SUBREGIONAL INFRASTRUCTURE RESEARCH

advertisement
SmartGrowth Strategy Update:
Discussion Paper:
Implications of tsunami risk for
existing and future growth areas
Prepared by: Martin Butler, Andy Ralph, Paul Baunton and Barry Somers
February 2013
A1494330
1
Executive summary:
The purpose of this discussion paper is to consider whether, taking account of the
tsunami hazard and possible mitigation measures, SGIC can have confidence to
approve the Settlement Pattern for the SmartGrowth Strategy Update in relation to:
i) Undeveloped Urban Growth Areas (specifically Te Tumu)
ii) Developed Urban Growth Areas (in which the risk1 will be increased through
intensification).
The workstream report Review of Identified Residential Urban Growth Areas
(October 2012) noted that tsunami risk was subject to further technical assessment
and would be part of the discussion paper on Future UGAs in the New Year. This
discussion paper presents the findings of research that has been undertaken to
assess the tsunami risk to SmartGrowth and whether the risk can be reduced to an
acceptable level.
Two recent reports by the Institute of Geological and Nuclear Sciences Limited are
the subject of this discussion report. They are:
Modelling of the tsunami risk to Papamoa, Wairakei and Te Tumu assuming an
altered ground level due to development of Wairakei and Te Tumu, and the
implications for the SmartGrowth Strategy, GNS Science Consultancy Report
2012/54, September 2012, and
Modelling of the evacuation rates required to achieve an acceptable level of health
and safety risk in Te Tumu from the Variation to the Southern Kermadec Scenario,
GNS Science Consultancy Report 2012/291, December 2012.
These Bay of Plenty Regional Council commissioned reports will contribute to better
understanding of potential tsunami impacts on coastal development as well as the
approach that should be adopted toward managing these impacts.
Tauranga City Council, using the data derived by GNS, is undertaking some
additional work relating to the areas affected by tsunami inundation to provide the
community with more accurate and up-to-date information on places to go to be safe
should a local source event occur. This work is being undertaken by TCC as part of
the preparation of a tsunami evacuation plan called Tsunami Survive. The
preparation of the evacuation plan has raised awareness and understanding of the
possible risk associated with a local source tsunami event, and this work is set to
continue.
Two statutes provide an overlapping framework for managing natural hazards.
Despite having different policy preparation timeframes, the current policy frameworks
are consistent.
The Resource Management Act 1991 includes earthquake and tsunami in its
definition of natural hazard. Under the RMA, the New Zealand Coastal Policy
Statement 2010 specifically includes tsunami among coastal hazards to be managed,
over at least 100 years. The Proposed Bay of Plenty Regional Policy Statement
takes a risk management approach that requires intolerable risk to be avoided,
“Risk” is used in this sense:
risk means the likelihood and consequences of a hazard (Civil Defence Emergency
Management 2002, section 4)
Risk is often expressed in terms of a combination of the consequences of an event (including
changes in circumstances) and the associated likelihood of occurrence (AS/NZS ISO
310000:2009 Risk management – Principles and guidelines, November 2009). (New Zealand
Coastal Policy Statement 2010, Glossary, Risk)
1
A1494330
2
existing tolerable risk to be reduced and new development to not be subject to risk
that exceeds acceptable levels. Policy statements are to be given effect by plans.
As part of the resolution of appeals on the Tauranga City Plan, BOPRC and TCC
have entered into a Memorandum of Understanding. The two councils have agreed
to collaborate in preparing district plan provisions that implement the risk
management approach.
The Civil Defence Emergency Management Act 2002 includes in its purpose
“encourage and enable communities to achieve acceptable levels of risk”. It requires
local authorities to set up regional groups to co-ordinate planning, programmes and
activities related to the 4Rs: [risk] reduction, readiness, response, and recovery. The
BOP CDEM Group Plan’s risk reduction principles include:

Events that have the potential to cause a significant number of deaths or
injuries to people are not acceptable…

Hazard information is to be freely available to enable the community to engage
in decisions about the acceptability of the risks they face and to equip
individuals to act to reduce their own risk.

Comprehensive risk reduction is achieved through integrated planning and risk
management across all councils….
A 2002 paleotsunami study found evidence of past tsunami and led to further studies
over the following decade. SmartGrowth’s Implementation Management Group
requested that BOPRC commission GNS to provide a further report examining the
risk to Pāpāmoa, Wairakei and Te Tumu assuming ground levels were modified to
reflect the final constructed situation. In turn, this led to another report examining
whether mitigation could reduce Te Tumu risk to an acceptable level. These latest
two GNS reports are the subject of this discussion report. The modelled results now
align with the paleotsunami evidence, adding credibility to both the paleo evidence
and the results of the modelling.
Compared with other hazards, tsunami are much riskier than earthquakes (based on
estimates of deaths). New Zealanders have had little opportunity to be well-informed
in terms of the risks associated with living on the coast. Comparison of the risk of
tsunami and volcanic hazards has not been undertaken; however, warning systems
would enable fatalities to be minimised in most volcanic events. With few if any fault
lines within the SmartGrowth area and an evenly spread volcanic risk, these hazards
do not influence where development should occur within the SmartGrowth area. The
shaking hazard is addressed by engineering and the Building Act; the liquefaction
hazard from earthquakes is addressed separately from this discussion paper.
To inform planning for evacuation, tsunami sources that impact on New Zealand are
divided into three categories:
• Distant source — more than 3 hours travel time from New Zealand;
• Regional source — 1–3 hours travel time from New Zealand; and
• Local source — 0–60 minutes travel time to the nearest New Zealand coast.
The travel time of the most hazardous tsunami to the study area is approximately
50 minutes, qualifying this scenario as a local source. This is too short for formal
warning and effective evacuation. While some natural signals may be able to be
detected, effective evacuation will be dependent on the preparation and
implementation of an entire evacuation strategy. Ongoing community engagement,
sustained tsunami education and evacuation training is required to ensure
appropriate evacuation response to natural signals so that individuals act to reduce
their own risk.
A1494330
3
The reports found that, assuming no evacuation, the study areas of Pāpāmoa,
Wairakei and Te Tumu are subject to intolerable risk from tsunami. These are the
first SmartGrowth areas where the consequences of tsunami have been analysed
and the risk assessed. It is likely that the level of risk throughout the settlement
pattern will vary and further work is recommended to assess the specific risk of other
developed and undeveloped urban growth areas in relation to their coastal location.
Undeveloped areas
The second report found that, with vertical evacuation facilities and a combination of
land use planning and emergency management measures, an acceptable level of
risk could be achieved for Te Tumu. Te Tumu was the first area assessed in this way
so as to inform the SmartGrowth review. Such mitigation measures may be an option
to be assessed for other areas.
Modelling of tsunami and their associated risk is a developing discipline and relies on
many assumptions with consequential uncertainty. Much was learned from the March
2011 Tohuku event in Japan where the amount of slip was greater than expected;
the Japan event occurred in a subduction zone similar to the Kermadec Trench, the
source of the most hazardous tsunami scenario.
Traditionally, evacuation has aimed to move people out of the inundation zone
entirely, inland or to high ground. Vertical evacuation provides people with safe
refuge above maximum inundation height, while remaining within the inundation
zone. New Zealand guidance for vertical evacuation is being developed, building on
the USA’s Federal Emergency Management Agency’s published guidance and
informed by review of the March 2011 Japan event.
In principle, the research has shown that including provision for vertical evacuation in
the development at Te Tumu could reduce tsunami risk to an acceptable level. It
remains to be shown that development that includes vertical evacuation facilities can
also comply with other relevant planning provisions and be commercially viable.
Developed Areas
Part of the current settlement strategy for accommodating future urban growth in the
western Bay of Plenty sub-region is to facilitate a degree of residential intensification
and encourage business growth in established urban areas, in an appropriate form
and location. This creates a tension between strategic land use planning and hazard
management policy that needs to be carefully considered.
The risk to Pāpāmoa, an already developed area, has been assessed to be
intolerable. The risk to other already developed areas should also be assessed.
For existing developed urban areas, a key aim should be to manage future
development and subdivision within an agreed ‘tolerable’ risk profile. That risk profile
and related costs and benefits have yet to be discussed with affected people and
communities. Part of the current emergency management work through such
education programmes as ‘Tsunami Survive’ is to raise the awareness and
understanding of tsunami so that people are better informed to hold that
conversation, and can take personal responsibility for action in a catastrophic
emergency event.
Intensification should not increase risk above acceptable levels. In theory,
intensification involving multi-storied buildings providing opportunities for vertical
evacuation could be undertaken without increasing risk and could even reduce risk.
A1494330
4
Recommendations:
G1
That SmartGrowth, its constituent councils, and the CDEM Group collaborate in
releasing information on the tsunami hazard and in engaging the relevant
communities to manage the risk of tsunami in developed and yet to be
developed areas.
D
Developed Urban Growth Areas and partially developed areas with further
development options (including by intensification)
D1
That SmartGrowth partner Councils collaborate to develop planning and other
methods to manage tsunami risk.
D2
That SmartGrowth partner Councils engage with the community to define
‘acceptable’, ‘tolerable’ and ‘intolerable’ risk and appropriate land and building
development solutions.
D3
That Regional Council prioritise areas for risk assessment in developed areas
and undertake risk assessment.
D4
That Tauranga City Council funding for tsunami evacuation training be
extended to the ongoing support of the ‘Tsunami Survive’ education and
communication programme within Tauranga City.
D5
Review planning provisions in place for zoned but largely undeveloped Urban
Growth Areas to ensure that they include mitigation measures.
D6
That current mapping work on the extent of tsunami inundation from Mount
Maunganui to Pāpāmoa, and the low-lying areas around Tauranga Harbour
(within Tauranga City) be completed and the spatial information displayed on
GIS and made available to affected people and communities. This is to include
identification of potential local vertical evacuation points, such as Mauāo and
Mount Drury, and buildings within local neighbourhoods where that is possible.
D7.
That technical work be commenced to enable tsunami related information to be
provided on LIMs, PIMs, resource consents and building consents, as
appropriate to meet statutory requirements, at an individual land parcel level
where it is known.
D8.
That further consideration be given to the construction of local vertical solutions
in areas of the community where evacuation options outside of the inundation
area do not exist.
D9.
That, where private structures are identified as potential local vertical
evacuation options, work is undertaken with property owners on how these
structures could form part of a network of safe evacuation options for at risk
areas.
U
Undeveloped Urban Growth Areas
U1.
That the CDEM Group continue its tsunami research programme to provide
consistent coverage across the whole region. In particular, the effects of
tsunami on Waihī Beach and the northern Tauranga Harbour should be
examined.
U2.
That the Regional Council assess the risk of tsunami for future growth areas,
excluding Te Tumu which has already been assessed.
A1494330
5
U3.
That Te Tumu be retained in the settlement pattern for the SmartGrowth
Strategy Update.
U4.
That structure plans for undeveloped urban growth areas include tsunami
mitigation measures (including, where necessary, identified areas of
avoidance) which reduce the risk to, or maintain it at, an acceptable level.
U5.
That future sea level rise be taken into account in the design of tsunami
mitigation measures relating to undeveloped urban growth areas.
U6.
Undertake development viability assessments which incorporate the inclusion
of proposed hazard mitigation measures.
U7.
That CoastCare be supported in its protection of dunes that provide a natural
defence against coastal hazards including tsunami.
U8.
That tsunami risk awareness be included in the long-term SmartGrowth
Communications Strategy.
A1494330
6
1.
Purpose:
The purpose of this discussion paper is to consider whether, taking account of the
tsunami hazard and possible mitigation measures, SGIC can have confidence to
approve the Settlement Pattern for the SmartGrowth Strategy Update in relation to:
i)
Undeveloped Urban Growth Areas (specifically Te Tumu)
ii)
Developed Urban Growth Areas (in which the risk will be increased through
intensification).
2.
Background:
The SmartGrowth Strategy was adopted in 2004 and reviewed in 2007. SGIC has
adopted a project plan to update the current SmartGrowth Strategy and work has
commenced on that programme.
A significant amount of research is being undertaken as part of the SmartGrowth
Update.
The workstream report Review of Identified Residential Urban Growth Areas
(October 2012) noted that tsunami risk was subject to further technical assessment
and would be part of the discussion paper on Future UGAs in the New Year. This
discussion paper presents the findings of research that has been undertaken to
assess the tsunami risk to SmartGrowth and whether the risk can be reduced to an
acceptable level.
2.1
Natural hazards SmartGrowth context
As noted in Issues Discussion Paper (24 July 2012), the current SmartGrowth
Strategy contains a section on hazards which includes categories for assessing land
as to its suitability for urban development given the risk of natural hazards. The
Strategy advocates for a precautionary approach to hazard management.
During the life of the existing SmartGrowth Strategy, there has been a growing
awareness of natural hazards by the community. This awareness is driven by:
 The impacts of global warming/climate change i.e. more intense rainfall and
potentially more flooding
 The Canterbury earthquake sequence
 International earthquakes and tsunamis e.g. Fukushima earthquake and tsunami
in Japan 2011
 An increasing awareness of the need for Civil Defence.
The Bay of Plenty Regional Council has recently commissioned work which will
contribute to better understanding of potential tsunami impacts on coastal
development as well as the approach that should be adopted toward managing these
impacts. The impact of liquefaction arising from earthquakes on future settlement
patterns is also being investigated. The results of this work will be fed into the
Strategy Update. While the tsunami hazard is included in this discussion paper,
liquefaction is considered separately.
Tauranga is a coastal city with exposure to the risk of inundation from tsunami. The
greatest risk posed by tsunami on this portion of the Bay of Plenty coastline is an
event triggered along the Kermadec Trench, located north-east of New Zealand, and
is called a local source event. The at-risk areas of the city include the existing urban
areas developed along the Bay of Plenty open coast from Mount Maunganui to
Pāpāmoa (a distance of 19km) and those low-lying urban areas located adjacent to
Tauranga Harbour. The potential effect of a tsunami on a landform normally depends
A1494330
7
on the size and location of the source event and various local factors including the
shape of the coastline, its aspect to the tsunami source, land form, and type and
location of development.
Recent scientific work commissioned by BOPRC and undertaken by the Institute of
Geological and Nuclear Sciences in 2011 and 2012 has provided more accurate
information on the risks presented to this portion of the BOP coastline. Tauranga City
Council, using the data derived by GNS, is undertaking some additional work relating
to the areas affected by tsunami inundation to provide the community with more
accurate and up-to-date information on places to go to be safe should a local source
event occur. This work is being undertaken by TCC as part of the preparation of a
tsunami evacuation plan called Tsunami Survive. The preparation of the evacuation
plan has raised awareness and understanding of the possible risk associated with a
local source tsunami event, and this work is set to continue.
2.2
Natural hazards policy context
All Councils have statutory responsibilities for the management of natural hazards
and the provision of emergency management. Part of these responsibilities is
ongoing engagement with the community on these issues including discussing and
developing an understanding of what is ‘acceptable’, ‘tolerable’ or ‘intolerable’ risk.
What local people and communities are willing to accept needs to be weighed
against the likely costs of mitigation measures to ensure the level of risk is at a
tolerable level. Despite the timeframes for formally adopting policy varying
significantly between the Resource Management Act 1991 and the Civil Defence
Emergency Management Act 2002, the current policy frameworks are consistent.
Resource Management Act
The Resource Management Act 1991 defines natural hazard as any atmospheric or
earth or water related occurrence the action of which adversely affects or may
adversely affect human life, property, or other aspects of the environment. The
definition of natural hazard specifically includes earthquake, tsunami, erosion,
volcanic and geothermal activity, landslip, subsidence, sedimentation, wind, drought,
fire, or flooding. The Act provides that natural hazards are to be avoided or mitigated.
Following the Canterbury earthquake sequence 2010–2011, the Government
appointed a Technical Advisory Group to review sections 6 and 7 of the RMA. The
TAG was to focus on whether sections 6 and 7 could be improved including, in
particular, giving greater attention to managing issues of natural hazards (noting the
RMA issues arising from the Canterbury earthquakes). The TAG’s report to the
Government recommends changes to how the RMA deals with natural hazards; the
Government has not yet indicated its position regarding those recommendations. The
Resource Management Reform Bill introduced to Parliament late in 2012 inserts a
replacement Schedule 4, “Information required in application for resource consent”,
which carries forward a natural hazard clause from the existing Schedule 4: “any risk
to the neighbourhood, the wider community, or the environment through natural
hazards”. Substantive change in response to the TAG report is yet to be announced.
Until now, the tsunami hazard has not been addressed in the context of land use
planning to implement SmartGrowth. In deciding on Plan Change 44 (Wairakei), TCC
declined to consider the tsunami hazard on the basis that “its risk is difficult to
quantify and it is outside the 100-year planning horizon for hazard risk commonly
accepted under the RMA”. It stated that such “low probability events are
appropriately addressed as part of civil defence emergency management planning
including planning for evacuation”. It can be inferred that “risk” is used here as
meaning likelihood alone. Risk is now understood to be the combination of the
A1494330
8
likelihood and consequence of an event (New Zealand Coastal Policy Statement
2010, Glossary, Risk).
Recent Environment Court case law indicates support for addressing natural hazards
through land use planning on the basis of the risk they pose. Taking a risk approach
allows for low likelihood hazards such as tsunami to be addressed depending on
their consequences.
The NZCPS 2010 (to be given effect by the regional policy statement, regional plans
and district plans) specifically includes tsunami among coastal hazards to be
managed, over at least 100 years [emphasis added]. Objective 5 is to ensure that
coastal hazard risks are managed by:

locating new development away from areas prone to such risks;

considering responses, including managed retreat, for existing development in
this situation; and

protecting or restoring natural defences to coastal hazards.
The operative Bay of Plenty Regional Coastal Environment Plan includes as an
objective: No increase in the total physical risk from coastal hazards. District plans
may not be inconsistent with a regional plan. The next regional coastal plan is being
prepared.
The Proposed Bay of Plenty Regional Policy Statement has adopted a risk
management framework for managing natural hazards. It follows the New Zealand
Standards typology of acceptable, tolerable and intolerable risk (refer AS/NZS
ISO 31000:2009 Risk management — Principles and guidelines and SAA/SNZ
HB 436:2004 Risk Management Guidelines). The Proposed RPS policy regime
requires intolerable risk to be avoided, existing tolerable risk to be reduced and new
development to not be subject to risk that exceeds acceptable levels. BOPRC’s
decisions on submissions retained the risk management policy framework. The
decisions removed from the notified version the criteria for the thresholds between
the three risk levels in favour of requiring reference to authoritative guidance. The
decisions have been appealed to the Environment Court by developers, an energy
utility, a transport agency, and advocacy organisations from the environmental and
rural sectors. The appeals, which range from seeking technical changes to
questioning the concept of acceptable risk, are yet to be decided. The Proposed RPS
includes a method of implementation that obliges the BOPRC to assess the level of
risk due to volcanic eruption, earthquakes and associated hazards, and tsunami.
Another method obliges all local authorities to collaborate in gathering hazard
information and, with their communities, establishing levels of risk acceptability.
Explanation of the relevant policy states that, in the end, judgement is required to be
exercised by or under the authority of elected representatives.
As part of the resolution of appeals on the Tauranga City Plan, BOPRC and TCC
have entered into a Memorandum of Understanding. The two councils have agreed
to collaborate in preparing district plan provisions that implement the risk
management approach.
Several national guides on how to manage natural hazard risk through land use
planning have been published recently. (See, for example, Saunders, W.S.A.;
Prasetya, G. and Leonard, G.S. 2011. New Zealand’s Next Top Model: Integrating
tsunami inundation modelling into land use planning, GNS Science Miscellaneous
Series 34, 42p.) Further work is in preparation.
A1494330
9
Civil Defence Emergency Management Act
The purpose of the Civil Defence Emergency Management Act 2002 includes the
following relevant provisions:
(a) improve and promote the sustainable management of hazards (as that term is
defined in this Act) in a way that contributes to the social, economic, cultural,
and environmental well-being and safety of the public and also to the protection
of property; and
(b) encourage and enable communities to achieve acceptable levels of risk
including—
(i) identifying, assessing, and managing risks; and
(ii) consulting and communicating about risks; and
(iii) identifying and implementing cost-effective risk reduction; and
(iv) monitoring and reviewing the process; and
(c) provide for planning and preparation for emergencies and for response and
recovery in the event of an emergency; and
(d) require local authorities to co-ordinate, through regional groups, planning,
programmes, and activities related to civil defence emergency management
across the areas of reduction, readiness, response, and recovery, and
encourage co-operation and joint action within those regional groups.
Under this Act, the Bay of Plenty Civil Defence Emergency Management Group has
been established. The BOP CDEMG comprises all seven councils in the Bay of
Plenty: BOPRC, TCC, and Kawerau, Ōpōtiki, Rotorua, Western Bay of Plenty and
Whakatāne District Councils (but not Taupō District Council). As required by the
CDEM Act, the Group has prepared its Bay of Plenty Civil Defence Emergency
Management Group Plan 2012-2017. In keeping with the 4Rs set out in (d) above,
the Group Plan includes a section on Risk Reduction with the following principles:

Events that have the potential to cause a significant number of deaths or
injuries to people are not acceptable – human life and safety will therefore take
precedence over all other risk priorities.

Events that have the potential to cause severe economic losses, substantial
damage to buildings, infrastructure or lifeline utilities will be prioritised
according to their risk.

The Bay of Plenty CDEM Group is risk averse and will apply the prudent
person principle for managing risk. (Prudence is demonstrated by the process
through which risk is managed, the process by which strategies are developed,
adopted, implemented, monitored and reviewed, based on an established
policy and review procedure, in light of their purposes.)

Hazard information is to be freely available to enable the community to engage
in decisions about the acceptability of the risks they face and to equip
individuals to act to reduce their own risk.

Comprehensive risk reduction is achieved through integrated planning and risk
management across all councils, and at the ‘all-of-council’ level within each
council, taking a multi-agency all-of-government approach, involving central
government and partner agencies such as lifelines and utility providers.
The Group Plan acknowledges that the CDEM Group is only one part of the region’s
risk management context, which involves many other stakeholders including central
government organisations, local authorities, emergency services and lifeline utilities.
Additionally individuals and communities should consider risk reduction. The Group
Plan notes that other statutes that provide legislatively for risk reduction include:

Resource Management Act 1991

Local Government Act 2002

Building Act 2004

Soil Conservation and Rivers Control Act 1941
A1494330
10
as well as growth strategies, guidelines and plans.
CDEM uses the framework of the 4Rs to meet its responsibilities under the CDEM
Act in any community. The 4Rs provide a useful basis for outlining the thinking in
regard to tsunami:
Reduction
 Land use planning and building design and construction provisions to reduce the
level of existing tsunami risk to a tolerable level and managing new development
within acceptable risk through such methods as City Plan policy and rules on new
development, subdivision and/or building design. Examples of the methods may
be minimum floor/platform heights, specific building design to resist tsunami
forces, and the provision of local vertical evacuation options in identified hazard
areas. The preference is to apply a remedy or mitigation when new development
occurs rather than retrofitting existing developed areas. Such controls will have a
cost impact which has, at this time, not been considered or quantified.
Consideration of cost and benefit impacts would form part of any community
discussion on what constitutes ‘acceptable’, ‘tolerable’ and ‘intolerable’ risk.
 Ongoing work is being undertaken by TCC using the GNS tsunami model outputs
to gain more accurate understanding on the potential extent of tsunami
inundation on Tauranga City. This work will provide a greater understanding of
the effects on people and property and will assist in appropriate planning
techniques (Reduction), public education and evacuation planning (Readiness),
and evacuation (Response).
 As part of the further work TCC is aiming to identify/map areas that are safe to
evacuate to, either by distance or vertically. Further consideration needs to be
given as to how the community could access some of the areas of vertical
evacuation that may be identified as well as the need to construct local vertical
evacuation facilities. Undertaking this work will ensure that people have a safe
place to go in a timely manner in the event of a ‘worst case’ tsunami.
Readiness
 Distribution to the community of the completed ‘Tsunami Survive’ evacuation plan
is planned for 2013.
 Proactive education of local people and communities through the TCC “Tsunami
Survive” education programme. TCC staff have been working through community
networks in the low-lying parts of Tauranga and the open coastal areas along
Mount Maunganui to Pāpāmoa to communicate messages on preparation,
responsibility and action plans if a tsunami event occurs.
 The focus for 2013 is to heighten the awareness of the issue within individual
households. The aim is to gain acknowledgement by individuals of their personal
responsibility to prepare and take action in a tsunami emergency event.
 Council is in the process of installing tsunami sirens for the most affected areas
of the city. It is noted however that sirens are best suited for regional and distantsourced tsunami events, rather than local events which pose the greatest risk.
 Information on tsunami is proposed to be placed with Land Information
Memoranda (LIMs), Project Information Memoranda (PIMs), resource consents
and building consents. Further technical work is required to bring the information
to a point where it meets the needs of Council’s statutory responsibilities. This will
inform engagement with the community on this matter, subject to TCC elected
members’ direction.
Response
 Response commences when an actual tsunami threat or event occurs. CDEM at
Local, Regional and National levels provides a lead role and works with
emergency services, public agencies and other service providers to appropriately
respond to the event. Part of the response may include radio messaging,
A1494330
11
activation of warning sirens, traffic management, or in the case of a minor threat,
placing warnings for people on beaches and at boat ramps.
Recovery
 CDEM works with welfare and utility organisations, local and regional authorities,
public agencies and service providers to support the affected community to reestablish the community structures and return to normality as promptly as
possible.
 BOP has two CDEM groups, the Welfare Advisory Group and the Lifeline Group
for infrastructural assets, whose role is to improve multi-agency communications.
This greater understanding of the relationships between organisations will both
assist in reducing impacts and enhance the speed of recovery.
Supporting the CDEMG is the Coordinating Executive Group (CEG), a statutorily
mandated committee made up of the CEOs (or their representative) of local
authorities, Fire Service, Police, District Health Boards, the Medical Officer of Health
and the Group Controller.
Integration of policy response
The role of the RPS in achieving integrated management and the co-ordinating
structure of the CDEM Group both point to local authorities in the region combining to
develop and implement a consistent approach to engaging with the community about
tsunami. The roles entrusted to councils carry a corresponding responsibility: the
duty for councils to carry out their functions with reasonable skill and care2; councils
ought to know that, if they do their work badly, people may be injured or worse3.
2.3
Tsunami research context
Research into the tsunami hazard to the Bay of Plenty region was commenced in
2001. A 2002 paleotsunami study found evidence of past tsunami and led to further
studies over the following decade. One output derived from these studies is mapped
tsunami evacuation zones.
The Ministry of Civil Defence and Emergency Management recognises four
development levels for mapping tsunami evacuation zones. The recommended
approach is to map now, and progressively refine the accuracy of boundaries as the
science improves over time. As the understanding of local tsunami hazard and risk
improves, the level of technical sophistication used in defining tsunami hazard and
evacuation zones should be advanced. Until higher stage assessments can be
undertaken, a precautionary approach is recommended.
In the Bay of Plenty, maps have been prepared to the recommended minimum
Level 2 standard of the Director’s Guideline for Civil Defence Emergency
Management Groups (December 2008). The Level 2 maps were published in
December 2010 and can be viewed on:
http://www.bopcivildefence.govt.nz/bay-of-plenty-hazards/natural-hazards/#Tsunami
The latest two GNS studies, the subject of this discussion paper, followed four
reports commissioned by the CDEM CEG. One of those four reports identifies
possible tsunami sources and two relate to SmartGrowth’s area of interest. (These
four reports have not yet been released by the CEG.) It should be noted that the
CEG-commissioned research does not cover Waihī Beach. After receiving a
2
After North Shore City Council v Body Corporate 188529 (Sunset Terraces) and Ors, SC
27/2010, at [17].
3 After Body Corporate No. 207624 v North Shore City Council SC 58/2011, at [76].
A1494330
12
presentation on a draft of one of the reports, SmartGrowth’s Implementation
Management Group requested that BOPRC commission GNS to provide a further
report examining the risk to Pāpāmoa, Wairakei and Te Tumu assuming ground
levels were modified to reflect the final constructed situation. In turn, this led to
another report examining whether mitigation could reduce Te Tumu risk to an
acceptable level. These latest two GNS reports are the subject of this discussion
report:
Modelling of the tsunami risk to Papamoa, Wairakei and Te Tumu assuming an
altered ground level due to development of Wairakei and Te Tumu, and the
implications for the SmartGrowth Strategy, GNS Science Consultancy Report
2012/54, September 2012, and
Modelling of the evacuation rates required to achieve an acceptable level of health
and safety risk in Te Tumu from the Variation to the Southern Kermadec Scenario,
GNS Science Consultancy Report 2012/291, December 2012.
The more detailed modelling undertaken for these reports would meet CDEM Level 3
standards except that the necessary probabilistic analysis is not yet available.
An earlier report “Tsunami source study”, referenced in Beban et al. September 2012
section 1.5 as “Goff et al (2006)”, found that some paleotsunami sites could not be
explained by the modelling available at that time. Modellers had been unwilling to use
scenarios with initiating seismic events of magnitude Mw 8.5 to 9.0 since, at that
time, the geophysical consensus understanding of subduction zones did not support
such large events. The Great East Japan earthquake in March 2011, magnitude
Mw 9.0, demonstrated that such large events are possible. Lessons from that
subduction trench event have been taken into account in the scenarios modelled in
these latest two reports. The modelled results now align with the paleotsunami
evidence, adding credibility to both the paleo evidence and the modelling.
These latest two reports have been prepared specifically to feed into the review of
the Settlement Pattern for the SmartGrowth Strategy Update.
2.4
Risk comparison context
Taking a risk approach provides a common basis for comparing different hazards.
Deaths are the predominant contributor to the “consequence” factor in risk. The first
report (Beban et al. September 2012, section 3.12) includes a comparison of the risk
of death from tsunami and earthquakes. This indicates that, for events with
equivalent return periods, the number of deaths from tsunami is several orders of
magnitude greater than from earthquakes. The comparison assumes no evacuation.
(Evacuation is discussed in the next section.) Property damage repair costs were
also estimated to be much greater for tsunami than for earthquakes.
This is consistent with an analysis undertaken following the disastrous Boxing Day
tsunami in the Indian Ocean in 2004 and reported in Webb 20054. The Webb report
compares the risk from tsunami for a number of New Zealand cities in which
Tauranga’s tsunami risk is shown as mid-range among the cities. Taig et al. 20125
includes a brief analysis of tsunami risk for some east coast cities (including
Whakatāne but not Tauranga); it concludes: “…tens of thousands of people in these
Webb, T. 2005. Review of New Zealand’s preparedness for tsunami hazard, comparison to
risk and recommendation for treatment, GNS Client Report 2005/162
5 Taig, T., Massey, C., Webb T. 2012. Canterbury Earthquakes Port Hills Slope Stability:
Principles and Criteria for the Assessment of Risk from Slope Instability in the Port Hills,
Christchurch, GNS Science Consultancy Report 2011/319
4
A1494330
13
cities are likely to be living with tsunami annual individual fatality risk in excess of 10-5
per year, while hundreds, if not thousands, are likely to be living with tsunami annual
individual fatality risk in excess of 10-4 per year. Such risk levels are the reason for
substantial initiatives having been taken in the relevant communities to mitigate
tsunami risks.” Annual individual fatality risk in excess of 10-5 per year is in the
“tolerable” risk range; in excess of 10-4 per year is “intolerable”. This situation
corresponds with a comment made by Taig (section 3.1.3) as involving “hazards of
which people had been aware of for some time without necessarily recognising the
level of risk involved (the risk might have been “accepted”, without being deemed
“acceptable” with reference to relevant risk criterion).” Webb commented (section
3.1), “In general, New Zealanders have had little opportunity to be well-informed in
terms of the associated risks of a coastal habitation.”
Comparison with volcanic risk has not been undertaken but it is expected that
warning systems would enable fatalities to be minimised in a large majority of
volcanic events (Taig et al. 2012); in any case, the volcanic risk to the SmartGrowth
area is not spatially differentiated and any mitigation would apply across the whole
area. This also applies to seismic risk: few if any fault lines are within the
SmartGrowth area leaving the shaking hazard to be addressed by engineering and
the Building Act; the liquefaction hazard deriving from earthquakes is addressed
separately.
2.5
Evacuation context
To inform planning for evacuation, tsunami sources that impact on New Zealand can
be divided into three categories:
• Distant source — more than 3 hours travel time from New Zealand;
• Regional source — 1–3 hours travel time from New Zealand; and
• Local source — 0–60 minutes travel time to the nearest New Zealand coast.
The second report (Beban et al. December 2012) assesses the scenario that causes
the greatest level of inundation, the Variation to the Southern Kermadec Scenario.
The travel time of such a tsunami to the study area is approximately 50 minutes
qualifying this scenario as a local source. The Webb (2005) report noted that there
are no formal warning arrangements for local-source tsunami. “… [E]ffective local
warnings are not currently available and are likely to take considerable time to
develop …”. Although seven years have passed, this statement holds true. The
Ministry of CDEM6 advises people to respond to natural warning signals:
“Natural warning signals are of key importance in response to local source tsunami
and they may be the only warnings possible for local or regional source tsunami.
• Strong earthquake shaking (i.e. it is hard to stand up)
• Weak, rolling earthquake shaking of unusually long duration (i.e. a minute or more)
• Out of ordinary sea behaviour, such as unusual and sudden sea level fall or rise
• The sea making loud and unusual noises, especially roaring like a jet engine.
“When experiencing any of the above go immediately to high ground or, if the
surrounding area is flat, go as far inland as possible, evacuating all coastal areas or,
where present, all evacuation zones. The first wave may arrive within minutes. Once
away from the water, listen to a radio station for information from local civil defence
about further action you should take.”
Working from the same page — consistent messages for CDEM, PART B: Hazard-specific
information — Tsunami. Published by the Ministry of Civil Defence & Emergency
Management, Version 1.0 April 2010
6
A1494330
14
Traditionally, evacuation has aimed to move people out of the inundation zone
entirely, inland or to high ground. The physical setting of Te Tumu, at the end of a
sand spit with a river and low ground on the landward side, precludes the option of
going inland and evacuating all coastal areas. However, some high ground exists,
opening the possibility of vertical evacuation. Vertical evacuation provides people
with safe refuge above maximum inundation height, while remaining within the
inundation zone. New Zealand guidance for vertical evacuation is being developed,
building on the USA’s Federal Emergency Management Agency’s published
guidance and informed by review of the March 2011 Japan event.
3.
Research findings:
The reports found that, assuming no evacuation, the study areas of Pāpāmoa,
Wairakei and Te Tumu are subject to intolerable risk from tsunami. These are the
first SmartGrowth areas where the consequences of tsunami have been analysed
and the risk assessed. It is likely that the level of risk throughout the settlement
pattern will vary and further work is recommended to assess the specific risk of other
developed and undeveloped urban growth areas in relation to their coastal location.
The research reported in the first report (Beban et al. September 2012) examined
twelve scenarios with the potential to generate tsunami that could affect the Bay of
Plenty. Tsunami from several Kermadec Trench scenarios could significantly
inundate the study area. This is consistent with the findings of the research that has
been undertaken over the last decade. When the risk (consequence and likelihood)
of these events for Pāpāmoa, Wairakei and Te Tumu was assessed against criteria
for acceptable, tolerable and intolerable risk, the risk was found to be intolerable.
The second report (Beban et al. December 2012) found that, with vertical evacuation
facilities and a combination of land use planning and emergency management
measures, an acceptable level of risk could be achieved for Te Tumu. Te Tumu was
the first area assessed in this way so as to inform the SmartGrowth review of the
Settlement Pattern for the SmartGrowth Strategy Update. Such mitigation measures
may be an option to be assessed elsewhere.
The research reports acknowledge that there is a high degree of uncertainty in
tsunami source models. Uncertainty arises under both aspects of risk: likelihood and
consequences.
In the second report (Beban et al. December 2012), the likelihood of the modelled
scenario (the Variation to the Southern Kermadec Scenario) derives from the “return
period” ascribed to the causal event: 610 years. This is back-calculated from the slip
observed in the Great East Japan earthquake in March 2011, the amount of
convergence of the tectonic plates required to produce that slip, and the time for the
average rate of plate convergence to produce that convergence. As such, the return
period is conservative in that each of these factors are optimised to produce the
minimum return period.
As reported in the first report (Beban et al. September 2012) other scenarios with
similar effects (the Kermadec-Hikurangi Scenario and Variation of the Whole
Kermadec Trench Scenario) have return periods of 360 years and 540 years
respectively. (The researchers acknowledge that it is possible that earthquakes as
large as those in these scenarios do not occur.) While the tsunami-producing
mechanisms described in the scenarios suggest a cyclic return period, the
possibilities raised by several such scenarios, each with its own return period,
introduce an element of randomness. The return periods are therefore inversed to
produce an indicative frequency or its approximate reciprocal, the annual
exceedance probability. This provides the probability or likelihood of an event
A1494330
15
occurring in any one year, rather than implying that such events occur at regular
intervals. Nevertheless, it is sobering to note that the paleotsunami evidence is that
large events, similar to the modelled scenario, last occurred 500–600 years ago.
In regard to “consequence” uncertainty, the second report (Beban et al. December
2012) assessed the degree of evacuation that would be required to achieve the
necessary acceptable risk. It found that, of a design population of 20,000 people,
6000 are required to evacuate for a night-time event and 7000 for daytime. The
report states that those people who do not evacuate are assumed to remain in their
respective buildings and be located above the ground floor. This implies that all of the
design population is safe. However, the tables showing how the evacuation rates are
determined show that (various) numbers of deaths are expected. However, the risk of
death (the combination of the event’s likelihood and the consequence (number of
deaths)) is nevertheless assessed as acceptable against the criteria adopted. The
minimum evacuation rates required to achieve an acceptable risk in relation to
various land uses are:
Housing (low density)
Housing (medium density)
Retirement
Mixed-use
Apartment Block
Rest-home/hospital
Education
Night time
37%
27%
100%
0%
0%
50%
0%
Day time
37%
27%
100%
35%
0%
50%
59%
These evacuation rates are presented by the researchers as showing that an
acceptable level of risk can be achieved. However, the report contains no statement
about the achievability of those evacuation rates. A report on evacuation lessons
learned from the Great East Japan earthquake in March 20117 refers to previous
studies. In Kesennuma City following a local offshore earthquake in 2003 (with
shaking at the high end of the range expected from the scenarios modelled for Te
Tumu (see next paragraph)) and despite regular education and evacuation drills,
almost 86% of residents did not evacuate. Evacuation rates reported for the 2011
event ranged between 20% and 72%. The requirement for 100% evacuation from
“Retirement” suggests that that land use may not be appropriate for the Te Tumu
area. It appears that the required evacuation rates may be challenging to achieve.
As noted above, formal warnings are unlikely to be issued before the arrival of a
tsunami with associated intolerable or tolerable risk and natural signals may provide
the only warning. The first report (Beban et al. September 2012, section 3.12)
includes estimates of the shaking that would be felt in the study areas of Pāpāmoa,
Wairakei and Te Tumu from the studied tsunami scenarios. Tsunami giving rise to
tolerable risk would result from scenarios with shaking intensities ranging between
5.3 and 7.1 Modified Mercalli Intensity; tsunami with intolerable risk from scenarios
with shaking intensities of 7.7–8.3. The relevant range from a simplified Modified
Mercalli Intensity Scale, further modified to suit New Zealand conditions, is presented
in the table below8:
7
Fraser, S.; Leonard, G.S.; Matsuo, I. and Murakami, H. 2012. Tsunami evacuation: Lessons
from the Great East Japan earthquake and tsunami of March 11th 2011, GNS Science Report
2012/17. 89 p.
8 http://www.gns.cri.nz/Home/Learning/Science-Topics/Earthquakes/MonitoringEarthquakes/Other-earthquake-questions/What-is-the-difference-between-Magnitude-andIntensity/The-Modified-Mercalli-Intensity-Scale
A1494330
16
Category
Definition
MM 5: Strong
Generally felt outside and by almost everyone indoors.
Most sleepers are awakened and a few people alarmed.
Small objects are shifted or overturned, and pictures
knock against the wall. Some glassware and crockery
may break, and loosely secured doors may swing open
and shut.
MM 6: Slightly damaging
Felt by all. People and animals are alarmed, and many
run outside. Walking steadily is difficult. Furniture and
appliances may move on smooth surfaces, and objects
fall from walls and shelves. Glassware and crockery
break. Slight non-structural damage to buildings may
occur.
MM 7: Damaging
General alarm. People experience difficulty standing.
Furniture and appliances are shifted. Substantial damage
to fragile or unsecured objects. A few weak buildings are
damaged.
MM 8: Heavily damaging
Alarm may approach panic. A few buildings are damaged
and some weak buildings are destroyed.
MM 9: Destructive
Some buildings are damaged and many weak buildings
are destroyed.
While some natural signals may therefore be able to be detected, effective
evacuation will be dependent on the preparation and implementation of an entire
evacuation strategy. (Not all tsunami sources generate natural signals; for example,
some tsunami (not included among scenarios reported here) may be generated by
non-seismic processes.) Ongoing community engagement, sustained tsunami
education and evacuation training is required to ensure appropriate evacuation
response to natural signals so that individuals act to reduce their own risk.
3.1
Research limitations
The first report (Beban et al. September 2012) specifically discusses the limitations of
the research in sections 1.1, 2.5, 3.13 and 4.8. While acknowledging the limitations,
the modelling meets the principles in AS/NZS ISO 31000:2009 Risk management —
Principles and guidelines. In particular, the reports:
 help decision makers take account of uncertainty, and are
 systematic,
 based on the best available information and
 responsive to change.
A1494330
17
Modelling of tsunami and their associated risk is a developing discipline. Much was
learned from the March 2011 Tohuku event in Japan where the amount of slip was
much greater than expected; the Japan event occurred in a subduction zone similar
to the Kermadec Trench.
The research has shown that, in principle, provision for vertical evacuation can be
included at Te Tumu so that tsunami risk is reduced to an acceptable level. It
remains to be shown that development that includes vertical evacuation facilities can
also comply with other relevant planning provisions. For example, the researchers’
assumptions include two ten-storey apartment blocks along the northern boundary of
Te Tumu, just landward of the coastal dunes. It is not known whether such towers
would meet obligations to protect the natural character of the coastal environment.
Structure planning that incorporates evacuation requirements is still required to be
undertaken and tested to ensure that it complies with the regional and city planning
regime.
No analysis of the economic or commercial viability of including provision for vertical
evacuation in development at Te Tumu has been undertaken.
The areas of Pāpāmoa, Wairakei and Te Tumu are the first to be researched to
determine their level of tsunami risk; Te Tumu is the first to be investigated to
determine whether intolerable risk can be reduced to an acceptable level. It is likely
that the level of risk throughout the SmartGrowth settlement pattern will vary. Further
work is recommended to assess the specific risk of other developed and
undeveloped urban growth areas, such as North-west Bethlehem, Katikati Stages 1
& 2, Ōmokoroa Stages 1 & 2, and Waihī Beach Stages 1 & 2, in relation to their
coastal location.
The modelling is based on current sea level and does not account for any sea level
rise over time.
4.
Conclusions:
4.1
Developed areas
In the Tauranga City area there is a significant established population, estimated to
be 51,000 people, in areas that are predicted to be affected by tsunami, with the
remainder of the population likely to be indirectly affected by a ‘worst case’ event.
This number will vary depending on time of year, day in the week and time of day.
Among councils’ key statutory functions are control of the use of land to avoid or
mitigate natural hazards (regional council) and control of any actual or potential
effects of the use, development or protection of land to avoid or mitigate natural
hazards (city and district councils); tsunami are natural hazards. In planning terms
there are policy aims set out in the Resource Management Act 1991, the Regional
Policy Statement, Tauranga City Plan and Western Bay of Plenty District Plan that
cannot be ignored and will influence development/redevelopment provisions for land
use and building going forward.
Part of the current settlement strategy for accommodating future urban growth in the
western Bay of Plenty sub-region is to facilitate a degree of residential intensification
and encourage business growth in established urban areas, in an appropriate form
and location. This creates a tension between strategic land use planning and hazard
management policy that needs to be carefully considered.
The risk to Pāpāmoa, an already developed area, has been assessed to be
intolerable. The risk to other already developed areas should also be assessed.
A1494330
18
For existing developed urban areas, a key aim should be to manage future
development and subdivision within an agreed ‘tolerable’ risk profile. That risk profile
and related costs and benefits have yet to be discussed with affected people and
communities. Part of the current emergency management work through such
education programmes as ‘Tsunami Survive’ is to raise awareness and
understanding of tsunami so that people are better informed to hold that
conversation, and can take personal responsibility for action in a catastrophic
emergency event.
One principle that might be applied for existing developed areas is that where people
cannot easily reach safety for various reasons, measures should be in place to
increase their safety and /or chances of survival. This principle and the ‘tolerable’ risk
policy suggest that new provisions relating to land use activity and/or building design
be applied within areas identified as susceptible to inundation from tsunami. Such
provisions could include minimum floor/platform levels or specific building design for
dwellings or buildings located in a tsunami risk area. Allied to this would be displaying
on mapping systems those existing areas or buildings that could be used for local
vertical evacuation facilities.
Intensification should not increase risk above acceptable levels; in areas of existing
development subject to tolerable risk, the risk should be reduced to be as low as
reasonably practicable (not increased). In theory, intensification involving multistoried buildings which provide for vertical evacuation could be undertaken without
increasing risk and could even reduce risk.
4.2
Undeveloped areas
Research has modelled tsunami effects on the coast of much of the area covered by
SmartGrowth. Recent research (some yet to be released) does not cover all of the
SmartGrowth coast. In particular, tsunami effects at Waihī Beach and the northern
Taranga Harbour have not been modelled in the recent research.
Risk arising from the recently modelled tsunami has been assessed for Wairakei
(approved for development but as yet undeveloped) and for Te Tumu, which is being
reconsidered for development. Without evacuation, the risk in both these areas has
been found to be “intolerable” for several tsunami scenarios.
Further research has examined the risk to Te Tumu assuming several areas of
existing high ground will be retained and engineered to provide vertical evacuation
facilities. This research has found that, in principle and subject to the preparation and
implementation of an entire evacuation strategy development could be undertaken
without risk exceeding acceptable levels.
This “in principle” finding may be sufficient to justify not removing Te Tumu from
being a future growth area for SmartGrowth. Further work is required to demonstrate
that development could be formally approved.
The risk to other growth areas should also be assessed and managed according to
the level of risk presented.
Recommendations are included in the Executive Summary.
A1494330
19
Download