Engineering Department - North Western Railway

advertisement
Chapter-5
Engineering Department
Anticipate
d Cost
Item
(1050
PH-16- Traffic facilities
works
MD -PNU - Through trap repl.
By 1 : 12 turnout with dead 18.00
end
Expenditu
re
upto
31.03.10
Physical
progress
in %
1
Name of works
PB
No.
11)
Sr. No.
PROGRESS OF WORKS-2009-10
Remarks
0.00
Estimate under sanction
at Hq level
0%
29
Bikaner-remodeling of yard,
BG washing line & sick line 8.16
shed
2.89
30
Lalgarh-Suratgarh-standared
III interlocking, central panel,
23.92
MACLS and block proving by
axle counters etc.
21.92 73%
31
Suratgarh-Bhathinda
standared III interlocking,
central panel, MACLS and 24.96
block
proving
by
axle
counters etc.
12.01 40%
5
32
LGH: Shunting arrangement
for traffic from SOG-LGH 2.5
towards LGH-KLYT side.
-
0%
6
33
LGH: Junction Cabin to
facilitate direct movement of 7.26
trains from SOG side to LGH-
626
%
100%
2
3
4
59
52%
Work of extension of
washing line to make it
for
24
coaches
concreting
completed.
Integrated sick line shed
in progress.
Birdwal,
Rajiyasar,
Piperan,
Arjansar,
Mahajan and Malkisar
stations completed and
commissioned.
S&T
structures
stations
completed at all stations.
Ballast
supply
completed. Pre NI work
of
Nathwana,
Lunkaransar and Dhirera
stations completed. (for
balance 7 stations)
S&T
structures
and
earthwork
completed.
P.Way work
and
material transportation is
in
progress.
Ballast
supply in progress. S&T
tender awarded and
work in progress. (for 2
stations)
Dropped
due
to
commissioing of LGH
bye pass.
Work completed. Bye
pass
line
is
commissioned.
Work
KLYT line.
7
34
8
35
9
38
10
42
can be deleted from PB
2011-12.
LGH-KLYT Crossing station
6.96
at New Bikaner
Bhatinda-conversion
into
crossing station by addl. loop 7.00
line at by pass cabin
Rohtak-Bhiwani-Std.-III
interlocking with central
panel
NACLS
block 11.88
providing by axle counters
etc.
Nal-Gajner
station.
:
Rewari-Hissar
interlocking
New
–
block
0%
5.79
99%
Work completed
commissioned
5.6.10.
0
0%
Detailed estimate under
sanction
at
Railway
Board.
8.39
5.47
100%
37.27
0.01
0%
Std.-III
and
on
Work
completed.
Maintenance
period
completed in May-10.
Final bill shall be passed
by Aug-10. Work can be
deleted from PB-201112.
Detailed
estimate
sanctioned.
Tender
opened on 31.3.10.
Track linking and Pre-NI
work completed. CRS
sanction awaited.
Plan and estimate under
preparation.
11
40
12
41
Bhatinda-B (By pass cabin) –
6.42
By pass line towards Sirsa
3.01
90%
13
48
Bikaner Division - New
14.05
crossing station (2 Nos.)
0
0%
14
28
Rewari - Yard remodelling
56.00
45.25 97%
Work completed.
15
39
Jaipur - Yard remodelling
28.214
1
0.28
Plan under approval.
Estimate sanctioned.
16
17
5%
44
Kanakpura goods shed development as model goods 5.50
terminal.
0.86
7%
47
Malakhera & Digawara
Conversion of 2-line stations
into 3-line with standard- III 5.90
interlocking,
simuttaneous
reception & despatch etc.
0.00
0%
60
Work
awarded
on
27.04.10. Earth work
started. The work of
coping wall of one PF
has been completed &
Excavation of RCC OH
tank completed.
Previously
it
was
decided to do the work
doubling work but as the
doubling work is not
sanctioned it is decided
work will be executed by
the Division. .
Plan
under approval of HQ
from 28.01.10. Estimate
under A/c vetting.
18
25
Jodhpur-Merta
road
Standard III interlocking with 14.89
central panel (10 stations)
12.23 100%
26
Merta road -Phulera Standard
III interlocking with central 19.14
panel (13 stations)
11.18 70%
20
27
MTD
BKN-Std-III
interlocking with central 19.58
panel (11 stations)
0
0%
21
36
Jodhpur - Phulera - Addl loop
6.00
lines(4 Stations)
0.44
80%
22
37
Bhikamkor-Standard-III
interlocking with central panel
6.65
for new block station. (RKBPLC Sec.)
1.00
90%
23
43
Keduli & Naya Kherdia-Addl
4.14
Loop Lines.
0.15
70%
24
45
Phalodi- Bypass line
5.56
0.00
0%
25
46
Mandiya Kalan -New Block
7.67
station. (RKB-PLC Sec.)
0.00
0
19
61
Work completed.
Completed:- 7 Station
out
of
13.
(GVMR,SBR,GA,
KMNC& NAC, MKN &
KQW).
Work in progress at
balance 06 stations.
(BOW, BSRL, NYK,
GCH, REN &JAC).
Work dropped during
2007-08.Work required
by COM under review
Work at JWL, AAS &
KSW
completed.
JAC - work to be done
with Std-III interlocking
work.
Work completed except
NI.
Due
to
non
availability of traffic staff
NI work was not taken.
Work
completed
at
KQW, at NYK to be
done with Std-III.
The estimate for this
work
has
been
sanctioned and tender is
to be invited shortly.
Procurement of material
management is also in
progress.
For
land
acquisition the award is
to be published by
DM/Jodhpur and file is
sent to Forest HQ
foffice, Lucknow.
Plan prepared under
signature at divisional
level.
1
65
29- Road Safety Works – LCs
MD -PNU Interlocking of level
3.6368
crossing gates ( 20 Nos. )
0.00
0%
3.93
100%
Detail
estimate
under
preparation.
Work completed. Final bills
of Sr.DEN/N, W & S
passed. Final bill of
Sr.DEN/E received & will
be passed in June-10.
Work can be deleted from
PB-2011-12.
Engineering work awarded
on 05.04.10. Work at LC
No. 164 & 195 in progress.
S&T
work awarded on
20.04.10 & 30.04.10 &
work in progress.
2
61
Elimination of deficiencies of
road surfaces, speed breakers,
2.66
safety sign boards etc. on 183 LXings over BKN Divn.
3
62
Jaipur Division - Upgradation of
2.90
level crossings ( 7Nos)
0.00
10%
4
58
JU Div-Manning of unmanned
2.68
level crossing (21Nos)
1.06
100%
Work completed.
80%
a) Engg work completed at
20
LCs.
b) One LC closed after
opening
of
ROB.
c) Work of ROB/Limited
height sub way sanctioned
on
03
LCs.
d) Work in progress at 07
LCs.
90%
Work completed.
0
Detailed
estimate
sanctioned.
AII
: NIT issued for
manning works. Proposal
for
creation
of
post
submitted to HQ on
18.5.2010.
BKN Div.: Tender for 42 LXings opened on 25.06.10
offers received for 31 LXings and for 11 L-xings of
Sr.DEN/E
section
no
response, fresh NIT issued
and to be opened on
09.09.10.
JP:
Tnder
under
finalization for 39 LCs.
JU: TENDER OPENED
ON 29.06.10
5
60
Jodhpur Division-Upgradation of
2.96
manned level crossings (31nos.)
6
59
N.W.RLY-Manning
of
level
crossings(51Nos.) (AII-14, BKN - 6.34
17, JP-10 & JU -07 Nos.)
7
63
Manning of Unmanned level
crossings (210 Nos) North
17.6
Western Railway (AII- 14Nos.
BKN-42,JP-39 & JU- 81 )(
62
1.00
0.00
30- Bridge Works (Road Safety Works – ROBs/RUBs)
S.
PB/ LB Nomenclature of works as
Latest
NO Item no. per PB/LB
sanctioned
cost (In Cr.)
1
PB/176 Chouth Ka Barwada 9.8359
Isarda - Re-girdering of
Br.
No.
23.
(30x18.30m)
2
PB/177
2.8678
Sawai Madhopur - Jaipur
- Regirdering of Br. No.06
,
77,
81
(Total
3
Bridges)
Br.
no.
77
(5x18.30m) by steel girder
3
PB/178 MadarPalanpur4.6000
Regirdering
&
strengthening
of
sub
structure (Bridge Nos.
736, 789, 792, 793, 823,
831,
843,
848
)
(Total 8 Bridges)
4
PB/179 Jethi - Chitrasani 5.5860
Regirdering
&
Strengthening of
sub
structure (bridge No. 845)
(6x30.50m) with under
slung super-structure
5
PB/180
6
PB/181
7
PB/182
Hisar-Bhatinda -Suratgarh
strengthening of major
bridge for 30 tones axle
load for upgrading of
feeder route to dedicated
freight
corridor.
Total bridge no. 5
Phulera - Degana - Repl.
of steel girders by prestressed concrete slabs
(bridge Nos 17, 21, 32,
34, 36, 39, 40, 44 & 47)
Jodhpur - Marwar Jn. Repl. of steel girders by
pre-stressed
concrete
Expenditure
up to month
in Cr.
3.5030
Status in details
Work completed in Nov.
2009
0.3420
Work completed in May
09.
1.8400
Work completed for Br.
No. 789, 793 & 843. Work
in progress for Br. No. 823
& 831.
i) GAD approved. CRS
sanction
awaited.
ii) RDSO design for under
slung girder for 25 T
loading
awaited.
iii)
Tender
for
strengthening
of
sub
structure
awarded.
Iv) Work order to be
placed to workshop for
girder.
Work completed for Br.
No. 170 & 175. Work
under plannig for balance
03 bridge No. 28, 68 &
142
9.0670
0.5710
4.6241
0.1611
Work in progress.
4.0870
2.6790
Jacketting
&
RCC
retainers completed. Slab
casting work completed.
63
8
PB/183
9
PB/184
1
67
2
68
3
69
4
70
5
71
6
slabs (bridge No 85)
(17X12.20m)
Jodhpur - Marwar Jn. Repl. of steel girders by
pre-stressed
concrete
slabs (bridge No 92)
(17X12.20m)
Phulera
Degana
Regirdering (bridge No
22)
(10X24.40m)
4.0870
0.0000
5.1554
0.9200
30- Road Safety Works –
ROBs/RUBs
ROB in lieu of LC No. 71 - A
6.99
at Hanumangarh
5.09
100%
2.93
100%
4.06
100%
3.53
100%
Rewari-Jhajjar Road -ROB in
17.17
lieu of LC No. 57-B
6.81
50%
72
Sirsa-ROB in lieu of LC No.
10.01
143.
3.48
58%
7
73
Palanpur-Ajmer - ROB in lieu
of LC No. 134-B near Abu 7.57
Road
1.5
45%
8
74
Jaipur-Ajmer - ROB in lieu of
7.78
LC No. 28 near Kishangarh
2.99
48%
9
75
Jaipur-Bandikui - ROB in lieu
5.04
of LC No. 181 near Dausa
1.14
30%
10
76
0
0%
11
77
2.33
55%
Rewari- Alwar ROB in lieu of
3.56
LC No. 58 - A
Hissar ROB in lieu of LC No.
6.67
92-A
Hissar ROB in lieu of LC No.
6.17
89-B
Rewari-Hissar - ROB in lieu
of
LC No.C- 53
7.51
Ajmer-Chittaurgarh - ROB in
lieu of LC No. 63-C near 6.69
Mandal
64
Launching arrangements
are being made.
CRS sanction received.
Casting of RCC retainers
completed.
Jacketting
work in progress. Casting
of PSC slab is in progress.
Work order for girder
fabrication
placed
on
MMR Workshop on 23-122008. GAD approved.
Work
completed
&
commissioned .
Work
completed
on
31.7.06.
Commissioned
for Road traffic on 15.9.06.
Work
completed
&
commissioned.
Work
completed
&
commissioned on 26.1.10.
Non track span completed
up
to
superstructure
completed and track span
superstructure work in
progress.
Work completed up to pier
cap level. Superstructure
work in progress.
Total 4 spans. 3 non track
span completed. All PSC
girders of track span cast.
Substructure completed.
Superstructure work in
progress.
All piles and pile cap cast.
1 pier cap cast and 2nd
pier cap in progress.
Work awarded. Design
and
drawing
under
approval.
Total 3 span. Work
completed up to pier cap
level. Superstructure work
in progress for track span
(Main).
12
78
Rewari-Sadulpur - ROB in
10.23
lieu of LC No. 100
6.5
98%
13
79
Rewari-Hissar - ROB in lieu of
1093%
LC No.33
478
%
92%
14
80
Bikaner-Lalgarh - ROB in lieu
1015%
of LC No. 138 near Bikaner
672
%
95%
0
0%
0.68
45%
0
0%
1.67
15%
6 nos. piles cast.
Bhiwani-Rohtak - ROB in
lieu of LC No. 53-B
15
81
4.75
16
82
Ajmer-Saradhana - ROB in
8.03
lieu of LC No. 5-A/2
Jodhpur-Samdari-Barmer ROB in lieu of LC No. C-325 5.85
Railway
portion
completed.
Railway
portion
completed.
Work
in
progress in approaches.
Railway
portion
completed.
Work
in
progress in approaches.
GAD under preparation.
Estimate for Rly. portion
prepared but part of
estimate from State Govt.
yet to be received. Work
deferred by Govt. of
Haryana for 2-3 years till
completion of ROB in lieu
of LC No. 53-C.
Total 3 span. Work
completed up to pier cap
level. Superstructure work
in progress for track span.
GAD
approved
and
detailed
estimate
sanctioned.
17
83
18
84
Rewari-Hissar-Bhatinda
ROB in lieu of LC No. 19-C (2 9.83
lane)
19
85
Nagaur-Basani road - ROB in
6.05
lieu of LC No. 63-C (2 lane)
0.56
25%
Total
2
spans.
Substructure completed.
Superstructure work in
progress.
20
86
Kuchaman city-Makarana ROB in lieu of LC No. 36-C (2 5.74
lane)
0.70
5%
Total 1 span. Piling work
in progress.
21
87
AWR ROB in lieu of LC 111-C
5.90
(4 lane)
22
88
Bikaner - ROB in lieu of LC
No. 139
7.31
31. Track Renewal Works
65
0.01
2%
0
0%
Test pile cast. Design of
sub and superstructure
under approval.
Work will be started after
commissioning of ROB at
LC No. 138.
PB
(1011)
No.
Descrp.
91
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
Mavli
- 3,20,95 28,79,09
Barisadri
sec.
CTR(S)
82.01 Km
40,00
92
Rai
ka 45,60,6
Bagh
- 3
Jaisalmer CTR (P) 44.92 km
41,18,12
70,00
93
Jaipur
Ajmer
TRR(S) &
TSR(P)
14.00 Km
Hisar
Bhatinda CTR - 41
km, TRR 32.4 km &
TSR - 10.7
km (P)
Phulera
Jodhpur TSR - 10
km (P)
Merta Road
- Jodhpur TTR
(25
Nos)
Phulera
Merta Road
- TTR (40
Nos)
Madar
Palanpur TTR
(43
Nos)
&
traps
(40 Nos)
CTR work of MG
section defreezed in
June 09.Balance 17
km CTR will be
planned as per site
requirement.
Work
completed
except replacement
of exisiting 1:8.5
T/Out 1 in 12 with
fanshaped
T/Out.
Agency for P.Way
work
nominated.
Work held up for
want of S&T agency.
Work frozen due to
gauge conversion
94
95
96
97
98
Last anticipated Cost
DRF
SRSF
REV
19001
2,80,95
4,76,72
27,29
66,60
1,00
84,55,5
4
1,01,33
84,05,54
50,00
Physical
completed.
3,06,00
19,60
1,34,76
11,46
Work completed.
2,78,00
11,34
35,51
84,00
Work completed.
4,13,00
18,60
1,21,70
1,68,00
Balance
work
planned with STD-III
interlocking work.
2,65,78
14,74
1,03,00
1,62,76
Vetted MS sent to
HQ vide letter no.
S336/2/2-30 dated
30.01.06.
Tender
opened on 09.02.10
.
66
work
PB
(1011)
No.
Descrp.
99
Madar
Palanpur TBR -40 km
Jaisalmer Rai
ka
Bagh
Palace
CTR - 10
km
(P)
(Osiyan
Dhelana)
Jaisalmer Rai
ka
Bagh
Palace
CTR - 186
km
(P)
(Marwar
Mathanian Jaisalmer)
Jaisalmer Rai
ka
Bagh
Palace
CTR (P) 30 km (Rai
ka
Bagh
Palace
Marwar
Mathanian)
Jaisalmer Rai
ka
Bagh
Palace
CTR (P) -10
km (Jetha
Chanda
Thaiyat
Hamira)
Jaisalmer Rai
ka
Bagh
Palace
CTR (P) -10
km (Marwar
Bithri
Ashapur
Gomat)
100
101
102
103
104
Last anticipated Cost
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
2,83,93
98,00
15,10
2,68,83
10,20,6
3
16,53
10,16,63
4,00
To be done by BCM,
Tender
is
being
invited.
Work completed.
1,81,32
,50
2,79,58
178,37,5
3
1,82,00
Work completed.
26,68,4
3
46,59
19,89,19
42,00
Work completed.
8,74,05
15,03
8,11,28
42,00
Work completed.
11,28,3
2
17,28
11,18,32
7,00
Work completed.
DRF
SRSF
67
PB
(1011)
No.
Descrp.
105
Suratgarh - 7,30,49
Anupgarh TSR - 17.4
km
106
Hissar
Bhatinda CTR
26.37 km,
TRR - 0.23
km & TSR 0.545 km
Bikaner
Bhatinda
(Loop
/
Yard)
TSR - 25
km
Phulera
Jodhpur
(Loop
/
Yard) - TSR
- 12 km
Loharu
Sikar
CTR - 30
km
Hanumang
arh
Sadulpur CTR
37.32 km
Churu
Bikaner
CTR
36.89 km
Ratangarh Bikaner
TRR
48.33 km
Marwar
Mavli Jn TSR - 32.38
km
107
108
109
110
111
112
113
Last
anticip
ated
Cost
exp up to Outlay
March 10
Descrp.
Last
Cost
34,10
Status of PB
work/ten (10-11)
der/esti
No.
mate or
other
remarks
7,19,51
1,00
35,42,6
6
53,21
35,22,66
20,00
Work will be done
after
gauge
conversion of SRPRSGNR section. (GT
track.)
Physical
work
completed.
6,94,39
29,40
6,44,39
50,00
TSR of loop lines at
PGK, DBI, MNSR,
SGRA, DABN, MBY,
SGF,
GSW
transferred to Const.
3,91,59
23,52
1,17,30
1,40,00
Work completed.
13,30,3
6
35,13
13,29,36
1,00
Work frozen due to
gauge conversion
23,89,8
1
18,31
8,93,58
2,10,00
Work dropped as
section under GC.
23,42,0
2
18,78
2,79,49
1,00
Work dropped as
section under GC.
4,90,22
7,00
Work dropped as
section under GC.
5,99,36
28,54
Tender to be opened
on 09.04.2010.
16,02,1
8
6,27,90
4,41
68
anticipated
PB
(1011)
No.
Descrp.
114
Bikaner
Bhatinda
Suratgarh
Anupgarh
TTR (52
48 Nos)
115
Phulera
Jodhpur &
Merta
Bikaner
TTR (1:12 31
Nos,
1:8.5 - 36
Nos) & trap
switches
(33 Nos)
Hissar
Bhatinda TTR (1:12 13 Nos &
1:8.5 - 17
Nos)
Rewari
Madar
TTR (1:16 1 No, 1:12 2 Nos &
1:8.5 - 30
Nos), traps
(15 Nos) &
diamond
crossings (2
Nos)
Jodhpur Merta
&
Bikaner
Merta
TBR-57km
Madar
Palanpur TBR - 73.79
km
116
117
118
119
Last anticipated Cost
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
41,94
5,85,02
1,40,00
5,77,61
27,54
2,26,40
2,80,00
Work in progress &
Material required fot
balance
work.
KYNT=1 & SGNR=1
and 1in12=13, 1in
8.5=7
will
be
replaced in STD-III
by Const.
Work is planned to
be executed along
with Std-III.Insertion
of 1:12 T/outs have
been planned in lieu
of 1:8.5 existing
T/outs
3,00,83
26,88
2,88,51
12,32
2,40,45
12,45
2,39,85
60
4,73,06
1,34,75
3,62,43
28,00
Balance
with BCM.
3,76,22
1,81,22
3,40,21
36,01
To be done by BCM,
Tender
is
being
invited.
DRF
- 7,98,50
&
&
SRSF
69
1in12=8, 1in8.5=11
in
HSR
yard
transferred to Const.
1in12=2 , 1in 8.5 =3
at JKHI balance as
on 1.4.10
1 T/out is 1:16
instead of 1:12
planned
PB
(1011)
No.
Descrp.
120
Madar
Palanpur TFR - 80
km
Suratgarh Bhatinda CTR (P) 3.27 km &
TRR - 1.33
km
Bathinda
(Bypass
Line)
&
Hissar
Bathinda CTR - 8.27
km (P)
Suratgarh Kalyan Kot
- TRR (S) 28.83 km,
Suratgarh
By-pass TRR - 0.7
km
&
Suratgarh
(Yard / Bypass) - TSR
(P) - 2.3 km
Sri
Ganganaga
r Yard CTR (P) 1.56
km,
TRR (S) &
TSR (P) 1.972 km
Rohtak
Bhiwani
TRR (P) 24.3 km
121
122
123
124
125
Last anticipated Cost
DRF
SRSF
REV
3,27,50
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
3,22,91
4,59
.Vetted M.S. sent to
HQ.NIT is being
issued.
4,70,54
10,46
4,39,82
30,72
Physical
completed.
work
9,54,31
26,46
9,34,31
20,00
Physical
completed.
work
22,23,1
1
7,36
12,14,02
3,08,00
Work will be done
after
gauge
conversion of SRPRSGNR section. (GT
track.)
4,79,91
24,90
2,79,80
2,00,11
Physical CTR work
completed.
15,25,68
71,19
Physical
completed.
15,96,8
7
70
work
PB
(1011)
No.
Descrp.
126
Udaipur
- 4,13,57
Himmatnag
ar - CTR 2.46 km &
TSR - 10.57
km (S)
127
Udaipur
- 8,32,83
Himmatnag
ar - TRR 24.82
km
(S)
128
Sri
Ganganaga
r
Hanumang
arh - CTR 20.97
km
(S)
Ratangarh
West
Sardar
Shahar
CTR - 15
km (S)
Bikaner
Bhatinda TSR - 19
km (P) (13
stations)
(24 loops)
Madar
Palanpur Through
switches &
CMS
crossing
renewal
(212 Nos)
129
130
131
Last anticipated Cost
DRF
SRSF
exp up to March 10
Outlay
REV
DRF
DRF
15,26
75,99
3,37,58
75,99
7,56,84
SRSF
Status
of
work/tender/estimate
or other remarks
Work frozen in view
of GC, Now work
has been defrezed in
june 09. Tender
opened on 08.10.09
& discharged.Tender
reinvited,
to
be
opened
on
19.03.2010.
Work frozen in view
of GC, Now work
has been defrezed in
june 09. Tender
opened on 08.10.09
& discharged.Tender
reinvited,
to
be
opened
on
19.03.2010.
Work dropped as
section under GC.
14,07,9
7
33,55
3,15,53
7,00,00
10,34,0
7
6,16
2,56,18
1,00
Physical
completed.
7,52,14
60,80
2,24,98
2,80,00
Work in progress &
will be completed by
Mar-10.
75,99
12,57,76
Work is in progress
for
CMS
crossings.Switches
are
yet
to
be
received from HQ.
13,33,7
5
71
work
PB
(1011)
No.
Descrp.
132
Merta Road
- Merta City
- CTR 14.66
km
(P)
Rai
ka
Bagh
Jaisalmer TSR - 15.47
km (P)
Madar
Palanpur TFR - 80
km
Rewari
Jaipur
Madar
TFR - 74.2
km
Madar
Durai
&
Marwar
Jodhpur TBR - 49.63
km
Merta
Phulera
TBR - 29
km
Renewal of
ordinary
curved
switches
and
crossing
with new 52
Kg (1:12 &
1:8.5) TWS
and
WCMSC on
existing
PSC layout
- 416 SETS
133
134
135
136
137
138
Last anticipated Cost
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
15,88,9
8
28,73
5,00,00
3,70,00
Work in progress.
10,69,3
6
30,32
75,99
3,84,00
Work in progress.
3,77,86
3,22,77
55,09
NIT is being issued.
3,41,52
3,28,09
13,43
DRF
SRSF
2,59,32
72,96
1,79,25
71,05
88,08,8
8
2,59,32
To be done by BCM,
Tender
is
being
invited.
80,00
80,00
Work planned with
BCM.
62,74
5,80,00
MS sent to HQ.
Tender is to be
called.
72
PB
(1011)
No.
Descrp.
138
Renewal of
ordinary
curved
switches
and
crossing
with new 52
Kg (1:12 &
1:8.5) TWS
and
WCMSC on
existing
PSC layout
- 416 SETS
CTR(TRR/S
& TSR/P)
5.60 Km at
BNSR,
KYNT,
SRPR,
SBNR and
RMSR
&
APH Loop
lineson
SOG-APH
section
TRR(P)
33.65 Km
(from
Km
195
to
228.650
SOG - BKN
section.
TRR(S) 34
Loop Lines
(25.30 Km)
on Phulera
- Jodhpur
BG section
of Jodhpur
Div.
139
140
141
Last anticipated Cost
DRF
SRSF
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
Estimate
process.
4,01,19
17,92
under
3,00,00
1,01,19
Work in progress &
will be completed by
Mar-10.
22,89,1
8
2,00,00
8,05,00
Work in progress &
will be completed by
Mar-10.
9,68,03
5,00
1,28,00
Detailed
estimate
under vetting.
73
PB
(1011)
No.
Descrp.
142
TRR(S) of
49
Loop
Lines
(35.581
Km)
and
Sleeper
Renewal
(P) of Loop
Lines
to
increase
the sleeper
density
from M+4 to
M+7
on
Madar
Palanpur
section
TRR(S) of
49
Loop
Lines
(35.581
Km)
and
Sleeper
Renewal
(P) of Loop
Lines
to
increase
the sleeper
density
from M+4 to
M+7
on
Madar
Palanpur
section
Laying of 60
Kg (90 UTS)
1 in 12 TWS
and WCMS
crossings on
58
Nos.
existing 1 in
12
fan
shaped turn
out sleepers
on Rewari Jaipur
section
142
143
Last anticipated Cost
DRF
SRSF
REV
16,71,7
6
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
2,00,00
Tender to be opened
on 09.04.2010 for
MD-HP and HPBWA sections.
5,39,00
Tender to be opened
on 09.04.2010 for
MD-HP and HPBWA sections.
13,78,4
0
32,23
1,00,00
74
5,60,00
Estimate
process.
under
PB
(1011)
No.
Descrp.
144
Rewari
Phulera
CTR
20.045 km,
TRR
24.09 km &
TSR - 13.25
km (S)
Jaipur
Phulera
CTR
28.45
km
(S)
Marwar
Mavali
CTR
113.55 km
(S)
10,59,4 6,81,47
5
Udaipur
Himmatnag
ar - CTR 22.32
km
(S)
Hissar
CTR - 9.78
km
bye
pass line &
Rewari
Hissar
TRR - 3 km
& TSR 41.4 km (P)
Ratangarh Bikaner &
Ratangarh Degana
CTR - 0.75
km & 22.77
km
(S)
respectively
145
146
147
148
149
Last anticipated Cost
DRF
SRSF
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
4,50,00
6,81,47 1,00
Work frozen due to
gauge conversion of
RPC section
6,06,84 10,20,00
31,23
3,00
3,31,93 1,00
Work frozen due to
gauge conversion of
RPC section
2,80,23 42,14,48
1,83,04
1,20,00
39,36,4 1,60,23
2
7,06,22
40,74
3,37,19
1,00
CTR
completed.Tender
for deep screening of
30.68 km (balance
work
of
CTR)
awarded
on
23.02.2010
CTR
completed.
Deep screening and
Welding works are
now frozen.
29,86,3
1
1,00,31
23,07,04
6,79,27
Work in progress by
PQRS & will be
completed by Mar10.
15,18,0
4
39,23
40,00
1,00
Work not required,
being done under
G.C.
75
PB
(1011)
No.
Descrp.
150
Suratgarh Bhatinda Hissar
TRR
25.73
km
(S)
(23
stations)
(37
loop
lines)
Rewari
Hissar
TRR - 65
km (P)
Rewari
Hissar
TRR(S) &
TSR(P) - 15
km
(12
stations)
Hissar
Bhatinda TSR - 16.4
km (P)
Hissar
Bhatinda TSR - 19.5
km
Rewari
Ringus
TSR - 33.57
km
Udaipur
City
Himmatnag
ar - TSR 24.82 km
151
152
153
154
155
156
157
Last anticipated Cost
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
15,23,2
3
14,73,23
50,00
Work in progress &
will be completed by
Mar-10.
45,89,6
4
45,09,64
80,00
Work in progress by
TRT & will be
completed by Mar10.
DRF
SRSF
REV
10,91,2
4
29,40
2,16,18
8,75,06
9,31,05
32,14
9,26,05
5,00
Physical
completed.
work
12,52,5
0
38,22
12,17,00
35,50
Physical
completed.
work
7,59,83
46,38
3,99,45
1,00
Work frozen due to
gauge conversion of
RPC section
5,59,48
17,13
1,57,77
4,01,71
Sawai
3,04,08
Madhopur Jaipur
TSR - 10.3
km (P)
19,60
2,83,43
20,65
Work frozen in view
of GC, Now work
has been defrezed in
june 09. Tender
opened on 08.10.09
& discharged.Tender
reinvited,
to
be
opened
on
19.03.2010.
Work completed
76
PB
(1011)
No.
Descrp.
158
Hissar
Bhatinda TSR - 19
km (P) (11
stations)
(23
loop
lines)
Merta Road
- Bikaner TSR - 18.2
km (P) (12
stations)
(24
loop
lines)
Merta Road
- Jodhpur TSR - 13.2
km (P) (10
stations)
(17
loop
lines)
Rai ka Bag
- Phalodi TSR - 7.6
km (P) (7
stations)
(10
loop
lines)
Rewari
Hisar - TSR
-100 km (P)
159
160
161
162
163
164
165
Last anticipated Cost
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
7,28,79
60,80
4,22,78
3,06,01
Physical
completed.
11,32,8
3
35,67
3,50,00
4,10,00
Work in progress.
8,25,46
25,87
30,00
3,74,00
Work in progress.
4,78,15
14,90
80,61
2,70,00
Work completed.
40,80,6
8
1,96,00
32,64,54
8,16,14
Madar
- 4,17,99
Palanpur TBR- 80 km
Merta Road 2,35,98
- Bikaner TBR
&
deep
screening 40 km
Bikaner
3,89,35
Division
Turnouts
(45 sets) &
traps
(32
sets)
1,96,00
3,00
4,14,99
98,00
50,00
1,40,00
Work in progress by
TRT & will be
completed by Mar10.
To be done by BCM,
Tender
is
being
invited.
Work planned with
BCM.
46,27
3,59,85
29,50
DRF
SRSF
77
work
Scope at KSI=3,
CKD=3,
BNW=6,
BWK=2,
STD=4,
KNL=2,
SSA=5,
SHN=2,
DNG=1,
BHT=2,
ADR=2,
RMN=2, SGA=2
PB
(1011)
No.
Descrp.
166
Rewari
- 3,54,93
Bandikui Jaipur
TTR
(37
Nos) (P)
Madar
- 3,30,21
Palanpur TTR
(43
Nos)
&
traps
(41
Nos)
Lalgarh
- 3,20,12
Suratgarh TTR
(40
Nos)
167
168
169
170
171
172
173
Last anticipated Cost
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
8,56
3,50,66
4,27
Work completed
15,74
1,40,00
Work balance is for
18 (1 in 8 1/2)
Turnouts,
material
awaited as it will be
done departmentally.
3,01,43
18,69
4,15,46
2,07,41
2,08,05
Scope of 12 turn out
will be utilised during
yard remodeling of
SOG yard by Const.
deptt.
Work will be done
with STD-III work by
Const. deptt.
2,86,95
1,00,30
56,00
DRF
Rewari
Hissar
TTR
(53
Nos)
Merta Road
- Bikaner TTR
(34
Nos)
Rewari
Phulera
TTR
(39
Nos)
Rewari
Hissar
TTR (P) (70
Nos)
(12
yards)
SRSF
3,54,93
23,39
3,00,00
54,93
7,89,15
56,00
50,00
93,00
Hissar
- 3,64,02
Bhatinda Bikaner
TTR
(P)
(24 Nos &
18
Nos)
(22 yards)
29,28
3,59,05
4,97
78
At BNW 1in12=12 &
at STD 1in12=8 and
1in
8.5
=41
(BNW=24, STD=3)
will be replaced by
the division, balance
will be replaced by
Const. along with
STD-III work.
1in12 turn outs at
BGD=2,
SSA=1,
SHN=4, DNG=2 &
1in8.5 turn out at
SSA=9,
DNG=1,
JKHI=2,
SGA=2,
RMN=1,
AS=4,
MHJ=4 & SOG=9
will be rteplaced by
the division.
PB
(1011)
No.
Descrp.
174
TTR(P) 58
nos
of
existing 1 in
12
(14
Nos.), 1 in
8.5
(31
Nos.) & D/S
(13
Nos.)
on
PSC
sleepers in
Jaipur yard,
RewariPhulera
section in
Jaipur
division
Rai
ka
Bagh
Palace
Jaisalmer Welding 145 km &
Bikaner
Merta Road
- Welding
(13
stations)
(858 joints)
Madar
Palanpur TFR - 80
km (P)
Degana
Jodhpur TFR - 73
km
Bikaner
Merta Road
- TFR - 73
km
Hissar
Bhatinda CTR - 21
km & TSR
- 10 km (P)
175
176
177
178
179
Last anticipated Cost
REV
exp up to March Outlay
10
DRF
SRSF
DRF
21,95
3,00,00
88,18
4,38,14
4,07,32
28,00
3,27,62
1,27,49
2,00,13
Vetted MS sent to
HQ. NIT is being
issued.
2,97,48
1,00,00
1,40,00
Estimate sanctioned.
Fittings required.
2,97,45
1,00,00
1,40,00
Estimate sanctioned.
Fittings required.
28,69,47
10,00
Physical
completed.
DRF
3,88,18
28,79,4
7
SRSF
63,11
79
Status
of
work/tender/estima
te or other remarks
work
PB
(1011)
No.
Descrp.
180
Merta Road
- Bikaner &
Jodhpur Through
weld repair
- 104 km
Rewari
Madar
TFR - 138
km
Works
in
progress
costing less
than
2.50
Cr
Works
in
progress
costing less
than
2.50
Cr
TRR(P) of
4.023 Km
bet
Km
508.5-589.6
&
614.7927.9
at
Imp & Maj
bridges in
MD-PNU
sec
TRR(P) of
15 Km from
Km
18.820.8, 35-39,
51.1-53.1,
69-72, 7576 & 76-79
in RE-HSR
sec
Glued
Joints
Renewal of
975
Nos.
MD-PNU
section
181
182
182
183
184
185
Last anticipated Cost
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
6,49,68
1,00,00
2,40,00
Estimate
revision
7,09,42
5,00,00
1,91,43
DRF
SRSF
REV
under
47,27,00
2,15,90
2,69,57
50,00
Work sanctioned in
PB 2010-11
11,81,7
7
1,50,00
New work sanction
in 2010-11.
5,19,84
1,00
Work sanctioned in
PB 2010-11
80
PB
(1011)
No.
Descrp.
186
TRR(S) of
12.58 Km &
ISD
of
47.618 Km
of
Loop
Lines from
M+4 to M+7
in MD-PNU
sec
Laying
of
60 Kg 1in12
TWS
&
WCMSC-50
nos in FLJU-MJ sec
Laying
of
60 Kg 1in12
TWS
&
WCMS in
RE-BKI sec
(18 nos) &
JP–SWM
sec
(40
nos)
TBR of 51
Km
in
MTD–JU
sec (33 Km
bet
Km
670-714) &
JU–MJ
sec(18 Km
from
Km
593-611)
CTR
of
5.166 Km
(From Km
187192.166) in
AQG-POK
sec
187
188
189
190
Last anticipated Cost
DRF
10,24,0
4
SRSF
REV
exp up to March Outlay
10
DRF
SRSF
DRF
1,13,23
1,00
11,40,9
2
1,00
13,23,6
1
1,00
3,27,94
1,40,12
1,00
7,25,05
15,85
50,00
81
Status
of
work/tender/estima
te or other remarks
Work sanctioned in
PB 2010-11
Estimate
preperation.
under
PB
(1011)
No.
Descrp.
191
TRR(P) of 5 5,16,63
Km (From
Km
160165)
&
CTR(P) of 1
Km (From
Km
181182)
in
SOG-BKN
sec
TRR(P) of 3,37,76
4.9
Km
(From Km
510.1-515)
in
BKNMTD sec
TTR(P) of 4,61,98
1in8.5
T/out-43
nos
&
Trap–19
nos in MDPNU sec
New Work
less
than
2.50 Crores
192
193
194
Last anticipated Cost
DRF
SRSF
REV
exp up to March Outlay
10
DRF
SRSF
DRF
Status
of
work/tender/estima
te or other remarks
2,38
1,00,00
New work sanction
in 2010-11.
50,00
17,89
32- Bridge Works-A
S.
PB/ LB Nomenclature of works as per
NO Item no. PB/LB
1
PB/176
2
PB/177
3
PB/178
Chouth Ka Barwada - Isarda Re-girdering
of
Br.
No.
23.
(30x18.30m)
Sawai Madhopur - Jaipur Regirdering of Br. No.06 , 77,
81
(Total
3
Bridges)
Br.
no.
77
(5x18.30m) by steel girder
Madar- Palanpur- Regirdering
& strengthening of sub
structure (Bridge Nos. 736,
789, 792, 793, 823, 831, 843,
848
)
(Total 8 Bridges)
5,00
Work sanctioned in
PB 2010-11
2,00,00
Latest
sanctioned
cost (In Cr.)
9.8359
Expenditure up
to month in Cr.
3.5030
Work completed in Nov.
2009
2.8678
0.3420
Work completed in May
09.
4.6000
1.8400
Work completed for Br.
No. 789, 793 & 843. Work
in progress for Br. No. 823
& 831.
82
Status in details
4
PB/179
Jethi
Chitrasani
Regirdering & Strengthening
of sub structure (bridge No.
845)
(6x30.50m) with under slung
super-structure
5.5860
i) GAD approved. CRS
sanction
awaited.
ii) RDSO design for under
slung girder for 25 T
loading
awaited.
iii)
Tender
for
strengthening
of
sub
structure
awarded.
Iv) Work order to be
placed to workshop for
girder.
Work completed for Br.
No. 170 & 175. Work
under plannig for balance
03 bridge No. 28, 68 & 142
5
PB/180
9.0670
0.5710
6
PB/181
4.6241
0.1611
Work in progress.
7
PB/182
4.0870
2.6790
8
PB/183
4.0870
0.0000
9
PB/184
Hisar-Bhatinda
-Suratgarh
strengthening of major bridge
for 30 tones axle load for
upgrading of feeder route to
dedicated freight corridor.
Total bridge no. 5
Phulera - Degana - Repl. of
steel girders by pre-stressed
concrete slabs (bridge Nos
17, 21, 32, 34, 36, 39, 40, 44
& 47)
Jodhpur - Marwar Jn. - Repl.
of steel girders by prestressed
concrete
slabs
(bridge
No
85)
(17X12.20m)
Jodhpur - Marwar Jn. - Repl.
of steel girders by prestressed
concrete
slabs
(bridge
No
92)
(17X12.20m)
Phulera Degana - Regirdering
(bridge
No
22)
(10X24.40m)
5.1554
0.9200
Jacketting
&
RCC
retainers completed. Slab
casting work completed.
Launching arrangements
are being made.
CRS sanction received.
Casting of RCC retainers
completed.
Jacketting
work in progress. Casting
of PSC slab is in progress.
Work order for girder
fabrication placed on MMR
Workshop on 23-12-2008.
GAD approved.
32- Bridge Works
1
195
2
196
3
199
AII-Regirdering of bridge no.509
incl. Strengthening (jacketting) of 6.00
sub-structure & foundation etc.
AII-Regirdering of bridge no.676
incl. Strengthening (jacketting) of 3.45
sub-structure & foundation .
MD-PNU-Regirdering
strengthening
of
sub
4.34
structures(Br. No. 736, 739, 823,
832, 843 & 848)
83
-
100%
Work completed.
-
100%
Work completed.
4.15
90%
Work completed except br.
no. 823. revised estimate
under process.
Jethi-Chitrasani -Regirdering
& strengthening of sub
structure (Br. No.845)
200
5.59
0.02
0%
GAD approved. Structural
design for Pile & Pile cap
under scruity at HQ. CRS
sanction awaited. Tender for
strengthening
of
sub
structure
awarded
on
29.5.08. Work order to be
placed to Worksghop for
girders.
5
201
Strengthening of major bridges
for 30 ton axle load for
upgradation of feeder rout to 9.07
dedicated freight on HSR-BTISOG sec.
0.76
20%
Work completed at Br. no.
68, 170& 175.
6
207
HSR-BTI-SOG-BDWL
:
Strengthening of substructure 4.11
(81 bridges)
0.00
0%
Tender opened on 25.05.10
& under TC.
7
208
0.00
0%
Tender opened on 25.05.10
& under TC.
8
197
8.24
100%
Work completed.
9
198
2.69
100%
Work completed.
4
RE-HSR : Strengthening of
2.81
substructure (64 bridges)
Chouth ka Barwara- Isarda9.84
Regirdering (Bridge No. 23)
Sawai Madhopur- Jaipur Regirdering (Bridge No. 6, 77 & 2.87
81)
0.67
50%
Work completed at Br. No.
21 & 44. substructure and
slab casting at Br. no. 17,
34, 36 & 40 completed. Work
in progress at Br. no. 39.
2.68
85%
Work in progress.
Completion.
4.09
1.04
65%
Work in progress.
5.15
0.93
25%
Girder under fabrication at
Manmad workshop.
9.77
6.35
9.67
6.54
90%
100%
Work commissioned.
Work commissioned.
2.76
2.15
100%
Work commissioned.
2.58
90%
Work commissioned.
2.26
100%
Work commissioned.
10
202
FL-DNA-Replacement of steel
girders by pre-stressed concrete
4.62
slabs(bridge Nos 17, 21, 32, 34,
36, 39, 40 & 47)
11
203
JU-MJ-Replacement of steel
girders by pre-stressed concrete 4.09
slabs(bridge No.85)
12
204
13
205
1
2
210
211
3
212
4
213
5
214
JU-MJ-Replacement of steel
girders by pre-stressed concrete
slabs(bridge No.92)
FL-DNA Regirdering (bridge
No.22)
33- S & T Works
RRI REWARI
AII-COR 6 Quad
JP-BKI: Block proving by Axle
Counter as last vehicle check
device(B-route) 10 sec
JAL-BMN-PNU-Block providing
8.25
by Axle Counter (25 Block sec.)
BKN-KLYT OFC
3.31
84
Nearing
6
215
7
216
8
217
BU-RE: Block proving by Axle
Counter as last vehicle check
3.40
device with P/B
token less
B/Inst.
Suratgarh-AnupgarhRepl.
BSNL own O/H by UG
composit quad cable (E route) 2.90
78 KM
JU-Phalodi OFC STM-I/ STM-4
3.41
equipment and DI/MUX
2.32
20%
0.05
0%
2.32
100%
9
218
MDB _JSM 6 Quad and OFC
10.67
cable
0.50
30%
10
219
JU-MTD-DNA
OFC STM-I/
4.53
STM-4 equipment and DI/MUX
0.45
30%
11
220
MTD,DNA,RKB TC in complete
4.76
yard
0.50
40%
221
Lalgarh-Bhatinda-Strengthing of
telecom circuit by optic fibre
cable
and
STM1/STM4 5.6431
equipments and D/I MUX.(318
KM.)
0
0
13
222
Degana-Phulera-optic
fibre
cable,and
STM1/STM4
3.2478
equipments and D/I MUX.(112
KM.)
0
0
14
223
Marwar-Mavli -Replacement of
6.0577
O/H alignment by 6 Quad cable.
0
0
12
85
Out of 9 Section, work
completed in 5 ( BU-RHG,
RHG-DGW, DGW-MKH ,
MKH-MWW & MWW- AWR.)
Work is ready in 2 block
sec. HIS- AIA & BWL- AIA
. Work is progress in 2 block
sec. (KRH-HIS & AWRPSL). Material received.
To be executed by Rail Tel
Corporation of India Ltd New
Delhi. Estimate duly vetted
by S.DFM submitted to HQ
on 31.05.10
Work commissioned
The work was transferred
back from RCIL to Railway in
the month of Nov-09.
Thereafter contract has been
awarded for MDB-PLC 6
quad cable. . For composite
work from PLC-JSM tender
under finalisation.
Contract
awarded
on
29.12.2009 .work is in
progress.100 kms of duct
has been laid.
Contract awarded. Work in
progress at MTD (PDC-Nov10). DNA already covered
under GC work, RKB will be
done
with
RRI
work
sanctioned this year.
Detailed
estimate
sanctioned.Finacial
Expenditure kept pending as
per Railway bd order. Board
has instructed not to incur
any liability till further
instructions.
Detailed
estimate
sanctioned.
Finacial
Expenditure kept pending as
per Railway bd order. Kept in
abeyance as per Railway
Board order.
Detailed
Estimate
sanctioned on 25.01.2010..
Finacial Expenditure kept
pending as per Railway bd
order
15
225
Rai ka bagh RRI
3.00
0.00
0%
Detailed
Estimate
sanctioned Tender schedule
under prepration. Tender
opened on 09.08.10.
36- Other Electrical Works
1
228
Approval for issue of NIT for
consultancy contract given
by
GM.
NIT
under
preparation and to be issued
by 15.7.2010.
JU- Provision of 10.5MW Wind
66.50
mill plant at JSM
42-
Workshop and Prod.
unit
234
Ajmer workshop - Periodical
overhauling of broad gauge 4.40
diesel locomotives
Ajmer - Modernisation of
carriage workshop
72.75
3
235
Madar - Routine over hauling
facilities
17.4
4
236
Ajmer
modernisation
workshop
5
233
LGH
Yard-Fright
examination facilities.
6
230
JU-Workshop- Enhancement of
periodical overhuling capacity of 16.17
coaches.
8.44
90%
7
232
BME-Integrated
complex.
0.00
0%
237
BGKT Arumenting Capacity of
Diesel Shed for accomodating
6.47
50 EMD locos North Western
Railway.
1
2
8
231
coach
of
train
care
58.73
0.97
100%
Work completed.
0
0%
Detailed estimate sanctioned
and tender opened on
22.1.09
0
0%
Detailed
estimate
sanctioned. Tender finalised.
0
2%
Work in progress.
07-08
3.33
86
0.00
0%
Work dropped due to
commissioning of KLYT-PLC
section and LGH bye pass.
Drawing
approved,Tender
opened on 26.03.2010 &
under T.C.
Work dropped in ref.to
CME/NWR letter no.NWR/M/
324/Intra/coach/vol-I dated
7.2.2008.
Again
case
referred in feb-10 for review.
Engg, Elect, Mechanicna
estimate prepared but S&T
estimate still awaited. Plan
under signature of Divisional
officers.
Mech. & Engg. estimate
vetted. Elec. Estmate under
vetting.
1
2
3
242
245
243
4
246
5
248
6
7
8
51- Staff Quarters
UDZ-HMT- Shifting of gang
from section to stations (16 4.23
Gangs)
ABR- Repl. Of gang quarters, 10
gangs (100 units type I quarters) 2.83
with type II.
Reconstruction of quarters TypeI-66, Type-II-17, Type-III-2 &
Type-IV-1 unit over BKN Divn.
(Type-I = BNW-2, HSR-33,
BKN-10, SGNR-6 & SDLP-15
Total-66 Qtrs.) (Type-II = BNW- 2.52
2, HSR-9, BKN-1, SGNR-1,
SDLP-2 LHU-1 & RTGH-1 Total17 Qtrs.) (Type-III = BNW-1 &
SDLP-1 Total - 2 Qtrs.) (Type-IV
= BNW-1)
Replacement of quarters, type-I88 & type-II-1 with type-II total 3.29
89 units on Bikaner Division.
Replacement of ganf quarters
with type-II 63 units over RTGH 3.27
sub-divn.
Nizampur
&
Ateli
:Replacement
of
gang
quarters, type I 118 & type II 22 units.
0.00
0%
Estimate resubmitted for A/C
vetting for construction of Type
II qtrs. In place of type I qtrs.
0.00
0%
Vetted material modification
sent to HQ on 18.12.09.
0.24
10%
Revised
preparation.
plan
under
Work de-freezed, NIT being
issued.
0.00
0%
0.00
0%
Estimate sanctioned. Tender
to be opened on 27.07.10.
240
4.11
0.00
0%
Tender opened on 24.10.08 &
tender cancelled. Material
modification (Type I to type II)
sent to HQ for sanctioned
second
week of Nov. 09.
Proposal returned by HQ with
objervation. The remarks of
objervation sent to HQ on
17.02.10 & again observation
received from HQ.
241
RKB-JSM- Replacement of
jack
arch
roof
type 4.03
quarters,type-I-136 units
0.71
0%
Revised estimate sanctioned
for 74 Qtrs. Tender to be
opened on 10.08.10.
244
Jodhpur division- Replacement
of arch type I- 84 type -II - 33 3.88
units with standard type-II.
0%
Estimate sanctioned for total
67nos.
Type-II
Qtrs
on
replacement
basis
within
sanctioned cost. Tender to be
opened on 03.08.10.
52- Staff Aminities
87
0.00
1
250
Construction of community halls
at Sikar, FL, JU, AII, HMH, 4.34
UDZ and ABR.
3.34
70%
2
251
Rewari- Jaipur - Improvement to
3.20
water supply, roads & drainage.
0.00
10%
3
252
Jodhpur - Upgradation of
Divisional Hospital (Pb No. 1
526/09-10/SR)
0.00
0%
ABR - Work in progress.
(35%)
UDZWork started but
stopped due to stay order.
(Land dispute between Army
and state govt.) started again
in Mar.2010 but stopped in
April
10.
(10%)
AIIWork
awarded
on
25.08.09 but proposed to be
dropped. work sanctioned for
renovation
of
existing
community Hall instead of
constructing
new
one.
HMH, SIKR, FL & JU : Work
completed.
The progress in water supply
work is 70 %. The progress of
RCC OH tank 20% & in drain
work 30% . The tender of road
work is under finalization.
Specification for modular OT is
being
collected,tender
schedule under preparation.
64- Other Specified Works
1
258
Udaipur- Upgradation of training
facilities at zonal railway training 3.00
institute.
2.25
80%
2.51
0.00
0%
for
(7 3.27
1.45
100%
AII-PNU-Infrastructure
facilities for mechanization of
track(7 stations).
2
259
3
260
Infrastructure
mechanisation
stations)
facilities
of track
88
2 sub works costing Rs. 55
lacs being done by RTM-LKO.
Supply order for 4 other sub
works costing Rs. 9.27 lacs
have been placed by COSJP/DMM-AII
Siding is to be provided on 6
stations i.e. MJ, RN, ABR,
JWB, SOH, IQG while rest
room is to be provided on 5
stations i. e. DOZ, JWB, SOH,
IQG & SOD. Detail Estimate
sanctioned. Tender to be
opened on14.07.10 for resting
facility & on 22.07.10 for
stabling siding. T. No. 100 &
101/10)
Work completed at JMS, HMH,
RMN, PGK & SBNR (5
stations) and work dropped at
KNL & APH (2 stations) Track
work will be executed by
CAO/C alongwith Std III work.
4
257
5
261
6
262
Jaipur- setting up of
Western Railway Zone.
North
133.74
Jaipur :- Upgradation of
15.06
Railway hospital
North Western
Railway
Integrated security system ( 4 8.27
stations)
*****
89
94.72
82%
0.06
0%
0.00
0%
HQ Office: - Work completed.
Township:
For township, 2.99 hectare
land out of total 15.50 hectare
allotted is available. Balance
12.51 hectare land is under
court’s
stay
order.
Work of construction of 17 unit
type-V
PHOD
houses
completed and handed over to
Open
Line.
Construction of club house has
been short closer due to land
under litigation. Construction
of 36 unit Type-V and 36 unit
Type-IV is in progress. The
progress held up due to Court
case.
Construction of 72 units TypeII, 108 units Type-III and 36
units Type-IV (Multistory),
health unit, shopping complex
near
Getore
Jagatpura
Railway Station in progress.
Tender to be opened on
16.07.10.
Tender floated by HQ &
opened on 30.03.10. Site to
be decide.
Download