Business Case 22 December 2011 Sinclair Knight Merz ABN 37 001 024 095 452 Flinders Street , Melbourne 3000 PO Box 2500 Malvern VIC 3144 Australia Tel: +61 3 9248 3100 Fax: +61 3 9248 3631 Web: www.skmconsulting.com LIMITATION: This report has been prepared on behalf of and for the exclusive use of Sinclair Knight Merz Pty Ltd’s Client, and is subject to and issued in connection with the provisions of the agreement between Sinclair Knight Merz and its Client. Sinclair Knight Merz accepts no liability or responsibility whatsoever for or in respect of any use of or reliance upon this report by any third party. The SKM logo trade mark is a registered trade mark of Sinclair Knight Merz Pty Ltd. Contents 1. Terms and definitions 3 2. Executive Summary 5 3. Introduction 11 4. Service Need 12 4.1. 4.2. 13 21 5. Background to service need Project Drivers Project Objectives and Scope 29 5.1. 5.2. 5.3. 5.4. 5.5. 5.6. 29 30 30 30 32 33 Investment Logic Map Objectives Scope Project Benefits Strategic Alignment Critical Success Factors 6. Stakeholder Analysis 34 7. Summary of Options for Spatial Improvement 37 7.1. 7.2. 7.3. 7.4. 7.5. 37 40 42 45 48 8. 9. Option 1: Do Nothing (Base Case) Option 2: Resurvey of the Entire State Option 3: Rebuild from existing survey accurate data Option 4: Adjustment from aerial imagery Option 5: Mixed approach Options Analysis 51 8.1. 8.2. 8.3. 51 54 66 Qualitative assessment against critical success factors Quantitative Assessment: Cost Benefit Analysis (CBA) Preferred VSLB option Socio-Economic Analysis 67 9.1. 9.2. 9.3. 67 67 68 Social Impact Environmental impact Qualitative Economic Benefits 10. Risk Analysis and Management 10.1. Risk Ratings 10.2. Risk Management Process 11. Procurement Strategy 11.1. Procurement options ii | P a g e 72 72 75 76 76 11.2. Procurement Selection 11.3. Recommended Procurement Solution 77 79 12. Funding Assessment 81 13. Public Interest Issues 83 14. Implementation and timing 85 14.1. 14.2. 14.3. 14.4. 14.5. Project Delivery Strategy Project Staging Implementation Timetable Project Governance and Oversight Project Management 85 86 87 90 92 15. Conclusion 93 Appendix A Background to Vicmap Property 94 A.1 A.2 A.3 A.4 A.5 What is a cadastral map base? History Additional detail on Vicmap Property and its layers Management of Vicmap Property Management and Operation 94 95 96 98 98 Appendix B User requirements for spatial accuracy 100 Appendix C Legislative alignment 102 C.1 Surveying Regulations 104 Appendix D Stakeholder Details 107 Appendix E Non Financial Assessment 131 Appendix F Additional assumptions and constraints relevant to the Cost Benefit Analysis 138 F.1 F.2 F.3 Equipment and resources Parcel Counts and Plan Information Production methodology assumptions for Option 5 138 138 140 Appendix G Cost Estimates 142 Appendix H Risk Assessment 146 Appendix I Financial cashflow 151 Appendix J Project Schedule 154 Appendix K Resource Plan 155 iii | P a g e Abbreviations Abbreviation Meaning ACTPLA Australian Capital Territory Planning and Land Authority ANZLIC Australian New Zealand Land Information Council AV Ambulance Victoria BCR Benefit Cost Ratio CAD Computer Aided Drafting CFA Country Fire Authority CORS Continuous Operating Reference System DCDB Digital Cadastral Data Base DEH Department for Environment and Heritage (SA) DIPE Department of Infrastructure, Planning and Environment (NT) DPCD Department of Planning and Community Development (VIC) DPI Department of Planning and Infrastructure (NT) DPIWE Department of Primary Industries, Water and Environment (TAS) DSE Department of Sustainability and Environment (VIC) ePlan Digital format for submission of cadastral survey and subdivision plan data to support the implementation of SPEAR ESTA Emergency Services Telecommunications Authority GIS Geographic Information System GNSS Global Navigation Satellite System GPS Global Positioning Systems GPSnet Also referred to as Vicmap Position- Victorian real time positioning service ICSM Intergovernmental Committee for Surveying and Mapping ILM Investment Logic Map ISB Information Services Branch (formerly SII) LGA Local Government Area LINZ Land Information New Zealand LIST Land Information System Tasmania LPMA Land and Property Management Authority (NSW) SINCLAIR KNIGHT MERZ 1|P a g e Abbreviation Meaning LV Land Victoria MFB Metropolitan Fire and Emergency Services Board NTGeSS Northern Territory Geodetic Survey System NTLIS Northern Territory Land Information System NTSDD Northern Territory Spatial Data Directory NPC Net Present Cost NPV Net Present Value OSGV Office of Surveyor General of Victoria SCDB Spatial Cadastral Database (WA) SDMS Spatial Data Management System SII Spatial Information Infrastructure (VIC) SIX Spatial Information Exchange (NSW) SLIP Shared Land Information Platform (WA) SPEAR Streamlined Planning through Electronic Applications and Referrals VOTS Victorian Online Titles System VicPol Victoria Police VicRoads Roads Corporation of Victoria VicSES Victorian State Emergency Services VSLB Victorian Spatial Land Base 2|P a g e 1. Terms and definitions The following terms and definitions are used in this document: Accuracy - is the level of closeness of a value to its true value. That is, how correct a coordinate is. Absolute accuracy - the degree to which planimetric/computed coordinates of a point/feature replicates the coordinates of the real world phenomenon that they represent with respect to a predefined datum. Business Custodian – as defined by the Australian and New Zealand Land Information Council (ANZLIC) is an organisation which in the course of its business will create, maintain and distribute authoritative spatial business information. High spatial accuracy - The degree to which the coordinates of a point/feature derived from the map base agrees with the real world coordinates of that point/feature, relative to (or in accordance with) a predefined range of uncertainty. For example, if a user specifies an accuracy tolerance of 0.03m, then the data has "high spatial accuracy" if the absolute accuracy of that point falls within the 0.03m tolerance. Occupation – buildings, fences and other constructions that may represent a parcel boundary Parcel – Smallest portion of registered land able to be transferred in ownership without further subdivision. A Parcel may contain one or many Properties or be part of a Property. The Business Custodian of Parcels is Land Victoria (a business custodian of the Department of Sustainability and Environment). Property – An occupiable space for community, residential, commercial or agricultural purposes as defined by Local Government. A property may comprise a part of one or many Parcels and will have one primary address. The Business Custodian of Property is Local Government. Relative accuracy - The measure of the agreement between the coordinates of a point with respect to the coordinates of other points, irrespective of its absolute accuracy. Spatial Information - Any information that can be geographically referenced to a location on the earth’s surface. Spatial accuracy - The degree to which the coordinates of a point/feature derived from the map base agree with the real world position of that point/feature on the earth’s surface. Survey accuracy - A type of accuracy relating to cadastral survey data (measurements) as defined by the relevant surveying legislation in force at the time of the survey. [The legislation currently in force is the Surveying (Cadastral Surveys) Regulations 2005.] 3|P a g e Vicmap Property – A spatial database comprising more than 3 million land parcels and associated property attributes, such as lot and plan number, and Crown description , in the State of Victoria. Vicmap Property is managed by DSE’s Information Services Branch under the principles of spatial custodianship whereby data supplied by custodians viz Land Victoria (parcels) and Local Government (properties) is spatially represented. Victorian Spatial Landbase (VSLB) – The proposed updated Vicmap Property. The proposed parcel and property components of Vicmap Property consisting of both spatial and textual information. 4|P a g e 2. Executive Summary This business case sets out the economic merits of improving the spatial accuracy and reliability of Victoria’s cadastral map base. The enhanced map base will be referred to as the Victorian Spatial Land Base (VSLB). ‘Vicmap Property’ is the current digital cadastral map base for Victoria and is the most complete authoritative source of the graphical representation of land parcel and property boundaries. As a fundamental Government-provided ‘enabling infrastructure’ service, Vicmap Property is relied upon by many government and non-government users to inform and support a range of decisions. This includes decisions relating to investment, cost estimation, land management and land use planning, and emergency planning and response decisions across virtually all conceivable sectors of economic and social activity. Vicmap Property does not meet the current or future needs and expectations of those government and private sector users who require high spatial accuracy. Less than 4% of parcels in the map base currently meet Vicmap Property users’ high spatial accuracy requirements for urban and peri-urban areas, which make up 70% of the map base parcels1. This results in significant financial and productivity costs for direct users of the database, as well as the broader economy. Although significant effort has been invested in Vicmap Property to improve spatial accuracy, this effort has generally been applied to address specific project needs and incomplete spatial data coverage, rather than as a comprehensive programme of works to improve database-wide spatial accuracy. The result is a map base which does not meet the needs and expectations of those users who require high levels of spatial accuracy. Service need The three project drivers are discussed below. Driver 1: Avoidable financial and productivity costs: The lack of high spatial accuracy in Vicmap Property leads to significant, avoidable financial and productivity costs in land administration and infrastructure planning and development across the public and private sectors Vicmap Property does not currently met user requirements for high spatial accuracy. Vicmap Property users requiring high spatial accuracy are therefore often forced to undertake additional surveying work, 1 Approximately 0.03-0.1 metres 5|P a g e leading to higher costs as well as project delays. For example, recently in a significant housing development in the urban fringe area of Melbourne, spatial information errors of up to 20m across the site resulted in costly delays and redesign works. In this one instance, the additional design works were estimated to cost $1 million, not including additional holding costs associated with the delay. Municipal councils (Local Government) also face ongoing costs associated with manually adjusting data collected through global navigation satellite systems (GNSS) to align with Vicmap Property. This inefficiency cost is estimated at $3 million per annum across the State. The lack of high spatial accuracy in the Vicmap Property map base has led to some asset owners developing their own proprietary databases, e.g. by Melbourne City Council and Barwon Water. This costly duplication undermines the Government’s reputation as a provider of critical spatial information. The difficulty in integrating new spatially accurate data into the map base exacerbates this problem as this data often needs to be distorted to fit within the less accurate Vicmap Property map base. Duplication costs are currently estimated at a minimum of $1.8 million annually and are expected to increase as the gap between the map base and user expectations continues to grow. The lack of high spatial accuracy in the current map database also contributes to the risk of accidental damage to underground services (typically water, power, gas, and telecommunication infrastructure). Estimates from Victorian asset owners indicate there are more than 30 incidents per annum where assets are damaged as a result of misalignment of the map base and asset locations provided by authorities. In Sydney in 2009, unintended contact with underground fibre cable resulted in direct damage cost of $1 million and business disruption costs estimated at $30 million. This incident demonstrates the high risk costs associated with misaligned positioning of underground assets. Emerging technologies in spatial information are increasing user expectations and further highlighting the deficiencies in Vicmap Property. For example, the map base cannot be readily integrated with new and more accurate databases, including recent government investments such as Streamlined Planning through Electronic Applications and Referrals (SPEAR) and ePlan. This lack of integration is a barrier to productivity and innovation. Driver 2: Cost of delay: The financial and opportunity cost of upgrading the spatial accuracy of the Vicmap Property dataset increases every year that action is delayed Vicmap Property is a dynamic database that grows and changes on a daily basis. This continual evolution and growth raises the cost of inaction. 6|P a g e Internal Government processes to maintain Vicmap Property and to update the dataset with new surveying data are inefficient due to the need to ‘work around’ an inaccurate database. Distortion and/or manipulation of new and often more accurate data collected is required in order to align with the current inaccurate Vicmap Property. This is a time consuming and counterproductive process that becomes more costly every year that action is delayed. The shrinking skill base in the surveying sector in Victoria also adds further urgency to the task. There are currently only 413 practising licensed surveyors in Victoria2, of which it is estimated 30% will reach retirement age in the next 10 years. These skills are not being adequately replaced as the industry faces great difficulty in attracting new graduates. Delaying the provision of a more efficient, reliable and userfriendly map base will therefore increase pressure on a shrinking and/or less specialised sector, and create additional difficulties in producing a map base of high spatial accuracy. Driver 3: Risk to Government Credibility: The inferior condition of the State’s fundamental information infrastructure does not meet user requirements and has not keep up to date with technological advancements. Government is perceived to be failing to deliver verifiable and reliable data required for decision making There have been examples of liability risk to Government as a result of users relying on the spatial accuracy of the information for their decision making. The Department of Planning and Community Development (DPCD) has faced legal action as a result of an apparent shift in property boundaries with respect to an environmental overlay when the cadastral map base was updated/realigned. As some 70% of planning overlays utilised under the Planning and Environment Act are not related to cadastral features and do not follow parcel boundaries, property boundaries shift relative to the overlays when the map base is updated (typically on a weekly basis). This resulting ‘overlay confusion’ creates financial uncertainty for affected property owners and property developers and is a notable legal risk to the Victorian Government. Options considered A range of options was considered to meet the project critical success factors in the development of a highly spatially accurate VSLB that can be easily interrogated, with a strong governance and custodianship regime. These options are detailed in the following table. 2 Surveyors Registration Board of Victoria- Register of Licensed Surveyors (as at June 2011) 7|P a g e Table 1 Options description Option Description Option 1: Do nothing This is the base case, where none of the project drivers are assessed, or project (or ‘Business as Usual’) objectives met Option 2: Resurvey of This is the only approach which can deliver state-wide accuracy consistent with the entire State current surveying regulation (i.e. survey accurate). This option involves rebuilding the map base with survey accurate data and therefore requires significant field survey effort. In addition to incurring the highest cost of all options considered, this option may be unviable due to the small and shrinking skill base available in the Victorian surveying sector Option 3: Rebuild from This approach will rebuild Vicmap Property using existing survey plans and title existing survey data records. This option will deliver a VSLB that is generally of high spatial accuracy but will be significantly limited by the availability of quality survey plans in some areas of the State Option 4: Adjustment This approach will adjust the existing Vicmap Property using ortho-rectified imagery. from aerial imagery With the exception of the “Do nothing” option, this option has the lowest cost of those identified but the improvement in spatial accuracy achievable is uncertain. The accuracy achieved is ultimately determined by the variable spatial accuracy of existing physical boundaries on the ground (fencing). This approach can therefore lead to further distortion in the map base and not provide a VSLB of high spatial accuracy in any part of the State Option 5: A Mixed This option will utilise the approach of Option 3 to rebuild the map base from approach (preferred existing survey data in urban and peri-urban areas combined with the adjustment option) approach of Option 4 in rural areas using aerial photography to provide the control framework supplemented with existing survey data where available Option assessment A cost benefit analysis (CBA) was undertaken alongside a qualitative assessment to compare the relative viability and merit of each of the options. The benefits considered in the CBA, and realised by each option (to varying degrees) include: Reduced costs to government associated with additional investigations/rework to obtain high spatial accuracy (public sector benefit) A reduced cost to government resulting from a reduction in complaints and requests for clarification in regards to Vicmap Property and its spatial accuracy (public sector benefit) 8|P a g e Avoided operating costs for Land Registration Services and Crown Land Registry with respect to their costs of reconciling Vicmap Property with submitted plans and reworking and adjusting of data (public sector benefit) Reduced project costs for land and infrastructure development due to access to a highly spatially accurate VSLB (public and private sector benefit) Avoided costs associated with development, maintenance and operation of duplicate spatial databases by a range of other authorities including water and energy providers (private sector benefit). The following table summarises the cost (real 2011/12 dollars), benefit cost ratio (BCR) and Net Present Value (NPV) results for Options 2 to 5 relative to the base case (Option 1 – Do Nothing). Table 2 Options assessment summary Cost Option BCR NPV Ranking Option Option Description (real $ 2011/12) Option 2 Resurvey of the state 931.7 m 0.36 ($424.9 m) 3 Option 3 Rebuild from existing survey data 192.0 m 1.65 $94.7 m 2 Option 4 Adjustment from aerial imagery 55.0 m 0.85 ($6.1 m) NA* Option 5 Mixed approach 158.0 m 2.37 $154.7 m 1 *Does not achieve, or facilitate high spatial accuracy requirements and therefore not ranked. Preferred Option Option 5 (Mixed approach) is recommended. This way forward achieves the highest BCR of all options considered with $2.37 dollars of benefit for the community for every dollar of investment. The NPV of the preferred option was higher than all the other options considered with a net benefit of $154.7 million over 20 years from commencement of implementation in 2012/13. This option is focused on delivering a solution that balances the user requirements against the cost and resource constraints in the market. It uses the shrinking skill base most effectively by delivering high spatial accuracy in the map base where it will result in the greatest overall benefit to the economy. This option will utilise a rebuild from survey accurate data in urban and peri-urban environments with additional field survey for control and infill surveys as needed. In rural environments aerial imagery will be applied as a control combined with selected field survey and/or existing survey accurate data based adjustment in problem areas. 9|P a g e This approach combines methods that will deliver high spatial accuracy for areas of the map base which face higher intensity of use (e.g. 0.03-0.1 metres in urban and peri-urban areas) and lesser improvement in spatial accuracy for areas that will face lower intensity of use of the map base (rural areas). This approach also provides the opportunity for ongoing enhancement and modernisation over time. The spatially improved database referred to as the VSLB will consist of data with high spatial accuracy for all urban and peri-urban areas. In order to maintain uninterrupted service during the transition to the VSLB, DSE would lock and duplicate sections of the map base, leaving one available for public use whilst the other is rebuilt. This will minimise the impact on map base users and ensure that planning and land administration works are not disrupted significantly over the development period. Funding requirements DSE does not have the capacity to fund this scale of capital investment. The preferred option has a capital cost impact for the State of $ 158.0m (real 2011/12 dollars) corresponding to $185.6 m (nominal dollars) over a 10 year period commencing in 2012/13. The following table outlines the project’s funding requirements. This excludes funding for recurrent costs. Table 3 Funding requirements (nominal $m) 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 TOTAL Costs 0.4 1.8 14.1 28.9 33.0 35.7 36.4 17.0 - - 167.4 Project Delivery Costs - 1.4 1.5 1.6 1.6 1.7 1.7 1.8 1.9 0.6 13.7 Capital Costs - 0.6 1.4 1.9 0.7 - - - - - 4.5 TOTAL 0.4 3.9 17.0 32.3 35.2 37.4 38.1 18.8 1.9 0.6 185.6 Upfront Development 10 | P a g e 3. Introduction This business case has been prepared to set out the economic merit of the necessary investment to improve the spatial accuracy of the State’s Vicmap Property database. The enhanced database will be referred to as the Victorian Spatial Land Base (VSLB). Vicmap Property is the State’s current digital cadastral map base and is the most complete readily available authoritative source of the graphical representation of land property and parcel boundaries3. Whilst it is considered by both private and public sector users as a fundamental Government service, the Vicmap Property dataset has not kept pace with the development of digital data or application technologies and in many cases fails to meet users’ needs and expectations. The development of the VSLB will deliver high spatial accuracy to the State’s digital cadastre database and will consist of high spatially accurate data for all urban and peri-urban areas. In the context of this project ‘high spatial accuracy’ refers to the degree to which the coordinates of a point/feature derived from the map base agrees with the real world coordinates of that point/feature, relative to (or in accordance with) a predefined range of uncertainty. For example, if a user specifies an accuracy tolerance of 0.03m, then the data has ‘high spatial accuracy’ if the absolute accuracy of that point falls within the 0.03m tolerance. This business case outlines the critical nature of the proposed investment in a highly spatially accurate VSLB and presents a range of the infrastructure and funding options available including the recommendation of a preferred course of action. Vicmap Property may also be referred to as Victoria’s cadastral map base. 3 SINCLAIR KNIGHT MERZ 11 | P a g e 4. Service Need The following section outlines the need to develop a highly spatially accurate digital cadastral map base for the State of Victoria. Key Points: Vicmap Property, the current digital cadastral map base, provides a critical and irreplaceable service for both the public and private sector. It is the most complete and readily accessible authoritative dataset of the State’s information on graphical land boundaries and associated property information. It is also the underlying fundamental dataset for land administration in Victoria. Both the private and public sector depend heavily on the accuracy of the information provided by Vicmap Property to inform planning, land management, investment and costing decisions across a range of sectors – e.g. local government and State Government, insurance firms, utility companies, emergency services, surveyors, property developers. The spatial information industry has been confirmed as a major contributor to the Australian economy, generating revenue of $1.37 billion in 2006-07 and cumulative contribution of between $6.4 and $12.6 billion to Gross Domestic Product in that same year (ACIL Tasman, 2008). Improved technology and access to spatial technologies has highlighted the deficiencies in Vicmap Property’s spatial accuracy. The State’s map base is currently not meeting user needs and expectations, posing unacceptable and avoidable reputation risk to the State. In addition to the impact on Government credibility, Vicmap Property’s inadequate spatial accuracy is leading to economic efficiency costs and/or risks for both the private and public sector. Unreliable accuracy of the existing Vicmap dataset is also necessitating the development of fit-for purpose proprietary datasets. Such duplication of datasets is an avoidable economic cost and erodes the Victorian Government’s reputation as a provider of vital spatial information. As Vicmap Property is not comprised of data of high spatial accuracy, when data of higher spatial accuracy is added to Vicmap Property often needs to be ‘distorted’ to fit with the less accurate Vicmap Property. Such adjustments further reduce private sector confidence in the Government’s datasets and create additional unnecessary duplication. Vicmap Property grows and changes on a daily basis. As such, the cost of improving the entire dataset’s spatial accuracy increases every year that action is delayed. Furthermore, an update of the dataset is needed within the next 5-10 years to fully utilise the expertise of a critical but shrinking skill base in the surveying sector. 12 | P a g e 4.1. Background to service need Vicmap Property is the cadastral map base of Victoria. It is a critical Government service providing information about the State’s graphical land boundaries and associated property information (See Figure 1 for example). The cadastral map (or map base) has the following main purposes: To provide a cartographic record of crown and private land surveys and subdivisions To facilitate the recording and administration of land transfer and land related dealings To record the status of land ownership To assist in the valuation and taxation of land To assist with land management To support urban and regional planning To support the provision of emergency services To provide the underlying map infrastructure of Victoria’s utility assets (water, sewer, roads, energy). Figure 1 Vicmap Property representation of property boundary information Source: DSE, 20114. Vicmap Property boundaries (black) & subdivision numbers (purple), LGA name (green), Locality name (blue) & Lot numbers (black), Vicmap Transport road centrelines (grey) and road names (black). Vicmap Property is the most complete and readily accessible state-wide dataset for land administration and is therefore perceived by users as the authoritative dataset for the State. It is heavily depended upon by both the public and private sector to inform land-related planning; investment and costing decisions; and, to operate critical state services such as emergency planning and response services. The property 4 http://www.dse.vic.gov.au/CA256F310024B628/0/C1B094A21FEABD97CA2577750021E880/$File/VicMap_Property+2010_11.pdf 13 | P a g e datasets provides businesses, government and the community with information that is crucial to identifying, managing and analysing assets within a geographic context. This information includes: Parcel and property geographical information relating to property title boundaries Parcel and property identifiers – Standard Parcel Identifiers and council property numbers Registered and proposed parcels on plans of subdivision Crown and freehold land differentiation Cadastral road casement boundaries and easements Unique Feature Identifiers, date stamps and data quality information Cross references to Vicmap Address and Vicmap Admin which are fundamental spatial datasets containing information relating to address locations and administrative boundaries. More background information on the history of Vicmap Property and its layers, management and operation is provided in Appendix A (page 94). 4.1.1. Vicmap Property and its users Victoria’s cadastral database is a vital piece of enabling ‘system infrastructure’ which is directly or indirectly relevant to all Victorians. All local government authorities use Vicmap Property to issue planning and building permits for building works and to estimate council rates payable. Emergency Services Organisations rely on Vicmap Property data to locate the property addresses from which triple-zero calls are made and to dispatch emergency services. A selection of Vicmap Property’s users and their dependence on the service are listed in the table below. Table 4: Sample of Vicmap property users Sector Example uses Facility and Fixed line (cable) data providers use a combination of Vicmap products to improve infrastructure managers telecommunications services throughout Victorian regional centres Utility companies Service planning and product supply, billing, and infrastructure (asset) protection and maintenance Developers To help in understanding existing tenure, planning constraints, asset location, and parcel location to facilitate investment and development Dial before you Dig This free service for information on underground pipes and cables in Australia relies on the map base to identify the location of underground assets in relation to property locations to prevent them being damaged during construction works 14 | P a g e Sector Example uses Local governments Local governments’ dependence on the service extends to setting property rates and taxes, confirming land use, zoning, subdivision, asset management and service delivery Emergency planning and Victoria’s cadastral map is used for all phases of emergency operations (planning, response organisations response, recovery, compensation), as well as being applied by the Emergency (VicSES, VicPol, AV, Services Telecommunications Authority (ESTA) to identify and locate sources of MFB, CFA) emergency triple-zero calls and dispatch responders State Government Managing environmental and natural resources including State Forests, parks and other public land, water resources and catchments For using land boundary information to assist in the planning and design of major infrastructure projects such as public transport, water and other critical services Urban planning – Establishing planning regimes for various land uses across urban and peri urban areas Land tenure management, including the management of Crown land - for weeds, fire and flood Management of natural disaster responses Quarantining – e.g. Agricultural Authorities wishing to quickly quarantine an area to reduce the risk of spreading a serious disease are able to utilise Vicmap Property to identify the properties within a set distance of the affected area. With this information, they can quickly identify the property owners or contacts to enforce a restriction area boundary (DSE 2011). Property conveyancing To identify land tenure and size and position of land parcels and real estate sector Lending institutions, Lending institutions confirm current tenure and title identification of properties banks Australia Post Use Vicmap Property to locate property addresses Insurance companies This sector uses the map base to confirm current tenure and title identification of land parcel properties (overlays and similar which may impact property risk) 15 | P a g e 4.1.2. Vicmap Property – a critical economic enabler Infrastructure is commonly perceived in terms of physical infrastructure such as roads or rail which supports the movement of people and goods. However, it is important to recognise that spatial infrastructure is also critical in supporting economic activity, increasing economic productivity and facilitating innovation. The spatial information industry is used by most sectors of the Australian and Victorian economies, with a direct impact on the value of production. A 2008 study commissioned by ANZLIC estimated that the spatial information industry generated revenue of $1.37 billion in 2006-07 with a cumulative contribution to GDP of between $6.43 billion and $12.57 billion (0.6% to 1.2%) in 2006-07 (ACIL Tasman, 2008). The range of users depending on the information provided by Vicmap Property demonstrates that property and parcel data is a fundamental part of Victoria’s spatial information infrastructure. 4.1.3. Inconsistency with new technology and applications A number of new, publicly accessible spatial technologies have become available over the past decade. The use of these technologies for gathering spatial data and other information has highlighted the deficiency in spatial accuracy of Vicmap Property. In particular, the high rates of adoption of global navigation satellite system positioning, aerial photography and satellite imagery when interfaced with Vicmap Property, reveals anomalies with Vicmap when comparing the location of parcel boundaries. The spatial data inaccuracy in Vicmap Property reduces confidence in Victorian Government datasets and inhibits Government’s ability to present Vicmap Property as an authoritative data source. 4.1.4. Inconsistency between Vicmap Property’s spatial accuracy and industry user requirements Vicmap Property was created in the early 1990s from the digitisation of paper-based map records held by the Melbourne Metropolitan Board of Works (now Melbourne Water) and the Department of Surveying and Mapping Victoria (now DSE). The spatial accuracy of the digital database is dependent upon the scale of the source hard copy mapping and the methods used to capture the data. Achievable spatial accuracies generally ranged from ±0.5 metres in urban areas, ±2.5 metres in peri-urban areas and up to ±25 metres in rural areas. Despite these estimates of spatial accuracy, the differences between the planimetric/computed coordinates of the data in Vicmap Property and the real world phenomenon that it is meant to represent have been found to be significantly greater in a number of instances. The level of spatial accuracy required by users varies significantly depending upon the applications for which Vicmap Property is used and how it interacts with users’ systems and data sets. The parameters for defining the optimal spatial accuracy of a spatial database need to be driven by the ability of improved 16 | P a g e technology to capture information; the needs of the relevant end user; and, the growing capacity of those users to access spatial information more readily. An increasing number of Vicmap Property users require data of high spatial accuracy. As provided in the Terms and Definitions in Section 1, data of high spatial accuracy refers to the position of a point, or series of points, where the coordinates of that point (s) when derived from the map base replicates the location of the real world phenomenon within a stated statistical estimate or uncertainty. As noted above, for the majority of users, this accuracy falls within the range of 0.03m-0.1m. Consultation undertaken with a range of users suggested that the spatial accuracy provided by Vicmap Property does not meet user requirements. It was noted that the spatial accuracy required to meet the needs of users was broadly 0.01-0.1m in the urban and peri-urban environment and 0.2-0.5m in the rural areas (see Table 5). It is noted that for the majority of users, this accuracy falls within the range of 0.03m-0.1m. Appendix B (page 100) provides further detail about the user groups consulted and their identified needs for spatial accuracy. Table 5: Spatial accuracy and parcel requirements Geographic area User spatial accuracy Number of parcels in % of parcels required requirements geographic area to user accuracy Urban & Peri-urban 0.01-0.1m 2.2 million 70% Rural 0.2-0.5m 1 million 30% Source: Spatial information Infrastructure, DSE (2010) Results from a review undertaken by Spatial Information Infrastructure (SII ) in 2010 (now Information Services Branch) suggested that less than 4% of parcels in the map base currently meet user accuracy requirements for Urban and Peri-urban areas (i.e. 0.01 to 0.1 metres absolute accuracy). Further, just over 50% of parcels are only accurate to 0.5m5. This indicates that nearly 50% of all parcels do not meet the less stringent user requirements for spatial accuracy required in a rural environment. Table 6 provides more detail on the results from the study. 5 In order to meet the spatial accuracy requirements needs of users, some 70% of the parcels (all urban and peri-urban parcels) would need to be accurate to between 0.03m and 0.1m, and 30% of parcels (Rural) accurate to 0.2m to 0.5m. 17 | P a g e Table 6: Vicmap Property - Spatial Accuracy Estimates Point Precision Values No of Points6 (in metres) PP=Point PP <= 0.1 Precision 0.1 < PP <= 0.5 0.5 < PP <= 1.0 1.0 < PP <= 2.5 2.5 < PP <= 5.0 5.0 < PP <= 10.0 10.0 < PP <= 25.0 PP > 25.0 TOTAL Percentage of total Approximate number cadastral boundary of parcels points in Vicmap 660,123 8,393,786 16,508 3,560,724 67,589 916,608 4,000,966 140 17,616,444 3.75% Property 47.65% 0.09% 20.21% 0.38% 5.20% 22.71% 0.00% 100.00% 119,910 1,524,718 2,999 646,800 12,277 166,500 726,769 25 3,200,000 Source: SII (2010) Importantly, it is the significant variation in spatial accuracy across Vicmap Property which impacts on its application and its use in relation to other aligned products. As such, significant upgrades to both urban, peri- urban and rural parcel representations in the map base are required to meet the needs of an increasing number of users. 4.1.5. Gap between Vicmap Property’s spatial accuracy and community expectations As awareness of spatial information increases within the community, accelerated by public use of technology such as personal GPS navigation systems and Google Maps etc, there is an expectation for cadastral map base information to be immediately accessible and easily interrogated. As discussed in more detail in Section 4.2.3, the expanding user base for cadastral map information expects that the information provided by the State is authoritative and is of high reliability, integrity and currency. There is also an expectation that the fundamental base layer in Vicmap Property should be compatible with a range of other complementary spatial data sets that are based on highly accurate spatial reference systems so that they can be integrated seamlessly without the need for manual ‘distortion’ to correct apparent mismatches. 4.1.6. Interstate property map base comparisons While all states and territories in Australia have complete cadastral coverage of their jurisdiction in digital form, most states have experienced similar difficulties to Victoria in establishing and maintaining a map base to a consistent degree of accuracy. Other Australian jurisdictions and New Zealand are in various stages of updating the map base to improve spatial accuracy. For example: 6 Note: A parcel may have few or many ‘points’ that are boundary corners or changes in direction. In Victoria there is an average of 5.5 points per parcel. 18 | P a g e Australian Capital Territory: The Australian Capital Territory digital cadastral map base (DCDB) is Australia’s ‘youngest’ map base and is the only map base in Australia which demonstrates a high degree of spatial accuracy (within 0.02 metres) over the whole jurisdiction. The Australian Capital Territory DCDB originates from a calculated/computed digital model based on field survey measurements supported by co-ordinated survey control. The Australian Capital Territory Planning and Land Authority (ACTPLA) is responsible for the DCDB and the Surveyor-General maintains the DCDB to high spatial accuracy through the incorporation of data from highly accurate cadastral surveys connected to the Australian Capital Territory survey control network. New South Wales: The NSW DCDB originated from the digitising of hardcopy maps. It used 1:500 to 1:4000 scale data in the urban areas and 1:25,000 to 1:100,000 scale maps in the rural areas. Updates to the database are carried out as necessary due to legal changes to title or in regions where there is a need and interest from utility, water or local government authorities. This leads to improved spatial accuracy in the land base to better than 0.3 m in urban areas and 3.0 m in rural areas. New Zealand: Land Information New Zealand (LINZ) has developed a system known as Landonline, which automates and integrates both title and survey systems. Landonline utilises a Survey-accurate Digital Cadastre (SDC) at its core, which provides the accuracy and integrity necessary for Landonline to make electronic survey transactions. The development of the SDC replaced the original DCDB, which originated from digitally scanned hardcopy survey plans spanning 11 years from 1985 to 1996. The SDC program included a survey conversion project, with the back capture of data shown on existing survey plans for 1.35 million parcels or 70% of New Zealand’s total parcel count. A cost/benefit analysis by LINZ did not support converting the survey records of the entire country, rather it identified areas of greatest survey activity, with priorities given to urban, high density perurban and adjoining rural areas. To quantify the resultant accuracy of the conversion and adjustment, each parcel block was subjected to accuracy testing. The result of this process identified that 80% of the total parcel count had an absolute spatial accuracy of 0.1m or better. Queensland: The Queensland DCDB was developed by manually digitising the best available cadastral maps. In 1992, the digital capture was completed at the agreed standard. The result was a seamless database of the cadastral network compiled to a range of accuracy ratings. Its positional accuracy was derived as a factor of the map scale used and the precision of the digitising. As a consequence, the positional accuracy of the DCDB throughout Queensland varies from 0.1 metre to 250 metres. As with other states and territories the need for improving the DCDB spatial component's accuracy is increasing. To achieve a desirable level of upgrade, the Queensland Government undertakes projects as co-operative ventures with local governments, with the extent of the upgrade projects limited by the amount of funding available. Methods of upgrade vary between 19 | P a g e local governments. Some local governments may have qualified people to enable them to do an 'inhouse' upgrade project, while use a competitive public tender to secure an authorised surveying company. The upgrade process may include full re-entry of bearing and distance from survey plans or employ some form of numerical or graphical adjustment. The use of aerial photography and satellite imagery is also being used to update rural and remote Queensland under the National Resources and Water’s DCDB Graphical Relativity Project, concentrated on zones where there is an interest in environmental monitoring and natural resource management activities. South Australia: The South Australian cadastre was acquired by digitising the cadastral boundaries from Government and Transport SA series maps in rural and pastoral areas. Consequently, the positional accuracy of the land parcel corners is dependent upon the scale of the source mapping and the manual digitising process. In some areas the positional accuracy of the parcel boundaries has been improved from graphical accuracy to survey accuracy. These more accurate coordinates have been derived by computation from lodged survey plans. More recently the Land Services Group (LSG) within the SA Government has commenced a four year program to reform Land Services, known as the Land Services Business Reform (LSBR) program. The first stage of this program is to procure a process for the provision of a new land administration system. In parallel, the Land Services Group is also developing a new system to support the State’s Digital Cadastral Data Base (DCDB). The system will be implemented using software and infrastructure that will provide LSG with a platform to improve the spatial accuracy of the DCDB. Tasmania: The Tasmanian DCDB originates from scanned and vectorised 1:5000 urban and town cadastral maps. The remaining State coverage is generated from 1:25,000 topographic and cadastral map series and digitised survey diagrams. Thus, the spatial accuracy in the township areas is +/- 3.5 m and +/- 17.5 m for the rest of the State. However, metre-level accuracy can be expected in areas where local government authorities have input their database into the state DCDB; these regions represent approximately 15% of the state’s parcel boundaries. Western Australia: The Western Australian DCDB is known as the Spatial Cadastral Database (SCDB). Originally the SCDB’s spatial accuracy was an outcome of the digitisation of the State hardcopy public plans, resulting in accuracies between 2 and 250m. In order to improve the spatial accuracy of this data, Landgate has been undertaking a programme of spatial upgrade. This has involved replacing the digitised dimensions with observed and or surveyed measurements and adjusting the position of these boundaries in relation to geodetic control points. Areas that have been upgraded now provide point accuracy comparisons between the planimetric coordinates of the map base and the real world position of ± 0.25 metres or better in urban regions, ± 2.0 metres in rural regions and ± 10 metres in pastoral regions. 20 | P a g e 4.2. Project Drivers Vicmap Property is part of the fundamental information infrastructure but increasingly fails to meet the needs and expectations of that group of users requiring high spatial accuracy. It is a dataset on which many other spatial layers in Victoria rely and it is utilised extensively by both public and private sector users. Section 4.1 (above) highlighted a number of background issues to explain why the level of spatial accuracy provided by Vicmap Property is insufficient. The key project drivers can be summarised as follows: Avoidable financial and productivity costs: The lack of spatial accuracy in Vicmap Property leads to significant, avoidable financial and productivity costs in land administration and infrastructure planning and development across the public and private sectors Cost of delay: The financial and opportunity cost of upgrading the spatial accuracy of the Vicmap Property dataset increases every year that action is delayed Risk to Government Credibility: The inferior condition of the State’s fundamental information infrastructure is exposing the Government to reputation risk due to its failure to meet user requirements and to keep up to date with technological advancements. These are discussed in more detail in the following sections. 4.2.1. Driver 1: Avoidable financial and productivity costs The current lack of spatial accuracy in Vicmap Property leads to financial and productivity costs in land administration and infrastructure planning and development across the public and private sectors. The gap between Vicmap Property’s actual spatial accuracy (level and consistency) and users’ requirements is a barrier to the effective and efficient use of the database for land administration and infrastructure planning and development. This lack of high spatial accuracy results in high preparation costs and/or modification costs and expensive time delays for the users who depend on the accuracy of this database. These costs impact industry users, the Government and the community at large. Furthermore, the inadequate spatial accuracy of Vicmap Property leads to higher maintenance and operational costs. The following sections identify some of the key inefficiencies that lead to higher financial and productivity costs to users relying on Vicmap Property for spatial information. 21 | P a g e Unnecessary delays in decision making and approvals It is currently not possible to readily interface Vicmap Property information with land administration processes such as subdivision applications and planning approvals. This results in costly delays for dealing registration and decision making and approvals. Further, given the lack of high spatial accuracy, referral authorities (i.e. those reviewing planning permits etc) are unable to utilise Vicmap Property data and aerial photography to determine whether an approval can be provided or whether further investigation is warranted. For example, in the consultation process, Sue-Anne Beattie from the Towong Shire Council indicated that “In this Shire, we might have to travel several hundred kilometres to investigate a situation simply because some simple questions could not be answered due to Vicmap’s positional inaccuracy. An accurate map base would not only contribute to a smaller carbon footprint for all users, but would save a bit of time and money as we wouldn’t have to get in the car and drive to check out situations that we should be able to answer from our desktop.” The text box below provides an example of the issues faced by councils. Council experience A number of local governments have recently sought to record the location of their assets using global navigation satellite systems (GNSS) or similar modern techniques/technologies. Whilst utilising GNSS to record assets improves the accuracy and reduces the labour intensity of data collection GNSS data collected is currently not compatible with Vicmap Property. Asset information, Vicmap Property and other spatial layers including aerial photography often conflict, limiting the usefulness of the products available. Anecdotal evidence from councils suggest that any labour cost savings from using GNSS are mostly lost when additional work is required to address misaligned data and/or to manually fit the data into the inaccurate map base. In addition, when the boundaries depicted in Vicmap Property move in line with data updates, some of the data collected using GNSS must be manually adjusted to realign with Vicmap Property within the local government data sets. It has been noted by several councils that responding to these manual adjustments requires 0.5 Full time Equivalent staff per council (or approximately $3 million in annual labour costs across the State) Costly surveying work to address Vicmap Property’s inadequate spatial accuracy Infrastructure developers and planning authorities are required to undertake additional and costly field surveys to compensate for the inconsistent and/or inadequate spatial accuracy of the Vicmap Property database. As such, the fitness for purpose of the database is questionable. The following text box provides 22 | P a g e an actual (anonymous) example of the costs incurred by land developers due to an insufficient level of spatial accuracy from Vicmap Property data. Land Development: Re-design requirements In 2009, a significant housing development of 2,000+ lots was designed in an urban fringe area of Melbourne. Concept design, infrastructure layout, financial feasibility and lot layouts were based on contents from Vicmap Property including relative and absolute parcel sizes. The total infrastructure spend for the project was estimated to be $200m with design fees in the order of $5m. However, reliance on Vicmap Property resulted in spatial errors of approximately 20m across the site. As a result, the whole design, including lot layout and infrastructure, needed to be adjusted for the true dimensions of the lots to be sub-divided. The re-design work delayed the project by an estimated three months and cost the developer in the order of $1m plus holding costs associated with the delay in commencement and completion of the project. This is an example where the developer relied on the Vicmap property database. Had the developer undertaken site surveying before design to avoid this error it is estimated that the additional surveying cost would have been in the order of $250,000. Costly Government maintenance and operation costs to overcome Vicmap Property’s inaccuracies (including manual manipulation of data) Processes to maintain Vicmap Property and to update the dataset with new surveying data are inefficient due to the need to ‘work around’ a spatially inaccurate database. For example, DSE’s Information Services Branch is required to distort and/or manipulate new survey accurate data and/or adjoining data in order to align with the current inaccurate Vicmap Property. Strathbogie Shire Council referred to this process as ‘dumbing down’ the data to make it fit.7 In addition to reducing the accuracy of the data incorporated into the map base, this process is an inefficient use of time and resources. This is a significant productivity cost as useful highly accurate data which has been collected, and should theoretically be available, cannot be fully utilised in the State’s authoritative map base. 7 Pers Comm, Di Bock, Strathbogie Shire Council (2010) 23 | P a g e Administrative burden Spatial inaccuracies in Vicmap Property often require Land Victoria and agency staff to perform additional preparatory work prior to using the data. In many cases ‘work around’ processes have been employed to overcome the issues caused by Vicmap Property spatial inaccuracies but these are neither efficient nor appropriate in the legislative framework which relies on the map base. Duplication inefficiencies Where agencies such as municipal councils, utilities and water authorities have not regarded Vicmap Properly as fit for purpose, they have developed and maintained their own spatial databases to ensure the spatial accuracy meets their own needs. Similarly, major infrastructure projects such as CityLink , the North-South pipeline and the Wimmera-Mallee pipeline have required specific map base upgrades to satisfy their needs. This leads to inefficiencies through the duplication of effort in database maintenance. Costs associated with mis-identified underground infrastructure Dial Before You Dig is a free, national referral service for information on the location of underground pipes and cables. Information provided by the service is supplied by most owners/managers of underground assets including water authorities, power, gas, and telecommunication providers. Utility companies contribute their underground asset information to Dial Before You Dig by aligning their assets with the map base. However, the inaccuracies in the map base result in the misalignment of the assets with respect to the property boundaries in Vicmap Property. This misalignment clearly reduces the reliability of the Dial Before you Dig service, often resulting in damaged critical underground assets during excavation and placing the community and the Government at risk. Conversely, works in parcels that have been incorrectly identified as containing assets may be either unnecessarily delayed as time is spent manually searching for an underground asset that is not actually present or suboptimal development takes place to avoid non-existent underground assets. This combination of unnecessary damage to underground assets and unnecessary delays imposes economic risks and costs on the Government, industry and the broader community (refer to following text box). 24 | P a g e Risk to underground infrastructure Victorian asset owners indicate there are more that 30 incidents reported per annum where underground assets are damaged as a result of being incorrectly represented on the plans provided to Dial Before You Dig. Damage to underground assets has the potential to significantly disrupt both residents and businesses (including any customers downstream from the damage) and may result in interruptions to electricity, gas, water, sewerage and telecommunications services well beyond the local works area. Unintentional contact with underground assets also presents a significant OH&S risk to excavator crews and has the potential to result in worker fatalities. In 2009, unintended contact to an underground fibre optic cable in Sydney’s CBD resulted in damage to eight pairs of fibre optic cables and three major copper cables, causing 11 mobile phone towers to be disconnected from the network. The direct cost of the damage was $1m. The indirect costs arising from the unintended contact were far more significant, as the same incident resulted in some 10,000 properties losing telephone and internet services. This business interruption cost was estimated to exceed $30 million.8 The increasing awareness of the inaccuracy of Vicmap Property has led many underground infrastructure owners to record their assets both via geographical co-ordinates and off-sets from fence lines or similar. However, this activity increases labour costs and makes the map base difficult to use due to the excessive information placed onto it. Reduced adoption of new technologies and reduced opportunities for innovation In its current form, Vicmap Property acts as a barrier to the efficient and effective uptake of emerging technologies in the spatial industry. For example, the increased uptake of spatial technologies such as Global Navigation Satellite Systems (GNSS) and aerial photography has revealed anomalies in the data quality of the map base that adversely affect the interface with other spatial data sets. This inhibits the use of these technologies in a broad range of land related activities. One common example is the utilisation of the real time GNSS network covering Victoria (Vicmap PositionGPSnet). Whilst GPSnet provides productivity benefits to many Victorian industries through greater positional accuracy and reliability, some users such as councils, are required to relate these accurate data 8 As reported in Daily Telegraph September 16, 2009. 25 | P a g e sets to the less accurate map base, meaning that the benefit associated with this high accuracy data cannot be fully realised (refer to example on previous page). 4.2.2. Driver 2: Cost of delay The cost of improving the spatial accuracy of the Vicmap Property dataset increases every year that action is delayed. In addition to the continued inefficiency costs discussed in Section 4.2.1, there are associated financial and opportunity costs, resourcing risks and escalated broader economic impacts. There are currently only 413 practising licensed surveyors in Victoria9, of which it is estimated 30% will reach retirement age in the next 10 years. The industry currently has great difficulty in attracting a sufficient number of graduates to replace the retiring population. The gradually shrinking field surveying skill base is of significant concern for delivery of this project. Delaying the commencement of the preparation of a map base with high spatial accuracy will increase the level of risk associated with the project due to the unavailability of a suitably skilled work force. Given the significant amount of field and surveying work required to update the map base, it is critical that the surveying inputs are completed before the impact of the current shortage of surveyors in the market is exacerbated. Delaying action will increase this resourcing risk. Vicmap Property is a dynamic dataset that grows and changes on a daily basis and therefore there is more data to update every year that action is delayed. As such, the cost of addressing this problem also increases with every year that the project is delayed. 4.2.3. Driver 3: Risk to Government Credibility Vicmap Property’s failure to meet user requirements and to keep up to date with technological advancements and widely available and accessible spatial information technologies is undermining users’ confidence in the map base. The inferior condition of the State’s fundamental information infrastructure is exposing the Government to unacceptable reputation risk. There have been examples of this reputation risk translating to liability risk to/from users relying on the information in the current spatially inaccurate map base for their decision making. The Department of Planning and Community Development (DPCD) has faced legal action as a result of an apparent shift in property boundaries with respect to an environmental overlay when the cadastral map base is updated/realigned. Currently, 70% of overlays utilised under the Planning and Environment Act are not related to cadastral features and do not follow parcel boundaries. Therefore, when Vicmap Property is 9 Surveyors Registration Board of Victoria- Register of Licensed Surveyors (as at September 2011) 26 | P a g e updated (typically on a weekly basis), the property boundaries’ relationships to the environmental overlay may change, creating uncertainty around affected property values and plans for property redevelopment and use, resulting in potential legal costs for Government. The Text Box below illustrates how this may occur. Government risk associated with environmental overlays Many of the environmental overlays utilised under the Planning and Environment Act relate to various environmental factors, identifying certain land use zones and hence are not tied to parcel location directly. However, the map base is still needed to represent the planning requirements spatially, which in turn impacts property values as well as property development. Inadequate spatial accuracy of Vicmap Property means that the environmental overlays do not adequately reflect the relationship with properties and that the relative positioning of an overlay with respect to property boundaries may change when the map base is updated to incorporate new or more accurate data. This leads to increased uncertainty regarding affected property values, and increased legal risk to Government. As shown below in Figure 2, a property previously perceived to be outside a planning or environmental overlay may actually be located within the boundary of the overlay when Vicmap Property is updated. Figure 2: Changes to planning overlays from Vicmap updates The economic costs associated with the changing relationships between property boundaries and environmental overlays include: Sudden change to property values for private land owners Unnecessary investments by landowners to comply or conform with environmental overlay requirements, only to discover that these overlays may no longer apply when the relative positioning to the map base shifts 27 | P a g e Legal risk cost to the Victorian Government - An inaccurate and ‘flexible’ Vicmap Property layer exposes the Victorian Government to legal risk. DPCD has already faced legal action as a result of a property that had become affected by an environmental overlay as a result of the cadastre update/realignment10. DPCD is currently required to check/assess approximately sixteen planning certificates in metropolitan areas per month relating to reviews of whether a property is incorrectly impacted by an overlay. These assessments involve mapping the property and the overlay and providing a certificate which legally confirms the overlays. There is an increasing desire to undertake these assessments in rural areas which are more likely to be affected by overlays. For example, developers of subdivisions in urban fringe areas may seek these certificates prior to commencing design and development. Incorrectly declaring a property ‘affected’ or ‘unaffected’ by a planning overlay is a substantial risk for DPCD and leaves them exposed to legal action. Updating to a statewide spatially accurate Victorian Spatial Land Base (VSLB) would remove the risk associated with a perpetually ‘moving’ base Significant administrative burden of processing and resolving these impacts - Currently ISB and DPCD employ a total of two full time staff on an ongoing basis to help adjust and rectify such issues. The Victorian bushfires in 2009 provide another example of the practical importance of the map base. The lack of spatial accuracy in Vicmap Property slowed and potentially hindered the recovery operations at a time when efficiency and certainty were of particular importance to those affected. During the bushfires, most of the boundary fencing was destroyed and as recovery efforts commenced, the location of property titles was not clearly discernable on the ground. Under the direction of the Surveyor-General, a surveying taskforce was created to deal with the matter of re-establishing property boundaries. Whilst the efforts of this (largely volunteer) taskforce is acknowledged and praised, a spatially accurate map base would have significantly reduced the need for on-the ground surveying and therefore reduced the response time giving the public more confidence in the Government’s response. A presentation by the head of the Victorian Bushfire Surveying Taskforce at an industry conference immediately after the fires identified a number of lessons that had been learnt from the project that could be acted upon in preparation for a response to a similar emergency event. One of the key measures identified included: “a spatially accurate digital cadastral map base that could provide benefits to a number of users including emergency services, utility companies and Councils responding to disasters such as bushfires.” 10 Pers comm., Lance Counsel, Department of Planning and Community Development (2010). 28 | P a g e 5. Project Objectives and Scope This section sets out the purpose of the proposed spatial accuracy upgrade of Vicmap Property, the objectives, scope and the expected benefits associated with the proposed investment. It also identifies how the proposed investment contributes to current Government policies and directions. 5.1. Investment Logic Map DSE (ISB and Land Victoria) undertook an investment logic mapping (ILM) session, as summarised in Figure 3. A discussion of the project objectives, scope and benefits are presented in the following Sections. Figure 3: Investment Logic Map PROBLEM The lack of spatial accuracy in Vicmap Property leads to significant, avoidable financial and productivity costs in land administration and infrastructure planning and development across the public and private sectors. 70% The cost of iupgrading the spatial accuracy of the Vicmap Property dataset increases every year that action is delayed 20% The inferior condition of the State’s fundamental land information is exposing the Government to reputation risk due to its failure to meet user requirements and to keep up to date with technological advancements 10% 29 | P a g e INTERVENTIONS High Level BENEFITS Support technological innovation and effective data use by Victoria’s map base users 45% Reduce financial and productivity inefficiency costs for government and private sector users of Vicmap Property Promote systems to support efficient use of spatial land base and other spatial data 35% Facilitate innovation and broader economic benefits by providing more robust and accessible information infrastructure SOLUTION Changes 45% Assets needed Develop and implement a State Survey Strategy to input to spatial land base Develop and implement strategy to integrate new and existing survey accurate data into spatial land base Enhanced survey data collection portal Develop and implement a survey accurate spatial land base IT hardware and software mapbase systems 20% Encourage public and industry access to accurate spatial map base 10% Increasing Vicmap Property's relevance and user base over time 20% Respond to risk of shrinking skill base in the surveying sector 10% Avoid cost to Government associated with delayed improvement of Vicmap Property accuracy 15% 5.2. Objectives There is a need to address the challenges associated with the spatial accuracy of the current Victorian map base, Vicmap Property, so as to mitigate the risks identified in Section 4.2. In order to do this, the intention of this project is to rebuild Vicmap Property to provide a highly spatially accurate VSLB. The objectives of this project are to: Create a VSLB of high spatial accuracy Ensure a single authoritative property map base for the whole of Victoria Support efficient use of the VSLB and other spatial data in Victoria Support innovative use of the VSLB and spatial technologies Continue and enhance the practice of spatial data custodianship in Victoria Provide a VSLB that complements other Government initiatives such as ePlan and SPEAR . 5.3. Scope The project will deliver a VSLB of high spatial accuracy in urban and peri-urban areas (70% of the map base) and improved spatial accuracy in rural areas. This project is limited to the two-dimensional (horizontal) aspects of the parcel and property layers of Vicmap. Changes to other spatial data layers that link to Vicmap Property will be the subject of future works as required. 5.4. Project Benefits The development of a VSLB is expected to deliver a range of benefits to both the public and private sectors. High spatial accuracy and improved alignment and interfacing with other data sets will reduce the costs associated with the utilisation of those data sets for most users. Development of the VSLB will also allow the full integration of land and spatial information systems including recent system investments such as Victorian Online Titles System (VOTS), Electronic Conveyancing, SPEAR and ePlan thereby supporting spatial enablement for Victoria. The overarching benefits including their more detailed breakdown are provided in the following table. These benefits will be assessed further in Sections 8.2 and 9. 30 | P a g e Table 7 : Benefit summary Benefit Benefit (detail) (consistent with ILM) Reduce financial and Reduction in survey time and cost due to more accurate dataset – including reduced productivity inefficiency field work, avoided mistakes, error correction as well as more timely project costs for government and finalisation private sector users of Reduced costs associated with asset management Vicmap Property Reduced unintentional, avoidable damage to underground infrastructure Reduced cost of re-design of projects that have relied on inaccurate datasets Lower land development and labour costs from reduced need for site work by surveyors Improved decision making in regards to emergency response and disaster management Lower labour costs in managing and maintaining the map base Reduced cost of maintaining/developing duplicated databases Reduced financial and economic cost associated with manipulation of data to align with a less accurate map base Facilitate innovation and Reduced barriers to the adoption of new technologies broader economic Improved compatibility between Victoria’s map base and other systems, including benefits by providing more robust and SPEAR and ePlan accessible information Reduced cost of accessing and using map base information leading to improved productivity which in turn facilitates innovation infrastructure Increasing Vicmap Increased public confidence in the VSLB as demonstrated by: Property's relevance and Elimination of duplicated map bases held by government authorities and utilities user base over time An increase in the number of new products and services based on the VSLB. A decrease in complaints about the spatial accuracy of the map base data Avoid cost to Government associated with delayed improvement of Vicmap Property accuracy 31 | P a g e Utilisation of existing skill base (internal and external to the department) for implementation of an improved map base Earlier realisation of benefits from existing government investment in spatial information 5.5. Strategic Alignment Development of the VSLB aligns with a range of policies, strategies and other projects currently being undertaken by Government as listed in Table 8 below. Development of the VSLB will support Land Victoria in aligning with a range of legislative requirements. In conjunction with the strategies listed, there is a range of projects and programs that have been introduced across government that development of an improved map base will align with. These include ePlan and SPEAR which allow for land transactions in Victoria to be submitted and processed electronically. Appendix C provides further detail on relevant legislation and its fit to this project. Table 8: Strategic Alignment Strategy Policy Fit Comments Land Victoria’s Strategic Plan 2009-14: Goal 2: Integrate and The spatially inaccurate Vicmap Property the next five years - priorities include: spatially enable Land is a barrier to the integration of a range Contributing to the implementation Victoria’s land of land information systems and industry of Electronic Conveyancing in information innovations. Victoria and nationally Without a high spatially accurate map Establishing the business case for a base, full benefits may never be realised survey-accurate digital cadastral on a range of systems including ePlan, database SPEAR and the integration of aerial Fully integrating land and spatial photography. information systems Contributing to the implementation of electronic plans of subdivision/ consolidation Victorian Spatial Information Strategy Spatially enabling The lack of high spatial accuracy in 2008-2010 strategy to spatially enable Victoria requires spatial Vicmap Property limits the framework Victoria into the future through: information and on which to build a strong spatial Creating a framework in which the products to be readily information system. Vicmap Property use of spatial information can available and interface data is not highly accurate and is flourish in a way that supports primarily used as an index and property industry quality information system. requirements. Vicmap Property is frequently misaligned Adopting an inclusive approach to the management of spatial information with other spatial data including aerial Developing the spatial information photography which undermines the community through collaboration authoritativeness of Victorian Spatial 32 | P a g e Strategy Policy Fit and partnerships Comments Data. Maintaining the foundations for Spatial Information Management Defining the vision for ‘Spatially Enabled Victoria’ Victorian Spatial Council – December 2009 Forum 5.6. The need to realise Vicmap Property is a fundamental spatial enablement building block in achieving spatial Data and services enablement. Current spatial inaccuracies that are accessible in Vicmap Property, when used in and accurate, well conjunction with aerial photography and maintained and other spatial data, distract from the sufficiently reliable usability and functionality of the VSLB to Need for precise drive efficient spatially enabled positioning outcomes. Critical Success Factors The following critical success factors have been identified and will be used to ensure the ‘fit’ of the proposed options. The critical success factors were determined through consultation with key project stakeholders. Table 9: Critical success factors Element Definition Data The spatial data held in the VSLB will represent all parcels in Victoria. The map base will be current, reliable and complete and achieve high spatial accuracy over time through the use of survey accurate data. Data will be easily interrogated and able to be efficiently interfaced with government and other private sector data sets. Continuity Data will be able to be maintained in a sustainable manner. Allows for continuous improvement in data quality, reliability and use of innovation Can be maintained with the shrinking skill base Systems The VSLB will be accessible and managed in an integrated system. Governance Good governance with a clear understanding by stakeholders of the responsibilities for the VSLB. A central point of governance to oversee all elements of the VSLB. Custodianship A single parcel/property spatial database will exist for Victoria managed and maintained by DSE, based on data provided by the relevant business custodians. 33 | P a g e 6. Stakeholder Analysis In line with the DTF Business Case guidance, the following key stakeholders were identified and consulted. Consultation took the form of workshops and one-one-one discussions. The broader spatial industry (i.e. users of spatial information) was also invited to provide written submissions. Consultation notes are provided in Appendix D. In the context of this consultation, where Stakeholders have referred to “survey accuracy” in regard to the map base, this has been interpreted as the stakeholders requiring the map base to be compiled from survey accurate spatial data to produce a map base that has an absolute accuracy with uncertainties (or tolerances) that align with the figures they have specified, for example within or between 0.05 metres and 0.1 metres. Table 10: Stakeholder analysis Stakeholder Position/ Key Issues Project Focus Local Government VSLB must be accurate to support The needs of local government in planning works, asset regards to the spatial accuracy of identification and alignment of the spatial database are met City of Melbourne Mornington Peninsula Shire Council Local Government Spatial Reference Group City of Greater Dandenong City of Wodonga Central Goldfields Shire aerial photography and other data sets and systems such as property rates/ ownership systems. Council Colac Otway Shire Strathbogie Shire Council Bass Coast Shire Council City of Casey Towong Shire Council Moira Shire Profession Surveying Industry VSLB needs to be ‘true’, including To ensure the process for Bodies accurate and complete and developing the survey accurate Surveying and Spatial support the needs of cadastral spatial database engages surveyors Sciences Institute surveyors who define and re- and utilise their knowledge and establish parcel boundaries. skills where appropriate. The Institution of 34 | P a g e Stakeholder Position/ Key Issues Project Focus Critical need to be able to align Access to a survey accurate spatial assets with the VSLB. Support database that supports effective utility rating and ownership and efficient use in operational systems. processes and infrastructure Surveyors Victoria Association of Consulting Surveyors Victoria Utility providers Barwon Water Coliban Water Yarra Valley Water planning and development. Crown Land Registry Register and record Crown land Spatial database correctly (Land Victoria) parcels represents all Crown land parcels. Land Registration Services Process and register land The new spatial database has a (Land Victoria) subdivision, consolidation and high level of completeness and property boundary surveys spatial accuracy that supports recent programs such as ePlan. Office of the Surveyor-General Primary government authority on A ‘true’ survey accurate Victoria (Land Victoria) cadastral surveying and the representation, the process for maintenance of the integrity of developing the survey accurate the cadastre. VSLB must map base should engage surveyors maintain the integrity of the and utilise their knowledge and surveying data captured. skills where appropriate. Oversee Crown Land Consistent approach to Management for holdings within representing freehold and Crown Victoria. Utilise VSLB to support land. Public Land Division administration Information Services Branch Current maintainers of the VSLB Clear communication of the new (formerly SII) (DSE) (including maintenance product and changes to all users. contracts) Ongoing relationships with users can be maintained through any upgrade program. Valuer- General Victoria States independent authority on Spatial database correctly (Land Victoria) property valuations. Oversees represents all parcels. Ensure government property valuations relative spatial accuracy is and council rating valuations represented and maintained. Department of Planning and Administer the planning scheme Map base that supports effective Community Development and planning maps in line with and efficient planning processes 35 | P a g e Stakeholder Position/ Key Issues Project Focus (Statutory Systems and Built the requirements of the Planning and removes risk from “shifts” in Environment) and Environment Act affected parcels. Department of Transport- The VSLB must be spatially Access to a survey accurate spatial VicRoads complete and accurate. It must database that supports effective maintain road widths and road and efficient infrastructure parcels. Must be survey accurate planning and development. to support use for infrastructure concept design. 36 | P a g e 7. Summary of Options for Spatial Improvement This section outlines the options considered for the assessment for a VSLB. This section does not compare the relative merit of the options. A full options assessment is provided in Section 8. The option development for this business case commenced with a review of the needs of both DSE and other major stakeholders in regards to the VSLB. A broad selection assessment was undertaken with the options which were then shortlisted through the initial assessment criteria, with the identification of five approaches to be developed and assessed as part of this business case. The options shortlisted have demonstrated the ability to be delivered with examples and case studies of previously successful implementation of these approaches both in Australia and internationally. This section contains an outline of the options put forward for assessment and of the potential approaches involved in improving the spatial accuracy of the VSLB. Option 1 - Do nothing (the base case) Option 2 - Resurvey of the entire State Option 3 - Rebuild from existing survey data Option 4 - Adjustment from aerial imagery Option 5 - Mixed approach. In developing these options, a number of industry case studies from across Australia (including Victoria) and New Zealand have been researched to confirm validity of these approaches. 7.1. Option 1: Do Nothing (Base Case) 7.1.1. Overall Description This is effectively a Business as Usual (or ‘without project’) option, which is defined by the current approach for improving the spatial accuracy of Vicmap Property. This approach only allows for localised, incremental improvement to be achieved over an extended period of time. The base case will not achieve state-wide high accuracy spatial data, will not address any of the problems outlined in Section 4.2, and will not meet the project objectives. It is only included as an option for the purpose of completeness. 37 | P a g e 7.1.2. Summary of Approach Option 1 (the base case) is a continuation of the status quo. Without additional funding, improvements to the existing Vicmap Property are limited to the following: Continuing to update Vicmap Property to identify and include all new properties and where possible, rectify erroneous parcel/property information Updating sections of the map base as new surveying data becomes available. As stated above, without a holistic approach supported by additional funding this will not achieve improvements in the spatial accuracy of the dataset as a whole. A summary of the inputs, costs and achievements associated with Option 1 is summarised below. Inputs/Dependencies Current inputs to maintaining Vicmap Property, which includes: New survey activity (e.g. subdivisions) will be used to update the dataset, but the full benefit of their improved accuracy cannot be fully utilised due to limitations in the current dataset Continued dependence on data from DSE, Barwon Water and Melbourne City Council Continued high dependence on a shrinking skill base to maintain Vicmap Property for an indefinite period. Achievable Accuracy Accuracy range achieved is 0.1-25+m; Will not achieve high spatial accuracy in urban and peri-urban areas Will not achieve high spatial accuracy in rural areas Will not meet user requirements and expectations for spatial accuracy Will not achieve consistent state-wide improvement Improvement in spatial accuracy will be ad-hoc at best, without the implementation of a strategic and whole-of system approach Cost No additional financial cost over current funding levels Significant opportunity cost associated with continued inefficiency as a result of inadequate accuracy, duplication and inability to adopt new technologies Achievements of user needs Long term resourcing burden due to the shrinking skill set Vicmap Property will continue failing to meet user demand and increasing expectations. 38 | P a g e 7.1.3. Impact of Approach Under this approach Vicmap Property will continue failing to meet user requirements and expectations for high spatial accuracy. Any improvement to spatial accuracy would be gradual and ad-hoc. It is noted that as part of the ongoing maintenance of Vicmap Property, new survey plans would be used to update the map base with respect to changes in cadastral boundaries. This may provide some improvement in spatial accuracy for parcels directly affected by this data but will not improve the spatial accuracy of the map base as a whole. Continuing with this approach will necessitate the continuation of expensive surveying methodology to tie cadastral surveys to the current spatial reference and the unnecessary use of scarce resources. In order to improve the spatial accuracy of the map base, a consolidated and methodical approach is needed to ensure that improvements to one section of the map base do not inadvertently alter the spatial accuracy of another section. This approach is not possible under the base case and as such, high spatial accuracy cannot be achieved under the base case. As new spatial data is incorporated into the map base, users will be faced with inconsistent spatial accuracy throughout the map base, leading to increased confusion. This will further reduce user confidence and adversely impact government credibility. A summary of the benefits and costs associated with Option 1: base case is provided in the table below. Table 11 Option 1: Cost and benefit summary Benefits No additional investment required Costs Does not address productivity and financial inefficiencies associated with the spatial inaccuracies in the current Vicmap Property Does not achieve high spatial accuracy Does not address government credibility concerns Does not address risks associated with the shrinking skill base in the surveying sector Does not facilitate integration with new technologies such as GNSS and existing government programs and systems introduced to improve the efficiency and effectiveness of land administration in Victoria. 39 | P a g e 7.2. Option 2: Resurvey of the Entire State 7.2.1. Overall Description This is the only approach which can deliver state-wide high spatial accuracy in a map base. It involves a resurvey of the whole state such that there are quality field measurements/survey plans available for all parcels in the State. This approach rebuilds the map base from survey accurate data and provides a map base of high spatial accuracy to an accuracy level consistent with the surveying regulations. This option involves a significant field survey effort and as it is highly resource intensive it represents a significant delivery risk. 7.2.2. Summary of Approach To deliver a state-wide map base with high spatial accuracy, this approach will utilise existing survey accurate data where possible and require a resurvey of the remaining areas of the state. The extent of the resurveying effort will depend on the quality of the existing data which is known to be variable and of limited extent. This approach is summarised as follows: Undertake field surveys to correct or improve cadastral information shown to be in error based either on the age or quality of survey work or where there are inconsistencies between surveys. This would include the formal amendment of Certificates of Title to accord with surveyed boundaries where appropriate Combine existing available digital observations with re-entered and/or field observations to create a single seamless spatial data set Use a mathematical least squares process to adjust derived boundary dimensions from measurements to monuments in cadastral surveys and provide statistical measures that indicate the accuracy of the adjustment from which a framework of geographical coordinates will be derived Test the accuracy of geographic coordinates, assigning accuracy status of coordinates that satisfy requirements and highlighting areas for further consideration Maintain topology of the adjusted cadastre i.e. parcels retained as closed polygons Update spatial data set with new survey measurements and readjust to generate new coordinates, as well as residuals and other statistics that indicate the accuracy of the new coordinates Deliver a highly spatially accurate VSLB. 40 | P a g e A summary of the inputs, costs and achievements associated with Option 2 is summarised below. Inputs Significant human resources required e.g. 500 FTE staff for 10 years Additional field survey measurements and coordinated control for input into the adjustment process Achievable Accuracy Existing survey accurate data Accuracy range achieved is 0.03-0.1m Will achieve high spatial accuracy in urban and peri-urban areas. Will achieve high spatial accuracy in rural areas Will meet user requirements and expectations for high spatial accuracy Will achieve consistent state-wide improvement This is the only option that will deliver a VSLB of high spatial accuracy and also meet the requirements of users who require survey accuracy as defined by the survey regulations. However this option is significantly limited by high cost, the very large human resource requirement and the limited pool of licensed surveyors in Victoria. Cost Approximately $930 million (real 2011/12 dollars) Achievements of user needs Fully meets the spatial accuracy needs of all users 7.2.3. Impact of Approach This field-based approach is resource intensive but would deliver improvements in spatial accuracy across the State to satisfy all users. The timeframe for this approach is dependent on the area that requires resurvey and the availability of suitable resources required to complete the additional field work. A summary of the benefits and costs associated with Option 2 follows in Table 12. 41 | P a g e Table 12 Option 2: Cost and benefit summary Benefits Provides a state-wide highly spatially accurate Cost cadastral map base Constructed from survey accurate data, and therefore meets the requirements of users Very resource intensive and therefore highest cost option High resourcing risk due to limited pool of licensed surveyors in Victoria requiring ‘survey accuracy’. Addresses project drivers by meeting user requirements and avoiding productivity and financial costs associated with current spatial inaccuracies Reduced duplication inefficiencies by public and private sector Provides state-wide consistency in spatial accuracy. 7.3. Option 3: Rebuild from existing survey accurate data 7.3.1. Overall Description This approach will rebuild Vicmap Property using existing survey plans and title records. It involves the capture of survey observations[1] from existing (and future) cadastral survey plans to rebuild the cadastre, thus enabling a mathematical adjustment to be undertaken based on known or field observed survey control supplemented with additional field survey measurements to provide coordinated control. 7.3.2. Summary of Approach This option has a number of key steps. The approach is consistent with the initial stages of work adopted by Land Information New Zealand (LINZ)11 in its ‘Survey Conversion Project’ which aimed to convert and adjust survey data to maximise the number of coordinates which achieve high spatial accuracy. This approach can be summarised as follows: [1] This refers to taking the original survey measurement data (from historical field survey notes/plans) and rebuilding the parcel boundaries, i.e. rebuild from existing survey data (or observations). 11 Row, LINZ 2008 42 | P a g e Capture boundary dimensions for all current parcels Capture traverse connections to survey control Survey and capture additional detail (e.g. cross-road traverse ties at/near intersections) Ensure sufficient survey control density is available to meet the relevant legislated accuracy needs for urban, peri-urban and rural areas Capture the latest co-ordinated survey mark information for relevant control to which measurements are available Use a mathematical least squares process to adjust captured boundary/ traverse dimensions to generate new geographic coordinates and statistical measures that indicate the accuracy of the new coordinates Test the accuracy of geographic coordinates against pre-determined tolerances that will provide a map base of high spatial accuracy, highlighting areas for further investigation Maintain topology of the adjusted cadastre (i.e. parcels retained as closed polygons) Undertake additional field work to correct or improve cadastral information that has shown to be in error either from age or quality of survey work, or where there are inconsistencies between surveys Update spatial data with new survey measurements and readjust to generate new coordinates, residuals and other statistical measures that indicate the accuracy the new coordinates Maintain topology and re assign relevant title information. A summary of the inputs, costs and achievements associated with Option 3 is summarised below. Inputs A human resource requirement of 60 FTE over 10 years Existing survey plans and associated title records Relevant identified survey mark information Sufficient survey control density to meet the accuracy needs for all areas including urban, peri-urban and rural Additional field survey measurements and coordinated control for input into the adjustment process. Achievable Accuracy Current relevant title information. Accuracy range achieved is 0.03-0.1m Will mostly achieve high spatial accuracy in urban and peri-urban areas Will not achieve high spatial accuracy in rural areas Will mostly meet user requirements and expectations for spatial 43 | P a g e accuracy Will mostly achieve consistent state-wide improvement This option will mostly deliver a VSLB of high spatial accuracy but will be significantly limited by the availability of quality survey plans in some areas of the State. Overall, this option will deliver high spatial accuracy of urban areas only. Cost Approximately $190 million (real 2011/12 dollars) Achievements of user needs Partially meets the accuracy needs of users 7.3.3. Impact of Approach Subject to the availability of suitable survey plan data and title records, this approach will result in significant improvement in spatial accuracy of the existing Vicmap Property to survey accuracy in many areas. It will also allow the ongoing systematic adjustment of Vicmap Property with minimal impact on the normal day to day maintenance and distribution of the data. The timeframe for this approach is largely dependent on the availability of suitable resources and time taken to complete the initial data conversion and the number of parcels. It is estimated the timeframe to achieve spatial upgrade using this approach would be in excess of 10 years depending on the extent of the State this option is applied to. This option also allows for future inclusion of survey accurate data and upgrading of the spatial accuracy of the VSLB. A summary of the benefits and costs associated with Option 3 is provided in the table below Table 13 Option 3: Cost and benefit summary Benefit Will partially achieve high spatial accuracy Improves day-to-day operation of Vicmap Property High financial cost associated with implementation Unlikely to achieve state wide high spatial accuracy Approach has been tested and proven in New Zealand Cost Success dependent on existing data quality Will deliver survey accuracy in some urban which cannot be confirmed prior to areas (though not consistently) implementation 44 | P a g e Burden on existing resources 7.4. Option 4: Adjustment from aerial imagery 7.4.1. Overall Description This approach will adjust the existing Vicmap Property using ortho-rectified imagery12. This approach effectively uses physical boundaries such as fences to define the boundaries in the map base. Whilst a less resource intensive and faster option than those previously discussed, its effectiveness ultimately depends on the whether these physical boundaries align with cadastral boundaries. It is known that this is often not the case and hence this method of adjustment will lead to further distortions in the map base and fail to satisfy the needs of most users, posing further risk to Government’s credibility. 7.4.2. Summary of Approach The initial stage of this approach involves deriving a set of measurements (bearings and distances) from Vicmap Property to create a spatial data set which in combination with similar data derived from the aerial imagery is able to be adjusted to provide improved spatial accuracy. Fundamental to this option is the availability of suitably accurate survey control in the form of fencing and/or other forms of reliable boundary features. This adjustment-based approach is dependent on the existing quality of Vicmap Property data, quality of the imagery and the densification of the survey control. Key assumptions in this process are that fencing is coincident with the true position of the cadastral boundaries and that a significant proportion of boundaries are fenced. The method of determining survey control can vary. One approach is the use of high resolution aerial imagery to derive survey control as compared to a second method of field measurement to generate coordinates for adjustment purposes. The methodology of this approach can be summarised as follows: Derive a parcel boundary data set of measurements (bearings and distances) from the current Vicmap Property to create a spatial data set which is then able to be adjusted and upgraded. This 12 Ortho-rectified imagery refers to imagery that has been corrected for distortions inherent in a flat photograph of a three-dimensional object (the earth's surface). 45 | P a g e involves converting the map base into ‘observation’ data so that weightings/constraints can be assigned and used in the adjustment process Identify high resolution imagery that would provide acceptable accurate coordinates for control purposes Capture control points from imagery or field survey capture Capture measurements of all fences and other features that define/delimit separate parcels throughout the state Use a mathematical least squares adjustment process to adjust derived boundary dimensions to generate new geographic coordinates and statistical measures that indicate the accuracy of the new coordinates Test the accuracy of geographic coordinates, assigning accuracy status of coordinates against predetermined tolerances, highlighting areas for further investigation Maintain the topology of the adjusted cadastre (i.e. parcels retained as closed polygons). A summary of the inputs, costs and achievements associated with Option 4 is summarised below. Inputs A human resource requirement of 15 FTE over 10 years A spatial data set derived from Vicmap Property which is then able to be adjusted and updated Achievable Accuracy Suitable high resolution imagery Ortho-rectified and geo-referenced High resolution Digital Elevation Model Coordinated survey control & relevant accuracy statements Derived from imagery Derived from field measurement. Accuracy achieved is 0.1-10m Will not achieve high spatial accuracy in urban and peri-urban areas Will not achieve high spatial accuracy in rural areas Will not meet user requirements and expectations for high spatial accuracy Will not achieve consistent state-wide improvement Option 4 will reduce the number of gross inaccuracies in the map base but is largely dependent on the underlying quality of Vicmap Property, the imagery and the degree of alignment of fencing to the cadastral 46 | P a g e boundaries. Cost Approximately $55 million (real 2011/12 dollars) Below Options 2 & 3 Achievements of user needs Does not meet the accuracy needs of the majority of users interviewed but will remove gross errors in the map base, particularly in rural areas. Does not deliver high spatial accuracy to the map base. 7.4.3. Impact of Approach The advantage of this approach is that the timeframe to undertake the spatial improvement is significantly reduced because there is a reduced need to re-enter or capture the title dimensions from existing survey plans. The result of this approach is determined by the existing quality and accuracy of Vicmap Property, the digital imagery and the uncertainty of the correlation of the derived data with the true position of the cadastral corners and/or boundaries. This approach will not provide the levels of spatial accuracy being sought. This approach is seen as an effective and appropriate method for improving spatial accuracy in some rural areas where the general accuracy requirements are lower than in other areas and time permits a more gradual improvement in spatial accuracy. A summary of the costs and benefits associated with Option 5 is summarised in the following table. Table 14 Option 4: Cost and benefit summary Benefit Cost Less resource intensive Considered to be an effective low cost option issues associated with the current Vicmap for rural areas (where spatial accuracy Property dataset requirements are not as onerous) Will not generally address the spatial accuracy Will result in significant variation in spatial accuracy across the map base – ranging from 0.1m to 10m 47 | P a g e There will be continued: Productivity and financial efficiency costs Risk to government credibility Duplication costs. 7.5. Option 5: Mixed approach 7.5.1. Overall Description This option will apply the methodologies outlined in Options 2, 3 and 4 according to their ‘fit’ and appropriateness to the urban and/or rural environment. 7.5.2. Summary of Approach This option will utilise the approach of Option 3 to rebuild the map base from existing survey data in conjunction with the re-surveying approach of Option 2 in the urban and peri-urban environments combined with the adjustment approach of Option 4 and selected field survey/observation based adjustment in rural areas. This approach is consistent with the complete approach being considered in New Zealand13. A summary of the inputs, costs and achievements associated with Option 5 is summarised below. Inputs A human resource requirement of 50 FTEs over 10 years. Existing survey plans and associated surveyors field note records A parcel boundary data set derived from Vicmap Property which is then able to be adjusted and updated Suitable high resolution Ortho rectified and geo-referenced imagery High resolution Digital Elevation Model Coordinated survey control & relevant accuracy statements Derived from Imagery and field measurement Relevant identified survey mark information Sufficient survey control density to meet the accuracy needs for all areas including rural, urban and peri-urban, typically at millimetre accuracy Current land title information Additional field survey measurements and coordinated control for input into the adjustment process. 13 The initial stage of the New Zealand approach has been discussed in this report and Land Information New Zealand is now considering the use of imagery to improve accuracy in rural areas. 48 | P a g e Achievable Accuracy Re-entered parcel measurements and field survey observations Spatial accuracy achieved is: Urban & peri-urban: 0.03-0.1m Rural: 0.1-10m. Will achieve High spatial accuracy requirements in urban and periurban areas Will not achieve High spatial accuracy in rural areas but will achieve significant reduction in gross inaccuracies Will mostly meet user requirements and expectations for High spatial accuracy Will not achieve consistent state-wide improvement but facilitates future spatial upgrades of rural areas This option delivers a compromised highly spatially accurate VSLB for Victoria. This option is focused on delivering a solution that balances the needs of users and demands on the map base against the areas of highest need and the cost and resource constraints in the market. This option also allows for the VSLB to be further upgraded in the future when there is sufficient demand in rural areas for survey accuracy. Cost Approximately $158 million (real 2011/12 dollars) Achievements of user needs Delivers significant accuracy improvements. Meets users need in urban and peri-urban areas. Does not meet high spatial accuracy requirements in rural areas but removes gross errors. 7.5.3. Impact of Approach This approach combines methods that will: Deliver high spatial accuracy for areas of the VSLB that will face higher intensity of use (e.g. urban and peri-urban areas) Improve the spatial accuracy for areas that will face lower intensity of use of the VSLB (rural areas). This method balances the needs of users who require spatial accuracy and the cost effectiveness of delivering improved spatial accuracy across a large geographic area. A summary of the costs and benefits associated with Option 5 is summarised in the following table. 49 | P a g e Table 15 Option 5: Cost and benefit summary Benefit Improves spatial accuracy for all users Improves government credibility Delivers high spatial accuracy for higher density areas (urban and peri-urban) Delivers significantly improved spatial accuracy in rural areas Allows for the VSLB to be further upgraded in the future 50 | P a g e Cost High financial cost associated with implementation (similar to other options) Does not provide high spatial accuracy across the state. 8. Options Analysis The five options were assessed and compared using the following: Qualitative assessment against the critical success factors. This assessment scores each option based on the cost-effectiveness of achieving the critical success factors detailed in Section 5.6. Achievement of the critical success factors cannot be quantified in monetary terms and cannot be captured in the quantitative assessment (see below). As such, cost-effective compliance with the critical success factors can only be assessed qualitatively. Quantitative assessment using a cost-benefit analysis (CBA) framework. Where possible, this approach quantifies the costs and benefits associated with each option and ranks the options based on their economic net present value (NPV) and benefit cost ratio (BCR). A further description of this approach is provided in Section 8.2. 8.1. Qualitative assessment against critical success factors The purpose of this assessment is to compare the cost effectiveness of each of the 5 options in realising the critical success factors. Table 16 outlines the critical success factors, their measurement and the weighting used to assess the options against these criteria. In addition to the critical success factors, each option has been assessed on its ability to deliver high spatial accuracy. This is the primary objective and compliance is essential. Scoring against criteria is completed on a scale of 1 to 10, where 1 does not meet the project objectives and critical success factors and 10 exceeds the objectives. Table 16: Assessment Criteria Criteria Measurement Weighting Whole-of-life costs (NPV) NA Financial Cost Non- Financial Data The spatial data held in the VSLB will correctly represent all parcels in Victoria in line with the relevant land and surveying legislation. Data will be of high spatial accuracy, current, reliable and complete Data will be easily interrogated and able to be efficiently interfaced with other government and private sector spatial data sets 51 | P a g e Weighting 40% Criteria Measurement Continuity Data will be able to be maintained in a sustainable Weighting Weighting 20% manner Allows for continuous improvement in data quality, reliability and use of innovation Can be maintained with the shrinking skill base Systems The VSLB will be accessible and managed in an integrated Weighting 20% Governance system Good governance with a clear understanding by Weighting 10% stakeholders of the responsibilities for the VSLB. A central Custodianship point of governance to oversee all elements of the VSLB. A single parcel/property spatial database will exist for Weighting 10% Victoria managed and maintained by DSE, based on data provided by the relevant custodians. The non-financial criteria and scoring are presented in more detail in Appendix E. 8.1.1. Results from the qualitative assessment The scores allocated against each criterion for all options and the total weighted score results are provided in Table 17 overleaf. Based on the qualitative assessment of the critical success factors, Option 1 and Option 4 are considered to be non-compliant. Option 1 is the least attractive option as it does not meet any of the needs of DSE or those stakeholders who require high spatial accuracy. Option 4, whilst being a much cheaper option than the other alternatives does not achieve high spatial accuracy for any part of the State and does not meet the project objectives. Most importantly, Option 4 does not facilitate the future improvement to a highly spatially accurate database. The most preferred option is Option 5 (Mixed approach) as it presents the best value for money in delivering the critical success factors and achieves high spatial accuracy for 70 percent of the map base. Option 5 also provides the opportunity for ongoing improvement and enhancement over time. 52 | P a g e Table 17: Summary of qualitative assessment against critical success factors Criteria/ Option Option 1 Do Nothing Option 2 Resurvey Option 3 Rebuild Option 4 Imagery Option 5 Mixed $0 $664.2m $144.6m $39.9m $112.5m No Yes In part * No In part ** Data 1 9 8 4 7 Continuity 1 9 8 4 7 Systems 5 9 9 8 9 Governance 1 8 8 6 8 Custodianship 1 8 8 4 8 Total Non-financial Score (unweighted) 9 43 41 26 39 Total Non-financial Score (weighted) out of 10 1.8 8.8 8.2 5 7.6 Cost per nonfinancial point (weighted) NA $75.5m $17.6m $8.0m $14.8m Financial Total Net Present Cost (NPC)*** Will deliver High Spatial Accuracy? Non-Financial**** Ranking (1 is best) NA 3 2 NA 1 Non compliant Non compliant with spatial with spatial accuracy accuracy requirements requirements * Option 3 will not deliver accuracy improvements to the majority of rural areas where modern survey observation data is largely not available **Option 5 (Mixed approach) will deliver high spatial accuracy in urban and peri-urban areas and will result in the removal of gross errors in rural areas. *** The Net Present Cost is a discounted cash-flow and does not represent the total real or nominal funding requirement for the project. It is measured over a 20 year timeframe from first year of implementation applying a discount rate of 6.5 (real). **** Score on a scale of 1 to 10. The summary of the qualitative assessment of the options is presented below. Option 1: (Do Nothing or base case option). This option fails to address the project and business objectives of DSE, making this option unacceptable. As such, Option 1 is the least preferred option. In addition to not achieving high spatial accuracy it provides no clear mechanism (other than undertaking Option 2, 3 or 5) to achieve high spatial accuracy over time. Option 2 (Resurvey of the Entire State): This option is the best option in terms of achieving the highest level of spatial accuracy possible across the whole State. However its very significant resourcing requirements make it impractical to implement. It is estimated that Option 2 will require at least 70 surveying teams (of two/ three people) full time for a period of 10 years. There are currently only 405 practicing licensed surveyors in Victoria and as such, there would be an inability of the market to resource this option without causing a significant shortage in the broader market. 53 | P a g e Option 3 (Rebuild from existing survey data): This approach provides for high spatial accuracy across Victoria subject to the data being used for the rebuild being of survey accurate quality (approximately two thirds of the State’s parcels that fall within the urban/peri-urban areas). This option will not deliver accuracy improvements to the majority of rural areas where modern survey observation data is largely unavailable. Option 4 (Adjustment from aerial imagery): This approach will not deliver high spatial accuracy or meet the project objectives. As such, this option does not meet the project objective of a highly spatially accurate map base. Option 5 (Mixed approach): This option presents the best value for money in the qualitative assessment (lowest cost per non-financial point), achieving the non-financial benefits and outcomes for the lowest cost among the valid options. Importantly, it practically achieves the needs the key stakeholders, enabling a map base of high spatial accuracy to be developed in those urban and periurban areas which are most critically in need of a map base with such accuracy. This approach can be delivered with the market available resources and allows for the future delivery of high spatial accuracy in rural areas. 8.2. Quantitative Assessment: Cost Benefit Analysis (CBA) This section contains a breakdown of the whole-of-life cost analysis that has been undertaken. The findings from the options assessment are also presented in this section noting that the preferred option has been identified as Option 5 (Mixed approach). A cost-benefit analysis (CBA) assesses the economic viability of a project from the whole of society perspective. A CBA assigns a monetary value to all the costs and benefits associated with a given option relative to the base case (i.e. Option 1, do nothing)14. This includes all the financial, economic, social and environmental costs and benefits. A project is deemed to be economically viable when the value of the benefits outweigh the value of the costs. The key outputs and decision criteria from a CBA include: Benefit cost ratio (BCR) – a ratio of all the quantified direct benefits and costs (including social, environmental and financial impacts) associated with each option. A ratio greater than one indicates that the (environment, social, and financial) benefits are greater than the costs and that the project provides a net benefit to society. 14 As such, Option 1 is not assessed an option in its own right 54 | P a g e Net Present Value (NPV) – the present value of the net benefits associated with a project (i.e. present value of the benefits less the present value of the costs). A NPV which is greater than zero implies that the project or policy is economically viable. Unlike a BCR, the NPV cannot be used to compare the relative value of a range of options. The following schematic summarises the costs and benefits considered in the analysis. It is noted that not all the benefits associated with the project have been quantified. Some additional benefits have been considered in the qualitative socio-economic assessment in Section 9. Given that the CBA compares all costs and benefits relative to the base case (i.e. only the incremental costs and benefits are quantified), Option 1 (base case) as a stand-alone option has been excluded from the analysis. Government benefits were calculated in compliance with the Standard Cost Model methodology. Nongovernment benefits were calculated using information provided from stakeholder consultation and published data sources including the Australian Bureau of Statistics (ABS). Figure 4: Cost Benefit Structure Cost Benefit Analysis Costs Government Costs Set Up Costs Non Victorian Government Costs* Benefits Victorian Government Benefits Reduced rew ork/ investigation Survey Accurate Data Development Costs Reduced operating/ maintenance costs Processing Costs Avoided project costs Non Victorian Government Benefits Avoided duplication Avoided project costs (land & infrastructure Maintenance and Operating Costs Project Management Costs * It is expected that there will be some costs to Vicmap Property users to realign their data and/or systems with the new VSLB. However, from the stakeholder consultation processes, these costs were not considered to be significant, with the benefits of an improved map base outweighing any costs. As such, these costs were not included in the quantitative assessment. 55 | P a g e 8.2.1. General Assumptions This section presents the economic and financial analysis of the options. A detailed Economics and Financial Model was constructed using a Net-Present Value method of discounted cash flow for the financial assessment and a Cost Benefit Analysis for the Economic elements. The financial analysis compares the nominal capital costs for each option and the present cost of the operating expenditure profile over 20 years. The dollar figures presented in this section are not the total funding requirement. As required under the Investment Evaluation Guidelines, DTF, this section presents a discounted cash flow assessment. All funding requirements are presented in Section 12. The key financial assumptions in the assessment of options include the following: All capital costs have been escalated using an average Consumer Price Index of 2.5% per annum until development completion For all options (excluding the ‘Do Nothing’), the period until 1 January 2016 includes design, planning and tendering. Development is to commence in 2015 calendar year Operational and maintenance costs have been escalated at 2.5% per annum. All costs (capital and recurrent) have been discounted over 20 years The assessment of cash-flows for options are only concerned with the incremental difference over the ‘Do Nothing’ (or business as usual) approach All discounted cash-flow analysis has been undertaken using a 6.5% real discount rate with a sensitivity analysis of 4% and 9% included in the modelling Where real costs are stated, these dollars are real as of 1 July 2011 (note that nominal/escalated costs are always presented in the business case unless otherwise stated) The rebuild of Vicmap Property to create the VSLB will not significantly alter the revenue streams associated with the products. Any increase in revenue will be used to offset operating and maintenance costs The risk provisions and contingencies are included in the total funding requirement More detailed assumptions and limitations relevant to the CBA are provided in Appendix F. 8.2.2. Quantified costs The costs assessed in the CBA over the ten year implementation period and ten years of operation broadly include the following: Set up costs Data development 56 | P a g e Data Processing Maintenance and operating costs Project management. Costs for each option were calculated using a ‘bottom-up’ resource planning approach with standard industry rates and, where applicable, government time rates. The assumptions for up-front development costs (Real $2011-12 dollars) are summarised below. Table 18 Cost summary (real 2011-12 dollars) Option 5 Option 2 Option 3 Option 4 (preferred) Upfront Development Costs $2.6 m $180.3 m $43.0 m $142.4 m Project Delivery Costs $928.5 m $11.1 m $11.5 m $11.6 m Capital Costs $0.6 m $0.6 m $0.6 m $4.1 m TOTAL $931.7 m $192.0 m $55.0 m $158.0 m All capital cost estimates are provided in Appendix G. The full cashflow for Option 5 (preferred option) is outlined in Appendix I. 8.2.3. Quantified benefits The benefits of the preferred Option 5 quantified in the analysis include: Reduced costs arising from additional investigations/rework associated with an inaccurate map base and a reduced need to respond to user complaints and/or requests for clarification in regards to Vicmap Property and its spatial accuracy (public sector benefit) Avoided Land Registration Services and Crown Land Registry administration costs due to reduced need to reconcile Vicmap Property with submitted plans and conversions (public sector benefit) Avoided project costs (land and infrastructure) for the private and public sector. This includes time and cost savings associated with reduced rework and reduced development costs associated with access to a more accurate map base (VSLB) (private and public sector benefit) Avoided duplication costs associated with development, maintenance and operation of duplicate or extensive supplementary spatial databases by a range of other authorities including water and energy providers (private sector benefit). 57 | P a g e It is assumed that all benefits begin to accrue in the 8th year of implementation – from 20% of full benefit, increasing to 30% (in year 9) and 50% (in year 10). This assumption is relatively conservative and recognises that with a long implementation period, some of the benefits will be realised prior to full implementation. It is assumed that 100% of the benefits will be realised once the new map base has been fully implemented. Further detail on each of the benefits quantified and the assumptions that these calculations are based on are provided below. 8.2.3.1. Avoided cost of investigations, reworks, complaints and requests for clarification As a result of spatial inaccuracies in Vicmap Property, there is an increasing need for government agencies (principally the Office of Surveyor-General Victoria (OSGV)) to respond to user queries/complaints or to address general inconsistencies with the map base. Whilst not monitored on a case-by-case basis, these inefficiencies result in significant costs for government (predominantly administrative staff time). The following three case studies/examples provided by the OSGV were used to estimate the annual cost which would be avoided if the spatial accuracy of the map base was improved: River Red Gum Forest Investigation Case study (Victorian Environmental Assessment Council (between 2005 and 2008). During the Government’s investigation into the extent, condition, values, management, resources and uses of riverine red gum forests and associated fauna, wetlands, floodplain ecosystems and vegetation communities, there were several inconsistencies noted between Vicmap Property positioning and that provided by field surveyors (See the following text box). OSGV was asked to address these inconsistencies by improving the accuracy of the relevant area. It is estimated that responding to this issue cost a total of $84,560 which was made up of 70 days effort of VPS staff, 62 days of drafting and surveying effort and an estimated 15 days to update the VOTS. This is considered to be a conservative cost estimate as it doesn’t include other hidden administrative costs, or travel and equipment costs. For the purposes of the analysis, it is assumed that OSGV handles an average of two cases of this scale per year. 58 | P a g e River Red Gum Forest Investigation Case study: Public Land Management – Mapping State Forests Due to the inherent spatial inaccuracies within Vicmap Property additional work is routinely undertaken to improve the accuracy of the map base for the purposes of defining both State Forest and National Park boundaries. In particular, work completed for the River Red Gum National Park (RRG) mapping program in support of the RRG forest investigation in 2008 identified differences between the Vicmap position of the Murray River and that derived by survey and rectified/controlled aerial imagery, as shown in the adjacent image. This program of works highlighted the need to accurately compile from field surveys the boundaries of the Murray River to provide a consistent base for the whole project and provide a Land Status report of each parcel in the area of Study. In all cases, it was required to undertake a re-plot based on survey field records and parish plans with the support of aerial photography to correct the boundaries of the parcels. This work came at considerable cost to Government in the form of both digitising the position of the Murray River and recompiling and adjusting the parcel boundaries. Estimates are in the order of several months work in total with an unknown amount of time in administration; surveying; equipment maintenance; and, travel and accommodation associated with these works. This example demonstrates that Vicmap Property cannot be used as a definitive linework source for Crown land as the data is often inaccurate and boundaries between different tenure types are not shown. Topographic boundaries are also poorly represented. Often there is little correlation between the framework datasets and Vicmap Property. This is especially true along the River Murray and the sea coast – the delineations of which are fundamental requirements of a dataset representing Victoria’s land estate. Errors in positioning at Mann’s Beach. A query by a Council Infrastructure Planner was directed to OSGV due to a disparity between Vicmap Property and existing aerial photography. These sorts of queries are very common (estimated at approximately 300 cases per year) and cost over $480 per case. Increased spatial accuracy and therefore confidence in the map base would eliminate these queries saving approximately $144,500 per annum. Clarification of information at Kinglake. The Surveyor General was asked to confirm advice provided in 1986 in regard to the relationship of a freehold parcel and the abutting Crown land reserve for the 59 | P a g e purpose of dispute resolution at VCAT by a local action group. The resolution of this matter resulted in significant re-work costs for the Surveyor General (site visits, data compilation client discussions etc), estimated at $6,760. This cost estimate is considered to be extremely conservative and does not include the additional costs to the private sector associated with delayed development. It is estimated that OSGV responds to approximately 15 similar sized cases per year, which could be fully avoided with a more accurate map base. Based on the above case studies, improving the spatial accuracy of the State’s map base would avoid a minimum of $415,000 per annum for OSGV. It is likely that the real cost is much higher for a number of reasons. Firstly, these estimates do not include any administrative, equipment or travel costs which are not monitored on a case-by-case basis. Secondly, the number of complaints, inconsistencies and disputes is expected to increase over time as the map base grows and user needs and expectations increase. Thirdly, while the value of avoided costs for other departments such as DPCD have not been captured in the current analysis, a reduction in these costs will also be a benefit for those departments. Due to limited data availability, the hidden costs described in these three examples and the expected growth in the difficulties resulting from a spatially inaccurate map base, have not been included in the analysis. 8.2.3.2. Avoided operating costs The operating costs for Land Registration Services (dealing with freehold land) and Crown Land Registry (dealing with Crown land) will be reduced when the VSLB replaces Vicmap Property. Based on consultation with these affected groups, the cost savings were conservatively estimated at $105,765 per annum (See Table below). Table 19 Avoided operation and maintenance costs Affected Group Work Function Avoided costs Heading Total avoided costs (per annum) Land Registration Lodgement and 30% reduction in staff related costs $68,651 Services registration of subdivision 75% reduction in printing /expenses plans and survey based applications Crown Land Reduced realignment costs Registry of crown land with map 30% reduction one FTE $37,114 base Total $105,765 These annual cost savings are conservative as they assume no growth in operation and maintenance cost under the do nothing option (i.e. base case). As the base case costs increase, the benefits of taking action (i.e. the avoided costs) also increase. 60 | P a g e 8.2.3.3. Avoided duplication costs The calculation of avoided duplication costs was based on cost estimates associated with known datasets currently managed by Barwon Water, Coliban Water, Central Highlands Water, Melbourne City Council and Goulburn Murray Water. The savings include reduced staffing costs and saved software licensing costs (See table below for assumptions). Table 20 Avoided duplication costs Avoided labour cost (per Avoided software licensing Total avoided costs per annum) costs (per annum) annum) Barwon Water $ 259,140 $89,032 $ 348,172 Coliban Water $ 155,484 $69,516 $ 225,000 Central Highlands Water $ 310,968 $40,860 $ 351,828 Melbourne City Council $ 259,140 $111,290 $ 370,430 Goulburn Murray Water $ 336,882 $137,204 $ 474,086 TOTAL $ 1,321,614 $447,902 $ 1,769,516 Agency 8.2.3.4. Avoided project costs A significant benefit associated with improving the accuracy of the map base is the avoided costs of infrastructure and land development. This benefit impacts both the public and private sector and is estimated to be approximately $16.1 million per annum. The percentage of infrastructure and land development costs associated with design and surveying requirements will be reduced by 0.24% (from 3.3% of the total cost to 2.9% of the total cost). These proportions are based on project case studies representing a range of project sizes from $900,000 to $750 million15 and have been tested for consistency with accepted industry standards. Private and public sector annual investment in infrastructure and land development was based on the average expenditure between 1999 and 2009 in the Australian National Accounts16. This was approximately $10.9 billion for the private sector and $5.2 billion for the public sector. 15 Based on publicly available information and information provided through the consultation process, the projects used as case studies were Wimmera Mallee Pipeline, North-South Pipeline, Clyde North Land Development and Minor Road works in Mornington Peninsula. 16 Private sector expenditure based on ‘Non-dwelling construction – Private New building’ and ‘Private Non-dwelling construction - New engineering construction’. Public Sector investment is based on ‘Public Gross fixed capital formation’, assuming that 65% of this expenditure is on new fixed infrastructure. 61 | P a g e 8.2.4. Quantitative cost benefit analysis results This section presents the quantified economic, financial and cost benefit impacts for each option (except Do Nothing). Whilst each of the options other than Option 1(Do nothing) are able to fulfil the bulk of the critical service needs of this project, Option 5 (Mixed approach) will deliver high spatial accuracy in urban and peri-urban areas and remove gross errors in the rural areas. Option 3 (Rebuild) provides high spatial accuracy in urban areas but not rurally. While Option 2 (Resurvey) is best able to deliver high spatial accuracy across the State, it comes at an untenable cost. Option 4 (Aerial imagery) will improve the overall spatial accuracy of the spatial database but it will not deliver high spatial accuracy. An additional difficulty with Option 4 is that it will present an occupation-based spatial database as distinct from a representation of the titles to the land parcels. Table 21 outlines the Benefit Cost Ratios and Net Present Value of each option extracted from the Economic and Financial Model. Both Option 3 and Option 5 have demonstrated benefit cost ratios greater than one with Option 5 demonstrating the higher ratio of 2.37 (see Table 21 and Figure 5 below) and delivering, in the most part, a VSLB with high spatial accuracy. In economic terms, the net present value of Option 5 is $154.7m compared to $94.7m for Option 3. Neither Options 2 nor 4 demonstrated a positive net present value and are therefore not considered as viable options. Option 5 is the preferred option. It has the highest BCR and the lowest cost from the options that are considered to be viable (i.e. with a BCR greater than one). Table 21: Benefit Cost Ratio and Net Present Value Assessment Cost BCR NPV Option Option Option Description (real $ 2011/12) Option 2 Resurvey of the state 931.7 m 0.36 ($424.9 m) 3 Option 3 Rebuild from existing survey data 192.0 m 1.65 $94.7 m 2 Option 4 Adjustment from aerial imagery 55.0 m 0.85 ($6.1 m) NA* Option 5 Mixed approach 158.0 m 2.37 $154.7 m 1 *Does not deliver high spatial accuracy therefore excluded from the assessment 62 | P a g e Ranking Figure 5: Cost Benefit Ratios summary for options delivering high spatial accuracy Figure 6: Net Present Values summary for options delivering high spatial accuracy 8.2.5. Sensitivity Analysis A sensitivity analysis has been applied to a number of assumptions in the economic and financial model to test the robustness of the model and option ranking to changing assumptions. Discount Rate Sensitivity Due to the extended timeframes for the project, in particular the 10 year development framework and to the fact that 100% of the annual benefits do not begin to accrue until development of the VSLB is completed, discount rates have been tested. The standard discount rate of 6.5% (real) has been tested with a positive and negative 2.5% adjustment. Table 22 outlines the impact on each of the options. Under the tested discount rates Option 5 still remains preferred with a consistently higher BCR (between 1.95 and 2.92) and NPV (between $94.7m and $245.2m). Under the lower discount rate (4%) the BCR and NPV for Option 4 improves (1.06 and $2.8 m respectively). However this benefit is still significantly lower than that for Options 5 and Option 3. 63 | P a g e Table 22: Discount Rate Sensitivity Discount rate 4.0% Option Description BCR NPV BCR NPV BCR NPV 1 Do Nothing - - - - - - 2 Resurvey of the state 0.45 ($414.4 m) 0.36 ($424.9 m) 0.29 ($417.8 m) 2.11 $177.7 m 1.65 $94.7 m 1.31 $40.8 m 1.06 $2.8 m 0.85 ($6.1 m) 0.68 ($11.3 m) 2.92 $245.2 m 2.37 $154.7 m 1.95 $94.7 m 3 4 5 Rebuild from existing survey data Adjustment from aerial imagery Mixed approach 6.5% 9.0% Benefit Sensitivity- Avoided Project Costs A significant element of the benefit calculation relates to the avoided project cost element. As highlighted in Section 8.2.3, this assessment relies on the conservative assumptions that 65% of public sector capital formation is new fixed infrastructure and that the average project cost saving from improved spatial accuracy is 0.24 % of the project expenditure. Further, the average capital formation cost for both the public and private sectors over the period 1999 to 2009 has been utilised instead of a forecast growth figure to provide a more conservative estimate of the benefit stemming from this element. Given the significance of this element, the 65% public sector capital formation rate is being tested at ± 15 percentage points, 50% and 80%. The 0.24% average cost saving is also being tested at 0.12% and 0.36%. Table 23 demonstrates that only Option 5 remains economically viable (with a BCR greater than one and a positive NPV) across each of the scenarios tested. 64 | P a g e Table 23: Sensitivity test results: avoided project costs Average cost Sensitivity Test: Public Sector Capital Formation saving 50% 65% 80% BCR NPV BCR NPV BCR NPV - - - - - - Option 2 0.18 ($547.2 m) 0.19 ($538.7 m) 0.20 ($530.2 m) Option 3 0.81 ($27.6 m) 0.87 ($19.1 m) 0.93 ($10.6 m) Option 4 0.54 ($18.3 m) 0.56 ($17.5 m) 0.58 ($16.6 m) Option 5 1.16 $18.1 m 1.25 $27.6 m 1.33 $37.1 m - - - - - - Option 2 0.33 ($441.9 m) 0.36 ($424.9 m) 0.39 ($408.0 m) Option 3 1.54 $77.7 m 1.65 $94.7 m 1.77 $111.6 m Option 4 0.80 ($7.8 m) 0.85 ($6.1 m) 0.89 ($4.4 m) Option 5 2.21 $135.7 m 2.37 $154.7 m 2.54 $173.6 m - - - - - - Option 2 0.49 ($336.6 m) 0.53 ($311.1 m) 0.57 ($285.7 m) Option 3 2.27 $183.0 m 2.44 $208.4 m 2.62 $233.9 m Option 4 1.07 $2.7 m 1.13 $5.3 m 1.20 $7.8 m Option 5 3.25 $253.3 m 3.50 $281.8 m 3.76 $310.2 m Option 1 Option 1 Option 1 0.12% 0.24% 0.36% Benefit Accrual Sensitivity The model assumes that benefits begin to accrue in year 8, ramping up over three years. As such, the model assumes that 20% of the annual benefits are realised in year 8, 30% in year 9, and 50% in year 10 (the final year of implementation). The full benefits associated with the project will be realised only once full implementation of the VSLB for the whole of Victoria is complete. Even if benefits do not begin to accrue until year 10 (upon which time 100% of annual benefits accrue, and there is no ramp up period for benefits), the project will achieve the results as detailed in Table 24. Even under this scenario, Option 5 is still preferred with the highest BCR and NPV of the options considered. 65 | P a g e Table 24: Sensitivity Test results: benefit accruing from year 10 onwards Option Option Description BCR Option 1 Do Nothing - Option 2 Resurvey of the Entire State 0.32 ($452.5 m) Option 3 Rebuild from existing survey data 1.46 $67.0 m Option 4 Adjustment from aerial imagery 0.75 ($10.1 m) Option 5 Mixed approach 2.12 $125.8 m 8.3. NPV Preferred VSLB option Option 5 (Mixed approach) is the preferred option. It has a positive BCR of 2.37 and a net present value of $154.7M and is best able to meet the projects critical success factors and deliver a value for money solution to Victoria. Both the qualitative assessment against the critical success factors and the quantitative CBA results indicate that Option 5 (Mixed approach) is the preferred option. It meets the greatest number of the projects critical success factors delivering high spatial accuracy over the majority of the State’s property parcels and will deliver the best economic and financial outcome of the options assessed. Under all sensitivity tests, it consistently achieves the highest BCR and NPV. Option 5 will utilise the approach of Option 3 to rebuild the map base from existing survey data in urban and peri-urban areas combined with the adjustment approach of Option 4 in rural areas using aerial photography to provide the control framework supplemented with existing survey data where available. Overall, this approach will deliver the highest possible accuracy in the urban and peri-urban environment (0.03-0.1 metres) and remove the gross errors in the rural elements of the VSLB, but will not achieve high spatial accuracy in some rural areas. This approach balances the needs of users who require high spatial accuracy and the cost effectiveness of delivering improved spatial accuracy across a large geographic area. It combines methods that will deliver high spatial accuracy for areas of the VSLB that will experience higher intensity of use (e.g. urban and periurban areas) and lower spatial accuracy but substantial improvement on the current spatial accuracy for areas that will likely experience lower intensity of use of the VSLB (rural areas). This approach also provides the opportunity for ongoing enhancement and modernisation of the map base. 66 | P a g e 9. Socio-Economic Analysis This section discusses the social, environmental and other wider socio-economic impacts that arise from undertaking this project. Although the analysis is only provided for the preferred option (Option 5- Mixed approach) it is noted that with the exception of Option 1 (Do nothing), the majority of impacts are incurred from undertaking any of the options presented in this business case. Much of the content of this section was established through the Stakeholder Consultation process. 9.1. Social Impact Quality Decision Making The current Vicmap Property is used extensively to support decision making in a range of organisations including utility providers, land developers, major asset owners and both state and local government. Reliance on a spatial database that is not of high spatial accuracy limits the ability of the users to make effective and timely decisions where spatial accuracy is a critical factor. Access to a spatially accurate VSLB which is high spatial accuracy in urban and per-urban areas will support users in making effective decisions with correct information. This will ensure that decisions that will affect the community and other stakeholders are assessed in the context of best available data and reduce the need for reassessments. 9.2. Environmental impact Reduced Paper Successful implementation of the VSLB will help realise the full benefits associated with ePlan and reduce the need for printing of documents associated with land registration transactions. Reduced need for site survey Removing the need for preliminary site surveys and having property layers correctly aligned with both aerial photography and environmental overlays will reduce the need to undertake field survey. Field survey, particularly in areas of high environmental significance, may require traversing of sensitive environmental areas such as grasslands, waterways and fragile landscape. The use of an upgraded map base for preliminary works and planning will reduce the need for multiple field surveys in these areas reducing environmental impacts and greenhouse gas emissions. 67 | P a g e 9.3. Qualitative Economic Benefits Economic Growth Robert Solow’s neoclassical theories of growth (e.g. Solow 1956) suggest that technology is fundamental to economic growth in that the introduction or improvement of technology will improve an economy’s long term growth rate (hence increasing economic activity). A 2008 study for ANZLIC18 indicated that the introduction of spatial information to an economy results in increased economic indicators (e.g. GDP and employment) as indicated in Figure 7. The VSLB is an improved technology item that will increase the productivity of capital and labour within the economy whereby access to the VSLB will create an increase in economic growth. Figure 7: Economic Growth with and without spatial information Source: ACIL Tasman (2008) pp19 Figure 7 demonstrates how the introduction of spatial information increases the growth gradient and hence it is reasonable to assume an improvement in the underpinning fundamental spatial database (the VSLB) will lead to a similar, albeit possibly smaller, increase in economic growth. Industry Productivity Access to, and use of, the highly spatially accurate VSLB is expected to assist a range of sectors, most notably land administration and construction. The following benefits could be readily realised from the implementation of the VSLB17: Land is prepared and made ready for construction more quickly (including expedited initial site or route selection and cadastral surveying and land titling etc.) 17 ACIL Tasman (2008) pp 62 68 | P a g e More efficient coordination of contractor and sub-contractor activity than in the past (within single construction projects as well as enabling improved oversight of a portfolio of projects, i.e., across a number of construction sites) Specific cost savings accruing to architects, designers, metal fabricators, engineering firms and subcontractors, both during initial construction and the maintenance of built assets. Critical infrastructure protection Access to, and use of, the VSLB is expected to assist in the management of critical infrastructure and particularly underground assets related to gas, communications, water and electricity. Many assets are currently located as distances from graphical parcel boundaries and not in their true location with respect to absolute spatial reference systems. Where the assets are incorrectly attributed or aligned to a parcel boundary in a spatial database without high spatial accuracy, there is a risk that these assets could be disrupted by works in the immediate area. Access to the VSLB and alignment of asset locations to the VSLB is expected to reduce the risk of service interruption and expensive repairs caused by damage to the asset. An example was provided in the text box in Section 4.2.1 (Costs associated with underground infrastructure). Reduced economic burden from shortage of licensed surveyors As stated in Section 4.2.2, there are currently 413 practising licensed surveyors in Victoria18, of whom some 30% will reach retirement age in the next 10 years. The industry currently has great difficulty in attracting a sufficient number of graduates to replace the retiring population. As such, in order to ensure the future surveying needs of the state are met, surveyors will need to be able to operate more efficiently. Based on property subdivision statistics, Western Australia has achieved a productivity improvement in the output of licensed surveyors of 120%19 between 2001 and 2009 since the introduction of a spatially accurate cadastral database. An upgraded map base (VSLB) for Victoria will reduce the need to engage surveyors in early stages of development and provide surveyors with additional information when completing surveying works. 18 Surveyors Registration Board of Victoria- Register of Licensed Surveyors (as at September 2011) 19 ACIL Tasman (2008), pp55 69 | P a g e On this basis, it can be seen that the availability of the VSLB will be fundamental to reducing the impacts of the looming shortage of licensed surveyors. Further, given the significant amount of surveying effort required to complete the VSLB, it is critical that the surveying inputs are completed before the impact of the current shortage of surveyors in the market is exacerbated. Realise the full benefits of recent program investments Over the past 10 years, DSE has made significant investments in a range of programs and systems to improve the efficiency and effectiveness of land administration in Victoria. The projects implemented include the SPEAR and Electronic Conveyancing initiatives which utilise the VSLB as a fundamental input through the lodgement and acceptance of digital data. The developing ePlan project has the capacity to provide significant resource savings, noting that additional development in this space will drive further improvements and efficiencies. The lack of high spatial accuracy in the map base currently hinders the ability for these projects to achieve their full benefits. Innovation The VSLB will reduce a significant barrier (lack of high spatial accuracy) to a range of technologies and innovations in the market. Just as the electronic purchase of title information extended the value chain of title information beyond land administration and into financing, the introduction of survey accuracy to the spatial database will likely extend the value chain of the VSLB into innovative areas beyond what can be realised at the moment. The proposed VSLB will also complement a range of recent Government investments and initiatives aimed at improving the delivery and management of spatial information. The SPEAR system is one such Government initiative which supports improved planning efficiencies in the registration of plans of subdivision at Land Victoria. This is achieved through an online management, referral and tracking system that provides for subdivision application to and approval by council, followed by online lodgement with Land Victoria for registration. The second stage of the lodgement, recording, storage and dissemination of digital data is in the final steps of development prior to implementation in the ePlan project. Integration of the map base and other systems such as SPEAR and ePlan will only be a viable option when the accuracy of Vicmap Property is improved. Better integration of the map base with these Government initiatives will facilitate innovation across the sector as users benefit from better and faster access to more robust information. This productivity improvement will translate to more innovative use of spatial information within the sector. 70 | P a g e Reduced Risk to Government As identified in Section 4.2.3, the current inaccuracy of the map base is a risk to Government’s credibility and in the worst case, poses a legal risk. Updating to the map base will remove the risk associated with a perpetually moving base and therefore diminish the risk associated with misaligned property boundaries and environmental and planning overlays. 71 | P a g e 10. Risk Analysis and Management This section includes the identification of risks for project delivery of the preferred option (Option 5Mixed approach) and an overview of the proposed mitigation and management of identified risks. The following pages summarise the project risks, causes, consequences and likely controls to document the current risk levels associated with the project. Mitigation recommendations have been made for all items other than those with an initial risk level of ‘low’. 10.1. Risk Ratings The project risks were assessed using consequence and likelihood measures, classified into the categories of financial, health and safety, environment, reputation and project delivery risk. It is noted that the bulk of the risks for this project are associated with Financial and Delivery risk. The consequence and likelihood measures used in the evaluation are provided in Appendix H. The Risk Assessment Summary shown in Table 25 contains the project risks categorised as having a ‘high’ or ‘very high’ risk level; the proposed mitigation measure identified and their current risk ranking without mitigation; and, the risk level after mitigation. A complete risk register is provided in Appendix H. Table 25: Risk Assessment Summary Risk Risk level (before mitigation) Proposed mitigation Risk level after mitigation Methods employed do not achieve High Undertake pilot program of Medium expected levels of high spatial implemented approach to test cost accuracy, leaving a retained liability effectiveness before committing to (complaints) if the level of efficiency full state wide program savings do not eventuate Savings not realised due to resources High Include hold points in agreement not being diverted to other activities with Treasury to enable in light of reduced complaints/ renegotiation if estimates are actions required by government outside expected range System requirements - existing High EOI/Tender to address how system requires more extensive contracted parties would develop upgrades to support an upgraded map base to fit with system and map base interfaces with other data/programs 72 | P a g e Medium Medium Risk Risk level (before mitigation) Proposed mitigation Risk level after mitigation Insufficient resources/skills to Very High Undertake annual resourcing plan Very High complete project delivery (due to and consult with major industry shrinking skill base) bodies and users of technical services to ensure that resourcing constraints can be managed with the market Implementation of program will be immediate. Funding risk – project is not funded Very High Work with DSE and DTF to devise and issues associated with Vicmap suitable performance targets that Property are not resolved would help garner acceptance of High the proposal. Implement a regime of communication with key stakeholders There is a risk for existing Vicmap Property users associated with transitioning to a new VSLB. Based on stakeholder consultation undertaken to date, this is not considered to be a very significant risk. To minimise the risk and associated increase in related costs, affected user groups will be consulted during the planning phase and throughout the VSLB’s implementation program. Further, in order to maintain uninterrupted service during the transition to the VSLB, DSE will lock and duplicate sections of the current Vicmap Property, leaving a copy available for public use whilst the other is adjusted and/or rebuilt. This will minimise the impact on Vicmap Property users and ensure that planning and land administration works are not disrupted over the development period. 73 | P a g e 10.1.1. Initial Risk Profile The initial risk profile indicated the presence of medium-high risk with some very high risk elements. The high risk items relate to elements such as the availability of skilled human resources; funding; achievement of the full benefits of the project; system requirements; and, the existing data being available. All these risks currently have marginal existing controls associated with them. Table 26 outlines the count of how many risk items fall within each risk category. Figure 8 below plots the risk profile of the project with existing controls. Table 26: Current Risk with existing controls 5 4 3 2 1 Total A 0 0 0 1 0 1 Risk Level B 0 0 0 0 0 0 Very High C 0 3 3 3 1 10 High D 0 0 1 2 1 4 Medium E 0 0 0 0 0 0 Low 0 3 4 6 2 15 Likelihood Consequence Total Figure 8: Current Risk with existing controls 10.1.2. Risk Profile with target mitigation In order to reduce the risk profile of the project, a range of mitigations has been recommended. These mitigations will manage the risk items in a way that will reduce their likelihood or consequence (or in some cases both). Mitigations should be implemented in keeping with the risk management process (see Section 10.2). The risk profile after mitigation shifts from medium-high to medium-low (see Table 27 and Figure 9). However, even with mitigation there is still a high risk associated with the availability of skilled human resources and the project not being funded. 74 | P a g e Table 27: Current Risk with mitigation Figure 9: Current Risk with mitigation 4 3 2 1 Total A 0 0 0 0 0 0 Risk Level B 0 1 0 0 0 1 Very High C 0 2 3 0 0 5 High D 0 5 3 0 1 9 Medium E 0 0 0 0 0 0 Low 0 8 6 0 1 15 Likelihood Consequence 5 Total 10.2. Risk Management Process The risk management process will be managed by the project manager (see Section 14.4 for Governance). It will be the responsibility of the project manager to update the Risk Management Register to: Record risks as they arise or are averted Record risks that have materialised Provide a risk mitigation and management strategy for the future Identify any potential new risk mitigation measures that maybe required for risks identified throughout the life of the project. The project manager will be responsible for ensuring that: Each risk is managed until it is no longer a threat The risk management/mitigation process adopted for each risk is effective Resources are made available to deal with risks at the appropriate time The risk register is regularly updated to record all risks as they arise and provide a mitigation and management strategy for project delivery. 75 | P a g e 11. Procurement Strategy The following section outlines the options for procurement for the project and defines the issues involved in the procurement process. The procurement assessment was constrained by the terms of reference for the business case which assumed that DSE through ISB and Land Victoria is the responsible body for the authoritative VSLB and that DSE will continue to collect and retain data in regards to land administration, including subdivision and land title information. The procurement strategy for this project is very important due to the issues associated with the scale of the data works required and the anticipated length of the project. The option to deliver this project through a Public-Private Partnership (PPP) approach has not been assessed and is therefore not excluded as a potential delivery option for further consideration. Should the Government wish to consider other private sector delivery models, a more detailed procurement analysis would be required. The development of the VSLB has several important constraints which influence and shape the recommended procurement strategy. These include the: Availability of existing and appropriate data inputs Need to utilise data that is currently in the hands of the Government that in some cases would not be readily available to private sector bodies Need to manage risk and scale of the project outputs in a cost and time constrained program Availability of specialised resources required to deliver the project. The various procurement options considered are discussed in the following sections. 11.1. Procurement options A range of procurement options exist to deliver the recommended solution, Option 5 (Mixed approach). The following procurement options have been assessed: 1) Traditional (In-house) - DSE (as project sponsor) secures all resources, raises sufficient funds and undertakes the rebuild works ‘in house’ to have the VSLB designed and constructed 76 | P a g e 2) Traditional (Contract outsource) – DSE (as project sponsor) secures all resources, raises sufficient funds and directly contracts to have the VSLB designed and constructed utilising contracted parties 3) Concession – A broad term where a consortium designs, builds, finances and maintains to specified output standards, the VSLB under an ‘exclusive’ arrangement with DSE. The VSLB would be effectively owned by the consortium over this duration but ownership reverts back to the State at the end of the term. The State would either pay for access and re-sell to users or allow the private consortia to sell access to the map base at pre-agreed rates to users. This model would utilise the Partnerships Victoria framework 4) Alliance – DSE specifies key high level project outcomes and a private sector partner (or partners) is selected to deliver the project allowing a collective sharing of all risks, waiver of legal recourse, unanimous decision making among all parties, an integrated project team, open book cost recovery payment system and little or no risk transfer to the private sector. 11.2. Procurement Selection Each procurement method has advantages and disadvantages as show below. Table 28: Procurement Options summary Criteria / Procurement Option Traditional (In house) Traditional (Outsource) Concession Alliance Ability to package Able to divide Able to divide works A concession An alliance approach up in parts (works works in in packages. Able to approach would would require all works able to be packages. Able to manage sub-projects. require all works to to be treated as one for segregated and manage sub- be treated as one for contracting purposes, managed in suitably projects. contracting purposes, but may be able to be sized work packages but may be able to be managed in smaller to meet resourcing managed in smaller packages by alliance needs) packages by winning partners. consortia Reasonable Scale Low transaction and Transaction costs Low transaction costs Very high transaction Moderate transaction costs. May be costs. Need to allow for Costs (e.g. cost of difficult to secure ‘open book’ tendering etc) attractive financing management for a non fixed asset solution 77 | P a g e Criteria / Procurement Option Traditional (In house) Traditional (Outsource) Concession Alliance Resource availability Currently Currently limited Currently insufficient Currently insufficient insufficient resources in a single resources in a single resources in a single resources in firm to complete this firm to complete this firm to complete this government to work in the forecast work in the forecast work in the forecast complete this timelines- may timelines would timelines- would work- would require development require a consortium require development of require of a consortium or to complete works a multi-party alliance significant sub-contracting of upsizing of packages critical skills sets Ability to Shift Risk Low level of risk Effective contracting Very high level of risk Low level of risk to Acceptable Levels transfer means of outsourced tasks transfer with transfer due to the that DSE will will support effective relatively low level of ‘best for project’ focus, retain the bulk of and efficient risk risk retained by the no right to action the risks transfer. This state against alliance parties. associated with supports retention of Low level of risk this option acceptable levels of transfer means that DSE risk within Land will retain the bulk of Victoria/DSE the risks associated with this option Innovation Limited Due to contracting High level of Some opportunity to Opportunities innovation requirements, limited opportunity exists to innovate exists opportunity opportunity exists innovate, and still exists meet the project critical success factors Key Advantages DSE is DSE is experienced in High level of risk experienced in this procurement transfer this procurement model model Moderate level of Moderate level risk transfer of control Moderate level of High level of control control Key Disadvantages 78 | P a g e Low level of risk Limited opportunity transfer for innovation once High level of in- contract is let Low level of control Low level of risk transfer Criteria / Procurement Option Traditional (In house) Traditional (Outsource) Concession Alliance house resources required Low opportunity for innovation 11.3. Recommended Procurement Solution The issues that are considered in forming an opinion with respect to the procurement methodology are as follows: The interdependencies of the development elements (e.g. data, geographies etc) which are critical to the affordability/risk issues There opportunity for innovation in design, timing, staging, financing and delivery for parts of the project (including some data) to be purchased independently from the private sector As the data custodian, DSE’s ability to remain engaged in the development process, particularly in regards to new data to be included (e.g. new subdivision data) which will occur in parallel to the VSLB development. A procurement approach that incorporates traditional design (that is program and output design requirements by DSE) followed by a tender for developers of various works packages would be the most appropriate. This approach is understandable and tested and allows for adequate risk transfer. However, in this project, this approach may have a limiting effect on innovation. To address these issues, it is recommended that in the output design and tender development stages of this project, DSE allows for tenders to submit (optional) innovative bids. Assessment of these ‘innovative’ options would need to be undertaken in keeping with the projects risk assessment framework, with suitable contractual transfer of risk associated with such options and a demonstrated value for money. Given the need to ensure effective delivery, resource constraints and the need to complete this project in timely manner, procurement should proceed using the Traditional (Outsource) arrangement. This procurement approach has some distinct advantages, namely: This approach is similar to that used for the VOTS project and as such, DSE is experienced in developing and administering a project within this framework 79 | P a g e It allows for suitable risk transfer and measurement of costs and timeliness against deliverables It provides DSE with adequate control mechanisms (i.e. through contract structure and administration) It supports ‘packaging’ of works into manageable parcels. This will help address the potential resource limitations in the market (e.g. no one firm has sufficiently large labour resource to complete whole project, therefore allows contracting/ sub-contracting arrangements to allocate work on a value for money basis). 80 | P a g e 12. Funding Assessment This section outlines the funding required in undertaking the preferred option in the timelines outlined in Section 14. The preferred option has a capital cost impact for the State of $158.0 m (real 2011/12 dollars) $185.6m (nominal dollars) over a 10 year period commencing in 2012/13. The operational cost impact can be managed within the existing Vicmap operating budget. The required funds are above the output funding of DSE’s spatial services and land administration services (ISB and Land Victoria). An overview of the timing of tasks and costs and personnel requirements is located in Section 14. The most significant funding impact from developing the VSLB stems from the data requirements, and in particular, the elements that are highly labour intensive, such as: Field Survey: Control Densification and Connections of Survey to Control - $23.1 m Infill Survey: To re-establish selected problem areas - $48.7 m Parcel data entry: Rebuild of urban areas - $20.5 m Table 29 and Figure 10 outline the funding requirements for the development of the VSLB. Table 29: Funding requirements ($M nominal) 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 TOTAL 0.4 1.8 14.1 28.9 33.0 35.7 36.4 17.0 - - 167.4 Project Delivery Costs - 1.4 1.5 1.6 1.6 1.7 1.7 1.8 1.9 0.6 13.7 Capital Costs - 0.6 1.4 1.9 0.7 - - - - - 4.5 TOTAL ($m) 0.4 3.9 17.0 32.3 35.2 37.4 38.1 18.8 1.9 0.6 185.6 Upfront Development Costs *Note- the funding requirements includes a 15% contingency allowance A full cash flow is provided in Appendix I. Figure 10 highlights the annual funding requirement cash flows, noting peak funding need of some $38.1m in the financial year ending June 30 2019. 81 | P a g e Figure 10: Funding requirement / cash flows 82 | P a g e 13. Public Interest Issues There are a number of public interest issues to be considered in accepting the preferred option (Option 5- Mixed Model). The public interest issues assessment is provided in Table 30 below: Table 30: Public Interest Issues Public Interest Issues Assessment Effectiveness The key objective of this project is to deliver a VSLB Is the project effective in meeting that meets the spatial accuracy requirements of Government objectives? users. A rebuild of Vicmap Property (into a VSLB) will support the Government in delivering a range of land administration practices including the ePlan and Electronic Conveyancing initiatives. Accountability and Transparency Development of the VSLB will remove user and Do the arrangements ensure that: community confusion over its applicable uses. In The community can be well informed about obligations of government and any private sector partners Affected Individuals and Communities particular, the VSLB will clearly outline the level of accuracy in any given area and hence its appropriateness for use. A thorough consultation process has been Have those affected been able to contribute undertaken with current Vicmap Property users effectively at the planning stages, and are and the wider spatial industry. Input from this their rights protected through fair appeals process was used to help shape the options put processes and other conflict resolution forward for assessment. mechanisms? An ongoing process of consultation will occur through the development program, with interested parties updated and able to provide feedback through regular industry sessions. Equity Access to the VSLB will be via similar means as the Are there adequate arrangements to ensure that current Vicmap Property. Equity access disadvantaged groups can effectively use the arrangements will be put in place for education infrastructure or access the related service? and disadvantaged groups to access the VSLB. This enhances access for disadvantaged groups. 83 | P a g e Public Interest Issues Assessment Public Access Access to the VSLB will be via similar means as Are there safeguards that ensure ongoing public Vicmap Property. access to essential infrastructure? Consumer Rights From the consultation carried out to prepare this Does the project provide sufficient safeguards for business case, it is not anticipated that there are service recipients, particularly those for whom any significant groups of vulnerable persons who government has a high level of duty of care, will be affected by development of the VSLB. and/or the most vulnerable? Security The project will be delivered in line with Does the project provide assurance that government expectations in regards to community community health and safety will be secured? health and safety. It is not expected that any of the development or operational elements of the project will negatively impact community health and safety. Privacy The VSLB will be developed and operated in Does the project provide adequate protection of compliance with current privacy requirements. In users’ rights to privacy? particular no private information will be captured and/or utilised in an identifying way through development or operation of the project. 84 | P a g e 14. Implementation and timing The following section outlines the implementation and scheduling requirements of Option 5 (Mixed approach). It also specifies the necessary governance arrangements for the project. 14.1. Project Delivery Strategy The delivery process for the preferred option will include: 1) Detailed program design Upon funding approval, DSE will develop a detailed program design that outlines the elements of work to be undertaken, timelines and detailed strategy for implementation. This detail will form the basis of the tender brief and documentation. 2) Procurement process including tender selection and negotiation A Request for Tender or a two-stage Expression of Interest and Request for Tender process will be released to the market (for design and implementation of an upgraded spatial land database). This process will also allow tenderers to put forward innovative solutions to develop and maintain a VSLB in accordance with Option 5. DSE will assess the tenders and select a preferred bidder. Final contract details will be negotiated with this preferred proponent in line with government procurement practice. 3) Data development and construction The selected tenderer will be required to undertake a pilot program to ensure the methodology, data use and quality assurance processes utilised meet the delivery expectations of DSE. Upon successful completion of the pilot, the preferred tenderer will commence delivery of the project utilising existing data, collected survey data and aerial imagery. Each of the development methods will be applied as appropriate to the area being completed. Data will be used to construct the VSLB with all required attribute information incorporated. Achieved survey accuracy will be tested through a thorough quality assurance process. 85 | P a g e 4) Staged transition from Vicmap Property to VSLB As geographic areas of upgrade are completed (e.g. Local Government Administration Areas), they will undergo a rigorous quality assurance process. Once quality of the data (and area) has been assured it will be uploaded to the Victorian Spatial Data Library (VSDL) and made available to users for access. Given areas will be completed in a staged fashion; the VSLB will be progressively rolled out over the program schedule. 5) Project close out A post-project review will be completed including an assessment of the VSLB product with respect to project KPI’s, contract performance and project management. The project close out assessment will be undertaken jointly by the selected tenderer and DSE. Details of the implementation plan and staging options are outlined in the following sections. 14.2. Project Staging It is recommended that the delivery be staged in workable packages. This will allow for effective risk mitigation and a milestone payment approach and allow for effective use of the limited pool of technical resources in the market without crowding out private sector works. A staged approach may result in some elements of the VSLB being completed later. For example, staging may result in peri-urban environments being completed first, with rural areas being completed later in the program. A staging schedule will be discussed as part of the tender and completed by the selected bidder in consultation with DSE. Whilst indicative timeframes have been included for ‘whole of project’ completion, it is possible to extend or compress timelines, particularly those associated with Stage 3 works, subject to sufficient resources being available. If the selected bidder seeks to implement an alternative staging approach it will also need to provide a detailed resource plan. The timelines, resource plans and funding cash flows presented in this business case are based on the implementation timetable outlined in Section 14.3. 86 | P a g e It is important to note that implementing this approach allows the VSLB to be further upgraded into the future if there is sufficient demand and/ or further technology improvements. This is particularly important for the rural areas in which high spatial accuracy will not be achieved through the upgrade process. 14.3. Implementation Timetable Assuming the project commences in 2013, the indicative delivery timetable incorporates: A delivery programme Confirmation of the procurement strategy and its implementation An EOI and RFT, evaluation, tender selection and negotiation process Required approvals Multiple departmental (and stakeholder) inputs Data capture and processing Construction of the VSLB Quality assurance Project close out (post project assessment). The key milestones for the delivery programme for DSE are outlined in Table 31. An indicative programme schedule is included in Appendix J along with a detailed resource plan in Appendix K. 87 | P a g e Table 31: Milestone dates Tasks Start Date Finish Date Project Planning/Initialisation [DSE] Jan-13 Dec-13 Contract Administration Jul-14 Dec- 20 Tender/Procurement Process Jan-14 Jun-14 Stakeholder engagement/communication Jul-13 Dec-21 Project Contractor PM establishment and reporting processes Jul-14 Dec-21 Staff Training Jul-14 Feb-15 Design and Development of Processes/Tools Jul-14 Mar-15 Software Licences Sep-14 Jan-15 Software Licence Maintenance Jul-14 Dec-21 Computer Hardware Sep-14 Dec-14 VSLB Data Model Changes and Data Migration Dec-14 Feb-15 Urban Area Rebuild from Source Data Pilot [35,000 parcels] Sep-14 Feb -15 Rural Area Adjustment using Imagery Pilot [4000 parcels] Dec-14 Jan-15 Pilot Project Review Feb-15 Jun-15 Contract approval for full project works Jun-15 Mar-15 Planning and Data Collation Jun-16 Dec-20 Parcel Data Entry Jun-16 Dec-20 Field Survey - Control Densification Jun-16 Dec-20 Field Survey - Connection of Surveys to Control Jun-16 Dec-20 Adjustment, QA and Data Upload Jun-16 Dec-20 Field based Accuracy Assessment Jun-16 Dec-20 Infill Survey to re-establish selected problem areas Oct - 17 Mar-21 Supplement Imagery/DEM capture Programs Mar-16 Oct-17 Imagery Capture Mar-16 Oct-17 Project Management & Setup [DSE] Project Management Information Technology Pilot Project [30,000 parcels] Rebuild in Urban Areas [2.3M parcels] Rural Areas Adjustment to Imagery [900,000 parcels] 88 | P a g e Tasks Start Date Finish Date DEM Mar-16 Oct-17 Planning and Data Collation Mar-18 Dec-19 Control Selection and Adjustment Mar-18 Dec-19 QA and Upload Data Mar-18 Dec-19 Area Selection Imagery Mar-18 Jun-21 Data collation and Key Entry of Source Plan Data Mar-18 Jun-21 Control Selection and Adjustment Mar-18 Jun-21 QA and Upload Data Mar-18 Jun-21 Field accuracy assessment check Mar-18 Jun-21 Jun-21 Dec-21 Rebuild with Imagery Controlled Adjustment Selected Areas - Rebuild from source plans & Control with Project Close out Project Close out, contract review and whole of project QA review The following items are critical to meeting the development completion date of the 30 December 2020 and the project close out date of the 31 March 2021: BERC funding provided to commence 1 July 2013 Procurement process completed 30 June 2014 Commencement of start up works by the selected tenderer on 1 July 2014 Commencement of the pilot project on 1 January 2015 Completion of the pilot project by 15 September 2015 Completion of rebuilt, adjustment to imagery and imagery controlled adjustment by 30 December 2020. During the development of the VSLB, DSE will progressively reduce maintenance of the current map base, Vicmap Property, over the development period and re-divert maintenance activities to the VSLB. It is critical that this timeframe is adhered to due to the emerging shortage of skilled professionals to complete this project (including licensed surveyors for field and office survey related tasks and skilled 89 | P a g e spatial professionals who have a strong understanding of the suitability and use of existing survey plans for the rebuild elements). 14.4. Project Governance and Oversight The Project will be governed by a Project Working Group, responsible for the project delivery and overseen by a Project Control Group. The project managing authority will be the Department of Sustainability and Environment, who will be responsible for the provision of a Project Manager. The Project Manager will chair the Project Working Group and will be answerable to the Project Control Group. The Project Control Group will, in turn, be responsible to the Executive Director Land Victoria. This framework will be updated to reflect the needs of the project over time and in order to provide mechanisms of certainty to the project while maintaining the appropriate checks and approvals. The roles, responsibilities and membership of the Project Control Group and Project Working Group are outlined below. 14.4.1. Project Control Group Role: Provide strategic overview and direction to the project in relation to local government or State Government policies and strategies Endorse procurement, acquisition and project delivery strategies Receive reports from the probity auditor on the procurement process Support and facilitate engagement of government decision makers on key issues. Key Responsibilities: Promote the vision for the project and secure consensus from stakeholders on the strategic outcomes Enable sufficient resources to ensure the delivery strategy can be implemented Be accountable for the leadership of the project and ensure the project objectives are being met Keep State Government leaders informed and committed to the project vision. Membership: Senior Manager - Executive Director Land Victoria 90 | P a g e General Manager – Director Land Registration Services Senior Policy Officer- LV Policy Manager and Manager Strategy and Projects ISB Representative/s from the Project Working Group (these members will not have voting rights). Deputy Surveyor General and Manager Data Acquisition and Management ISB). 14.4.2. Project Working Group Role: Develop and implement delivery strategies (including the procurement, site acquisition and development strategy) Provide corporate overview and advice in relation to the planning, development and implementation Set work priorities for the project Oversee and facilitate significant plans (i.e. design plans and specifications, expressions of interests and requests for proposals) Promote and communicate the scope and objectives to key internal and external stakeholders. Key Responsibilities: Promote the vision for the project and secure consensus from key stakeholders on the strategic outcomes Consult with key internal and external stakeholders to provide timely information and obtain support for the project Influence, procure and direct human and financial resources for the many activities and tasks for the development of the project Be accountable for the procurement phase of the Victorian Spatial Land Base Appoint Project Working Sub-Groups and advisors as required to assist with the various work elements of the project Report to the Project Control Group, Council and State Government as appropriate. 91 | P a g e Membership: Senior Project Manager – Deputy Surveyor-General Senior Policy Officer – Land Victoria Policy Officer Senior Member – Manager Data Acquisition and Management ISB and Assistant Director Land Records and Information Services Project Manager – Manager SPEAR and ePlan. 14.5. Project Management DSE will be responsible for project management and will appoint an appropriate Project Manager. The nominated Project Manager will be responsible for the delivery and monitoring of the Project Management Plan. This plan will encompass the procurement, delivery and risk management strategies. It will also include the governance, stakeholder, quality and benefit management plans. A probity auditor will be engaged during the procurement phases to ensure that probity issues are identified and actioned in line with Victorian Government procurement guidelines. The Project Manager will provide monthly reports to the Project Control Group. The Project Manager will be responsible for ensuring all reporting and contractual liabilities of government are actioned. 92 | P a g e 15. Conclusion Funding of $185.6 million (nominal) commencing in the 2012/13 financial year is required to replace Vicmap Property with the VSLB. This investment will deliver a net benefit to the State of Victoria of $154.7 million to 2031 and deliver further ongoing benefits beyond this time. In addition this investment will reduce the opportunity cost associated with continuing to operate Vicmap Property, which does not meet the needs of users who require high spatial accuracy. Development of a highly spatially accurate VSLB will address the service needs of those users who require high spatial accuracy and deliver benefits in regards to reduced duplication, more efficient and effective land and infrastructure planning and development and reduced costs to Government from decreased complaints and more efficient land administration processing. Option 5 will deliver a VSLB that will achieve the high spatial accuracy in the urban and peri-urban environment (0.03-0.1 metres), will move the gross errors in the rural elements of the VSLB but will not achieve high spatial accuracy in some rural areas. The cost of developing and delivering Option 5 is $185.6m (nominal) with expenditure to be spread across a 10 year development timeline. This timeline has been adopted to effectively distribute the expenditure requirements and in keeping with the limited pool of skilled resources available to complete the project. This timeline approach reduces the delivery risk and supports the project being delivered via a Traditional (Outsource) procurement approach. The financial impact of Option 5 is shown in Table 32. Table 32: Forecast funding requirements (nominal $m) 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 TOTAL 0.4 1.8 14.1 28.9 33.0 35.7 36.4 17.0 - - 167.4 Project Delivery Costs - 1.4 1.5 1.6 1.6 1.7 1.7 1.8 1.9 0.6 13.7 Capital Costs - 0.6 1.4 1.9 0.7 - - - - - 4.5 TOTAL ($m) 0.4 3.9 17.0 32.3 35.2 37.4 38.1 18.8 1.9 0.6 185.6 Upfront Development Costs *Note- the funding requirement includes a 15% contingency allowance 93 | P a g e Appendix A Background to Vicmap Property A.1 What is a cadastral map base? The modern interpretation of the cadastre derives from the French model introduced by Napoleon in 1808 for the collection of land tax. The cadastre is generally regarded as a comprehensive register of metes and bounds of real property and of legalities of ownership, tenure, rights, restrictions and responsibilities. The graphical representation of these elements within a cadastral map base includes the following: A series of large scale maps showing property boundaries, building and structures on the land and major natural features. A register or number of registers containing information on ownership, valuation and any other matters dealt with by the cadastre for every land parcel. The map base is based on land parcels, not buildings, people or any other criteria The map base must be complete in so far as every parcel of land in a jurisdiction must be displayed on the maps and included in the respective registers Each parcel must have a unique common identifier to be used by all authorities dealing with parcelbased information including the folio (certificate of title) number and survey plan number etc The map base must be continuously updated and include an unambiguous definition of the parcel both in map form and on the ground. The cadastral map has five main purposes: To provide a cartographic record of land parcelation/subdivision To facilitate the recording and administration of land transfer and other dealings To record land ownership To assist in the valuation and taxation of land To assist property infrastructure planning and development. 94 | P a g e A.2 History Vicmap Property was derived from what were originally two logically and physically separated databases. Melbourne Water created a digital data set covering the Melbourne Metropolitan area. Survey and Mapping Victoria created a similar data set covering rural Victoria. The Metropolitan Base was created as a reference framework for Melbourne Water's assets and reflected Melbourne Water's business needs by holding subdivisions at both the proposed and approved stages. It focused on rateable properties and placed less emphasis on the cadastral changes that did not relate to ‘property’. Primarily, the data was captured by manually digitising Melbourne Water's comprehensive series of 1:480 and 1:500 scale base maps. Digital capture commenced in 1984 and initial coverage was obtained by 1990. Survey and Mapping’s rural data set reflected a more basic view of land administration, comprising transferable parcels of land. This project entailed a complete re-compilation of the source data, being original Parish plans, registered plans of subdivision and VicRoads survey plans. The process required the production of pencil-plot compilations at a chosen scale of 1:2,500 over towns and built- up areas (using survey-acquired control) and 1:25,000 for the balance of the state (using existing standard Vicmap 1:25,000 topographic mapping as control). In a small number of areas, where existing base mapping could be used or where compilation at 1:25,000 was impractical (e.g. along the Murray River and parts of South Gippsland), mapping at 1:10,000 was produced. Where the mapping of other authorities’ (Local Government or Water Boards) at a similar or better scale and accuracy was available, it was adopted or upgraded and used in preference to producing new compilations. Apart from a small number of maps compiled directly to digits, these pencil plots were also hand-digitised. Digital capture of the balance of Victoria, beyond the Metropolitan area, started in 1983 with State-wide coverage being obtained in December 1994. In addition to the accuracy limitations noted above, it is also important to acknowledge that the compilation methodology used to build Vicmap Property is a potential source of errors. The hardcopy maps which were digitised are likely to include errors; incorrect interpretation of data including survey and boundary definition; and, possible scale issues. 95 | P a g e In 1994, the Office of Geographic Data Coordination, under the Department of Finance, and Melbourne Water Corporation agreed to consolidate the two data sets supporting the development of a state wide digital cadastral data base (Vicmap Property) managed by Geographic Data Victoria (now Information Services Branch). Although merging the metropolitan and rural data set has provided a seamless, state wide graphical representation of the parcel framework, the spatial accuracy of the data varies depending on the accuracy of the source mapping used in digitising the parcel line work. Since the initial formation of Vicmap Property, significant effort has been invested into correcting large spatial integrity errors, ensuring completeness and improving consistency of the data such that it is interoperable with other existing DSE and local government data sets. A.3 Additional detail on Vicmap Property and its layers Vicmap Property is commonly used as a reference base to support ancillary data needs for a range of public and private sector users. For example local, State and Federal governments, conveyancers, the real estate sector, financial institutions, valuation authorities, emergency services, facility and infrastructure managers, land owners, land developers and planners all have an interest in the land market and rely on Vicmap Property as a fundamental data set and as a legal and fiscal resource to plan, manage and analyse their interests. Figure 11 highlights the spatial layers available, how they rely on Vicmap Property and how they are utilised by various sectors of the economy. Users are able to access Vicmap Property through a number of channels. Some users, including Emergency Services Telecommunications Authority, State Government Departments and Local Government agencies, gain access directly from DSE via an online order and distribution service known as the Spatial Data Mart. All other users access the data through a network of authorised Vicmap Data Service Providers (DSPs), or in small packets per locality, directly through DSE’s Land Channel online (www.land.vic.gov.au). Irrespective of distribution channel, all users of the data are required to hold an annual access licence from DSE. A total of 3980 seats were licensed to regular users in 2009. The data provided is in GIS format which can be viewed with freely available map viewers, or analysed and manipulated with more sophisticated GIS and CAD packages. 96 | P a g e Figure 11: Vicmap Layers and Uses 97 | P a g e A.4 Management of Vicmap Property Vicmap Property is managed by DSE’s Information Services Branch with key input provided by Land Victoria, Local Government, and VicRoads. Key participants in the management of Vicmap Property are: Information Services Branch: maintainer of Vicmap Property (and 14 other Vicmap products). Land Victoria: the authoritative source for all registered parcel information (spatial and aspatial) Land Registration Services: responsible for officially recording changes in land ownership and registering mortgages, easements and land subdivisions. Subdivision data is provided to ISB to be included/ updated in Vicmap Property as appropriate Office of Surveyor-General Victoria: Primary government authority on surveying and the cadastre (land property boundaries, geographic names and tenure) Local Government: the authoritative source of all property information including street address VicRoads: the primary government authority for the creation of the state’s major road infrastructure. A.5 Management and Operation Regular updating and maintenance of Vicmap Property is conducted to ensure high integrity of spatial data and is performed by private industry via contractual agreement with DSE. Maintenance and update of Vicmap Property is primarily driven by new land development where the private sector surveyors work in conjunction with land developers to subdivide land and prepare the plans of subdivision for approval and registration. Along with changes to public (Crown) land, these plans of subdivision are primary building blocks of Vicmap Property and a source of increased spatial accuracy in the map base. They also enhance the framework upon which property and address information is referenced. As a framework spatial dataset for the State of Victoria, Vicmap Property relies heavily on authoritative sources of new and amended cadastral and property information. These authoritative suppliers of information are known as custodians and in the cadastral (parcel) area the custodians include Land Victoria Division of DSE and private sector surveyors. Land Victoria is responsible (in part) for officially recording changes in land ownership and registering mortgages, easements, land subdivisions and dealings with Crown land. The Surveyor-General of Victoria is the primary Government authority on surveying and the cadastre (land property boundaries and tenure) and 98 | P a g e works in conjunction with the Surveyors Registration Board of Victoria to oversee the regulation of cadastral surveys and assesses the competency and licensing of surveyors. Property and Address custodians have been identified as Local Government and all 79 municipal councils continuously provide new and changed information for Vicmap Property. Currently there are 3.3 million parcels, 3.1 million properties and 3.1 million address points to maintain. Users of Vicmap Property are actively encouraged to notify DSE of inconsistencies and errors in the data and custodians regularly undertake data improvement projects within their own databases correcting and improving their data in Vicmap Property. This work constitutes approximately 25% of the maintenance effort each year. A greater number of change requests relating to spatial accuracy are now being notified as attribute content and completeness reach very high levels and usage of Vicmap Property increases. 99 | P a g e Appendix B User requirements for spatial accuracy The following table provides a more detailed summary of user spatial accuracy requirements for urban, peri-urban and rural areas. It is noted that where users have indicated that they require the information in the cadastral map base to be “survey accurate” that this has been interpreted requiring the map base to be compiled from survey accurate spatial data to produce a map base that has an absolute accuracy with uncertainties (or tolerances) that align with the figures they have specified, for example within or between 0.05 metres and 0.1 metres. Table 33 : Spatial Accuracy needs of users Users (consulted groups) Identified needs Surveyors Must be ‘true’ to the surveying -Institution of Surveyors requirements (that is accuracy in Victoria line with the surveying -Association of Consulting Surveyors Victoria User accuracy requirement Urban Peri-Urban Rural 0.01-0.1m 0.05-0.1m 0.05-0.1m 0.02-0.1m 0.02-0.1m 0.02-0.1m 0.05-0.1m 0.05-0.1m 0.2-0.5m regulations). Must align with other data sets. -Surveying and Spatial Sciences Institute Land Victoria Needs to support interfacing with Land Registration Services ePlan, current survey examinations and survey information searching needs and other reliant spatial systems. Must align with the surveying regulations. Local Government Must allow for all functions -City of Melbourne including rates, asset -Mornington Peninsula -City of Casey 100 | P a g e management and planning to be accurately integrated. Must align with aerial photography. Support Users (consulted groups) Identified needs -City of Greater Dandenong the use of GNSS asset recording -Central Goldfields and planning activities with little - Colac Otway User accuracy requirement Urban Peri-Urban Rural 0.05-0.1m 0.05-0.1m 0.2-0.5m 0.05-0.1m 0.05-0.1m 0.25-0.5m 0.1-0.2m 0.2-0.5m 0.5- 1m or no data realignment needed. - Wodonga - Strathbogie - Bass Coast -Moira Utilities Must support engineering Yarra Valley Water planning works and recording of Coliban Water as constructed assets Barwon Water Planning Allow planning scheme overlays Department of Planning and to be tied to co-ordinated points Community Development so that any improvement in accuracy allows the overlays to be realigned to match Transport Must allow for maintenance and VicRoads identification of transport VicTrack parcels. Spatial integrity needs to be maintained. Must be accurate to support infrastructure concept design. Note: more details on the needs of specific users have been identified in Section 6- Stakeholder Analysis 101 | P a g e Appendix C Legislative alignment The following section outlines the relevant legislation and its fit to this project. Table 34: Legislative Alignment Legislation Fit Comments Land Act 1958 An Act to consolidate the Law relating to Vicmap Property is currently the Conveyancing and the Law of Property. primary spatial representation of Crown Lands within Victoria. Property Law Act 1958 An Act to consolidate the Law relating to Vicmap Property is often used by Conveyancing and the Law of Property. conveyancers and others involved in the land administration process. Vicmap Property also interfaces with a range of other systems and could be further utilised to support econveyancing. Subdivision Act 1988 The purposes of this Act are to— Vicmap Property currently has (a) set out the procedure for the subdivision subdivisions and consolidations and consolidation of land, including entered. The graphical misalignment buildings and airspace, and for the of submitted survey plans and creation, variation or removal of easements Vicmap Property requires manual or restrictions; and rectification by ISB. (b) regulate the management of and dealings with common property and the constitution and operation of bodies corporate. Transfer of Land Act 1958 An Act to consolidate the Law relating to Supports the Land Act, Property Law the Simplification of the Title to, and the Act and Subdivision Act. Dealing with, Estates and Interests in Land. 102 | P a g e Legislation Fit Comments Surveying Act 2004 The purposes of this Act are to— Preparation of plans lodged under (a) provide for the annual registration of this act and creation/consolidation of licensed surveyors to perform cadastral parcels is directly reflected in Vicmap surveying in Victoria; Property. (b) provide for investigations into the professional conduct of licensed surveyors; (c) establish the Surveyors Registration Board of Victoria; (d) provide for the establishment of the Surveyors Registration Board of Victoria Fund; (e) repeal the Surveyors Act 1978 and make consequential amendments to other Acts; (f) provide for fees for the maintenance of the survey control network. Surveying (Cadastral The objectives of these Regulations are to— Specifies the required competence of Surveys) Regulations 2005 (a) prescribe standards for cadastral cadastral surveyors in boundary re- surveys; establishments and impacts on the (b) regulate and control the making of cadastral surveys by licensed surveyors; (c) prescribe forms and other matters relating to cadastral surveys. 103 | P a g e accuracy of parcel representation in Vicmap. Legislation Fit Comments Survey Co-ordination The objectives of these Regulations are to— Specifies the required accuracy Regulations 2004 (a) provide for standards of measurement standards for certain surveys, data and accuracy of certain surveys; from which is used to inform Vicmap (b) provide for the connection of surveys to Property. existing surveys, standard traverses and permanent marks; (c) prescribe forms, procedures, standards and other matters relating to surveying and the co-ordination of surveys. Planning and Environment The purpose of this Act is to establish a Graphical representations of Parcels Act 1987 framework for planning the use, in Vicmap Property are used to development and protection of land in develop the graphical representation Victoria in the present and long-term of planning overlays in Victoria. interests of all Victorians. Local Government Act The purpose of this Act is to establish the Supports the subdivision of land and 1989 role and powers of Local government in the placement of survey control. Victoria including the functions and decision making powers of Local Government. C.1 Surveying Regulations Survey accuracy in Victoria is defined by the surveying regulations20. (Regulation 7(1) of the Surveying (Cadastral Surveys) Regulations 2005) states that: 7(1)(a) the internal closure of any cadastral survey is such that the length of the misclose vector does not exceed; (i) 15 millimetres + 100 parts per million of the perimeter for boundaries crossing level or undulating land; and 20 Surveying (Cadastral Surveys) Regulations 2005, and Survey Co-ordination Regulations 2004 104 | P a g e (ii) 15 millimetres + 150 parts per million of the perimeter for boundaries crossing steep or mountainous land 7(1)(c) All lengths are measured or determined to an accuracy of 10 millimetres + 60 parts per million. Table 35 indicates the allowable errors in distances from 0 to 1000 metres in terms of the requirements of the Surveying (Cadastral Surveys) Regulations 2005, and the Survey Co-ordination Regulations 2004. Table 35: Surveying Measurement Accuracy- Allowable Error Ranges Linear measurement Allowable error ranges (metres) distance (metres) Reg 7(1)(a)(i) Reg 7(1)(a)(ii) Reg 7(1)(c) 0-20 0.015-0.017 0.015-0.018 0.010- 0.011 20-100 0.017-0.025 0.018-0.030 0.011-0.016 100-200 0.025-0.035 0.030-0.045 0.016-0.022 200-300 0.035-0.045 0.045-0.060 0.022-0.028 500-1000 0.065-0.115 0.090-0.165 0.040-0.070 From a survey measurement perspective, data should be as accurate as possible, subject to a small practical survey contingency allowance and the conditions of the land which is being surveyed. For the updated map base to be truly ‘survey accurate’ it must reflect the accuracy requirements of the relevant surveying regulations for two forms of position measurement - length and misclose vector21 (see text box below). 21 The third component of position is height, or elevation, which is not considered in this discussion. 105 | P a g e Position measurement of length and misclose vector Measurement of length is a single dimension and component of the determination and depiction of the position of a point in a parcel or polygon in a spatial database. Accuracy of measurement of length is generally depicted in metres. A further component of position is a second dimension indicated by direction, usually determined by the measurements of angles or bearings within either a local environment or known geographic reference frame respectively. Accuracy of direction can be described in an angular sense e.g. seconds of arc, or by reference to a ‘misclose vector’ i.e. errors in length (metres) in both a northerly and easterly direction. The third component of position is height, or elevation, which is not considered in this discussion. 106 | P a g e Appendix D Stakeholder Details It is noted that where users have indicated that they require the information in the cadastral map base to be “survey accurate” that this has been interpreted as the necessity for the map base to be constructed of data (measurements) that is survey accurate as determined by the relevant surveying legislation. Sector Organisation Contact email/ Feedback- key points telephone Local Local Michelle mhanslow@moor GPS, ortho-rectified or geo-referenced aerial photography, surveyed subdivision plans etc. It is not Government Government Hanslow abool.vic.gov.au, unusual for these recorded assets to appear to be located in an adjacent parcel of land once 03 5366 7147 imported into the map base due to the inaccuracy of the parcels. A spatially accurate graphical Spatial Reference cadastral map base will correct this issue and enable the map base to be integrated into other Group (subset datasets (e.g. imagery) for better visualising of the on-ground situation. of Municipal Vicmap Property is currently used as a base indicator only for the identification and location of Association of properties. It cannot be relied upon for location of assets; to identify boundaries and/or determine if Victoria) a dwelling has been constructed across a boundary or not; or to determine if a land owner (horticulturist or grazier) is making illegal use of part of the road reserve (i.e. without a permit) or if there is a compliance concern relating to a boundary issue (overhanging trees etc). Staff regularly refer to the map base as 'proof' of the on-ground situation. This is of concern, as accuracy in some rural areas can be out by 20m or more. Currently it is not possible to determine where the map base is inaccurate without undertaking surveys. E.g. is a road formation actually outside the road reserve and hence encroaching on to someone's title, or is there simply a problem of mismatch between the aerial photo & cadastral layer? The reverse problem of apparent encroachment of private assets onto road reserves is also an 107 | P a g e Sector Organisation Contact email/ Feedback- key points telephone issue. Improved accuracy would reduce unnecessary work in getting 'title re-establishment' surveys done. Benefits of survey accurate cadastral map base (with 2cm GPS) -Issue of building permits – can readily confirm boundary location -Construction of roads – can ensure within road reserve -Vegetation rehabilitation – now know the extent of ‘responsible agency’ authority -Weed eradication – know whose land the weeds are on (road reserve, etc) – not relying on poor occupation (fencing) if it exists -Asset location – whose land? Can now transfer old plans accurately without field locating assets (e.g. Telstra 0.3m off boundary in urban) -Data exchange between authorities – all using the same base without local ‘corrections’ or adjustments so can overlay datasets confidently -Accurate definition of extent of properties for rating, addressing, etc purposes This project is seen as a priority by the LGSRG, and a reasonably quick completion will remove the need for other solutions to be put in place as work arounds (such as Councils maintaining their own cadastre, or using that of a utility company or private organization, or having to have 'map accurate' and ''position accurate' files for the same data) Cadastral accuracy - Ideally sub-decimetre at 95% CI. But could go out to sub-metre for a boundary line (not just the corner) 108 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Accessibility – as the spatially accurate cadastral map base would be a fundamental dataset, it will need to be freely available (e.g. as part of data exchange agreement) or it will not be used (everyone needs to be accessing the same datasets). City of Melbourne David Hassett david.hassett@m MCC collect data for own use, feed into Vicmap Property through Logica. Historical issues with the elbourne.vic.gov. cadastral map base meant that about 10 years ago data was removed and repopulation of the MCC au, 03 9658 9794 area begun. Logica has mostly adopted MCC attributes and geometry. MCC updates dramatically changed from initial Melbourne Water base. MCC provide both parcel and property to Logica Property layer of Vicmap Property is that which is mostly used by MCC. The cadastral representation of parcels is less important for use for land administrative purposes but is important for legal uses. MCC often deals with parcels in the 3rd dimension (strata). MCC geometry is extremely complex. Have reconciled all parcels and properties for attributes and geometry but this is not transferred to Vicmap Property. Notification and Editing Service (NES) information- interest in provision. Planning scheme geometry is also critical and complex in MCC. Cadastral map base used in all parts of the business. Accuracy: connect imagery and the cadastre. In process of building a 3D model of the city- if geometry doesn’t meet creates significant problems. MCC has a true orthophoto of the city. Areas that have been updated are accurate to 0.1m or better, as is ortho imagery Interpretation and analytical problems- brings into question accuracy of other data. Must have the 109 | P a g e Sector Organisation Contact email/ Feedback- key points telephone cadastre map base set at the same level of accuracy as the best and most appropriate of MCC’s other data set needs All new areas of the city are survey accurate including Southbank, Docklands, Kensington Banks, Commonwealth Games Village, some of CBD (program of block by block accuracy improvement). MCC has a licensed surveyor on site who is involved in this process. Pressure of work load means that improving accuracy is of lower priority to some other projects including the 3D city project. If underlying data is not fit for purpose everything else is not worth it (house of cards) Increasing use of cadastral map base by non-tech users- need to remove confusion for them, will help improve the efficiency of a range of business areas if can open up cadastre without some of the historical limitation Aerial imagery needs to support and be supported by the cadastre. Conflict undermines both. Sub-division plans are registered in the system upon approval, uploaded to Logica monthly. Changes are updated as modification or can upload the whole set. All crown land, all parcels and all properties are updated this way. MCC runs continuous survey of the city driven by triggers such as a planning application, new works or maintenance program. Line work is in the browser. Current project for geo-coding all entrances for buildings- critical for emergency services. Would also like to align with 1 address file: address matching would lead to huge efficiencies. Parcel Identification Program (PIP) work has been hugely beneficial. Must see cadastral map base as infrastructure. Improved accuracy will open up new technologies including software: ESRI and FME. CAD and GIS have had historical interfacing issues, but the 3D cadastral representation is mostly drawn from the CAD world. Need to seamlessly integrate 3D visual supporting a 3D cadastral map base (3D geometries). Leadership needs to come from government. 3D is already used in the private 110 | P a g e Sector Organisation Contact email/ Feedback- key points telephone building sector but government systems don’t support it. Planning- setbacks should be 3D- improve efficiency, support clear and consistent position from government. Support reduction in planning red tape if can clearly demonstrate requirements. 4D valuable for legal matters including assessments of/for contaminated land, planning approvals, patterns and projections, road issues. MCC currently has 1 FTE on map base, 0.5 FTE on Crown land (interfacing with map base), and 2 on staff cartographers. MCC would like to maintain road status through the cadastral map base, particular lane ways. Currently Vicmap doesn’t incorporate arcades and hence it is not useful for mapping pedestrian traffic movements. Need seamlessness between parcel and property and link into other information including arcades, 3D etc. Helpful if rights (restrictions and responsibilities) could also be recorded- who is the authority’s point of reference e.g. even identifying where the rail tunnel is? Spatial representation would make this more accessible to the public. Mornington Peninsula Shire Phil Hughes philh@mornpen.v Use Vicmap as base of system. Full file replace each month. Everyone uses- available on all best tops, ic.gov.au, 03 5950 uses web browser, also on external website Maps and aerials via web 1323 Development now use web boundaries- reduced enquiries to council- good uptake through advertising. Site advertises non-reliance- limitations with encroachment and accuracy. Sommerville and Hastings are in general 2-3 metres out. More an inconvenience issue Previous water data used to populate- digitally correct. Came from 1: 25,000 maps. Don’t use cadastre for accuracy. All assets are GPS located then fine tuned with aerial photography. Polygons used as a link to customer service and property activities. Reliance on attribute factor. Supplies some maintenance data. Linked to corporate info 111 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Content more important than accuracy. Changes- updated through NES. All corporate systems integrated through GIS including document management system As we educate about the value of GIS there is demand for more. Rely on DSE aerial and AusImage. Would be happy with consistent 25cm accurate to align with aerial photography. Built layers such as planning layer alignment inaccuracy requires buffer analysis on planning applications. Identification of polygon not space Geo-code address for asset information. Drainage network noted as linear on map base. Roads separate but linked- own road centreline data Little bit of 3D undertaken some 3D models of business areas of some towns, based on aerial photography, not such much need for accuracy. 3D used mostly for planning functions. 4D: good but not necessary, more interest in future than the past ‘Proposed parcel’ layer in system building and planning applications linked to GIS to help identify precedents and cumulative impact. Getting accurate definition of the coastal boundary is critical (Morn Pen 194km of coast line)- issue for boat shed management. Construction work is managed on site not on the cadastral map base. Geo-referenced engineering drawings can cause problems. No need to redesign the wheel- just fix problems. Aerial photographysurvey controlled may be appropriate. Needs to be price managed- and be price neutral for local government. City of Wodonga 112 | P a g e Paul Drummond pdrummond@wo Some areas out by more than 25m in urban area. Vicmap data where inaccurate causes issues when donga.vic.gov.au layered with internal information. Can’t use some GPS tools because they don’t align with map base. Sector Organisation Contact email/ Feedback- key points telephone Vicmap is critical but will become irrelevant if not accurate. City of Casey Moira Shire Central John Skerman jskerman@caset. Need for effective capture of council assets and support for getting planning and other layers ‘in sync’ vic.gov.au (survey accurate). Must consider cost of change over to users. James jhargreaves@moi Planning, compliance, time delay caused by lack of survey accuracy. Helps inform council’s strategic Hargreaves ra.vic.gov.au decision making. Vital map base is as accurate as possible Diane Daniell Provided presentation about own upgrade process. Survey accuracy of Vicmap has been an issue Goldfields Shire since early 90’s desperately needs resolving to improve the ability of regional councils to use GIS Council tools in the most effective manner Colac Otway Greg Slater Shire Greg.slater@cola Use for planning assessments, asset management, environmental management, works planning, cotway.vic.gov.au customer request, record management, local laws enforcement, revenue collection and home care services. Require accuracy of 0.3m across shire. Good to align with aerial photography. City of Greater Milind Joshi Dandenong Bass Coast Shire Paul Lennox Council mjoshi@cgd.vic.g Operates own map base as it is more accurate than Vicmap Property. Need to resurvey disputed ov.au areas. p.lennox@bassco Have upgraded some areas of shire using imagery adjustment to remove gross errors (30-40metres), ast.vic.gov.au Significant inefficiencies to incorporate as built data. Initial specification of Vicmap Digital is no longer fit for purpose and needs now to be Survey Accurate. Wellington Bill Haigh Shire Council 113 | P a g e Bill.Haigh@wellin Mapbase inaccurate to a minimum of 6m. Four areas particularly bad. gton.vic.gov.au Towong Shire Sue-Anne Sue- Overall an improved survey accurate map base would make life so much easier. It’s not just metro Council Beattie Anne.Beattie@to areas that need good positioning, we do have quite a number of little projects on the go involving Sector Organisation Contact email/ Feedback- key points telephone wong.vic.gov.au telemetry and a major wireless broadband project where the determination of tower and sensor sites is extremely important. We have had to figure out ways of answering questions from these projects that would have been a lot easier and cheaper if the map base was complete and accurate. In this Shire we might have to travel several hundred kilometres to investigate a situation simply because some simple questions could not be answered due to Vicmap’s positional inaccuracy. An accurate map base would not only contribute to a smaller carbon footprint for all users, but would save a bit of time and money as we wouldn’t have to get in the car and drive to check out situations that we should be able to answer from our desktop. -the ability to position assets either based on GPS or aerial photography and have the resulting representation to the cadastral map base appear correct as a consequence of the cadastre being spatially correct. At this point in time, nothing is positioned relative to the cadastre, as the cadastre can move, or just looks so wrong when you turn the aerials on; -the ability to use the cadastre overlaying the aerial to prepare “mud maps” or plans for a project that don’t require us to first go out and perform a survey to just be able to prepare a decent plan. The savings for a small budget Council like ourselves would be appreciated; Strathbogie Di Brock Shire Council Currently have to ‘dumb down’ data to fit. Takes time and requires manual manipulation of data. ogie.vic.gov.au Holds council back from doing things as effectively as possible. 03 9326 9700 Critical that surveyors are involved throughout the development phase. Data will only be as good as Surveying Association of Industry Consulting acsv@acsv.com.au the surveying data that goes into it. If survey accuracy could be achieved it would help improve the Surveyors Kevin.barge@cha effectiveness of surveyors. People who aren’t informed rely on Vicmap and surveyors often spend a 114 | P a g e Kevin Barge di.brock@strathb Sector Organisation Contact email/ Feedback- key points telephone rterkc.com.au significant amount of time addressing or explaining why the survey results and Vicmap vary. Surveying and Andrew 03 9248 3389 Survey accuracy of Vicmap has always been a talking point issue for the industry, with a strong Spatial Sciences Bashfield vic@spatialscienc position that accuracy should be addressed. Accuracy needs to reflect the requirements of the bulk of es.org users at a minimum and the most advanced users in the best- so as to allow for innovation and Institute growth. SSSI is very supportive of the initiative and would like to be further involved in discussions as the project develops. The Institution Andrew Reay of Surveyors 93269227 Survey is critical to this project. The ISV should be involved in the project development and are critical isv@isvic.org.au stakeholders. There is no point in doing anything other than survey accuracy- meaning millimetre Victoria accuracy in line with the regulations or better. Surveyors want to see this project done as soon as possible- should have been done years ago. Major Barwon Water Ian McLachlan, ian.mclachlan@b Barwon Water has invested significant time and money into upgrading their map base. Urban areas in Service/ Spatial arwonwater.vic.g Geelong are all now at least accurate to 0.2m, some rural areas are still out by significant margins but Utility Information ov.au, 03 5226 this is gradually being improved through aerial imagery rectification process. Don’t use Vicmap as it is Providers Coordinator 2308 less accurate, though provide data to SII to be incorporated in the map base. Could halve labour cost associated with maintenance and operation of their own product. This could then be reinvested into improving systems and working on core business tasks. Have access to CORS networks though site provision arrangement. This could be used to help facilitate upgrade. Has provided cost and saving profile for Barwon Waters spatial/ map base. Coliban Water 115 | P a g e Neville Pearce nevillep@coliban. Coliban Water plot and run its own cadastral map base, which is not as spatially accurate as the state com.au, map base Sector Organisation Contact email/ Feedback- key points telephone 5434 1256 Run own cadastral map base due to the infrequency of updates of the Vicmap (which can be 6 0429 943 905 months behind) meaning that front desk activities cannot run effectively (not suitable for meeting enquiry needs). Current Coliban Cadastral mapbase generally has 25cm-50cm accuracy in urban areas and 1-2metre accuracy in rural areas. Require accuracy of 0.1m in urban areas and 0.5m in rural areas to meet business needs but cannot justify investment to get own cadastral map base to this level. Would see the benefit of being more accurate than this (would love the Barwon Water system) but can’t justify the cost to business. Currently 3 people working in GIS area. One spends the majority of time on map base, other two work in map base part time as required. Being able to shift to an accurate and timely state cadastral map base would allow ¾ of a job in the GIS group to be re-directed to other activities Previously worked at Central Highlands Water- they are in the same position but would be able to redirect 1.5 FTE staff. Current operation of Coliban Cadastral map base does not require data purchasing and no surveying/ re-surveying is being completed. Alignment of aerial photos and graphical cadastral map base is significantly out Current map base is still AGD (1966 Australian geodetic datum), not converted to GDA (1994 Geodetic Datum of Australia). Aerial Photos are AG and need to be converted to GDA94 to enable 116 | P a g e Sector Organisation Contact email/ Feedback- key points telephone them to be used in conjunction with Vicmap. Overlaying is an issue. Coliban have 3 in house GPS units but do not use the data from these as they would require significant work to convert data and would still not align effectively 2 key areas where cadastral map base is a business barrier Implementation of new assets. As constructed records need significant manual processing (basic asset work 2-3 hours, can be a weeks’ time on large project) to process an input into the system. As such there is currently a 3-4 month delay in getting as constructed records into the cadastral map base. Developers: Not able to export cadastre information to developers, meaning that developers go and duplicate the work to do their planning and recording. When the developers give back the data at the end it needs to be manually converted back into the cadastral map base (again- can be a multi- day activity) Currently package software management that includes the GPS and cadastral map base requirements. Moving to the state cadastral map base would allow for this to be reduced (expect to be $5,000- $10,000 pa minimum at contract renewal), but would likely be less at renegotiation, (current contract expires in 3.5 years). Coliban currently developing a long term strategy for all GIS/ spatial use. Expects GIS to become a portal to the whole business and a key operational tool. But this will require the base document to be correct and timely. This will streamline operations and increase efficiency of operations. Central 117 | P a g e David Trevenen dtrevene@chw.n Maintains own map base. Would love not to but Vicmap doesn’t meet current needs. Expects Sector Organisation Contact email/ Feedback- key points telephone Highlands et.au Water significant software savings and ability to use labour for more valuable tasks if didn’t need own map base. Yarra Valley Charles Water Moscato 9872 1685 Rural areas that were digitised from 1:50,000 are a huge issue, particularly where there is now urban development in these areas. Urban areas from 1:25,000 base not so bad. Developers submit survey accurate as constructed sewer and water information which then has to be reconciled with Vicmap through additional marks on the cadastral map base including ‘off fence’ marks for buried assets. Property boundaries and location of property connections don’t align meaning that spatial search is not sufficient to show connections, also need secondary search against the centroid. Offsets are set to fence lines, not property boundaries, but fences can move over time where redevelopment occurs. “Dial before you dig” is hugely affected. Sometimes, “Dial before you dig” data indicates no assets exist inside a particular property boundary, when in fact there is, or vice versa. This can cause accidental damage to assets, or ‘go slow’ to avoid damage when not necessary. Risk is disruption to service. Use Vicmap as base layer, own system sits alongside with own layers. Accuracy would allow the removal of ‘to fence’ references: cleaning up cadastre. Would also allow for additional QA process to be built in. In urban built environment would like .01m to 0.2m accuracy. In rural areas .5m would be great. Accuracy to 0.05m would be great for urban areas- speed up works and aid identification YVW- own property team. Plot new survey info as it comes in as ‘blue lines’ showing the true alignment, equal to 5-10% of the GIS teams’ time (equivalent of 2 weeks per year). Also creates a business risk as not clear no non-specialists (including Dial before you dig) what the blue line means. 118 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Developers and consultants due to cadastral map base risk do extra survey work which is priced into project risk, either through survey time, or if used to cost project, through additional materials to allow for inaccuracy. Map Base access in XML format with most current data would be good. Currently minimum 2-3 week delay. Used to managing inaccuracy and delays through process and procedures. Inaccuracy creates additional work, incomplete data is a QA issue, undermines whole system. To effectively use the cadastral map base you need to understand the history and limitations, but as spatial technology becomes more imbedded and accessible, most users don’t, therefore don’t understand the limitations. Creates business risk in the underlying work arounds that are in place. Survey Accuracy would clean the map base and remove a lot of confusion, misinterpretation and make it ‘safer’ for non-specialists to use the mapbase. State Land Ian Ireson (03) 8636 2226 Two key tasks interact with map base: Subdivisions and management of Crown land Government Registration Director Land Ian.ireson@dse.vi Subdivisions: Services (DSE) Registration c.gov.au Only use as an index Services Can’t check against new plan Can’t take plans in digital form- or requires rework Can’t compare existing parcel size Productivity gains- would like to get to exception testing only 119 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Relative accuracy- ticks some of the boxes- e.g. New parcels fit into old parcels Absolute accuracy coordinates positionality correct Currently takes 1.5 days per plan Crown land registry: Map base is record of crown land, true record of crown land parcels, position and content Used to manage crown land and used to check against adjoining developments Infrastructure projects often cut across both freehold and crown land When selling crown land need to ensure accuracy of what selling Would expect a 2-3 person saving from accuracy Other LASSI (external users)- view of map base, overlaid with survey information Currently index Can’t currently ‘do NZ model’ Can extract and digital update- requires re-input e-Plan currently paper or SPEAR as PDF e-Plan format intelligent software checking About 30% of plans rejected as not completed or flawed Overlaying other projects would be useful such as aerial photography 120 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Adverse possession claims often rely on map base and historic aerial photographs Currently 2 lot non-survey but this could be extended with a survey accurate map base Save initial development costs, and enable GPS to a greater extent Needed for effective asset management Land developers and surveyors are key users Improve and simplify the subdivision process 8,000 plans of subdivision per annum Survey Accurate map base may reduce the average cost of sub-div How plans presented back to the public needs to be considered- currently titles rely on surveyors drawing- SA map base may limit need to redraw Need to show: easements, rights and obligations, graphical type info which relates to property Reproduce plan of sub-division as title search and has all dimensions and easements 2.1m title searches per annum but only 200,000 land transfers per annum Wrong descriptions and missing parcels mostly an issue for Crown Land Accuracy tied to survey requirements and is regulated Allow work by exception not manual process E-conveyancing process tie in 121 | P a g e Surveyor- John Tulloch, General Victoria Surveyor- (03) 8636 2525 Survey accurate map base needs to reflect the regulations- this is critical to it being Survey Accurate. Sector Organisation Contact email/ Feedback- key points telephone (DSE) General State john.tulloch@dse Main use of map base by OSGV is enquiries from user groups (e.g. How does council advise etc. .vic.gov.au where there are conflicts). Often stems from inappropriate use of the map base or not fully appreciating its limitations Government David Boyle, (cont’) Deputy (03) 8636 2541 Surveyor- David.R.Boyle@ds General e.vic.gov. Get about 300 complaints a year about the map base. Generally require research, historic data compilation. A basic complaint will take 3 hours to address. A complex one can take 7-8 months (Lake King). Often there are gaps in the map base, often affecting Crown land parcels. There is a 200 metre wedge of ‘missing’ data between GDA 94 map zones 54 and 55 within Vicmap, commencing at the Murray and petering out near Daylesford approximately 150km to the south. This has taken 12 months of recompilation and associated cartographic work to rectify the problem at the Murray River only. Where project goes through a site also required to digitally enhance around the site for any project Issues are predominantly rural and peri-urban Often works goes to ‘best fit’ not actual rectification. Impacts on service provision Administrative difficulties as not finite answer Need a clear position on what to rectify and why Is a fence a reasonable reflection of the boundary? Overlaying aerial will result in this Map base is used by a lot of people for a lot of things. Accurate map base could cut 25% of surveyor time on a standard 2 lot subdivision 122 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Currently a significant regulatory burden by requiring surveyors to collect co-ordinate information which is rarely used. Need position as the means not only for attaining accurate map base but also retaining Consider maintaining in a collaborative way Currently move to new coordinate instead of field surveys Field surveys generally accurate to 2-5cm., but need to comply with regulations Over collection of data and new coordinate data is often not fed into map base Recompilation : MGA/DGA datum Measurements - marks in ground vs coordinates Testing for reliability High integrity product: close as possible to the truth- therefore must come from survey plan- legally defendable representation Tie map base to geodetic survey network through the capture of field observations as coordinates cannot be readjusted to accord with a consistently changing geodetic datum (caused by the gradual move in the Australian tectonic plate) Survey Coordination Act 1958 specifies acceptable level of accuracy (some regional allowance) Requires a knowledge of levels of uncertainty In QLD survey plans are not millimetre perfect planimetric accuracy SII took over map base in the early 2000’s, currently a parcels index with a focus on improving the 123 | P a g e Sector Organisation Contact email/ Feedback- key points telephone textual information 1995 surveyors began collecting coordinate information- only some is used- cost is borne by surveyors with some pass through to developers Also costs LV to manage data submitted, and cost of data storage by Logica, co-ordinate data may only be used in Greenfield developments Cadastral infrastructure standards. Currently LV has little control but all of the responsibility Delays getting info into map base (some crown land updates up to 2 year delay) Valuer-General Robert Marsh, (03) 8636 2505 Map base is an important tool and is used to verify some of the work done by Valuer-General n Victoria (DSE) Vauer-General robert.marsh@ds regards to position of lots and planning overlays. Same issues as noted by DPCD also affect Valuer e.vic.gov.au General. Survey accuracy could give some significantly more value tools to aid efficient working in DSE, including Valuer General. There is an expectation that such a critical tool and base data set relied on by so many would be ‘right’ in terms of spatial accuracy. Information John Gallagher john.gallagher@d ISB has management/ maintenance responsibility for Vicmap. Feeds data to other areas of Services Branch Manager Data se.vic.gov.au, 03 government as required. Map base is affected by the quality of the data coming in and the legacy (DSE) Acquisition and 8636 2337 from which it was built. A lot of time and attention has been discussed on addressing completeness Management ISB and attribute information. Survey accuracy has been improved where funds have allowed. Some incoming data is an issue and does not ‘fit’ exactly as provided; therefore adjustment is needed either to Vicmap or the incoming data. Currently spend $1m+ pa through contracts maintaining Vicmap including with Logica. Updates provided every 2 weeks. Operations would be easier and complaints would reduce if Vicmap was survey accurate, but it is a huge task. Vicmap fulfils the needs of a lot of 124 | P a g e Sector Organisation Contact email/ Feedback- key points telephone groups, but those who require survey accuracy provide pretty consistent feedback about what needs to be improved. Crown Land Ivan Powell, Phone: (03) 8636 Crown land is grossly affected by the lack of survey accuracy. Some crown parcels aren’t properly Registry (DSE) Manager Land 2218 incorporated in the map base, though this is slowly being rectified. Conversion project underway. Records and Mobile: 0413 486 Lack of survey accuracy and lack of completeness of crown parcels makes Vicmap a poor tool for Information 916 effective crown land management. SII do a good job, but they are working with something that is Services Email: ‘past its used by date’ for an upgrade. Lack of survey accuracy also hinders legal compliance and ivan.powell@dse. prosecution of offences on crown land, as GPS is often used as part of the evidence to show that the vic.gov.au act took place on crown land, when lined up with Vicmap it can undermine the validity of this evidence. Vicmap needs to be fixed. It needs to be complete- reflecting all Crown land parcels and as accurate as possible. May require significant resurveying- remembering no adverse possession on the crown. Department of Lance Counsel lance.counsel@d Map base is used as basis for planning scheme documents published on line. Issues can arise when Planning and pcd.vic.gov.au the map base is updated and overlays not tied to boundaries e.g. Environmental overlays, waterways, Community 03 9637 8602 etc, shift across properties. This can result in properties that were previously not affected becoming Development affected which impacts on development opportunity (and hence value). Currently have 2 staff that (DPCD) update, check when Vicmap is updated to realign where necessary. This could be saved if he map base was fixed. DPCD has faced recent legal action as a result of a property that had become affected by an environmental overlay as a result of the cadastre update/realignment. The cadastral map base update meant that the productive use of the property was reduced, which in turn adversely impacted 125 | P a g e Sector Organisation Contact email/ Feedback- key points telephone the value of the property. Whilst this matter has recently been settled, an inaccurate and frequently shifting Vicmap Property layer exposes the Victorian Government to substantial legal risk. Currently DPCD assesses sixteen planning certificates in metropolitan areas per month, and there is a push to undertake planning certificates in rural areas as well which are more likely to be affected by overlays. Incorrectly declaring a property ‘affected’ or ‘unaffected’ based on the frequently shifting VSL is an area of substantial risk for DPCD and leaves them exposed to legal action. Updating to a state wide survey accurate VSLB would remove the risk associated with a perpetually moving base VicRoads Bernard Toulet bernard.toulet@r SSI section of Vic Roads Director oads.vic.gov.au, Second largest property manager after DSE Property 03 9854 2832 Services Group within VicRoads for cadastre and titles, including Gazetted roads Current cadastral map base treats roads as a vacuum: sometime road width is not even maintained within the cadastre. Some is Crown land which has equal rights to be protected. Also true of Gary Nisbet municipal roads Acting Manager gary.nisbet@road Cadastral map base used for urban property development, title searching, acquisitions, Vicmap Survey & s.vic.gov.au property, 3 titling systems Declarations 03 9854 2086 Vicmap Property doesn’t provide/ isn’t closely linked to the titles which is a fundamental flaw, reduces usability, reduces confidence in the system VicRoads deal mostly with parcels but need functionality around properties. Needs to have a wider search- other records required 126 | P a g e Sector Organisation Contact email/ Feedback- key points telephone Linkages to Crown land (roads) is minimal No parcels that talk about roads as a whole. A road may be multiple parcels, or surrendered to the crown, and becomes one parcel until you want to add to it. Need consistency, 90% of roads are treated as vacuums VMP needs to act as a backbone on which everything else is built, therefore it needs to be complete, consistent and accurate DLI deals with cadastral map base through planning scheme amendments, Planning applications, rezoning etc and is used to support these actions. There is often confusion between the engineering plans and the cadastral map base that requires multiple documents to be submitted for planning purposes. Difference between parcel boundaries in the planning scheme and Vicmap (out of sync) causes confusion and issues. Needs to be part of a true cadastral database with supported data matching and alignment. Most important requirement is that the data set is complete (more important than accurate). Currently there are lots of sliver titles which add unnecessary complexity and are often misrepresented. VicRoads would like a complete and accurate cadastral map base to help support management of own land and assets. Vicmap parcels to draw diagrammatically what we have would be better if it truly represented all parties. VicRoads currently has 40 licenses (continuous), but 200+ people within the organisation would use regularly. Cadastral map base frequently used by engineering groups for preliminary planning and development of projects. Some design occasionally occurs on the basis of the dimensions of the cadastral map base. This is often done by people who 127 | P a g e Sector Organisation Contact email/ Feedback- key points telephone don’t really understand the limitations of the cadastre. VicRoads has developed its own layers, particularly of the “as built” assets. Used as a tool in land management. Survey side will often do on site works for larger projects such as Bypasses etc as cadastral map base cannot be relied upon. Often resurvey a number of parcels due to the linear nature of much of VicRoads works. Vicmap used to approximate but often recreate from survey information and aerial photography to check. Cadastral map base and planning works is often better defined when aligned with own work, then field survey and built assets are fed into Vicmap. Currency of data- internal policy about delays. Education of users about limitations- but this often not understood, or not frequent for non-GIS professional users. Would be happy if could get ‘shovel width’ in urban areas (e.g. 20cm) ½ metre accuracy in regional areas would not be realistic without resurveying the whole state. Fit for purpose: developers will often look at the cadastral map base in the early days of a project. Often concept design is based on Vicmap. Assure Vicmap fits design, but due to accuracy or miscalculation sometimes redesign, acquisition or planning scheme variation are required. Need coordinated titles. This would assist field surveyors, but not related to VMP. The state cadastral map base should be built as part to whole, not whole to part as is currently the way. Vicmap Transport (roads) doesn’t align with Vicmap Property. Reference information to centreline doesn’t frequently exist, or is wrong. Therefore manage assets as a single line rather than a width. And the single line is not centreline. Wouldn’t use road parcels for asset management. Inconsistencies with aerial photography cause issues that need to be resolved on the group. For metro projects largely use DSE 128 | P a g e Sector Organisation Contact email/ Feedback- key points telephone aerial photography. For own projects get own aerial photography, or source from local government. Key Issues: Incompleteness: parcels not represented, no titles link, road vacuum Inconsistency with other programs, layers etc Inaccuracy: most important for engineering groups Also limitation of reconciling via aerial photography as occupation doesn’t equal title boundary Single integrated system is needed Professional cadastral map base users know limitations and can work to them Technical users, can adapt and interpret but don’t know limitations Non-technical users: risk of them producing content that is misinterpreted on wider circulation as it was completed on the basis of incorrect, inaccurate or incomplete base data set (dangerous scenario). Many crown boundaries not adequately defined Also, need to change cost profile of re-establishing as this acts as a disincentive to land holders. Need rules for filling roads vacuum, Estimate of the cost to put road polygons into Vicmap Roads in 2005 was $2m+ 3D issues are especially relevant for roads (bridges and tunnels in particular), e.g. City Link elevated roadway Other 129 | P a g e PSMA/ Ex- Brian Marwick Survey accuracy of Vicmap is becoming more and more of an issue. Is a barrier to innovation. Number Sector Organisation Contact email/ Feedback- key points telephone Logica of ways could go about the upgrade. Critical as underpinning information. Look to other areas who have done upgrade and learn from their mistakes. 130 | P a g e Appendix E Non Financial Assessment This section provides additional detail in the criteria used for the non-financial assessment in Section 8.1. The non-financial assessment was undertaken in keeping with the critical success factors. The criteria, measurement, score and weighting are shown in Table 36 as follows: Table 36: Non-financial criteria Criteria Measurement Weighting and Score Non- Financial Data The spatial data held in the VSLB will correctly Weighting 40% represent all parcels in Victoria in line with the Scoring 0-10 relevant land and surveying legislation. Data will be of high spatial accuracy, current, reliable and complete Data will be easily interrogated and able to be efficiently interfaced with other government data sets. Continuity Data will be able to be maintained in a sustainable Weighting 20% manner Scoring 0-10 Allows for continuous improvement in data quality, reliability and use of innovation Can be maintained with the shrinking skill base Systems Governance The map base will be accessible and managed in an Weighting 20% integrated system. Scoring 0-10 Good governance with a clear understanding by Weighting 10% stakeholders of the responsibilities for the map base. A Scoring 0-10 central point of governance to oversee all elements of the map base. Custodianship A single parcel/property map base will exist for Weighting 10% Victoria managed and maintained by DSE, based on Scoring 0-10 data provided by the relevant custodian. 131 | P a g e Table 37 outlines the category scores used for assessing options ability to meet the project critical success factors. Table 37 Non-financial scoring Score Definition 1 Does not meet the needs of the measurement of the criteria. Will not achieve the requirements of the criteria. 2 May meet some of the measurement criteria in a very limited way. 3 May meet some of the measurement criteria in a limited way. 4 May meet some of the measurement criteria but does not achieve the basic requirement criteria. 5 Just meets an acceptable level of the needs of the measurement of the criteria. May achieve the basic requirements of the criteria. 6 Meets an acceptable level of the needs of the measurement of the criteria. Will achieve the basic requirements of the criteria. 7 Meets an acceptable level of the needs of the measurement of the criteria. Will achieve the requirements of the criteria. 8 Meets a high level of the needs of the measurement of the criteria. Will achieve the requirements of the criteria. 9 Meets a high level of the needs of the measurement of the criteria. Will achieve/ exceed the requirements of the criteria. 10 132 | P a g e Exceeds the measurement needs of the criteria. Will achieve all of the requirements of the criteria. Table 38 outlines the non-financial elements and their score for each option. Table 38: Non financial assessment review Option 1 Option 2 Option 3 Option 4 Option 5 Do Nothing Resurvey of the Rebuild from Adjustment from Mixed approach entire State existing survey aerial imagery data The data in the Resurvey will allow This approach This approach will This approach will map base will not the achievement of could deliver a not achieve high deliver high spatial be highly spatially high spatial VSLB of high spatial accuracy. accuracy in urban accurate accuracy for the spatial accuracy However, it may and peri-urban whole state. subject to all remove gross environments, but However there is required data inaccuracies from will only remove significant risk in being available. the map base. gross inaccuracies this approach due However, it is (not achieve high to the limited highly unlikely that spatial accuracy) in resource pool of sufficient data will rural licensed surveyors be available for environments. in Victoria. rebuild, particularly in Data some rural areas. Score: 1 out of 10 133 | P a g e Score: 9 out of 10 Score: 8 out of 10 Score: 4 out of 10 Score: 7 out of 10 Option 1 Option 2 Option 3 Option 4 Option 5 Do Nothing Resurvey of the Rebuild from Adjustment from Mixed approach entire State existing survey aerial imagery Continuity data Innovation is Data quality will be As per option 2. Data Data maintenance being inhibited by maintained with Data quality quality/accuracy efficiency will be the current input of survey improvement in improvement will high. With high spatial accurate data in a rural areas will be again be ad-hoc spatial accuracy inaccuracies. Data seamless way. minimal/ad-hoc and dependent on achieved in urban maintenance Innovation new surveys and and peri-urban effort is potential is specific programs. areas, there is the hampered by the maximised due to The approach does opportunity for need to high data not allow for continuous manipulate continuous imporvement in accurate data to improvement in spatial data quality fit the map base. spatial data across the map Data quality quality, to achieve base. improvement is eventual high ad-hoc and spatial accuracy localised Score: 1 out of 10 134 | P a g e Score: 9 out of 10 Score: 8 out of 10 Score: 4 out of 10 Score: 7 out of 10 Option 1 Option 2 Option 3 Option 4 Option 5 Do Nothing Resurvey of the Rebuild from Adjustment from Mixed approach entire State existing survey aerial imagery Systems data Whilst Vicmap The VSLB will be The VSLB will be The VSLB will be The VSLB will be Property is largely built in line with built in line with built in line with built in line with accessible and the requirement the requirement the requirement the requirement management in for an integrated for an integrated for an integrated for an integrated an integrated solution. That is, a solution. That is, a solution. That is, a solution. That is, a system, due to solution whereby solution whereby solution whereby solution whereby gross errors in the the VSLB will the VSLB will the VSLB will the VSLB will spatial accuracy effectively interface effectively effectively effectively of Vicmap with other interface with interface with interface with Property some government and other government other government other government collected data user spatial and user spatial and user spatial and user spatial cannot be systems with systems with systems. As this systems with effectively minimal manual minimal manual approach will use minimal manual integrated into manipulation of the manipulation of an ‘occupation’ manipulation of the map base data required. the data required. model, may still the data required. using current require additional systems. manipulation of the data. Score: 5 out of 10 135 | P a g e Score: 9 out of 10 Score: 9 out of 10 Score: 8 out of 10 Score: 9 out of 10 Option 1 Option 2 Option 3 Option 4 Option 5 Do Nothing Resurvey of the Rebuild from Adjustment from Mixed approach entire State existing survey aerial imagery data Whilst there is A single group will A single group will A single group will A single group will currently a strong be responsible for be responsible for be responsible for be responsible for management the delivery and the delivery and the delivery of the the delivery and regime in place maintenance of the maintenance of VSLB. The group maintenance of for Vicmap VSLB. The group the VSLB. The will oversee the the VSLB. The Property there is will oversee the group will oversee project delivery group will oversee some uncertainty project delivery and the project and confirm the project associated with confirm delivery is delivery and delivery is in delivery and the interface in keeping with the confirm delivery is keeping with the confirm delivery is between ISB, required in keeping with design concept of in keeping with Land Victoria, and regulations and the the required the project. This the required other associated design of the regulations and option will be regulations and parties and who is project. This group the design of the unlikely to align the design of the the ultimate will liaise with project. This with a range of project. This responsible party associated group will liaise current group will liaise for Vicmap stakeholders as with associated regulations (such with associated Property. required but will stakeholders as as the cadastral stakeholders as hold responsibility required but will surveying required but will for the VSLB hold responsibility regulations) and hold responsibility product. for the VSLB hence survey work for the VSLB product. under the product. regulations will Governance need to be managed separately. Score: 1 out of 10 136 | P a g e Score: 8 out of 10 Score: 8 out of 10 Score: 6 out of 10 Score: 8 out of 10 Option 1 Option 2 Option 3 Option 4 Option 5 Do Nothing Resurvey of the Rebuild from Adjustment from Mixed approach entire State existing survey aerial imagery Custodianship data Due to some This option will This option will Due to this option This option will users requiring deliver high spatial deliver high spatial not delivering high achieve high high spatial accuracy and as accuracy and as spatial accuracy spatial accuracy accuracy not such the vast such the vast there are expected and as such the currently majority of users majority of users to be at least 3 vast majority of provided by currently operating currently separate map users currently Vicmap Property independent map operating bases operating in operating there are bases will migrate independent map Victoria. A single independent map currently at least to the VSLB. A bases will migrate group within DSE bases will migrate 5 separate map single group within to the VSLB. A will be responsible to the VSLB. A bases operating DSE will be single group within for the delivery single group within in Victoria. responsible for the DSE will be and maintenance DSE will be delivery and responsible for the of the VSLB and responsible for the maintenance of the delivery and will co-ordinate delivery and VSLB and will co- maintenance of with other groups maintenance of ordinate with other the VSLB and will to ensure that it the VSLB and will groups to ensure co-ordinate with continues to be fit co-ordinate with that it continues to other groups to for its designed other groups to be fit for its ensure that it purpose. ensure that it designed purpose. continues to be fit continues to be fit for its designed for its designed purpose. purpose. Score: 1 out of 10 137 | P a g e Score: 8 out of 10 Score: 8 out of 10 Score: 4 out of 10 Score: 8 out of 10 Appendix F Additional assumptions and constraints relevant to the Cost Benefit Analysis The total financial requirement of each option is subjected to a number of critical assumptions. These assumptions are outlined below. Please note that a number of these issues are noted as part of the risk analysis presented in Section 10. This business case is dependent on the following assumptions: DSE through ISB and Land Victoria is the responsible body for the authoritative VSLB DSE through ISB and Land Victoria will continue to collect and retain data in regard to land administration including subdivision and land title information. F.1 Equipment and resources The following equipment and resource assumptions have been utilised in the development of the options and cost estimates for the recommended option, (Option 5 – Mixed approach). Sufficient and appropriately skilled professional and technical staff are available to the project Allowance for office based resourcing of 50 operational staff to undertake data entry and adjustment activities Hardware purchase of 50 desktop workstations and 3 File Servers Software; 50 copies of GIS/adjustment software (@ $8,000/licence). F.2 Parcel Counts and Plan Information Parcel counts in Table 39 are supplied by DSE-ISB. Table 39: Parcel counts by accuracy Current Accuracy (m) No. of Points22 % Points Location Derived No. Parcels (approx.) <0.1 660,123 4% Urban 119,910 0.1 - 0.5 8,393,786 48% Urban 1,524,718 0.5-1.0 16,508 0% Outer urban and towns 2,999 22 The number of points is the number of vertices or changes in direction along parcel boundaries 138 | P a g e Current Accuracy (m) No. of Points22 % Points Location Derived No. Parcels (approx.) 1.0-2.5 3,560,724 20% Outer urban and towns 646,800 2.5-5.0 67,589 0% Outer urban and towns 12,277 5.0-10.0 916,608 5% Rural 166,500 10.0-25.0 4,000,966 23% Rural 726,769 >25 140 0% Rural 25 Total Number of Parcels 3,200,000 Plan/parcel counts in Table 40 are supplied by DSE-LV. Table 40: Parcels by type Parcels in Vicmap # of Parcels Crown Plan of Sub Total Multi-lot 1,250 360,249 361,499 Roads 1,279 2,262 3,541 Crown Parcels 348,052 Subdivision plans Sub Totals 350,581 348,052 2,465,498 2,465,498 2,828,009 3,178,590 Table 41 and Table 42 outline the assumptions associated with the number of plans and parcels by plan type and the type of data capture. Table 41: Submitted plans Ave Plans # of Plans # of Parcels Certified Plans 21,402 22,048 1.0 Cluster Subdivision 721 5,026 7.0 Lodged Plans 128,128 1,179,542 9.2 12,392 12,518 Plan of Subdivision 152,184 838,642 5.5 Registered Plan 19,365 184,514 9.5 Strata Plan 17,447 112,215 6.4 Title Plans 361,657 473,504 1.3 Totals 713,296 2,828,009 4.0 Plan of Consolidation 139 | P a g e Parcels/Plan Table 42: Digitally captured plans and parcels Plans # of Plans # of Parcels Digitally Captured 3,844 151,908 F.3 Production methodology assumptions for Option 5 Urban rebuild from survey data 2.3 million parcels within the urban/rural towns areas that will be processed by this methodology Average of 5 parcels per Plan No existing digital subdivision plans are used Land Registration Services scanned plans and field notes are readily accessible and able to be efficiently retrieved based on Plan numbers/Street name-locality Work Packages of approx. 200 parcels are defined 5hrs field work/Work Package for connection of existing surveys to control network and coordination of cadastral control marks 7.5% of subdivision plans require some additional field survey to resolve conflicts or re-establish boundaries (allow 4 hrs field survey per plan). Rural imagery adjustment component 900,000 parcels within the rural areas that will be processed by this methodology Imagery requirements; 0.30m resolution imagery and Digital Elevation Model (DEM) to better than 2m vertical accuracy. Assume that existing suitable imagery/DEM will cover 80,000 sq. km. of rural area [Whole Rural area is assumed approx. 200,000 sq. km.] Capture of 50,000 sq. km. of new ortho-imagery is captured by this project Capture of 60,000 sq. km. of new LiDAR sourced DEM is captured by this project Assume that DSE’s Coordinated Imagery Project (CIP) will capture another 60,000 sq. km. of ortho-imagery and 60,000 sq. km. of high accuracy DEM Assume that approximately 16 points per parcel Assume 150 parcels per Work Package 140 | P a g e 10% (90,000 lots) will require rebuild from source plans/documentation (average of 3 lots per plan). 141 | P a g e Appendix G Cost Estimates Option 2 Upfront & Development Costs Project Planning/Initialisation [DSE] Tender/Procurement Process Staff Training Design and Development of Processes/Tools VSLB Data Model Changes and Data Migration Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] Sub-total $102,160 $263,323 $199,071 $247,723 $192,891 $1,205,359 $62,681 $2,273,208 Contingency Total Upfront & Development (including contingency) $340,981 $2,614,189 Ongoing Costs Contract Administration Stakeholder engagement/communication Project Delivery Contractor PM Software Licence Maintenance Urban Infill Survey to re-establish [Assume 60% of parcels require re-survey] Rural Infill Survey to re-establish [Assume 80% of parcels require re-survey] $2,783,651 $548,334 $6,384,314 $344,256 $390,162,490 $407,126,076 Sub-total $807,349,121 Contingency Total Ongoing Costs $121,102,368 $928,451,489 Capital Costs Software Licences Computer Hardware Sub-total $529,843 Contingency Total Capital Costs $79,476 $609,320 Total Real Dollars for Option 2 142 | P a g e $529,843 $931,674,997 Option 3 Upfront & Development Costs Project Planning/Initialisation [DSE] Tender/Procurement Process Staff Training Design and Development of Processes/Tools VSLB Data Model Changes and Data Migration Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] Planning and Data Collation Parcel Data Entry Field Survey - Control Densification Field Survey - Connection of Surveys to Control $102,160 $263,323 $199,071 $247,723 $192,891 $1,205,359 $62,681 $5,133,078 $35,866,329 $38,992,590 $48,332,577 Adjustment, QA and Data Upload Field based Accuracy Assessment Sub-total $20,572,125 $5,621,683 $156,791,588 Contingency Total Capital Costs $23,518,738 $180,310,327 Ongoing Costs Contract Administration Stakeholder engagement/communication Project Delivery Contractor PM $2,783,651 $548,334 $5,992,384 Software Licence Maintenance Sub-total $344,256 $9,668,625 Contingency Total Ongoing Costs $1,450,294 $11,118,919 Capital Costs Software Licences Computer Hardware Sub-total $529,843 $529,843 Contingency Total Capital Costs $79,476 $609,320 Total Real Dollars for Option 3 143 | P a g e $192,038,565 Option 4 Upfront & Development Costs Project Planning/Initialisation [DSE] Tender/Procurement Process Staff Training Design and Development of Processes/Tools VSLB Data Model Changes and Data Migration Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] Planning and Data Collation Control Selection and Adjustment QA and Upload Data Sub-total $102,160 $263,323 $199,071 $247,723 $192,891 $1,205,359 $62,681 $1,494,511 $30,964,816 $2,634,664 $37,367,199 Contingency Total Upfront & Development (including contingency) $5,605,080 $42,972,279 Ongoing Costs Contract Administration Stakeholder engagement/communication Project Delivery Contractor PM Software Licence Maintenance Sub-total Contingency Total ongoing costs $2,783,651 $548,334 $6,384,314 $255,669 $9,971,968 $1,495,795 $11,467,764 Capital Costs Software Licences Computer Hardware Imagery Capture DEM Sub-total Contingency Total Capital Costs Total Real Dollars for Option 4 144 | P a g e $529,843 $1,470,305 $1,556,353 $529,843 $79,476 $609,320 $55,049,362 Option 5 Upfront & Development Costs Project Planning/Initialisation [DSE] Tender/Procurement Process Staff Training Design and Development of Processes/Tools VSLB Data Model Changes and Data Migration Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] Planning and Data Collation Parcel Data Entry Field Survey - Control Densification Field Survey - Connection of Surveys to Control Adjustment, QA and Data Upload Field based Accuracy Assessment Infill Survey to re-establish selected problem areas Planning and Data Collation $102,160 $263,323 $199,071 $247,723 $192,891 $1,205,359 $62,681 $2,171,092 $20,561,414 $9,419,962 $13,669,021 $13,529,672 $1,279,863 $48,763,416 $441,415 Control Selection and Adjustment QA and Upload Data Selected Areas - Rebuild from source plans & Control with Imagery Area Selection Data collation and Key Entry of Source Plan Data Control Selection and Adjustment QA and Upload Data Field accuracy assessment check Sub-total Contingency $7,893,832 $671,643 $14,532 $1,275,080 $1,013,090 $74,806 $787,602 $123,839,648 $18,575,947 Total Upfront & Development (including contingency) $142,415,595 Ongoing Costs Contract Administration Stakeholder engagement/communication Project Delivery Contractor PM Software Licence Maintenance Sub-total Contingency Total ongoing costs $2,783,651 $548,334 $6,384,314 $344,256 $10,060,555 $1,509,083 $11,569,638 Capital Costs Software Licences Computer Hardware Imagery Capture DEM Sub-total Contingency Total Capital Costs Total Real Dollars for Option 5 145 | P a g e $514,777 $1,466,144 $1,551,949 $3,532,870 $529,930 $4,062,800 $158,048,033 Appendix H Risk Assessment Table 43: Risk Analysis Matrix (Consequence) Type Code Consequence Rank Financial AUS$ FIN Health and H&S Safety Risk Analysis Matrix Environment Reputation or Community Concern Project Delivery risk 146 | P a g e ENV REP DEL Determine the Consequence (C) Insignificant Minor Moderate Major Severe <$10,000 $10k to $1m $1m to $10m $10m to $100m >$100m Local treatment with short recovery - minor short term health effects. Medical treatment required or short term acute health effects. Lost Time Injury (off work recovery required) or short / medium term health issues. Extensive injuries or chronic health issues. Single fatality or permanent disability. Major onsite release with some damage, no offsite Onsite release, damage. Numerous Offsite release, no containable with minimal and/or widespread but significant environmental damage. Localised small scale impacts on damage. Remediation in impact on energy usage. energy and waste. terms of weeks. Remediation in terms of days. Workforce concern Local community concern Regional concern Permanent change in Small change to schedule Small changes on project project plan resulting in which are rectified during schedule not impacting small reduction in project project period overall benefits benefits. Major offsite release, Major offsite release, long short to medium term term environmental environmental damage. damage. Remediation in Remediation in terms of terms of years. months. Widespread reputation loss to single business unit, widespread community outcry. Widespread reputation loss to more than one business unit, extreme community outcry nationally. Project benefits are impacted and some targets not met Project unable to meet its objectives and benefits will not be realised Table 44: Risk Analysis Matrix (Likelihood) Determine the Likelihood (L) Likelihood Almost certain SemiQuantitative Frequency More than once More than once during the per year. project. Environmental Frequency Rank 5 4 3 2 1 Common occurrence, high volume/ use. A Medium High Very High Very High Very High Probable Once during the project. Once every one to 10 years. Common occurrence, low volume/ use. B Medium Medium High Very High Very High Possible Could happen during the project life. Once every 10 to 100 years. Occasional occurrence, high volume/ use. C Low Medium Medium High Very High Unlikely Unlikely to occur during project life. Once every 100 to 1000 years. Occasional occurrence, low volume/ use. D Low Low Medium Medium High Very unlikely to Less than once occur during every 1,000 the project life. years. Rare occurrence. E Low Low Low Medium Medium Rare Risk Level Project Frequency Required Actions Very High Implement control measures to ensure the risk level is reduced. communicate and consult thoroughly on risks to ensure the positive benefits out-weigh the negative impacts. High High risk is undesirable and represents a band where the failure of any likelihood or consequence controls will place the risk into the “very high” category. Verify, and where possible quantify, the accuracy and certainty for the existing risk level. Implement control measures to ensure the risk level is reduced or is confirmed to be ALARP. Medium Medium risks are only tolerable if examination proves them to be ALARP. Implement management plans to prevent the occurrence and monitor for changes. Reduce to Low Risk if the benefits outweigh the cost of the additional control. The Project Manager is responsible for monitoring these risks. 147 | P a g e Table 45: Project Risk Analysis Results Ref. No: 1 Risk Area Cost (project delivery) 2 Benefits 3 Cost ( savings) 4 Government liability Risk Issue Consequences Cost overrun Complex and untested costing More complex administrative needs Under-estimation of task effort. Methods employed do not achieve expected levels of survey accuracy Retained liability (complaints) if the level of efficiency savings do not eventuate Complex and untested methods of upgrade (on this scale) Project does not meet user Reliance on untested data needs and will not generate (including the availability of expected benefits required data) Cost overrun leading to LV to seek additional funding from Treasury. Existing Controls Project costing completed using a task and resource plan approach. Internal review of costing Cost approach tested against comparative interstate and international projects Approach tested against comparative interstate and international projects Project does meet targets Retained liability (complaints) if the level of efficiency savings do not eventuate Existing legal framework and Loss of faith in system, contracts to ensure survey accuracy reduced tenders, legal action is delivered Social, community and language Promotion and communication barriers may impede engagement and uptake 6 Multiple related projects currently occurring which may cannibalise Conflict with other projects efficiency savings targeted by this program Survey accuracy expectations are not met Communication plan poorly targeted and executed Estimation based on experience with large data maintenance/processing projects. Lack of confidence in the Communication and engagement rebuilt map base leading to low plans will be a key focus in the take up. project design Other projects operating Not all benefits are realised. concurrently with an upgrade of Poor interfacing between the map base projects. Current Risk (with existing controls) Control Effectiveness Type C L Risk Level Review of existing and proposed projects including any potential conflicts. Mitigation Recommendations Target Risk (with recommendations) Person Allocation Responsible Type C L Risk Level Undertake pilot program of each implemented approach to test cost effectiveness before committing to full DSE state wide program. Adequate FIN 4 C Medium Marginal DEL 1 D High Marginal DEL 2 C High Adequate DEL 4 C Medium Legal framework, transparent process, DSE communication with stakeholders Medium Use of local staff and communication plan Steering committee to consist of representative of agencies, organisations and groups involved in the project. DSE Medium Target areas which have had funding projects first. Ensure requirements from other projects are incorporated into the project design and implementation plan. DSE Project specification relying on existing documented methods Savings non realised due to resources not being diverted to other Lack of understanding of user activities in light of reduced drivers and infrastructure costs complaints/actions required by government. 5 148 | P a g e Causes Adequate Adequate REP DEL 2 3 D C Undertake pilot program of each implemented approach to test effectiveness in achieving survey accuracy targets DSE Include hold points in agreement with Treasury to enable renegotiation if DSE estimates are outside expected range Project Manager FIN 4 C Medium Project Manager DEL 3 C Medium Project Manager DEL 3 C Medium Legal team DEL 4 B Medium Communicatio REP n manager 4 D Low 3 D Medium Project Manager DEL Ref. No: Risk Area Risk Issue Causes Consequences Funding may be impacted. Technology advancement Start delays. Data issues. benefits are not realised. Parties not delivering to contract. Insufficient skilled resources left in market to complete the projects. Existing Controls Control Current Risk (with existing controls) Effectiveness Type C L Risk Level Mitigation Recommendations Person Target Risk (with recommendations) Allocation Responsible Type C L Risk Level Timelines Project not completed by 2020 deadline (time overrun) Project planning and contractual arrangements Adequate DEL 4 C Ensure works agreement requires Medium project completion within required timeframe DSE Project Manager DEL 4 D Low 8 Timelines Not all benefits are realised . Delays to progress compared with Poor project management. Poor Lack of resources retained in Nominate an experienced Land program are not identified early program oversight the market to complete the Victoria Project Manager enough to ensure corrective action. project Adequate DEL 3 C Monthly reporting by the project Medium manager. Contractual arrangements setting timetable. DSE Project Manager DEL 4 D Low 9 Project Design System requirements Marginal FIN 2 C Project Manager FIN 4 C Medium 10 Project Delivery Interruptions to existing Vicmap Need to 'lock' sections of the Property operations whilst rebuild is Interruption to user operations Consultants with user groups map base whilst rebuild occurs completed. Marginal DEL 3 D Project Manager DEL 4 D Low Recurrent Costs The design and operation of the new System complexity, under system will result in recurrent costs in estimate of recurrent operating excess of the budget capacity of costs. Land Victoria. Marginal FIN 3 C Project Manager FIN 4 D Low 7 11 149 | P a g e Existing system requires more Cost/Time overrun leading to extensive upgrades to support LV to seek additional funding an upgraded map base from Treasury Higher operating costs Review of existing systems to ensure that they will support an upgraded map base Ensure thorough recurrent cost analysis is undertaken EOI/Tender to address how contracted parties would develop map base to fit DSE with system, and interfaces with other data/programs Lock down periods to be managed for limited periods of time and to avoid Medium DSE major project development areas during planning phases. Undertake an annual review of operating maintenance costs and report on costs profile changes. Undertake a Medium legislative/regulatory review to ensure DSE data processes and inputs are appropriate for ongoing maintenance of the VSLB High Ref. No: 13 14 15 Risk Area Risk Issue Causes Consequences Existing Controls Funding risk The project is not funded and issues Lack of Treasury support. Lack of associated with Vicmap Property are Project does not proceed community/stakeholder support not resolved project scope. Feedback is to be obtained from DTF before submission of the full business case Existing Data Reliance of existing Vicmap Property data. Uncertainties in the quality and/or Reliance on existing title and survey availability of existing data plan data Availability of aerial photography Review of existing data and understanding of need to revisit thought survey, and other means factored in project cost. Resources 150 | P a g e Insufficient resources/skills to complete project delivery Higher development costs. Timeline delays. Inability to fully complete project There are a limited number of skilled resources available in the Project unable to be fully sector to complete the technical delivered work required for this project Regular contact with industry associations and monitoring of the number of licensed surveyors through the Surveyors Registration Board Control Current Risk (with existing controls) Effectiveness Type C L Risk Level Adequate Marginal Marginal Fin DEL DEL 1 2 2 Mitigation Recommendations Person Target Risk (with recommendations) Allocation Responsible Type C L Risk Level C Work with DSE and DTF to devise suitable performance targets that would Very High help garner acceptance of the DSE proposal. Implement a regime of communication with key stakeholders Project Manager FIN 1 D High C Allow tenderers to review data sets and background information as required to DSE minimise risk cost bidding and ensure project completion Project Manager DEL 3 C Medium Undertake annual resourcing plan and consult with major industry bodies and Very High users of technical services to ensure DSE that resourcing constraints can be managed with the market Project Manager DEL 3 D Medium A High Appendix I 151 | P a g e Financial cashflow Year Ending 30 June REAL 2011-12 dollars 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 m m m m m m m m $22.191 $3.329 $25.520 m m m m m m m m m m m m m $0.002 $0.157 $0.125 $0.009 $0.097 $24.710 $3.706 $28.416 m m m m m m m m m m m m m m m m m m $0.007 $0.636 $0.505 $0.037 $0.393 $26.135 $3.920 $30.055 m m m m m m m m m m m m m m m m m m $0.005 $0.482 $0.383 $0.028 $0.298 $25.991 $3.899 $29.890 m m m m m m m m m m m m m m m m m m $11.863 $1.779 $13.642 m m m m m m m m m m m m m - - - - $11.093 $1.664 $12.757 m m m m m m m m m m m m $0.300 $0.067 $0.779 $0.042 $1.187 $0.178 $1.366 m m m m m m m $0.303 $0.068 $0.786 $0.042 $1.199 $0.180 $1.379 m m m m m m m $0.306 $0.068 $0.794 $0.042 $1.211 $0.182 $1.392 m m m m m m m $0.309 $0.069 $0.802 $0.043 $1.223 $0.183 $1.406 m m m m m m m $0.312 $0.070 $0.810 $0.043 $1.235 $0.185 $1.420 m m m m m m m $0.315 $0.070 $0.817 $0.044 $1.247 $0.187 $1.434 m m m m m m m m m m m m m m $0.321 m $0.045 m $0.366 m $0.055 m $0.421 m - - $0.705 $0.746 $1.451 $0.218 $1.669 m m m m m $0.237 $0.251 $0.489 $0.073 $0.562 m m m m m - - - - - - - $0.524 $0.554 $1.078 $0.162 $1.240 m m m m m $30.371 m $31.461 m $31.310 m $15.076 m $1.448 m $0.421 m - - Upfront & Development Costs Project Planning/Initialisation [DSE] Tender/Procurement Process Staff Training Design and Development of Processes/Tools VSLB Data Model Changes and Data Migration Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] Planning and Data Collation Parcel Data Entry Field Survey - Control Densification Field Survey - Connection of Surveys to Control Adjustment, QA and Data Upload Field based Accuracy Assessment Infill Survey to re-establish selected problem areas Planning and Data Collation Control Selection and Adjustment QA and Upload Data Selected Areas - Rebuild from source plans & Control with Imagery Area Selection Data collation and Key Entry of Source Plan Data Control Selection and Adjustment QA and Upload Data Field accuracy assessment check Sub-total Contingency Total Upfront & Development (including contingecy) - $0.102 m $0.263 m $0.365 m $0.055 m $0.420 m Ongoing Costs Contract Administration [Per Year] Stakeholder engagement/communication Project Delivery Contractor PM [Per Year] Software Licence Maintenance Sub-total Contingency Total ongoing costs - - $0.297 m $0.066 m $0.771 m $1.135 m $0.170 m $1.305 m Capital Costs Software Licences Computer Hardware Imagery Capture DEM Sub-total Contingency Total Upfront & Development (including contingecy) - - $0.515 m $0.515 m $0.077 m $0.592 m Total Real Dollars for Option 5 - $0.420 m $3.611 m 152 | P a g e $0.199 $0.248 $0.193 $0.801 $0.050 $1.491 $0.224 $1.714 $0.404 $0.013 $0.212 $2.007 $0.919 $1.334 $1.320 $0.125 $4.759 $15.362 m $0.428 $4.052 $1.857 $2.694 $2.667 $0.252 $9.611 $0.031 $0.553 $0.047 $28.568 m $0.432 $4.092 $1.875 $2.720 $2.693 $0.255 $9.704 $0.125 $2.233 $0.190 $0.436 $4.132 $1.893 $2.747 $2.719 $0.257 $9.799 $0.126 $2.255 $0.192 $0.441 $4.172 $1.911 $2.774 $2.745 $0.260 $9.895 $0.127 $2.277 $0.194 $0.222 $2.106 $0.965 $1.400 $1.386 $0.131 $4.996 $0.032 $0.575 $0.049 $0.318 $0.071 $0.825 $0.044 $1.259 $0.189 $1.448 - - - Year Ending 30 June NOMINAL DOLLARS 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 - $0.107 m $0.277 m $0.384 m $0.058 m $0.442 m $0.214 m $0.267 m $0.208 m $0.863 m $0.054 m $1.605 m $0.241 m $1.846 m $0.446 m $0.014 m $0.234 m $2.215 m $1.015 m $1.472 m $1.457 m $0.138 m $5.253 m $12.245 m $1.837 m $14.081 m $0.484 m $4.585 m $2.101 m $3.048 m $3.017 m $0.285 m $10.874 m $0.035 m $0.626 m $0.053 m $25.107 m $3.766 m $28.873 m $0.501 m $4.745 m $2.174 m $3.155 m $3.123 m $0.295 m $11.254 m $0.145 m $2.590 m $0.220 m $0.002 m $0.183 m $0.145 m $0.011 m $0.113 m $28.656 m $4.298 m $32.954 m $0.519 m $4.911 m $2.250 m $3.265 m $3.232 m $0.306 m $11.648 m $0.150 m $2.681 m $0.228 m $0.009 m $0.756 m $0.601 m $0.044 m $0.467 m $31.066 m $4.660 m $35.726 m $0.537 m $5.083 m $2.329 m $3.379 m $3.345 m $0.316 m $12.056 m $0.155 m $2.775 m $0.236 m $0.007 m $0.587 m $0.466 m $0.034 m $0.362 m $31.668 m $4.750 m $36.418 m $0.278 m $2.631 m $1.205 m $1.749 m $1.731 m $0.164 m $6.239 m $0.040 m $0.718 m $0.061 m $14.815 m $2.222 m $17.037 m - - - - - - $0.320 m $0.071 m $0.830 m $1.222 m $0.183 m $1.405 m $0.331 m $0.074 m $0.860 m $0.046 m $1.311 m $0.197 m $1.507 m $0.343 m $0.076 m $0.890 m $0.048 m $1.357 m $0.203 m $1.560 m $0.355 m $0.079 m $0.921 m $0.049 m $1.404 m $0.211 m $1.615 m $0.368 m $0.082 m $0.953 m $0.051 m $1.453 m $0.218 m $1.671 m $0.380 m $0.085 m $0.986 m $0.053 m $1.504 m $0.226 m $1.730 m $0.394 m $0.088 m $1.021 m $0.055 m $1.557 m $0.234 m $1.790 m $0.407 m $0.091 m $1.057 m $0.056 m $1.611 m $0.242 m $1.853 m $0.422 m $0.058 m $0.480 m $0.072 m $0.552 m - - Softw are Licences Computer Hardw are Imagery Capture DEM Sub-total Contingency Total Upfront & Development (including contingecy) - - $0.554 m $0.554 m $0.083 m $0.638 m $0.578 m $0.612 m $1.190 m $0.179 m $1.369 m $0.798 m $0.844 m $1.642 m $0.246 m $1.889 m $0.275 m $0.291 m $0.567 m $0.085 m $0.652 m - - - - - - - Total Nom inal Dollars for Option 5 - $0.442 m $3.889 m $16.957 m $32.322 m $35.221 m $37.397 m $38.148 m $18.828 m $1.853 m $0.552 m - - Upfront & Development Costs Project Planning/Initialisation [DSE] Tender/Procurement Process Staff Training Design and Development of Processes/Tools VSLB Data Model Changes and Data Migration Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] Planning and Data Collation Parcel Data Entry Field Survey - Control Densification Field Survey - Connection of Surveys to Control Adjustment, QA and Data Upload Field based Accuracy Assessment Infill Survey to re-establish selected problem areas Planning and Data Collation Control Selection and Adjustment QA and Upload Data Selected Areas - Rebuild from source plans & Control w ith Imagery Area Selection Data collation and Key Entry of Source Plan Data Control Selection and Adjustment QA and Upload Data Field accuracy assessment check Sub-total Contingency Total Upfront & Development (including contingecy) Ongoing Costs Contract Administration [Per Year] Stakeholder engagement/communication Project Delivery Contractor PM [Per Year] Softw are Licence Maintenance Sub-total Contingency Total Upfront & Development (including contingecy) Capital Costs 153 | P a g e Appendix J Project Schedule 154 | P a g e Appendix K Resource Plan The following section outlines the resources required to deliver the preferred option (Option 5Mixed approach). Delivery of the project will require the following resources from the delivery team. Table 46 Required resources and key tasks Resource Title Key Tasks Project initialisation, Project Management, Quality Assurance, Review. Contract Project Director (PD) administration, Project oversight and reporting Should have a strong background in managing Project Manager (PM) Project Adm./ Project Management, Quality Assurance, Review. Contract administration, Project reporting Administration support, Project accounts, Project documentation Documentation Cadastral Technical Cadastral systems leader, technical advisor on cadastral issues including Advisor implementation/ integration of regulations etc IT Developer Developer of the IT architecture and tools used to undertake the cadastral update. IT Systems Designer Designer of the system tools used to undertake cadastral update, QA and on-going management/ maintenance of IT systems Data Capture Team Team manager of data capture operators, quality assurance, communication and Leader team reporting Data Capture Operator Field Survey Team Adjustment Team Leader Capture, conversion and input of required data (including survey plans, etc) into the new cadastre Surveying (in accordance with the surveying regulations) parcels, infill and control as required. Capture of survey data and transmittal to the data capture team. Team manager of adjustment operators, quality assurance, communication and team reporting Adjustment Team Adjustment and input of required data (including adjustment of existing map base Operator to aerial photography, etc) into the new cadastre The project will be delivered in keeping with the project tasks outlined in Appendix F. The project hours allowed under each staff category across the broad project phases are documented in Table 47 below. 155 | P a g e Table 47 : Resource tasks and hours Phase Description Tasks Task Code Total Project Hours by Staff Category PD PM Adm / Docum entation Cadastral Technical IT Developer Advisor IT System s Data Capture Data Capture Designer Team Leader Operator Field Survey Team (incl. Equip.) Adjustm ent Adjustm ent Team Leader Team Operator PROPOSED IMPLEMENTATION OPTION Project Management & Setup [DSE] Project Planning/Initialisation [DSE] Contract Administration Tender/Procurement Process Stakeholder engagement/communication 105 106 200 115 112 2376 152 320 172 3024 388 768 144 3888 344 1024 104 2808 264 256 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Project Delivery Contractor PM Staff Training 110 1100 1536 0 10368 88 2688 204 2112 36 768 0 384 40 2688 48 0 432 2112 64 2688 48 0 408 Design and Development of Processes/Tools Software Licences Software Licence Maintenance Computer Hardware VSLB Data Model Changes and Data Migration 300 306 307 305 525 32 0 0 0 0 88 0 0 0 56 64 0 0 0 0 120 0 0 0 312 584 0 0 0 472 280 0 0 0 40 112 0 0 0 0 80 0 0 0 320 8 0 0 0 0 64 0 0 0 0 0 0 0 0 0 Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 parcels] 400 600 12 16 4556 32 40 15024 16 0 8372 28 36 6076 8 0 1832 0 0 744 236 20 3104 2978 0 3810 2306 0 4490 791 164 3755 835 171 1414 Planning and Data Collation Parcel Data Entry Field Survey - Control Densification Field Survey - Connection of Surveys to Control Adjustment, QA and Data Upload Field based Accuracy Assessment 500 505 506 508 510 515 0 0 0 0 0 0 0 0 0 4 0 0 0 0 0 4 0 0 0 0 0 0 0 0 0 0 0 60 0 0 0 0 0 60 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8785 8625 5750 0 11500 0 34660 0 0 8625 191667 0 0 23000 0 223292 0 0 0 0 28750 34500 3450 2875 69575 138000 138000 0 0 0 23000 17250 2875 43125 51750 51750 0 0 0 0 59225 0 59225 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4556 0 40 0 0 0 0 0 40 0 4 0 0 0 0 4 15072 0 80 0 0 0 0 0 80 0 0 0 0 0 0 0 8452 0 0 0 0 0 0 0 0 0 40 0 0 0 0 40 6176 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1832 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 744 0 0 0 0 2976 0 0 2976 0 40 600 600 0 0 1240 41980 0 0 0 0 0 0 0 0 0 0 11700 600 0 0 12300 239402 0 0 0 0 0 0 0 0 0 0 0 600 0 2400 3000 215065 0 0 0 0 0 22950 2700 25650 0 0 0 900 300 450 1650 125930 0 0 0 0 0 44550 2700 47250 0 0 0 5425 300 0 5725 113614 Project Management Information Technology Pilot Project [30,000 parcels] Total Management and Establishment Costs Rebuild in Urban Areas [2.3M parcels] [Option 3a] Sub-total [Option 2 in selected problem areas] Infill Survey to re-establish selected problem areas Sub-total Rural Areas Adjustment to Imagery [900,000 parcels] [Option 4b] Supplement Imagery/DEM capture Programs [Assume 900,000 - 90,000 parcels upgraded this way] Imagery Capture DEM Planning and Data Collation Control Selection and Adjustment QA and Upload Data 520 700 705 800 810 815 Sub-total Rebuild with Imagery Controlled Adjustment Selected Areas - Rebuild from source plans & Control with Imagery [Option 3b in selected areas] Area Selection 900 [Assume 10% or 90,000 parcels upgraded in this method] Data collation and Key Entry of Source Plan Data 905 Control Selection and Adjustment 906 QA and Upload Data 908 Field accuracy assessment check 910 Sub-total TOTAL PAGE 156 An assessment of these options indicates that the staff allocation and phasing broadly allows for the following resources (full time equivalent) across phases: Table 48: Resource FTE staff Tasks FTE Start Date Finish Date Project Planning/Initialisation [DSE] Jan-13 Dec-13 Contract Administration [Per Year] Jul-14 Dec- 20 Tender/Procurement Process Jan-14 Jun-14 Stakeholder engagement/communication Jul-13 Dec-21 Jul-14 Dec-21 Jul-14 Feb-15 Design and Development of Processes/Tools Jul-14 Mar-15 Software Licences Sep-14 Jan-15 Software Licence Maintenance Jul-14 Dec-21 Computer Hardware Sep-14 Dec-14 VSLB Data Model Changes and Data Migration Dec-14 Feb-15 1-Sep-14 1-Feb-15 1-Dec-14 1-Jan-15 Pilot Project Review 15-Feb-15 15-Jun-15 Contract approval for full project works 15-Jun-15 1-Mar-16 1-Jun-16 30-Dec-20 1-Jun-16 30-Dec-20 1-Jun-16 30-Dec-20 Project Management & Setup [DSE] Project Management Project Contractor PM establishment and reporting processes 29 Staff Training Information Technology Pilot Project [30,000 parcels] Urban Area Rebuild from Source Data Pilot [35,000 parcels] Rural Area Adjustment using Imagery Pilot [4000 22 parcels] Rebuild in Urban Areas [2.3M parcels] Planning and Data Collation Parcel Data Entry Field Survey - Control Densification 44 SINCLAIR KNIGHT MERZ PAGE 157 Tasks FTE Start Date Finish Date Field Survey - Connection of Surveys to Control 1-Jun-16 30-Dec-20 Adjustment, QA and Data Upload 1-Jun-16 30-Dec-20 Field based Accuracy Assessment 1-Jun-16 30-Dec-20 Infill Survey to re-establish selected problem areas 1-Oct-17 30-Mar-21 Supplement Imagery/DEM capture Programs Mar-16 1-Oct-17 Imagery Capture Mar-16 1-Oct-17 Mar-16 1-Oct-17 Planning and Data Collation 1-Mar-18 30Dec-19 Control Selection and Adjustment 1-Mar-18 30Dec-19 QA and Upload Data 1-Mar-18 30Dec-19 1-Mar-18 31-Jun-21 1-Mar-18 31-Jun-21 Control Selection and Adjustment 1-Mar-18 31-Jun-21 QA and Upload Data 1-Mar-18 31-Jun-21 Field accuracy assessment check 1-Mar-18 31-Jun-21 30-Jun-21 31-Dec-21 Rural Areas Adjustment to Imagery [900,000 parcels] DEM 21 Rebuild with Imagery Controlled Adjustment Selected Areas - Rebuild from source plans & Control with Imagery Area Selection Data collation and Key Entry of Source Plan Data 7 Project Close out Project Close out, contract review and whole of project 7* QA review *Part of the overall Project Management FTE count The project will require 50 FTE staff over the 10 year implementation period. The most fundamental risk associated with the proposed timelines and structure is the availability of suitable resources to undertake the required tasks. This is particularly an issue for the field survey teams. It is estimated that 11 field survey teams (of 1 licensed surveyor per team) would be required. There are currently 413 licensed surveyors in Victoria and hence it is estimated that SINCLAIR KNIGHT MERZ PAGE 158 the project will utilise 3% of the full time capacity of the profession. This can be compared with a full re-survey of the State as required by Option 2 which would potentially engage over 25% of the surveyors in the state for a minimum of 10 years. Task Sheets Table 49 outlines the tasks and sub-tasks expected to be undertaken in the development of a survey accurate map base. This task list was used to develop the costing model and outlines the steps expected to be undertaken by the contracting party in delivery of the proposed Victorian Spatial Land Base. Table 49 Project task list Tasks PROJECT PLANNING [DSE] Implementation Options Review and Decision Project Implementation Team Selection/Appointment High Level Implementation Plan Detailed Project Plan Project Implementation plan Project Quality & review plan Review/Amendment of Project Plan Communication Plan Draft Communication Plan Review/Finalise Communication Plan Governance Committee Selection/Appointment PROJECT MANAGEMENT (PER YEAR) Contract Administration [DSE] Project Review (Monthly) Project Meetings - Project team (Bi-weekly) SINCLAIR KNIGHT MERZ PAGE 159 Tasks Project Meetings - Client (Monthly) Project Reports (Monthly) Project Delivery Contractor Management Costs [Contractor] Project Review (Monthly) Project Meetings - Project team (Bi-weekly) Project Meetings - Client (Monthly) Project Reports (Monthly) Project Staff Supervision Stakeholder Communication Newsletters (Quarterly) Stakeholder Workshops/Information Sessions (Quarterly) Preparation Workshops Follow-up Miscellaneous Reports/Communiqués CONTRACT TENDERING [DSE COSTS] Draft Tender Documentation Contract Documentation Project Specification Finalise Tender Documentation Contract Documentation Project Specification Tender Process EOI Tender Advertising Tender Briefing SINCLAIR KNIGHT MERZ PAGE 160 Tasks Tender Q&A Tender Reviews and Short listing Probity Auditor Tender Presentations/Interviews Recommendations & Internal Queries Appointment of successful Tenderer DEVELOPMENT OF SYSTEMS/PROCESSES Requirements Definition/Functional Design DCDB Data Management/Synchronisation Processes Design Data Collection processes Data Capture Processes /Entry Tools Adjustment Processes/Tools QA Processes/Tools Field Survey Processes Detailed Design of Tools Data Capture/Entry Tools Adjustment Tools QA Tools Data Management Processes Build Tools Data Capture Adjustment QA Data Management Testing/Amendments SINCLAIR KNIGHT MERZ PAGE 161 Tasks Data Capture Adjustment QA Data Management Software and Hardware Computer Hardware - Servers Adjustment Software Desktop Workstations Software Maintenance (@10% of purchase price) Update/Modifications to Tools after Pilot Testing Data Capture Adjustment QA Data Management TRAINING Define Training Requirements Training Outline/Develop Structure of Content Training Resources Level of training for various Operator levels (included in above) Develop Training Packages Data Capture/Entry Tools Adjustment Tools QA Tools Data Management Processes Field Survey Processes Deliver Training SINCLAIR KNIGHT MERZ PAGE 162 Tasks Data Capture Adjustment QA Data Management Field Survey Processes PROOF OF CONCEPT PILOT - REBUILD FROM SOURCE PLANS Pilot Area Selection Select Representative Areas Define Data Package Areas (these will be adjusted together) Source Data Collection/Collation Research/collate survey observation data (already scanned) Review/Identify Control Densification Requirements Key Entry of Subdiv. Plan Data [Per Parcel] [Assume 95% lots require] Key Entry of Survey Fieldnotes Traverse Data [Per Plan/Parcel?] Collate/Report for Field Survey Requirements Supplementary Field Survey - Control Densification Field Survey - Control Densification (Time /Control Point) Document/PSM Sketches Supplementary Field Survey - Control Connection Field Survey - Connection to existing surveys not currently on MGA/AMG Document Review/QA Data Collection (Package level) Check all inputs available for adjustment Check misclosures Adjustment Run Adjustment Process SINCLAIR KNIGHT MERZ PAGE 163 Tasks Check Adjustment Outputs/Residuals & identify anomalies Resolve Anomalies/additional data collection Re-Run Adjustment Process Load back to DCDB Load back and Unlock Final QA Document and Review Pilot Outcomes Field QA on accuracy of selected points Document results/Report Review/Discuss Changes to Methodology Review Implementation Plan PROOF OF CONCEPT PILOT - ADJUSTMENT OF RURAL AREAS - IMAGERY DATA CONTROLLED Pilot Area Selection Select Representative Areas Define Data Package Areas (these will be adjusted together) Source Data Collection/Collation Collect/Review & Load Best Available Imagery Extract Cadastre from DCDB Control Selection and Adjustment On-screen identification of Occupation and create control links (cadastre to imagery) Set weightings/constraints [per work unit] Run Adjustment Process [per work unit] Review Outputs from Adjustment - ID Anomalies [per work unit] Create new links/remove as required [per work unit] Re-Run Adjustment Process [per work unit] SINCLAIR KNIGHT MERZ PAGE 164 Tasks Document/Report Results Load back to DCDB Load back and Unlock Final QA Document and Review Pilot Outcomes Field QA /Re-establishment of selected points [per work area = No of Points surveyed] Document results/Report Review/Discuss Changes to Methodology Review Implementation Plan IMAGERY/DEM CAPTURE Imagery Capture Develop Specifications/Procurement Process Ortho-Imagery - flying and production DEM Development Develop from LiDAR or Stereo-Imagery FULL IMPLEMENTATION - REBUILD FROM SOURCE PLANS Area Selection Define Work Package Areas (these will be adjusted together) Source Data Collection/Collation (per Package Area) Research/collate survey observation data (already scanned) - Per Package Review/Identify Control Densification Requirements Key Entry of Subdivision Plan Data Key Entry of survey Abstract of Field Records Traverse Data Collate/Report for Field Survey Requirements (Per Work Package) Supplementary Field Survey - Control Densification (Per Package Area) SINCLAIR KNIGHT MERZ PAGE 165 Tasks Field Survey - Control Densification (Time /Control Point) ID & Measure Cadastral Control Marks (per package area) Document/PSM-Control Mark Sketches Supplementary Field Survey - Control Connection (Per Package) Field Survey - Connection to existing surveys not currently on MGA/AMG Document Review/QA Data Collection (Package level) Check all inputs available for adjustment Check misclosures Set Constraints/weighting Adjustment (Per Package) Run Adjustment Process Check Adjustment Outputs/Residuals & identify anomalies Resolve Anomalies/additional data collection Re-Run Adjustment Process Load back to DCDB (Per Package) Load back and Unlock Easements - include from old Cadastre & adjust? Resolve Mismatches (old centroids not transferring) Final QA Field Accuracy Assurance (Per Package) Field QA on accuracy of selected points Document results/Report InFill Survey - Re-establishment as Required Field Survey for selected re-establishments Document results/Plans/Abstract of Field Records/Surveyor’s Report SINCLAIR KNIGHT MERZ PAGE 166 Tasks Cadastral Model Upgrade Define Requirements Implement changes to Model Data Migration FULL IMPLEMENTATION - ADJUSTMENT TO IMAGERY Area Selection Define Data Package Areas (these will be adjusted together) Source Data Collection/Collation Collect/Review & Load Best Available Imagery [per LGA] Extract Cadastre from DCDB [per package] Control Selection and Adjustment Adjustment of Road Boundaries (50% of points) On-screen identification of Occupation and create control links (cadastre to imagery) Set weightings/constraints (per Package) Run Adjustment Process Review Outputs from Adjustment - ID Anomalies Adjustment of Other Boundaries (50% of points) On-screen identification of Occupation and create control links (cadastre to imagery) Set weightings/constraints (per Package) Run Adjustment Process Review Outputs from Adjustment - ID Anomalies Create new links/remove as required Re-Run Adjustment Process Document/Report Results SINCLAIR KNIGHT MERZ PAGE 167 Tasks Load back to DCDB Load back and Unlock Final QA Potential Update of Cadastral Data Model Define Requirements Implement changes to Model Data Migration SINCLAIR KNIGHT MERZ PAGE 168