Appendix Key Changes to Code of Practice on Surface Water Drainage Existing Version Minimum Platform Levels for General Developments Revised Version Minimum Platform Levels for General Developments The minimum platform level shall not be lower than:- The minimum platform level shall not be lower than:- (i) 75 cm above the highest tide level in the vicinity. For this purpose, the highest tide level shall, unless otherwise specified, be taken as follows :- (i) 104.0 mRL for developments along the southern coast, and 104.5 mRL for developments along the northern coast; or ° along the southern coast of Singapore Island from Tuas to Changi : RL 101.75m (ii) 30 cm above the adjacent road/ground level; or ° along the north-eastern coast of Singapore Island from Changi to Causeway : RL 102.05m (iii) 60 cm above the highest recorded flood level, if any, as advised by PUB; or ° along the north-western coast of Singapore Island from Tuas to Causeway : RL 102.35m (ii) (iv) Any other level as may be specified by PUB; whichever is the highest. the adjacent road/ground level; (iii) 30 cm above the highest recorded flood level, if any, as advised by PUB; or (iv) other level as may be specified by PUB; whichever is the highest. Minimum Platform Levels for Commercial/ Multi-Unit Residential Developments with basements Minimum Platform Levels for Commercial/ Multi-Unit Residential Developments with basements The minimum platform level shall not be lower than:- The minimum platform level shall not be lower than:- (i) 75 cm above the highest tide level in the vicinity. For this purpose, the highest tide level shall, unless otherwise specified, be taken as follows :- (i) 104.0 mRL for developments along the southern coast, and 104.5 mRL for developments along the northern coast; or ° along the southern coast of Singapore Island from Tuas to Changi : RL 101.75m (ii) 60 cm above the adjacent road/ground level; or ° along the north-eastern coast of Singapore Island from Changi to Causeway : RL 102.05m ° along the north-western coast of Singapore Island from Tuas to Causeway : RL 102.35m (ii) (iii) 60 cm above the highest recorded flood level, if any, as advised by PUB; or (iv) Any other level as may be specified by PUB; whichever is the highest. the adjacent road/ground level; (iii) 30 cm above the highest recorded flood level, if any, as advised by PUB; or (iv) other level as may be specified by PUB; whichever is the highest. Minimum Crest Level Minimum Crest Level Minimum crest level is required for an entrance, exit or opening to a basement or underground structure (basement, tunnel, underground facility, etc) as follows:- Minimum crest level is required for an entrance, exit or opening to a basement or underground structure (basement, tunnel, underground facility, etc) as follows:- (i) (i) Basements of General Developments Basements For basements, underpasses and sunken/underground facilities, the minimum crest level shall be at least 15 cm above the minimum platform level. (ii) Special Underground Facilities For Rapid Transit underground stations/tunnels, underground road networks, depressed roads, and other special underground facilities, the minimum crest level shall be at least 15 cm above the minimum platform level (iii) Linkage to Special Underground Facilities All developments with direct or indirect links to these special underground For basements, underpasses and sunken/underground facilities, the minimum crest level shall be at least 15 cm above the minimum platform level. (ii) Special Underground Facilities and Basements of Commercial/ MultiUnit Residential Developments For Mass Rapid Transit underground stations/tunnels, underground road networks, depressed roads, basements of Commercial/ Multi-Unit Residential Developments and other special underground facilities, the minimum crest level shall be at least 30 cm above the minimum platform level. (iii) Linkage to Special Underground Facilities and Basements of Commercial/ MultiUnit Residential Developments facilities shall comply with the same minimum crest level requirements. All developments with direct or indirect links to these special underground facilities and basements of Commercial/ Multi-Unit Residential Developments shall comply with the same minimum crest level requirements. Minimum Reclamation Level Minimum Reclamation Level For land reclamation works, the minimum reclamation level shall not be lower than:- For land reclamation works, the minimum reclamation level shall not be lower than:- (i) RL 103.0m along the southern coast; and (i) RL 104.0m along the southern coast; and (ii) RL 103.5m along the northern coast; or (ii) RL 104.5m along the northern coast; or (iii) Any other levels as may be specified by PUB. (ii) Any other levels as may be specified by PUB. Drainage Design Standards Drainage Design Standards Major rivers – return period of 50 to 100 years as specified by the PUB The drainage design standards for new drains will be increased to cater for more intense storms The new return periods used for drainage design are: Important installations/developments such as airports and tunnels – return period of 50 years Outlet drains and secondary drainage facilities – return period of 5 years - 10 years for catchments less than 100 hectares - 25 years for catchments of 100 to 1000 hectares - 50 years for catchments more than 1000 hectares (and critical installations) Earth Control Measures at Construction Sites Earth Control Measures at Construction Sites The basin / tank shall have a storage capacity to cope with the volume of water from a rain based on a minimum design return period of 1 in 2 years storm. The basin / tank shall have a storage capacity to cope with the volume of water from a rain based on a minimum design return period of 1 in 5 years storm. Intensity-Duration-Frequency (IDF) Curve Data IDF Curve Data Data from 1931-2009 Data from 1931-1989