RESPONSE OF ORE MASSES TO STOPE SEQUENCE VARIATIONS *N. Saeidi, D. Millar LaurentianUniversity 935 Ramsey Lake Road Sudbury, Canada P3E 2C6 (*Corresponding author: nsaeidi@laurentian.ca) ABSTRACT For a mine section comprising 100 different stoping activities, there are ~10 158 different possible stoping sequences to explore in the mine schedule optimization search and this figure is indicative of the challenge posed in maximising profitability through mine schedule optimization.Any viable excavation timetable must satisfy all conditions that will constrain feasible sequences. In general, consideration of additional constraint will tend to reduce profitability. Geomechanical constraints on mine schedules, introduced with the aim of avoiding excavation instabilities, can be established for underground mine schedule optimization processes but, currently, this is done only rather crudely; precedence relations between excavation activities (stoping or development) are encoded to produce particular stope sequence patterns (e.g. chevron or pyramidal sequences) that ‘override’ basic access precedence. The work reported aimed to investigate automated processes for formulation of such geomechanical constraints. The timetable optimization approach to the problem precipitated a fresh look at time dependent, and excavation sequence dependent, deformation. Abundant evidence emerged that supported the notion that any methodology developed that failed to account for such time and sequence dependencies was itself bound to failure. Yet, it was also recognised that any deviation at all from an assumption of linear elasticity for geomechanical numerical modeling, adopted to inform geomechanical constraint formulation, would rapidly lead to impractical levels of computational effort. Thus the approach presented here represents a compromise: the elastic stress fields induced by individual mining activities are computed for each activity, independently considered within a computational domain identical to that of all other activities. These are stored in a database. Instability risk for a specific sequence of mine activities can be assessed through superimposition of stress fields drawn from the pre-computed database. Time stamps allocated to events corresponding to the excavation processes permit the conversion of the sequence of elastic stress fields into a time table of stress fields. For specific locations within the computational domain, the aggregate effect of the sequence of mine activities leads to stress-time histories having a castellated appearance, a result of the near instantaneous response of an elastic medium to the excavation perturbations. Time dependent deformation responses are crudely allowed for through the reprofiling these castellated histories through graphical construction of curved responses, where the curve gradients are related to a viscous parameter. Such curves form the basis for a geomechanical constraint formulation adopted mine schedule optimization. Figure 1 – Typical time-dependent stope closure of the Ventersdorp Contact Reef at Western Deep Levels Mine[1]. Dashed lines are added to emphasize differences between expected elastic and visco-elastic deformation responses. KEYWORDS Mine schedule optimization, time-dependent deformability, excavation sequencing [1] Malan, D. F., 1999. Time-dependent Behaviour of Deep Level Tabular Excavations in Hard Rock. Rock Mechanics and Rock Engineering, Springer-Verlag , 32(2), pp. 123-155.