SULIT UNIVERSITI TEKNIKAL MALAYSIA MELAKA PEPERIKSAAN SEMESTER 2 SESI 2010/2011 FAKULTI KEJURUTERAAN PEMBUATAN KOD MATA PELAJARAN : BMFP 4513 MATA PELAJARAN : PRODUCTION AND PLANNING CONTROL (PERANCANGAN & KAWALAN PENGELUARAN) PENYELARAS : H HAERY IP KURSUS : BMFA/ BMFB/ BMFP/ BMFR/BMFU MASA : 9.00 PAGI – 12.00 PAGI ( 3 JAM) TARIKH : XX APRIL 2011 TEMPAT : DEWAN UTeM ARAHAN KEPADA CALON: 1. Kertas soalan ini mengandungi DUA (2) Bahagian iaitu Bahagian A dan B. 2. Sila jawab SEMUA soalan di Bahagian A. 3. Jawab SATU (1) soalan sahaja dari Bahagian B 4. Gunakan muka surat baru untuk setiap soalan yang dijawab. KERTAS SOALAN INI TERDIRI DARIPADA EMPAT BELAS (14) MUKA SURAT SAHAJA (TERMASUK MUKA SURAT HADAPAN) SULIT (BMFP 4513) SULIT PART A ANSWER ALL QUESTIONS QUESTION 1 What are the special requirements of supply chain systems in global environments? [2 marks] ANSWER Supply chains in a global environment must be flexible, so that the firm can react to sudden changes that might occur in parts availability or currency rates. They must be able to use latest information technology for scheduling and managing shipments of parts and products. And they must be staffed with specialists to handle duties, customs, and political issues in other countries. (The strategic importance of the supply chain, moderate) QUESTION 2 Differentiate between a push and a pull system. [3 marks] ANSWER A push system pushes material into downstream workstations regardless of the resources available. A pull system uses signals to request delivery from upstream stations to the station that has production facilities available. In a pull system, materials or parts are pulled where they are needed when they are needed. (Just-in-time and lean production, moderate) QUESTION 3 Hitooth, Inc., produces short runs of custom airwave blower for the defense industry. You have been asked by the owner, Mr. Otoho , to reduce inventory by introducing a kanban system. After several hours of analysis, you develop the following data for airwave blower used in the cvo. Daily Demand Lead Time Safety Stock Kanban Size 1,000 cvo 2 days ½ day 500 cvo How many kanban do you need for this equipment? [5 marks] 2 SULIT (BMFP 4513) SULIT ANSWER • Demand during lead time-of 2 days: (1,000 x 2 ) = 2,000 • Safety stock (1/2 day) = 500 • Maximum inventory level = 2,500 Number of kanbans needed: 2,500 (Maximum inventory level) 5 500 (Kanban size) QUESTION 4 Ezee Electronics Sdn Bhd is an electronics manufacturing company that produces a variety of products for several applications. One of the main products is Robo Vacuum. Given below are the production information for Robo Vacuum: Week 1 2 3 4 5 6 7 8 9 10 Working days (days) 2 2 4 1 2 2 4 2 4 5 Machine capacity (products/hour) 5 4 2 3 1 4 2 2 5 2 Time Available (hours/day) 2.2 4.25 4 4 4 5.5 6.75 4 3.8 3 The Robo Vacuums cost RM 650 each and the holding cost is 0.5% per week. The fixed order cost is estimated to be RM 200. a) Based on the table above, Generate the demand for Robo Vacuum for week 1 until week 10. [5 marks] b) Apply the Silver Meal heuristic to find the ordering policy. [ 6 marks] c) Apply the Least Unit Cost heuristic to find the ordering policy. [ 6 marks] 3 SULIT (BMFP 4513) SULIT d) By comparing the Silver Meal and least Unit Cost heuristic, which method results in the lowest cost policy? [ 3 marks] ANSWER a). Week 1 2 3 4 5 6 7 8 9 10 Working days (days) 2 2 4 1 2 2 4 2 4 5 Machine capacity (products/hour) 5 4 2 3 1 4 2 2 5 2 Time Available (hours/day) 2.2 4.25 4 4 4 5.5 6.75 4 3.8 3 DEMAND (units) 22 34 32 12 8 44 54 16 76 30 b) K = 200 Holding cost = 0.005 * 650 = 3.25 r = (22, 34, 32, 12, 8, 44, 54, 16, 76, 30) a) Silver Meal Solution Start in period 1: C(1) = 200 C(2) = [200 + ((3.25)(34)]/2 = 155.25 C(3) = [(155.25)(2) + (3.25)(2)(32)]/3 = 172.83 Stop. y1 = r1 + r2 = 56 Start in period 3: C(1) = 200 C(2) = [200 + (3.25)(12)]/2 = 119.5 C(3) = [(2)(119.5) + (2)(3.25)(8)]/3 = 97 C(4) = [(3)(97) + (3)(3.25)(44)]/4 = 180 4 Stop. SULIT (BMFP 4513) SULIT y3 = r3 + r4 + r5 = 32 + 12 + 8 = 52 Start in period 6: C(1) = 200 C(2) = [200 + (3.25)(54)]/2 = 187.75 C(3) = [(2)(187.75) + (2)(3.25)(16)]/3 = 159.83... C(4) = [(3)(159.833..) + (3)(3.25)(76)]/4 = 305.125 Stop. y6 = r6 + r7 + r8 = 44 + 54 + 16 = 114 Obtain y9 = r9 + r10 = 106 Silver Meal Solution = (56, 0, 52, 0, 0, 114, 0, 0, 106, 0) Cost = (4)(200) + (3.25)(34 + 20 + 8 + 70 + 16 + 30) = $1378.50 c) Start in period 1: C(1) = 200/22 = 9.09 C(2) = [200 + (3.25)(34)]/(22 + 34) = 5.54 C(3) = [200+(3.25)(34+(2)(32))]/(22+34+32) = 5.89 Stop. y1 = r1 + r2 = 56 Start in period 3: C(1) = (200)/(32) = 6.25 C(2) = [200 + (3.25)(12)]/(32 + 12) = 5.43 C(3) = [200 + (3.25)(12+(2)(8))]/(32+12 8) = 5.60 Stop. y3 = r3 + r4 = 44 Start in period 5: C(1) = 200/8 = 25 C(2) = [200+(3.25)(44)]/(8 + 44) = 6.60 C(3) = [200+(3.25)(44+(54)(2))]/(8+44+54) = 6.55 C(4) = [200+(3.25)(44+(54)(2)+(16)(3))]/(8+44+54+16) = 7.97 Stop. y5 = r5 + r6 + r7 = 106 5 SULIT (BMFP 4513) SULIT Start in period 8: C(1) = 12.5 C(2) = 4.9 C(3) = 5.3 Stop y8 = r8 + r9 = 92 y10 = r10 = 30 LUC solution: (56, 0, 44, 0, 106, 0, 0, 92, 0, 30) Cost = (200)(5)+(3.25)(34 + 12 + 98 + 54 + 76) = $1,890.50. d) Summary of Results Silver Meal = $1378.50 Least unit cost = $1890.50 From the results, we can say that the Silver Meal method results in the lowest cost policy. QUESTION 5 Two engineering students, Belegug and Ontohod, are two brothers currently planning to prepare for the Final Exam Test. Between of them requires the test preparation of course subjects such as Mathematic, Statistic, English, PPC, and Engineering Economy. Based on the experience, they estimate that they will need the time for self study in the following amount of time (in hours) with each set of course materials such as follows: Mathematic Statistic English PPC Engineering Economy ONTOHOD 1.8 0.8 3.1 1.1 2.3 BELEGUG 1.2 2.2 0.7 0.5 1.5 They agree that Ontohod will get the opportunity to see each of course materilas before Belegug. Determine the exact times that each will begin and end studying each subject in order to minimize the total time required for both to complete studying all five subjects if they start the study at 8:00 P.M . [10 marks] 6 SULIT (BMFP 4513) SULIT ANSWER OTO (minute) 108 48 186 66 138 Mathematic Statistic English PPC Engineering Economy Engineering Economy Statistic Statistic 8:00 pm 8:48 Mathematic English Engineering Economy 11:06 11:00 BELEGUG (minute) 72 132 42 30 90 PPC Mathematic 12:54 12:36 English 4:00 2:06 PPC 5:06 4:42 The optimal sequence is 2-5-1-3-4. QUESTION 6 The MPS planner at Amburadul Sdn Bhd uses MPS time-phased records for planning enditem production. The planner is currently working on a schedule for the P24, one of Ambradul’s top-selling products. The planner uses a production lot size of 70 and safety stock of 5 for the P24 product. Week Forecast Orders Available Available to Promise MPS 1 30 13 2 30 8 3 30 4 7 4 40 5 40 6 40 7 45 8 45 SULIT 5:36 (BMFP 4513) SULIT a) Complete the MPS time-phased record for product P24 [5 marks] b) Verify if Amburadul Sdb Bhd can accept the following order [5 marks] Order 1 2 3 4 c) Amount 40 30 30 25 Desired Week 4 6 2 3 Update the MPS time-phased record for accepted orders. [5 marks] ANSWER a. Item: P24 Week 1 2 3 4 5 6 7 8 Forecast 30 30 Orders 13 8 Available 60 30 Available to Promise 69 MPS 70 If On-hand = 20, MPS lot size = 70 30 4 70 66 70 40 40 40 45 45 30 60 70 70 20 45 70 70 70 70 70 2 3 4 5 6 7 8 Forecast 30 30 Orders 13 8 Available (on hand =0) 40 10 Available to Promise 49 0 MPS 70 0 If On-hand = 0, MPS lot size = 70 30 4 50 66 70 40 0 10 0 0 40 0 40 70 70 40 0 0 0 0 45 0 25 70 70 45 0 50 70 70 Or Week 1 8 SULIT (BMFP 4513) SULIT b. Order 1 2 3 4 Amount 40 30 30 25 Desired Week 4 6 2 3 Accept (Y or N) Y Y Y Y c. Item: P24 Week 1 2 3 4 5 6 7 8 Forecast 30 30 Orders 13 38 Available 60 22 Available to Promise 39 MPS 70 If On-hand = 20, MPS lot size = 70 30 29 62 1 70 40 40 22 40 40 30 12 45 45 37 70 70 62 70 70 Week 2 3 4 5 6 7 8 Forecast 30 30 Orders 0 30 Available (on hand =0) 40 10 Available to Promise 40 0 MPS 70 0 If On-hand = 0, MPS lot size = 70 30 25 50 5 70 40 40 10 0 0 40 0 40 40 70 40 30 0 0 0 45 0 25 70 70 45 0 50 70 70 1 QUESTION 7 Consider the following MRP record: Week Gross Requirements Scheduled Receipts Projected Available Balance Planned Order Release 52 40 70 1 25 35 10 9 2 30 50 30 3 5 4 15 25 10 5 5 15 20 6 10 10 SULIT (BMFP 4513) SULIT Suppose 15 units of the scheduled receipt for 40 units due on Week 2 are scrapped during week 1, and no scrap ticket is issued. Furthermore, assume this lot isn’t counted before it’s put away in the stockroom on Week 2, but is recorded as receipt of 50 units. What will be the impact of these actions on factory operations? [10 marks] ANSWER Without recording the scrap, the MRP record will appear as it does in the problem. If the scrap had been reported, it would be: Week Gross Requirements Scheduled Receipts Projected Available Balance Planned Order Release 1 25 35 2 30 35 15 10 3 5 4 15 10 -5 5 5 15 5 6 10 -5 Q = LFL, LT = 5, SS = 0 The 5 unit shortage may not be discovered until week 4. At that time, it will be necessary to expedite the scheduled receipt of 15 from week 5 into week 4, and cover the deficiency in week 6. QUESTION 8 A Manufacturing site is supplied by 3 suppliers: A,B, and C. They ship to the site using a trucking company that has a depot in the vicinity. The distances between these entities is as follows: To From A B C Depot Site A 10 20 5 25 B 10 15 6 20 10 C 20 15 30 10 Depot 5 6 30 Site 25 20 10 20 20 SULIT (BMFP 4513) SULIT a) Assume that when A wishes to ship to the site, a truck comes from the depot. Then after loading, they go to the site and returns to the depot. The same pattern is repeated from shipment from B to C. Find the total traveled to bring lots from all three suppliers to the site? [5 marks] b) Determine the percentage saving in travel time if the truck picks up all lots in one pass, travelling from Depot to A , then to B, then to C, then to Site, and back to Depot? [5 marks] ANSWER a. Depot-A-site-return = Depot-B-site-return = Depot-C-site-return = Total = 156 5+25+20 6+20+20 10+30+20 =50 =46 =60 b. Depot-A-B-C-site-return = 5+10+15+30+20 =60 Savings =[156 - (156-60)]/156=38.46% QUESTION 9 There are options for shipping $ 100,000 of machine parts from Tanjung Perak to Klang port in Malaysia as follows: By using a ship that will take 30 days at a cost of $ 3,800 By using truck from Banjarnegara to Tanjung Periuk and then ship to Klang at a total cost of $ 4,800. This option will take only 20 days. You are paid via a letter of credit the days parts arrive. Your holding cost is estimated at 30% of the value per year. {Note: 1 year = 365 days} a) Determine which option is more economical [5 Marks] b) If you have a third option where the costs is only $ 4,000 and takes 25 days, what is your most economical plan? [5 Marks] ANSWER a) Daily holding cost = (Annual holding cost Cost)/Days in year 11 SULIT (BMFP 4513) SULIT = (30 % $100,000)/365 = $82.20. Difference in cost per day between shipping options = ($4,800 – $3,800)/10 days = $100. Since the daily holding cost ($82.20) is less than the daily cost of faster shipping with option b ($100), use the slower shipping, option a. b) Difference in cost per day between shipping options = ($4,000 – $3,800)/10 days = $20. Since the daily holding cost ($82.20) is more than the daily cost of faster shipping ($20), use the faster shipping, option a. 12 SULIT (BMFP 4513) SULIT PART B ANSWER ONE OF THE QUESTION ONLY QUESTION 10 Qlic-Qlic Instruments, The Bandoengers producer of portable ‘korek kuping’ unit and other medical products, develops a 4 –month aggregate plan. Demand and capacity (in units) are forecast as follows: Capacity Source LABOR Regular Time Overtime SUBCONTRACT DEMAND Month -1 Month-2 Month-3 Month-4 235 20 12 225 255 24 15 294 290 26 15 321 300 24 17 301 The cost of producing each ‘korek kuping’ unit is RM 985 on regular time, RM 1,310 on overtime, and RM 1500 on a subcontract. Inventory carrying cost is RM 100 per unit per month. There is to be no beginning or ending inventory in stock and backorders are not permitted. Set up a production plan that minimizes cost using the transportation method. [15 Marks] ANSWER Total cost = RM 1,186,810 13 SULIT (BMFP 4513) SULIT QUESTION 11 Buih Soda, Inc., has a new ‘tarik’ drink for which it has high hopes. Encik Tareq, the production planner, has assembled the following cost data and demand forecast: Quarter Forecast 1 2 3 4 1,800 1,100 1,600 900 Cost / Other data Previous quarter’s output Beginning Inventory Stockout Cost Inventory Holding Cost Hiring Employees Terminating Employees Subcontracting Cost Unit Cost on regular time Overtime Cost Capacity in regular time 1,300 cases 0 cases RM 150 RM 40 per case at end of quarter RM 40 per case RM 80 per case RM 60 per case RM 30 per case RM 15 extra per case 1,800 cases per quarter Encik Tareq job is to develop aggregate plan. The three initial options he wants to evaluate are: • Plan A : A chase strategy that hires and fires personnel as necessary to meet the forecast. • Plan B : A level strategy • Plan C : A level strategy that produces 1,200 cases per quarter and meets the forecasted demand with inventory and subcontracting Evaluate which strategy are the lowest plan between Plan A, B, and C [15 marks] 14 SULIT (BMFP 4513) SULIT ANSWER • Plan A: Chase plan Period Demand Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total Cost 1,800 1,100 1,600 900 5,400 Total Cost: • Reg. Time Production Hiring (Increase) Change 1,800 1,100 1,600 900 5,400 RM162,000 500 –700 500 –700 Layoffs (Decrease) 500 0 500 0 1,000 0 700 0 700 1,400 RM112,000 RM40,000 RM 314,000 Plan B: Level Strategy of 1,350 cases Period Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total Cost Total Cost: Forecast 1,800 1,100 1,600 900 5,400 Reg. Time Production 1,350 1,350 1,350 1,350 5,400 RM162,000 Inventory Holding –450 –200 –450 0 0 0 0 0 0 RM0 Shortage Change 450 200 450 0 1,100 RM165,000 Hiring (Increase) 50 0 0 0 Layoffs (Decrease) 50 0 0 0 50 RM2,000 0 0 0 0 0 RM0 RM329,000 An alternative way of viewing this problem assigns the same costs to regular time production and to hiring (i.e., $162,000 and $2,000) but places holding cost at $28,000 and shortage cost at $67,500. Total cost is then $259,500. • Plan C: Level Strategy at 1200, plus subcontracting: Period Forecast Quarter 1 1,800 Quarter 2 1,100 Quarter 3 1,600 Quarter 4 900 Total 5,400 Cost Total Cost: RM222,000 Reg. Time Production 1,200 1,200 1,200 1,200 4,800 RM144,000 Overtime Production Subcontract Production 600 300 0 RM0 900 RM54,000 Inventory Holding Change 0 100 0 300 0 –100 100 0 0 0 300 0 400 RM16,000 Hiring (Increase) Layoffs (Decrease) 0 0 0 0 0 RM0 100 0 0 0 100 RM8,000 Plan C, because it is not only the lowest cost, but has the added advantage of providing steady employment for the employees after the initial first quarter layoff. 15 SULIT