CHAPTER 7. Improvement Proposals

advertisement
CHAPTER 7. IMPROVEMENT PROPOSALS
7.1
INTRODUCTION
Formulation of improvement Proposals is a pre-requisite for development of any project facility.
Highway Improvement options ought to be technically sound, environmental friendly, and
economically most feasible. They not only include formulation of typical cross sections separately
for rural and urban areas depending on requirements of capacity augmentation, but also include:

Provision of rural service roads to interconnect two near by cross roads;

Identification of urban areas that require Bypasses/Re-alignments;

Identification of optimal bridge alignments;

Provision of pedestrian/vehicular underpasses

Provision of bus bays and bus shelters

Provision of way side amenities

Provision of toll plaza
The first step that is required to identify improvement options is to collect information on the
project corridor primarily from engineering surveys and secondarily from various agencies
concerned. Information on past and present traffic, availability of land, condition of CD structures,
potential sources of construction material, environmentally sensitive areas and social hot spots
has been collected from secondary sources. Information pertaining to existing urban settlements,
present configuration of intersections, importance of cross road, utility lines, locations of bus
stops, truck parking has also been collected from primary surveys. Close observation of all these
parameters coupled with frequent site visits lead to identification and finalization of improvement
options for the project corridor.
The project corridor predominantly traverses through rural areas with intermittent settlements at
close intervals. These settlements generally have an intersection coupled with residential and
commercial developments along the corridor. The rural sections of project corridor do not pose
any major concern except for acquiring additional land to make a total land width of 60m as
ROW, which may call for acquisition of some structures along the corridor in rural areas.
The choice available for widening in rural areas are i) Symmetrical widening and ii) Widening
eccentrically. The decision of eccentric widening on either side of the existing road is dependent
upon which side merits preference and the distance of the existing centerline from the RoW
boundaries. The factors influencing the preference are:

Availability of land

Geometric improvement

Utility Lines

Ribbon developments and settlements

Environmental and Social concerns
It is preferred to widen the corridor eccentrically wherever site conditions permit to utilize the
existing formation completely and to avoid two longitudinal joints on either side. Also this would
7-1
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
ensure uninterrupted traffic movement during construction. It is proposed to provide pedestrian
underpasses at locations of schools and rural settlements along the project corridor to avoid
pedestrians entering main carriageway.
Accordingly, the widening options considered for rural sections are

Eccentric Widening on left hand side

Eccentric widening on right hand side
At certain location along, where the developments are on both sides of the project corridor such
as at Banduri (Existing Km 95.0 to 96.0) and at Gadu (Existing Km 101.5 to 102.8), concentric
widening has been resorted to avoid destruction of properties along the road side.
There are few major urban areas along the corridor, namely Nawagadh, Jetpur, Junagadh and
Kesod. Apart from these, there are several other minor settlements and villages along the
corridor where it has been observed that there is sufficient commercial activity and movement of
pedestrians within the settlements. In order to segregate the through traffic from local traffic and
to provide safe passage to slow moving non-motorized vehicles, it is proposed to plan bypass or
realignments for above urban settlements.
At sharp curve locations realignments have been proposed in order to meet the design speed
criteria.
7.2
BYPASS CANDIDATES
Nawagadh and Jetpur are twin settlements at the beginning of the project corridor which are
connected with each other and have continuous developments on either side of the road
Presently all the traffic is moving through these developments is experiencing severe
congestion. Apart from these developments there are two railway crossings, one is a Road under
Bridge (RUB), with insufficient clearance and the other one is at grade level crossing. Hence it is
required to bypass initial developments of Jetpur-Nawagadh.
Junagadh is Major urban settlement along the corridor, which is presently having a two lane
bypass for about 10km length. Part of this bypass is yet to be constructed on Jetpur side as it
requires a ROB. Presently, an existing state highway is used for this missing link which has one
at grade railway crossing. There are very little developments adjacent to this existing bypass for
substantial length except for end section on Somnath side of Junagadh, continuous
developments have been observed along the bypass and beyond the existing bypass for a length
more than 1 Km. Further to this, Project corridor has an at-grade junction at the end where the it
takes a perpendicular right turn towards Somnath. There is one at-grade railway crossing near
the end of bypass. Beyond, the bypass, the existing road again crosses the same railway line
with a two lane ROB. Hence, there would be a requirement of extending/connecting exiting
bypass at both ends for Junagadh town.
Kesod is another major urban settlement along the corridor, which is presently having a four lane
divided road for some length. The project corridor mostly traverses through continuous
7-2
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
settlements in the Kesod town with substantial local traffic movement. There is a bypass
proposal that has been already made for this town on right hand side of the town while moving
towards Somnath by the R & BD,-NH division and a land width of 30m has already been
acquired for the same.
In addition to these three major settlements, two minor settlements at Vanthali (Km 46.5) and
Agatrai (Km 61) along the corridor require realignments.
The above settlements require bypasses/realignments because of continuous and thick ribbon
developments, non-availability of Right of Way and poor geometry. There are proper buildings
very close to the existing carriageway at these locations. It would not be possible to
accommodate four lane cross section with service roads through these urban areas within the
available ROW. Acquisition of land through these settlements appears to be difficult due to social
resistance. Initial appreciation of these urban areas revealed that there is enough space to take
bypasses on either side of towns. Details of these realignments are given below in the table.
Elaborate description of bypass alignments is presented in the next chapter in this volume of the
report.
Table 7-1: Details of Bypass/Realignments
Proposed Chainage (Km)
S.No
From
to
Side
0.765
Right
Name
1
0.000
4.700
4.700
Right
2
23.450
24.750
1.300
Right
Bypass/ Realignment (RHS)
Along the NH-8B upto Unidirectional
Flyover at
Jetpur Bypass, Start point is at Km 111 of
NH-8B
Junagadh Bypass-1
3
32.500
40.450
7.950
Right
Junagadh Bypass-2
4
43.700
44.350
0.650
Left
Vanthali Realignment
5
58.100
60.300
2.200
Left
Agatrai Realignment
6
63.600
75.000
11.400
Right
Kesod Bypass
1
7.3
Length
(km)
GRADE SEPARATORS/ UNDERPASSES
It is proposed to provide flyovers/vehicular underpasses at some locations of major intersections
and urban areas in order to provide an uninterrupted flow for through traffic moving on the project
corridor. These flyovers/underpasses were proposed to have 2-lane configuration in each
direction with service roads at ground level for movement of local traffic.
In addition to above, it is also proposed to provide vehicular underpasses in newly proposed
bypass alignments where alignment crosses a major road and cattle passes in rural sections
where agricultural lands and village are separated by project corridor.
Details of these grade separators/underpasses are mentioned below in the following sub
sections:
7-3
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
7.3.1
Flyover / Vehicular underpasses
Table 7-2: Locations of Flyovers
S.No
Proposed
Chainage
1
0+750.754
7.3.2
Existing Chainage
Span Arrangement
Start point of Jetpur Bypass
2x45m (Unidirectional)
Remarks
Start point of project corridor,
junction with NH-8B
Vehicular Underpasses
Table 7-3: Locations of Vehicular Underpasses
S.No
Proposed
Chainage
Existing Chainage
1
24.715
26.300
2
68.720
Kesod Bypass
3
4
110.227
116.205
114.750
121.000
7.3.3
Size (Nos. x
span x height in
m)
2x10.25x5.5
2x10.25x5.5
2x10.25x5.5
2x10.25x5.5
Remarks
Doraji-Junagadh SH crossing at
Junagadh
SH intersection to Mangrol/
Porbandar at Kesod Bypass
Dari-Sathroda Road crossing
Sasan-Veraval SH crossing
Pedestrian/Cattle Underpasses
Table 7-4: Locations of Cattle/Pedestrian Underpasses
S.No
Proposed
Chainage
1
1.706
2
6.100
3
4
5
6
7.4
20.000
34.225
37.050
55.650
7
58.797
8
9
10
11
12
13
64.882
71.500
91.050
94.699
106.100
119.900
Size (Nos. x span x
height in m)
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
1 x 4 x 3.5
Remarks
Jetpur Bypass
Jetalsar Village
Vadala village
Junagdh Bypass
Junagdh Bypass
Manekwada
Agatrai Bypass
Kesod Bypass
Kesod Bypass
Banduri Village
Zadka Village
Near Supasi Village
Balpura Village
SERVICE ROADS
Service roads of adequate width have been proposed between two close-by intersections or
settlements to enforce proper access control along the corridor. Service roads in the form of slip
roads have been also proposed at all VUP and Flyover locations and at few PUP locations.
These details have been provided in chapter 9 of this volume.
7-4
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
7.5
WIDENING OPTIONS
A detailed evaluation of the information collected and options described in the preceding
subsections has enabled formulation of widening scheme that best suits the different stretches of
the Project Road. Whilst details of these are provided in the Chapter 9: Preliminary Designs of
this report, tentative length of proposed individual widening options along the project corridor is
given in table, Table 7-5, below:
Table 7-5: Length of Widening Options Considered
S.No
Widening Option
Code
Total Length (Km)
1
Eccentric widening on LHS while moving towards Somnath
EL
27.250
2
Eccentric widening on RHS while moving towards Somnath
ER
54.750
3
Concentric
CON
7.325
4
Bypass and Realignments
BYP/RE
34.165
Total length (as per design chainage)
7.6
123.490
TYPICAL CROSS SECTIONS
Cross sectional elements are based on the design standards and specifications set in the earlier
chapters. The lane width shall be 3.5m, paved shoulder width 1.5m, hard shoulder width 1.5m,
median width 4.5m/1.5m and shyness strip 0.25m on both sides of median. While lane width for
service roads and slip roads is 5.5m/7.0m.
Based on foregoing considerations various typical cross sections have been developed for the
project corridor to suit the specific site requirement. The following table presents the summary of
cross section schedule while the details are elaborated in the Chapter 9: Preliminary Designs of
this report.
Table 7-6: Summary of Cross Section Schedule
S.No
Cross
Section Type
1
Type I
Typical Cross Section for LHS Widening without Service Road
20.485
2
Type II
44.485
3
Type II-A
4
Type III
Typical Cross Section for RHS Widening without Service Road
Typical Cross Section for RHS Widening without Service Road (median 4.5m t0
20m)
Typical Cross Section for New Construction without Service Road
5
Type IV
9.655
6
Type IV-A
7
Type V
8
Type V-A
9
Type VI
Typical Cross Section for Reconstruction without Service Road
Typical Cross Section for Reconstruction without Service Road (median 4.5m t0
20m)
Typical Cross Section for LHS Widening with both side 7.0m Service Road
Typical Cross Section for LHS Widening with both side 7.0m Service Road WITH
1.5M MEDIAN
Typical Cross Section for RHS Widening with both side 7.0m Service Road
10
Type VII
Typical Cross Section for Concentric Widening with both side 7.0m Service Road
2.000
11
Type VII-A
0.500
12
Type VII-B
13
Type VIII
Typical Cross Section for Concentric Widening with both side 5.5m Service Road
Typical Cross Section for Concentric Widening with both side 5.5m Service Road
(1.5M MEDIAN)
Typical Cross Section for LHS Widening with 5.5m Service Road on LHS
14
Type IX
Typical Cross Section for New Construction with 5.5m Service Road on RHS
0.800
Remarks
Length
(Km)
0.760
25.775
0.220
0.300
0.600
0.600
1.050
0.675
7-5
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
S.No
Cross
Section Type
15
Type X
16
Type XI
17
Type XI-A
18
Type XII
19
Type XII-A
20
Type XIII
21
Type XIV
22
Type XV
23
Toll Plaza
Remarks
Typical Cross Section for PUP Approach without RE wall and without Service
Road
Typical Cross Section for VUP/PUP Approach with RE wall and with both Side
7.0m Service Road
Typical Cross Section for VUP/PUP Approach with RE wall and with both Side
5.5m Service Road
Typical Cross Section for Unidirectional Flyover Approach with Slip Road
Length
(Km)
2.030
2.980
2.770
0.500
Typical Cross Section for Unidirectional Flyover Approach without Slip Road
Typical Cross Section for ROB Approach with RE wall and with both Side 7.0m
Service Road
Typical Cross Section for ROB Approach with RE wall BUT without Service
Road
Typical Cross Section for Concentric Widening with Service Road on both side
at existing four lane section
0.800
Toll Plaza Location
1.800
Total Length (Total length as per design chainage)
0.530
3.250
0.925
123.490
The cross-sections detailed herein have references to side of widening viz. Left Hand Side (LHS)
or Right Hand Side (RHS). The sides herein refer to increasing chainage i.e. the direction of
travel is from Jetpur at junction with NH-8B towards Somnath.
The drawings for all these cross-sections have been presented below for ready reference.
TYPE - I
Figure
TYPE
-I
TYPICAL CROSS SECTION FOR LHS
WIDENING
WITHOUT SERVICE ROAD
TYPICAL
FOR LHS
WIDENING
WITHOUT
7-1:
Type CROSS
I, TCS SECTION
for Left Hand
Side
Widening
withoutSERVICE
ServiceROAD
Road
TYPE - II
TYPE
- IIWidening
TYPICAL
FOR
RHS
WIDENING
WITHOUT
SERVICE
ROADRoad
Figure 7-2:
Type CROSS
II, TCSSECTION
for Right
Hand
Side
without
Service
TYPICAL CROSS SECTION FOR RHS WIDENING WITHOUT SERVICE ROAD
7-6
TYPE - IIA
TYPICAL CROSS SECTION FOR RHS
WIDENING
WITHOUT SERVICE ROAD
TYPE
- IIA
TYPICAL CROSS SECTION FOR RHS WIDENING WITHOUT SERVICE ROAD
TYPE - II
Final Feasibility-cum-Preliminary
Report
TYPICAL CROSS SECTION Design
FOR RHS WIDENING
WITHOUT SERVICE ROAD
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
VOLUME I:
MAIN REPORT
TYPE - IIA
TYPICAL
CROSS
SECTION
WIDENING
WITHOUT
SERVICE
ROAD(median 4.5 to 20m)
Figure 7-3: Type II-A,
TCS for
Right
HandFOR
SideRHS
Widening
without
Service
Road
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
REVISIONS
TYPE - III
TYPICAL CROSS SECTION FOR NEW CONSTRUCTION WITHOUT SERVICE ROAD
TYPE - III
TYPICAL
CROSS
Figure
7-4:
TypeSECTION
III, TCSFOR
for NEW
NewCONSTRUCTION
ConstructionWITHOUT
withoutSERVICE
ServiceROAD
Road
TYPE - IV
Figure
7-5:
TypeSECTION
IV, TCSFOR
forRECONSTRUCTION
ReconstructionWITHOUT
withoutSERVICE
ServiceROAD
Road
TYPICAL
CROSS
TYPE - IV
TYPICAL CROSS SECTION FOR RECONSTRUCTION WITHOUT SERVICE ROAD
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
REVISIONS
TYPE - V
73252\LASA\RH\DFR\TCS-02
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
73252\LASA\RH\DFR\TCS-02
HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH
ASIA PVT.
LTD., SECTION FOR LHS WIDENING WITH BOTHNATIONAL
TYPICAL
CROSS
SIDE 7.0m
SERVICE ROAD
TYPICAL CROSS SECTIONS
Figure 7-6: Type V, TCS for LHS widening with both side 7.0m Service Road (4.5m median)
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
REVISIONS
7-7
TYPE - VI
TYPICAL CROSS SECTION FOR RHS WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
Final Feasibility-cum-Preliminary Design
Report
TYPE - I
TYPE
- V ofWITHOUT
Preparation of Feasibility– cum-Preliminary
Design FOR
for 4/6
Laning
Jetpur- SERVICE ROAD
TYPICAL CROSS SECTION
LHS
WIDENING
CROSS
FOR LHS WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
Somnath section of NH 8D,TYPICAL
Package
No:SECTION
NHAI/DBFOII/DPR/02
VOLUME I:
MAIN REPORT
TYPE - II
TYPICAL CROSS SECTION FOR RHS WIDENING WITHOUT SERVICE ROAD
- VI
Figure 7-7: Type VI, TCS for RHS TYPE
widening
with both side 7.0m Service Road
TYPICAL CROSS SECTION FOR RHS WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
TYPE - VA
TYPICAL CROSS SECTION FOR LHS WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
TYPE
- IIA
TYPE
- VA
R E V I SIONS
73252\LASA\RH\DFR\TCS-0
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
TYPICAL
CROSS
SECTION
FOR
WIDENING
SERVICE
ROAD ROAD
TYPICAL
CROSS
SECTION
FOR
LHSRHS
WIDENING
WITHWITHOUT
BOTH SIDE
7.0m SERVICE
Figure 7-8: Type VA, TCS for LHS widening with both side 7.0m Service Road (1.5m median)
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TCS-0
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
TYPE - VII
Figure 7-9:TYPICAL
Type VII,
TCS
for Concentric
widening
with both
side 7.0m
Service
Road
(1.5m median)
CROSS
SECTION
FOR CONCENTRIC
WIDENING
WITH BOTH
SIDE 7.0m
SERVICE
ROAD
TYPE - VII
TYPICAL CROSS SECTION FOR CONCENTRIC WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
TYPE - XI
TYPICAL
CROSS
SECTION
AND BOTHSIDE
7.0m SERVICE
ROAD
HIGHWAYS AUTHORITY
OF INDIA
LEA ASSOCIATES
SOUTH
ASIA PVT.
LTD., FOR VUP/PUP APPROACH WITH RE WALLNATIONAL
TYPICAL CROSS SECTIONS
R E V I SIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section
of NH-8D
to be Executed
as BOT
(Toll) Project on DBFO Pattern Under NHDP Phase III
NATIONAL
HIGHWAYS
AUTHORITY
OF INDIA
TYPICAL CROSS SECTIONS
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
TYPE - VIIA
R E V I SIONS
73252\LASA\RH\DFR\TCS
73252\LASA\RH\DFR\TCS-04
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
Figure 7-10:
Type CROSS
VII-A, TCS
for Concentric
widening
withWITH
both
side
5.5m
Service
Road
TYPICAL
SECTION
FOR CONCENTRIC
WIDENING
BOTH
SIDE
5.5m
SERVICE
ROAD(4.5m median)
7-8
TYPE - XIA
TYPICAL CROSS SECTION FOR VUP/PUP APPROACH WITH RE WALL AND BOTHSIDE 5.5m SERVICE ROAD
TYPE
- VIIA
TYPE
- IV
TYPE - IV
TYPICAL CROSS
SECTION
CONCENTRIC
WIDENING WITHWITHOUT
BOTH SIDE
5.5m SERVICE
TYPICAL
CROSSFOR
SECTION
FOR RECONSTRUCTION
SERVICE
ROAD ROAD
TYPICAL CROSS SECTION FOR RECONSTRUCTION WITHOUT SERVICE ROAD
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
NATIONAL HIGHWAYS AUTHORITY OF INDIA
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TCS73252\LASA\RH\DFR\TCS-
TYPICAL CROSS SECTIONS
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Consultancy
of as
Feasibility-cum-Preliminary
Design
for 4/6-Lane
of Jetpur-Somnath
SectionServices
of NH-8DfortoPreparation
be Executed
BOT (Toll) Project on DBFO
Pattern
Under NHDP
Phase III
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
R E V I SIONS
TYPE - VIIB
Figure 7-11:
Type VII-B,
for Concentric
widening
withWITH
both
sideSIDE
5.5m
Service
Road
TYPICAL
CROSSTCS
SECTION
FOR CONCENTRIC
WIDENING
BOTH
5.5m
SERVICE
ROAD(1.5m median)
73252\LASA\RH\DFR\TCS-0
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
TYPE -- VIII
VIII
TYPE
TYPE - VIII
TYPICAL CROSS
CROSS SECTION
SECTION FOR
FORLHS
LHSWIDENING
WIDENINGWITH
WITH5.5m
5.5mSERVICE
SERVICEROAD
ROADON
ONLHS
LHS
TYPICAL
TYPICAL
CROSSVIII,
SECTION
LHS WIDENING
WITH
5.5m
SERVICE
ROAD
ON LHS
Figure
7-12: Type
TCS FOR
for LHS
widening
with
5.5m
Service
Road
on
TYPE - IX
TYPE
TYPE -- IX
IX
TYPICAL CROSS SECTION FOR NEW CONSTRUCTION
WITH 5.5m SERVICE ROAD ON RHS
TYPICAL
CROSS
FOR
NEW
CONSTRUCTION
WITH
SERVICE
ON
Figure
7-13:SECTION
Type IX,
TCS
for
New Construction
with
5.5m ROAD
Service
Road
TYPICAL
CROSS
SECTION
FOR
NEW
CONSTRUCTION
WITH 5.5m
5.5m
SERVICE
ROAD
ON RHS
RHS
LHS
on RHS
TYPE - XIII
TYPICAL CROSS SECTION FOR ROB APPROACH WITH RE WALL AND WITH BOTHSIDE 7.0m SERVICE ROAD
TYPE - X
CROSS
PUP APPROACH
WITHOUT
RE WALL
AND and
WITHOUT
SERVICE
ROADRoad
TYPE
-- X
FigureTYPICAL
7-14: Type
X, SECTION
TCS forFOR
PUP/CUP
Approach
RE wall
without
Service
TYPE
Xwithout
TYPICAL
TYPICAL CROSS
CROSS SECTION
SECTION FOR
FOR PUP
PUP APPROACH
APPROACH WITHOUT
WITHOUT RE
RE WALL
WALL AND
AND WITHOUT
WITHOUT SERVICE
SERVICE ROAD
ROAD
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TCSTYPICAL CROSS SECTIONS
REVISIONS
NATIONAL HIGHWAYS AUTHORITY OF INDIA
NATIONAL HIGHWAYS AUTHORITY OF INDIA
TYPICAL
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design
for CROSS
4/6-LaneSECTIONS
of Jetpur-Somnath
TYPICAL
CROSS
SECTIONS
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
R E V I SIONS
Consultancy
Consultancy Services
Services for
for Preparation
Preparation of
of Feasibility-cum-Preliminary
Feasibility-cum-Preliminary Design
Design for
for 4/6-Lane
4/6-Lane of
of Jetpur-Somnath
Jetpur-Somnath
Section of
Section
of NH-8D
NH-8D to
to be
be Executed
Executed as
as BOT
BOT (Toll)
(Toll) Project
Project on
on DBFO
DBFO Pattern
Pattern Under
Under NHDP
NHDP Phase
Phase III
III
LEA
LEA ASSOCIATES
ASSOCIATES SOUTH
SOUTH ASIA
ASIA PVT.
PVT. LTD.,
LTD.,
TYPE - XIV
TYPICAL CROSS SECTION FOR ROB APPROACH WITH RE WALL AND WITHOUT SERVICE ROAD
NATIONAL HIGHWAYS AUTHORITY OF INDIA
73252\LASA\RH\DFR\TCS73252\LASA\RH\DFR\TCS-
7-9
73252\LASA\RH\DFR\TCS-0
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
TYPE - VA
TYPICAL CROSS SECTION FOR LHS WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
TYPE - XI
TYPE -WITH
XI RE WALL AND BOTHSIDE 7.0m SERVICE ROAD
TYPICAL CROSS SECTION FOR VUP/PUP APPROACH
TYPICAL CROSS SECTION FOR VUP/PUP APPROACH WITH RE WALL AND BOTHSIDE 7.0m SERVICE ROAD
Figure 7-15: Type XI, TCS for VUP/PUP Approach with RE wall and with both Side 7.0m Service Road
TYPE - VII
TYPICAL CROSS SECTION FOR CONCENTRIC WIDENING WITH BOTH SIDE 7.0m SERVICE ROAD
73252\LASA\RH\DFR\TCS-
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
TYPE - XIA
TYPE - XIA
TYPICAL
SECTION
VUP/PUPApproach
APPROACH with
WITH RE
5.5mSide
SERVICE
ROAD
Figure 7-16:
Type CROSS
XI-A, TCS
for FOR
VUP/PUP
REWALL
wallAND
andBOTHSIDE
with both
5.5m
Service Road
TYPICAL CROSS SECTION FOR VUP/PUP APPROACH WITH RE WALL AND BOTHSIDE 5.5m SERVICE ROAD
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TCS-07
TYPICAL CROSS SECTIONS
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TC
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
REVISIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
REVISIONS
TYPE - XII
Figure 7-17:
Type CROSS
XII, TCS
for Unidirectional
Flyover
Approach
with Slip Road
TYPICAL
SECTION
FOR UNIDIRECTIONAL
FLYOVER
APPROACH
7-10
Final Feasibility-cum-Preliminary Design Report
Preparation of Feasibility– cum-Preliminary Design for 4/6TYPE
Laning
- XII of JetpurSomnath section of NH 8D, Package
No:CROSS
NHAI/DBFOII/DPR/02
TYPICAL
SECTION FOR UNIDIRECTIONAL FLYOVER APPROACH
VOLUME I:
MAIN REPORT
TYPE - VIIB
TYPICAL CROSS SECTION FOR CONCENTRIC WIDENING WITH BOTH SIDE 5.5m SERVICE ROAD
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TCSTYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
Figure 7-18: Type XII-A, TCS for Unidirectional
TYPE - XIIA Flyover Approach without Slip Road
TYPICAL CROSS SECTION FOR UNIDIRECTIONAL FLYOVER
NATIONAL HIGHWAYS AUTHORITY OF INDIA
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
73252\LASA\RH\DFR\TCS-08
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
R E V I SIONS
TYPE - XIII
TYPICAL CROSS SECTION FOR ROB APPROACH WITH RE WALL AND WITH BOTHSIDE 7.0m SERVICE ROAD
TYPE - XIII
TYPICAL CROSS SECTION FOR ROB APPROACH WITH RE WALL AND WITH BOTHSIDE 7.0m SERVICE ROAD
Figure 7-19: Type XIII, TCS for RoB Approach with RE wall and with both side 7.0m service road
TYPE - XIV
TYPICAL
FOR
APPROACH
WITH
RERE
WALL
AND
WITHOUT
SERVICE
ROAD
Figure
7-20:CROSS
Type SECTION
XIV, TCS
forROB
RoB
Approach
with
wall
and
without
service
road
TYPE - XIV
TYPICAL CROSS SECTION FOR ROB APPROACH WITH RE WALL AND WITHOUT SERVICE ROAD
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
REVISIONS
R E V I SIONS
LEA ASSOCIATES SOUTH ASIA PVT. LTD.,
NATIONAL HIGHWAYS AUTHORITY OF INDIA
73252\LASA\RH\DFR\TC
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
NATIONAL HIGHWAYS AUTHORITY OF INDIA
TYPICAL CROSS SECTIONS
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
7-11
73252\LASA\RH\DFR\TCS-
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
TYPE - XV
Figure
7-21:
Type
XV, TCS
for
concentricWIDENING
widening
with
both
side
Service
Road
at existing
four
lane
Section
TYPICAL
CROSS
SECTION
FOR
CONCENTRIC
WITH
BOTH
SIDE
SERVICE
ROAD
AT EXISTING
FOUR
LANE
SECTION
7.7
CD AND OTHER STRUCTURES
7.7.1
Flyovers/Underpasses/ROB
Flyovers
Flyovers have been proposed at major intersections on the existing road
bypass/realignments. The proposed cross-section at these locations is shown in Fig 7-20.
and
The location, length, span and width of the cross-section are listed out in the Table 7-7 below.
Table 7-7: List of Flyovers
S
No.
R E V I SIONS
1
Proposed
Proposed Span
Chainage
LEA ASSOCIATES SOUTHArrangement
ASIA PVT. LTD.,
(km)
0+750.754
Unidirectional
2X45
Vertical
Clearance
(m)
5.5
Total
Total Width of
Span NATIONAL HIGHWAYS AUTHORITY OF INDIA
Structure (m)
(m)
Remarks
TYPICAL CROSS SECTIONS
Intersection with NH8B at start of project
corridor
Consultancy Services for Preparation of Feasibility-cum-Preliminary Design for 4/6-Lane of Jetpur-Somnath
Section of NH-8D to be Executed as BOT (Toll) Project on DBFO Pattern Under NHDP Phase III
90
1 x 12 (for down
direction traffic)
Figure 7-22: Typical Cross-section of Flyover
7-12
73252\LASA\RH\DFR
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
7.7.2
Vehicular Underpasses
For cross movement of traffic, underpasses are proposed at regular intervals along the project
corridor. The Manual of Specifications for four laning of NHs obviously recommends the provision
of vehicular underpasses along the highway. The vehicular underpasses are of 5m vertical
height. Keeping this in mind, the Consultants have proposed underpasses at the locations as
listed in the Table 7-8 below.
Table 7-8: List of Vehicular Underpasses
S No.
1
2
3
4
7.7.3
Size (Nos. x
span x height
in m)
2x10.25x5.5
2x10.25x5.5
2x10.25x5.5
2x10.25x5.5
Location
(km)
24.715
68.720
110.227
116.205
Total Width
Remarks
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
Doraj-Junagarh SH Crossing
Keshod Bypass
Dari-Sathroda Road Crossing
Sasan-Veraval SH Crossing
Pedestrian Underpasses
As the project is proposed to develop as an access controlled highway and direct access of local
traffic to main highway is not deemed to be provided. However, to facilitate the movement of
pedestrians only from one side of project road to other side, underpasses are essential. The
Manual of Specifications for four laning of NHs obviously recommends the provision of
pedestrian underpasses along the highway. The Consultants have proposed underpasses at the
locations with sizes of structures as listed in the Table 7-9 below.
Table 7-9: List of Pedestrian Underpasses
S No.
1
2
3
4
5
6
7
8
9
10
11
12
13
7.7.4
Location
(km)
1.706
6.100
20.000
34.225
37.050
55.650
58.797
64.882
71.500
91.050
94.699
106.100
119.900
Size (Nos. x span
x height in m)
Total Width
1x4x3.5
2 x 10.75 + Median
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
1x4x3.5
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
2 x 10.75 + Median
ROBs
The ROBs proposed along the corridor are listed in Table 7-10 below.
7-13
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
Table 7-10: List of ROBs
S.No
Name Of Bypass
Proposed
Chainage
Type of Structure
Width
Proposed Span Arrangement
12
1
Jetpur Bypass
2+800
ROB
2
Junagarh Bypass
On Existing
Alignment
On Existing
Alignment
23+996
ROB
12
1X35
112+938
ROB
12
3X30
118+374
ROB
12
1X40
3
4
7.8
1x47+1x29.6+1x33
CD WORKS
Along the project corridor, there are a number of culverts, minor bridges and major bridges, the
details of which are already given in Chapter 6 of the report. The list of the proposals is
presented in the Appendix 7-1 to Appendix 7-6 in Vol. - II of this report.
7.9
PROJECT FACILITIES
The following project facilities have been proposed for the project corridor
 Bus-bays and bus shelters;
 Truck lay-bys;
 Rest area/Way side amenity
 Toll plaza;
 Roadside furniture;
 Street lighting;
 Traffic aid posts;
 Highway Patrolling
 Medical aid posts;
 Ambulances
 Vehicle rescue posts;
 Highway Traffic Management System
7.9.1
Bus-bays and bus shelters
There are several bus stops along the project corridor, where buses are presently stopping.
Generally these stops are associated with a settlement area or an intersection with a crossroad.
Efforts were made to collect information from Gujarat State Transport Corporation (GSTC) on the
official bus stops. It is proposed to provide two bus stops/bus bays at each location to cater for
both the directional traffic. Details of bus stops and bus bays are given below in the following
table.
7-14
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
Table 7-11: Locations of Bus Stops
S.No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
7.9.2
Location
Jetpur Bypass
Jetalsar
Pipamadva
Navi Shankli
Choki
Vadal
Shukhpur
Eisting Junagadh Bypass
Eisting Junagadh Bypass
Eisting Junagadh Bypass
Vanthali
Kanja
Khokharda
Khubhadi
Manekvada
Magalpur
Kesod Bypass
Kesod Bypass
Koylala
Panidara
Juthal
Maliya Hatina
Bhanduri
Zadaka
Gadu
Shantipara Patiya
Kedivav
Kindrava
Adari-Vavadi
Sipasi
Dari
Dabhor
Talala Chokadi
Bhalpara
Design Chainage
Left
Right
5789.9
8750.0
9950.0
13400.0
20000.0
22450.0
28450.0
30350.0
32250.0
42250.0
48250.0
50600.0
51600.0
55350.0
57950.0
66370.0
68500.0
78000.0
81900.0
84750.0
86480.0
90900.0
94600.0
97600.0
101380.0
103900.0
105900.0
108200.0
110350.0
114120.0
116350.0
117560.0
120247.3
5789.9
8750.0
9950.0
13400.0
19600.0
22250.0
28200.0
30350.0
32350.0
42250.0
48250.0
50600.0
51600.0
55350.0
57950.0
66300.0
68500.0
77700.0
81900.0
84500.0
86132.5
90900.0
94600.0
97600.0
101100.0
103700.0
105600.0
108300.0
110100.0
113800.0
116050.0
117500.0
120247.3
Truck Laybys
Truck Parking has been observed at many locations in front of Hotels/Dhabas and near petrol
pump. However once the facility is developed the truck drivers would tend to stop their vehicles
at the designated truck parking locations. Details of proposed truck lay bys are given below in the
following table.
7-15
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
Table 7-12: Locations of Truck Lay Bys
Proposed chainage
25.52
82.45
96.45
7.9.3
Side
LHS
LHS
RHS
Rest Areas/Wayside amenity
It is proposed to provide one Rest area /Way side amenity near km 48.4 (design chainage) on
RHS.
7.9.4
Toll Plazas
It is proposed to provide three main toll plazas, one at km 10.36 (design chainage), second one
at km 51.25 (design chainage) and the third one at 106.90 (design chainage). Initially there would
be four plus one toll lane in each direction at each toll plaza and subsequently additional number
of toll lanes would be added later as and when traffic demands. However, the total land required
would be acquired at initial stage only.
7.9.5
Road Furniture
Road furniture such as Traffic Signs and Pavement Markings, Guard Rails and Traffic Safety
Devices, Boundary Stones, Hectometer / Kilometer Stones and Traffic Blinker Signal (L.E.D) at
intersections has been proposed in accordance with the Manual of Specification and standards
for Four Laning of National Highways through Public Private Partnership.
Metal beam crash barriers have been proposed at the locations of bridge approaches and high
embankments (3m and more) and at sharp curves on outer side of curves.
Delineators and Guard Posts have been proposed depending upon the proposed radii of the
horizontal alignment and height of embankment. The delineator posts have been proposed near
all curves of radii less than 1000m, with spacing given as per IRC 79. The guard post has been
proposed where the embankment height is between 2m to 3 m.
Traffic Blinker signal (L.E.D) have been proposed at all at-grade intersections and median
openings as.
7.9.6
Lighting System;
The details of lighting system proposed for the propjet corridor have been given in the following
table.
7-16
Final Feasibility-cum-Preliminary Design Report
VOLUME I:
Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02
MAIN REPORT
Table 7-13: Details of lighting proposed
S. No.
1
2
3
4
5
6
7.9.7
location
At all major bridges
At all grade separated structures and their appraoches
At all Underpasses
At all median openings
At all Toll Plazas
At all Truck lay bys and busbays
Traffic aid posts;
Three traffic aid posts each with buildings having 25 (twenty five) square meters of plinth area,
have been proposed.
7.9.8
Highway Patrolling
Three Highway patrol units manned two persons apart from the driver with communication facility
and three patrol vehicles with seating capacity for four personnel besides the driver and space to
carry essential traffic management and safety tools. With light on its top and a siren on board
equipped with traffic cones and other accessories for traffic control which are fully visible during
night time. Have been proposed to render assistance to users in distress and disabled vehicles
through own intervention or by calling from assistance from Control Room, Crane operators or
ambulance as required.
7.9.9
Medical aid posts;
Three medical aid posts each with one Medical aid post building and 2 (two) residential quarters,
have been proposed for the project highway
7.9.10 Ambulances
Four Ambulances manned by two trained paramedics and equipped with first aid, life saving
medical services and support system implements for transporting the victims to the nearest
trauma hospitals, and providing emergency medical aid during transportation of victims from
accident site to the nearest trauma hospital have been proposed.
7.9.11 Vehicle rescue posts;
Three vehicle rescue posts consisting of one mobile crane having the capacity to lift a truck with
a Gross Vehicle Weight of 20,000 kilograms have been proposed for prompt removal of
accidental/break down vehicles or debris or any other obstruction, which may endanger or
interrupt the smooth flow of traffic
7.9.12 Highway Traffic Management System
It is proposed to have Advanced Traffic Management System (ATMS) fulfilling the requirements
as stipulated in the standard Manual.
7-17
Download