ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 01630 – System Descriptions 01630.1 Introduction This section contains a system description for each of the systems that shall be constructed as part of the Project. These system descriptions contain the function, major components, system description, and basis for design for each system. Alternate arrangements that meet the overall Facility functional requirements will be considered. 01630.2 Electrical and Controls Systems This section contains a system description for each of the major electrical and controls systems that will be constructed as part of the Project. These system descriptions describe the function, major components, and basis for design for each system. Contractor shall coordinate transmission system operation, generator production, and utility metering with the Employer. Employer shall review and approval the transmission system operations, generator production, and utility metering. The system descriptions contained within this section are as follows: 01630.2.1 AC Power Supply (230/400 V) (APB) AC Power Supply (400 V) (APC) AC Power Supply (6600 V) (APD) DC Power Supply (APH) Uninterruptible Power Supply (API) Emergency Power Black Start (6600 V) (APK) Plant Intercommunications Paging (CMA) Commercial Telephone (CMD) Distributed Control System (COA) Grounding (EEB) Raceway (EEC) Steam Turbine Generator Bus Duct (GTA) Combustion Turbine Generator Circuit Breaker (GTO) Generator Step-Up Transformer (GTU) Combustion Turbine Generator Bus Duct (GTK) Building Lighting (LTA) Area Lighting (STH) AC POWER SUPPLY (230 V) (APB) Function The AC Power Supply (230 V) System provides 230 volt single-phase power for 230 volt loads. Major Components The AC Power Supply (230 V) System will consist of the following major components: 230 volt ac, single-phase panelboards. General Description Source: 01630, 2005 System Descriptions Page 1 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Power for the AC Power Supply (230 V) System shall be provided by the three phase, 4 wire AC Power Supply (400 V) System switchboards and/or motor control centers. The 230 volt power shall be fed to panelboards which contain circuit breakers for distribution of the 230 volt single-phase power. The panelboards shall also provide branch circuit protection and a means of disconnect for the branch circuit loads through manually operated thermal magnetic circuit breakers. The AC Power Supply (230 V) System shall accommodate plant startup and be designed to meet 100 percent of the required continuous plant loads and provide 10 percent spare capacity for use during commercial operation. Low Voltage AC panelboards color shall be grey. 01630.2.2 AC POWER SUPPLY (400 V) (APC) Function The AC Power Supply (400 V) System provides 400 volt three-phase power for the 400 volt auxiliary electric system and electric loads. The AC Power Supply System (400V) shall include overcurrent, phase, ground fault protection, and fault recorders. Major Components The AC Power Supply (400 V) System will consist of the following major components: 6600 volt to 400 volt switchgear transformers with solidly grounded secondary. 400 volt, three-phase, four-wire metal enclosed switchgear with metal enclosed, withdrawable air circuit breakers. 400 volt, three-phase, four-wire motor control centers (MCC). 400 volt, three-phase, four-wire panelboards. Maintenance Power System HVAC Power and Control Panels General Description The AC Power Supply System is shown on One-Line Diagram 144807-CAPC-E1002. The switchgear transformers shall receive power at 6600 volt, three-phase from the AC Power Supply (6600V) System and transform it to 400 volt, three-phase power. The transformer 6600 volt primary shall be connected delta. The 400 volt secondary of the switchgear transformers shall be connected solidly grounded wye. Each indoor switchgear transformer shall be a dry type, resin encapsulated transformer furnished with AA cooling rating, and an 80C temperature rise. Each outdoor switchgear transformer shall be an oil-filled transformer furnished with an ONAN cooling rating and a 65C temperature rise. Oil filled transformers shall be provided with containment sized to hold 110% of the oil reservoir capacity. All switchgear transformers shall be provided with a no load tap changer. Motor loads greater than or equal to 0.18kW and less than or equal to 160kW shall be fed from the 400 volt switchboards and/or MCCs. All other loads shall receive power from 230 V panelboards. Three 400V switchgears with incoming breakers shall be provided in the turbine building, one for each combustion turbine/HRSG. Each switchgear shall receive power from the 6600V system via an associated 400V switchgear transformer and transform the power to 400V for distribution to 400V loads Source: 01630, 2005 System Descriptions Page 2 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 and 400V motor control centers. The 400V switchgear shall be located indoors. Their respective 6600V to 400V transformers shall be dry-type, resin encapsulated, and located indoors. Each switchgear shall have tie breaker to an adjacent Unit’s 400V switchgear to allow operation with its incoming transformer out of service. Therefore, each transformer shall be sized for the entire load of its associated switchgear plus the load of the adjacent unit’s 400V switchgear it is tied to. The transformers shall be throatconnected to their associated low voltage switchgear lineups. One 400V switchgear with two incomer breakers shall be provided at the circulating water intake. The switchgear shall receive power from the 6600V switchgear via a 400V switchgear transformer and transform the power to 400V for distribution to 400V loads and 400V motor control centers. The 400V switchgear shall be located indoors. Their respective 6600V to 400V transformers shall be oil immersed and located indoors. Each transformer shall be sized for the entire load of the associated switchgear. The transformers shall be connected by either cable, bus duct, or cable bus to their associated low voltage switchgear lineups. One 400V switchgear with two incomer breakers shall be provided at the water treatment building area. The switchgear shall receive power from the 6600V switchgear via a 400V switchgear transformer and transform the power to 400V for distribution to 400V loads and 400V motor control centers. The 400V switchgear shall be located indoors. Their respective 6600V to 400V transformers shall be dry-type and located indoors. Each transformer shall be sized for the entire load of the associated switchgear. The transformers shall be throat-connected to their associated low voltage switchgear lineups. Motor Control Centers shall be provided as needed to distribute power to cyclic 400V loads, 400V intermediate loads, and small 400V loads that require motor starters or are essential to plant operation. Individual 400V MCCs shall be provided with spare starters and spare breakers as design permits. Motor control centers in general shall be located indoors. It is anticipated that the following MCCs will be required. Exact quantity and locations to be determined during detail design. Combustion Turbine 1 MCC 1 &2 (located in CT Supplier Control/Electrical Enclosure) Combustion Turbine 2 MCC 1&2 (located in CT Supplier Control/Electrical Enclosure) Combustion Turbine 3 MCC 1&2 (located in CT Supplier Control/Electrical Enclosure) Steam Turbine MCC 1&2 Turbine Building Services MCC 1&2 Control Building Switchboard 1 & 2 HRSG 1 MCC 1 HRSG 2 MCC 1 HRSG 3 MCC 1 Water Treatment MCC 1 & 2 Hypochlorite/Hydrogen Generation MCC Admin/Maintenance/Warehouse Shop MCC Intake MCC 1 & 2 Desalination MCC 1 & 2 MCCs shall receive power from breakers in the 400V switchgear. Each MCC shall contain combination full voltage type “2” co-ordination motor starters and molded case circuit breakers. 400V Switchgear breakers to MCCs shall be electrically operated. All motor starters up to an including 55kW shall be fully withdrawable. The internal control voltage for the LV switchgear system shall be 220V dc supplied from two independent station batteries (APH System) for controls and a 230V ac power supply for breaker spring charge. Source: 01630, 2005 System Descriptions Page 3 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Protection of LV switchgear shall be in accordance with Generation Standard GGS0803, Generation MV and LV Protection Philosophy for Power Stations. Protection equipment shall be microprocessor based and shall conform to ESKASAA04 – Eskom Standard for Electronic Protection and Fault Monitoring Equipment for Power Systems. Switchgear load analysis, load study, fault analysis, and fault study shall be submitted to the Employer by the Contractor to ensure the switchgear is properly sized and protected. The interface to the LV switchgear to the station control system shall be with a redundant control system communication bus network, providing the control and monitoring facilities to the operators in the control room. MCCs and 400V switchgear finish color shall be grey. The AC Power Supply (400V) System shall be designed to feed the low voltage loads. Each Switchgear transformer and associated low voltage switchgear line-up shall be sized to serve its maximum coincidental operation load. Each single-ended lineup 400V Switchgear shall be provided with one equipped space for the installation of an additional circuit breaker in the future. Each 400V MCC shall be shipped from the manufacturer with spare starters, breakers, or spaces to allow for future growth. The maintenance power system shall consist of circuit breakers that provide ground fault and overcurrent protection, cables, raceways and switched socket outlets to provide power to maintenance equipment rated above 16 amps. The switched socket outlets shall be of the 63 amp 5 pin type. 01630.2.3 AC POWER SUPPLY (6600 V) (APD) Function The AC Power Supply (6600 V) System provides a high resistance grounded power source to plant auxiliaries requiring 6600 volt power. The AC Power Supply System (6600V) shall include overcurrent, phase, ground fault protection, and fault recorders. Major Components The AC Power Supply (6600 V) System will consist of the following major components: Two two-winding delta primary, resistance grounded wye secondary 6.6 kV unit auxiliary transformers (UAT). The unit auxiliary transformers shall each be provided with an off load tap changer. One neutral grounding resistor on the secondary of each unit auxiliary transformer. Two Turbine Building 6600 volt metal-clad, internal arc proof certified Switchgears with main breakers, feeder breakers and tie breakers. 6600 volt cable bus or non-segregated phase bus duct connection from each unit auxiliary transformer to its respective switchgear lineup. Remotely fed 6600V metal-clad, internal arc proof certified Switchgears with main breakers, feeder breakers and tie breaker. Transformer rail removal system (furnish only – shared with the generator step-up transformers). General Description The AC Power Supply System is shown on the One-Line Diagram 144807-CAPF-E1001. The AC Power Supply (6600 V) System shall receive three-phase power via the unit auxiliary transformers from the generator bus via an isolated phase bus duct tap to each unit auxiliary transformer. Source: 01630, 2005 System Descriptions Page 4 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The unit auxiliary transformer shall transform the high voltage to 6600 volts and deliver it to the 6600 volt switchgear. The secondary winding (6600 V) of the transformer shall be high resistance grounded to limit the maximum line to ground fault current. The unit auxiliary transformer shall be furnished with an ODAF cooling rating. The transformer shall be oil filled. An oil containment basin shall be provided. Drainage shall be routed to an oil/water separator. Firewalls shall be provided if required by NFPA 850 The impedance and primary voltage rating of the unit auxiliary transformer shall be selected to enable motor starting while limiting fault currents to the design levels. Each switchgear lineup connected to the unit auxiliary transformers shall consist of one main circuit breaker, two tie circuit breaker, and motor, transformer, and subfed switchgear feeder circuit breakers. It shall distribute power to large motors and 400V switchgear transformers, combustion turbine starting equipment (LCI), and feeds to the black start generation equipment (APK), and intake area switchgear. All medium voltage switchgear shall be of the metal clad internal arc proof certified type in accordance with IEC 56, 62271-100, 62271-200, and GGSS 1201 Rev. 1, Appendices AA – Criteria 1-6. Arc detection for selective tripping shall be provided as part of the protection scheme. The switchgear arc venting system shall be coordinated with the building systems to provide safe outlet of the arc gases out of the switchgear building. Each circuit shall be provided with a power cable earthing switch. Additionally, the switchgear bus shall be provided with earthing switch. Mechanical interlocks shall be provided to prevent closing an earth switch on a live power cable or bus bar. The 6.6kV Switchgear shall be provided with spares and equipped spaces as noted on the one lines. Medium voltage switchgear shall utilize multifunction microprocessor based electronic protective relays for motor and feeder protection. Protection shall be in accordance with Employer Standard GGS0803 “Generation MV and LV Protection Philosophy for Power Stations”. Protection equipment shall be in accordance with Eskom Standard for Electronic Protection and Fault Monitoring ESKASAA04. Switchgear load analysis, load study, fault analysis, and fault study shall be submitted to the Employer by the Contractor to ensure the switchgear is properly sized and protected. The 6.6kV Switchgears powered from the unit auxiliary transformers shall be connected to the transformer via cable bus or non-segregated phase bus duct. 6600 volt equipment interrupting rating shall be sufficient to interrupt the maximum fault current available. The internal control voltage and breaker spring charge for the MV switchgear shall be 220V supplied from the station batteries (APH System). The interface to the Medium Voltage switchgear to the station control system shall be with a redundant control system communication bus network, providing the control and monitoring facilities to the operators in the control room. Switchgear finish color shall be cream (RAL 2000) The AC Power Supply (6600 V) System shall be designed to supply power for the maximum coincidental load requirements. The unit auxiliary transformers maximum rating shall be sized for full load operation with the other unit auxiliary transformer out of service and the tie breaker closed. Source: 01630, 2005 System Descriptions Page 5 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 A transformer rail removal system, complete with permanent foundations, shall be furnished to allow removal of any unit auxiliary transformer from its foundation and transport it to the location of any other unit auxiliary transformer. The rail removal system shall be designed to move the transformer in a fully assembled state, without dismantling the transformer or draining the oil. The rail system shall be stored when not in use. The Contractor shall design and install permanent foundations for support of the rail system. The Contractor’s design shall not preclude moving transformers between the Coega 3x1 block and the future Coega 3x1 block. 01630.2.4 DC POWER SUPPLY (APH) Function The DC Power Supply System provides a reliable source of power for critical control and power functions during normal and emergency operating conditions. Batteries shall be provided to provide power to the Uninterruptible Power Supply (UPS) System, switchgear control power, control room lighting (backup supply) and other critical loads. Other DC systems to be provided include the Combustion Turbine Generator dc power supply system (one per Combustion Turbine, located in its associated electrical/control package). Major Components The DC Power Supply System will consist of the following major components: Two 220 volt dc lead acid station batteries. Two full-capacity redundant solid-state chargers per battery. Main DC distribution panel (per battery). General Description The DC Power Supply System shall consist of a station battery system. The system shall utilize flooded type batteries. These batteries provide DC power to critical BOP loads and control power for the auxiliary electrical system equipment. Each battery shall be connected to a main distribution panel and continuously charged by two fully redundant battery chargers. Under normal conditions, the battery chargers supply dc power to the dc loads. The battery chargers receive 400 volt ac power from the AC Power Supply (400V) System. The chargers shall continuously float-charge the battery while supplying power to the dc loads. Under abnormal or emergency conditions when 400 volt ac power is not available, the battery supplies dc power to the dc loads. Recharging of discharged batteries occurs whenever 400 volt ac power becomes available. The rate of charge is dependent upon the characteristics of the battery, battery chargers, and the connected dc load during charging. Each station battery charger shall be sized to provide the normal continuous dc power requirements while recharging the battery in less than 12 hours (24 hours if one charger is out of service). The station battery shall be sized to safely shut down the power plant upon loss of all ac power, and supply essential dc loads for a minimum of 240 minutes, or as required by the Steam Turbine equipment, whichever is longer. The battery shall be located in a space conditioned area so that suitable temperatures can be maintained, thus helping to ensure long battery life. The battery room shall be a fire rated room and shall be provided with ventilation to prevent hydrogen buildup. DC distribution panel finish color shall be red. Source: 01630, 2005 System Descriptions Page 6 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The station battery system shall be sized in accordance with IEEE 485 to serve the loads assigned to that battery. Battery rating shall account for aging of the cells and temperature differences. UPS System Panelboards shall be provided with at least 10% spare breakers for future use. 01630.2.5 UNINTERRUPTIBLE POWER SUPPLY (API) Function The Uninterruptible Power Supply (UPS) System provides 230 volt ac, single-phase, 50 hertz power to essential instrumentation and equipment loads that require non-interruptible ac power, including the DCS system, switchgear control power supplies, building egress lighting, and control room normal lighting. Major Components The Uninterruptible Power Supply shall consist of the following major components: One full-capacity, 230 volt ac, single-phase, 50 hertz inverter. One solid-state static transfer switch. One manual bypass switch. Essential service ac panelboards for distribution of 230 volt ac essential service power. One alternate source transformer and voltage regulator. General Description The normal source of power for the UPS shall be from the DC Power Supply System. The full-capacity inverter shall be connected to a 230 volt ac panelboard through a static transfer switch and a manual bypass switch. The inverter shall be in a free-standing, floor-mounted enclosure and use solid-state silicon controlled rectifier switching assemblies and other devices to invert dc to ac power. Protecting, monitoring, regulating, and phasing devices shall be included with the inverter. During normal operation, the inverter shall supply the essential ac loads. A solid-state switch connected to the output of the inverter shall continuously monitor both the inverter output and the alternate ac source. Upon loss of the inverter output, the static switch shall automatically transfer essential ac loads without interruption from the inverter output to the alternate source. The power supply for the alternate source transformer and regulator shall be the AC Power Supply (400 V) System. During normal operation, the inverter-static switch-power panel combinations shall be dedicated to furnishing the power required by the UPS. The AC Power Supply (400 V) System shall be utilized as a backup to the inverter systems. A manual bypass switch shall be provided to enable isolation of the inverter-static switch from service for testing and maintenance without interruption to the UPS System loads. UPS System loads shall be fed from the UPS ac panelboards through fast tripping circuit breakers or fuses. The inverter shall be maintained in synchronism with the alternate ac power source. AC distribution panel finish color shall be grey. The UPS System shall be designed to meet 110 percent of the maximum coincidental operating load. UPS System Panelboards shall be provided with at least 10% spare breakers for future use. 01630.2.6 EMERGENCY POWER- BLACK START (6600 V) (APK) Source: 01630, 2005 System Descriptions Page 7 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Function Black Start System shall provide three-phase power directly to the AC Power Supply (6600 V) System, and shall have the capability of starting one of the combustion turbines from shutdown, while utilizing no external power sources. Source: 01630, 2005 System Descriptions Page 8 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Major Components The Black Start System shall include the following major components: Multiple diesel engine driven generators rated 6600 volt nominal, three-phase, 50Hz Individual unit and overall digital control panels for automatic starting, stopping, synchronizing, load sharing, and parallel operation of generator units locally and remotely Electrically operated circuit breakers with generator and system protection for automatic synchronizing of units during normal operation and testing Fuel storage and automatic fuel feed system Auxiliary equipment, instruments, and starting system required for start-up and operation Interconnecting piping and wiring General Description The Emergency Power/Blackstart System is shown on One-Line Diagram 144807-CAPF-E1001. In the event that power is not available from the system grid, Black Start System shall have the ability to start, synchronize, and transfer power to the medium voltage switchgear automatically in order to provide the required power to the auxiliary power system needed to start one of the combustion turbine generators, from a shutdown state. Multiple diesel engine driven generators shall be utilized for this purpose, in an N+1 configuration. The system will be designed for operation of the critical loads for the duration necessary to allow the combustion turbine generator to reach full power output, without the need for refueling. Each unit shall be mounted on its own common steel base. The fuel system may be incorporated into the steel base, or supplied as a separate system. Units shall be complete with transformers, motor starters, and electrical control equipment required for operation. Transformers shall not be located in the same structure as the diesel generator. System design shall not preclude connection to the second 3x1 Coega CCGT block. Automatic and manual start-up, control, and synchronizing shall be possible locally or remotely. Local control shall be from an overall local control panel. Each unit shall have its own local control panel connected to the overall panel. Failure of the overall control panel shall not shutdown the unit control panels. Interconnecting piping and wiring for equipment mounted on the steel base shall be factory installed. During black start operation, the plant AC Power Supply (6600V) System shall receive power from the generators. Configuration of the medium voltage switchgear, and low voltage switchgear breakers to utilize the black start generator power shall not require manual opening and closing of main or tie feeder breakers. Dedicated metering and protection, CTs, and VTs shall be used to allow interconnection of buses to a dead bus or synchronization to a live bus. The Black Start System shall be capable of completing a fully functional test of equipment and auxiliary systems while the plant is operating normally. Each ground conductor from the generator shall be routed through an electrically operated contactor. The contactor shall be normally closed and open when the generator is starting up and shall remain open until the generator is synchronized to the system and then automatically/manually close. All medium voltage switchgear shall be of the metal clad internal arc proof certified type in accordance with IEC 56, 62271-100, and 62271-200, Appendices AA – Criteria 1-6. Arc detection for selective tripping shall be provided as part of the protection scheme. The switchgear arc venting system shall be coordinated with the building systems to provide safe outlet of the arc gases out of the switchgear building. Source: 01630, 2005 System Descriptions Page 9 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Each circuit shall be provided with a power cable earthing switch. Additionally, the switchgear bus shall be provided with earthing switch. Mechanical interlocks shall be provided to prevent closing an earth switch on a live power cable or bus bar. The 6.6kV Switchgear shall be provided with spares and equipped spaces as noted on the one lines. Two spare breakers shall be provided for future connection of the blackstart/emergency generation system to the second 3x1 block. Medium voltage switchgear shall utilize multifunction microprocessor based electronic protective relays for motor and feeder protection. Protection shall be in accordance with Employer Standard GGS0803 “Generation MV and LV Protection Philosophy for Power Stations”. Protection equipment shall be in accordance with Eskom Standard for Electronic Protection and Fault Monitoring ESKASAA04. 6600 volt equipment interrupting rating shall be sufficient to interrupt the maximum fault current available. The internal control voltage and breaker spring charge for the MV switchgear shall be 220V dc for control, supplied from the station batteries (APH System). Interface to the station control system shall be with a redundant control system communication bus network, providing the control and monitoring facilities to the operators in the control room. Switchgear finish color shall be cream (RAL 2000). 01630.2.7 PLANT INTERCOMMUNICATIONS PAGING (CMA) Function The Plant Intercommunications Paging System shall provide the facility personnel with a plant wide paging and alarm system. Major Components The Plant Intercommunication Paging System shall consist of the following major components: Handsets Amplifiers. Speakers and supports Associated raceway and wiring. General Description The Plant Intercommunications Paging System shall be designed to provide a reliable, convenient method of voice paging and alarm tones for facility personnel. It shall accommodate a minimum of five (5) party lines. Handset/Speaker stations shall be located throughout the plant facility. Installation locations include: the STG Electrical/Control enclosure, the Packaged Electrical Electronic Control Compartment (PEECC) for each Combustion Turbine, each LCI Compartment, Turbine Building, Heat Recovery Steam Generator area, Water Treatment Building, Diesel Storage area, Circulating Water Intake structure, Hypochlorite Generfation Building, Hydrogen Generation Building, Control Building, and Administration Building. Classified hazardous locations shall be provided with equipment suitable for the environment. 01630.2.8 COMMERCIAL TELEPHONE (CMD) Source: 01630, 2005 System Descriptions Page 10 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Function The Commercial Telephone System provides station personnel with reliable and convenient onsite and offsite voice communication. Major Components The Commercial Telephone System shall consist of the following major components: Raceway and wiring shall be provided to the Control Building, Administration Building, Maintenance Shop, and the Warehouse for the telephone system. Main Distribution Frame and PABX located in the communications room in the plant Admin building. Intermediate Distribution Frame (IDF) enclosures shall be installed in the Control Building, Maintenance Shop, and the Warehouse Telephone handsets and stations. General Description The telephone system equipment will be provided by the Contractor. Wiring for the telephone outlets shall be unshielded twisted pair Category 5 minimum Each building and enclosure noted above shall include an Intermediate Distribution Frame (IDF) enclosure that shall be provided with suitable surge protection fuses. The Commercial Telephone System shall be designed to provide a reliable, convenient method of onsite and offsite voice communications for facility personnel. 01630.2.9 DISTRIBUTED CONTROL SYSTEM (COA) Function The Distributed Control System (DCS) shall provide modulating control, digital control, monitoring/indication, alarming, logging, data archiving, and indicating functions for the plant equipment. Distributed I/O / process control cabinets (DCS cabinets) shall be interconnected via a redundant plant data highway. The DCS shall provide the following functions: Monitoring of plant equipment and process parameters and display of this information to the plant operators in meaningful formats. Overall control of plant output in a coordinated response to the load demands. Control and monitoring of all plant equipment from the plant control room. Operator control and monitoring interface through screen-based operator work stations (OWS). Standard displays include process graphics (simplified P&ID), trend, and permissives (active text). Control functions are implemented using pop-up stations on the process graphic displays. Visual/audible alarms for abnormal events based on field signals or software generated signals (including out-of-limit parameters) from the systems, processes, and equipment. Sequence-of-events (SOE) recording with 1 millisecond resolution to assist with diagnostic evaluation of plant upsets and trips. Historian for plant operating data archive and generation of operating and historical reports. Built-in hardware and software diagnostics. Engineering work station (EWS) for logic, tuning, and graphic additions, modifications, and documentation. Shift supervisor monitoring through a shift supervisor work station. Source: 01630, 2005 System Descriptions Page 11 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Performance calculations. Plant asset management system. Remote diagnostic interface. Remote web server interface. Dual GPS time synchronization. Major Components The Distributed Control System shall include, but not be limited to the equipment described below: System equipment cabinets containing redundant processing units, redundant data highway communications equipment, redundant datalink hardware, and redundant power supplies. Processor memory utilization and duty cycle shall be 70 percent or less. I/O cabinets (or enclosures) containing the system input/output equipment and wiring terminations for process sensing and equipment control interface. DCS terminations for process sensing and equipment control interface. SOE input cards with one (1) millisecond resolution for critical inputs. Six (6) operator work stations, each with dual screen, keyboard and mouse to provide the normal interface between the operator and the plant processes and equipment being controlled or monitored. Alarm indications shall also be displayed on these screens. One (1) shift supervisor work station (a fully featured and functioning operator work station with the exception that all control functions are disabled). Three (3) printers: - One (1) color printer - Two (2) laser printers One (1) engineer/operator work station (EWS) with dual screen, keyboard, and mouse to provide the interface between the plant engineer and the plant processes and equipment for control system tuning, and system program and screen graphic display modification and development. Historian with long-term removable storage media and data storage, retrieval, and reporting software. Standard redundant data highway to provide communication between the various components of the DCS. Fully integrated control of all balance-of-plant functions and combustion turbine controls Redundant datalink communication interfaces are provided between the DCS and the following listed equipment (time critical control data and trips for these interfaces shall be hardwired): - Steam turbine control system - Power metering - Low and medium voltage switchgear - Sodium hypochlorite generation system - Hydrogen generation system - Desalination system - Demineralizer system - Water treatment systems Hardwired interfaces are provided between the DCS and the following listed equipment: - Air compressor panel - Automatic generation control (AGC) remote terminal unit (RTU) - Each CEMS Operators' control console containing the DCS operator work stations, CEMS work station, plant communications and security hardware, HRSG drum level indicators, and hardwired emergency trip push buttons to allow tripping of major equipment independently of the DCS. General Description Source: 01630, 2005 System Descriptions Page 12 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The DCS shall be a microprocessor-based system composed of functionally distributed (modular) processors, input/output modules, and operator interface devices, all connected via a redundant communications network. Screen-based work stations shall be provided for operation of the plant control systems as well as providing alarm and data acquisition functions. All DCS displays and operator interface functions shall be available on all screens. The work stations shall include keyboards and mouse for entering operatorinitiated control commands. Hardwired devices such as pushbuttons, switches and indicators shall be provided as required by codes and regulations and for emergency shutdown. The DCS shall include an overall minimum of 20 percent spare I/O capacity and equipment after field commissioning is complete. Spare capacity shall be included for functional control for each processing unit. Spare equipment shall include I/O cabinet terminal points and active I/O points. The DCS design shall incorporate functional redundancy to ensure maximum reliability during system operation. Redundant processing units shall be provided as required to ensure that a single point of failure shall not result in loss of generation capacity. Where redundant processors are provided, one processor of the pair shall be active; the other processor shall operate in a hot standby mode and shall be continuously updated to be aware of the status of the active processor. In the event of a failure in the active processor, all functions shall instantly be assumed by the standby processor. The transfer to the standby processor shall be alarmed. Redundant power supplies shall be provided for all control components in the system. Peripheral devices such as printers shall be powered from the UPS. The DCS shall be equipped with a diagnostic package that includes both hardware and software to detect system malfunction and equipment failure. The occurrence of any malfunction or equipment failure shall be alarmed instantly. The diagnostic package shall be capable of pinpointing the defective component down to the card level. The DCS shall be designed to react in a predictable manner to certain failure: Upon system logic failure, as detected by system diagnostics, a controller shall transfer to its backup. If the backup is unavailable, the controller outputs shall fail to a predictable state and shall enable any manual shutdown facilities which are appropriate to provide orderly shutdown of equipment. Upon system logic power supply failure, the controller shall transfer to its backup. If the backup is unavailable, the system outputs shall fail to a de-energized state. Upon power failure to an active or running controlled device or equipment, the system shall react in a predetermined manner, either to command a restart of the equipment upon power resumption, or to cycle the logic to a status requiring equipment shutdown. The response time of the system shall be sufficient to maintain control over the plant processes under all system operating conditions including extreme plant upset conditions with all points in alarm. The response time is the total elapsed time for transmission of data through the system communication path. This time shall include all communication time from processor to processor, I/O scans, nodes, gateways, screens, keyboards, and associated equipment internal to the system. Source: 01630, 2005 System Descriptions Page 13 of 65 ESKOM COEGA CCGT 144807.71.0201 01630.2.10 WORKS INFORMATION EMPLOYER REVIEW 20October06 GROUNDING (EEB) Function The Grounding System provides an adequate path to permit the dissipation of ground fault currents, lightning induced potentials, and switching surges for protection of plant personnel and electrical equipment. Major Components The Grounding System shall consist of the following major components: Ground grid and ground loop conductors with stingers for attachment to metallic structures and equipment. Grounding rods. Grounding connections. General Description A ground grid system consisting of bare stranded soft drawn copper conductors connected to copper-clad ground rods shall be installed for the facility to provide a low resistance path to ground for fault currents, lightning strikes, and other electrical current surges. The ground grid shall be buried beneath and around all major plant buildings and structures. The grid shall be arranged in a rectangular pattern with spacing between conductors determined by safe step potentials. The number, location, and depth of the ground rods shall be determined by the soil resistivity and subsurface structural properties of the plant site. All below grade connections between grounding conductors or between ground conductors and ground rods shall be made using an exothermal welding process which fuses the two members together. Two bare ground conductors shall be buried along the entire length of all below grade duct banks. All onsite areas shall be connected to the plant ground grid with a minimum of two connections. Bare copper ground "stingers" shall be connected to the grid and extended through the building floor slabs to electrically connect the ground grid to building steel, support steel, large motors, electrical switchgear, motor control centers, large power transformers, generators, and other equipment, including Instrumentation junction boxes.. A copper grounding conductor shall be installed the entire length of power level cable trays, racks, trenches, and wireways included in the Raceway System. Ground conductor for cable trays shall be bolted to each tray section. The conductor shall be connected at various locations to the ground grid or ground loop. The Grounding System shall be designed with sufficient capacity to dissipate the ground current under the most severe conditions and to maintain safe voltage gradients. A low noise, isolated ground system shall be provided for grounding of sensitive electronic equipment according to the manufacturer's instructions. This system shall consist of an insulated ground conductor connected to the plant ground grid at one point. All signal grounds and other low level ground connections shall be made to this dedicated copper. Other special grounding required by equipment manufacturers shall be provided as necessary. A lightning protection system shall be installed where required for plant structures. The structures requiring lightning protection shall be determined during detailed design. The design basis for the Grounding System shall be the, , NRS 042, IEC 6100-5-2, and IEC 60204-1. and the applicable industry standards and practices. Minimum conductor sizes for earthing shall be as Source: 01630, 2005 System Descriptions Page 14 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 specified in Table 54F and paragraph 543.1.2 of IEC 364-5-54. Industry standards for safe step-andtouch potentials shall be paramount in design considerations. The design basis for the Lightning Protection System shall be in accordance with NRS 042 and IEC 61000-5-2 Equipment shall be designed for EMC immunity and emissions properties compatible with the expected environment in the plant. Where applicable, IEC product family standards shall be used instead of generic standards. As a minimum, equipment shall be tested to pass the immunity requirements of IEC 61000-4 and ENV 50204 Standards. Equipment shall also meet CISPR 11 (EN-55011) and CISPR 22 (EN-55022) requirements for EMC emissions. 01630.2.11 RACEWAY (EEC) Function The Raceway System provides support and protection for electrical power and control circuits between various pieces of equipment, devices, and cabinets. Major Components The Raceway System shall consist of the following major components: Cable tray. Cable trenches and tunnels. Wireway. Duct bank. Electrical manholes. Cable drawpits/handholes. Junction boxes and pull boxes. General Description A general description of the various components within the Raceway System is included below: Cable Tray/Cable Racks--The cable tray/cable racks shall provide support to electrical cable which is routed throughout the plant either directly to equipment or to areas of concentrated electrical loads. Conduits--Conduits shall only be used to extend unarmoured cables from cable trays, band wireways to equipment or cabinets, and for circuits between equipment and cabinets within buildings. (All cables between buildings/enclosures should be armored.) Wireways--Wireways shall provide an advantageous wiring transition between power panels or other groupings of equipment. Wireways shall be oiltight, metallic wiring enclosures with hinged covers. Direct Buried Conduit—For remote areas in the plant where a single power supply is required remote from a cable tunnel or trench, cables can be installed in direct buried steel conduit or concrete encased PVC conduit underground. Electrical Manholes--Reinforced concrete manholes shall be provided, where required, so that cable may be installed without exceeding allowable pulling tensions and cable sidewall pressures. Junction Boxes/Pull Boxes--Junction boxes (terminal boxes) and pull boxes shall provide access to the conduit system, serve as a transition from one type of raceway to another, and serve as circuit and raceway collection points. Source: 01630, 2005 System Descriptions Page 15 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Components of the Raceway System shall separate different types of cables to avoid electromagnetic interference as required by equipment manufacturers. Maintain a separation of at least 600mm between control cable and power cable rated up to 6.6kV, and 100mm between control cable and power cable rated 11 kV. All power cabling running between buildings shall be either to be run in suitable cable racks or trays above ground, or in suitable cable tunnels. Direct buried cables are not acceptable. All piping runs outside of main buildings shall be to be run in pipe tunnels, pipe trenches, or supported on suitable plinths or racks above ground. Large numbers of electrical and control cables are routed via tunnels and tenches with cable rack or cable trays. There must be a separate cable rack or cable tray for the control cable (usually the top rack). Where only a few cables are run for longer distances, buried conduit can be used. Control sleeves should be at least 600mm away from LV and MV sleeves up to 6.6kV and 1000mm away for 11kV". The design basis for the Raceway System shall be the Electrical Engineering Design Criteria section and the applicable industry standards and practices. For low voltage cables, BS7671 must be followed. Due to coastal location, materials resistant to corrosion should be selected for cable trays/cable racks. 01630.2.12 STEAM TURBINE GENERATOR BUS DUCT (GTA) Function The Steam Turbine Generator Bus Duct System provides a path for transfer of power from the steam turbine generator terminal equipment to the generator transformer low voltage terminals and the static excitation system transformer. Major Components The Steam Turbine Generator Bus Duct System will consist of the following major components: Aluminum welded type isolated phase bus duct including straight pieces, fire wall penetrations, bends, and phase transpositions. Bus duct supports and hangers. Tap bus to Static Excitation System Transformer Connections to the Generator and Generator Step-Up Transformer and Generator surge protection/potential transformer equipment. System Description Isolated phase bus will be used for the steam turbine generator bus duct. The isolated phase bus duct will consist of individual aluminum rigidly supported conductors, housed in a 3-phase individual aluminum enclosure. The bus will be installed with rigid, nontracking, fire-resistant, porcelain, and nonhygroscopic insulating supports capable of withstanding the mechanical forces of short-circuit currents. The bus will be self-cooled, and provided with the following features: Online temperature monitoring system that monitors temperature for all bolted connections. The system shall include a local and remote alarm of bolted connection temperature. Source: 01630, 2005 System Descriptions Page 16 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Bus Duct air pressurization system. The air pressurization system shall prevent moisture and dust ingress. The system shall monitor air consumption as a means of detecting sealing system. Air tight inspection doors are provided for access to all bolted connections and fitted close to all sharp bends in the busbar system to provide adequate access for maintenance requirements. The Steam Turbine Generator Bus Duct System will be rated to continuously carry, as a minimum, 115% of the Steam Turbine Generator maximum continuous current rating, and will be braced for the fault current available. Temperature rise at the site altitude shall be limited as per SANS 60694:2003. The bus duct insulation system shall maintain minimum insulation levels as per SANS 60694:2003 when filled with atmospheric air at the site specific environmental conditions. The Bus Duct System shall comply with the provisions of BS 159. 01630.2.13 COMBUSTION TURBINE GENERATOR CIRCUIT BREAKER (GTO) Function The Generator Circuit Breakers allow the generators to be synchronized to or disconnected from the system. The Combustion Turbine Generator circuit breaker shall allow disconnection of the generator from the system without power interruption to the Unit Auxiliary Transformer. Major Components The Generator Circuit Breaker consists of the following major components: Indoor enclosure. Self-cooled SF6 circuit breaker. Non load break isolating switch. Grounding switch – Generator side Grounding switch – Transformer side Control cabinet. PT’s and CT’s General Description Generator Circuit Breakers shall be installed on two of the three combustion turbine generators, and they shall be installed between the generator step-up transformer and the generator to provide a means for synchronization or disconnection of the generator and the system, while maintaining power supply to the Unit Auxiliary Transformer. The Generator Circuit Breakers shall be capable of full-load and fault current interruption. The Generator Breakers shall provide motorized no-load break isolating switches on the transformer side of the breaker. Grounding switches shall be provided for the generator transformer side and the generator side of the breaker. Grounding switches shall be capable of carrying the through fault current for the appropriate Source: 01630, 2005 System Descriptions Page 17 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 times with the resultant temperature rises limited. Grounding switches shall be suitable for the short circuit current curve of the generator. The design of the Generator Circuit Breaker System shall be rated to continuously carry 120% of the Combustion Turbine Generator maximum continuous current rating, and shall be braced for the maximum fault current available. The Generator Circuit breaker shall comply with the provisions of IEC 62271-100. 01630.2.14 GENERATOR STEP-UP TRANSFORMER (GTU) Function The Generator Step-up Transformer provides the means to step up the generator terminal voltage to the substation voltage for power transmission. Major Components The Generator Transformer System shall consist of the following major components: One, three phase, two winding steam turbine generator step-up transformer. Three, three phase, two winding combustion turbine generator step-up transformers. Transformer rail system (furnish only – shared with the unit auxiliary transformer). General Description The generator step-up transformer shall transform electrical power received at generator voltage at its low voltage terminals through the Steam Turbine Generator Bus Duct System and the Combustion Turbine Generator Bus Duct System to the nominal transmission voltage of 400 kV. Each generator step-up transformer shall be three phase, two winding oil-filled transformer furnished with ODAF cooling rating and a 65C temperature rise. The transformer high voltage winding shall be connected grounded wye. The transformer low voltage winding shall be delta connected. The transformer shall be provided with an on-load tap changer. The transformer shall have sufficient capacity to carry the maximum power output of each respective turbine across the site ambient temperature range. Surge arresters shall be provided at the high voltage bushing to protect the transformer from surges on the high voltage system resulting from lightning strikes or other system disturbances. Protective relays shall detect and provide protection from internal and external faults, overheating, and overvoltage conditions. The transformer shall be provided with current transformers (CTs) as required. Each transformer shall be set on a concrete pad. Oil containment basin shall be provided. Drainage shall be routed to an oil/water separator. Firewalls shall be provided if required by NFPA 850. The Generator Transformer System shall be designed to carry 10% greater than its respective generator rated MVA. The final selection of the electrical impedance for the Generator Transformer shall be coordinated with the fault current ratings of the 400kV system, and the requirements of the South African Grid Code. A transformer rail removal system, complete with permanent foundations, shall be furnished to allow removal of any generator step-up transformer from its foundation and transport it to the location of any other generator step up transformer. The rail removal system shall be designed to move the transformer in a fully assembled state, without dismantling the transformer or draining the oil. The rail system shall be Source: 01630, 2005 System Descriptions Page 18 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 stored when not in use. The Contractor shall design and install permanent foundations for support of the rail system. The Contractor’s design shall not preclude moving transformers between the Coega 3x1 block and the future Coega 3x1 block. 01630.2.15 COMBUSTION TURBINE GENERATOR BUS DUCT (GTK) Function The Combustion Turbine Generator Bus Duct Systems provide a path for transfer of power from the combustion turbine generator terminals to the Generator Circuit Breaker, the Generator Step-up Transformer low voltage terminals, the Unit Auxiliary Transformer, and the Static Excitation System Transformer Major Components The Combustion Turbine Generator Bus Duct Systems shall consist of the following major components: Aluminum welded type isolated phase bus duct including straight pieces, bends, phase transpositions, and phase transpositions for each combustion turbine. Bus duct supports and hangers. Tap bus to Unit Auxiliary Transformer and Static Excitation System Transformer.. Connections to the Generator, Generator Circuit Breaker (where used), Static Excitation System Transformer, Unit Auxiliary Transformer, and Generator Step-Up Transformer General Description Isolated phase bus shall be used for the Combustion Turbine generator bus duct. The isolated phase bus duct shall consist of individual aluminum rigidly supported conductors, housed in a three-phase individual aluminum enclosure. The bus shall be installed with rigid, nontracking, fireresistant, porcelain or epoxy resin, and nonhygroscopic insulating supports capable of withstanding the mechanical forces of short-circuit currents. The bus will be self-cooled, and provided with the following features: Online temperature monitoring system that monitors temperature for all bolted connections. The system shall include a local and remote alarm of bolted connection temperature. Bus Duct air pressurization system. The air pressurization system shall prevent moisture and dust ingress. The system shall monitor air consumption as a means of detecting sealing system. Air tight inspection doors are provided for access to all bolted connections and fitted close to all sharp bends in the busbar system to provide adequate access for maintenance requirements. The Combustion Turbine Generator Bus Duct System shall be rated to continuously carry, as a minimum, 115% of the Combustion Turbine Generator maximum continuous current rating, and shall be braced for the fault current available. Temperature rise at the site altitude shall be limited as per SANS Source: 01630, 2005 System Descriptions Page 19 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 60694:2003. The bus duct insulation system shall maintain minimum insulation levels as per SANS 60694:2003 when filled with atmospheric air at the site specific environmental conditions. The Bus Duct System shall comply with the provisions of BS 159. 01630.2.16 BUILDING LIGHTING (LTA) Function The Building Lighting System provides personnel with illumination for plant operations and control under normal conditions, means of egress under emergency conditions, and emergency lighting to perform certain manual operations during a power outage of the normal power source. Major Components The Building Lighting System shall consist of the following major components: Light fixtures. - Industrial fluorescent. - Commercial fluorescent. - Industrial emergency incandescent. - High-pressure sodium. Light switches. Convenience receptacle socket outlets. General Description The Building Lighting System will consist mainly of switched industrial fluorescent fixtures for interior industrial areas. Finished areas with suspended ceiling systems shall consist of commercial recessed fluorescent troffers. Emergency incandescent lights shall be provided for interior egress lighting in the event that the normal source of power for lights is lost. High-pressure sodium light fixtures - suitable for wet locations - shall be provided outside and above exterior door entrances, miscellaneous exterior platforms and process equipment areas. High pressure sodium fixtures shall be provided for interior unheated locations, such as the turbine building, water treatment building, and warehouse. Other areas, such as the fire pump building, hypochlorite generation building, hydrogen generation building shall be lit with appropriate sources. Light sources used in hazardous locations shall be listed for use in those locations. . High pressure sodium fixtures shall be provided with E40 lamp sockets and powered from 230 volt, 50 Hz lighting panelboards. Luminaires shall comply with the requirements of SANS 1464 and SANS 1119. Incandescent lights 200W and below shall be of the clear type with E27 type lampholders. The power supply for the building lighting system shall be from the normal AC power, essential services AC power, or dc power system as required. The emergency lighting system shall be powered from the essential services ac system; the luminaries shall be designed to burn at all times. The control room lighting shall be fed from the essential services ac system and backed up by the dc system. The bottom of convenience socket outlets in finished areas shall be installed 0.4 m above the floor in areas that have suspended ceilings, and 1 m above the floor in areas that do not have ceiling systems. The bottom of light switches shall be installed 1.2 m above the floor. Convenience socket outlets in finished areas shall be 13 amp, 230 volt. Convenience socket outlets in industrial areas shall be 16 amp, 230 volt, 3 pin type and shall be provided so a 25 metre extension cord can access plant process equipment areas. All outdoor convenience outlets shall have IP56 or greater Source: 01630, 2005 System Descriptions Page 20 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 weather proof covers. Outdoor convenience socket outlets shall be derived from a 32 milliamp MCB residual current circuit breaker. The lighting system shall be designed to provide the required illumination levels in all areas and to meet fire and safety codes. Illumination levels shall be in accordance with the recommendations of SANS 0114 Part 1 (Interior Lighting) and SANS 0114 Part 2 (Emergency Lighting). 01630.2.17 AREA LIGHTING (STH) Function The Area Lighting System provides illumination for the performance of general yard tasks, safety, and Facility security. Major Components The Area Lighting System shall consist of the following major components: High-pressure sodium luminaries. Roadway lighting poles. Interconnecting cable. General Description Illumination for roadways, parking areas, and other outdoor plant yard areas shall be provided by photoelectric controlled high-pressure sodium luminaries. Where nearby structures for mounting the light fixtures are not available, low maintenance galvanized steel anchor based lighting poles shall be provided. Connections between area lighting poles shall be direct buried armoured cable circuits. Power for the area lighting shall be 230/400 volt, 50 Hz provided by the AC Power Supply System. Power for roadway or area lighting installed on poles shall be 230 volt, 50 Hz. Area lighting shall be provided at the following locations: Transformer area. Circulating water intake structure. Building entrances. Paved roadways. Parking areas. Security fence installations. The Area Lighting System shall be designed to provide the required illumination levels in site areas where lighting is necessary for safety and tasks. Illumination levels shall be in accordance with SANS 10389-1 and SANS 10389-2. All cable connections for lighting shall be located within the lighting fixtures and poles. 01630.3 Mechanical Systems This section contains system descriptions for each of the major mechanical systems that will be constructed as part of this Project. These system descriptions describe the function, major components, and basis for design for each system. The system descriptions contained within this section are as follows: Station Air (CAA) Control Air (CAB) Source: 01630, 2005 System Descriptions Page 21 of 65 ESKOM COEGA CCGT 144807.71.0201 01630.3.1 WORKS INFORMATION EMPLOYER REVIEW 20October06 Closed Cycle Cooling Water (ECB) Fuel Gas Supply (FGA) Fuel Oil Receiving and Supply (FOA) Boiler Feed (FWA) Condensate (FWC) Condensate Polishing (FWD) Cycle Makeup and Storage (FWF) Condenser Air Extraction (HRB) Circulating Water (HRC) Heat Recovery Steam Generators (SGA) Boiler Vents and Drains (SGF) High Pressure Steam (SGG) Low Pressure Steam (SGH) Hot Reheat Steam (SGJ) Cold Reheat Steam (SGK) Steam Turbine Drains (SGL) Steam Turbine Generator (TGA) Combustion Turbine Generators (TGH) Fire Protection Water Supply and Storage (WSE) Station Air (CAA) Function The Station Air System supplies clean, dry air to nonessential users such as hose stations that require compressed air for operating pneumatic tools for maintenance work. Major Component The Station Air System shall include the following major components: Two full capacity, completely packaged, water cooled, electric motor driven, oil flooded, rotary screw compressors, producing air at 125 psig (860 kPaG), complete with inlet air filters, oil/air separation, after-cooling and air/water separation. Two complete full capacity (to match compressor capacity) refrigerated air dryers, complete with all controls and provisions for remote trouble annunciation. One vertical, cylindrical, ASME Section VIII, Div. 1, air receiver, with relief valve and drain trap. Interconnecting piping, valves, instrumentation, and accessories. General Description Compressed air is supplied by one of two full capacity air compressors to the air receiver. Normally, one compressor shall operate, loading and unloading to maintain the receiver pressure between 110 and 125 psig (760 and 860 kPaG). The second compressor shall be maintained in standby mode for immediate startup in the event of trouble or trip of the operating compressor. Compressed air from the receiver flows to the in-service air dryer, through the dryer’s inlet air filter, and enters an air-to-air heat exchanger where it is precooled by the chilled outgoing air. The air then enters the air-to-refrigerant heat exchanger and is cooled to the desired dew point. Air/water mixture enters the separator and liquid water is removed from the air. An automatic drain discharges the collected condensate from the system. The dry, chilled air enters the secondary side of the air-to-air exchanger to reheat and help cool incoming compressed before exiting and then flows to the distribution system. The compressed air is dried to a dew point of +40 oF (+4 oC). The distribution piping supplies dried, filtered compressed air to quick disconnect hose connections distributed throughout the plant. Source: 01630, 2005 System Descriptions Page 22 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Bypass lines shall be provided around the air receiver and air dryers. Air drops from the main compressed air header to air users shall have a dirt leg and drain valve below the lowest air user. The individual branch lines from the air drop to air users shall include an isolation valve and flexible hose or tubing pig tail for connection to the final air user. Station air shall be provided throughout the Turbine Building, Water Treatment Bldg, and around the combustion turbine and HRSG, including hose stations on top of the HRSG at drum level. All vent, drain, and air user connections shall be furnished with a single ball valve for isolation. Materials of Construction Materials of construction shall be as follows: Air receiver – carbon steel ASME SA285, Gr. C, or ASME SA516 Gr. 70 Piping 2-1/2 inch (65 mm) and larger - carbon steel, A53 or A106, Gr. B, standard weight Piping 2 inch (50 mm) and smaller – carbon steel, A53 or A106, Gr. B, schedule 80 fittings Valves 2-1/2 inch (65 mm) and larger – Cast steel, ASTM A216 WCB, CL150, RF flanged Valves 2 inch (50 mm) and smaller – Forged steel, ASTM A105, SWLD ends. Controls and Instrumentation The station air compressors and dryers are operated from local control panels on the compressors and dryers. Running status and one trouble alarm for each compressor, and one trouble alarm for each dryer, shall be monitored at the DCS operator interface stations. Compressed air system pressure at the air receiver shall be monitored and displayed in the DCS. The DCS shall also have supervisory control capability (start, stop, lead/lag selection). Operating Requirements In order to maintain both dryers in ready status, the plant operator must alternate use of the two full capacity dryers on a weekly basis. This is a manual operation performed at the air dryers. 01630.3.2 Control Air (CAB) Function The Control Air System supplies clean, dry air to plant equipment that requires control air for operation, and for pneumatic instruments and valves. Major Components The Control Air System shall include the following major components: Two full capacity, completely packaged, water cooled, electric motor driven, oil flooded, rotary screw compressors, producing air at 125 psig (860 kPaG), complete with inlet air filters, oil/air separation, after-cooling and air/water separation. Two complete full capacity (to match compressor capacity) desiccant dryer units, each including dual coalescing type prefilters, with automatic drains, for removal of moisture and oil, a dual tower, heatless regeneration, desiccant air dryer, and dual particulate type afterfilters for removal of desiccant particles, complete with all controls, humidity indicators and provisions for remote trouble annunciation. Source: 01630, 2005 System Descriptions Page 23 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 One vertical, cylindrical, ASME Section VIII, Div. 1, air receiver, with relief valve and drain trap. Interconnecting piping, valves, instrumentation, and accessories. General Description Control air is supplied by one of two full capacity air compressors to the air receiver. Normally, one compressor shall operate, loading and unloading to maintain the receiver pressure between at approximately 110 and 125 psig (760 and 860 kPaG). The second compressor shall be maintained in standby mode for immediate startup in the event of trouble or trip of the operating compressor. Air from the receiver flows through the prefilters, to the active tower of the in desiccant air dryer, and is dried to a dew point of -40 °F (-40 °C). A portion of the dried air is used to regenerate the desiccant in the inactive tower of the in-service dryer and the remaining air passes through the afterfilters and flows to the distribution system. The distribution piping supplies dried, filtered Control air to plant equipment requiring air. Bypass lines shall be provided around the air receiver and air dryers. Air drops from the main Control air header to air users shall have a dirt leg and drain valve below the lowest air user. The individual branch lines from the air drop to air users shall include an isolation valve and flexible hose or tubing pig tail for connection to the final air user. Control air shall be provided throughout the plant site, including the circulating water intake structure, as required to serve all instrument air user requirements. All vent, drain, and air user connections shall be furnished with a single ball valve for isolation. Materials of Construction Materials of construction shall be as follows: Air receiver – carbon steel ASME SA285, Gr. C, or ASME SA516 Gr. 70 Piping 2-1/2 inch (65 mm) and larger - ASTM A312 TP304 stainless steel, standard weight Piping 2 inch (50 mm) and smaller – ASTM A312 TP304 stainless steel, schedule 80 SWLD fittings Valves 2-1/2 inch (65 mm) and larger – Cast stainless steel, ASTM A351 CF8M, CL150, RF flanged Valves 2 inch (50 mm) and smaller – Forged stainless steel, ASTM A182 F316, SWLD ends Controls and Instrumentation The control air compressors and dryers are operated from local control panels on the compressors and dryers. Running status and one trouble alarm for each compressor, and one trouble alarm for each dryer, shall be monitored at the DCS operator interface stations. Control air system pressure at the air receiver shall be monitored and displayed in the DCS. The DCS shall also have supervisory control capability (start, stop, lead/lag selection). Operating Requirements In order to maintain both dryers in ready status, the plant operator must alternate use of the two full capacity dryers on a weekly basis. This is a manual operation performed at the air dryers. Source: 01630, 2005 System Descriptions Page 24 of 65 ESKOM COEGA CCGT 144807.71.0201 01630.3.3 WORKS INFORMATION EMPLOYER REVIEW 20October06 Closed Cycle Cooling Water (ECB) Function The Closed Cycle Cooling Water System provides water for plant components and equipment that require water cooling. Typical cooling water users are: Steam turbine generator coolers Steam turbine stator coolers Steam turbine lube oil coolers Steam turbine generator gas dryer Combustion turbine generator coolers Combustion turbine lube oil coolers Combustion turbine generator gas dryer Combustion turbine atomizing air coolers Combustion turbine base cooling Boiler feed pump lube oil and seal water coolers Sample coolers and chiller units for secondary sample coolers Air compressors Major Components The closed cycle cooling water system will include the following major components: Three 50 percent capacity, horizontal end suction, centrifugal pumps with electric motor drives. Two full capacity, shell and tube, closed cycle cooling water heat exchangers. One atmospheric pressure, closed cycle cooling water expansion tank. One chemical addition tank. One suction strainer at the inlet of each closed cooling pump. Interconnecting piping, valves, instrumentation, and accessories. General Description Two of three closed cycle cooling water pumps circulate closed cycle cooling water through one of two closed cycle cooling water heat exchangers to the headers that distribute cooling water to the equipment to be cooled. Cooling water return headers collect and return the cooling water to the suction of the cooling water pumps. The atmospheric pressure closed cooling water expansion tank is connected via piping to the pump suction header and provides a reservoir of water to make up to the closed cooling water system as well as providing storage capacity for the additional water volume of the system due to thermal expansion. The tank shall be installed at an elevation above the highest point in the cooling water system. Makeup water to the expansion tank is supplied from the Cycle Makeup and Storage System (FWF). Sample connections and a chemical addition tank are provided for monitoring the condition of the inhibitors in the closed cycle cooling water and for adding chemicals. The standard Employer treatment for closed cooling water is trisodium phosphate conditioning plus tolytriazole (if copper alloys are present). Isolation valves are provided at the inlet and outlet of the closed cycle cooling water heat exchangers and each of the components requiring cooling water. A sentinel or thermal relief valve shall be installed between the cooled equipment and the outlet isolation valve to prevent overpressure due to thermal Source: 01630, 2005 System Descriptions Page 25 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 expansion of liquid contained between closed isolation valves. Test/vent or test/drain valves shall be provided between the isolation valves and the coolers. All vent, drain, and instrument connections shall be furnished with a single valve for isolation. Materials of Construction Materials of Construction shall be as follows: Closed cycle cooling pumps – Cast or ductile iron casing, stainless steel shaft and shaft sleeves, and cast steel impeller Closed cycle cooling head tank – ASTM A285, Gr. C or ASTM A516 Gr. 70 Chemical addition tank – ASTM A285, Gr. C or ASTM A516 Gr. 70 Closed cycle cooling heat exchangers – Carbon steel shell with CSDS A52 or A66 coating and impressed current cathodic protection provided for internal surfaces. Titanium tubes and tube sheets. Piping 2-1/2 inch (65 mm) and larger – ASTM A53 A106 Gr. B standard weight Piping 2 inch (50 mm) and smaller – ASTM A53 A106 Gr. B Schedule 80 Valves 2 inch (50 mm) and smaller – Forged steel ASTM A105 Valves 2-1/2 inch (65 mm) and larger – Cast steel ASTM A216 WCB Controls and Instrumentation The Closed Cycle Cooling Water System is controlled through the DCS. The closed cycle cooling water pumps are operated from the DCS operator interface stations in the control room. Normally two pumps will be running and the third pump will be in “standby”. The standby pump shall start automatically, in the event that the running pump trips or the system differential pressure is low. The DCS shall monitor and indicate the closed cycle cooling water expansion tank level, pressure drop across the strainer, and the closed cycle cooling water heat exchanger inlet and outlet water temperature and pressure. Low water level in the expansion tank shall be alarmed. 01630.3.4 Fuel Gas Supply (FGA) Function The Fuel Gas Supply System receives gas from the LNG facility and delivers it to the equipment requiring fuel gas. The fuel gas system heats, conditions, and delivers fuel gas to the combustion turbines as the primary fuel. The delivery temperature of the gas shall meet the combustion turbine manufacturer’s recommendations for minimum superheat above the gas hydrocarbon dew point temperature. Major Components The Fuel Gas Supply System shall include the following major components in the common fuel gas supply line: One motor operated remote emergency shutoff valve near the site boundary Two full capacity fuel gas filter separators in parallel installed upstream of the site fuel gas pressure regulating and metering station. Two full capacity site fuel gas pressure regulating and metering stations in parallel located near the site boundary. The Fuel Gas Supply System shall include the following major components for each combustion turbine/HRSG unit: Source: 01630, 2005 System Descriptions Page 26 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 One full capacity fuel gas filter/separator installed upstream of the fuel gas heaters. One hot water heated fuel gas heater to raise the temperature of the fuel delivered to the combustion turbine to 365F, or other temperature as required by the CTG manufacturer, for cycle performance enhancement and emissions control. One electric start-up fuel gas heater. One full capacity fuel gas scrubber installed immediately downstream of the fuel gas heaters. One atmospheric pressure drain tank to collect drains from the fuel gas filter/separator, startup heater, and fuel gas scrubber. One fuel gas flow meter, supplied by the combustion turbine manufacturer, for installation in the fuel gas piping downstream of the fuel gas scrubber. Interconnecting piping, valves, instrumentation, and accessories. General Description Natural gas is delivered from an offsite pipeline to the site metering and pressure regulation station. Custody of the gas is transferred at the fence, or at the outlet of the last valve, of the regulating and metering station. If the gas supplied does not meet the combustion turbine manufacturer’s recommendations for superheat above the hydrocarbon fuel dew point, additional heating shall be provided. Because hot water for the fuel gas heater is not available during startup, a startup fuel gas heater shall be provided to heat the gas to the turbine manufacturer’s recommended minimum superheat temperature. Fuel gas to the combustion turbine flows through a filter/separator, fuel gas heater, a fuel gas scrubber, and a gas flow meter assembly to the gas supply connection at the CTG. Piping downstream of the scrubber shall be stainless steel. Drains from the fuel gas filter/separators, heaters, and scrubbers shall be directed to a dedicated drain tank. The drain tank shall vent to atmosphere and have a connection for periodic removal of the liquids collected. The fuel gas heaters, the filter/separators, fuel gas scrubbers, the filter/separator drain tanks, and related flanged connections must be located in an area defined as hazardous because of the potential for discharge of fuel gas. All electrical devices and instrumentation located within these areas shall be rated in accordance with Section 01400 and the specific equipment technical specifications herein.. The fuel gas piping shall include provisions for cleaning by blowing with fuel gas or compressed air. These provisions shall include a flanged section of piping to be left out of the fuel gas line to each combustion turbine and a temporary pipe spool for directing the fuel gas or air blow to a safe location. A remote operated emergency fuel shutoff valve shall be provided at the site interface point to allow the control room to shut off the fuel gas supply in case of an emergency. All miscellaneous vent, drain, and instrument connections shall be furnished with a single ball valve for isolation. Materials of Construction Fuel gas filter separators – ASME SA285, Gr. C or SA516-70 Fuel gas scrubbers – ASME SA285, Gr. C or SA516-70 Fuel gas filter separator/scrubber drain tanks – ASTM A285, Gr. C or A516-70 (atmospheric – non-ASME code) Fuel gas heaters – Carbon steel shell and tubes Source: 01630, 2005 System Descriptions Page 27 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Piping – ASTM A53 or A106 Gr. B, upstream of the final fuel gas filter separator, and ASTM A312, TP304, downstream of the final fuel gas filter separator. Weld code W1 shall be used for carbon steel piping upstream of the fuel gas separator and for stainless steel piping between the fuel gas scrubber and the combustion turbine. Valves 2 inch (50 mm) and smaller – CL600, socket weld, forged steel ASTM A105 for carbon steel piping and ASTM A182 TP304 for stainless steel piping. Valves 2-1/2 inch (65 mm) and larger – CL300 and CL600, buttwelded, flanged, wafer, or lug, cast steel ASTM A216 WCB for carbon steel piping and ASTM A351 Gr. CF3 for stainless steel piping. Note: All valves shall be suitably rated for fuel gas service (Factory Mutual or otherwise approved). Controls and Instrumentation The fuel gas regulating and metering station will be monitored and controlled by the fuel gas supplier. Flows, pressures and temperatures are transmitted to the DCS. The fuel gas system shall be monitored and controlled by the DCS. A fuel gas flow meter shall be provided in each line to the combustion turbines. Individual combustion turbine gas consumption rates shall be monitored by the DCS. Fuel through the gas heaters shall be monitored and temperature controlled by the DCS. Fuel gas is typically heated with IP economizer outlet water. Gas temperatures are controlled by regulating the flow of water to the heaters. Liquid-side to gas-side leakage in the fuel gas heaters shall be monitored by level switches in the downstream filter/separator and shall be alarmed in the DCS. The levels in the fuel gas filter separators and scrubbers are monitored and controlled locally by level switches and a drain control valve. The highhigh level switch shall be monitored and alarmed in the DCS. Leakage from the gas side to the liquid side in the heaters shall be monitored by level switches in a tube leak detection column located in the water piping downstream of the fuel gas heaters. Detection in the column causes waterside isolation and an alarm in the DCS. Other approaches to leak detection shall also be considered. If hydro testing with water is performed, the system shall have low point drain capability and the piping shall be drained and thoroughly dried immediately after hydrotesting is complete. Temporary spools are required for flow element replacement during gas/air blow. 01630.3.5 Fuel Oil Receiving and Supply (FOA) Function The Fuel Oil Receiving and Supply System receives diesel from off-site storage tanks, stores it in the Fuel Oil Storage Tank, and delivers fuel oil to the combustion turbines as a secondary fuel. Major Components The Fuel Oil Receiving and Supply System shall include the following major components: One vertical, steel, column supported, cone roof, field erected Fuel Oil Storage Tank. The tank shall be sized for 24 hours of base load operation of three combustion turbines on fuel oil. Space shall be provided for a future second tank of similar size. Either a cathodic protection system shall be provided for the tank bottom exterior surfaces in contact with soil Source: 01630, 2005 System Descriptions Page 28 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 or a concrete seal slab shall be placed under the tank to isolate the tank bottom from the soil. Containment shall be provided around the fuel oil tanks large enough to contain 110% of the tank storage capacity. Two horizontal, end suction, electric motor driven full capacity fuel truck unloading pumps. Three fuel forwarding pump skids, each with two full capacity (equal to 100 percent flow for one combustion turbine plus continuous recirculation flow), horizontal, end suction, electric motor driven, fuel oil forwarding pumps. Two full capacity, horizontal, end suction, electric motor driven, fuel transfer pump shall provide fuel oil to the auxiliary boiler, black start diesel generator, and diesel driven fire pump. A basket strainer shall be provided on the suction of each pump. Interconnecting piping, valves, instrumentation, and accessories. General Description Fuel oil is normally received from off-site storage tanks (by others) but may also be delivered by truck through the fuel truck unloading station. Containment shall be provided around truck unloading stations and fuel oil unloading pumps in accordance with Employer's regulations. Interface for the fuel oil supply pipe from off-site storage tanks shall be at the fence line. An automatic tank level control valve shall be provided that is coordinated with the off-site fuel supply system. The fuel oil storage tank shall be of double wall construction with foam connections on the fuel oil tank for fire protection foam system. The tank shall have valved connections with blind flanges to allow addition of the future storage tank and pumps. The fuel forwarding skids shall take fuel oil directly from the fuel oil storage tank suction. A flow orifice and transmitter are required in the fuel line to each combustion turbine to provide a fuel oil flow signal to the DCS. This flow signal may be re-transmitted from the DCS to the CEMS equipment for emissions calculations. Separate flow meters shall be provided to record fuel flow to the aux boiler and diesel generator, individually. During operation of the combustion turbines on fuel oil, one fuel oil forwarding pump for each forwarding skid shall be in service for each combustion turbine operating on fuel oil. The fuel oil forwarding pump suction pipe shall be routed flat or sloped down to the pumps. All piping shall be routed aboveground or in trenches. Routing of oil piping underground shall be avoided because of requirements for double containment. Road crossings shall be made in trenches and all other oil lines shall be routed on sleepers or in the pipe rack so they are available for visual inspection. Separate 2x100% fuel oil forwarding pumps shall be furnished to feed the diesel engine day tanks and the auxiliary boiler fuel system. Both the diesel engine and the auxiliary boiler shall be furnished with separate supply pumps to directly feed the equipment. All vent, drain, and instrument connections shall be furnished with a globe valve for isolation. Materials of Construction Fuel oil storage tank – ASTM A36, ASTM A283 Gr. C, or ASTM A285, Gr. C, as limited by API-650. Fuel oil pumps – Ductile iron or cast steel casing, stainless steel shaft and shaft sleeves, and cast steel impeller. Piping – Carbon steel ASTM A53 or A106 Gr. B Valves 2 inch (50 mm) and smaller – CL 600, socket weld, forged steel ASTM A105 Valves 2-1/2 inch (65 mm) and larger – CL150, flanged, cast steel ASTM A216 WCB Controls and Instrumentation Source: 01630, 2005 System Descriptions Page 29 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Control of the fuel oil receiving and supply system is provided through local controls and remotely through the DCS operator interface stations in the control room. The operators shall start a fuel oil forwarding pump prior to starting a gas turbine on fuel oil or before transferring the gas turbine fuel supply from gas to oil. Controls shall also be provided for the fuel oil forwarding pumps feeding the auxiliary boiler and the diesel generator day tanks. Alarms and automatic shutdowns shall be annunciated in the control room and displayed on the DCS operator interface stations. Level indication for the fuel oil storage tank is displayed on the DCS operator interface station and locally at the tank by means of a level indicator (float and gage board type indicator). Differential pressure across the transfer pump duplex strainer is monitored by a differential pressure transmitter and alarmed in the DCS when the strainer needs cleaning. The fuel oil forwarding pump discharge header pressure is monitored and displayed in the DCS. Fuel oil flows to the combustion turbines are monitored in the DCS and may be transmitted to the CEMS for use in emission calculations. 01630.3.6 Boiler Feed (FWA) Function The Boiler Feed System provides water from the deaerator to the high-pressure, intermediate-pressure, and low pressure economizers of the Heat Recovery Steam Generators (HRSG). The Boiler Feed System also supplies water for the HP steam desuperheater(s) and HP steam bypass desuperheater(s), and reheat steam desuperheater(s). Major Components The boiler feed system shall include the following major components for each Heat Recovery Steam Generator: Two 100% capacity, segmental ring, multi-stage, variable speed, motor driven, IP/HP feedwater pumps. Each pump shall have an inter-stage bleed-off for intermediate-pressure feedwater. The pumps shall include a pressurized lube oil system, lube oil coolers, mechanical seals, hydraulic coupling or variable frequency drive as determined by the Employer, and seal water coolers. Two 100% capacity, segmental ring, multi-stage, variable speed, motor driven, LP feedwater pumps. Consideration will be given to other pump types depending on the expected deaerator and LP drum operating pressures. The pumps shall include a pressurized lube oil system, lube oil coolers, mechanical seals, and seal water coolers. The pumps will be electric motor driven by either direct coupling, speed increaser, hydraulic coupling or variable frequency drive as determined by the Employer. A modulating recirculation control system for each feedwater pump to ensure minimum pump flow. Flow elements, one per pump discharge for flow measurement and recirculation control, one each for the economizer feedwater flows for use in three element drum level control, one each for HP and reheat attemperation spray flows, and one for HP steam bypass spray flow. Each boiler feedwater pump shall have a duplex suction basket strainer with differential pressure transmitter for monitoring and alarming. Drain and vent connections on these strainers shall be the largest standard sizes available. Interconnecting piping, valves, instrumentation, and accessories. For pumps with top suction and discharge connections, flanged spool pieces shall be provided to facilitate pump dismantling for maintenance and chemical cleaning. Source: 01630, 2005 System Descriptions Page 30 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 General Description Two boiler feedwater pumps per HRSG shall supply HP and IP feedwater at the pressure necessary to overcome static and friction losses and provide the pressure required at the economizer inlets. The pumps shall be sized to supply feedwater to the HP drum at 3 percent above the highest safety valve set point. One full range HP feedwater control valve shall be provided for controlling HP drum level. One full range feedwater control valve shall be provided for controlling IP drum level. The feedwater regulators shall automatically control the feedwater flow rates to match the steam flows and maintain steam drum levels. Two boiler feedwater pumps per HRSG shall supply LP feedwater at the pressure necessary to overcome static and friction losses and provide the pressure required at the economizer inlet. The pumps shall be sized to supply feedwater to the LP drum at 3 percent above the highest safety valve set point. One full range LP feedwater control valve shall be provided for controlling LP drum level. The feedwater regulators shall automatically control the feedwater flow rates to match the steam flow and maintain steam drum level. Desuperheating spray water shall be provided to several users. HP steam desuperheater and HP steam bypass desuperheater water shall be provided from the HP feedwater pump discharge. Hot reheat steam attemperation shall be provided with spray water from the IP feedwater discharge. Each boiler feed pump shall be provided with a recirculation line back to the deaerator storage tank containing a modulating control valve sized to maintain the minimum pump flow rate as specified by the pump manufacturer. The boiler feedwater system shall be filled from the condensate system. Connections from the Condensate System shall be provided on the feedwater piping to supply water for filling the economizers and drums. The boiler feed system shall be designed in accordance with ASME B31.1, Power Piping. All vent, drain, and instrument connections exposed to pump discharge pressures shall be furnished with double gate or globe valves for isolation. Materials of Construction Feedwater pumps – Cast 1-1/4 chrome steel casing, 12 percent chrome steel shaft, impellers and wear rings Feedwater pump duplex suction strainers – cast iron or carbon steel body with stainless steel baskets Piping – ASTM A53 or A106 Gr. B or C (seamless for discharge piping) HP Boiler Feedwater Valves 2 inch (50 mm) and smaller – forged steel ASTM A105, socket weld HP Boiler Feedwater Valves 2-1/2 inch (65 mm) and larger – cast steel ASTM A216 WCB or WCC IP Boiler Feedwater Valves 2 inch (50 mm) and smaller – forged steel, ASTM A105, socket weld IP Boiler Feedwater Valves 2-1/2 inch (65 mm) and larger – cast steel ASTM A216 WCB or WCC LP Boiler Feedwater Valves 2 inch (50 mm) and smaller – forged steel, ASTM A105, socket weld LP Boiler Feedwater Valves 2-1/2 inch (65 mm) and larger – cast steel ASTM A216 WCB or WCC Welding codes – W1, W2 (refer to Section 01400, Supplemental Q210 for definition) Source: 01630, 2005 System Descriptions Page 31 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Controls and Instrumentation The feedwater system shall be controlled and monitored through the plant DCS. The boiler feed pumps shall be started, stopped and monitored from the DCS operator interface stations. The boiler feedwater pumps shall be tripped on low level in the deaerator. A flow element shall be provided for each IP/HP boiler feed pump to measure pump HP discharge flow upstream of the minimum flow recirculation line to the deaerator. This flow element shall be used to control the recirculation valve. A flow element shall be provided for each LP boiler feed pump to measure pump LP discharge flow upstream of the minimum flow recirculation line to the deaerator. This flow element shall be used to control the recirculation valve. A flow element shall be provided in the common HP discharge line to measure total flow to the HP economizer. This flow signal shall be used in the three element level control scheme for the HP drum, which is used to control the HP feedwater drum level control valves. A flow element shall also be provided in the common IP discharge line to measure total flow to the IP economizer. This flow signal shall be used in the three element level control scheme for the IP drum which shall be used to control the IP feedwater drum level control valve. On units where the IP economizer supplies water for fuel gas heating, this flow element shall be located between the economizer and the IP drum downstream of the branch to the fuel gas heater. A flow element shall be provided in the common LP discharge line to measure total flow to the LP economizer. This flow signal shall be used in the three element level control scheme for the LP drum, which is used to control the LP feedwater drum level control valves. A flow element shall be provided in the HP steam bypass spray line for developing the calibration of the HP spray valve flow used in the HP bypass spray control logic. A flow element shall also be provided in the reheat steam attemperation spray line. Boiler feedwater pressures shall be monitored upstream and downstream of the boiler feed pumps. Feedwater temperatures shall be monitored in the common suction discharge piping. Boiler feedwater pump suction strainers shall be monitored by differential pressure transmitters. Alarms shall be indicated on the DCS operator interface stations. 01630.3.7 Condensate (FWC) Function The Condensate System receives and condenses steam from the steam turbine exhaust and miscellaneous drains, and returns the condensate to the deaerator (s). The Condensate System also supplies water for desuperheating hot reheat bypass steam, LP bypass steam (if required), turbine gland seal steam (if required), reverse flow steam (if required), turbine exhaust hood spray, condenser curtain/ neck sprays, and miscellaneous steam drains to the condenser (if required). Condensate that must be dumped due to system upset conditions or high hotwell levels shall be returned to the Condensate Storage Tank for reuse. Further information on the operation of this tank is provided in the description of the Cycle Makeup and Storage System (FWF). Major Components The condensate system shall include the following major components: Source: 01630, 2005 System Descriptions Page 32 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 One full capacity, two shell condenser with double water pass design and divided water boxes arranged to allow two separate cooling water paths. The condenser hot well shall be sized to hold a minimum of 5 minutes supply of condensate. Corrosion control provisions shall be provided for water box surfaces wetted by circulating water. Three 50 percent capacity, multistage, vertical can type condensate pumps with discharge connections above the floor level. The condensate pumps shall be direct coupled to, and driven by, vertical electrical motors with Kingsbury type thrust bearings mounted at the top of the motors and a radial bearing at the drive end of the motor. A minimum flow recirculation control system to ensure minimum flow requirements for the pumps and the turbine gland steam condenser. Eight flow elements, one orifice plate for minimum flow control located in the pump recirculation line, one flow nozzle per deaerator for level control, one orifice plate per HRSG for hot reheat bypass desuperheater control and special calibrated flow nozzle test sections shall be furnished for performance testing. The calibrated flow nozzle test sections are required for overall plant performance testing. They are temporarily installed in place of each deaerator flow element when performance testing is conducted. Only the main flow nozzles to each HRSG (see FWC P&ID Sht E) get replaced like this during performance testing. Additionally, one orifice plate shall be provided per HRSG for LP steam bypass desuperheater control (if required). A basket strainer with differential pressure monitoring instrumentation at the suction of each condensate pump. The basket strainer shall have a full lift out basket. Tee type strainers shall not be used. Interconnecting piping, valves, instrumentation, and accessories. General Description The condensate pumps shall take suction from the condenser hotwell and discharge to the condensate distribution system. The condensate shall flow from the pumps through the recirculation control flow orifice, through the steam turbine gland steam condenser, and then split into three lines to the deaerators and three lines to the HRSG hot reheat bypass sprays. The minimum flow recirculation line shall branch off the main header downstream of the minimum flow control orifice and return the recirculated condensate to a connection above the condenser tubes. In each of the individual lines to the deaerators, there shall be a condensate flow control valve and a flow element to provide the condensate flow signal for the deaerator level control. The condensate level in the hotwell shall be monitored and controlled by the addition of makeup water from the Cycle Makeup and Storage System or by dumping of condensate to the condensate storage tank. The demineralized makeup water shall be admitted to the condenser shell above the tube bundles and is cascaded down through the tube bundle to deaerate the makeup water. The condensate dump line shall branch off the main condensate header downstream of the minimum flow recirculation line. The condensate system shall supply water for desuperheating the hot reheat steam bypass to the condenser, desuperheating LP steam bypass (if required), desuperheating gland seal steam (if required), desuperheating miscellaneous drains discharged to the condenser (if required), supplying turbine exhaust hood spray water, or for supplying water to condenser neck sprays for overtemperature protection during steam bypass operation and reverse flow (if required). Chemical addition connections shall be provided for the addition of chemicals from the Cycle Chemical Feed System (FWE). Water sample connections upstream and downstream of the chemical addition points shall be provided for the Sampling and Analysis System (SAC). The condensate system shall be designed in accordance with ASME B31.1. Source: 01630, 2005 System Descriptions Page 33 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 All miscellaneous vent, drain, and instrument connections shall be furnished with a single ball, gate, or globe valve for isolation. Materials of Construction Condensate pumps – carbon steel column, cast iron bowls, carbon bearings, stainless steel shaft, stainless steel first stage impeller and stainless steel wear rings Condensate pump suction strainers – Carbon steel or cast iron body with stainless steel basket Orifice plates – ASTM 240 Gr. 304 stainless steel Piping – ASTM A53 or A106 Gr. B Valves 2 inch (50 mm) and smaller – forged steel ASTM A105, socket weld Valves 2-1/2 inch (65 mm) and larger – cast steel ASTM A216 WCB, flanged Weld codes – W1, W2 (refer to Section 01400, Supplemental Q210 for definition) Controls and Instrumentation The Condensate System shall be controlled through the DCS. Normally, the two 50 percent capacity condensate pumps will be started manually from the DCS operator interface stations and the third pump will be in standby mode to start automatically in the event of a trip of the running pump or during full steam bypass with three Combustion Turbines online. The condenser level shall be monitored by redundant level transmitters. A makeup control valve shall add water on low level and a dump control valve dumps water to the condensate storage tank on high level. The condensate pumps shall be tripped on low-low condenser level. A flow element shall be installed in the condensate header upstream of the steam turbine gland steam condenser (and steam jet air ejector condenser, if applicable) to measure condensate pump discharge header flow. This flow element shall be used to control the minimum flow recirculation valve to ensure that adequate flow is maintained through the pump and gland steam condenser. A flow element shall be provided in each deaerator line to measure flow to the deaerator. This flow signal shall be used to control deaerator level and condensate pump minimum flow. Condensate system temperatures and pressure shall be monitored and displayed on the DCS operator interface stations. A flow element is provided in each of the Hot Reheat steam bypass spray lines for developing the calibration of the RH spray valve flows used in the bypass spray control logic. Condensate pump suction strainers shall be monitored by differential pressure transmitters and alarms shall be indicated on the DCS operator interface stations. Each condensate pump discharge pressure shall be locally indicated. Condenser absolute pressure shall be monitored by redundant pressure transmitters to generate condenser protective logic for permitting and tripping the steam bypass systems discharging into the condenser. 01630.3.8 Condensate Polishing System (FWD) Function The function of the Condensate Polishing System is to remove contaminates from the condensate and to maintain the quality of the feedwater in the cycle. Major Components The Condensate Polisher System shall include the following major equipment and components: Source: 01630, 2005 System Descriptions Page 34 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Three half capacity Cation Ion Exchange Vessels Three half capacity Mixed Bed Ion Exchange Vessels Two full capacity recycle pumps Resin Hopper Cation Bed Regeneration Tank Mixed Bed Cation Regeneration Tank Mixed Bed Anion Regeneration Tank Mixed Resin Storage Tank Cation Resin Storage Tank Condensate Polisher Water Heater Acid Feed and Dilution Skid with local control box, dilution tank, eductor and specific conductivity analyzer Caustic Dilution Skid with local control box, dilution tank, eductor and specific conductivity analyzer. Caustic Storage Tank Acid Storage Tank with vent dryer All necessary piping, valves, and instrumentation required for operating the system. General Description Effluent from the condensate pumps is split between three Ion Exchange trains. Each train contains a cation and mixed bed exchanger. The cation exchanger filter any solids and acts as a guard for the trailing mixed beds by removing ammonia and prevents premature exhaustion of the mixed beds. The mixed bed exchangers contain both anion and cation exchange resins that remove dissolved impurities from the condensate. Typically, two polishing trains are in service while the third is placed in standby or is undergoing regeneration. Samples shall be taken from the effluent of each cation and mixed bed in service. These samples shall be routed to the sample panel (SAC). The samples shall be tested to determine the quality of water being discharged. The results of these analyses shall determine when a specific polisher vessel should be taken off line and regenerated. During regeneration, the ion exchange resin is transferred from the ion exchange bed to the cation regeneration tank. Here the resin is cleaned and separated into cation and anion fractions (if applicable). The anion fraction is routed to the anion regeneration vessel. Here the anion resin is treated with caustic while the cation resin is treated with acid. Both resins are then rinsed with demineralized water. The resins are combined (if applicable) in the resin storage tank for transfer back to the ion exchange vessel. Alternative regeneration system designs will be considered for installation depending upon the selected suppliers proprietary design practices. The resin transfer system shall guarantee a minimum 99.9% transfer efficiency (i.e. ≥99.9% resin removal from any given vessel- service/separation/ regeneration/ storage). Materials of Construction Ion Exchange Vessels (cation and mixed bed) –304 or 316 stainless steel Regeneration Vessels and Resin Storage Vessels –lined carbon steel Condensate Polisher Recycle Pumps – Stainless Steel Condensate piping, vent, and drain piping – Carbon steel Resin Transfer piping – PPL lined Source: 01630, 2005 System Descriptions Page 35 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 All wetted components not listed above shall be provided according to the following services: Concentrated Acid- Alloy 20 Dilute Acid- PPL Lined Concentrated Caustic- Carbon Steel Dilute Caustic- Stainless Steel Condensate- Carbon Steel Controls and Instrumentation Control of the system shall be via local PLC with supervisory control and monitoring from the DCS Instruments and analyzers shall be used to monitor and manage the operation of the condensate polishers and associated equipment. These instruments include differential pressure transmitters, flow transmitters, pressure switches, level switches, pressure indicators, temperature indicators, temperature switches and temperature transmitters. The system shall also be provided with conductivity analyzers. 01630.3.9 Cycle Makeup and Storage (FWF) Function The Cycle Makeup and Storage System receives demineralized water from the Cycle Makeup Treatment System (WTD) and stores it in the Demineralized Water Storage Tank. The demineralized water is distributed for the following uses: Steam cycle emergency makeup water to the condenser to replace condensate/feedwater/steam lost to leakage, drains and boiler blowdown. Injection water to the combustion turbines for NO x emissions control when firing liquid fuel. Combustion turbine wash water. Condensate polisher regeneration supply. Condensate system fill. Dilution water to the cycle chemical feed system (may be supplied from FWC instead). In addition, the Cycle Makeup and Storage System receives condensate from the condensate dump system and stores it in the Condensate Storage Tank. This water is subsequently reused in the cycle to help minimize the consumption of cycle treatment chemicals. Cycle users include the following: Steam cycle normal makeup water to the condenser to replace condensate/feedwater/steam lost to leakage, drains and boiler blowdown. Condensate pump seal water. Makeup water to the closed cycle cooling expansion tank. Major Components The Cycle Makeup and Storage System shall include the following major components: One vertical, welded steel, self supporting dome or cone roof, field erected Demineralized Water Storage Tanks. One current tank and space for one future tank of like design to service the second 3x1 CC block shall be provided. The tanks shall be coated internally with Source: 01630, 2005 System Descriptions Page 36 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 an epoxy coating system suitable for immersion in high purity water. The tanks shall be equipped with a vent and air filter and piping inlet, outlet, overflow, drain, instrument connections, and corrosion control prevention for exterior tank bottom plates. All connections internal piping appurtences shall be stainless steel. Each tank shall be sized for supporting three combustion turbines at full load on diesel fuel for 24 hours based upon a water injection to diesel fuel consumption ratio of not less than 1.3. Two full capacity, horizontal, end suction, electric motor driven, demineralized water transfer pumps. The demineralized water pumps shall be of stainless steel construction. The pumps shall have recirculation lines back to the demineralized water tank, with flow control orifices, to provide minimum flow protection for the pumps. One vertical, welded steel, self supporting dome or cone roof, field erected Condensate Storage Tank. One current tank and space for one future tank of like design to serve the second 3x1 CC block shall be provided. The tank shall be equipped with a vent and air filter and piping inlet, outlet, overflow, drain, instrument connections, and corrosion control prevention for exterior tank bottom plates. The Condensate Storage Tank shall have a useable capacity of 946,000 litres. Interconnecting piping, valves, instrumentation, and accessories. General Description The Cycle Makeup and Storage System consists of two demineralized water storage tanks, one condensate storage tank, and two demineralized water transfer pumps, associated piping, valves and instrumentation. Demineralized water is supplied to the demineralized water storage tanks through an aboveground line from the Cycle Makeup Treatment System in the Water Treatment building. All piping and valves shall be stainless steel. The condensate storage tank shall be filled by the high level dump valve in the condensate system. Normally, water shall be supplied to the condenser by “vacuum drag” from the condensate storage tank. The static head of water in the storage tank combined with the vacuum in the condenser shall provide the motive force to supply makeup water to the condenser. In cases when the water level in the condensate storage tank is too low to support “vacuum drag”, the transfer pumps may be used to provide normal makeup to the condenser hotwell. The transfer pump shall also be operated if makeup is required to the elevated closed cycle cooling water head tank. When the combustion turbines are operating on fuel oil and demineralized water injection is required for NOx control, one of the two demineralized water transfer pumps shall operate to provide demineralized water to the suction side of the CTG water injection systems. Water sample connection(s) shall be provided for the Sampling and Analysis System (SAC) to monitor makeup water quality. All miscellaneous vent, drain, and instrument connections shall be furnished with a single ball or globe valve for isolation. Materials of Construction Demineralized water storage tank – Carbon steel coated in accordance with Technical Specification 13202 Condensate storage tank – Carbon steel coated in accordance with Technical Specification 13202 Demineralized water transfer pumps – All wetted parts of stainless steel construction. Piping – ASTM A312 TP304 stainless steel. Source: 01630, 2005 System Descriptions Page 37 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Valves 2 inch (50 mm) and smaller – CL 600, forged steel ASTM A182 F316, socket weld Valves 2-1/2 inch (65 mm) and larger – CL 150, cast steel ASTM A351 Grade CF8 or CF8M, flanged or welded Piping that can only contain condensate may be carbon steel. Valves in this piping may be carbon steel or cast/ductile iron. Controls and Instrumentation The demineralized water pumps shall be controlled from the DCS operator stations. When required, one pump shall be started in manual mode, and the other shall be in standby mode to automatically start in the event that the running pump trips or header pressure becomes low. Level transmitters on the demineralized water storage tank and the condensate storage tank monitor level in the tanks and the levels shall be displayed on the DCS operator interface stations. The tank level signals shall also be used for control in the Cycle Makeup Water Treatment System (WTD), provide high and low level alarms, and interlock pump operation. A pressure transmitter monitors the demineralized water transfer pump discharge header, the pressure is displayed on the DCS operator interface stations, and is used for start of the standby pump if one pump is running and header pressure is low. Pressure shall be monitored on each demineralized water transfer pump suction or discharge. 01630.3.10 Condenser Air Extraction (HRB) Function The Condenser Air Extraction System removes the noncondensable gases from the cycle during steam turbine generator operation, rapidly reduces the condenser pressure before unit startup, and vents the condenser steam space after turbine trips. Major Components The Condenser Air Extraction System shall consist of two identical equipment skids. Each skid shall include the following major components: One full capacity two stage condensing steam jet air ejector assembly designed for holding operation. One full capacity condenser exhauster vacuum pump designed for hogging operation, including: o Vacuum pump. o Separator tank. o Seal water cooler. o Seal water recirculation pump. Piping, valves, controls, and instrumentation necessary for proper system operation. General Description The Condenser Air Extraction System shall consist of two identical equipment skids. Each skid shall contain one two stage dual element steam jet air ejector package designed for holding operation, a separate electric motor driven hogging vacuum pump assembly, and the interconnecting piping between the condenser and the air ejector package. Each dual element steam jet air ejector package shall consist of two 100% first stage air ejectors, two 100% second stage air ejectors, one 200% capacity intercondenser, one 200% aftercondenser, and associated piping and valves. Each hogging vacuum pump assembly shall consist of one large capacity Source: 01630, 2005 System Descriptions Page 38 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 vacuum pump discharging to atmosphere through a separator and silencer. A motor operated condenser vacuum breaker valve shall be located on the condenser shell. This valve shall be sized in accordance with the steam turbine manufacturer’s requirements. The hogging system must be able to draw the condenser pressure down from atmospheric to 10 inches HgA in not more than 15 minutes. The vacuum pump shall compress the non-condensable gases and discharge the gases to a separator at a pressure slightly above that of atmospheric pressure. Any entrained moisture discharged from the condenser vacuum pump shall be collected in the separator and reused as seal water or sent to drain. The dry non-condensable gases shall be vented to atmosphere through a silencer. Materials of Construction Materials of construction for the Condenser Air Extraction System shall be as follows: Piping – ASTM A312 TP304 stainless steel. Valves 2 inch (50 mm) and smaller – Forged steel ASTM A182 F316, socket weld. Valves 2-1/2 inch (65 mm) and larger – CL 150, cast steel ASTM A351 Grade CF8 or CF8M, flanged or welded. Welding codes – W1, W2 Controls and Instrumentation The condenser air extraction system shall have two operating modes: hogging and holding. During startup, the vacuum pump shall be used to evacuate the air from the condenser and rapidly reduce the condenser pressure. The hogging process is done to allow admission of steam to the condenser in as short a time as possible. Holding is the normal operating mode when the pressure in the condenser is maintained below atmospheric pressure. During the holding mode when auxiliary steam is available, the steam jet air ejector package shall remove non-condensable gases from the steam spaces of the condenser. The Condenser Air Extraction System shall be controlled through the DCS. 01630.3.11 Circulating Water (HRC) Function The circulating water system provides cooling water to the steam turbine condenser for condensing the turbine exhaust steam and provides cooling water to the closed cycle cooling water heat exchangers. The circulating water system rejects the steam turbine exhaust heat energy, and steam turbine bypass system heat energy, and heat from auxiliary loads by way of a once through cooling system using sea water. Major Components The circulating water system shall include the following major components: One intake structure. One effluent channel. Two 50 percent capacity, vertical, mixed flow, electric motor driven circulating water pumps with discharge connections above the floor level. Source: 01630, 2005 System Descriptions Page 39 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 One motor operated butterfly valve on the discharge of each circulating water pump and auxiliary cooling water pump. One full capacity, vertical, electric motor driven auxiliary cooling water pump with discharge connection above the floor. Two through-flow traveling screen assemblies with electric motor drives, and screen wash systems for cleaning. Removable bar grates that can be replaced with individual stop log assemblies for each circulating water pump bay. Buried concrete circulating water pipe for both the current and future power blocks. Above ground large diameter steel circulating water pipe. Interconnecting piping, valves, instrumentation, and accessories. General Description Two 50 percent circulating water pumps circulate water from the circulating water pump sump in the sea water intake structure to the condenser and back to the sea via the effluent channel and outfall structure. The intake structure shall be arranged to allow individual pump cells to be taken out of service by installation of a stop log to allow dewatering. Each pump cell shall be provided with a bar screen and traveling screen to protect the pumps and remove debris. A permanent monorail system shall be provided to remove the bar screens and traveling screens for cleaning or maintenance and to install the stop logs. The monorail system shall include an electric hoist designed for the heaviest piece. The intake structure shall be designed to include two future cells for the future circulating water pumps and auxiliary cooling water pump for the future power block. Openings shall be provided in the intake structure of the same size and arrangement as what is provided for the current pumps and the openings shall be permanently covered. The intake structure shall also include two pump cells for use by the LNG Facility Owner. Pump, bar screen, and traveling screen equipment and design details will be provided by the LNG Facility Owner. The effluent channel shall be sized for both the current and future power blocks. The effluent channel shall also be sized to accommodate the discharge water from the LNG Facility at the same time both power blocks are operating. Water flow from the LNG Facility will be approximately 10% the rate of the power plant circulating water system. Exact values will be provided at a later date. A motor operated butterfly valve shall be provided at the discharge of each circulating water pump. Valve opening and closing speed and position shall be determined in accordance with the pump manufacturer’s recommended starting procedure and the Contractor’s water hammer analysis. The auxiliary cooling water pump shall supply 100 percent of the cooling water required for Closed Cycle Cooling Water Heat Exchangers when the circulating water pumps are not operating. The auxiliary cooling water pump shall also be used for filling the circulating water system prior to starting the circulating water pumps. Buried concrete circulating water pipe shall be installed for both the current power block and future power block. The buried pipe for the future power block shall be terminated at grade and the pipe openings shall be covered to allow future connection. A system transient (water hammer) analysis shall be performed on the circulating water system. A circulating water sump flow study shall be performed for large pumps. Since the cooling water supply is the ocean, a thorough analysis of the hydraulic gradient for the system is required. Hydraulic gradients must be determined for low, normal and high levels and at summer and Source: 01630, 2005 System Descriptions Page 40 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 winter water temperatures. Vacuum priming of the condenser water boxes will be required and a fixed or adjustable weir may be required at the outfall to ensure that priming can be maintained under all operating conditions. Vacuum pumps for priming and condenser air extraction shall be supplied with the coldest cooling water available, i.e. circulating or auxiliary cooling water. The system design pressure shall be set based on the circulating water pump shutoff head. The auxiliary cooling water pump shutoff head shall not exceed the circulating water system design pressure unless a relief valve is provided to protect the circulating water system. All vent, drain, and instrument connections shall be furnished with a single valve for isolation. Materials of Construction Circulating water pumps – Super austenitic stainless steels like AL6XN or super duplex stainless steels like Ferralium 255 for the suction bell, bowl, column, impeller, and shaft with cutless rubber bearings. Piping 24 inch (610 mm), above grade - ASTM A53 or A106 Gr. B, with interior dielectric coating (if needed, depending on water quality) Piping > 24 inch (610 mm), above grade - ASTM A139 Gr. B, with interior dielectric coating ( if needed, dependent on water quality) Piping > 24 inch, below grade – AWWA C301 or C303 concrete cylinder pipe, testable joints Valves 2 inch (50 mm) and smaller – Forged steel ASTM A105 Valves 2-1/2 inch (65 mm) and larger – Cast steel ASTM A216 WCB Large Butterfly valves – Cast or ductile iron, rubber lined, rubber or nylon coated discs. Controls and Instrumentation The auxiliary cooling and circulating water pumps shall be controlled by the DCS. All pumps shall be manually started and stopped from the DCS operator interface station. The system shall be fully primed with the auxiliary cooling water pump prior to starting a circulating water pump. Level transmitters mounted on the upper water boxes must detect level in the water boxes as a permissive for starting the circulating water pumps. A pump start command shall initiate opening of the motor operated pump discharge valve with a simultaneous pump start command or with a delayed pump start command depending on the pump manufacturer’s recommendations, and water hammer analysis. Operation of the auxiliary cooling water pump shall be interlocked with the circulating water pumps to prevent it from operating at the same time if the discharge heads are not compatible. 01630.3.12 Heat Recovery Steam Generators (SGA) Function The Heat Recovery Steam Generators (HRSGs) generate steam for power generation using the hot exhaust gas from the Combustion Turbine Generators (CTGs). The HRSGs are horizontal gas flow natural circulating units with integral economizers, evaporators, steam drums, superheaters, reheaters, and attemperators. Major Components Source: 01630, 2005 System Descriptions Page 41 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Three HRSGs shall be furnished as part of the power block. Each HRSG shall include the following major components: High pressure economizers, steam drum, evaporators, superheaters, and attemperators. Reheater and reheat attemperator. Intermediate pressure economizers, steam drum, evaporators, and superheaters. Low pressure economizers, steam drum, evaporators, and superheaters. Low pressure economizer recirculation and bypass system. Inlet duct expansion joints and transition piece. Exhaust expansion joint, breeching, stack, and stack isolation damper. HRSG bypass stack, expansion joints, diverter damper, and damper sealing system. HRSG structure, casing, ductwork, and platforms. A full system of thermal insulation and lagging. Interconnecting piping, valves, instrumentation, and accessories. General Description The HRSGs are triple pressure units with reheat. High temperature exhaust gas from each combustion turbine enters its respective HRSG upstream of the last stage HP superheater/reheater assembly. The gases travel horizontally through the HRSG heating each successive pressure level and then are exhausted through the stack to atmosphere. Emissions are controlled in the CTGs to meet current World Bank emissions standards as specified herein with the CTGs burning both diesel and natural gas. The HRSGs do not include duct burners or SCR systems. Materials of Construction Materials of construction for each HRSG shall be as specified in Section 15511 herein. Controls and Instrumentation HRSG operation shall be controlled by the plant Distributed Control System (DCS). During normal operation, each HRSG shall operate in sliding pressure mode based primarily upon CTG load and ambient conditions. At some reduced load, the steam turbine may be required to control the pressure in order to prevent excessive steam/water velocities, moisture carryover, and other damaging effects in the HRSG at reduced operating pressures. Steam temperature at the outlet of the last stage HP superheater and reheater shall be controlled by interstage spray attemperators. Every effort shall be made to minimize attemperator spray during normal full load operation. 01630.3.13 Boiler Vents and Drains (SGF) Function The Boiler Vents and Drains System collects blowdown and drains from the heat recovery steam generators (HRSGs), economizer drains, evaporator drains, and steam line drains in the HRSG area. HRSG, economizer, evaporator, and steam line drains shall be routed to the HRSG blowdown tanks where flashing steam is separated from the water at near atmospheric pressure. The water collected in the blowdown tanks is quenched and routed to the cycle makeup treatment system (WTD) recycle tank. Steam produced from flashing drains is vented to the atmosphere. Major Components Source: 01630, 2005 System Descriptions Page 42 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The Boiler Vents and Drains System shall include the following major components: One vertical blowdown tank for each HRSG. One quench water control valve for each blowdown tank. Interconnecting piping, valves, instrumentation, and accessories. General Description HRSG drains and steam line drains in the HRSG area, that operate during plant startup and operation shall be piped to drain headers that run to the blowdown tanks. Continuous, intermittent, and startup blowdown lines from the HP and IP drums shall be individually piped to the blowdown tank. Hot drains entering the blowdown tanks partially flash to steam. The steam is vented to atmosphere and the liquid is drained to the plant cycle makeup treatment system. Drain inlets shall be mounted tangentially to the tanks to provide cyclonic separation of the steam and liquid phases of the drains. Chrome alloy steel wear plates shall be provided on the interior of the tanks at the same elevation as the tangential drain connections. Though vented to the atmosphere, the tanks shall be designed in accordance with ASME Section VIII, Div. 1, for 100 psig (690 kPa) design pressure and 650 degrees F (345 degrees C) design temperature. Chrome alloy piping shall be used for at least 20 diameters downstream of the blowdown valves. A temperature element and control valve shall be provided to supply service water to the blowdown tank drain line to quench the drains to a temperature of approximately 140 degrees F (60 degrees C). The drain piping shall include a loop seal or mixing chamber that will assure that the temperature control element is always submerged. Materials of Construction Materials of construction shall be as follows: Blowdown Tanks – Carbon steel ASME SA 515, Gr. 70, minimum with internal chrome alloy steel wear plates. Piping 2-1/2 inch (65 mm) and larger - carbon steel, A53 or A106, Gr. B, schedule 80 minimum for pipe upstream of tank. Piping 2 inch (50 mm) and smaller – carbon steel, A53 or A106, Gr. B, schedule 80 minimum. Superheater drain headers – 2.25 CR alloy steel, ASTM A335, Gr. P22 Valves 2-1/2 inch (65 mm) and larger – CL150, cast steel, ASTM A216 WCB, CL150, RF flanged. Valves 2 inch (50 mm) and smaller – CL600, forged steel, ASTM A105, socket weld. Welding Code – W2 Controls and Instrumentation A temperature element monitors the temperature of the blowdown tank drain to the waste water treatment. The temperature signal is displayed on the DCS operator interface stations and is used to control the control valve that adds water to quench the blowdown stream to approximately 140 degrees F (60 degrees C). 01630.3.14 High Pressure Steam (SGG) Function Source: 01630, 2005 System Descriptions Page 43 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The HP Steam System shall deliver superheated steam from the HRSG superheater outlets to the steam turbine stop and control valve(s). The HP steam system shall also supply steam to the steam turbine gland seal system. The HP Steam System shall include the capability to bypass the steam turbine during unit startups, shutdowns, and load rejections. The bypass system capacity shall be 100 percent of the steam produced in the HRSG when the combustion turbine is at base load (guarantee conditions). Major Components The high pressure (main) steam system shall include the following major components: Interconnecting piping, valves and accessories. Flow, temperature and pressure instrumentation. Full capacity steam bypass system. General Description HP steam shall be piped from each HRSG high pressure superheater outlet to a common supply header which shall supply HP steam from each HRSG to the steam turbine and to the steam turbine gland sealing system. The steam lines from each HRSG shall include a turbine bypass system, an isolation valve, and flow, pressure, and temperature measuring devices along with power operated drains (where required). Each of the steam turbine bypass systems shall include a combination pressure reducing and desuperheating valve, or a pressure reducing valve and a separate steam desuperheater. During steam turbine bypass operation, the HP steam shall be conditioned to cold reheat steam conditions and returned to the cold reheat piping ahead of the IP steam tie in to the cold reheat piping and the HRSG reheater inlet. Chrome alloy piping shall be used for at least 40 diameters downstream of the HP bypass desuperheater if the CRH system piping is carbon steel. The HP steam piping shall be provided with a drip leg near the turbine stop valve(s) for removal of condensate from the steam line. Drip legs shall also be provided at all low points in the piping. Condensate collected in the drip legs shall be directed to the HRSG blowdown tank(s) and/or the condenser. HP steam piping shall be designed and tested in accordance with ASME Code for Pressure Piping B31.1, Power Piping. Steam line drains shall be designed in accordance with the ASME Turbine Water Induction Prevention Standard. Materials of Construction Materials of construction shall be as follows: Piping 2-1/2 inch (65 mm) and larger – 9 CR, alloy steel, ASTM A335, Gr. P91, seamless Piping 2 inch (50 mm) and smaller – 9 CR, alloy steel, ASTM A335, Gr. P91 or 2.25 CR, alloy steel, ASTM A335, Gr. P22 Valves 2-1/2 inch (65 mm) and larger – cast steel, ASTM A217 C12A, butt weld ends. Valves 2 inch (50 mm) and smaller – forged steel, ASTM A182, Gr. F22 or ASTM A182 Gr. F91, socket weld. Welding Codes – W1, W2 (refer to Section 01400, Supplemental Q210 for definition) Controls and Instrumentation Source: 01630, 2005 System Descriptions Page 44 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Steam pressures, temperatures and flows shall be transmitted to the DCS and displayed on the DCS operator interface stations. The pressure and temperature compensated steam flow signal shall be used in the HP drum three element level control scheme and the HP bypass valve control scheme. The HP superheater outlet temperatures shall be used for control of the HP steam desuperheater spray control valve. Steam turbine throttle pressure and temperatures shall be monitored in the DCS. Separate instrumentation, provided by the turbine manufacturer, shall be provided to supply this information to the steam turbine control system. Steam pressure shall be used in the control for the HP bypass system. Steam pressure shall also be measured to determine the saturation temperature for the HP steam header. Prior to steam turbine synchronizing and controlling HP header pressure, the HP steam bypass valves shall be controlled to pressure setpoints generated in the DCS. As the pressure rises to the set point, the bypass valve shall modulate open as needed to maintain the HP steam pressure set point. The bypass steam temperature shall be monitored in the DCS and shall be used to control the bypass steam desuperheater outlet temperature. Temperature elements shall be located as far downstream of the desuperheater as possible, but upstream of the bypass tie-in to the cold reheat piping. HP steam bypass desuperheater spray water flow (in the feedwater system) shall be measured in the DCS and used to calibrate the spray flow logic. The HP steam bypass spray control valve, spray block valve and bypass valve shall have closed limit switches indicating closed valve position. The HP steam bypass valve shall have a solenoid operated valve in the air supply that can be energized to allow the control system to modulate the valve and deenergized to close the bypass valve. This provides for an immediate closing of the valve in the event of DCS or positioner failure or in the event of high bypass steam enthalpy, loss of condenser vacuum, or hot reheat path blocked. Temperature elements shall be installed in the HP steam piping drip legs. These temperatures shall be monitored in the DCS. When steam temperatures nearing saturation temperature are detected, the DCS shall alarm this condition and alert the operator to open the associated drain valve. 01630.3.15 Low Pressure Steam (SGH) Function The LP Steam System shall deliver superheated steam from the HRSG LP superheater outlets to the steam turbine admission stop and control valves(s). The LP Steam System shall include the capability to bypass the steam turbine, during unit startups, shutdowns, and load rejections, if required by the Supplier’s design. The bypass system capacity shall be 100 percent of the LP steam produced in the respective HRSG when the combustion turbine is at base load (guarantee conditions). Major Components The low pressure steam system shall include the following major components: Interconnecting piping, valves and accessories. Flow, temperature and pressure instrumentation. Full capacity steam bypass system. General Description Source: 01630, 2005 System Descriptions Page 45 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 LP steam shall be piped from each HRSG low pressure superheater outlet to a common supply header, which shall supply LP steam to the steam turbine. The steam lines from each HRSG shall include a turbine bypass system, a unit isolation valve, and flow, pressure, temperature and level measuring devices along with power operated drains (where required). If LP steam turbine bypass systems are required for the Supplier’s design, each system shall include a pressure reducing valve and a steam desuperheater (or a combination valve/desuperheater) if required to protect condenser. During LP steam turbine bypass operation, the LP steam shall be conditioned to a suitable pressure and temperature and admitted to the condenser. The LP steam piping shall be provided with drip legs at all low points in the piping. Condensate collected in the drip legs in the steam turbine area shall be directed to the condenser. Condensate collected in the drip legs elsewhere shall be directed to the HRSG blowdown tank(s) and/or the condenser. The steam bypass piping downstream of the desuperheater shall be well drained (sloped all the way to the condenser) or provided with low point drip legs with dual level switches and power operated drain valves. Materials of Construction Materials of construction shall be as follows: Piping 2-1/2 inch (65 mm) and larger – Carbon steel, ASTM A53 or A106, Gr. B Piping 2 inch (50 mm) and smaller – Carbon steel, ASTM A53 or A106, Gr. B Valves 2-1/2 inch (65 mm) and larger – Cast steel, ASTM A216 WCB, flanged or butt welded ends Valves 2 inch (50 mm) and smaller – Forged steel, ASTM A105, socket weld: gate, globe, or ball style Welding Codes – W1, W2 (refer to Section 01400, Supplemental Q210 for definition) Controls and Instrumentation Steam pressures, temperatures and flows shall be transmitted to the DCS and displayed on the DCS operator interface stations. The pressure and temperature compensated steam flow signal shall be used in the LP drum three element level control scheme and the LP steam bypass valve control scheme. LP steam turbine admission pressure and temperatures shall be monitored in the DCS. Separate instrumentation, provided by the turbine manufacturer, shall be provided to supply this information to the steam turbine control system. Level switches shall be installed in the steam piping drip legs. The level switches shall be monitored in the DCS. When water is detected, the DCS shall alarm this condition and automatically open the associated drain valve. On the drip leg on the LP steam common header, a second (high-high) level switch shall be provided for DCS alarming of further increase in level above the high level alarm level. LP steam bypass desuperheater flow (from the condensate system) shall be monitored in the DCS and used to calibrate the spray flow logic. LP steam piping shall be designed and tested in accordance with ASME Code for Pressure Piping B31.1, Power Piping. Steam line drains shall be designed and operated in accordance with ASME TDP-1 (Recommended Practices for the Prevention of Water Damage to Steam Turbines used for Electric Power Generation). The LP steam bypass spray control valve, spray block valve and bypass valve shall have limit switches indicating closed valve position. Source: 01630, 2005 System Descriptions Page 46 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The temperature elements in the LP steam bypass lines to the condenser shall be located as close to the condenser as is practical. The LP steam bypass valves shall have a solenoid operated valve in the air supply that can be energized to allow the control system to modulate the valve and de-energized to close the bypass valve. This provides for an immediate closing of the valve in the event of DCS or positioner failure or in the event of high bypass steam enthalpy or loss of condenser vacuum. 01630.3.16 Hot Reheat Steam (SGJ) Function The Hot Reheat Steam System shall return reheated steam (Hot Reheat Steam) from the HRSGs to the reheat stop and control valves of the steam turbine. The Hot Reheat Steam system shall include the capability to bypass the steam turbine, during unit startups, shutdowns, and load rejections. The bypass system capacity shall be 100 percent of the sum of the cold reheat steam from the HP steam turbine (or HP steam bypass) and the IP steam produced when the associated combustion turbine is at base load (guarantee conditions). Bypass steam shall be conditioned and dumped into the condenser. Major Components The reheat steam system shall include the following major components: Interconnecting piping, valves, and accessories. Flow, temperature, and pressure instrumentation. Full capacity steam bypass system. General Description Reheat steam from each HRSG shall be piped to a common header, which shall return the hot reheat steam to the steam turbine reheat stop and control valve(s). The hot reheat steam line from each HRSG shall include a reheater safety valve, a turbine bypass system, an isolation valve, and instrumentation for temperature and pressure. Each of the steam turbine bypass systems shall include a combination pressure reducing and desuperheating valve, or a separate pressure reducing valve and a steam desuperheater. During steam turbine bypass operation, the hot reheat steam shall be conditioned to a pressure and temperature suitable for admission to the condenser. The hot reheat steam piping shall be provided with drip legs at all low points in the reheat piping. Condensate collected in the drip legs shall be directed to the HRSG blowdown tank (s) and/or the condenser. Chrome alloy pipe shall be used for the first 40 diameters downstream of the bypass valve. The steam bypass piping downstream of the desuperheater shall be well drained (sloped all the way to the condenser) or provided with low point drip legs with dual level switches and power operated drain valves. Reheat steam piping shall be designed and tested in accordance with ASME Code for Pressure Piping B31.1. Steam line drains shall be designed and operated in accordance with the ASME Turbine Water Source: 01630, 2005 System Descriptions Page 47 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Induction Prevention standard. Reheater safety valves shall be provided in accordance with the ASME Boiler and Pressure Vessel Code, Section I. Materials of Construction Materials of construction shall be as follows: Piping 2-1/2 inch (65 mm) and larger – 9 CR, alloy steel, ASTM A335, Gr. P91, seamless or ASTM A335, Gr. P22, seamless if appropriate. Piping 2 inch (50 mm) and smaller – 2.25 CR, alloy steel, ASTM A335, Gr. P22. Valves 2-1/2 inch (65 mm) and larger – Cast steel, ASTM A217 C12A, butt weld ends. Valves 2 inch (50 mm) and smaller – Forged steel, ASTM A182, Gr. F22, socket weld. Welding Codes – W1, W2 (refer to Section 01400, Supplemental Q210 for definition) Controls and Instrumentation Steam pressures and temperatures shall be transmitted to the DCS and displayed on the DCS operator interface stations. The reheater outlet temperatures shall be used for control of the reheat steam attemperator spray control valve. Steam turbine hot reheat pressure and temperatures shall be monitored in the DCS. Separate instrumentation, provided by the turbine manufacturer, shall be provided to supply this information to the steam turbine control system. Steam pressure shall be used in the control of the hot reheat bypass system. The hot reheat steam bypass valves shall be controlled to pressure setpoints generated in the DCS. As the pressure rises to the set point, the bypass valve shall modulate open as needed to maintain the hot reheat steam pressure set point. The bypass steam temperature and pressure shall be monitored in the DCS and used to control the bypass steam desuperheater outlet enthalpy for condenser protection. Temperature elements shall be installed in the hot reheat steam piping drip legs. These temperatures shall be monitored in the DCS. When steam temperatures nearing saturation temperature are detected, the DCS shall alarm this condition and alert the operator to open the associated drain valve. The hot reheat steam bypass desuperheater flow (in the condensate system) shall be monitored in the DCS and used to calibrate the spray flow logic and to monitor possible water flow into an idle bypass line. The hot reheat bypass spray control valve, spray block valve and the bypass valve shall have limit switches indicating closed valve position. The temperature elements in the hot reheat steam bypass lines to the condenser shall be located as close to the condenser as is practical. The hot reheat steam bypass valve shall have a solenoid operated valve in the air supply that is energized to allow the control system to modulate the valve and is de-energized to close the bypass valve. This provides for an immediate closing of the valve in the event of DCS or positioner failure or in the event of high bypass steam enthalpy or loss of condenser vacuum. 01630.3.17 Cold Reheat Steam (SGK) Function The Cold Reheat Steam System shall return exhaust steam (Cold Reheat Steam) from the high pressure steam turbine to the HRSG reheaters. Source: 01630, 2005 System Descriptions Page 48 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Major Components The cold reheat steam system shall include the following major components: Interconnecting piping, valves and accessories. Flow, temperature, level and pressure instrumentation. General Description Cold reheat steam shall be piped from the high pressure turbine exhaust connection through a common line that includes safety valves and then splits to the reheaters at each HRSG. The cold reheat return line to each HRSG shall include an isolation valve, a flow balancing control valve, reheater safety valves and instrumentation for flow, temperature, level, and pressure. The flow balancing valves shall be suitable for maintaining appropriate return steam flow back to each HRSG. The cold reheat system shall also receive steam from the HP steam turbine bypass systems. The bypass steam shall be conditioned to cold reheat temperature and pressure and then admitted to the cold reheat piping upstream of the IP steam connection from the HRSG to the cold reheat piping. The cold reheat steam piping shall be provided with drip legs at low points in the piping for removal of condensate from the steam lines. Condensate collected in the drip legs shall be directed to the HRSG blowdown tank(s) and/or the condenser. Cold reheat steam piping shall be designed and tested in accordance with ASME Code for Pressure Piping B31.1. Steam line drains shall be designed and operated in accordance with the ASME Turbine Water Induction Prevention standard. Cold reheat piping safety valves or rupture disk(s) shall be in accordance with ASME Boiler and Pressure Vessel Code, Section VIII. Reheater safety valves shall be in accordance with the ASME Boiler and Pressure Vessel Code, Section I. Materials of Construction Materials of construction shall be as follows: Piping 2-1/2 inch (65 mm) and larger – Carbon steel, ASTM A53 or A106, Gr. B seamless; or ASTM A335, Gr. P11 or P22 for alloy application. Piping 2 inch (50 mm) and smaller – Carbon steel, ASTM A53 or A106, Gr. B, seamless; or A335, Gr. P22 for alloy applications. Valves 2-1/2 inch (65 mm) and larger – Cast steel, ASTM A216 WCB, or ASTM A217, Gr. WC9 for alloy butt weld end. Valves 2 inch (50 mm) and smaller – Forged steel, ASTM A105, or, ASTM A182, Gr. F22 for alloy socket weld. Welding Codes – W1, W2 (refer to Section 01400, Supplemental Q210 for definition) Controls and Instrumentation Steam pressures, temperatures and flows shall be transmitted to the DCS and displayed on the DCS operator interface stations. The pressure and temperature compensated HRSG IP steam flow signal shall be used in the IP drum three element level control scheme. Steam turbine exhaust pressures and temperatures shall be monitored in the DCS. The steam flow to each HRSG shall be measured, pressure and temperature compensated, and the cold reheat flow control valves modulate to control the cold reheat steam flows in proportion to the individual HRSG steam flow contributions. Level switches shall be installed in the steam piping drip legs. The level switches shall be monitored in the DCS. When water is detected, the DCS alarms this condition and automatically opens the associated Source: 01630, 2005 System Descriptions Page 49 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 power operated drain valve. On the drip leg on the cold reheat steam common header, a second (highhigh) level switch shall be provided for DCS alarming of further increase in level above the high level alarm/interlock level. Special attention shall be paid to predicted performance at low load operating conditions, such as startup or one combustion turbine operating at part load with the steam turbine on line. These conditions can result in high cold reheat steam temperatures (greater than 775 F) which require the selection of chrome alloy piping for the cold reheat line. 01630.3.18 Steam Turbine Vents and Drains (SGL) Function The Steam Turbine Vents and Drains System collects leak off, blowdown, and drains from the steam turbine and the steam turbine area. Drains shall be routed to the turbine area drains tank where flashing steam is separated from the water at near atmospheric pressure. The water collected in the blowdown tanks is quenched and routed to the cycle makeup treatment system (WTD) recycle tank. Steam produced from flashing drains is vented to the atmosphere. Major Components The Steam Turbine Vents and Drains System shall include the following major components: One vertical blowdown tank. One quench water control valve. Interconnecting piping, valves, instrumentation, and accessories. General Description Steam turbine drains and steam line drains in the steam turbine area that operate during plant startup and operation shall be piped to drain headers that run to the blowdown tank. Hot drains entering the blowdown tank partially flash to steam. The steam is vented to atmosphere and the liquid is drained to the cycle makeup treatment system. Drain inlets shall be mounted tangentially to the tank to provide cyclonic separation of the steam and liquid phases of the drains. Chrome alloy steel wear plates shall be provided on the interior of the tanks at the same elevation as the tangential drain connections. Though vented to the atmosphere, the tanks shall be designed in accordance with ASME Section VIII, Div. 1, for 100 psig (690 kPag) design pressure and 650 degrees F (345 degrees C) design temperature. A temperature element and control valve shall be provided to supply service water to the blowdown tank drain line to quench the drains to a temperature of approximately 140 degrees F (60 degrees C). The drain piping shall include a loop seal or mixing chamber that will assure that the temperature control element is always submerged. Materials of Construction Materials of construction shall be as follows: Blowdown Tanks – Carbon steel ASME SA 515, Gr. 70, minimum with internal chrome alloy steel wear plates. Piping 2-1/2 inch (65 mm) and larger - carbon steel, A53 or A106, Gr. B, schedule 80 minimum for pipe upstream of tank. Piping 2 inch (50 mm) and smaller – carbon steel, A53 or A106, Gr. B, schedule 80 minimum. Source: 01630, 2005 System Descriptions Page 50 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Superheated steam drain headers – 2.25 CR alloy steel, ASTM A335, Gr. P22 Valves 2-1/2 inch (65 mm) and larger – CL150, cast steel, ASTM A216 WCB, CL150, RF flanged. Valves 2 inch (50 mm) and smaller – CL600, forged steel, ASTM A105, socket weld. Controls and Instrumentation A temperature element shall monitor the temperature of the blowdown tank drain to the cycle makeup treatment system. The temperature signal shall be displayed on the DCS operator interface stations and shall be used to operate the control valve that adds water to quench the blowdown stream to approximately 140 degrees F (60 degrees C). 01630.3.19 Steam Turbine Generator (TGA) Function The Steam Turbine Generator (STG) generates electric power using high pressure, reheat, and low pressure steam produced in the three Heat Recovery Steam Generators (HRSGs). The STG shall be an electric utility grade unit designed specifically for combined cycle service. Major Components Each Steam Turbine Generator shall include the following major components: Complete steam turbine with high pressure, intermediate pressure, and low pressure sections Hydrogen or air cooled generator Turbine control system Control and monitoring equipment Protective relay panels Lube oil conditioning system Turbine enclosure with sound attenuation A full system of thermal insulation and lagging. Interconnecting piping, valves, instrumentation, and accessories. General Description The STG shall consist of high pressure, intermediate pressure, and low pressure sections designed specifically for combined cycle service. The STG shall be a condensing unit with single or dual flow downward exhaust. High pressure steam shall enter the HP turbine through one or more main steam stop and control valves. The exhaust of the HP turbine shall return steam to the cold reheat inlets of the HRSGs. Hot reheat steam from the HRSGs will combine and enter the intermediate pressure steam turbine through reheat stop/control valves. The exhaust of the IP turbine section shall be ducted to the inlet of the low pressure turbine(s) and then discharged to the steam surface condenser. Low pressure steam from LP section of the HRSGs shall be admitted to the low pressure turbine section through LP steam admission stop and control valves furnished by the steam turbine manufacturer. Materials of Construction Materials of construction for the STG shall be as specified in Section 15561 herein. Controls and Instrumentation Steam Turbine Generator operation shall be controlled by STG manufacturer’s dedicated control system. The plant Distributed Control System (DCS) will have supervisory control and monitoring functions that fully replicate the manufacturer’s control system operator interface. During normal operation, the STG Source: 01630, 2005 System Descriptions Page 51 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 shall operate in sliding pressure mode based primarily upon CTG/HRSG load and ambient conditions. At some reduced load, the steam turbine may be required to control the pressure in order to prevent excessive steam/water velocities, moisture carryover, and other damaging effects in the HRSGs at reduced operating pressures. A steam turbine bypass system shall be provided as described elsewhere herein. Special provisions shall be included to prevent the admission of water into the steam turbine during operation. These provisions shall be in accordance with either the current edition of ASME TDP-1 or the standards of the STG manufacturer, whichever is more stringent. 01630.3.20 Combustion Turbine Generators (TGH) Function Three (3) Combustion Turbine Generators (CTGs) produce shaft power to generate electricity and produce hot exhaust gases that are used to produce steam for power generation in the Heat Recovery Steam Generators (HRSGs). Major Components Each Combustion Turbine Generator shall include the following major components: “F” Class CTG machine complete with a full complement of auxiliary equipment, enclosures, walk-in compartments, and controls. Inlet filter silencer. Thermal insulation and lagging. Interconnecting piping, valves, instrumentation, and accessories. General Description The CTGs shall be manufacturer’s standard “F” Class machines designed for dual fuel operation in a combined cycle configuration. Each CTG shall be a regularly manufactured unit with a proven history of superior reliability, maintainability, and performance in a power plant environment. Exhaust emissions shall be controlled in the CTGs to meet current World Bank emissions standards as specified herein when burning both diesel and natural gas. Materials of Construction Materials of construction for each CTG shall be as specified in Section 15562 herein. Controls and Instrumentation Combustion Turbine Generator operation shall be controlled by CTG manufacturer’s dedicated control system (if separate from the DCS). If separate from the manufacturer’s dedicated control system, the DCS shall have full supervisory control and monitoring capability as specified in Section 17101 herein. 01630.3.21 Fire Protection Water Supply and Storage (WSE) Function The Fire Protection Water Supply and Storage System receives water from the desalination plant and stores it in the Fire Water Storage Tank and Service/Fire Water Tank. Full capacity fire water pumps, one electric motor driven and one diesel engine driven, and one electric motor driven pressure maintenance Source: 01630, 2005 System Descriptions Page 52 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 pump, supply fire water under pressure to the Site Fire Protection System, which includes fire hydrants and fixed water suppression systems. Major Components The Fire Protection Water Supply and Storage System shall include the following major components: One electric motor driven fire pump. One diesel engine driven fire pump. One diesel storage tank. One pressure maintenance pump. Interconnecting piping, valves, instrumentation, and accessories. One combined service/fire water storage tank with 250,000 gallons (946,000 litres) net capacity for service water and a sufficient net reserve capacity of fire water to meet applicable Code requirements. In no case shall the reserve fire water storage capacity be less than 250,000 gallons (946,000 litres) net. Minimum total net tank capacity is therefore 500,000 gallons (1,892,000 litres). The fire water storage volume shall be protected by a standpipe so that it cannot be used by the service water system. One fire water storage tank with sufficient net capacity to meet applicable Code requirements. In no case shall the fire water storage capacity be less than 250,000 gallons (946,000 litres) net. General Description Each fire pump shall be a full capacity, horizontal, double suction, horizontal split case style pump. One shall be electric motor driven and the other shall be diesel engine driven. The fire pumps shall be of cast iron, bronze fitted construction. Each pump shall be furnished with a pump control panel that senses pressure in the fire system and starts the pump when the fire system pressure falls below the set pressure. The pressure maintenance pump shall be full capacity, electric motor driven, and of cast iron bronze or stainless fitted construction. The pump shall be furnished with a pump control panel that senses pressure in the fire system and starts the pump when the fire system pressure falls below the set pressure. A recirculation line which branches to the Fire Water Storage Tank and the Service/Fire Water Storage Tank, with flow meter, shall be provided for periodic flow testing of the pumps. A diesel storage tank shall be provided to store enough diesel for 12 hours operation of the diesel engine. Fire water flows by gravity from the storage tanks to the suctions of the fire water pumps. Normally the pressure maintenance pump will operate to maintain a pressure in the fire mains above the starting set pressures of the motor and diesel driven fire pumps. When a fire suppression system is actuated, or a hydrant is opened, the pressure maintenance pump cannot maintain pressure in the fire mains, and as the fire main pressure drops, the motor driven fire pump shall start, and if the main pressure continues to fall, the diesel fire pump shall start. The recommendations of NFPA Standard 850 shall be followed. Materials of Construction Fire water pumps – Cast iron casings, carbon steel shafts, bronze impellers and shaft sleeves. Piping – Carbon steel ASTM A53 or A106 Gr. B seam welded. Valves 2 inch (50 mm) and smaller – CL 600, socket weld, forged steel ASTM A105 Source: 01630, 2005 System Descriptions Page 53 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Valves 2-1/2 inch (65 mm) and larger – Class 175 WWP, flanged, cast iron (ASTM A126 Class A or equivalent), with bronze trim (ASTM B61 or equivalent), UL listed / FM approved (Gate and globe valves to be OS&Y) Controls and Instrumentation Each fire water pump and the pressure maintenance pump shall be controlled from a local fire pump control panel. The pumps may be started manually or automatically at predetermined pressure setpoints for each pump. Typical starting pressures for the pumps are 135 psig (930 kPa) for the motor driven fire pump and 125 psig (865 kPa) for the diesel driven fire pump. Once started, the fire pumps shall only be shut down from the local panel. Fire pump status shall be indicated remotely on the Fire Alarm Annunciator Panel (FAAP) in the control room. A level switch on the diesel fire pump fuel tank monitors level in the tank and low level shall be alarmed on the FAAP in the control room. 01630.4 Water Management Systems This section contains system descriptions for each of the systems associated with water treatment and use that will be constructed as part of this Project. These system descriptions describe the function, major components, and basis for design for each system. The system descriptions contained within this section are as follows: 01630.4.1 Cycle Chemical Feed (FWE) Steam Cycle Sampling and Analysis (SAC) Service Water (WSC) Potable Water (WSD) Desalination (WTA) Cycle Makeup Treatment (WTD) Waste Collection and Treatment (WWC) Oily Waste Drains (WWD) Cycle Chemical Feed (FWE) Function The function of the Chemical Feed System is to provide conditioning chemicals to minimize corrosion and scale formation throughout the condensate-feedwater-steam cycle for the combined cycle units. The Cycle Chemical Feed System shall be designed to provide water conditioning chemicals to the main steam generator cycle and the auxiliary boiler cycle. Major Components The Cycle Chemical Feed System shall include the following major equipment and components: Two oxygen cylinder manifolds One oxygen feed skid containing two feed systems Ammonia feed skid with local control panel, calibration column, and two full capacity pumps for the main steam cycle Ammonia feed skid with local control panel, calibration column, and two full capacity pumps for the Auxiliary Boiler. Nonvolatile boiler additives could also be fed. Boiler additive feed skid with local control panel, calibration column, and full capacity pump for each pressure level. Associated system piping, valves, instrumentation, and expansion joints. Source: 01630, 2005 System Descriptions Page 54 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 General Description The Cycle Chemical Feed System for the main steam generator cycle consists of three subsystems that operate independently of each other; an oxygen feed subsystem, a boiler additive feed subsystem, and an ammonia feed subsystem. These subsystems are designed to minimize corrosion and corrosion product transport in the steam cycle. An ammonia solution shall be fed downstream of the condensate polisher and to the Auxiliary Boiler. The solution is used for pH adjustment and shall be added as required to maintain a condensate pH within the selected range of 9.2 to 9.6 at full flow. Ammonia shall also serve as the primary pH control for the HRSG’s. Oxygen is used as a part of oxygenated treatment (OT) to minimize corrosion and corrosion product transport. There shall be provisions to feed at two points; the first is located downstream of the condensate polisher and the second is located at the LP drum outlet. The oxygen feed equipment consists of three subsystems; storage equipment (oxygen cylinders), oxygen feed skid (pressure regulator, rotameter, control valve, and shutoff valves), and injection equipment (injection nozzle, local isolation check valve, and relief valve). A boiler additive system shall be used to feed sodium hydroxide in “trace caustic” mode to the LP, IP, and HP drums. Materials of construction Oxygen cylinder manifolds - 316 stainless steel Oxygen feed piping and accessories - 316 stainless steel Ammonia feed pumps, piping and accessories - 304 stainless steel Boiler additive feed pumps, piping and accessories - 316 stainless steel Instrumentation and controls Each chemical feed system shall be operated from local panels with feed rate set by the DCS. The ammonia feed system shall be designed to feed the ammonia solution to maintain the pH (as measured by specific conductance) of the boiler feed water between 9.2 and 9.6. Ammonia feed to the Auxiliary Boiler shall be manually controlled. Oxygen is fed in proportion to condensate and boiler feed pump flow and biased by downstream oxygen residual to achieve the selected oxygen concentration (30 to 50 ppb). The oxygen feed system shall be interlocked to shut off oxygen feed at high cation conductivity levels, high oxygen level in the HRSG downcomer, and also at low load. The boiler additive system shall be configured to operate based on a manual set point via the DCS. 01630.4.2 Steam Cycle Sampling and Analysis (SAC) Function The function of the Steam Cycle Sampling and Analysis System is to provide a means to monitor the performance and operation of the steam-condensate-feedwater cycle, to monitor the quality of various process fluids, and to provide sufficient data to operating personnel for detection of any deviations from control limits so that corrective action can be taken. Major Components Source: 01630, 2005 System Descriptions Page 55 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The Steam Cycle Sampling and Analysis System shall consist of the following major components: One sample panel enclosure located in the Turbine Building. One sample chiller. General Description The sample panel shall serve the entire power block. The panel is divided into four sections. These include a primary cooling rack, a sample conditioning side, an analyzer section and a dry section. The sample panel obtains samples for analysis from the following points of the steam-condensatefeedwater cycle: Cycle water makeup. Condensate pump discharge. Individual Cation and Mixed Bed Condensate Polisher Effluent Samples Condensate after chemical feed. High-, intermediate-, and low-pressure drum boiler water of each HRSG. High-, intermediate-, and low-pressure drum saturated steam of each HRSG. Hot reheat steam of each HRSG. High-pressure superheat steam of each HRSG. These samples are routed to the sample panel, which provides temperature and pressure conditioning and performs automatic analyses of the samples. The primary cooling rack provides the following functions: Receives all samples. Provides blowdown of all samples to waste. Provides primary cooling of all boiler water and steam samples. The sample conditioning section provides the following functions: Regulates flow of all samples. Provides secondary cooling of all high purity samples. Provides safety relief for overpressure protection of all downstream equipment for all samples. Provides pressure control and indication for all samples. Provides temperature indication for all samples. Provides for measurement of specific conductance, cation conductivity, dissolved oxygen, sodium, silica, and pH of selected sample streams. Provides control and indication of sample flow rates to each analyzer. Provides grab samples for each sample. Provides high temperature protection of all analyzers with the use of high temperature shutoff valves. Provides cooling water safety relief for overpressure protection of each sample cooler of the boiler water and steam samples. Provides drainage to waste for all sample streams and discharges from all analyzers. Provides demineralized flush water for all analyzers/probes during a plant shutdown or for analyzer calibration. The analyzer section of the sample panel provides the following functions: Transmits measurement signals of dissolved oxygen, sodium, and silica, from the sample conditioning section of the sample panel to the dry section. Provides sample sequencers, capable of controlling and varying the sequence schedule independently to each analyzer for all samples sharing analyzers. The dry section of the sample panel provides the following functions: Transmits and indicates measurement signals of specific conductance, cation conductivity, dissolved oxygen, sodium, silica, and pH to the plant Distributed Control System (DCS) for recording, data acquisition, and data storage. Houses all electrical and control components associated with the sampling system. Source: 01630, 2005 System Descriptions Page 56 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The sample panel shall be located in the Turbine Building. The sampling area shall include a safety shower and fume hood and shall have provisions for wet testing of the samples. The sample panel is designed to condition the samples before analysis. First, the samples pass through the primary cooling rack, located outside the polisher regeneration building. The primary cooling rack includes primary coolers, isolation valves, and blowdown valves. The samples flow through the tube side of the primary coolers where the majority of heat removal occurs. Closed cycle cooling water is used on the shell side of the coolers. Final cooling takes place when the samples pass through the secondary coolers. These coolers are similar to primary coolers, except that chilled water is provided by the secondary sample chiller for sample cooling. The secondary sample chiller maintains the chilled water at an adjustable set point and within a narrow range. Conditioned samples are sent to pH and conductivity cells, sodium analyzers, and silica analyzers. Flow to each analyzer branch is controlled and indicated on the flow indicators. Flow indicators should be set to maintain 500 to 1300 mL/min, sufficient to supply inline instrumentation and grab samples. Flow adjustment shall be done by adjusting the appropriate needle valve. Grab samples can be taken at any time for laboratory analysis. Materials of construction Metallic, wetted materials (valves, panel tubing, etc)* - 316 SS Non-metallic items (conductivity cells, ph probes, etc) - manufactures standard Panel face - painted 20 gauge carbon steel Sample panel trough - 304 SS Sample lines* - 316 SS *Hot Reheat Steam and Superheat Steam shall be 316H SS until after the primary sample cooler. Controls and Instrumentation The Steam Cycle Sampling and Analysis System shall be controlled manually from the sample panel. All analyzed parameters shall be transmitted to the DCS. If sequencers are used, then each sequencer shall provide signals to the DCS to indicate which sample is currently active and the DCS shall hold all other sample values at their last good value (or each sequencer shall provide separate sample signals to the DCS, each of which is held at the last good value when not active). Where sample lines are shared and selected manually, the DCS will be able to distinguish which sample is being fed to the analyzer Alarms generated by the Steam Cycle Sampling and Analysis System are annunciated in the control room and displayed on the DCS operator workstation. To protect system equipment, protective actions shall be automatically taken if certain system components malfunction. Protective actions include the following: High Temperature Protection--The high temperature shutoff valves close on high temperature to protect the associated equipment. High Pressure Protection--The safety relief valves open on high pressure to protect the associated equipment. During a loss of flow condition, the associated sample line shall be automatically flushed with demineralized water to protect probes and analyzers. 01630.4.3 Service Water (WSC) Function Source: 01630, 2005 System Descriptions Page 57 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 The Service Water System receives service water from the desalination plant, the wastewater treatment, or the back-up city water supply and stores it in the Service/Fire Water Storage Tank. The service water is distributed for the following uses. HRSG blowdown tank cooling. Steam turbine area drains tank cooling. Miscellaneous service water users throughout the plant. Component Description The Service Water System shall include the following major components: Two full capacity, horizontal, end suction, electric motor driven, service water pumps. Interconnecting piping, valves, instrumentation, and accessories. General Description The Service Water System shall consist of two service water pumps, associated piping, valves and instrumentation. The service water pumps shall be of cast iron and bronze fitted. The pumps shall have recirculation lines back to the Service/Fire Water Tank, with flow control orifices, to provide minimum flow protection for the pumps. Service water is supplied to the service water pumps from the Service/Fire Water Storage Tank through an aboveground suction line. The pumps deliver service water to various users throughout the plant. All service water piping shall be carbon steel. All miscellaneous vent, drain, and instrument connections shall be furnished with a single ball or globe valve for isolation. Materials of Construction Service water pumps – Cast iron construction, bronze fitted. Piping – ASTM A53 Grade B ERW Valves 2 inch (50 mm) and smaller – CL 600, forged steel ASTM A105, socket weld Valves 2-1/2 inch (65 mm) and larger – CL 150, cast iron, flanged Welding codes – W1, W2 Controls and Instrumentation The service water pumps are controlled by the DCS. When required, one pump shall be started in manual mode, and the other shall be in standby mode to automatically start in the event that the running pump trips or header pressure becomes low. A level transmitter on the Service/Fire Water Storage Tank monitors level in the tank and the level is displayed on the DCS operator interface stations. The tank level signal shall be used to provide high and low level alarms, and interlocks for pump operation. A pressure transmitter monitors the service water pump discharge header, the pressure shall be displayed on the DCS operator interface stations, and shall be used for start of the standby pump if one pump is running and header pressure is low. Pressure shall be monitored on each service water pump suction or discharge. Source: 01630, 2005 System Descriptions Page 58 of 65 ESKOM COEGA CCGT 144807.71.0201 01630.4.4 WORKS INFORMATION EMPLOYER REVIEW 20October06 Potable Water (WSD) Function The Potable Water System draws water from the Service/Fire Water Storage Tank, treats the water to make it suitable for potable water uses and provides it to the Potable Water Storage Tank. Potable water supply pumps deliver water from the storage tank to building services, safety showers, and other miscellaneous users. Major Components The Potable Water System shall include the following major components: One Potable Water Storage Tank with a minimum size of 75,000 litres. Two full capacity Potable Water RO Feed Pumps. One packaged Reverse Osmosis (RO) unit. Hypochlorite, caustic, and soda ash injection systems. Two full capacity Potable Water Supply Pumps. Interconnecting piping, valves, instrumentation, and accessories. General Description Potable water is supplied to the Potable Water Storage Tank through an aboveground line from the Service/Fire Water Storage Tank using the Potable Water RO Feed Pumps and RO unit in the Water Treatment building. The Potable Water Pumps shall be horizontal, end suction, electric motor driven pumps and shall have recirculation lines to provide minimum flow protection for the pumps. The Potable Water Storage Tank minimum size shall be sized to accommodate the full complement of Employer staff along with all coincident miscellaneous uses. The tank shall be coated internally with an epoxy coating system suitable for immersion in potable water. The tank shall be equipped with a vent and air filter and piping inlet, outlet, overflow, drain, instrument connections, and corrosion control prevention for exterior tank bottom plates. All miscellaneous vent, drain, and instrument connections shall be furnished with a single ball or globe valve for isolation. The Potable Water System shall be designed and controlled to ensure that adequate water supply pressure is maintained for all users at all times. Materials of Construction Potable Water Pumps – All wetted parts of stainless steel construction. Piping, valves, and all other components exposed to potable water shall be metallic and shall be certified for drinking water service in accordance with NSF/ANSI-61 or approved equivalent standard. Controls and Instrumentation The Potable Water Pumps shall be controlled from the DCS operator stations. When required, one pump shall be started in manual mode, and the other shall be in standby mode to automatically start in the event that the running pump trips or header pressure becomes low. Source: 01630, 2005 System Descriptions Page 59 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 A level transmitter on the Potable Water Storage Tank monitors level in the tank and the level shall be displayed on the DCS operator interface stations. This level indication shall also provide high and low level alarms and interlocks for pump operation. A pressure transmitter shall monitor the potable water discharge header. The pressure shall be displayed on the DCS operator interface stations and used for start of the standby pump if one pump is running and header pressure is low. Pressure shall be monitored on each potable water pump suction and discharge. Flow metering for water supplied to the plant shall be measured with a mag-flow type flow meter complete with flow integrator. The accuracy of this mag-flow meter shall be 0.5%. A second, identical, independent mag-flow meter with integrator shall provide back-up redundancy. Water users within the plant shall be metered with mag-flow type flow meters complete with flow integrator and accuracy of 1%. 01630.4.5 Desalination (WTA) Function The Desalination system shall be comprised of two water treatment processes: Sea Water Reverse Osmosis Pretreatment, and Sea Water Reverse Osmosis. The function of the Desalination system is to produce water of sufficient quantity and quality to satisfy all plant fresh water needs including feed for the demineralization system. Component Description The Desalination system consists of the following major components and ancillary systems: Dissolved Air Flotation (DAF) equipment Solids Processing equipment Ultrafiltration (UF) equipment Cartridge Filter equipment Sea Water Reverse Osmosis (SWRO) equipment Chemical Injection Systems General description The Sea Water Pretreatment process, referred to as Dissolved Air Flotation (DAF), shall consist of rapid mix, flocculation and flotation processes. These processes together agglomerate particles into larger particles and remove them from the water. The flotation process is preferred over a sedimentation process since oil and grease and high concentrations of organic material could be present in the source water. Clarified water from DAF is filtered through UF membranes, which is then desalinated by the Sea Water Reverse Osmosis process. Raw water from the ocean shall be dosed with sodium hypochlorite whenever required and blended with effluent from the wastewater system and supplied to the rapid mixing tank. Sodium hypochlorite is dosed after the raw water screens to prevent biofouling within the downstream processes. The rapid mixer shall be comprised of a concrete chamber with a vertical turbine impeller designed to provide rapid mixing. The concrete chamber shall be coated with appropriate material to negate any corrosive effects of seawater. Water to be treated (raw water from ocean and recycled water from waste treatment system) shall be dosed with sulfuric acid and coagulant as required. Provisions for addition of polymer shall be included for dosing over the rapid mixer outlet weir. The coagulated water flows under gravity to a common inlet chamber of the DAF unit. Flow shall be distributed evenly to two DAF streams. Space shall be set aside for a third DAF stream when the second combined cycle power block is added. Each DAF stream shall be sized at 50% of ultimate capacity. The inlet and outlets of each flocculation stage shall be designed to direct flow diagonally across each chamber from bottom to top to minimize flow short circuiting. An inlet penstock shall be provided to allow Source: 01630, 2005 System Descriptions Page 60 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 each DAF stream to be isolated. Manual drain valves shall be provided on each flocculation chamber to allow draining down of the chamber to the solids processing area. Each flocculation stream shall feed one DAF chamber. Flocculated water enters the DAF unit under a baffle wall at the inlet riser. Recycle water (i.e., filtered water saturated with air under pressure) shall be introduced at the inlet riser via distribution nozzles. The pressure drop across the recycle nozzles causes the air to come out of solution, forming a microbubble air blanket. The DAF recycle system shall consist of two variable speed recycle pumps (one operating, one standby) that draw water from the UF Feed Tank, two air absorber vessels (one operating, one standby), and two air compressors and receivers (one operating, one standby). Flow meters and valves shall be provided to control recycle flow to each DAF stream. The sludge blanket shall be removed either hydraulically or mechanically and shall be initiated automatically after a preset (adjustable) time interval. Mechanical desludging is preferred so that sludge can be sent directly to dewatering, avoiding the necessity of an intermediate clarification step. However, if a hydraulic sludge removal system is provided, an intermediate clarification step shall be included and shall be independent of the clarification step used for membrane filtration backwash treatment. During desludging, the system shall have the ability to automatically spray service water on the DAF walls. DAF sludge shall flow by gravity to the solids treatment area. Pumping to the solids treatment area may be required for high solids concentrations. The clarified water from DAF shall flow to the UF Feed Tank. Water from this tank shall also be used for recycle flow to the DAF system, as described above. The tank shall be provided with level sensors for process control. The UF system shall be a horizontal, pressurized, cartridge type. The Clean-In-Place (CIP) and maintenance wash systems shall be independent, including pumps and necessary chemical tanks. The UF system shall include an integrity testing system to ensure integrity of membrane fibers. Three UF trains shall be furnished. Each train shall be designed for 50% capacity. Space shall be allocated for two identical trains to be added in the future when the second power block is built. The intent is to provide one spare train at all times. It is expected that the number of operating UF units will be same as the number of operating SWRO units. Back washing/ chemically enhanced backwashing shall be on a frequent-timed basis and not based on trans-membrane pressure. The contractor shall determine the feasibility of using SWRO reject as potential source of UF backwash water. The filtrate water from the UF system shall flow to the SWRO Feed Tank. Water from this tank shall be used to feed the SWRO units as well as provide necessary water for UF backwashing. The tank shall be equipped with level sensors. Water from the SWRO Feed Tank shall be pumped through the cartridge filters to the suction side of the high pressure SWRO Feed Pumps. The high pressure pumps shall be provided with a Variable Frequency Drives (VFD). The cartridge filters shall be sized to provide one spare and shall be connected to a common header. Such an arrangement allows change of cartridge elements without having to shutdown the plant. The cartridge filters shall be provided with differential pressure measurement. Cartridge filters shall be disposal type and rated at 5 micron. Sodium bisulfite shall be added downstream of the cartridge filters for dechlorinating feed water since RO membranes are sensitive to chlorine. Acid and antiscalant shall be added upstream of the cartridge filters. Chlorine, ORP and pH monitoring devices shall be installed downstream of cartridge filters, after allowing sufficient mixing of all chemicals added. The effluent from the cartridge filters is pressurized by the High Pressure SWRO Feed Pumps. The water is then treated by a single pass, single stage SWRO. The SWRO shall be comprised of 3 X 50% trains in parallel. Provisions shall also be included for a future increase in capacity. The reject from the SWRO is directed back to the ocean. The SWRO effluent feeds into the Service/ Fire Water Tank and/or the Fire Water Tank. Source: 01630, 2005 System Descriptions Page 61 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Materials of Construction All materials shall be optimally selected to be compatible with the product flows as well as any chemical additions taking place in close proximity of the piece of equipment in question. Controls and Instrumentation The facility is controlled locally by PLCs with supervisory control and monitoring available in the plant DCS . The UF and SWRO processes shall have independent PLCs. Acid addition shall be paced with the pH of clarified water based on the optimal pH required for coagulation. Polymer addition, if required, shall be flow paced, based on a dose selected by the operator through jar testing. Chlorine addition shall be flow paced, based on maintaining a chlorine residual up to the cartridge filters and shall be operator selectable. Sodium bisulfite shall be added to achieve zero chlorine residual. Antiscalant is flow paced, based on a dose selected by operator. 01630.4.6 Cycle Makeup Treatment (WTD) Function The Cycle Makeup Treatment system shall be comprised of two water treatment processes: Brackish Water Reverse Osmosis (BWRO), and Electrodeionization (EDI). The function of the Cycle Makeup Treatment system is to produce water of sufficient quantity and quality to satisfy all plant Deminiralized water needs including HRSG makeup and NOx injection water. Component Description The Desalination system consists of the following major components and ancillary systems: Brackish Water Reverse Osmosis (BWRO) equipment Electrodeionization (EDI) equipment Cartridge Filter equipment Recycle Tank Chemical Injection Systems General description The recycle tank shall act as a point of recovery for drain waters from the HRSG Blowdown Tanks, Turbine Area Drains Tank, and ionized contaminants from Electrodeionization (EDI). The Recycle Tank shall be sized to provide adequate storage capacity for the current combined cycle block as well as the future combined cycle block of similar size. The tank should include enough storage to allow for cyclical operation of the BWRO system while the plant is operating on natural gas. The tank vent shall be designed to release any hydrogen that might become entrained in waste streams to the recycle tank. The cycle makeup treatment system accepts feed water from the service/ fire water tank and/or the recycle tank. The BWRO feed shall travel through cartridge filters, where any large particles are removed. Reverse Osmosis Feed Pumps shall then feed the two-pass, two-stage Brackish Water Reverse Osmosis (BWRO) process. This process shall be designed to minimize reject waters being sent to the Waste Water Recycle Basin (WWRB). Upon entering the first pass, product water shall pass through to the RO 2nd Pass Feed Pumps and reject water shall enter the second stage. Caustic shall be fed between the RO passes to facilitate carbonate removal. Product water from the second stage shall pass through to the RO 2nd Pass Feed Pumps, while any remaining rejects shall be sent to the Wastewater Recycle Basin (WWC). The second pass of the BWRO system shall be of the same arrangement as described for the first pass. Product water from the second pass shall enter the Reverse Osmosis Product Tank, while reject water from the second pass shall be sent to the Wastewater Recycle Basin. The BWRO process Source: 01630, 2005 System Descriptions Page 62 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 shall be designed to supply sufficient flows to keep the plant in operation during regular cleaning and maintenance intervals of the BWRO units. Water from the RO Product Tank is pumped to the Electrodeionization (EDI) skids via the RO Product Pumps. The Electrodeionization units shall continuously remove contaminant ions from the flow steam while continuously being regenerating by way of an electrical current. Contaminant ion flow shall be sent to the Recycle Tank while the Electrodeionization effluent shall be sent to the Demineralized Water Storage Tank. The EDI process shall be designed to supply sufficient flows to keep the plant in operation during regular cleaning and maintenance intervals of the EDI units. Mixed bed exchanger connections shall be supplied downstream of the Electrodeionization units. Materials of Construction All materials shall be optimally selected to be compatible with the product flows as well as any chemical additions taking place in close proximity of the piece of equipment in question. Controls and Instrumentation The facility is controlled locally by PLCs with supervisory control and monitoring available in the plant DCS. The BWRO, and EDI processes shall have independent PLCs. Sodium bisulfite shall be added to achieve zero chlorine residual. Antiscalant is flow paced, based on a dose selected by the operator. Caustic shall be flow paced, based on a dose selected by the operator.. 01630.4.7 Wastewater Collection and Treatment (WWC) Function The Wastewater Collection and Treatment System collects and conveys wastewater originating in the plant to the Dissolved Air Floatation (DAF) Influent. Major Components The Wastewater Collection and Treatment System shall include the following major components: One wastewater collection lift station with two full capacity wastewater transfer pumps sized for the current 3x1 combined cycle block. One wastewater recycle basin sized for both the current and the future combined cycle blocks and with provisions for pumps for the future block. Two full capacity wastewater recycle pumps sized for the current 3x1 combined cycle block. Interconnecting piping, valves, instrumentation, and accessories. General Description The wastewater collection and treatment system shall collect plant and equipment drains in the wastewater collection lift station. Two full capacity wastewater transfer pumps (one operating, one standby) shall pump the wastewater to the wastewater recycle basin. Two full capacity wastewater recycle pumps (one operating, one standby) shall pump the wastewater from the wastewater recycle basin to the DAF influent. All vent, drain, and air user connections shall be furnished with a single valve for isolation. Materials of Construction Materials of construction shall be as follows: Source: 01630, 2005 System Descriptions Page 63 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Wastewater Pumps – Cast iron casings, carbon steel shafts, bronze impellers and shaft sleeves. Piping – Carbon steel ASTM A53 or A106 Gr. B seam welded. Valves 2 inch (50 mm) and smaller – CL 600, socket weld, forged steel ASTM A105 Valves 2-1/2 inch (65 mm) and larger – Class 175 WWP, flanged, cast iron (ASTM A126 Class A or equivalent), with bronze trim (ASTM B61 or equivalent) (Gate and globe valves to be OS&Y) Controls and Instrumentation Monitoring of the wastewater collection station and recycle basin levels shall be provided from the Distributed Control System (DCS). Alarms generated by the Wastewater Collection and Treatment System are annunciated in the control room and displayed on the DCS operator interface stations. 01630.4.8 Oily Waste Drains (WWD) Function The Oily Waste Drains System collects and treats potentially oil-contaminated wastewater originating in the plant and conveys the treated water to the waste water collection lift station. Major Components The Wastewater Collection and Treatment System shall include the following major components: One full capacity fire pump house submersible sump pump. One full capacity fuel oil containment submersible sump pump per CTG and one for STG. Two full capacity condensate trench submersible sump pumps. Two 50 percent capacity stormwater submersible pumps. One stormwater collection lift station. One oil/water separator. One oil analyzer. Interconnecting piping, valves, instrumentation, and accessories. General Description Wastewater is collected from areas where there is potential for oil contamination. These wastes shall be collected by floor drains, piping, trenches, and sumps which shall be routed to the stormwater collection lift station. The stormwater collection lift station shall collect the wastewater and direct the water to the inclined plate oil/water separator. The inclined plate oil/water separator shall be above ground and remove oil contamination by utilizing the specific gravity difference between water and oil. Discharge from the inclined plate oil/water separator shall be routed to the waste water collection lift station. The oil shall be retained for eventual removal and disposal offsite in accordance with the Employer’s regulations. Oil and/or fire protection water shall be captured in the containment area and held there for disposal by others. Containment sized to handle all oil plus 1 hour of fire protection water flow. Materials of Construction Source: 01630, 2005 System Descriptions Page 64 of 65 ESKOM COEGA CCGT 144807.71.0201 WORKS INFORMATION EMPLOYER REVIEW 20October06 Materials of construction shall be as follows: Oily waste drains collection and treatment pumps – Cast iron casings, carbon steel shafts, bronze impellers and shaft sleeves. Piping – Carbon steel ASTM A53 or A106 Gr. B seam welded. Valves 2 inch and smaller – CL 600, socket weld, forged steel ASTM A105 Valves 2-1/2 inch and larger – Class 175 WWP, flanged, cast iron (ASTM A126 Class A or equivalent), with bronze trim (ASTM B61 or equivalent), (Gate and globe valves to be OS&Y) Controls and Instrumentation Monitoring of the Oily Waste Drains System sump levels shall be provided by the Distributed Control System (DCS). Alarms generated by the Oily Waste Drains System shall be annunciated in the control room and displayed on the DCS operator interface stations. Source: 01630, 2005 System Descriptions Page 65 of 65