent a method of managing time-based projects. The PEP need not be elaborate but
should set out the essentials of the project as defined in this document. It should form a reference
document for the project team. This Appendix presents a procedure for preparing and updating a PEP
and is intended to be used by the PIA and the DM to manage time-based Sections of the Works. The
appendixes purpose is to set out the process and contents of a PEP to ensure the orderly
management of time based projects.
Definitions
See Particular Conditions of contract for relevant definitions
Responsibility for Implementation

PEP preparation – PIA

PEP approval – DM
Implementation
Project Identification
The Project will normally be identified jointly by the DM and the PIA and then the PIA will be requested
to prepare a PEP for the Section of the Works.
PEP Contents
The PEP should contain the following:

Project Title

Project Objectives

Background

Scope



Deliverables

Skills Transfer

Constraints
Delivery Process

Tasks

Action Plan
Project Organisation

Staffing
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i



4
C
5
D
6
E
Page D (20)
Employer’s Requirements
Organogram
Programme


3
B
Gantt chart
Quality Plan

Project Responsibilities

PEP review process

Communication: Consultation required, lines of communication, contacts

Review, Verification and Validation and Approval Processes

Other Relevant Quality Elements as defined in ISO9001:2000
Cost Plan

Source of Funds

Authority for using funds

Expected Cost per Task per person

Disbursements
PEP Review
The PEP must be reviewed on a regular basis as defined in the PIA’s Quality Plan. This may entail the
adjustment of scope, resources, costs and budget.
---- END OF SECTION ----
Improved BoTT: Version 1: June 2001
REPUBLIC OF SOUTH AFRICA
DISTRICT MUNICIPALITY NAME …….
District
Municipality Logo
IMPROVED BOTT
Volume 1
Part E
Works Specifications, Preliminary
and General Items
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (i)
General Specifications, Preliminary and General Items
TABLE OF CONTENTS
PAGE(S)
1.
PS1 GENERAL DESCRIPTION ................................................................................................ 1
1.1
Scope ...................................................................................................................................... 1
1.2
Establishment of Lump Sums for Sections of the Works .......................................................... 2
2.
PS2 DESCRIPTION OF THE SITE AND ACCESS................................................................... 3
3.
PS3 NATURE OF GROUND AND SUB-SOIL CONDITIONS ................................................... 3
4.
PS4 DETAILS OF THE CONTRACT ........................................................................................ 4
5.
PS5 CONSTRUCTION PROGRAMME ..................................................................................... 5
5.1
Project Programmes .................................................................................................................. 5
6.
PS6 ACCOMMODATION AND EQUIPMENT AND SITE FACILITIES ..................................... 6
6.2
Construction Camp & Depot ...................................................................................................... 6
6.3
Water Supply ............................................................................................................................. 7
6.4
Power Supply............................................................................................................................. 7
7.
PS7 SITE FACILITIES REQUIRED ........................................................................................... 7
8.
PS8 FEATURES REQUIRING SPECIAL ATTENTION ............................................................ 7
8.1
Labour Based Construction ....................................................................................................... 7
8.2
Provision of a Temporary Workforce for the Contract ............................................................... 9
8.3
Restriction of the Utilization of Personnel in the Permanent Employ of the Contractor............. 9
8.4
SMME development .................................................................................................................. 9
8.5
Additional Reference Sources ................................................................................................. 10
9.
SPECIFICATIONS FOR PRELIMINARY AND GENERAL ITEMS .......................................... 10
9.1
Measurement and Payment .................................................................................................... 10
10.
SCHEDULE OF QUANTITIES ................................................................................................ 11
106762682 / 7/6/01
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (1)
General Specifications, Preliminary and General Items
14.
PS1 GENERAL DESCRIPTION
14.1
Scope
This contract comprises the provision of water services to communities in the jurisdictional
area of the
[……………………………….. Water Services Authority]
This area will be the Site of the Works. The Works are to be executed over a period of time as
detailed in the Appendix to Tender. The Works may comprise one or more different Projects.
Individual Projects will consist of Sections of the Works that will be identified as the Contract
progresses and may consist of all or any combination of the following:
[List in this section the main components of the envisaged contract, below are
examples]
Project 1:
Water Supply to __________________________.
Section 1.1
Design and construction of water supply systems, including any combination
of the following:

Source analysis and verification

Purification

Pump stations

Reservoirs

Rising and gravity mains

Reticulation
Section 1.2
The provision of sanitation to communities within the above _______ including
the following:

Geohydrological study of the immediate area to assess pollution potential

Provision of basic sanitation education

Provision of different types of sanitation systems
Section 1.3
The operation and maintenance of the above facilities for a period of time of
between 1 and 3 years may include the following:

Operation and maintenance of water treatment works and water care works, water
reticulation systems, bulk supply schemes, commonly water schemes

Operation and maintenance of pump stations reservoirs
Improved BoTT: Version 1: June 2001
Volume
Part
14.2
2
A
1
i
3
B
4
C
5
D
6
E
Page E (2)
General Specifications, Preliminary and General Items

Operation and maintenance of wastewater treatment works

Training and mentoring of water services authorities [providers] staff
Establishment of Lump Sums for Sections of the Works
The Improved BoTT contract comprises the whole Works, and will include a number of
smaller, individual Projects and Sections, each of which will be identified, and quantified. Each
Project will consist of one or more Sections of the Works that will commence with an 8.1A
Notice. The different Sections that are envisaged are:

Business Planning and Design

Construction

Operations and Maintenance

Sanitation.
ISD is to be included in each particular Section as required.
It is envisaged that the following number of individual Projects and Sections of the Works will
form part of this contract:

For the 1st year [x Projects and Sections]

For the 2nd year [y Projects and Sections]

For the 3rd year [z Projects and Sections]
The Water Services Act, Act 108 of 1997 (WSA 108/97) mandates that a Water Services
Development Plan (WSDP) should be compiled for each Water Services Authority (WSA). In
the WSDP the following number of projects have been identified to date. This information has
been used to quantify the worth of the Contract. The Sections and Projects are taken from the
approved Project lists.
No, and name of projects to be inserted here
The process to establish individual Sections of the Works for Construction is as follows:

The tender process will yield a Tender Bill of Principal Quantities for the Permanent
Works (TBPQPW), comprising rates and a list of items, which typically make up 70%90% of typical water supply projects. This TBPQPW will, amongst others be utilised to
evaluate the tenders.

Once the contract has been awarded, an individual Construction or combined
Construction and O&M Sections of the Works are established as follows:

The PIA drafts a PEP for Business Planning. After agreement as per the
process defined in Volume 2 Part 1, each individual Project is priced
during the Business Planning and Design Section of the Works, using the
Tender BPQPW rates with a Section Bill of Principal Quantities for the
Permanent Works (SBPQPW), made up of items (adapted for locality and
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i
3
B
4
C
5
D
6
E
Page E (3)
General Specifications, Preliminary and General Items
access as applicable) from the TBPQPW. The PIA also shows which
percentage of the Section’s cost is represented by this SBPQPW. This
percentage should be between 70% and 90%, depending on the work
involved in the Section.
15.

The Engineer will, in negotiations with the PIA agree on the percentage
described in the previous step, the Cost for the Section is converted into a
provisional Lump Sum offer for the construction of the Section with the
allocation of risk as defined in the Conditions of Contract.

The steps as detailed in Volume 2, Part 1 are then executed. The
Business Plan will either be approved by the DM Business Appraisal
Committee or other parties as required. Thereafter the individual
Sections are finalised and converted into a lump sum. If not approved the
Section of the Works is terminated.

Where a Section of the Works has commenced, interim payments will be
made based on monthly progress reports and certificates presented by
the PIA in accordance with clauses 4.21 and 14.3 of the Conditions of
Contract. The agreed SBPQPW and completion of individual items shall
also be used in this process.

At the end of the construction Section of the Works, the following
possibilities exist:

The Section of the Works terminates in the usual manner, with a
defect liability period of 12 month; or

The Project then enters an Operation and Maintenance Section of the
Works for a longer period of 1 to 3 years, as agreed in the Business
Plan.
PS2 DESCRIPTION OF THE SITE AND ACCESS
The Site of the Work is to be undertaken is supply area of
[enter the name of the WSA here].
A detailed map of the area is attached in Appendix named area.
Projects involved are located on this map. The Schedule of Quantities has been subdivided
per project due to differences in accessibility as well as locality.
This Schedule be one or more Sections, the current Schedule shows one Section.
16.
PS3 NATURE OF GROUND AND SUB-SOIL CONDITIONS
[A typical description should be given here, as to the geology, soils typically occurring,
types of rock. It might be useful to include typical zonal weather (for the zones as
defined by the Computing Centre for Water Research, University of Natal (CCWR)),
which form part of this area. There should be enough background data for the area (DM)
to enable an experienced contractor to deduct what he can expect when working in the
area – it must give the contractor enough confidence to allocate his risk properly, but
not give so much that the client might be subject to additional claims]
Improved BoTT: Version 1: June 2001
Volume
Part
2
A
1
i
3
B
4
C
5
D
6
E
Page E (4)
General Specifications, Preliminary and General Items
Typical sites, and material types will be shown during the site inspection to the tenderers, and
these will be deemed to be normal sites. However, as the sites are typical only, the following
shall apply:

The tenderer shall tender for excavation in typical soft material;

The tenderer shall tender for excavation in typical intermediate material;

The tenderer shall tender for an extra-over rate for hard excavation
For each individual Construction Section, the split between soft and intermediate excavation
shall be determined.
It shall be the PIA’s responsibility to allow for all testing required for the detail design phase of
the individual projects
17.
PS4 DETAILS OF THE CONTRACT
The work required for these Project involve the following:

Drafting of guidelines on the materials, specials and typical details to be used in the
provision of water services for the District Municipality (DM). (This is to be a guidance
document for use in the DM in the improved BoTT contract and thereafter). This
guideline shall become the property of the District Municipality. For the purposes of
this contract these Work is termed “Standardisation”.
The following shall be kept in mind:


Ease of maintenance

Most economic life for individual components

Minimum level of supply and acceptable supply levels and disruptions

Least total life cycle costs to the operating authority
Business Planning; Preliminary Design; Design and Construction of Water Supply
Systems; comprising the following:

Establishment of the Level of Living Index for the particular community
(Van Schalkwyk)

Community liaison, including basic Health and Hygiene education

Establishment of the (raw) water source

Establishment of the particular Level of Service (LOS) for the particular
community based on the Level of Living Index, the Free Basic Water
Policy and Sustainability.

Preliminary and detail design of the individual project

Construction;

Normal Defects Liability period; or Operation and Maintenance Section of
the Works for 1 to 3 years, including a defects liability period
Improved BoTT: Version 1: June 2001
Volume
Part




2
A
1
i
3
B
4
C
5
D
6
E
Page E (5)
General Specifications, Preliminary and General Items
Implementation of Basic Sanitation, comprising the following:

Sanitation planning

Community liaison, basic health and hygiene education

Choice of sanitation systems

Implementation of Sanitation systems

Operation and Maintenance
Institutional and Social Development to ensure sustainability comprising of:

Community empowerment

SMME development

Capacity building and training

People development

Project Steering Committee development

Local WSP providers (If necessary)
Mentoring the staff of the DM with reference to the following:

Duties of the Local Authority in terms of current legislation

Setting up tariff structures with acceptable levels of cross subsidisation
and sustainability as goal

Drafting and implementing Operation and Maintenance systems with the
following in mind:

Acceptable levels of non-supply to water services users

Efficient operation of all plant to minimise energy requirements

Effective maintenance to achieve least life cycle cost
[add others as necessary]
18.
PS5 CONSTRUCTION PROGRAMME
18.1
Project Programmes
Upon appointment the PIA shall draw up a PEP for a business plan to assess all available
information on water services in the DM and discuss it with the DM to develop the
Standardisation guidelines.
For each Section of the Works and as part of his Business Plan per Project, the PIA shall
provide an outline programme as per the conditions of contract to illustrate his understanding
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (6)
General Specifications, Preliminary and General Items
of the work to be done, the times allowed for and the sequencing of the particular work items.
Specific reference must be made to all partnering functions, i.e. the following:
19.

Social and Institutional Development

Operation and Maintenance
PS6 ACCOMMODATION, EQUIPMENT, SITE FACILITIES AND
SUPERVISION
[Guidance Note –One of the options below be selected or modified to suite]
19.1.1 Central Office
(a)
The PIA’s staff will be required to have permanent representation at offices within two
hours of the DM offices for effective functioning and interaction. The PIA may make
use of existing offices and facilities. Effective communication between the PIA and the
DM is paramount and this shall be the ruling criteria regarding availability. The PIA will
be expected to have a full time presence in these offices.
The PIA will be expected to provide all furnishings for computer equipment and related
software for the use of its employees.
OR
(b)
[The Local Authority will make available to the successful contractor two
adjacent offices in their office building for use by the contractor. These offices
will be equipped with desk and chair, but all working equipment such as
computers, printers etc. must be supplied by the contractor. These offices
should serve as coordination and liaison centre for the contractor].
19.1.2 Time related Items
These items will be paid per month after the PIA’s obligation of the item have, in the opinion of
the Engineer, been discharged. The period for which Supervision by the PIA’s Representative
at the Central Office is to be provided will be agreed with the DM and 28 days notice shall be
given to the PIA for commencement and for termination of such supervision. Intermittent
supervision may be required by the DM.
19.2
Construction Camp & Depot
For each individual Construction Section of the Works, the PIA shall set up a construction
camp when required (as per any usual contract), the size and functionality of which shall be in
relation to the individual Sections. For these camps, the following shall apply:

The PIA shall make arrangements with the relevant authority for a suitable site where
he can establish his construction camp.

Ablution facilities shall be provided for workmen where they can wash, dress, etc. One
shower and one toilet per ten workmen shall be provided. Such facilities shall at all
times be maintained in a clean and hygienic condition. Toilets shall be screened from
public view and their use shall be enforced.

The camp and site in general shall be kept clean, tidy and hygienic for the duration of
the individual project.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (7)
General Specifications, Preliminary and General Items

It shall be the PIA’s responsibility to ensure that he is in compliance with all relevant
laws and regulations as well as tribal requirements.

Wherever feasible, the PIA shall make the construction camp part of the permanent
works, for use by the DM. Use may include training centres, O&M centres, etc. or the
PIA shall, on completion of the works remove the facilities.

In addition the PIA, as part of his establishment in the District Municipality shall have a
depot. The purpose of the depot is to keep sufficient materials and equipment for
operation and maintenance purposes of completed individual Sections of the Works
where there is a long-term O&M Section of the Works and shall be covered in the
business plan under the O&M responsibilities. This depot should be established after
consultation with the DM.
[This depot may be established in the yard of the DM to facilitate the transfer of skill –
and to enable the DM to take over the complete O&M function at the end of the contract
(in case of long term O&M functions. This is a part which will need to be assessed by
the final drafter on behalf of the DM It may also be an option to move the standard
delivery point of material to this yard.]
19.3
Water Supply
Water supply will not necessarily be available at individual sites. The PIA shall be fully
responsible for all his water requirements and shall assess the suitability of the water for
construction of concrete structures prior to the commencement of construction on any Section
of the Works.
19.4
Power Supply
Power supply will not necessarily be available at individual sites. The PIA shall, for construction
purposes, make his own arrangements for power. If power is needed for the operation of the
individual Project after completion, then the PIA shall find the most economic way to supply
power to the Project, and if feasible, utilise the supply for construction purposes. In this case,
in accordance with the Conditions of Contract, the DM shall be reimbursed for power
consumed for construction purposes.
20.
PS7 SITE FACILITIES REQUIRED
[This section needs to be completed by the DM in the final drafting of the document]
21.
PS8 FEATURES REQUIRING SPECIAL ATTENTION
21.1
Labour-Based Construction
The Works shall be carried out using labour-based construction methods, where appropriate,
and the PIA shall adhere to the principles set out below.
Labour-based or labour intensive construction may be defined as the economically efficient
employment of as much labour as is technically feasible to produce the standard of
construction demanded by the specification and allowed by the funding available. In other
words, Works based on labour-intensive principles aim at devoting the highest feasible
proportion of Project costs to unskilled, semi-skilled and skilled labour without jeopardizing the
technical quality of the product demanded by the specification. Labour-based methods of
construction result in the creation of a significant increase in employment opportunities per unit
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (8)
General Specifications, Preliminary and General Items
of expenditure. The intensive employment of labour achieves value for money through
innovative techniques of work and management. In particular:

As far as possible, payment of wages for labour is related to production output: a
reasonable “task” is set, upon completion of which the labourer may go home or start
a new task and

Employment is either on a daily/casual/temporary basis or in the form of a short-term
monthly contract.
A high degree of community participation shall be exercised throughout the process and the
PIA shall describe this in his business plan.
The PIA shall note that:

It is required from the PIA to provide all training, superintendence, labour (i.e. local
people where labour-based works are performed), small tools and materials for the
execution of the labour intensive construction.
The following types of activities shall use labour-based construction methods on this project:

Clearing and grubbing of the Site

Cleaning and tidying up of the Site

Excavation of pipe trenches in soft conditions and where trench depths permit
economic production.

Standpipes and yard connections

Backfilling and compaction of all pipe trenches irrespective of depth

Laying, bedding and testing of all pipe work of nominal diameter up to 200mm,
including all fittings and valves

Mixing, transporting, placing and finishing of all concrete

Spoiling of all materials within distances not exceeding 20 metres

Building of small brick structures

Erection of steel frameworks

Spring protection schemes

River abstraction

Plumbing
Sites where labour-based methods or SMME development cannot be practised shall be
identified by the PIA in the respective Business Plan and specifically approved in writing by the
DM prior to commencement of construction.
The PIA shall note the minimum wages as prescribed by legislation. The Programme
Implementation Agent shall, when requested by the Engineer, submit a detailed breakdown /
explanation of the basis on which labour-based rates have been calculated.
Improved BoTT: Version 1: June 2001
Volume
Part
21.2
1
i
2
A
3
B
4
C
5
D
6
E
Page E (9)
General Specifications, Preliminary and General Items
Provision of a Temporary Workforce for the Contract
The PIA shall have regard for the stipulation laid down for all RDP Projects that he employs
labour from the local community through the Institutional Labour Desk, or similar
arrangements, that have been established for this purpose. The stipulation shall apply equally
to all construction and operation and maintenance Sections of the Works. Throughout all his
activities the PIA shall ensure that the objective of leaving behind skills in the community is
met.
The PIA shall utilise labour desks, to be set up as appropriate, to assist in identifying available
local labour, semi-skilled labour and Sub-Contractors where available. The Labour Desk
shall also be used to assist and advise regarding conditions of employment, minimum wages,
disputes and disciplinary procedures.
Although the PIA shall adhere to the statutory minimum wage rate, he is, however, at liberty to
negotiate additional incentive payments based on performance. Such negotiations should be
approved by the Labour Desk prior to implementation of the said incentives.
The Occupational Health and Safety Act must be adhered to.
21.3
Restriction of the Utilization of Personnel in the Permanent Employ of the Contractor
The PIA shall limit the utilization on the Works, of his permanently employed personnel to that
of key personnel only, as defined below, and shall execute and complete the Works utilizing a
Temporary Workforce of local residents, employed directly by the PIA and/or by his subcontractors.
“Key personnel” means all contract managers, site agents, site clerks, materials and survey
technicians, quantity surveyors, trainers, supervisors, foremen, skilled plant operators and the
like, and all other personnel in the permanent employ of the PIA or his sub-contractors who
posses special skills, and/or who play key roles within the Programme Implementation Agent’s
or his sub-contractor’s operations.
21.4
SMME development
The PIA shall be required to sub-let portions of the Works as hereinafter defined, in
accordance with the provisions of the Contract to Small, Medium and Micro Enterprises
(SMME):

Hand excavations in soft material

Laying of pipes up to 200mm nominal diameter, including the provision of bedding and
selected fill materials, testing and disinfection

Placing and compaction of bedding and backfill materials

Disposal of surplus material

Brickwork

Site clearance

Dismantling and re-instatement of existing fences

Plumbing

[Other portions as determined by DM]
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (10)
General Specifications, Preliminary and General Items
The Engineer may at his discretion, upon receipt of a written and fully motivated application
from the PIA, and where he deems the circumstances so to warrant, and provided always that
the PIA has complied fully and in all respects with the provisions of the Contract pertaining to
subletting or has utilized his best endeavours to comply therewith, authorize in writing that the
PIA may employ local residents with the sole intent of executing the job training of such local
residents to suitable levels of skill that enables the PIA to sub-let appropriate portions of the
Works to such local residents.
Without limiting the generality of application of this sub-clause, circumstances which may be
considered by the Engineer to warrant such authorization include:
The Engineer shall not grant such authority in cases where it may reasonably be concluded on
the available evidence that the invitation of further tenders/quotations in accordance with the
terms of the Contract, is likely to result in the successful completion of the portions of the
Works concerned by local sub-Contractors.
The Engineer shall monitor progress achieved with sub-Contractor training, and successful
completion of this training shall be subject to his approval or instruction.
21.5
Additional Reference Sources
The principle embodied in the following guidelines as contained in “The Framework Agreement
for Public Works Project Using Labour Intensive Construction Systems” shall be taken into
account by the PIA:
22.

Broad Guidelines for the Selection Criteria for Employment

Guidelines for Task Based Payment Services and Conditions of Employment

Guidelines for a Training System
SPECIFICATIONS FOR PRELIMINARY AND GENERAL ITEMS
A preliminary and general section of the schedule of quantities is provided to cover the PIA’s
charges for compliance with the requirements of the Conditions of Contract and with the
Employers Requirements.
Provision is made in the schedule for lump sums to cover the cost of supplying and
dismantling and removing offices facilities and equipment of a preliminary and general nature
in terms of the contract. Wherever practicable, separate preliminary and general items are
scheduled.
The sum tendered in the schedule for the preliminary and general items shall cover the PIA’s
direct and indirect costs and profit, as well as all other costs for the provision of the item and
the costs of complying with the obligations, liabilities, risks and requirements associated with
the item.
22.1
Measurement and Payment
22.1.1 Fixed costs
These amounts will be paid in one single payment, in terms of the schedule of payments
issued after the PIA obligations in terms of that item have, in the opinion of the Engineer have
been discharged. Should the amount of the contract increase, the “extra over” will be paid in
one lump sum on the anniversary date of the Commencement Date for establishment.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (11)
General Specifications, Preliminary and General Items
The fixed costs shall cover the PIA’s initial costs of providing performance sureties, insurance,
third party as well as other financing options and the setting up of offices as required by the
contract.
22.1.2 Value Related costs
These amounts will be paid in terms of the schedule of payments issued after the PIA
obligations in terms of that item have, in the opinion of the Engineer have been discharged.
The value related costs shall cover the PIA’s ongoing costs of providing performance sureties,
insurance, third party as well as other financing options as required by the contract.
22.1.3 Time Related costs
These amounts will be paid monthly in terms of the schedule of payments issued after the PIA
obligations in terms of that item have, in the opinion of the Engineer have been discharged.
The sums shall cover the costs of providing supervision and management as the PIA’s feels is
necessary for the Works and shall cover the costs of supervisory and administrative staff,
transport and other employment package requirements of such staff that may include but is
not limited to subsistence allowances bonus, cell-phones, medical aid, pension or provident
fund provision, insurance and other items as necessary for the proper execution of the works.
22.1.4 Monitoring of Implementation
This shall include the PIA’s designer’s fee for construction monitoring which shall include:

Be available to provide the PIA with technical interpretation of plans.

Visit the site at a reasonable frequency to review important materials, critical work
procedures and/or completed elements or components.

Review a sample of each important work procedure and construction material for
compliance with the requirements of the plans and specifications and to review
random samples and review important completed work prior to enclosure or on
completion as appropriate.
Contract Monitor
23.
Type A
An experienced professional Engineer or other relevant qualifications for other
types of services, with greater than 10 years experience.
Type B
A qualified professional Engineer or relevant qualification for other types of work
with 5 –10 years experience
Type C
A qualified technician with 2 years experience.
SCHEDULE OF QUANTITIES
See Volume 5, Part 3 – Employer’s Requirements Ps and Gs.
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (12)
General Specifications, Preliminary and General Items
---- END OF SECTION ----
Improved BoTT: Version 1: June 2001
Volume
Part
1
i
2
A
3
B
4
C
5
D
6
E
Page E (1)
General Specifications, Preliminary and General Items
Improved BoTT: Version 1: June 2001
Download