PREBID MEETING HELD ON 25 Oct 2013 Addendum For

advertisement
PREBID MEETING HELD ON 25 Oct 2013
Addendum For
Installation of HVAC system in a building at IST, Islamabad
Points raised during pre-bid meeting held on 25 Oct 2013 are as under:-.
1. Date of Bid Submission
Bids will be received on 04 Nov 2013 before 1000 hours and will be opened on
same date at 1030 hrs.
2. Item 1 Total outdoor units are 15 as given in this item, Unit No 16 shown does not exist and
may be ignored.
3. Item 2 is for 100% fresh Air Units with humidifiers, based on 43.9 deg C dry bulb and 28,3
deg C wet bulb C temperature in summer and 0.6 deg C dry bulb and 99% RH in winter.
4. Item 3 & 4 is related to Indoor units. The Indoor Units Given In Schedule On Drawing No 1
Are Correct, As Per Following Details:
a. Floor and Number Wise Indoor Units In BOQ (Wall Mounted, Cassette Type & Floor
Mounted Are As Under:
i.
The Unit # 58 To 73 (1.5 Tons) 16 Units Are Wall Mounted. On Lower Ground
Units No 158, 159 And 160 Units Have Been Changed From Cassette To Vertical
type, However, 158-A, 159-A and 160-A are New Addition as Stand-By Vertical
Units. Rest Of The Units are all Cassette Type.
b. All Cost Of Y-Connectors And The Cost Of Expansion Valves Will Be Included In
The Cost Of Units.
c.
5. Item 5 Supply And Installation Of Sheet Metal Ducting Complete In All Respect As Shown
On The Drawings, Complete With Accessories Hangers, Supports & As Approved By The
Engineer/Consultant:
Page 1 of 5
22 Gauge
2500
Sq. ft
24 Gauge
18528
Sq. ft
26 Gauge
1250
Sq. ft
6 Item 6 Supply & installation of following Aluminum Foil Fiber Glass 16kg/m3 density)
insulation wrapped with Aluminum tape and shall be protected with 8 oz canvas,
complete in all respect as shown on the drawings as approved by the engineer/consultant:
Sound liner 1'' thick
Thermal insulation 1'' thick
Thermal insulation 2'' thick
2860
17150
1860
Sq. ft
Sq. ft
Sq. ft
7 Item 7 Supply& installation of Refnet Y Connectors for phase 1 as per specification and
thickness shall not be less than 18 gaugeand shall be included in the cost of indoor units.
8 Item 8 Supply and Installation of refrigerant pipes type L thickness not less than 20
gauge (Liquid+Gas) with expanded rubber foam insulation for Multi Split type A/C units
good quality cable try from each FCU to outdoor units installed on roof top, including
control wiring, Flushing, gas charging, hangers, supports and brackets of following sizes
all refrigerant pipes should be in PVC Dura Duct as approved by the Engineer/consultant:
6.35mm x t0.8
1450
Rft
9.52 mm x t0.8
1850
Rft
12.7 mm x t1.0
1450
Rft
15.88 mm x t1.2
8.6 mm x t1.2
41.3 mm x t1.6
3320
702
710
Rft
Rft
Rft
34.9 mm x t1.4
270
Rft
22.2 x t1.2
650
Rft
9 Item 9 Supply and Installation of PVC condensate drain pipe with insulation from each
FCU to condensate tank complete in all respect ready to operate as approved by the
Engineer/Consultant. Quantity-1 Lot
10 Item 10 Supply& installation ofRefnet Y Connectors for phase 2 as per specification and
thickness shall not be less than 18 gaugeand shall be included in the cost of indoor units.
11 Item 11Supply & installation of Communication cable complete project forMDS units
complete in all respect, as approved by the Engineer/ Consultant. Quantity- 1 Lot
Page 2 of 5
12 Item 12 Supply and installation of Aluminum Registers for supply of fresh air and
exhaust air of following sizes, complete in all respect, support and other accessories etc.
Make: Steel Craft, as approved by the Consultant:
For Basement floor
SAD 24'' x 6''
For Lower Ground Floor SAD 24'' x6''
For Upper Ground floor SAD 24''x 6''
3
9
24
No.
No.
No.
For First Floor
For First Floor
For Second Floor
10
No.
40
40
No.
No.
SAD 24'' x 6''
SAD 24'' x 12''
SAD 24'' x 3''
13 Item No 13Supply and Installation of Electronic Expansion valve (EXV) as per
manufacturer's recommendation and approved by the Engineer/consultant. The price of
this item shall be included in the cost of indoor units.
14 Item No 14Supply and installation of Best quality PVC water tank 500 gallons normally
used as overhead tank for condensate including level automatic controller with upper and
lower level sensor complete in all respect as approved by the
Engineer/consultant.Quantity-1 No.
15 Item No 15Supply & installation of Centrifugal Pump as specified (25 GPM) against 20
ft head, suitable to throw condensate water collected in the tank from basement to lower
ground floor in open space as shown on the drawings through automatic water level
controller complete in all respect and as approved by the Engineer/consultants.
Quantity- 1 No.
16 Item No 16Supply and installation of electrical DB for air conditioning with incoming
and outgoing circuit breakers with AEG/ Hager/Terasaki/Fuji/BB including bus bar volt
& Ampere meters, selector switch phase indicator lamps complete in all respect approved
equivalent by the engineer/consultant of following capacity. Quantity-1 No.
Incoming 1800 ATP MCCB
1
No.
Outgoing 200 ATP MCCB
11
No.
Outgoing 150 ATP MCCB
5
No.
Outgoing 130 ATP MCCB
2
No.
Outgoing 125 ATP MCCB
3
No.
Outgoing 100 ATP MCCB
3
No.
Outgoing
3
No.
80 ATP MCCB
Page 3 of 5
17 Item No 17Supply and installation of copper conductor power cables make by Pakistan
Cables/ AEG Cables/ New Age cables or approved equivalent cables by the Consultant in
cable tray from DB to all out door units installed on roof as shown on the drawings in
cable trey , complete in all respect as and as approved by the Engineer/consultant as
detailed below:
3.5 core 300 mm sq
660
Rft
3.5 core 35 mm sq
1270
Rft
3.5 core 25 mm sq
80
Rft
3.5 core 16 mm sq
65
Rft
3.5 core 30 mm sq
1
Rft
3.5 core 18 mm sq
1
Rft
3.5 core 10 mmsq
1
Rft
3.5 core 5 mmsq
1
Rft
18 Item No 18Construct, fabricate and install Foundation structure for frame for placing
condensing units in consultation with structural Engineer of the client.
Quantity-17 No.
19 Item No 19 Supply of Manufacture's recommended spare parts for all above items for 2
years normal operation as approved by the engineer/ Consultant. ( provide list)
Quantity- 1 Lot
20 Item No 20Supply of Digital type Wall mounted temperature and humidity indicator.
Quantity-12 No
21 Item No 21Make wall openings in concrete walls of lift well and provided 1'' thick
wooden Box in the openings as per sizes given on the drawings complete in all respects
as per satisfaction of Engineer/Consultant. Quantity -1 Lot.
22 Item No 22Testing, balancing & commissioning of the system. Quantity- 1Lot
23 Item No 23Operation and maintenance of the system (8:00) hr at least one month
operation in summer and one month in winter. Quantity- 1Lot
24 Item No 24After completion of commissioningprepare as build drawing for the record of
the client after obtaining approval of the engineer/consultant.
Quantity-1Lot
Page 4 of 5
25 Chinese equipment shall be quoted separatelyas proposal # 1 and Japanese, Korean and
Malaysian equipment as proposal # 2.
26 Earnest money should be in Pay Order.
27 Following Advance payments can be taken against scheduled bank guarantee:
i.
ii.
iii.
iv.
On approval of Technical submittals by the consultant.
On opening LC.
On production of Bill of Lading
On delivery of equipment at site against theft insurance.
10%
10%
10%
20%
Page 5 of 5
Download