POWER UTILITY The power and utility area consists of equipments, their potential outputs and general condition. Boilers (8): All boiler supply steam to a common 875 psi header at 825°F No.1 Power: Design maximum steam flow 200,000 #/hr Fuel: Sludge, Bark, TDF and natural gas General condition of this boiler is good. The primary super heater section is an exception and was scheduled for partial replacement in year 2001. The ID fan rotor was replaced in 2000. No.2 Power: This boiler was dry fired and severely damaged. It is not considered repairable. No.2A Package: Design steam flow 165,000 #/hr Fuel: Natural Gas General Condition: Fair This boiler is need of super heater repairs. 50% of super heater tubes were scheduled for replacement in 2000. The generator wall tubes in this boiler do not have vibration bars and stress related cracking is suspected to be present (no failures in this area to date) No.2B Package: Design steam flow 165,000 #/hr Fuel: Natural Gas General Condition: Very Good This boiler received a major overhaul in 1999 which included generator wall tube replacement and vibration bars to prevent stress related cracking. This boiler, like its twin 2A, is difficult to properly warm up and bring into service due to the lack of a startup burner and an oversized main burner for starting purposes. No.2C Package: Design steam flow 165,000 #/hr Fuel: Natural Gas General Condition: Excellent This is a new boiler that went into operation in 1999 to replace the No.2 power boiler. No.1 Waste Heat: Design steam flow 65,000 #/hr Heat Source: #2 Gas Turbine Generator Exhaust This unit is not operational and requires a major overhaul before returning to service. It will also require retrofit of steam injection for NOx control No.2 Waste Heat: Design steam flow 65,000 #/hr Heat Source: #3 Gas Turbine Generator Exhaust This boiler was found to be in good condition following the inspection / overhaul of the gas turbine generator / waste heat boiler unit in 1999. Recovery Boiler: Designed to process 2.1 MM # dry solids/day and generate 250,000 #/hr steam Primary Fuel: Black Liquor Secondary Fuel: Natural Gas This boiler is in poor condition overall. The integrity of the furnace and other pressure parts are in fair condition. The duct work, cascade evaporators and precipitator are in extremely poor condition. Five of the twenty two pendants in the intermediate super heater section have been removed following tube failures in the past several years. ABB conducted a study of the boiler capabilities considering the super heater issue and concluded that the maximum steam output be limited to 200,000 #/hr. This equates to a 1.8 MM dry solids/day firing rate. The recovery boiler was last fired in 2000 and is no longer considered an operational unit. Black Liquor Evaporators: Design is 1200 gpm, however they are limited to 900 gpm due to all internal body heaters being bypassed. General condition is fair. These units were last operated in 2000. Turbine Generators (4) No.1 Steam Turbine (General Electric): Rated 25,000 KW, will operate at 30 MW Single 65# extraction with condensing exhaust. General condition: Good. Due for major overhaul in 2001. Mark II EHC is obsolete. No.4 Steam Turbine (Westinghouse): Rated 30,000 KW, will operate at 40 MW Single 65# extraction with condensing exhaust. General condition: Fair. Scheduled for major overhaul in 2000. No.2 Gas Turbine: Rated 16,000 KW, not operational No.3 Gas Turbine: Rated 16,000 KW, limited to approximately 14.5 MW due to NOx emissions. This unit is not equipped with steam injection for NOx control. This unit was overhauled in 1999 and is in good condition. 15 KV Electrical Distribution System This system consists of original main bus and feeders, plus add-ons that have taken place in past several years during expansion projects. The system is in fair condition but is not user friendly and presents risk when bring the public utility on and off the Mill system. Maintaining designed system voltages across the four buses could not be accomplished primarily due to transformer taps being frozen in place. A study of entire electrical systems needs to be done in order to provide for a reliable and efficient operation. Boiler Feed Water System Demineralizers: Consists of three cation and three anion units. The units are rated in 600 gpm each. The system is in good condition with new resin in all units. All vessel rubber liners were inspected and repaired in 1999. Deaerator: Consists of two heaters with one storage vessel. The system is rated at 1.2 million pounds per hour. The system is in good condition. Feed Water Pumps: Consists of four 750 gpm pumps. Three pumps are steam turbine driven and one electric. All four are in very good condition. Water Supply Seven wells at site are capable of providing 20 million gallons/day but are limited to 10% of the total mill usage by governmental regulation. All are in good condition. The surface water treatment plant is capable of providing 20 mgd. The city provides lake water to surface water treatment plant. Equipment consists of a lift station, two clarifiers, eight multimedia filters, associated pumps and a three million gallon storage tank. The filter media was replaced in 2000. There are two sludge ponds. Wastewater Treatment Hydraulic capacity approximately 18 mgd. Consists of two primary clarifiers, three aeration basins, two secondary clarifiers, and a lift station to move effluent water through pipe to discharge at a long distance. The system is in good condition. Sludge Dewatering Plant Capable of dewatering up to 225 bone dry tons (BDT) per day of fuel to #1 power boiler. The system was upgraded to 345 BDT/day. The system includes screw presses, pre-thickening devices and associated tanks and pumps. Compressed Air System The system consists of five rotary compressors with a total output of 9840 cfm. Equipment consists of two Sullair rated at 1520 cfm each, one Sullair rated at 1800 cfm, two Centex rated at 2500 cfm each. All are in good condition with two being rebuilt in 1999. Instrument Air Dryers: Three sets. All required new desiccant in 2000. Condition: Fair to Good DEINK PLANT MAJOR PROCESS EQUIPMENT Warehouse Bale Dewiring: One (1) Lamb Mark 5 / 150-08-D Bale Dewiring Machines. Rated at 90 bales/hr each. Installed in 2000. Bale Dewiring Conveyor: Nielson & Hiebert 7”-10” x 182’-2” Rated at 30 FPM, 2592 ODSTPD. Installed in 2000. Pulper Feeder: Newsprint Conveyor: Grace Metal Slat Conveyor Rated at 11950 ODSTPD. Installed in 1992 Magazine Conveyor: Grace Metal Slat Conveyor Rated at 211 ODSTPD. Installed in 1992 Drum Pulper Feeder Conveyor: Nielson & Hiebert 96” x 116.11’ Rated at 30 FPM, 1406 ODSTPD. Installed in 2000. Deinking Plant Pulping: Ahlstrom Drum Pulper – Fiberflow 425 extended Rated at 1700 ADSTPD. Installed in 2000. HD Cleaners: Three (3) BIR 1200 HDC 12” Cleaners Rated at 1044 GPM @ 3.43% cons. Installed in 1992. Seven (7) Mill Fabricated 12” Cleaners Rated at 1079 GPM @ 3.43% cons. Installed in 2000. Coarse Screening: Two (2) Thermo Black Clawson Fiberprep CH7 Screens Rated at 2532 GPM feed @ 3.31% cons. Installed in 1992. One (1) Thermo Black Clawson Fiberprep CH7 Screen Rated at 2532 GPM feed @ 3.31% cons. Installed in 2000. One (1) Thermo Black Clawson Fiberprep CH5 Screen Rated at 1119 GPM feed @ 3.64% cons. Installed in 1992. Four (4) Thermo Black Clawson Fiberprep CH3 Screens Rated at 979 GPM feed @ 3.31% cons. Installed in 1992. One (1) Thermo Black Clawson Diablo 2 Screen Rated at 280 GPM feed @ 2.97% cons. Installed in 1992. One (1) Thermo Black Clawson Diablo 3 Screen Installed in 1992. Floatation: Two (2) Flotation Mixing Cells – Voith Sulzer 1.5 Meter Cells Rated at 3859 GPM @ 1.18% cons. Installed in 1992 Fourteen (14) Primary Flotation Cells – Voith Sulzer 3 Meter Cells Rated at 4266 GPM @ 1.18% cons. Installed in 1992 Four (4) Secondary Flotation Cells – Voith Sulzer 2 Meter Cells Rated at 2650 GPM Installed in 1992 One (1) Flotation Mixing Cell – Voith Sulzer ECC6/44 Rated at 20000 GPM Installed in 2000 Six (6) Primary Flotation Cells – Voith Sulzer ECC6/44 Rated at 12700 GPM Installed in 2000 Two (2) Secondary Flotation Cells – Voith Sulzer ECC6/44 Rated at 5200 GPM Installed in 2000 Forward Cleaners: Five (5) Banks of Alshtrom Cleaners 144, 4 Rows, RB45, SPU Rated at 6298 GPM @ 0.9151% cons each. Installed in 2000 Four (4) Banks of Beloit PB50 Cleaners – 48 Cleaners per Bank Rated at 2017 GPM @ 0.8% cons per bank. Installed in 1992 Two (2) Banks of Beloit PB20 Cleaners – 20 Cleaners per Bank Rated at 586 GPM @ 0.6% cons per bank. Installed in 1992 One (1) Banks of Beloit PB10 Cleaner – 10 Cleaners per Bank Rated at 193 GPM @ 0.375% cons per bank. Installed in 1992 Fine Screens: Five (5) Voith Sulzer Screens – VPS 40/16 Rated at 6300 GPM @ 0.9% cons. Installed in 2000 Two (2) Thermo Black Clawson Screens – Fiberprep SPM-1500 Rated at 2780 GPM @ 0.75% cons. Installed in 1992 One (1) Thermo Black Clawson Screens – Fiberprep SPM-800 Rated at 1314 GPM @ 0.685% cons. Installed in 1992 One (1) Thermo Black Clawson Screens – Fiberprep SPM-400 Rated at 308 GPM @ 0.68% cons. Installed in 1992 Disk Filters: Two (2) Celleco Disk Filters – 4 MLW-18 Rated at 48376 GPM @ 0.77% cons. Installed in 1992 One (1) Kvaerner Disk Filters– DF-520X28/30 MLW-18 Rated at 940 ODSTPD Installed in 2000 Screw Presses: Three (3) Hymac Presses – SP-70SL Rated at 150 ODSTPD Installed in 1992 Five (5) Kvaerner Presses – SP-70SL / HHC 5-38RPM Rated at 210 ODSTPD Installed in 2000 Note: One (1) SP-70SL / HHC was transferred to AR in 2005 (4 on hand now) Stock Conveyors: One (1) Collection Conveyor – Nielson & Heibert 42” x 89’ CC / HLOA Rated at 170 T/hr @ 200 FPM Installed in 2000 One (1) Transfer Conveyor – Nielson & Heibert 42” x 77’-2” HLOA Rated at 170 T/hr @ 200 FPM Installed in 2000 One (1) Stock Conveyor – Continental Conveyor Curved Belt 42” x 1900’ Rated at 170 T/hr @ 300 FPM Installed in 2000 Idled Equipment Available for Sale: Two( 2) High Consistency Hydra Pulpers Voith – HD40 with Hansen RVK24S 9.9375:1 Ratio Gearbox and 900HP, 4160V, 1200RPM Motor. Rated at 260 BDSTPD @ 12% Consistency based on application. Idled in 2000 Two (2) Contaminex – Voith CMS 30 with 120 HP Motor to be used with Voith Hydra Pulpers. Idled in 2000 Seven (7) Cleaner Banks – Two (2) Beloit UB 20, One (1) Beloit UB 30 and Four (4) Beloit UB 40 High Flow UniFlow Cleaner Banks. Removed in 2000 Two (2) Disperger Systems – Suzler – Escher Wyss HD3 with 900HP, 4160V, 1200RPM Motors, Heating Screws, etc. Built in 1991 MAJOR EQUIPMENT ASSETS Wood Handling & Preparation Major Components have been out of service for approximately 5 years 1. 2. 3. 4. Log Handling: Chip/Bark Handling: DeBarkers: Bark Hogs: Chain Conveyors Belt Conveyors Two (2) 12’ x 67.5’ FPM Drum, Two sections gone Jeffery Bark Hogs 5. 6. 7. Wood Chipping: Rechipper: Chip Screens: One (1) 104” – 15 Knife Murray Chipper One (1) 40” – 6 Knife Arcowood One (1) # 812 Black Clawson – Two (2) Rotex Chip Screens Pulp Mill Major Components have been out of service for approximately 5 years 1. 2. 3. 4. 5. Kraft Avg. Daily Production Capability; Bleached SWD; 575 Tons Un Bleached and Semi Bleached Continuous Digester: Kamyr Ground Wood, Stone Avg. Daily Production Un-Bleached SWD; 500 Tons Grinders: 10 Great Northern Waterous Ground Wood Refined: 450 Tons TMP Plant Major Components have been out of service for approximately 4 years 1. Sunds Defiberator Refiners: Two (2) RLP58S, 12000 HP Primary Two (2) R158S, 12000 HP Secondary One (1) RLP58S, 12000 HP Rejects Flotation DeInking Facility Major Components have been out of service for approximately 2 years Maximum production capacity is 1700 Tons per day Bleach Plant Sequence, Kraft; C-E-H, Towers; 1 UpFlow, 2 DownFlow; 500 Tons per day Major Components have been out of service for approximately 5 years Pulp Processing Drainers: Kraft Mill: Major Components have been out of service for approximately 5 years 1. 2. 3. 4. 5. 6. 7. Screens: 3 Primary, 2 Secondary, 1 Reject Hymac Cleaners: 1 - 20’ Magna Cleaners Washers: 1 – Impco CV Brown Stock, 3 – Dorr Oliver Vacuum Bleached Stock Deckers: 1 – Impco Vacuum Drainers: GWD Mill – 2 Hymac, 2 Thune Presses Screens: 9 – Impco Vibratory, 11 – Hymac Cleaners: 5 – 36” Magna Cleaners, 1- Two Stage , Twenty Body Bauer Steam PROCESS DESCRIPTION / FLOW DIAGRAM DEINK PROCESS The deink mill was initially installed and run in 1993 at a production rate of approx 300 TPD. Many expansion projects occurred between 1995 until 2001 to replace the pulp production capacity after the shutdown of Kraft, Groundwood and TMP mills. Total production of the plant at full operation by design is 1700 TPD. Modifications to the Deink mill from to expansion projects included changing from the batch pulpers and trash screens to a continuous drum pulper and trash screens. Other changes included modifications to the high-density cleaners and coarse screens before the floatation cells, and removal of the reverse screens after the floatation cells. The pulping chemistry was changed to neutral pH, and the screw presses were located after the disc filters in the process. The paper arrives at deink plant by truck and rail. It comes in bales and loose shipments. Old newspapers known as ONP, and old magazines known as OMG are shipped and are stored separately so that they may be metered for the deink process. Operators place the paper for the pulpers on the proper conveyor. As the paper goes to the top its respective conveyor, it passes through a weighing device, which determines how much paper is being fed to the pulper. During pulping, water, chemicals, ONP and OMG are all added to the pulper. These work to hydrolyze the fiber and also separate ink and filler from the mixture. The system continuously feeds into the drum pulper the desired quantities of hydrogen peroxide, sodium silicate, DTPA (chelant) and surfactant along with hot water and paper. As the paper travels through the drum, the mechanical rubbing brought about by the rotation breaks down the paper into pulp. The chemicals and water help the paper to disintegrate for removal of ink from the fibers. The end section of the pulper has a screen and shower nozzles and wash the pulp from the drum. As the pulp is flushed from the drum, the contaminants roll to the end and are discharged to the ground. The pulp is pumped from the pulper to coarse screen feed chest. From the chest, pulp is fed to high density cleaners in to banks. The high density cleaners remove large material that is heavier than water. These contaminants include rocks, glass, nuts, bolts, etc. From the high density cleaners the stock passes through two banks of centrifugal coarse screens with holes that remove additional rejects from the stock. Rejects from the quaternary screen are discharged to a sand separator and are subsequently land filled. After removal of large contaminants, the pulp enters the floatation system for ink removal. The stock is diluted to a 1.25% consistency after the floatation feed chest before it enters the floatation mixing cell chamber. There are three lines of floatation with two stages each, the primary stage and the secondary stage. In each cell, air is drawn in and thoroughly mixed with the pulp. The ink attaches to the air bubbles and is turned into inky foam which is skimmed off. The accepted pulp exits the bottom of first cell and moves to the second cell to repeat the process through all seven cells on A and B line and six cells on C line. The accepted pulp from the primary floatation stage is discharged into a deareation chest to be further processed. The inky foam discharges into a weir and onto the secondary system. The secondary floatation stage which operate like the primary stage, recovers acceptable fiber from the inky foam. The inky foam rejected from the secondary stage goes into the sludge tank. The accepted pulp returns into the floatation cells for additional cleaning. The accepted pulp after being deinked in the floatation system must now be cleaned. The stock is pumped to the forward cleaners. The forward cleaners perform under the same principles as the high density cleaners, only at much lower consistency. There are four stages in forward cleaners to remove additional contaminants and ink heavier than water. The accepted pulp enters the fine screen feed chest and the rejects go to the sludge tank. The fine screen also contains four stages and removes all but the smallest of particles. The accepted pulp from the fine screens is sent to the disc filters and the rejects are sent to the sludge tank. The pulp sent to disc filters is dewatered to a 12% to 15% consistency using vacuum. From the disc filters the pulp is conveyed and pumped to the screw press feed chest. Screw presses remove the water from the stock by squeezing it at high pressure. The stock exits the press at approximately 30% consistency. The removed water is reused in the pulping process. PAPER PROCESS The process for the paper machines begins with stock preparation. The stock preparation process is to bleach the mechanical and deink pulps with sodium hydrosulfite to improve brightness, and meter these pulps together with bleached Kraft. The pulps are mixed together in blend chests that are agitated, and then diluted with recycled water to slurry of 99% water and 1% fiber. After blending the stock is de-aerated, screened to remove contaminants not removed in the pulping process, dyed, pH controlled, and heated. At this time, the pulp is ready for paper machines. The paper machine complex consists of three twin wire paper machines. All three paper machines make a newspaper grade made from pulp manufactured in the mills for pulping processes. The pulp furnishes vary with the grade of paper that is being manufactured. In the wet end of the paper machine, the mixed pulp is sprayed from the head box between two moving wire screens. Water is removed from the pulp with vacuum pumps which create a pressure differential between the stock and the screen. After passing between the wire screens, the stock begins to form a paper sheet which passes through the press section of the machines. Water is squeezed out of the sheet while moving between several rollers. The sheet then enters the dryer section where the water is removed by evaporation. In the dryer section, the sheet moves along a series of rolls called the calendar stack. The calendar stack is designed to remove the wrinkles and smooth the sheet. The sheet is then collected on a reel and then cut to customer specifications. Through the paper machine process, the pulp is dewatered and dried from a 99% consistency to about a 4% consistency as finished paper. A large portion of the water that is dewatered from the pulp is recycled and reused in the paper making process. POWER SYSTEM The power and utilities department plays a key role in the manufacturing of newsprint. It supplies four services to the mill: electricity, steam, air and water. The water is supplied to the mill as surface water from a nearby lake and from seven wells located on the mill site. Chlorine gas, used as Biocide, Alum and Polymer are added to the raw water as it enters the surface water treatment plant. The water used to make steam in the boilers at the mill must be treated before its use. Demineralizing is the process which removes minerals in order to prevent scaling on boiler tubes. This is a critical concern on any boiler operation. There are six boilers in the power and utilities area that produce 875 psi steam. The No.1 power boiler is a negative draft type boiler with a fluidized sand bed. This boiler is fueled form the bark from the woodyard, sludge from the waste water treatment plant, and tire derived fuel (or scrap tire chips) which can be supplemented with natural gas. It produces 200,000 pounds of steam per hour. There are also 2A, 2B and 2C package boilers which are fired by natural gas and can each produce 165,000 pounds of steam per hour. The last two boilers are the No.1 and No.2 waste heat boilers. The exhaust heat produced in No.1 and No.2 gas turbines can be used to generate steam in the waste heat boilers. These boilers can each produce 70,000 pounds of steam per hour which is an efficient use of mill resources. WASTEWATER TREATMENT The purpose of the wastewater treatment plant is to eliminate pollutants from the water so it can be safely discharged. The mill uses an activated sludge process to remove these pollutants. The main sewer carries wastewater generated at the mill into the division structure. The process sewer at the deink plant also joins at this point. The influent is divided into two primary clarifiers. Sludge is removed from the bottom of the clarifiers and pumped to the surge tank. From the clarifiers, the overflow goes onto the chemical feed box where nutrients in the form of ammonia and phosphoric acid are supplemented. Defoamer is also fed on as needed basis. From the box, the effluent goes through the aeration basins which are equipped with mechanical surface aerators. The effluent enters two secondary clarifiers for final clarification before it is discharged to the outfall. A portion of the biological sludge that settles at the secondary clarifiers is recycled back to the aeration basins to maintain the microbial population. From the surge tank, sludge is pumped to the sludge plant for dewatering. A portion of the deink sludge is directly pumped from the deink plant to the sludge plant. Sludge is combined kept agitated in the mix tanks. Polymer and Alum are added to the sludge for conditioning. Sludge is pumped to flock tanks which feed the gravity belt thickeners (GBT’s). From the GBT’s the sludge goes into the screw presses where any remaining water is extracted to achieve approximately 50% dryness. Sludge emerging from the screw presses is transported to the No.1 power boiler by a conveyor. The derived fuel is also deposited on this conveyor to be burned in the boiler as supplemental fuel. FINISHING AND SHIPPING Once the paper sheet has been manufactured, the rolls are processed and stored in the finishing area prior to be shipped out to the customer. After the rolls are cut to the size on the winder, they are conveyed by a series of automatic elevators, conveyors, ramps, kickers, cushion stops and turntables, to the roll wrap area. After the rolls are inspected, a protective wrap is placed on them, inside protective heads are inserted, and the roll ends are crimped. The roll ends are then glued in preparation of protective outside head application, using heat, the heads are sealed to the ends of the roll. After the rolls leave finishing, they enter the shipping area on one of the two conveyor belts. The rolls are checked for proper identification numbers, size and weight and marked for rail, truck or warehouse storage for later shipments. The storage for paper at the mill is for 5,000 tons of paper. At the time of loading, the rolls are secured with air bags, wood supports or metal banding. Once a load is completed, the shipment is checked for correct roll and weight count.