9. guidelines for environmental and social

advertisement
E4085v12
REPUBLIC OF MOZAMBIQUE
MINISTRY OF AGRICULTURE
INSTITUTO NACIONAL DE INVESTIGAÇÃO AGRONÓMICA
DE MOÇAMBIQUE (IIAM)
AGRICULTURAL PRODUCTIVITY PROGRAM
FOR SOUTHERN AFRICA
(APPSA)
Environmental and Social Management Framework
(ESMF)
3 January 2013
TABLE OF CONTENTS
EXECUTIVE SUMMARY ........................................................................................... viii
1. INTRODUCTION......................................................................................................... 1
2. PROJECT DESCRIPTION ......................................................................................... 2
2.1. Project Development Objectives and Principles .................................................... 2
2.2. Project Components ............................................................................................... 3
2.3. Anticipated sub-Project types under APPSA ......................................................... 9
3. PROJECT IMPLEMENTATION ARRANGEMENTS ......................................... 10
4. BASELINE INFORMATION ON PROJECT TARGETED AREAS ................... 15
4.1. Agro-ecological Zone 1 (R1) ............................................................................... 17
4.2. Agro-ecological zone 3 (R3) ................................................................................ 18
4.3. Agro-ecological zone 4 (R4) ................................................................................ 18
4.4. Agro-ecological Zone 5 (R5) ............................................................................... 19
4.5. Agro-ecological Zone 7 (R7) ............................................................................... 19
5. WORLD BANK SAFEGUARD POLICIES ............................................................ 20
6. LEGAL AND INSTITUTIONAL FRAMEWORK FOR ENVIRONMENTAL
AND SOCIAL MANAGEMENT IN MOZAMBIQUE ............................................... 24
6.1. Legal Framework ................................................................................................. 24
6.2. Institutional Framework ....................................................................................... 31
7. POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS AND
MITIGATION MEASURES ......................................................................................... 36
7.1. Potential adverse environmental impacts............................................................. 37
7.2. Potential adverse socio-economic impacts .......................................................... 44
7.3. Potential positive impacts .................................................................................... 46
8. GUIDELINES FOR SUB-PROJECT PREPARATION, APPRAISAL,
APPROVAL AND MONITORING .............................................................................. 49
8.1. Project identification and preparation .................................................................. 50
8.2. Appraisal and Approval of sub-projects application ........................................... 52
8.3. Disclosure of sub-projects information ................................................................ 54
8.4. Annual Monitoring Reports and review .............................................................. 54
8.5. Environmental and Social Audit .......................................................................... 55
8.6. Summary of preparation, appraisal, approval and implementation procedures ... 55
9. GUIDELINES FOR ENVIRONMENTAL AND SOCIAL MANAGEMENT
PLAN AND MONITORING REQUIREMENTS........................................................ 58
9.1. Environmental and Social Management .............................................................. 58
9.2. Pest Management ................................................................................................. 59
9.3. Involuntary resettlement ...................................................................................... 60
10. TRAINING AND CAPACITY BUILDING REQUIREMENTS ......................... 60
10.1. Institutional Capacity Assessment ..................................................................... 60
10.2. Proposed Training and Awareness Programs .................................................... 60
10.3. Technical Assistance (TA) ................................................................................. 65
11. ESMF MONITORING REQUIREMENTS ........................................................... 66
12. PROPOSED IMPLEMENTATION BUDGET...................................................... 66
ii
LIST OF TABLES
Table 1. Potential Sub-projects to be financed by APPSA ............................................... 10
Table 2. Safeguard policies triggered by the proposed project ......................................... 20
Table 3. Ministries with environmental and Social-related responsibilities in APPSA ... 32
Table 4. Summary of the negative and positive impacts of indicative sub-projects......... 48
Table 5. Criteria for Requiring a Field Appraisal ............................................................. 53
Table 6. Government agencies to be involved on a case by case ..................................... 57
Table 7. Training and sensitization requirements ............................................................. 62
Table 8. Proposed specific training packages and timing ................................................. 63
Table 9. Estimated implementation budget for APPSA ................................................... 67
LIST OF FIGURES
Figure 1: Proposed organization and structure for APPSA in Mozambique .................... 12
Figure 2: Proposed organization and management system for the RCoL. ....................... 15
Figure 3: Location of APPSA targeted areas .................................................................... 16
Figure 4. Flow of activities to be carried out for the ESIA process in Mozambique ....... 29
Figure 5. Proposed sub-projects identification, submission, evaluation and monitoring . 56
LIST OF ANNEXES
ANNEX I: ToR FOR AN SESIA OF MEDIUM-SCALE IRRIGATION SCHEMES
ANNEX II: CHECKLIST FOR ENVIRONMENTAL AND SOCIAL SCREENING
ANNEX III: RESOURCES SHEET
ANNEX III.1. SMALL DAMS AND RESERVOIRS
ANNEX III.2: SMALL IRRIGATION SCHEMES
ANNEX III.3. RURAL ROADS
ANNEX III.4. FOOD PROCESSING
ANNEX III.5. STRUCTURES AND BUILDINGS
ANNEX III.6. ELECTRIC ENERGY
ANNEX IV: ENVIRONMENTAL AND SOCIAL FIELD APPRAISAL FORM
ANNEX V: GUIDELINES FOR ANNUAL REPORT
ANNEX VI: GUIDELINES FOR ANNUAL REVIEWS
ANNEX VII: GUIDELINES FOR AN ESMP
ANNEX VIII: LIST OF VISITED SITES, CONSULTED STAKEHOLDERS AND KEY
OBSERVATIONS
iii
ABBREVIATIONS AND ACRONYMS
ANE
National Roads Administration
Administração Nacional de Estradas
APPSA
Agriculture Productivity Program
for Southern Africa
ARA
Regional Water Admnistration
BOD
Biochemical Oxygen Demand
CAADP
Comprehensive Africa Agriculture
Development Programme
CBD
Convention on Biological
Diversity
CCARDESA
Centre for Coordination of
Agricultural Research and
Development for Southern Africa
CEPAGRI
Agriculture Promotion Center
CGIAR
Consultative Group on
International Agricultural Research
CNDS
National Commission for
Sustainable Development
COD
Chemical Oxygen Demand
DARN
Directorate of Agronomy and
Natural Resources
Direcção Nacional de Agronomia e
Recurso Naturais
DEP
Department of Roads and Bridges
Departamento de Estradas e Pontes
DER
Department of Rural Extension
Departamento de Extensão Rural
DNA
National Directorate of Water
Direcção Nacional de Águas
DNAIA
National Directorate of
Environmental Impact Assessment
Direcção Nacional de Avaliação de
Impacto Ambiental
DNS
National Directorate of Health
Direcção Nacional de Saúde
DNSA
National Directorate of Agrarian
Services
Direcção Nacional de Serviços
Agrários
DNTF
National Directorate of Land and
Forestry
Direcção Nacional de Terras e
Florestas
DPCA
Provincial Directorate for
Coordination of Environmental
Action
Direcção Provincial de Coordenação
Ambiental
DPOPH
Provincial Directorate of Public
Works and Housing
Direcção Provincial de Obras
Públicas e Habitação
Administração Regional de Águas
Centro de Promoção de Agricultura
Conselho Nacional de
Desenvolvimento Sustentável
iv
EA
Environmental Assessment
ESIA
Environmental and Social Impact
Assessment
ESMF
Environmental and Social
Management
Framework
ESMP
Environmental and Social
Management Plan
FAAP
Framework for African
Agricultural Productivity
FAEF
Faculty of Agronomy and Forestry
FAO
United Nations Food and
Agricultural Organization
GMO
Genetically Modified Organisms
GIS
Geographic Information System
GoM
Government of Mozambique
IDA
International Development Agency
IIAM
National Agrarian Research
Institute
IFDC
International Finance and
Development Corporation
IFPRI
International Food Policy Research
Institute
IPM
Integrated Pest Management
IRRI
International Rice Research
Institute
IWMI
International Water Management
Institute
MINAG
Ministry of Agriculture
Ministério da Agricultura
MCT
Ministry of Science and
Technology
Ministério da Ciência e Tecnologia
MISAU
Ministry of Health
Ministério da Saúde
MOPH
Ministry of Public Works and
Housing
Ministério das Obras Públicas e
Habitação
msl
Meters above sea level
v
Faculdade de Agronomia e
Engenharia Florestal
Instituto de Investigação Agrária de
Moçambique
NAPA
National Action Plan to Adapt to
Climate Change
NGOs
Non-Governmental Organization
OP/BP
Operational Policy/Bank Policy
PEDSA
Strategic Plan for the Agricultural
Development
PMP
Pest Management Plan
PNGA
National Environnemental
Management Program
PQR
Resettlement Policy Framework
Política Quadro de Reassentamento
QGSA
Environmental and Social
Management Framework
Quadro de Gestão Sócio-Ambiental
RAP
Resettlement Action Plan
RCdL
Regional Centers of Leadership
RCoLs
Regional Centers of Leadership
R&D
Research and Development
RU
Registration Unit
SADC
Southern African Development
Community
SAR
Sodium Absorption Rate
SDPI
District Services of Patrimony and
Infrastructures
SESIA
Simplified Environmental and
Social Impact Assessment
SPA
Provincial Services of Agriculture
Serviços Provinciais de Agricultura
SPER
Provincial Services of Rural
Extension
Serviços Provinciais de Extensão
Rural
TA
Technical Assistance
TBD
to be determined
TDS
Total Dissolved Solids
ToR
Terms of Reference
UASMA
Social Affairs and Environmental
Unit
Unidade de assuntos ambientais e
sociais
UEM
Eduardo Mondlane University
Universidade Eduardo Mondlane
vi
Centro Regional de Excelência
Serviços Provinciais de Património e
Infraestruturas
UNCCD
UN Convention on Combating
Desertification
UNFCCC
United Nations Framework
Convention on Climate Change
WHO
World Health Organization
vii
EXECUTIVE SUMMARY
Introduction
The Government of Mozambique has requested World Bank financing for the
Agriculture Productivity Program in Southern Africa (APPSA). The Project Development
Objective of APPSA is to improve the availability of agricultural technologies within and
across SADC countries and will be implemented in Malawi, Mozambique and Zambia.
APPSA will pursue this objective by: (i) establishing Regional Centers of Leadership
(RCoLs) on commodities of regional importance, thereby allowing regional
specialization around priority farming systems and more strategic investment in
agricultural research capacity; (ii) supporting regional collaboration in agricultural
training and dissemination; and (iii) facilitating increased sharing of agricultural
information, knowledge and technology across boundaries of participating countries.
Overall responsibility for APPSA will lie with the National Agrarian Research Institute
(IIAM) of the Ministry of Agriculture (MINAG) which will have responsibility of
implementing, coordinating and managing activities in the different areas of research and
development. The project will be implemented over a six-year period as part of which an
Regional Centre of Leadership (RCoL) will be established around Quelimane in
Zambézia Province, and technology generation and dissemination activities will be
implemented in the RCoL and other Satellite research stations of Umbelúzi, Chóckwe,
Nampula and Sussundenga. On-farm trials will also be carried out in areas adjacent to
the research station, though these are currently not selected.
The activities supported under APPSA are expected to have both positive and adverse
social and environmental impacts thus triggering World Bank’s safeguard policies. This
Environmental and Social Management Framework (ESMF) outlines the process and
procedures to be followed for mitigating the adverse social and environmental impacts of
activities financed under APPSA. In accordance with the World Bank Policy (OP 4.01
Environmental Management) and the Mozambican legislation (Decree 45/2004) the
project is a Category B and thus this ESMF has been prepared.
The objectives of the ESMF are to:





Establish clear procedures and methodologies for the environmental and social
assessment, review, approval and implementation of investments to be financed
under APPSA;
Specify appropriate roles and responsibilities, and outline the necessary reporting
procedures, for managing and monitoring environmental and social concerns
related to project investments;
Determine the training, capacity building and technical assistance needed to
successfully implement the provisions of the ESMF;
To establish the project funding required to implement the ESMF requirements;
and
Provide practical information resources for implementing the ESMF.
viii
Project description
APPSA support to Mozambique will be through an International Development Agency
(IDA) credit of USD 30million with a national counterpart contribution of USD
2.2million. APPSA in Mozambique includes three components: (1) Technology
Generation and Dissemination; (2) Strengthening Regional Centers of Leadership; and (3)
Coordination and Facilitation.
Component 1: Technology Generation and Dissemination. Component 1 will finance
technology generation and dissemination activities associated with the commodity or
commodity group1 being targeted by RCoLs, through collaborative regional R&D
projects.
Component 2: Strengthening Regional Centers of Leadership. This component will
support core national capacity building activities taking place within the RCoLs and will
be driven primarily by the specific needs of each RCoL. Investments in Mozambique will
support capacity strengthening, primarily within the Instituto de Investigação Agrária de
Moçambique (IIAM), but also in the Ministry of Agriculture (MINAG), the Faculty of
Agronomy (UEM) and the Ministry of Science and Technology (MCT). To strengthen
the capacity of the rice program, IIAM proposes to establish a new research facility
around Quelimane in the Zambezia province of central Mozambique.
Component 3: Coordination and Facilitation. This component will finance three main
types of activities: (i) research coordination at the national level (to be done by
coordination units or teams established in the various implementing agencies); (ii)
research facilitation at the regional level by CCARDESA (for example, planning and
implementation of regional research and training activities, as well as dissemination of
information among the participating countries); and (iii) policy analysis and dialogue to
assess what policies are needed to facilitate technology generation and dissemination
activities within the region.
Components 1 and 2 raise the principal safeguards issues associated with the project, and
thus the ESMF focuses specifically on these components. Under component 1 seven
research priorities are defined: Genetic diversity of Rice; Rice improvement; Agronomy,
Water and Production Systems Management; Agricultural Mechanization; Post Harvest
Technologies; Socio economic studies, market search and impact evaluation; Innovation
and technology development. Under Component 2, several infrastructures will be
renovated, rehabilitated or built.
Under APPSA, the types of sub-projects that may be financed include: Increased area of
rice production, Construction of small Agro-processing facilities, Construction and/or
rehabilitation of small irrigation schemes, Rehabilitation of access roads, Use of
agriculture machinery, Testing of different technologies (land preparation, water and soil
1
Research may target the commodity itself, or the larger farming system within which that commodity is
produced.
ix
conservation, pest control, etc), Construction and/or rehabilitation of infrastructures such
as laboratories, agro-processing facilities, seed storage, etc.
Baseline information on project targeted areas
Targeted areas are located in 5 agro-ecological regions of the country, namely: R1
(Boane- Maputo), R3 (Chockwe-Gaza), R4 (Sussundenga-Manica), R5 (Namacurra and
Nicoadala-Zambezia) and R7 (Nampula-Nampula).
World Bank Safeguard Policies
World Bank OP 4.01 (Environmental Assessment), OP 4.09 (Pest Management) OP 4.12
(Involuntary Resettlement) and possibly OP 4.04 (Natural Habitats), are triggered by the
proposed Project. The ESMF provides practical tools for preparing and/or implementing
Environmental and Social Management Plans (ESMPs), Pest Management Plans (PMPs)
and Resettlement Action Plans (RAPs). Preparation of the latter is described in a separate
document, the Resettlement Policy Framework (RPF).
Legal and Institutional Framework for Environmental Management in
Mozambique
Relevant legislations in Mozambique that are pertinent for APPSA include the following:
 The National Environment Management Program
 National Action Plan to Adapt to Climate Change (NAPA)
 The Environmental Law
 ESIA Regulation
 Environmental Quality Standards and Effluents Emissions Regulation
 Pesticide Regulations
 Land Policy
 Land Law
 Water Policy
 Biosafety Regulation
The ESIA regulation (Decree 45/2004) defines three categories of projects: Category A
(full ESIA required), Category B (Simplified ESIA is required) and Category C (exempt
from an ESIA). These are broadly in agreement with World Bank categories. Pesticides
Regulations were passed in September 2002 and regulate the use of pesticides in
Mozambique. These should be closely adhered to for any subproject that contemplates
pest management.
Potential environmental and social impacts and mitigation measures
While the actual project sites and subprojects to be supported are not known, the potential
impacts presented in the ESMF are based on field visits and consultations undertaken and
serve as a guideline for a thorough assessment once the sites and subprojects have been
selected.
The proposed project is a Category B project as all identified potential impacts for the
sub-projects are site-specific; few if any of them are irreversible; and in all cases
mitigation measures can be readily designed. However, the consultant recommends that
APPSA avoid sensitive areas and observe the 350 ha threshold of Mozambican EIA
x
Regulation (Decree 45/2004) for irrigation sites to ensure that sub-projects stay within
category B (for details refer to Chapter 6).
Although some negative impacts are expected from this project, there are also significant
positive impacts that would counteract the negative ones. The positive impacts include:
improved income of the participating farmers, improved food security at household level,
improved rice crop agronomic practices and technologies, and improved rice varieties
that are adapted to different climatic conditions.
Potential adverse impacts include:
 hydrologic: changes to the low flow regime, altering the hydrologic flux,
sedimentation of rivers and streams lowering the water table, waterlogging,
increased pollutant concentrations, Agrochemical pollution, Anaerobic effects
(methane emission from large rice paddies and euthrophication of water bodies
from over-supply of nutrients).
 edaphic: soil salinity, erosion, compaction increased in intensity of human activity
in areas surrounding the scheme, altered river morphology, damage to channel
structures due to erosion and sedimentation.
 biological: Caused by changes of land and water uses. Effects on rare and
endangered species and aquatic habitats should be considered.
 socio-economic: conflicts related to land rights/uses, increased population
densities; reduced income due to several factors; Human migration to the
development area, effects on human health, effects on cultural property, issues
related to involuntary resettlement and gender related effects.
Mitigation measures to address the adverse impacts and enhance positive impacts have
been identified in the ESMF.
Sub-project Preparation, Appraisal, Approval and Monitoring
The Ministry for the Coordination of Environmental Affairs (MICOA) is responsible for
cross-sectoral environmental (and social) management. Provincial Directorates for the
Coordination of Environmental Affairs (DPCA) will have a key role in the appraisal and
approval of subprojects supported under APPSA to ensure compliance with Mozambican
environmental legislation and the safeguards outlined in the ESMF. Both MICOA/
DNAIA should be part of the Consultation Forum within APPSA implementation
arrangements, but the Directorate of Agronomy and Natural Resources (DARN) within
IIAM should be responsible for this ESMF implementation.
The completed ESMF checklist along with any additional planning reports [e.g. ESMP,
RAP, and PMP] will be forwarded together with the overall application to the review
authority (SDAE/SDPI) for pre-approval. For most of the sub-projects under APPSA,
final approval will be provided by the DPCA and the Consultation Forum of which
MICOA is suggested to be included as a member. DPCA will issue the environmental
(and social) license to categorize all sub-projects. Before issuing of the environmental
(and social) license the WB will have to give the final approval to any sub-project.
xi
In accordance with the new World Bank Policy on Public Disclosure of Information,
additional reports such as ESMPs, RAPs and PMPs will be made available for public and
private review at a places easily accessible to local people.
Projects implementation and monitoring will be carried out by IIAM and jointly with the
communities assisted by extension workers. District authorities (SDAE/SDPI) assisted by
DPCA and/or APPSA funded technical assistance will prepare annual monitoring reports
that include information on the implementation of the ESMF. DPCA is required to
conduct annual inspections for all category B projects.
Annual reviews of the implementation of the ESMF will be carried out by an independent
local consultant, NGO or other service provider that is not involved in APPSA, but the
approval must be done by the consultation Forum and the WB. Independentlycommissioned tri-annual environmental auditing should be carried out.
The consultant proposes that successful incorporation of environmental safeguards
depends on: 1. The preparation, appraisal and approval process detailed in the ESMF
must be an integral part of APPSA Operations Manual; 2. Training, capacity building and
technical assistance must be provided at all levels from the community level to project
management level; 3. Annual and mid-term review must fully evaluate compliance with
the ESMF and the Operations Manual.
Guidelines for environmental and social management plan and monitoring
requirements
The additional management actions may include the preparation of Environmental and
social Management Plans (ESMPs), Pesticide Management Plans (PMPs) and
Resettlement Action Plans (RAPs).
Guidelines for the preparations of ESMPs are provided. A comprehensive PMP is
presented as a standalone document. A separate Resettlement Policy Framework (RPF)
has been prepared for use in conjunction with the ESMF and this provides guidelines for
the preparations of RAPs. Technical expertise and funds will be provided for the
preparation of specialist reports as required.
Training and Capacity Building
Training and capacity building is the key to the successful implementation of the ESMF
and the RPF. The objective of the training is to:
 Train IIAM, extension teams and communities to identify, prepare, implement
and manage the environmental and social aspects of their subprojects.
 Ensure that district, provincial and national level officials have the capacity to
appraise, approve and supervise the implementation of subprojects.
Three levels of training are proposed namely: awareness raising, sensitization and indepth technical training. In any case it will mostly be conducted through workshops and
refresher courses. Training will include case studies of actual sub-project interventions
using the environmental checklist and visiting sites. The focus of the training will mainly
xii
be IIAM, selected farmers and extension officers who will in turn train community
members to implement components of the ESMF at the community level.
Appropriate training and assistance will also be provided for district, provincial and
national level agencies. Technical assistance under the project will support IIAM,
extension teams and communities to implement the ESMF including the preparation of
ESMPs, PMPs, and RAPs.
ESMF monitoring requirements
Indicators of ESMF implementation are: Number of national, provincial, district level
staff trained in implementation of this ESMF; Number staff attending training course in
ESIA and ESMF implementation; Number of sub-projects correctly submitted for
approval; Number of mitigation measures implemented; Number of written warnings of
violation of ESMPs issued to project proponents; Number of recommendations from the
Audit that have been implemented; Number of performance contracts signed between
IIAM and farmers.
These indicators should be integrated into APPSA’s Monitoring and Evaluation (M&E)
system to guarantee that the ESMF will be implemented in full.
ESMF Implementation Budget
The budget includes funds for:
 Institutional development activities;
 The training program for communities and extension teams and local authorities
to implement the ESMF;
 Allowances for the preparation and/or implementation of sub-projects ESMPs,
RAPs, etc. The costs of implementing these plans are included in the sub-projects
budgets;
 Annual reviews and tri-annual audits;
 PMP implementation and monitoring.
The overall budget for implementation of the ESMF is estimated at US$ 1,408,000.
xiii
1. INTRODUCTION
This Environmental and Social Management Framework (ESMF) outlines the process
and procedures to be followed for activities financed under the Agriculture Productivity
Program for Southern Africa (APPSA) that has the potential to trigger some of the World
Bank safeguard policies. The Project Development Objective of APPSA is to improve the
availability of agricultural technologies within and across SADC countries and will be
implemented in Malawi, Mozambique and Zambia. APPSA will pursue this objective by:
(i) establishing Regional Centers of Leadership (RCoLs) on commodities of regional
importance, thereby allowing regional specialization around priority farming systems and
more strategic investment in agricultural research capacity; (ii) supporting regional
collaboration in agricultural training and dissemination; and (iii) facilitating increased
sharing of agricultural information, knowledge and technology across boundaries of
participating countries.
The ESMF covers the activities to be undertaken for technology generation and
dissemination activities associated with Rice in the case of Mozambique, and those
related to supporting the core national capacity building activities taking place within the
Regional Centre of Leadership (RCoL) for Rice Research in Mozambique. APPSA intends
to generate technological solutions to increase production and productivity and added
value for the rice crop in Mozambique and in Southern Africa, thus contributing to the
improvement of food diet, family income and to reduce the burden on rice imports. The
National Agrarian Research Institute (IIAM) is the agency responsible for implementing
the APPSA including the provisions of this ESMF.
APPSA for Mozambique is based on main guiding documents for the country’s economic
development such as the Strategic Plan for the Agricultural Development (PEDSA, 2010
– 2020) and the Strategy for the Development of the Rice Sector in Mozambique (EDA,
2005). The principles of PEDSA are consistent with the pillars and principles of the
Comprehensive Africa Agriculture Development Programme (CAADP) and it is,
therefore under its context that Mozambique will implement CAADP. APPSA also seeks
to improve natural resources management, which is the basis to achieve economic growth
and poverty reduction in Mozambique as well as to reduce vulnerability to ongoing
climate changes and rising food prices.
APPSA intends to promote regional approaches for technology generation and
dissemination through the support, reinforcement and dissemination for commodities of
regional importance and benefit. In Mozambique it is expected that the APPSA plays a
role of leadership in regional initiatives for rice research, it is connected to the global
research system with capacity to establish regional partnerships and provides a crucial
contribution to strengthening and improving the national agricultural research system.
The RCoL in Mozambique will establish linkages with other CoL located in the APPSA
participating countries (Malawi: Maize and Zambia: Legumes) in aspects of training and
sharing of knowledge and technologies of regional relevance.
1
The project will be implemented over a six year period and the RCoL will be established
around Quelimane, Zambézia Province, which will have responsibility of implementing,
coordinating and managing activities in the different areas of research and development.
As part of organic functional structure of IIAM, the activities of APPSA will be
undertaken through the Zonal Research Centers of IIAM (South, Centre and Northeast).
This ESMF is prepared because the actual sites on Research stations and those for onfarm trials will not be known by project appraisal, and, therefore, site specific issues
would not be determined. The ESMF thus provides a uniform approach for addressing all
potential negative environmental and social impacts, and to provide enhancement
measures for positive impacts.
The main purpose of the ESMF is to:





Establish clear procedures and methodologies for the environmental and social
assessment, review, approval and implementation of investments to be financed
under APPSA;
Specify appropriate roles and responsibilities, and outline the necessary reporting
procedures, for managing and monitoring environmental and social concerns
related to project investments;
Determine the training, capacity building and technical assistance needed to
successfully implement the provisions of the ESMF;
To establish the project funding required to implement the ESMF requirements;
Provide practical information resources for implementing the ESMF.
2. PROJECT DESCRIPTION
2.1. Project Development Objectives and Principles
The development objective of APPSA in Mozambique is to enhance the national and
regional specialization in agricultural research and technology dissemination for the rice
crop, to enhance the regional collaboration in training and dissemination and to facilitate
increased sharing of agricultural information, technologies and knowledge beyond
borders of other APPSA participating countries.
From the RCoL in Mozambique it is expected that APPSA contributes in such a way that,
in a long term perspective, an increase in the adoption of improved agricultural
technologies for all the APPSA participating countries is reached, as measured through
the increase in the adoption of improved varieties, technologies and better methods of
agro processing and handling. It is also expected that the support from APPSA to the
RCoL in Mozambique results in an increase of national income due to increased rice
production and domestic marketing, and contributes substantially to the reduction of rice
imports and, in this way, to the stability in the country’s balance of payments.
2
2.2. Project Components
APPSA support to Mozambique will be through an International Development Agency
(IDA) credit of USD 30million with a national counterpart contribution of USD
2.2million.
APPSA in Mozambique includes three components: (1) Technology Generation and
Dissemination; (2) Strengthening Regional Centers of Leadership; and (3) Coordination
and Facilitation.
Component 1: Technology Generation and Dissemination. Component 1 will finance
technology generation and dissemination activities associated with the commodity or
commodity group2 being targeted by RCoLs. All activities financed under Component 1
will be undertaken through collaborative R&D projects involving the participation of at
least two countries. R&D projects will focus on topics that provide solutions to regional
problems. R&D projects will support research, technology dissemination, training, and
other activities (e.g., knowledge exchange) that will contribute to enhanced regional
collaboration. The proposal for each R&D project will identify a clear objective or
specify a well-defined hypothesis and describe a detailed set of activities that will be
carried out within a defined time frame and budget. It will outline the collaborative
implementation arrangements, detailing the roles responsibilities of the institutions
involved and the participating staff. It will include also a results framework that is
aligned with the RCoL results framework, as well as an explanation of how performance
indicators will be monitored. Every R&D proposal will include a set of activities
designed to ensure that technologies generated through APPSA enter the dissemination
system and are made available to farmers and other end users.
R&D projects will be developed through the following process: (i) for each commodity
being targeted by APPSA, priorities will be identified at national level; (ii) for each
commodity being targeted by APPSA, regional planning meetings will be convened by
CCARDESA to facilitate the identification of regional research and dissemination
priorities and preparation of associated sub-project proposals; (iii) a peer review process
facilitated by CCARDESA will provide feedback on the relevance and quality of subproject proposals; and (iv) sub-project proposals will be confirmed and implemented at
national level.
Technology Generation Priorities. Each APPSA participating country will support
research relating to the commodity or commodity group being targeted by the RCoL that
they are hosting, as well as research relating to the commodities or commodity groups
being targeted by RCoLs in other APPSA participating countries. Each country is
expected to devote the largest share of its research funds to activities related to the
commodity or commodity group being targeted by the RCoL that it is hosting, but a
portion of the IDA funds will go to support research on commodities or commodity
groups being targeted by RCoLs hosted by other APPSA participating countries.
2
Research may target the commodity itself, or the larger farming system within which that commodity is
produced.
3
Research priorities are expected to cover the full range of issues associated with the
commodity or commodity group, including germplasm collection and characterization,
germplasm improvement (plant breeding), crop management, and post-harvest activities
including processing and storage.
Technology Dissemination Priorities. The second sub-component will support technology
dissemination through a range of activities that link RCoLs to institutions within and
across countries to enable scaling up of innovations. Technology generation and
dissemination activities will target participation from a range of institutions, in line with
FAAP principles of pluralism, and they will aim to strengthen linkages between
researchers, extension and end users. Although APPSA is not intended to be a fullfledged dissemination or extension program, it is expected to play an important role in
improving and scaling up the technical content, information, and knowledge available
within the dissemination system.
Technology dissemination activities supported by APPSA could be expected to focus on:

Improving the content and accessibility of technology messages and
knowledge products around maize, food legumes or rice technologies, including
the use of information and communication technologies;

Improving the capacity of advisory service providers through technical
training of lead farmers, extension agents and private or civil society advisory
service providers;

Strengthening the capacity of dissemination officers or technology transfer
experts within research institutes to enable them to engage more with farmers,
extension agents and advisory service providers;

Establishing or improving platforms for farmer, private sector and civil
society dialogue and consultation around technology priorities;

Improving farmer-research-extension feedback mechanisms to obtain a
better analysis of farmer preferences;

Regional information sharing and exchange activities with other
participating countries;

Research on technology dissemination methods or tools, including those
targeting gender specific issues such as household nutrition and food safety.
APPSA will also support technology multiplication activities by RCoLs to improve the
availability of materials for further scaling up by private sector or civil society. This will
include seed multiplication at the level of breeder/pre-basic and basic seed production
within the research system or initial production in the case of farm implements or
machinery.
Component 2: Strengthening Regional Centers of Leadership. This component will
support core national capacity building activities taking place within the RCoLs and will
be driven primarily by the specific needs of each RCoL. In general APPSA will support:
(i) upgrading of research infrastructure including physical infrastructure and equipment;
(ii) improving management and performance systems including knowledge and
4
information systems; (iii) developing human capital including by providing scientific
training at the post graduate level and upgrading skills through short courses or targeted
training; and (iv) strengthening seed, regulatory and related services.
Mozambique: Investments in Mozambique will support capacity strengthening, primarily
within the Instituto de Investigação Agrária de Moçambique (IIAM), but also in the
Ministry of Agriculture (MINAG), the Faculty of Agronomy (UEM) and the Ministry of
Science and Technology (MCT). To strengthen the capacity of the rice program, IIAM
proposes to establish a new research facility around Quelimane in the Zambezia province
of central Mozambique. With the help of analysis undertaken by IIAM, potential sites in
Nicoadala and Namacurra districts have been identified based on proximity to rice
production clusters, accessibility, water quality, and level of investment needs. The
preferred site is the location where the rice program is currently undertaking field testing
and laboratory analysis in a temporary space. Further feasibility assessments—including
a detailed hydrological assessment—are needed to determine which of the potential sites
is most appropriate to develop a full-fledged facility. The size of the new facility will
expand the area available for field testing and multiplication to approximately 50
hectares.
APPSA financing will also be used to build laboratory analytical capacity in soil, water
and plant analysis; biotechnology; seed quality; Geographic Information System (GIS)
and simulation modeling; agro processing and storage; pests and diseases identification;
and grain physical and chemical analysis. The RCoL will be staffed with scientists
recruited from the CGIAR system, IIAM, and private firms, but gaps have been identified
in the areas of molecular biology, agronomy (soil, water and environment),
mechanization and agro-processing, and economy, extension, sociology and rural
innovation. APPSA will finance post graduate training at the MSc and PhD levels.
Because IIAM has relatively few scientists operating within its headquarters and zonal
structures APPSA financing could also be used to finance new research staff on
consulting contracts. Measures to transition these positions to the IIAM budget, however,
would begin early during implementation. APPSA financing may initially fund 100
percent of newly recruited research staff, but cost sharing measures would be introduced
quickly, and by Project closing the salaries of staff will be paid entirely by Government.
Component 3: Coordination and Facilitation. This component will finance three main
types of activities: (i) research coordination at the national level (to be done by
coordination units or teams established in the various implementing agencies); (ii)
research facilitation at the regional level by CCARDESA (for example, planning and
implementation of regional research and training activities, as well as dissemination of
information among the participating countries); and (iii) policy analysis and dialogue to
assess what policies are needed to facilitate technology generation and dissemination
activities within the region.
National Level Coordination and Management: APPSA financing will be provided at the
national level to pay for costs related to the coordination of national and regional aspects
of the Project (travel, meetings); management and administration costs (including
consultants or staff where gaps exist); and national level monitoring and evaluation.
5
Regional Facilitation by CCARDESA: At the regional level, the Project will finance
regional facilitation activities including: (i) regional planning, monitoring and evaluation
activities needed to establish and monitor regional collaborative activities; and (ii)
regional exchange of information, knowledge and technologies. CCARDESA will play
an important role in facilitating the development of collaborative research sub-projects, as
well as in facilitating peer review and quality control. Financing for the regional
facilitation function will be sourced from each participating APPSA country on the basis
of a work plan and budget envelope agreed at appraisal stage.
R&D Policy Analysis and Dialogue: APPSA financing will support analytical work,
needs assessments, and policy dialogue or policy harmonization activities on key areas
that affect R&D at national and regional level. This includes issues such as intellectual
property rights, progress the implementing the SADC common seed certification system
or biosafety regulations.
Support for SADC Regional Seed Regulatory System. SADC is currently in the process
of rolling out its harmonized seed regulatory system, which is expected to (i) strengthen
systems and structures for seed inspection, testing, and certification across the region; (ii)
establish a regional variety release catalogue; and (iii) strengthen alignment of national
seed systems to SADC harmonized seed policy. APPSA investments in Component 2 at
the national level are expected to support the national seed authorities in Malawi,
Mozambique, and Zambia in building their capacity and aligning national legislation and
regulatory systems to the harmonized regional system. Additional support may be
provided under Component 3 at the regional level for support by the SADC Seed Center
in facilitating these activities, particularly in technical assistance and capacity building;
information and knowledge management; and addressing policy gaps in intellectual
property rights.
APPSA support for regional activities related to seed will be channeled through
CCARDESA. It will reflect the priorities identified in the five-year strategic plan for the
SADC Seed Center, which is currently in draft form, but which is expected to be
validated and endorsed in early to mid-2013.
Components 1 and 2 raise the principal safeguards issues associated with the project.
Taking into consideration the regional nature of APPSA, the main research
themes/priorities take into consideration the following aspects: a) the strategic importance
of rice in Mozambique to balance the country imports and exports (PEDSA), b) regional
(CCARDESA) and Global Priorities on Research and Development of Rice in Africa and
the World, and c) the common rice research needs identified for the three countries
participation in the APPSA programme. The seven research priorities defined for the
APPSA in Mozambique are:
1. Genetic diversity of Rice in the Country
Objective: collect, characterize, register, manage and conserve genetic pool of the rice
crop as means of protecting local genetic diversity. Main results to be achieved with this
research theme are:
a) Germplasm collected;
6
b) Country local germplasm diversity collected, characterized, mapped and
registered;
c) Gene banks for conservation and dissemination created;
d) Genetic diversity for the relevant characteristics for rice breeding studied.
2. Rice improvement
Objective: Accelerate the development, availability and adoption of more productive
varieties of high quality and nutritive value and adapted to biotic and a-biotic factors.
Main results to be achieved with this research theme are:
a) Varieties adapted to different production systems, with the cooking qualities
demanded by the local and regional market (aromatic, long grain, translucent,
intermediate amylase content, high head rice recovery) developed;
b) Varieties for intensive production systems developed;
c) Hybrids for commercial farming developed;
d) More healthy and nutritive varieties developed;
e) Varieties tolerant to diverse biotic and a-biotic factors (pests and diseases, water
stress, thermal regime, salinity/sodicity and other toxicities) and adapted to
climatic changes developed;
f) Varieties with wide regional adaptation developed;
g) Breeder seed produced and maintained.
3. Agronomy, Water and Production Systems Management
Objective: Develop strategies, crop practices and high productivity technologies taking
into account the sustainable management of different rice production systems.
Main results to be achieved with this research theme are:
a) Sustainable rice production systems that are profitable, efficient and viable for
specific local production conditions developed;
b) Efficiency of water use in the rice fields improved;
c) Integrated soil fertility and water management for the specific conditions of each
location (irrigated and rain fed rice) developed;
d) Crop practices and measures of control conducive for high productivity of
irrigated and rain fed rice (direct seeding/transplanting, dates of
seeding/transplanting, population density, fertilizer, pest control, diseases and
weeds) identified and tested;
e) Land preparation technology aiming at better water soil fertility management and
weeds control improved;
f) Conservation Agriculture technologies for upland production ecosystems tested;
g) Impact of climatic changes expected in the rice production systems studied;
h) Agriculture practices and mechanisms that allow to increased capacity of
adaptation to climatic variability and changes developed and tested.
4. Agricultural Mechanization
Objective: Develop and test appropriate machineries and agricultural implements to
support the different activities of the rice production cycle. Main results to be achieved
with this research theme are:
7
a) Machineries and agricultural tools of different technology levels for pre harvest
operations developed and tested;
b) Machineries and agricultural tools of different technology levels for post harvest
operations developed and tested;
c) Local artisans and operators for operation and maintenance of appropriate
agricultural equipment for rice crop production, trained.
5. Post Harvest Technologies
Objective: Add value to rice post harvest products, through improvement of quality, more
innovative and efficient processing, access to markets and development of new products
based on rice. Main results to be achieved with this research theme are:
a) Technologies and business models for rice post harvest products in order to
increase the post harvest revenue, the product quality and its market value
developed;
b) Other food products based on rice developed;
c) Innovative uses for rice byproducts (straw, husk and bran) developed;
d) Packaging for a more attractive display in the market improved.
6. Socio economic studies, market search and impact evaluation
Objective: Understand, characterize and evaluate existing farming systems and identify
the needs for products and technology development that satisfy farmers and market needs
in order to enhance their impact. Main results to be achieved with this research theme are:
a) Social economic organization forms that maximize the productivity and farmers
income studied;
b) Socio economic studies in different rice production regions to identify and
evaluate the technological needs for farmers and consumers realized;
c) Market studies to quantify the rice demand (types, tastes and quality, new
products derived from rice, use of byproducts and residues and its degree of
quality) realized;
d) Strategic vision for research and development priorities for each period
established;
a) Impact of research in the development of rice crop evaluated;
b) Contribution of innovations for the country balance of payments, for Mozambique
and other APPSA participating countries, evaluated;
c) Data base on research results and technological advancements with the rice crop,
which can be used at national and regional level, produced.
7. Innovation and technology development
Objective: Support the development of the rice sector in Mozambique and in the Region,
through the research and development achievements and impacts of APPSA. Main results
to be achieved with this research theme are:
a) Innovative tools for training and communication produced;
b) Technology extension and dissemination capacity developed;
c) Sustainable and user friendly Rice technology packages developed;
8
d) Effective systems for wide scale adoption of sustainable and viable technologies
for rice production, agro-processing and added value, for the country and the
region, established.
For the implementation of the above mentioned research thematic areas there will be
need to create specialized and support services such as laboratories, green houses and
other technological instruments to allow an effective rice research and development in the
context of the objectives established for the APPSA. The following support services are
previewed:
a)
b)
c)
d)
e)
f)
g)
h)
Soil, water and plant analysis,
Biotechnology products,
Quality control and seed maintenance,
Use of GIS and simulation models,
Agro-processing and storage,
Identification of pests, diseases and weeds,
Chemical and physical analysis of the rice grain,
Meteorology: collection, processing and data analysis.
These specialized services, apart from their primary function to support rice research and
development, can also play an important role in service provision, in terms of analysis,
diagnosis and recommendations for other agricultural commodities and entities, either
public or private, and therefore be a source of revenue for the RCoL.
2.3. Anticipated sub-Project types under APPSA
Under the context of APPSA the following sub-projects may have an impact on the
biophysical and social environment. Potential impacts from these sub-projects are
identified in Chapter 8.
9
Table 1. Potential Sub-projects to be financed by APPSA
Sector
Water supply
Sub-projects with potential negative
environmental and social impacts


Transportation
Agriculture and
market





Infrastructures

Construction/rehabilitation of
small dams or weirs
Rehabilitation and/or
construction of small- scale
irrigation and drainage systems
Rehabilitation of access roads
Increased area of rice
production
Construction of small Agroprocessing facilities
Use of agriculture machinery
Testing of different
technologies (land preparation,
water and soil conservation,
pest control, etc)
Construction and/or
rehabilitation of infrastructures
such as laboratories, agroprocessing facilities, seed
storage, etc
Sub-projects with potential
positive environmental and
social impacts
 Construction of flood
and drainage related
infrastructure



Promote improved
agriculture technologies
Promote conservation
agriculture
Promote IPM approach
3. PROJECT IMPLEMENTATION ARRANGEMENTS
3.1. Regional implementation mechanisms
Because APPSA is a regional program, implementation will be based on partnerships and
collaboration among the participating countries. Countries will work together in a number
of ways: (i) by undertaking joint technology generation, dissemination, and training
activities through research sub-projects; (ii) by coordinating their respective national
activities to achieve a shared regional objective; and (iii) by sharing knowledge and
technological outputs from their national programs throughout the region. To the extent
possible, APPSA implementation will rely on existing regional platforms, networks, and
partnerships to share information and create opportunities for collaboration.
3.2 National Implementation mechanisms
The proposed organization and structure takes into consideration that the RCoL is a
research centre established within the framework of IIAM, with responsibilities for
scientific research at national and regional level. In its regional responsibility, the RCoL
has a straight linkage with CCARDESA and other regional RCoLs.
Taking into account the limitations in human resources in the current rice research
program within IIAM, the organizational structure proposed considers the need for the
establishment of partnerships that can complement the available capacity. It is also
10
proposed that the RCoL puts in place implementation mechanisms based in partnerships
and collaborative programs with other research and academic institutions at national,
regional and international level.
Figure 1 illustrates the organizational structure of APPSA in Mozambique whose
implementation will be supported by APPSA. In terms of institutional arrangements for
APPSA, IIAM will be the implementing agency which is an autonomous entity under
MINAG.
MINAG will have the responsibility of political guidance and general supervision to
APPSA and will be supported by a consultative and advisory Forum for decision making.
Several relevant institutions concerned with rice (government, private sector, research
and academic institutions) will be part of the consultative and advisory Forum. This
Forum will give attention to issues of strategic guidance for the institutional agenda, will
appreciate the relevance of results achieved and propose measures for strategic
reorientation of research priorities and dissemination, approaches and methodological
principles. The operation of this Forum will be guided by Terms of Reference to be
developed and the professionals representing different institutions involved will be
appointed on the basis of professional and technical experience and competence with the
rice crop.
It is advised that this Forum integrates a representative from either the Ministry for
Coordination of Environmental Affairs (MICOA) or MINAG’S Environmental Unit. This
will guarantee decision making on environmental and social issues at Project’s level.
IIAM will have the responsibility of coordination and management of APPSA with
respects to the establishment and implementation of rice research and development
activities in the RCoL. Within IIAM the Directorate of Agronomy and Natural Resources
(DARN) is the unit responsible for implementation of the provisions of this ESMF. The
current presence of several CGIAR institutes within IIAM premises constitutes one of the
strong points of national research system and an opportunity for the establishment of
specific partnerships for specific research areas.
11
MINAG (PEDSA)
Supervision and Policy
Orientation
CCARDESA –
Board of
Directors
Consultation Forum (MINAG,
MCT, MIC, UEM-FAEF, Private
Sector)
Consultation and Advice
CGI
AR
FARA
IIAM
Management, Coordination,
Research and Dissemination
CCARDESA - Executive
Secretariat
Regional coordination,
training, technology transfer
and sharing of knowledge
Center of Leadership (CoL)
IIAM – Zambezia (CoL Headquarters)
Implementation and Coordination of Activities
Plant breeding, Agronomy, Soil and Water
Management, Agro processing, Mechanization,
Socioeconomics, Training and Dissemination,
Support Services
Research network, incl. possible partnerships with
national, regional and international inst and networks
Extention
Services
Technology
dissemination
Rice
Producers
and Rice
Producers
Organization
s
Private
Sector
Rice value
chain actors
Training
institutions
Training and
students
internships
IIAM
Central Research Centre (Nicoadala site)
 Rainfed lowland rice
Southern Research Centre (EAChokwé, EA
Umbeluzi)
 Irrigated rice
Northeast Research Centre (PA Nampula)
 Upland and rainfed lowland rice
Other CoL
commoditi
es
Malawi
(Maize)
Zambia
High Education Institutions
Mechanization, Integrated Pest Management,
Socioeconomics, and biotechnology.
Training Centers (Polytechnics, Agricultural
Schools - Chókwé, Sussundenga, Umbeluzi)
Training of beneficiaries
Treino dos beneficiários
Private Sector
Seed multiplication, Agro processing, markets.
IRRI (CGIAR) – Plant Breeding, Agronomy, Agroprocessing, mechanization.
IWMI (CGIAR) – Water management
IFPRI (CGIAR) – policy analysis
IFDC
Soil fertility management, input markets.
Figure 1: Proposed organization and structure for APPSA in Mozambique
12
At regional level, implementation mechanisms based on partnerships and collaborative
programs among APPSA partner countries will be in the form of a regional facilitation
undertaken by CCARDESA (Centre for Coordination of Agricultural Research in
Southern Africa), through its executive secretariat. The main role of the CCARDESA
secretariat will be the coordination of training, sharing of knowledge and technology
transfer at regional level. IIAM and RCoL will have a direct linkage with CCARDESA in
terms of the regional implementation of APPSA.
The RCoL in Mozambique, with its headquarters in Zambezia Province, will have under
its responsibility the implementation, coordination and management of activities in the
different areas of research and development. As part of organic functional structure of
IIAM, the activities of the RCoL will be undertaken through the Zonal Research Centers
of IIAM (South, Centre and Northeast). For specific research areas where the current
national agricultural research system does not have the required capacity, partnerships
with other research and academic institution at national, regional and international level
will be established. Figure 1 illustrates some of potential partnerships and areas of
research where the RCoL could develop partnerships [universities, training centers,
private sector, CGIAR (IRRI, IWMI, IFPRI) and IFDC].
Other partners/collaborators of RCoL include the Extension Services, Rice Producers and
their organizations, Private sector and Education Institutions. The RCoL will establish
linkages with other RCoL located in the APPSA participating countries (Malawi: Maize
and Zambia: Legumes) in aspects of training and sharing of knowledge and technologies
of regional relevance.
To ensure environmental and social issues are adequately addressed as per the safeguards
policies applicable to the project, the Research Stations will designate one
social/environment specialist from the Provincial Directorate for the Coordination of
Environmental Action (DPCA) to be the contact person for the project; who will
participate in the project meetings at provincial level, join technical project missions, and
provide technical support and guidance on an ongoing basis.
3.1 Organization and internal management system of RCoL
Internally, the RCoL will be organized and structured in order to allow an efficient and
operational management system. Figure 2 illustrates the proposed management system
for the RCoL in Mozambique, which will be structured at three different levels: strategic,
tactical and operational level.
a) The management at strategic level takes into consideration the principles
established in the Strategic Plan for Agricultural Sector Development (PEDSA),
the Strategic Plan of IIAM and strategic priorities at regional level (CCARDESA),
to allow the creation of RCoL institutional agenda for research and development.
Therefore, IIAM and CCARDESA will have the responsibility for the
institutional agenda guidance and its programmatic implementation.
b) Tactical management is meant for the establishment of mechanisms and
procedures to organize the portfolio of research programs and projects according
to the strategic plan, research agenda and development priorities at national and
13
regional level. It is at this level that the necessary synergies will occur and will be
aligned among the core functions of the RCoL (Research and development,
Technology transfer and communication, Institutional development and
Administrative and financial management). At this level, the process of
management and coordination of the different research and development
programs will also take place, supported by a technical and scientific committee.
The technical and scientific committee will be the body in charge to appraise the
scientific and technical merit of different programs and research projects as well
as their relevance and impact (composed by the research program coordinators
and other national and international researchers and academicians invited
according to the theme under evaluation).
c) The operational management includes the organization and operation of different
research and development programs and projects, their units and research teams
including the support and interaction with national and international partners.
14
Orientation and Guidance on National and
regional Priorities
(IIAM and CCARDESA)
Strategic
Level
Institutional Agenda
(CdL)
Institutional
Development
Research and
Development
Communication
and Technology
Transfer
Administrative and
Financial
Management
Tactical Level
Management and Coordination of Research and Development Programs
Scientific and
Technical
Committee
Genetic
Diversity
Rice
Improvement
Agronomy,
Water and
Farming
Systems
Agriculture
Mechanization
Post Harvest
Technology
Socioeconomics
Studies
Innovation
and
Technology
Development
Operationa
l Level
Research network, research units, research teams, support services, partnerships, technical
assistance
Figure 2: Proposed organization and management system for the RCoL.
4. BASELINE INFORMATION ON PROJECT TARGETED AREAS
APPSA will be implemented over a six-year period across 4 candidate IIAM research
stations in northern, central and southern Mozambique. Most likely the research stations
will be located in Namacurra and Nicoadala (Zambézia Province), Sussundenga
(Manica), Nampula (Nampula), Chockwé (Gaza) and Umbelúzi (Maputo) (Figure 3). The
Rice CoL headquarters will be located in Namacurra, where new facilities will be built
15
and experimental land acquired. A number of small-holder farms (to be identified) will
also be involved as on-farm experiments.
Figure 3: Location of APPSA targeted areas
Targeted areas are located in 5 agro-ecological regions of the country, namely: R1
(Boane-Maputo), R3 (Chockwe-Gaza), R4 (Sussundenga-Manica), R5 (Namacurra and
16
Nicoadala-Zambezia) and R7 (Nampula-Nampula). The following environmental
description is based on identified agro-ecological zones (MINAG, 2007).
4.1. Agro-ecological Zone 1 (R1)
The climate in this region is semi-arid dry, with a mean annual precipitation between
500mm (Moamba, Sábié, and Magude) and 800mm (Manhiça, Marracuene, Boane,
Namaacha and Matutuíne), confirming the gradient from the coast to the interior. The
rainfall is concentrated between October/November and March, and is very irregular. The
mean annual temperature varies between 20ºC and 26ºC, being lower along the Libombo
plateau. The potential evapotranspiration varies between 1.400 a 1.500 mm. Low
precipitation and high temperatures imply a water deficiency even during the rainy
season, for most of the region.
The soils are characterized as alluvial and of basaltic origin. Except for the soils in the
Pequenos Libombos Plateux, Moamba and Maputo, Umbeluzi, Sabie and Incomáti river
valleys, the soils are in general sandy to loam-sandy, with good to marginal fertility.
Main activities carried out in R1 are cattle production, which represents 4% of the
national production. Agriculture is carried out all year round, but in small portions due to
erratic rains and soil salinity. The main crops in this area are maize, groundnuts, beans,
cassava, sweet-potato, fruits and vegetables.
Umbelúzi Research Station was visited on December the 10th and the details of
conversations and field observations are presented in Annex XI.
The Umbelúzi Research Station was created in 1909 during the colonial period. With an
extension of 600 ha, the research focus on this station is on: Cereals (maize and rice),
legumes (beans), roots (cassava and sweet potato), and fruits trees. For these crops, IIAM
is researching on new varieties with improved characteristics and cultural/agronomic
practices. The station uses agro-chemicals namely pesticides and fertilizers such as: NPK,
and Urea. There have not been any accidents and/or incidents with the use of agrochemicals and the station has a storage place that is in good condition for safe storage of
the chemicals.
The Station has 117 workers of whom more than 60% belong to the communities around
the station. The workers have the permit to cultivate station’s area, but there is no conflict
with either workers or local communities. There is an experience with on-farm trials but
these are usually located outside Umbelúzi, in areas such as: Manhiça, Marracuene,
Matutuíne and Changalane. The criteria to select an on-farm trial site are: (i) farmer with
minimal conditions to perform the trials (land, tools and interest); and (ii) capacity to
provide extension of the results to other farmers. Depending on the crop and type of
experiment, the on-farm sites may vary from one place to another.
17
4.2. Agro-ecological zone 3 (R3)
R3 is located in southern Mozambique, extending from central to northern Gaza Province
(Chockwe, Guija, Chibuto, Chicualacuala, Massingir and Massangena) and a narrow strip
in the western Inhambane Province (Mabote) up to the Save River. It occupies an area of
75.460 km2, with the lowest human density in the country of 5 inhabitants/km2. Most R3
is located below 200m, but along the Zimbabwe and South-Africa borders the altitudes
reach 200 to 500m.
The climate is semi-arid dry, with mean annual precipitation of between 350 and 800mm,
concentrated between November and February. Potential evapotranspiration is generally
higher than 1500 mm. It is one of the driest places in the country. The mean annual
temperature is higher than 26°C. High temperatures are responsible for water deficiency
higher than 800mm annually, but it exceeds 1100mm in Pafúri. The relative annual
humidity is about 60-65%.
R3 is characterized by relatively poor soils with high salinity. There is a predominance of
fluvic soils along the river valleys. The main rivers are the Limpopo, Elefantes, Changane
and the Save. At certain places rich Mananga soils predominate. Close to the SouthAfrican border, the soils are red, derived from calcareous materials.
Erratic precipitation together with high temperatures limits the production of the main
crops of millet, maize, groundnuts and beans. Cattle production is also important in this
region.
4.3. Agro-ecological zone 4 (R4)
This region is located in central Mozambique and extends through most of Manica
Province (Machaze, Mossurize, Manica, Gondoloa, Chimoio, Macossa and Sussundenga)
and a small portion of central Sofala Province (Chibabava and Gorongosa). To the south
it is limited by the Save River, occupying an area of 64.000 km2 and presenting a human
density of 13 inhabitants/km2.
80% of the region belongs to the gneiss-granitic complex. The altitude varies between
200 to 1000 msl (meters above the sea level).
The climate is dry, with mean annual precipitation between 800 and 1000mm, distributed
between November and March. The potential evapotranspiration is between 1200 and
1400 mm and the mean annual temperature not higher than 24ºC.
The soils are ferrasols to litossols and the hydrographic network is composed of the
following rivers: Save, Buzi, Pungué and Mavuzi, where the soils are alluvial and
hydromorphic.
Main crops in the area include: maize, millet, cassava, beans, rice, and ground nuts; and
other crops grown include cotton, sugar cane, sunflower and tobacco.
18
4.4. Agro-ecological Zone 5 (R5)
R5 is located in central Mozambique along low altitude areas (0-200 msl) in Sofala
(Machanga, Buzi, Nhamatanda, Muanza, Cheringoma and Marromeu) and Zambézia
(Mopeia, Chinde, Inhassunge, Quelimane, Nicoadala, Namacurra, Maganja da Costa and
Mocuba). This is a coastal area that extends from the Save River through the South of
Pebane District in Zambézia. R5 occupied an area of 74.000 Km2 and have a human
density of 22 inhabitants/km2.
The topography is characterized by a smooth relief between 0 and 200 msl; the geology is
characterized by sedimentary rocks from the quaternary and tertiary.
The climate is influenced by the tropical humid savanna climate, with annual mean
precipitation higher than 800mm, but at some places it varies between 1200 and
1400mm, occurring between December and March. The potential evapotranspiration
varies between 1000 and 1400mm and the mean annual temperature ranges between 24
and 26ºC. This creates an appropriate condition for rainfed agriculture.
The predominant soils are fluvissols to arenossols, but letossols and ferrasols are also
found. In general the soils are of high fertility and the freatic level to the surface. The
hydrographic network is composed of the rivers: Buzi, Pungué, Zambeze, Luala and
Licungo.
Main crops in this area are: rice, maize, cassava, millet, beans and tobacco and cotton.
4.5. Agro-ecological Zone 7 (R7)
R7 is the most extensive zone with 234,000 km2 and a human density of 11
inhabitants/km2, between 200 and 500 metres in Zambézia (Morrumbala, Alto Molocue,
Lugela, Ile, Gilé and Namaroi), Nampula (Murrupula, Nampula-Rapale, Ribawé, Lalaua,
Mecuburi and Muecate), Tete (Moatize and Chiuta), C. Delgado (Namuno, Balama and
Montepuez) e Niassa (Mecanhelas, Cuamba, Maúa, Majune, Mecula, Marrupa, Mavago,
Lago, N´gauma, Metarica, Nipepe and Muembe). The altitudes vary between 200 and
1000 metres, with a smooth topography.
The climate is tropical humid of Savanna (Aw) according to the Koppen classification,
with a mean annual precipitation of 1000 to 1400 mm, between November and
March/April, while the potential evapotranspiration is between 1300 and 1500 mm. The
mean annual temperature varies between 20 and 25ºC.
The soils are ferrasols, lixissols and luvissols, with low to medium fertility. Along the
water courses the soils are hydromorphic and alluvial, associated with Dambos. Main
rivers crossing this region are: Licungo, Lúrio, Messalo, Lugenda, Chire and Rovuma.
The main crops in this area are: maize and millet, cashew nuts, cotton, tobacco and beans.
19
5. WORLD BANK SAFEGUARD POLICIES
In this section World Bank Operational Policies that are triggered by the project are
reviewed (Table 2). The purpose of this review is twofold:
1. Ensure that the proposed project is environmentally and socially sound, and the
proposed measures will support compliance with triggered policies, and
2. Assess the relevance and implementation arrangements for these policies under
the project.
Table 2. Safeguard policies triggered by the proposed project
Safeguard Policy
Environmental Assessment (OP/BP 4.01)
Natural Habitats (OP/BP 4.04)
Pest Management (OP 4.09)
Physical Cultural Resources (OP 4.11)
Involuntary Resettlement (OP/BP 4.12)
Indigenous Peoples (OP/BP 4. 10)
Forests (OP/BP 4.36)
Safety of Dams (OP/BP 4.37)
Projects in Disputed Areas (OP/BP 7.60)
Projects on International Waterways (OP/BP 7.50)
Yes
[X]
[X]
[X]
[ ]
[X]
[ ]
[ ]
[X]
[ ]
[ ]
No
[ ]
[ ]
[ ]
[X]
[ ]
[X]
[X]
[ ]
[X]
[X]
Environmental Assessment (OP/BP 4.01)
The Project triggers WB’s OP/BP 4.01 Environmental Assessment because (i) research
activities to be supported under Component 1 could include breeding, germplasm, farm
management and processing; and (ii) capacity building for RCoLs to be supported under
Component 2 are likely to include infrastructure and equipment investments.
OP/BP 4.01 establishes the fact that some level of environmental assessment is required
for all Bank financed development projects. The Bank classifies proposed projects into
one of four categories, depending on the type, location, sensitivity, and scale of the
project and the nature and magnitude of its potential environmental impacts:
Category A: if it is likely to have significant adverse environmental impacts that are
sensitive, diverse, or unprecedented. For a Category A project, the borrower is
responsible for preparing a report, normally an EA (or a suitably comprehensive regional
or sectoral EA).
Category B: if its potential adverse environmental impacts on human populations or
environmentally important areas -including wetlands, forests, grasslands, and other
natural habitats- are less adverse than those of Category A projects. These impacts are
20
site-specific; few if any of them are irreversible; and in most cases mitigation measures
can be readily designed.
Category C: if it is likely to have minimal or no adverse environmental impacts. Beyond
screening, no further EA action is required for a Category C project.
Category “FI”: if it involves investment of Bank funds through a financial intermediary,
in subprojects that may result in adverse environmental impacts.
The WB project category definitions do not completely concur with those from the
National EIA regulation 45/2004 (see Chapter 6) for Mozambique. According to that
instrument, irrigation projects whose extension is equal or above 350 ha or that are
located in ecologically sensitive areas are of Category A, but following the WB criteria,
they do not necessarily fall within category A unless the area is sensitive and the impacts
irreversible.
The APPSA project has been classified as an environmental assessment (EA) Category B
non-transferred Project as described in the World Bank’s project documentation. The
consultant concurs with this assignation/characterization insofar that all identified
potential impacts for the activities are site-specific; few if any of them are irreversible;
and in all cases mitigation measures can be readily designed.
Bank policy also requires that EA is initiated as early as possible in project processing
and is integrated closely with the economic, financial, institutional, social, and technical
analyses of a proposed project.
The commissioning of EA work is the responsibility of the borrower and the Bank
reviews the findings and recommendations of the EA to determine whether they provide
an adequate basis for processing the project for Bank financing. OP 4.01 also determines
that (a) before the Bank proceeds to project appraisal, the EA report must be made
available in a public place accessible to affected groups and local NGOs and must be
officially submitted to the Bank; and (b) once the Bank officially receives the report, it
will make the report available to the public through its InfoShop. In commissioning the
formulation of the ESMF (this document) and by making the document available to the
public, the proposed project will be in compliance with OP 4.01.
This ESMF presents the process and procedures including checklists to assist in
identifying potential social and environmental impacts, and provides guidance to project
managers and implementers for avoiding or mitigating them. Where necessary, IIAM
will determine if more detailed studies are required and request that an environmental and
social assessment be carried out and that an ESMP be prepared before the project
interventions are considered in specific sites in compliance with OP 4.01.
21
Pest Management (OP/BP 4.09)
The project triggers the OP/BP 4.09 because technology generation and dissemination
activities to be supported could result in increased pesticides and agrochemical use on
research stations and among farmers reached by the program.
The Bank supports strategies that promote integrated pest management (IPM) approaches,
such as biological control, cultural practices, and the development and use of crop
varieties that are resistant or tolerant to the pest. However, the Bank may finance the
purchase of pesticides when their use is justified under an IPM approach. In appraising a
project that will involve pest management, the Bank assesses the capacity of the country's
regulatory framework and institutions to promote and support safe, effective, and
environmentally sound pest management.
a) The procurement of any pesticide in a Bank-financed project is contingent on an
assessment of the nature and degree of associated risks, taking into account the
proposed use and the intended users. With respect to the classification of
pesticides and their specific formulations, the Bank refers to the World Health
Organization's Recommended Classification of Pesticides by Hazard and
Guidelines to Classification (Geneva: WHO 1994-95). The following criteria
apply to the selection and use of pesticides in Bank-financed projects: They must
have negligible adverse human health effects.
b) They must be shown to be effective against the target species.
c) They must have minimal effect on non-target species and the natural environment.
The methods, timing, and frequency of pesticide application are aimed to
minimize damage to natural enemies. Pesticides used in public health programs
must be demonstrated to be safe for inhabitants and domestic animals in the
treated areas, as well as for personnel applying them.
d) Their use must take into account the need to prevent the development of
resistance in pests.
The Bank requires that any pesticides it finances be manufactured, packaged, labeled,
handled, stored, disposed of, and applied according to standards acceptable to the Bank.
The Bank does not finance formulated products that fall in WHO classes IA and IB, or
formulations of products in Class II, if (a) the country lacks restrictions on their
distribution and use; or (b) they are likely to be used by, or be accessible to lay personnel,
farmers, or others without training, equipment, and facilities to handle, store, and apply
these products properly.
Activities under the APPSA with a focus on irrigated agricultural expansion may result in
the introduction or expansion of pest management activities in certain areas. The ESMF
implementation tools and procedures are designed to identify the potential for the
introduction or expansion of pest management activities in sub-projects and, as needed,
requires the preparation of a Pest Management Plan (PMP). Sub-projects involving the
procurement of pesticides or pesticide application equipment, or increased pesticide use,
will not be funded until experience demonstrates that the local capacity exists to
adequately manage their environmental and social impacts in compliance with OP 4.09 as
described above and the pesticide regulation as described in Chapter 6.
22
Involuntary resettlement (OP/BP 4.12)
OP 4.12 applies to all land acquisition and any changes in access to resources due to a
sub-project. The policy applies whether or not affected persons must move to another
location. The Bank's policy requires a full Resettlement Action Plan (RAP) if over 200
people must be relocated or if these people are not physically displaced but lose over 10%
of their assets due to the project. If the impact is less than this an Abbreviated
Resettlement Action Plan should be prepared instead.
The nature and scale of sub-projects proposed under APPSA means that only minimal
displacement, and the subsequent need for relocation and/or compensation, is likely to
occur as a consequence of project implementation, especially at the headquarters in
Zambézia. However, since these impacts are not yet known, the ESMF provides criteria
for determining the need for resettlement in the form of Checklist (See Chapters 10 and
11 and Annex II of the ESMF). Additionally, a Resettlement Policy Framework (RPF)
has also been prepared for APPSA and complements this ESMF with regards to
involuntary resettlement.
Natural Habitats (OP/BP 4.04)
The Bank supports the protection, maintenance, and rehabilitation of natural habitats and
their functions in its economic and sector work, project financing, and policy dialogue
and expects borrowers to apply, a precautionary approach to natural resource
management.
In the context of APPSA implementation and development the following elements of
Bank policy will apply:
1. Promotion and support to natural habitat conservation and improved land use and the
rehabilitation of degraded natural habitats;
2. The Bank does not support projects that, in the Bank's opinion, involve the significant
conversion or degradation of critical natural habitats unless there are no feasible
alternatives for the project and its siting, and comprehensive analysis demonstrates that
overall benefits from the project substantially outweigh the environmental costs. If the
environmental and social assessment indicates that a project would significantly convert
or degrade natural habitats, the project includes mitigation measures acceptable to the
Bank. Such mitigation measures include, as appropriate, minimizing habitat loss (e.g.,
strategic habitat retention and post-development restoration) and establishing and
maintaining an ecologically similar protected area;
3. Wherever feasible, Bank-financed projects are sited on lands already converted
(excluding any lands that in the Bank's opinion were converted in anticipation of the
project).
For APPSA the impact on natural habitats will be small, but on-farm trials located in
Umbelúzi and Nampula the impacts maybe considerable if areas for on-farm trials are
located in natural habitats and thus, OP4.04 is triggered. However, proper planning is
required regarding site selection which should always avoid areas requiring
23
transformation of undisturbed natural habitat. The Project area encompasses a number of
natural habitats such as rivers (Mucelo, Umbelúzi) and thus, some sub-projects may
impact on natural habitats either through encroachment (e.g. new cropping areas),
hydrologic interference (water extraction) or indirectly by improving access to natural
habitats which did not previously exist (e.g. the rehabilitation or construction of access
roads). To address this concern, the ESMF provides the appropriate environmental
checklists and planning methods to identify any potential impacts of sub-projects on
natural habitats and to develop appropriate mitigation measures to minimize or avoid
damage.
Safety of Dams (OP/BP 4.37)
When the Bank finances a project that includes the construction of a new dam, even of
small size such as retaining ponds or wells, it requires that the infrastructure be designed
and its construction supervised by experienced and competent professionals. It also
requires that the borrower adopt and implement certain dam safety measures for the
design, bid tendering, construction, operation, and maintenance of the infrastructure and
associated works. For the life of any infrastructure, the owner is responsible for ensuring
that appropriate measures are taken and sufficient resources provided for the safety of the
dam. For small dams, generic dam safety measures designed by qualified engineers are
usually adequate.
APPSA will not fund any large dams as defined by OP4.37 but may fund small water
diversion weirs and irrigation or water supply systems that will depend on existing or
new small dams or weirs hence OP 4.37 is triggered. The design, construction and
operation of new small dams/weirs will use sound engineering as required by the OP 4.37.
Nevertheless, should a small dam be proposed, it is still subject to World Bank and
Mozambique EA and resettlement policies and regulations and the ESMF provides
guidelines on how to incorporate environmental considerations into the planning and
appraisal process.
6. LEGAL AND INSTITUTIONAL FRAMEWORK FOR ENVIRONMENTAL
AND SOCIAL MANAGEMENT IN MOZAMBIQUE
6.1. Legal Framework
In 2004 Mozambique adopted a new Constitution in which the GoM committed to assure
sustainable development by adopting policies and promoting initiatives that guarantee the
ecological balance, conservation and preservation of the environment aimed at improving
the quality of life of its citizens (Constituição da República de Moçambique, Article 117).
Mozambique has also acknowledged and adhered to international efforts in order to
assure environmental sustainability. Some of them include: Vienna Convention on the
protection of the ozone layer; the United Nations Framework Convention on Climate
Change (UNFCCC), Kyoto Protocol (As a non-Annex I Party), Montreal Protocol on the
substances that destroy the ozone layer and the respective London and Copenhagen
24
amendments; Cartagena Protocol on Biosafety, Convention on Biological Diversity
(CBD); UN Convention on Combating Desertification (UNCCD); Basel Convention on
the control of trans-border movements of dangerous residuals and their elimination; and
the Bamako Convention on the prohibition of importation of dangerous waste and the
control of trans-border movements of such waste in Africa.
In the context of the proposed APPSA Project the key elements of the national legal
framework that are relevant:










The National Environment Management Program
National Action Plan to Adapt to Climate Change (NAPA)
The Environmental Law
ESIA Regulation
Environmental Quality Standards and Effluents Emissions Regulation
Pesticide Regulations
Land Policy
Land Law
Water Policy
Biosafety Regulation
National Environnemental Management Program (PNGA)
The National Environmental Management Program (PNGA), approved by the Council of
Ministers in 1995, seeks to promote and implement a sound environmental policy. The
PNGA is the master plan for the environment in Mozambique and contains a National
Environment Policy, Framework Environmental Law and Environmental Strategy.
The PNGA consists of sectoral and cross-sectoral plans, for the medium and long term,
which intends to lead Mozambique to sustainable development. Thus, its implementation
will require a range of actions at all levels and across sectors. In accordance with the
PNGA, MICOA, in close co-ordination with other ministries, private and civil groups,
will work towards:





Development of inter-sectoral policies for sustainable development
Development and promotion of integrated resource-use planning
Promotion of sector legislation and establishment of norms and criteria for
environmental and social management
Protection and sustainable use of the countries' natural resources
Creating conditions for law enforcement and environmental and social monitoring
National Action Plan to Adapt to Climate Change (NAPA)
In 2007 the Council of Ministers of Mozambique approved the NAPA plan that presents
four important and urgent actions to adapt to climate change. MICOA has the
responsibility of coordinating a multi-institutional group to implement such actions. The
four main actions are:
25
1. Enhance the existing early warning system in order to assure that rural
communities are previously informed about natural disasters in order to avoid
human life losses.
2. Enhance farmer’s capacity to adapt to climate change by providing improved
inputs, rehabilitation and/or construction of irrigation schemes, creation of
alternative means of income generation such as agro-processing and promoting
sustainable use of natural resources.
3. Reduce the impact of climate change on coastal areas by controlling land use and
implementing erosion control activities in coastal areas.
4. Water resources management through multi-sectoral activities such as integrated
watershed management, improve hydrometric network in the country and improve
human capacity.
The plan has a time-span of 3 years (2007-2010) and is being updated for the next 3 years.
Environmental Law
The Environmental Law was passed by the Mozambican Parliament in July 1997. It aims
at providing a legal framework for the use and correct management of the environment
and its components and to assure the sustainable development of Mozambique. It is
applicable to all public or private activities, which may influence the environment either
directly or indirectly. Salient features of the Law include:





Those who pollute, or in any way degrade the environment, are liable and under
obligation to rehabilitate the environment or to compensate for the resulting
damage.
The Law forbids the pollution of the soil, subsoil, water or atmosphere by any
polluting substances, or any other form of degradation of the environment, which
fall outside the limits stipulated by the Law.
Projects and operations that are likely to have a negative impact on the
environment are subject to an environmental impact assessment by independent
assessors.
To protect environmental components that have a recognized ecological and
socio-economic value, environmental protection zones can be created.
Licensing of activities that are liable to cause significant environmental impacts is
required. The issuance of an environmental license is dependent on an appropriate
level of environmental impact assessment being completed and accepted.
A National Commission for Sustainable Development (CNDS), linked to the Council of
Ministers, was created by a provision in the Environmental Law in October 2000 to coordinate and integrate sectoral policies and plans related to environmental management at
the highest level.
Environmental and Social Impact Assessment (ESIA) Regulation
ESIA Regulation were passed by the Council of Ministers in July 2004 (Decree 45/2004)
and published in the Government Gazette (Boletim da Republica, I Série, Number 39 of
29 September 2004).
26
Three categories of project are defined by the Regulation (Article 3):
Category A: Activities presented in Annex I of the ESIA Regulation are considered to
have significant adverse impacts on the environment and are subject to an Environmental
and Social Impact Assessment (ESIA).
Category B: Activities listed in Annex II of the ESIA Regulation are those for which
potential environmental impacts are less adverse than those of Category A projects and
are subject to a Simplified Environmental and Social Impact Assessment (SESIA).
Category C: Activities listed in Annex III of the ESIA Regulation are exempt from an
ESIA and/or SESA but still require observance of good management practices.
According to the project description there are no activities to be considered under
Category A. However, if the project affects directly or indirectly sensitive areas, it is
classified as Category A. Sensitive areas include among others:
a) Natural forests
b) Zones of potential erosion, including dunes along the coastline
c) Conservation or protected zones or areas
d) Wetlands
e) Zones where the habitats and ecosystems are in danger of extinction
f) Zones of outstanding landscape beauty
g) Zones of archaeological, historical and cultural value that should be preserved
h) Zones where plant or animal species threatened with extinction are located
i) Ground waters used for public consumption
j) Areas for the protection of spring and water sources.
A proposed project is classified as Category B if its potential adverse environmental
impacts on human populations or environmentally important areas are less adverse than
those of Category A projects. These impacts are reversible and in most cases mitigation
measures can be easily defined. All activities that do not appear in Category C or in
Category A are considered to be Category B.
Selected activities considered to be Category C include the following:




Transformation or removal of indigenous vegetation with areas between 100 and
200 hectares without irrigation;
Irrigation schemes with an individual or cumulative area between 50 and 100 ha;
Industries of conservation of fruits and horticultural products equal or greater than
300 ton/day;
Rehabilitation or Construction of infrastructures (laboratories, offices, rural roads,
facilities etc).
27
It is expected that most sub-projects under the APPSA project will be categorized as
Category B and thus they require a simplified ESIA. Some sub-projects will also fall
under Category C and these are exempt from a normal ESIA but they require a good
management practice.
An ESIA (for Category A) must be approved at the central level (Direcção Nacional de
Avaliação de Impacto Ambiental - DNAIA), while a Simplified ESIA (for Category B) or
Category C should be approved at the provincial level (Direcção Provincial de
Coordenação Ambiental - DPCA). For all three categories MICOA issues an
environmental license on completion of the ESIA process. The ESIA process in
Mozambique is shown in the flow diagram shown in Figure 4.
See Chapter 5 for synergies among this regulation and the OP 4.01 regarding sub-projects
classification and ESIA procedures.
Environmental Quality Standards and effluents emission Regulation
Regulation related to Environmental Quality Standards and Effluents Emissions was
approved by the Council of Ministers in May 2004 (Decree 18/2004) and published in the
government’s gazette (Boletim da República number 22 of 2 of June 2004). It aims at
controlling and maintaining the level of concentration of pollutants at an admissive level.
MICOA is responsible for ensuring compliance with this Regulation.
Article 12 refers to water quality standards for agriculture, livestock production,
irrigation and aquaculture and these water quality parameters are given in detail in Annex
IV of the Regulation. Parameters for irrigation water quality include water salinity
(electrical conductivity), pH, Sodium Absorption Rate (SAR) and Total Dissolved Solids
(TDS).
Article 18 refers to parameters to maintain soil quality which include agricultural
practices (crop rotation, fertilization, etc.) and permitted practices according to the slope
of the terrain to avoid soil erosion.
28
Procedures for participation
Licensing
Request license for land use and utilization
or special license to the MINAG/DNTF
Temporary License
Present the project to CPI or the institution
responsible for the activity
Submit the project to MICOA for Preevaluation
Registration of the EIA process by
MICOA
Elaboration of pre-viability study and
Terms of Reference by the proponent
EPDA approval by MICOA
Elaboration of ESIA by the proponent
ESIA approval by MICOA
Environmental and Social
License
Approval of executive project by
responsible institution
Construction License
Approval of the activity by the responsible
ministry
Operational License
Construction by the proponent
Environmental and Social Monitoring by
the proponent
Environmental Auditing by
MICOA
Figure 4. Flow of activities to be carried out for the ESIA process in Mozambique
(source: Directiva Geral de AIA, DNAIA, 2001).
29
Pesticides Regulation
Ministerial Diploma 153/2002 of 11 September 2002 regulates the use of pesticides in
Mozambique. In terms of this regulation only those pesticides registered with the
National Directorate of Agricultural Services (DNSA) may be used. DNSA has
established a Registration Unit (RU) for the registration of the pesticides and the issue of
permits for their use. All substances with a pesticide action or regulators of plant growth
and which are to be imported, produced, commercialized and used in Mozambique must
be registered. The request for registration must be submitted together with the pesticide's
process according to the Standards for Registration and Handling of Pesticides published
by DNSA.
Concurring with OP 4.09, the composition and physical-chemical characteristics of the
pesticides proposed for registration shall conform to the specifications from the World
Health Organization (WHO) or the United Nations Food and Agricultural Organization
(FAO) and must appear on the label.
Any company legally established in Mozambique may obtain a title for the registration of
pesticides, after approval by the Ministries of Industry and Commerce, Agriculture,
Coordination of Environmental Affairs and Health. Registered companies must assume
full technical and environmental responsibility of the pesticides. The validity of the title
is 2 years, after which it can be renewed.
Pesticides that are not registered but are considered effective in the control of an
emergency situation due to an outbreak of epidemics or a plague, can be used with a
Permit for Emergency Use, given by the RU according to the Standards for the
Registration and Handling of Pesticides. These permits have the validity of the
emergency period.
Land Law
In accordance with the Constitution and the Land Policy, the Land Law (No. 19/97)
confirms that all land in Mozambique belongs to the State. Individuals (and associations)
may acquire, by default or through application, the right to use and occupy land through a
variety of mechanisms such as customary tenure, continuous occupation of a piece of
land for a number of years or official authorization. Although land may not be transferred
(i.e. sold) and there is no "land market" per se, holders of land rights are able to transfer
improvements, such as buildings, from one party to another.
The Land Law provides all Mozambican nationals, corporate persons (e.g. associations
and companies) and local communities the right to use and benefit from land. Certain
land belongs to the public domain in which no rights of land use and benefit can be
acquired, except where special licenses have been issued for specific activities. Such land
includes zones of total and partial protection, such as national parks, coastal zones and
the banks of navigable rivers. Land occupied by, among other infrastructure, aerial,
surface, subterranean and underwater installations and conductors of electricity, including
a strip of land of 50 m on each side, are considered to be zones of partial protection.
30
For purposes other than settlement and cultivation the land and natural resources are
usually considered to be common property. Such areas include livestock grazing areas,
the surrounding bush and woodland areas where people collect or exploit natural
resources, such as fuel wood, poles, thatching grass, medicinal plants, honey, wildlife,
etc., and open water bodies which are used for fishing.
Water Policy
In august 2007 the Cabinet Council approved the new National Water Policy published in
the official Gazette nr. 43/Serie I, supplement 5 of 30 of October 2007. This new policy
is a review of the Water Policy of 1995 (Boletim da República, I Série Number 34 of 23
of August 1995), which emerged from the Water Law of 1991.
The new Water Policy intends to achieve in the medium-term (2015) and long-term
(2025) the following main objectives:
(a) Satisfaction of basic needs of human water consumption.
(b) Improvement of sanitation in urban and rural areas.
(c) Water efficiently used for economic development.
(d) Water for environmental conservation.
(e) Reduced vulnerability to floods and droughts.
(f) Agreements on water allocations and management coordination for
international river basins.
Objective (c), (d) and (e) are particularly pertinent to the proposed project:
Biosafety regulation
The Decree 6/2007 of 25th April establishes the rules for imports, exports, transit,
production, manipulation, handling and utilization of Genetically Modified Organisms
(GMO) and sub-products, to achieve environmental protection, conservation of
biodiversity and human health.
Given the regional context of the APPSA, this regulation will be applied when
researching on new varieties and transferring technologies and genetic materials on Rice
from Mozambique.
6.2. Institutional Framework
The implementation of the ESMF will need to take place at all levels of APPSA (Central
to local), taking into account the coordination and implementation arrangements set out
for the project (Figure 1).
31
Environmental and Social Management
Central Level
MICOA is responsible for implementing the PNGA and associated environmental policy
and legislation. The Ministry has primarily a co-coordinating role in order to ensure the
integration of environmental variables in the process of planning and managing socioeconomic development. In this regard MICOA must co-operate with the other ministries
and sectors (see Table 3).
Table 3. Ministries with environmental and social-related responsibilities in APPSA
Institution
MICOA
MINAG (IIAM, DNTF, DNSA)
MOPH (ARAs)
District administration
Environment-related responsibilities
for APPSA
Environmental and Social Management,
ESIA approval, auditing
Sub-project approval, ESIA review,
environmental screening review and
monitoring,
Issue water licenses and guarantee
sustainable water use
Road rehabilitation authorization
MICOA is also responsible for regulating Environmental and Social Impact Assessment
(ESIA) procedures in Mozambique through the National Directorate for EIA (DNAIA).
As indicated above (section 6.1. Legal Framework), all projects likely to have adverse
environmental and social impacts are obliged to register the project with MICOA for
determination of its Category (A, B or C) and issuing an Environmental and Social
License.
MICOA is also responsible for enforcement of Environmental Quality Standards and of
Emissions and Effluents legislation and for territorial planning.
MICOA shall be a member of the Advisory Forum within institutional arrangements for
implementation of the APPSA in Mozambique.
Provincial and District levels
MICOA has established Provincial Directorates (DPCA) in all Provinces. DPCAs are
responsible for approving and monitoring the ESIA process with regards to Category B
and C projects, inspect project’s compliance with environmental regulations and promote
coordination among all sectors in the province. The level of organization and capacity
varies from province to province. For example DPCA-Zambézia promotes regular multisectoral meetings to discuss environmental issues in the province.
Major limitations at DPCAs in Zambézia province are limited human, material and
financial resources. These, hold back full completion of DPCA’s tasks especially
monitoring and inspection activities.
32
At the district level the environmental activity is based in the District Services of
Patrimony and Infrastructures (SDPI) through a Section of Environmental Management.
The SDPI is responsible for several environmental activities including monitoring and
inspection, which they should report to DPCA. However, this is a newly created structure
and all visited districts have none or limited staff and resources to carry out their
responsibility.
The Consultant recommends that IIAM should designate an entity within DPCA to be the
contact point for the APPSA project at provincial level. Main tasks include advise,
monitoring and inspection as well as emitting environmental licenses for sub-projects.
Regulation of Pesticide use, registration and management
Central Level
According to Pesticides Regulations Ministerial Diploma 153/2002, DNSA of the
MINAG, through its Registration Unit is the official agency responsible for the
registration of the pesticides and the issue of permits for their use, after approval by the
National Directorate of Health (DNS/MISAU), the National Directorate for
Environmental Impact Assessment (DNAIA/MICOA) and the National Institute for
Agrarian Research – Department of Animal Science (IIAM/DCA).
Within APPSA arrangements, IIAM is the project coordinator institution and thus,
responsible for making sure that formal procedures will be followed.
Provincial and District Levels
DPA through Agricultural Services is the institution with the responsibility of inspecting
if users have a use, handling or transportation permit. It also should monitor the use and
impact of pesticides from agricultural activities and report to DPCA.
At the district level pesticide use, handling and transportation is controlled by SDAE,
which works with an extension team in providing training for farmers and other
individuals/institutions in this matter. APPSA shall adopt an IPM strategy and will be
responsible to transfer new technologies to small farmers.
Land management
Central level
At the central level the National Directorate of Land and Forests (DNTF) which is part of
MINAG is the institution responsible for ensuring that the national land policy is
implemented. The Department of Agri-measurement must co-ordinate, promote, develop,
supervise and monitor activities related to mapping, large-scale land surveying, satellite
imaging and mapping, while the Department of Cadastre must deal with land registration
and land title accreditation.
33
Provincial and District Levels
Provincial Services of Geography and Cadastre are represented in each country's
Provinces. The responsibilities of the Provincial Geography and Cadastre Services
include:




Produce land-use maps (based on title rights) and documenting all the procedures
in the process of authorizing land use and utilization rights. The Provincial
Geography and Mapping Services do not authorize/allocate land use and
utilization rights, but simply prepares and channels the respective documentation.
Responsibility for the land law and regulations, the resolution of disputes, the
transfer of land use and utilization rights and the collection of land use fees.
Registration of community land acquired under customary law and documenting
the rights acquired by individual persons under customary law.
Sharing and providing information relevant to economic planning in the Province
by supplying information about areas occupied or abandoned. It also prepares
master plans for land occupation in co-ordination with other institutions
At the district level land management is under the responsibility of the District Services
of Economic Activities (SDAE) through a Land Section.
Agriculture development
Central level
At central level all activities related to agriculture development are the entire
responsibility of MINAG through several departments including Direcção Nacional de
Serviços Agrários (DNSA) and Centro de Promoção de Agricultura (CEPAGRI). Its
main tasks are the development of farmers, public and private sectors through
dissemination of improved technologies and promotion of agribusiness among others. As
IIAM is the institution responsible for coordinating APPSA, it must dialogue with DNSA,
DE and CEPAGRI for reviewing, approving and monitoring all activities within APPSA.
Provincial and District levels
At provincial level DPA, through its Agrarian (SPA) and rural extension (SPER) services,
is the institution responsible for defining priorities, organizing farmers associations and
deciding the best options for agriculture development.
DPA has a Department of Rural Extension (DER) composed of extension workers and
their supervisors who are responsible for implementing several activities for rural
development such as training on: application of appropriate agriculture techniques (crop
rotation, test and introduce resistant varieties, crop consociation among others), use and
handling of pesticides and fertilizers, among others.
At the district level SDAE will be the institution directly involved with APPSA which
through its extension team will identify and select site for on-farm testing, site for
development, prepare activities for submission, and conduct monitoring of field activities.
34
Irrigation
Central level
At the central level, the Services for Agricultural Hydraulics under DNSA at MINAG
assumes the responsibility of authorizing irrigation schemes but the issuance of a license
for water use and payment thereof falls under the responsibility of DNA/ARAs (Center,
North and South).
At the provincial level irrigation is under responsibility of DPAs through an irrigation
supervisor. This works in close relationship with extension teams at the district level. At
the district level irrigation is under responsibility of SDAE through an extension team
that covers each Administrative Post.
Roads Rehabilitation and Construction
Central level
At the central level the National Roads Administration (ANE) under Ministry of Public
Works and Housing (MOPH) is responsible for overseeing the planning and management
for the rehabilitation and construction of National Roads. A Social Affairs and
Environmental Unit (UASMA) have been created within ANE. The role of UASMA is to
ensure that environmental and social considerations are incorporated into all road projects
within Mozambique in accordance with the environmental guidelines for roads (i.e.
Social and environmental clauses in bidding documents).
Provincial and District Level
At the provincial level the Department of Roads and Bridges (DEP) under the Provincial
Directorate of Public Works and Housing (DPOPH) is responsible for secondary and
tertiary roads. However, rehabilitation and construction of access roads are the
responsibility of the district administration. In theory DEP should be responsible for
environmental and social considerations in road projects but currently do not have the
capacity to do so. This task is currently carried out by UASMA. Through a program of
capacity building in environmental management UASMA intends to strengthen the
capacity of DEP in this regard.
Inland Water Management
Central Level
The National Water Directorate (DNA) in the MOPH is responsible for water resources
in Mozambique. DNA's responsibilities are:



Carry out inventories of hydrological resources and water needs at national,
regional and catchment levels and establish and operate an information system;
Promote the formulation of policies for development, hydrological resources use,
water supply and sanitation;
Promote water legislation and supervise water legislation enforcement;
35


Promote studies for short, medium and long term planning on water utilization
and hydrological resource development;
Ensure investment for studies, projects and works on water supply and sanitation
in accordance with adequate and efficient management.
Provincial and District Levels
At provincial level MOPH is represented by the Provincial Directorate of Public Works
and Housing (DPOPH) and the Department of Hydro Resources represents DNA. This
department is responsible for the measurement of water flow in the major target rivers
(Umbelúzi, Mucelo, Limpopo) of this project and, theoretically for ensuring adequate
management of hydrological resources and guaranteeing a potable water supply and
sanitation for all the population while maintaining environmental integrity.
At district level the District Directorate of Public Works and Housing (DDOPH)
respectively represents DNA.
Regional Water Administrations
The regional water administrations (ARAs) are regional structures, created within the
decentralization process for water resources management. They are under the
MOPH/DNA supervision. The jurisdictional area of ARAs coincides with one or a group
of catchments basins. ARAs have economic, administrative and patrimonial autonomy.
They have the responsibility of operational management of water resources at regional
scale. Another competence of this institution is the issuing of licenses and concessions for
the public use of water and effluent discharge. They have also to inspect and monitor the
operators under their area of jurisdiction.
7. POTENTIAL ENVIRONMENTAL AND SOCIAL IMPACTS AND
MITIGATION MEASURES
Based on field visits and consultations on the proposed activities under APPSA, the
major positive and negative social and environmental impacts and mitigation measures
were identified. The precise nature of impacts will be available when the actual project
activities and sites will be finalized. The potential impacts described below provide a
broad understanding of the social and environmental impacts of proposed activities and
the mitigation measures. Key impacts relate to the potential interventions related to
Genetic diversity of Rice, Rice improvement, Agronomy, Water and Production Systems
Management, Agricultural Mechanization, Post Harvest Technologies and Innovation
and technology development (see section 2.2. for details). Over and above the proposed
mitigation measures, additional mitigation measures, where applicable, will be
considered when ESMPs are prepared for sub-projects. Impact assessment has also to
take into consideration the possible cumulative impacts by considering other rice projects
and developments in the area.
36
7.1. Potential adverse environmental impacts
HYDROLOGY
Impacts on hydrology, specially related to water quantity may arise if irrigation schemes
are to be developed in the context of the proposed project and the potential impacts
associate to this are described below.
Low flow regime
Changes to the low flow regime may have significant negative impacts on downstream
users, whether they draw water (irrigation schemes, drinking supplies) or use the river for
transportation or hydropower. For target areas issues to consider are:




Minimum demands from both existing and potential future users need to be clearly
identified and assessed in relation to current and future low flows;
The quality of low flows according to the Environmental Quality Standards and
effluents emission Regulation (Decree 18/2004) is also important;
Return flows are likely to have significant quantities of pollutants from various
sources such as nitrogen, phosphorus, sulfur, among others. Low flows need to be
high enough to ensure sufficient dilution of pollutants discharged from irrigation
schemes and other sources such as industry and urban areas. A reduction in the
natural river flow together with a discharge of lower quality drainage water can have
severe negative impacts on downstream users, including irrigation schemes.
Habitats both within and alongside rivers are particularly rich, often supporting a high
diversity of species. Large changes to low flows (±20%) will alter micro-habitats of
which wetlands are a special case. It is particularly important to identify any
endangered species and determine the impact of any changes on their survival. Such
species are often endangered because of their restrictive ecological requirements.
Mitigation measure: Integrating low flow release strategies into dam operation protocols
or watershed management plans are the best mechanism for mitigating the potential
negative impacts of changes to low flows. This can be achieved through the strategic
partners namely: ARA-Norte, ARA-Centro or ARA-Sul.
Flood and sediment transport regimes
It is important that new irrigation infrastructure does not adversely affect the natural
drainage pattern, thus causing localized flooding or altering the hydrologic flux. This is
particularly important for places where the hydrologic flux is changing, even though this
is not the case of APPSA’s command area. In these places, radically altered flood
regimes may have negative impacts thus, the following should be considered:


Flood waters are important for fisheries both in rivers and particularly in estuaries.
Floods trigger spawning and migration and carry nutrients to coastal waters.
Controlled floods may result in a reduction of groundwater recharge via floodplains
and a loss of seasonal or permanent wetlands.
37


Changes to the river morphology may result because of changes to the sediment
transport regime of flood waters. This may be either a positive or negative impact, as
dams typically interrupt the natural sediment transport regime and can cause
downstream scour for many hundreds of kilometers; and
Sediment accumulation in the reservoir can reduce the storage capacity and affect the
operational life of the reservoir.
Mitigation measure: See mitigation measures for low flow regimes. The protection of
flood plains may also be a useful measure as they function as groundwater recharge zones
and also attenuate peak discharges downstream. These are additional positive functions of
wetlands.
Fall of water table
Lowering of the water table by the provision of drainage to irrigation schemes with high
water tables brings benefits to agriculture. However, lowering the groundwater table by
only a few meters adversely affects existing users of groundwater whether it is required
for drinking water for humans and animals or to sustain plant life. For example, wetlands
are particularly affected, especially during the dry season. Springs are fed by groundwater
and will finally dry up if the level falls. Similarly, normal flows in rivers will be reduced.
In all APPSA targeted areas about 80% of people use water from wells and boreholes and
from surface waters. Thus, any change in the availability of groundwater for drinking
water supply needs to be assessed in terms of the economics of viable alternatives. People
may be forced to use superficial water sources that carry health risks, particularly guinea
worm infection and schistosomiasis.
A number of negative consequences of a falling water table are irreversible and difficult
to compensate for example salt water intrusion and land subsidence.
Mitigation measure: Ground and surface water withdrawal need controlling either by
licensing, other legal interventions or economic disincentives.
Rise of water table
In the long-term, one of the most frequent problems of irrigation schemes is the rise in
the local water-table (waterlogging). Low irrigation efficiencies (as low as 20 to 30% in
some areas) are one of the main causes of rise of water table. Poor water distribution
systems, poor main system management and archaic in-field irrigation practices are the
main reason. Ground water rising under capillary action will evaporate, leaving salts in
the soil and makes the soil difficult to work and not suitable for some crops.
Waterlogging may also imply increased health risks. Field visits confirmed that where
irrigation schemes exist, the Operation and Maintenance (O&M) is deficient. For
example in Chóckwe the irrigation scheme is obsolete and problems such as soil salinity,
poor drainage among others were reported.
Mitigation measures: Good irrigation management, closely matching irrigation demands
and supply, can reduce seepage and increase irrigation efficiency, thereby reducing the
groundwater recharge. The provision of drainage will alleviate the problem locally but
38
may create problems if the disposal water is of a poor quality. Apart from measures to
improve water management, two options to reduce seepage are to line canals in highly
permeable areas and to design the irrigation infrastructure to reduce wastage.
WATER QUALITY
Solute Dispersion
The changing hydrological regime associated with irrigation schemes may alter the
capacity of the environment to assimilate water soluble pollution. In particular,
reductions in low flows result in increased pollutant concentrations already discharged
into the water course either from point sources, such as industry, irrigation drains and
urban areas, or from non-point sources, such as agrochemicals leaking into groundwater
and soil erosion. Reduced flood flows may remove beneficial flushing, and reservoirs
may cause further concentration of pollutants. Where low flows increase, for example as
a result of hydropower releases, the effect on solute dispersion is likely to be beneficial,
particularly if the solutes are not highly soluble and tend to move with sediments.
Mitigation measures: Measures proposed for low flow impacts are also applied to
mitigate the impacts of solute dispersion.
Agrochemical pollution
A high nutrient level is essential for productive agriculture. Under APPSA, there will be
an increase in rice, maize and legumes production area. The use of both natural and
chemical fertilizers may result in an excess of nutrients, which can cause problems in
water bodies and to health. Agrochemicals enter the water bodies mainly through run-off.
Accumulation of agrochemicals residues in surface waters can have an effect on domestic
water supply and aquatic organisms. Several studies have demonstrated that the use of
chemical in rice paddies produces an effect on water ecosystems. For example, in the
70’s fish kills in the US were attributed to the application of Aldrin with seed rice that
entered in the aquatic ecosystem (Ginn and Fisher, 1974). Moody(1990) reports that the
problem with herbicide in Sacramento, California is the Thiobencarb, which gives a bitter
taste to the water and Molinate, which is toxic to fish.
During the field visit it was observed that, for rice production, agrochemicals are not used
in general by the farmers, but some of the agrarian stations do. For example, in Chóckwe
Agrarian Station fertilizers such as Ureia and NPK are used. When agrochemicals are
used, they are usually drained into the surface and groundwater systems, and DPA and
DPCA have weak capacity for monitoring/control agrochemicals use. The use of these
sources for drinking water supply is at risk due to the presence of nitrogen and
phosphorus salts. This run-off of fertilizers and pesticides may lead to eutrophication and
upset aquatic biota and ecosystems.
Mitigation measure: In case of herbicides such as Thiobencarb and molinate, the water
must be retained in the field for 14 and 12 days, respectively after their application in
order to keep the concentrations of Thiobencarb in the river below 8ppb and of Molinate
below 4.5 ppb. Overall pesticides and chemicals used for agriculture must be assessed
39
and monitored as part of the environmental management process and measures to ensure
compliance with the WB OP 4.09 and the National Pesticide Regulation (Ministerial
Diploma 153/2002). To achieve this, a general Pest Management Plan (PMP) is presented
as a standalone document and should be strictly followed.
Anaerobic effects
Most anaerobic conditions in water bodies are the result of an over-supply of nutrients, as
discussed above, resulting in eutrophication. Anaerobic conditions can be caused by
oversupply of nitrogen and phosphorus from other sources in the area (commercial
agriculture, mining etc). Anaerobic conditions also occur when water is so polluted as to
kill most aquatic life. Anaerobic decomposition should be avoided as it produces gases
such as hydrogen sulphide, methane and ammonia all of which are poisonous and some
of them (methane) contribute to the greenhouse effect.
Mitigation measures: Adopt the IPM approach to limit the use of agrochemicals that can
be leached to water bodies. Especially in rice and irrigated lands manage the discharge
and infiltration of waters that is over-supplied with nutrients by nitrogen and phosphorus.
AIR QUALITY
Methane emissions from wetland rice agriculture have been estimated up to 100 Tg/yr,
which accounts for approximately 20% of the global anthropogenic budget (Roger and
Joulian, 1999). According to the IPCC (1994) flooded rice fields are one of the two main
agricultural sources of methane, together with ruminant enteric digestion. Mitigation of
CH4 emissions are needed to stabilize or even lower atmospheric concentrations. Factors
affecting methane emissions from rice paddies include soil properties (in clay, poorly
drained is higher), agricultural practices (water management, organic matter utilization
and mineral fertilizer).
Considering that a rice paddy may emit between 5 and 100 g/m2 of methane depending of
water and soil conditions, rice varieties used and water management efficiency and, that
around 75*105 m2 (roughly 100*150 m2 times 500 plots) will be developed in the APPSA
context, it can be roughly estimated that, emissions may vary between 37.5*106 and
75*107 g of methane.
Mitigation Measures: Methane and other gases emissions from rice paddies can be
reduced by using varieties with low water needs, higher yield per ha thus reducing the
extent of waterlogged area, temporary drainage periods during the crop cycle and using
mineral fertilizers (Sulphate and nitrogen containing and Gypsum fertilizers reduce
emissions) rather than organic; and Methane emissions may also be reduced by proper
irrigation management.
SOIL PROPERTIES AND SALINITY EFFECTS
Impacts on soils may arise if irrigation schemes are to be developed in the context of the
proposed project. Impacts on soils may also occur from the development of cultural
40
technologies, use of machinery, rehabilitation/construction of infrastructure. The
potential impacts arising from the proposed activities are described below.
Soil salinity and properties
The increased use of agrochemicals, needed to retain productivity under intensification,
can introduce toxic elements that occur in fertilizers and pesticides. Also, on irrigated
lands salinization is the major cause of land being lost to production and is one of the
most common adverse environmental impacts associated with irrigation. Soil salinization
was observed in Umbelúzi Agrarian Station, where a white salt layer was detected in a
small area, where APPSA will be potentially developed.
The accumulation of salts in soils can lead to irreversible damage to soil structure
essential for irrigation and crop production. Effects are most extreme in clayey soils
where the presence of sodium can bring about soil structural collapse. This makes
growing conditions very poor, makes soils very difficult to work and prevents
reclamation by leaching using standard techniques. A number of APPSA target areas
have clayey soils but Zambézia have the heaviest soils with very low permeability in a
flat topography. These areas are at risk from salinization as they are difficult to leach.
High water losses through the soil profile will result in useful cations being washed out
from the soil-complex, resulting in a general lowering of pH. This may in turn result in an
increased availability/release of heavy metals. Similarly, organic material in the soil may
decrease leading to a degradation of soil structure and fertility.
Mitigation measure: Careful management can reduce the rate of salinity build up and
minimize the effects on crops. Management strategies include: leaching; altering
irrigation methods and schedules; installing sub-surface drainage; changing tillage
techniques; adjusting crop patterns; and, incorporating soil ameliorates. All such actions,
which may be very costly, would require careful study to determine their local suitability.
Reducing salt inputs is one way of improving drain water quality. Groundwater drains,
either from pipe (tile) drains or deep ditches, carry out the dual task of controlling the
water table and through leaching, counteracting the buildup of salts in the soil profile.
Normally water is applied in excess of the crop water requirement and soluble salts are
carried away in the drainage water although in some areas leaching can be achieved
during the rainy season. The safe disposal of salts is of prime importance, either to the sea
(using dedicated channels if river quality is threatened) or to designated areas such as
evaporation ponds where the negative impacts can be contained.
Erosion and sedimentation
Soil erosion rates are greatest when vegetative cover is reduced and can be 10 to 100
times higher under agriculture compared with other land uses. Moreover, the method of
cultivation profoundly affects the vulnerability of the land to erosion. Because rice land is
wetter, it is less able to absorb rainfall and runoff will therefore be higher. Field size,
stream size (drop size), slope and field layout are all difficult to change and all
significantly affect erosion rates. The micro-topography of a field will thus be disturbed.
41
Unavoidably, this effect creates disproportionate water distribution over the field. In
addition it might create disputes between water users.
Soil erosion by water is an old problem in Center of Mozambique, especially in the
highlands of Manica Province, but in the other sites no erosion problems were detected.
Thus, APPSA is advised to carefully study and implement agricultural techniques to
avoid adding on this problem.
-
-
Mitigation measures: There is a wide range of management and design
techniques available to minimize and control erosion that include Providing
good vegetative cover to dissipate water energy;
Contour drainage to slow down surface runoff;
Terrace and contour cultivation (land-leveling) and the construction of field
bunds;
Careful design of irrigation scheme can avoid the occurrence of erosion
problems;
Improved water management practices related to surface irrigation methods
(for example by using gates, siphons, checks).
Irrigation infrastructure needs to be designed to ensure that localized erosion,
e.g. gully formation, does not occur. Construction activities generally expose
soil to erosion. Following the completion of construction work, vegetation
should be established around structures so that bare soil is not exposed to
erosive forces.
Hinterland effect
The development of agriculture or increased production of some commodities such as
rice, maize and legumes in developing countries is often associated with an increase in
intensity of human activity in areas surrounding the scheme and/or production area. This
may be due to people moving into the area as a result of the increased economic activity
or may be carried out by farmers and their families who are directly engaged in
irrigation/production activities. In either case typical activities are: more intensive rain
fed agriculture; an increase in the number of livestock; and greater use of forests,
particularly for fuel wood. All these activities are liable to increase erosion in the area by
decreasing vegetative cover which will have a detrimental effect on the local fertility and
ecology as well as contribute to sediment related problems.
Clearing higher parts of the catchment can result in a rising downstream water table. In
areas where the groundwater is saline the higher recharge may cause higher salinity
levels in the rivers and cause pressure levels in the lower areas to rise thus impeding
leaching.
Mitigation measures: Mitigating actions can be put in place relatively easily with
forethought as to problems that might arise. Some of the actions are:
- Planting deeper rooting crops and trees in the higher and sensitive to erosion lands;
- Allowance should be made for livestock, fuel wood or vegetable gardens within the
layout of the experimental fields and irrigated areas;
42
-
Alternatively, protection of vulnerable areas may be necessary.
Channel structures
The susceptibility of channel structures to damage is strongly related to changes in
channel morphology and changes in sediment regime. Increased suspended sediment will
cause problems at intake structures in the form of siltation as well as pump and filtration
operation. Abstraction structures may become clogged with sediment or left some
distance from the water. Degradation of the river bed is likely to threaten the structural
integrity of hydraulic structures (intakes, headworks, flood protection etc.) and bridges.
In fact, this is already happening in Umbelúzi as a deficient management of the irrigation
scheme is happening.
Mitigation measures: The best mitigation measure is to maintain the river’s pre-existing
hydrologic, hydraulic and sediment transport regimes as described above.
Soil Compaction
Improper management of machinery may lead to compaction. This may be caused by
poor timing of field operations, pressure from wheels, tillage equipment, trampling by
animals, reduced use of organic matter, frequent use of chemical fertilizers and plowing
at the same depth for many years. The signs of soil compaction are slow plant emergence,
thin stands, uneven early growth, small grain heads, abnormal rooting patterns, shallow
or horizontal root growth and reduced nutrients concentration (Ramazan et al, 2012).
Mitigation measures: The best mitigation measure is to properly use machinery avoiding
excessive utilization especially in heavy soils.
BIOLOGICAL AND ECOLOGICAL CHANGES
The main impacts associated with (irrigated) agricultural projects are a consequence of
the changes in land and water uses in the project area, but also in land around the project
and on aquatic ecosystems that share the catchment. The overall habitat as well as
individual groups (mammals, birds, fish, reptiles, insects etc.) and species need to be
considered. Rare and endangered species are often highly adapted to habitats with very
narrow ranges of environmental gradients. Such habitats may not be of obvious economic
value to man and therefore current knowledge of the biota may be poor and a special
study may be required.
Under APPSA, there are no environmentally sensitive areas since the project will focus
on existing experimental stations and existing farms. However, given the characteristics o
the project of developing agricultural production it is important to assess the area in order
to detect the existence of wetlands and other sensitive ecosystems. Wetlands usually
support a wide range of species and are particularly important for water fowl and as
staging areas for migrating birds. Also wetlands contribute as buffer to reduce flood
peaks, as low-cost water purification system and as a protection from erosion. These
places also have specialized and important habitats providing grazing for cattle and
wildlife and vital spawning grounds for many fish species. Flood flows trigger migration
43
and breeding in a large number of species. This high environmental and socio-economic
value of wetlands makes their study and preservation of key importance in an ESIA.
The consumption of water for (irrigated) agriculture and the reduced quality of return
flows is likely to adversely impact on downstream ecosystems. Reduced flows, increased
salt concentrations, lower oxygen levels, higher water temperatures and increased
pollution and silt loads all tend to favor vigorous, tolerant species (aquatic weeds). The
demands of different ecotypes will change through the year both in quantity and quality.
It is important to consider the biological and ecological changes that may occur in the
surrounding areas of experimental fields. However, if irrigated or improved agricultural
technologies are to be developed they may have positive impacts by for example settling
migrant slash and burn farmers or a negative impact by for example raising the demand
for fuel wood due to increases in local populations (see impacts on soils).
Mitigation measures: The creation of compensation areas or habitat enhancement within
and/or outside the command area may be useful mitigation measures where the natural
habitat change is assessed as detrimental.
7.2. Potential adverse socio-economic impacts
The major purpose of APPSA is to support research on agricultural (rice, maize and
legumes) production, agro-processing and commercialization, and ultimately to improve
the economic and social well-being of the target area. Although these activities will have
many positive impacts on the community, some potential adverse impacts are envisaged.
Impacts on land rights
Agricultural development and especially those involving irrigation have often become
arenas of multiple conflicts, of which the following are worth noting: a) there is conflict
among water users over water allocation, land rights, or maintenance issues; b) conflict
may arise between users and the authority responsible for the project over inappropriate
design of infrastructure, peasant relocations, water charges, or management issues; c)
conflict between project beneficiaries and non-beneficiaries; and d) finally conflict may
arise from land acquisition for agriculture or infrastructure development.
Mitigation measures: Ensuring participation farmers and other community members in
the planning and design stages of both new developments and the rehabilitation of
existing agricultural infrastructure, as well as the provision of technology, extension, and
marketing services, can minimize negative impacts and maximize positive ones.
Consultations with local communities and the assistance of NGOs can also greatly
minimize adverse socio-economic impacts. The Resettlement Action Plans (RAP) will
need to be prepared where land acquisition is involved or where access to resources is
involuntarily restricted, as described under the RPF.
44
Population change
Owing to project activities, there is likelihood of increase in population densities either
in the context of labor for works or to benefit from the technology dissemination and
increased incomes.
Mitigation Measures: Careful planning of labor requirements and arrangements needs to
be done. Further the project should ensure robust technology dissemination
methodologies to ensure dissemination of technology beyond research stations and
surrounding localities to larger areas to benefit a large proportion of the population.
Income generation
In general the research approach of APPSA will not directly promote income generation.
However it will require recruitment of additional labor, force which may create some
source of income to local communities. However, socio-economic problems may reduce
the income generating capacity including:




Reduced farming flexibility: as APPSA focuses on rice, maize and legumes
cultivation thus reducing emphasis on activities such as grazing animals, operating
woodlots;
Insufficient external supports such as markets, agro-chemical inputs, extension and
credit facilities;
Increased inequity in opportunity, often as a result of changing land-use or water use
patterns; and
Changing labor patterns that make labor-intensive irrigation unattractive.
Mitigation measures: Improved planning, with user involvement, has the potential to
reduce if not remove the above problems for both new and rehabilitation of infrastructure
subprojects under APPSA. Extension services, with training and education, also offer
much scope to improve the income and amenity.
Human migration
Project establishment attracts temporary populations both during construction and during
peak periods of agricultural labor demands. This impact is expected to occur mainly in
the new site in Quelimane in the Namacurra district of Zambezia province where the
RCoL for Mozambique will be established.
Mitigation measures: Careful planning of the impact of the research station construction
and later activities need to be assessed on the local community, the social and economic
infrastructure. Appropriate measures for dealing with the labor involved in the
construction activities will need to be put in place.
Human health
Wetland rice and irrigated schemes can create a variety of health risks, in part because of
ecological change (mosquito and snail propagation along shallow shorelines, associated
with aquatic weeds) and in part because of demographic changes. In some cases
45
infections occur in adjacent areas to the rice and irrigated fields, especially canals, ditches
etc.
Mitigation measures: Depending on the ecological requirements of local vector species
any of a range of interventions may be successfully applied; alternating wetting and
drying periods. The frequency of dry phases must enable the larvae dry out, steepening of
the shorelines, controlling aquatic weeds, and sitting settlements away from the reservoir.
Issues related to involuntary resettlement
The exact numbers of project affected people, the degree of impact on the families’
livelihoods (their losses, ownership status, tenancy status etc.) are not determined yet and
must be done during the process of developing RAPs. However, acquisition of land for
the rice development, rehabilitation/construction of infrastructure and access roads may
affect an estimated 200 households, without, however, physical displacement. For
example, in Mucelo farmers are cultivating inside IIAM’s area (conflicts already exist)
and in Namacurra, inside the area where RCoL will potentially be established there are
over 100 farmers using the land for rice cultivation. These situations may bring conflicts,
which are raised and dealt by the RPF developed for APPSA.
Mitigation measures: The Resettlement Policy Framework (RPF) outlines the mechanism
and tools for addressing the potential scope of resettlement and land acquisition outlined
above. RAPs will be required for APPSA activities that lead to involuntary resettlement
and these are described in the RPF.
Gender issues
Changing land use patterns and workloads resulting from the introduction or formalizing
of new agricultural technologies are likely to affect men and women, ethnic groups and
social classes unequally. Historically and due to cultural habits it has been men from the
more powerful and settled group that have had the greatest access to benefits and
increased income from agriculture. Women, migrant groups and poorer social classes
have often lost access to resources and gained increased workloads. Conversely, the
increased income and improved nutrition from agriculture benefit women and children in
particular.
Mitigation measures: Inclusion of disadvantaged groups (women, youth, and minor
ethnic groups) into key project processed from planning and implementation is critical to
ensure that both men and women from the local communities participate in the planning
and decision making process on R&D needs thus benefiting all the sections of the society.
7.3. Potential positive impacts
APPSA is expected to have positive environmental impacts as it supports the
development and dissemination of agricultural technologies that promote sustainable use
of land and water. Below is a description of potential positive environmental impacts and
measures to enhance or maintain the positive impacts.
46
Reduced flood and drought vulnerability
Uncontrolled floods can cause tremendous damage and flood control is therefore often an
added social and environmental benefit of reservoirs built to supply irrigation water.
Enhancement measure: To guarantee this positive impact it is necessary to maintain and
manage efficiently the infrastructures and the whole system.
Increase in agriculture productivity
Improved agricultural technologies and use of agro-chemicals (fertilizers and pesticides)
will contribute to improved crop productivity.
Enhancement measure: To achieve this impact it is suggested to promote better
agriculture techniques such as contour crops and terraces in all APPSA target areas,
especially those in slopes. The use of pesticides should follow the best practices
according to OP 4.09 (see Chapter 5).
Reduced deforestation
Improved crop production will likely settle the farmers, which will reduce the need for
new crop areas and thus deforestation. This is important in all APPSA areas but with
emphasis in Manica where high levels of deforestation were observed.
Enhancement measure: This effect will be accomplished as farmers realize the benefits of
permanent cultivation plots and efficiently manage and operate the irrigation scheme.
Improved livelihoods
APPSA will support a range of economic infrastructure to support agricultural
productivity and increased returns like rehabilitation and/or construction of new irrigation
schemes, access roads, and infrastructures, among other. Thus one of the potential
positive impacts is income generation and reduced food insecurity in the region.
Enhancement measure: Measures for operations and maintenance of these infrastructures
is essential to sustain benefits. Also important is to ensure access of all sections of the
community to these infrastructures and the resultant benefits.
47
Table 4. Summary of the negative and positive impacts of indicative sub-projects.
Sub-projects
Construction of small dams or
weirs



Rehabilitation
and/or 
construction of small- scale 
irrigation
and
drainage
systems









Rehabilitation of access roads
Increased area of rice
production
















Use of agriculture machinery







Potential negative
environmental and social
impacts
Flood
and
sediment
transport regimes
Solute Dispersion
Agrochemical pollution
Low flow regime
Flood
and
sediment
transport regimes
Fall of water table
Rise of water table
Solute Dispersion
Soil salinity and properties
River morphology
Channel structures
Human health
Issues
related
to
involuntary resettlement
Cultural property
Erosion and sedimentation
Hinterland effect
Soil Compaction
Agrochemical pollution
air quality
Soil salinity and properties
Erosion and sedimentation
Hinterland effect
biological and ecological
changes
Impacts on land rights
Population change
Income generation
Human migration
Human health
Cultural property
Issues
related
to
involuntary resettlement
Gender issues
Soil salinity and properties
Erosion and sedimentation
Soil Compaction
Population change
Income generation
Human migration
48
Potential positive
environmental and social
impacts
 Availability of irrigation
water
 Increase in ground water
table



Increase in agriculture
productivity
Reduced
flood
and
drought vulnerability
Improved livelihoods

Improved livelihoods

Increase in
productivity


agriculture
Improved livelihoods

Increase in agriculture
productivity
Reduced deforestation

Improved livelihoods
Testing
of
different
technologies (land preparation,
water and soil conservation,
pest control, etc).


Cultural property
Gender issues







Agrochemical pollution

Anaerobic effects

air quality
Soil salinity and properties
Erosion and sedimentation 
Soil Compaction
biological and ecological
changes
Impacts on land rights
Population change
Human migration
Cultural property
Issues
related
to
involuntary resettlement
Gender issues
Reduced
flood
and
drought vulnerability
Increase in agriculture
productivity
Solute Dispersion

Agrochemical pollution
Anaerobic effects
air quality
Soil salinity and properties
Erosion and sedimentation
Soil Compaction
biological and ecological
changes
Cultural property
Issues
related
to
involuntary resettlement
Gender issues
Improved livelihoods






Construction
and/or
rehabilitation of infrastructures
such as laboratories, agroprocessing facilities, seed
storage, etc











Improved livelihoods
8. GUIDELINES FOR SUB-PROJECT PREPARATION, APPRAISAL,
APPROVAL AND MONITORING
This chapter describes the process for ensuring that environmental and social potential
impacts are adequately addressed through the institutional arrangements and procedures
used by APPSA for managing the identification, preparation, approval and
implementation of sub-projects.
As stated in Chapter 5, APPSA is a category B project and thus most of the sub-projects
will fall within this category. However, according to national legislation, some subprojects may fall within Category C. In this case, the sub-project does not require an
Environmental and Social Impact Study, but it will be necessary to develop a code of
good environmental and social management practices. However, it is recommended to
49
avoid sensitive areas and observe the 350 ha threshold for irrigation schemes to ensure
that sub-projects stay within category B. To safeguard environmental and social
components in this section the consultant recommends procedures for small-scale
(probably Category C) and medium-scale sub-projects (probably Category B) separately.
8.1. Project identification and preparation
IIAM will be responsible for sub-project planning including identification and
management of on-farm experiments, thus sub- project planning will be integrated into
IIAM’s annual activity plan. The District Administration and Serviços Distritais de
Actividades Económicas (SDAE) have a key role in assisting IIAM in selecting on-farm
sites and contact farmers. Farmer’s organizations and institutions (for example in
Zambézia) are the key players in site selection and, most importantly, selected farmers
must formally agree to engaging with project activities.
It is important that IIAM, through its research stations, partners with selected farmers to
identify sub-projects for on-farm trials. For sub-projects at either research station or onfarms, IIAM prepare (in consultation with farmers and/or extension staff) the sub-project
proposals to avoid or minimize adverse environmental and social impacts.
This ESMF provides a checklist and screening guidelines (see Annex II) together with
information on typical sub-projects impacts and mitigation measures (see Annex III
Resource Sheets). The aim of the checklist and screening guideline is to assist IIAM and
its partners in identifying potential impacts based on field investigations and adopt
measures to avoid them. The Resource Sheets provide advice on how to avoid or
minimize impacts and cover a range of possible sub-project.
Project preparation teams must bear in mind that these lists are not exhaustive and thus,
should be open minded to other impacts and mitigation measures that may arise during
project preparation.
The checklist and screening contain a certification by IIAM and farmers that the
application includes all measures required to avoid or minimize adverse environmental
and social impacts.
8.1.1. Small-scale sub-projects
According to the World Bank Operational Policy 4.01 (Environmental Assessment)
beyond screening, no further action is required for Category C projects. The Mozambican
EIA regulation (Decree 45/2004) states that Category C projects shall follow specific
environmental management norms. Thus, IIAM is requested to prepare an ESMP for
category C projects.
According to the Decree 45/2004, under the context of APPSA, the possible sub-projects
that will probably fall within Category C are:
50




Small Irrigation Schemes (up to 50 ha)
Groundwater abstraction up to 200 m3/year
Rice (legume or maize) Processing facilities
Infrastructures (especially markets and grain storage facilities)
The application identifies the potential impacts of the sub-projects, describes the
measures built into the sub-projects to address these impacts and annexes the completed
checklist. For some sub-projects, mitigation measures and implementation of these
measures will need to be specified in more detail in the ESMPs and this should be
presented as an annex to the application. Training will be provided to IIAM team and
communities to adequately addressing these situations when preparing their applications.
There may, however, be situations where the advice of DPCA or APPSA-funded
technical assistance, is required. These include:


Land is acquired for a sub-project or someone's access to resources they are
defendant upon or use is restricted or denied: The need for a Resettlement Action
Plan (RAP) must be determined and, if needed, prepared according to procedures
detailed in the RPF.
A sub-project will involve the use of pesticides: a Pest Management Plan (PMP)
will be prepared in line with PMP document for the APPSA areas that will cover
PMP needs for sub-projects that trigger the policy i.e. all sub-projects with PMP
requirements will draw from the main PMP.
In case additional planning reports (e.g. ESMP, RAP, and PMP) must also be prepared
together with the sub-project application, sub-project cannot be finally approved and
funded until such reports are received, approved and disclosed.
Wherever possible IIAM should attempt to avoid the need for special planning reports
(e.g. ESMP, RAP or PMP) since they require extra resources to prepare and this may
require amendments to the sub-project design. Nevertheless, in the event of IIAM and
communities teams identifying good sub-projects that will significantly contribute to
local development these additional studies must be carried out and reports prepared.
8.1.2. Medium-scale sub-projects
According to the World Bank Operational Policy 4.01 (Environmental Assessment) the
scope of an environmental assessment for a Category B project may vary from project to
project, but it examines the project's potential negative and positive environmental
impacts and recommends any measures needed to prevent, minimize, mitigate, or
compensate for adverse impacts and improve environmental performance. The
Mozambican ESIA regulation (Decree 45/2004) states that Category B projects shall
follow a simplified Environmental Impact Study.
According to the Decree 45/2004, under the context of APPSA, the possible sub-projects
that will probably fall within Category B are:
51



Development of agronomic activities (use of pesticides, cultural practices,
mechanization, etc)
Rural Roads
Infrastructures (laboratories, agro-processing, grain storage, etc)
Under the proposed APPSA arrangements and the ESIA regulation (Decree 45/2004),
IIAM will be responsible for preparation of the simplified ESIA for medium-scale subprojects. They will most probably procure the services of an environmental consulting
firm to prepare the simplified ESIA.
The format for the ESIA will follow the requirements under the Decree 45/2004 and the
OP 4.01 requirements. In addition, medium-scale sub-projects that also require the
preparation of a RAP in the context of involuntary resettlement should refer to the RPF
for guidance.
The Terms of Reference (ToR) for a Simplified ESIA of irrigation and drainage projects
is attached as Annex I.
8.2. Appraisal and Approval of sub-projects application
8.2.1 Small-scale sub-projects
The completed ESMF checklists along with any additional planning reports (e.g. ESMP,
RAP or PMP) produced by IIAM and its partners are forwarded together with the overall
application to the review authority – DPCA. This institution may require consultation
with relevant technical personnel and must be trained in proposal evaluation and
environmental screening. In the present situation, DPCA in all APPSA target areas lack
adequate human resources to carry out environmental activity.
The first step in the approval process is a desk appraisal to determine if all the relevant
information has been provided, and if it is adequate. DPCA will then determine if it is
satisfied that the proponent have thoroughly considered all environmental and social
issues with regards to the identification of potential adverse effects arising from the subproject as well as mitigating measures to adequately address negative impacts. If required,
APPSA-funded technical assistance may provide support to this process. If the desk
appraisal indicates that the proposed sub-project may have environmental or social
concerns that are not adequately addressed in the application, or if the application meets
certain criteria (see Table 4), the review authority requires a field appraisal before the
application can be considered further. An example of a format for a field appraisal report
is provided in (Annex IV).
52
Table 5. Criteria for Requiring a Field Appraisal
Criteria
Field Appraisal
1. Land must be acquired for a sub-project, an
individual or community's access to land or
available resources is restricted or lost, or an
individual or family is displaced
2. A sub-project may-affect a protected area or a
natural habitat. This is unlike to happen within
the APPSA context since most of the
developments will be performed in existing farms
and experimental stations.
3. A sub-project may have an impact on
ecologically sensitive ecosystems
Determines the scale and level of impact. A
Resettlement Action Plan (RAP) may then be
required according to procedures detailed in RPF
Document.
Determines if the sub-project will adequately
avoid adverse effects on a protected area or
natural habitat, as provided for in Chapter 10 of
the ESMF.
4. A sub-project will involve or introduce the use
of pesticides
5. A sub-project may involve, or result in:
* Diversion or use of surface waters;
* Production of waste ;
* New or rebuilt irrigation or drainage
* Small dams, weirs, reservoirs, wells, or water
points.
A field appraisal determines the scale and level of
impact. The application may need to be revised to
describe how the sub-project will avoid or
minimize adverse impacts to ecologically
sensitive areas. This may require a distinct
Environmental and Social Management Plan
(ESMP) as outlined in chapter 10 of the ESMF
A field appraisal determines the scale and level of
the concerns. If needed, a PMP is prepared
according to the requirements of Chapter 10 of
the ESMF.
A field appraisal determines the scale and
potential adverse effects, and may include an
ESMP as outlined Chapter 10 of the ESMF.
Note: these criteria should be updated based on field experience in implementing sub-projects.
Based on the desk appraisal and, if needed, the field appraisal, DPCA will make the
decision about approval conditions and implementation supervision (e.g. erosion control,
waste management, human safety). For most of the sub-projects under APPSA final
approval will be taken by the respective DPCA which will be responsible for the issuing
of an environmental license.
8.2.2. Medium-scale subprojects
Under the implementation arrangements for APPSA and the ESIA regulation in
Mozambique, IIAM will submit the simplified ESIA to DPCA/MICOA for review and
approval. DPCA will coordinate with the DNA, ARAs, DPOH and DPAs on any
technical questions regarding the design and potential environmental and social issues
related to the sub-projects. In regards to specific land use issues, DPCA will consult with
the DPA how to address potential displacement and resettlement of project affected
parties (this is discussed in more detail in the RPF). DPCA will then grant an
Environmental License or reject the ESIA and request for more information.
53
As emphasized in the World Bank’s safeguard policies, projects financed by the World
Bank cannot be approved and funded until ESIA (and RAPs) are also received and
approved by the Bank, and then disclosed.
8.3. Disclosure of sub-projects information
In compliance with World Bank guidelines, before a sub-project is approved, the
applicable documents (ESIA, ESMP and/or RAP) must be made available for public
review at a place accessible to local people (e.g. at a local government office, at the
DNAIA/DPCA/SDPI), and in a form, manner, and language they can understand. They
must also be forwarded to the Bank for disclosure at the Public Information Center in
Maputo.
8.4. Annual Monitoring Reports and review
Monitoring of the compliance of project implementation with the mitigation measures set
out in its ESMP, PMP and/or RAP will be carried out jointly by IIAM, the communities,
extension teams and assisted by APPSA-funded technical assistance, if needed. DPCA
should supervise the monitoring activities and are required to report annually on subproject activities during the preceding year. The information to be included in these
annual reports to capture experience with implementation of the ESMF procedures is
shown in Annex V. An annual monitoring report must be submitted to the Consultation
Forum and the WB by IIAM. Monitoring of Category A sub-project should entirely be
the responsibility of IIAM, through most probably a consultant firm.
Compliance monitoring comprises on-site inspection of activities to verify that measures
identified in the ESMP, PMP and/or RAP are being implemented. This type of
monitoring is similar to the normal tasks of a supervising engineer whose task is to
ensure that the Contractor is achieving the required standards and quality of work.
MICOA, through DPCA and DNAIA (or a consultant) will have the responsibility of
conducting the environmental inspection. An annual inspection report must be submitted
(together with the monitoring report) to the IIAM and WB for review and approval.
Annual reviews may be carried out by an independent local consultant, NGO or other
service provider that is not otherwise involved with APPSA. Annual review should
evaluate the annual monitoring report from district authorities and the annual inspection
report from DPCA/DNAIA. The purpose of the reviews is two-fold:
1. To assess compliance with ESMF procedures, learn lessons, and improve future ESMF
performance;
2. To assess the occurrence of, and potential for, cumulative impacts due to projectfunded and other development activities.
The annual reviews will be a principal source of information to the Consultation Forum
for improving performance, and to Bank supervision missions. Thus, they should be
undertaken after the annual report on monitoring has been prepared and before Bank
54
supervision of the project. Guidance on undertaking annual reviews is provided Annex
VII of this ESMF.
8.5. Environmental and Social Audit
An independently-commissioned environmental and social audit will be carried out on a
tri-annual basis. The audit team will report to the IIAM and the World Bank, who will
lead the implementation of any corrective measures that are required. An audit is
necessary to ensure (i) that the ESMF process is being implemented appropriately, and (ii)
that mitigation measures are being identified and implemented. The audit will be able to
identify any amendments in the ESMF approach that are required to improve its
effectiveness.
An Audit Report will include:
 A summary of the environmental performance of APPSA, based on the ESMPs;
 A presentation of compliance and progress in the implementation of the subprojects ESMPs;
 A synopsis of the environmental monitoring results from individual sub-projects
monitoring measures (as set out in the sub-project ESMPs).
The main tasks of the audit study will be:
 Consideration of the description of the project;
 Indicate the objective, scope and criteria of the audit;
 Verify the level of compliance by the proponent with the conditions of the ESMP;
 Evaluate the proponent’s knowledge and awareness of and responsibility for the
application of relevant legislation;
 Review existing project documentation related to all infrastructure facilities and
designs;
 Examine monitoring programs, parameters and procedures in place for control
and corrective actions in case of emergencies;
 Examine records of incidents and accidents and the likelihood of future
occurrence of the incidents and accidents;
 Inspect all buildings, premises and yards in which manufacturing, testing and
transportation takes place within and without the project area, as well as areas
where goods are stored and disposed of and give a record of all significant
environmental risks associated with such activities;
 Examine and seek views on health and safety issues from the project employees,
the local and other potentially affected communities; and
 Prepare a list of health and environmental concerns of past and on-going activities.
8.6. Summary of preparation, appraisal, approval and implementation procedures
In summary, the process for sub-projects identification, preparation, evaluation, approval
and monitoring is presented in Figure 5.
55
ACTIVITY
Sub-project identification,
preparation and submission
Sub-project review and pre-approval
Sub-project approval and precategorization
RESPONSIBILITY
IIAM and farmers
associations
Regional decision
on project
identification
Consultation Forum
(CF)
Assisted by APPSA
DPCA/CF
World Bank approval and public disclosure
procedures
Final sub-project review and approval
(Environmental License)
Project implementation and
monitoring
DPCA for both category B
and C
IIAM with extension teams,
and farmers
IIAM/DPCA
Supervision and annual monitoring
report
Assisted by APPSA
or APPSA
Rice RCoL
funded
funded
technical assistance
DPCA Annual Inspection for category B
and C sub-projects.
Annual monitoring report review
and approval
WB and CF
independently-commissioned
tri-annual auditing
Figure 5. Proposed sub-projects identification, submission, evaluation and monitoring
56
There are two basic scenarios for small-scale sub-projects preparation and approval with
regards to environmental screening:
Scenario 1: The environmental checklist does not trigger any additional environmental
management measures.
Scenario 2: The environmental checklist triggers the need for additional environmental
measures [ESMP/PMP/RAP] and IIAM, communities/extensions teams to prepare these
(with technical assistance if required).
In all cases appraisal involve the DPCA and final approval involve the Consultation
Forum (CF), and the latter will also ensure that all sub-projects implementation are in
compliance with Mozambican ESIA Regulations (See Section 6.2). In some sub-projects
relevant government agencies must provide inputs for the appraisal (Table 6) and
approval process.
Table 6. Government agencies to be involved on a case by case
Sub-projects
Agency involved
Rural roads
District Administration
Irrigation
ARAs/DPA/SDAE
Land acquistiton
DNTF
Water Abstration
ARA-Zambeze/ARA-centro
Pest management
DNSA/DPA
Construction (facilties)
DNOPH
It cannot be emphasized sufficiently that the successful incorporation of environmental
safeguards are contingent upon three fundamental prerequisites:
1. The preparation, appraisal and approval process detailed in the ESMF must be an
integral part of APPSA’s Operations Manual.
2. Training, capacity building and technical assistance must be provided at all levels from
the community level to project management level.
3. Annual and mid-term review must fully evaluate compliance with the ESMF and the
Operations Manual.
Failure to comply with these prerequisites will result in environmental management
procedures being sidelined or overlooked.
57
9. GUIDELINES FOR ENVIRONMENTAL AND SOCIAL MANAGEMENT
PLAN AND MONITORING REQUIREMENTS
This chapter of the ESMF describes the additional management actions that may be
required as determined by the checklist and the World Bank OPs that are triggered by this
project.
The additional management actions may include the preparation of Environmental and
Social Management Plans (ESMPs), Pesticide Management Plans (PMPs) and
Resettlement Action Plans (RAPs).
Since APPSA target areas and detailed activities are not known yet the following section
(and Annex VII) only present guidelines for the design of a comprehensive ESMP. A
detailed PMP is also presented and should be strictly adopted by sub-projects but should
be adjusted to the particular situation of each site.
9.1. Environmental and Social Management
The environment is broadly defined to include the natural environment (air, water, soil,
land and the associated fauna and flora), and human health and safety. In the case wherea
sub-project is of Category B (according to the Decree 45/2004) or the checklist indicates
that more explicit impact mitigation measures are required for a sub-project, an
Environmental and Social Management Plan (ESMP) is required. For guidance the
contents of a typical ESMP are given in Annex VII.
The ESMP should meet the requirements for a sub-project and be easy to use. There is no
standard format or length. For many small and medium-scale sub-projects, it may be no
more than a few paragraphs or perhaps just a table. On sub-projects with more significant
environmental concerns (e.g. rehabilitation of a road that passes through a wetland), a
more substantive ESMP may be warranted to highlight its importance and in this case
technical assistance may be required to prepare the ESMP.
The basic elements of an ESMP are:
 A description of the possible adverse effects that the ESMP is intended to
mitigate;
 Addresses the requirements of OP 4.01 Environmental Assessment;
 A description of planned mitigation measures, and how and when they will be
implemented;
 A program for monitoring the environmental effects of the project both
positive and negative;
 A description of who will be responsible for implementing the ESMP; and
 A cost estimate and source of funds.
IIAM together with the extension team will prepare the ESMP, but communities should
participate in preparing the ESMP since local knowledge is important in identifying,
designing and planning the implementation of practical mitigation measures. It is
58
especially important where the success of an ESMP depends on community support and
action, both in implementing mitigation measures and in monitoring their success.
9.2. Pest Management
Pest management issues can be raised on a variety of agriculture sub-projects such as:
 New land-use development or changed cultivation practices in an area;
 Expansion of agricultural activities into new areas;
 Diversification into new agricultural crops, particularly if these tend to receive
high usage of pesticide - e.g. maize, legumes and rice;
 Intensification of existing low-technology agriculture systems;
 As indicated in Chapter 5 the Bank supports strategies that promotes
integrated pest management (IPM) approaches, such as biological control,
cultural practices, and the development and use of crop varieties that are
resistant or tolerant to the pest. The purchase of pesticides may be permitted
when their use is justified under an IPM approach.
 In addition to agricultural insect pests and plant diseases, pests also include
weeds, birds, rodents, and human or livestock disease vectors.
Mozambican regulation on pesticides and OP 4.09 conforms to the specifications of the
World Health Organization (WHO) and FAO. There are no specific policies with regards
to pest management and crop protection in the context of IPM approaches in
Mozambique. Research into plant health and to a certain extent IPM approaches are
carried out by IIAM (National Agrarian Research Institute) and Faculty of Agronomy and
Forestry (FAEF) of Eduardo Mondlane University (UEM). Under these agencies research
in IPM will continue and the knowledge passed on to extension services. Currently IPM
approaches in APPSA target areas are at an early stage with reliance more the use of
conventional pesticides.
Major problems in the targeted areas regarding the use of pesticides:
The potential problems with respect to use of pesticides in APPSA areas include:
* Excessive or inadequate use, which may result in problems for the human health and
the environment, especially the contamination of soils. Signs of soil
contamination/depletion were not observed within the visited sites. However, soil salt
accumulation was observed in Chóckwe;
* Use of out-of-date pesticides (not observed in most of areas);
* Use of non-authorized and/or non-labeled pesticides or the re-packaging of pesticides;
* Application without the adequate equipment, with an increase of the risk of
contamination;
* Used/ empty pesticide's packages, washed in rivers and leading to water contamination.
* No adequate monitoring of pesticides use and handling is carried out.
If pest management issues are raised by sub-projects interventions as outlined above a
PMP must be adopted. As capacity to prepare PMPs is weak, the PMP could be used as
guidance.
59
The PMP minimizes reliance on synthetic chemical pesticides, and promotes the use of
biological or environmental pest control methods, such as integrated pest management
(IPM) based on prevention, surveillance and monitoring, and ultimately intervention in
accordance with OP 4.09 (see Chapter 5). APPSA strategic partners such as UEM, MCT,
CCARDESA and other countries may contribute towards the development of IPMs.
9.3. Involuntary resettlement
The World Bank's policy on involuntary resettlement (OP 4.12) applies to all land
acquisition and any changes in access to resources due to a sub-project as described in
Chapter 5. The Bank's policy requires that a Resettlement Action Plan (RAP) be prepared
when people are relocated, or if these people are not physically displaced but lose their
assets due to the project. A separate Resettlement Policy Framework (RPF) has been
prepared and must be used in conjunction with this document. In addition the
Environmental and Social Checklist (Annex II) indicates when a RAP is needed.
10. TRAINING AND CAPACITY BUILDING REQUIREMENTS
This section outlines the types of training and capacity building that is required to support
implementation of this ESMF. These recommendations result from observation and
discussions made during field visits carried out as part of the preparation of this ESMF.
Training and capacity building is the key to the successful implementation of the ESMF.
10.1. Institutional Capacity Assessment
Institutional capacity to address environmental and social management issues, and
consequently to implement most of the measures outlined in this ESMF, is considered
weak. Although most agencies have some experience in environmental management they
have limited capacity especially the DPCAs and farmers and require some form of
capacity building.
Generally Mozambique has good environmental laws and regulations but the capacity to
enforce them is weak across all sectors.
10.2. Proposed Training and Awareness Programs
In order to successfully implement the guidelines and recommendations in the ESMF, it
is important to ensure that target groups and stakeholders who play a role in
implementing the ESMF are provided with the appropriate training and awareness
provisions. These include:
Central Level project management:
 IIAM
 Consultation Forum
60
Provincial level project management:
 Provincial Services for Agricultural Services (DPA)
 Provincial Directorate for Environmental Coordination (DPCA)
 Provincial Directorate for Public Works and Housing (DPOPH)
 Research Stations
 Zonal Research Centers
Local level project implementation:
 Extension workers
 Selected farmers
 Farmers associations and leaders
These stakeholders have different training needs in terms of raised awareness,
sensitization to the issues, and detailed technical training:



Awareness-raising in which the participants acknowledge the significance or
relevance of the issues, but are not required to have technical or in-depth
knowledge of the issues;
Sensitization in which the trainees become familiar with the issues to a sufficient
extent that allows them to demand their precise requirements for further technical
assistance; and
In-depth technical training to a level that allows trainees to go on to train others,
including technical procedures and take action.
The objective of the training under this ESMF is to:



Support IIAM, representatives and community leaders and associations to
prioritize their needs, and to identify, prepare, implement and manage the
environmental and social aspects of their sub-projects;
Ensure that provincial and district government officials are able to appraise,
approve and supervise the implementation of sub-projects; and
Strengthen local extension teams to provide technical support [including basic
ESMPs, RAPs, and PMPs] to communities in preparing their sub-projects.
Table 7 sets out the general training requirements of each of the groups and Table 8
presents details of the training to be carried out and the chronological order of training.
For each training session, the value of inviting participation of other stakeholders, such as
those from local authorities and the local private sector, should be considered.
61
Table 7. Training and sensitization requirements
Provincial level project
management
Extension workers/contact
farmers/NGOs
IOs/farmers
associations/leaders
Integrating Environmental and Social
Management into Development Planning
T
T
S
A
-
Linkages between environmental, social and
natural resource management and sustainable
rural livelihoods
A
T
T
S
S
EA legislation and relevant environmental
policies (national and international)
A
A
T
S
A
ESIA procedures and methods for impact
assessment and monitoring
A
T
T
S
S
Potential impacts of sub-projects and suitable
mitigation measures
A
A
T
T
T
Addressing land acquisition and access to
resources through resettlement planning and
compensation
A
T
T
T
S
Participatory Public Consultation
T
T
S
S
A
Use of this ESMF, its procedures, resources
and forms (including the PMP)
A
T
T
T
T
Methods of community involvement
A
A
T
T
A
Inter-community lesson-learning and review
A
A
T
S
-
District level project
management
Central level project
management
Training component
Legend: T =Technical training, S =Sensitization, A = Awareness-raising
62
Table 8. Proposed specific training packages and timing
Target audience
Central PM
Provincial PM
Extension
workers/selected
Farmers/NGOs
Training component
Length
Timing
In-depth training in
integrating environmental
management into developing
planning and Public
consultation
1 day
Quarterly for 3
years to update
Awareness on ESIA
procedures, legislation, use of
this ESMF, potential impacts,
community involvement,
Linkages between
environmental, social and
natural resource management
and sustainable rural
livelihoods and land and
resources acquisition
In-depth training in
Integrating Environmental
Management into
Development Planning
(tailored to each province’s
situation), Linkages between
environmental, social and
natural resource management
and sustainable rural
livelihoods,
land and resources
acquisition; ESIA procedures,
Public Consultation and
Use of this ESMF.
1 day
One-off at
APPSA kickoff
3 days in each
province
One per year
during three
years
Awareness in environmental
legislation, potential impacts
and community involvement
1 day in each
province
In-depth training on potential
impacts, ESMF
implementation, land
acquisition and community
involvement
3 days in each
district
One-off at the
APPSA kickoff and one
refresher in the
middle
One per year
during three
years
63
farmers associations/Leaders
Sensitization in ESIA
procedures, legislation,
Linkages between
environmental, social and
natural resource management
and sustainable rural
livelihoods and public
consultation
1 day in each
province
Once at the
kick-off of
APPSA and a
refresher in the
middle
In-depth training on potential
impacts and use this ESMF
3-days in each
district
Awareness in legislation,
public consultation and
community involvement;
1 day in each
district
One per year
during three
years
once at the
kick-off of
APPSA
Sensitization in ESIA
process, land acquisition and
Linkages between
environmental, social and
natural resource management
and sustainable rural
livelihoods
1 day in each
district
Once at the
kick-off of
APPSA and a
refresher in the
middle
The most profitable strategy would be to run workshops and refresher courses.
Communities exchange visits, training of trainers (selected farmers) and on-job training
of extension workers should also be considered. The training materials developed for the
workshop should include at least the following components:





Case studies (where possible developed by the workshop participants) based on
the scope of work of the sub-projects interventions that can be used to
demonstrate the basic principles of EA;
Workshops on sub-projects preparation guidelines developed and presented in
Chapters 8 and 9 above should also be a training component;
An overview of environmental assessment (scoping, screening, EA methodologies,
impacts and mitigation measures, public participation, monitoring and evaluation);
Review of relevant environmental legislation but with emphasis on regulations
regarding ESIA;
Designing effective public awareness campaigns.
A provisional program for a three-day workshop is presented in Box 1.
64
Box 1. Proposed agenda for a 3-day workshop Introducing ESMF
Day One:
(a) Introduction Environmental and Social Management
(b) Legal and institutional arrangements for ESMF (including WB operational
policies)
(c) ESIA procedures in Mozambique (including public consultation and Community
Support)
(d) ESMF procedures (environmental screening and community involvement)
(e) The Environmental and Social Management plans (IPM, RAP, EMP) and
contractor responsibilities
Day two:
(a) Overview of sub-projects
(b) Descriptions of the areas of influence and possible constraints to project
implementation
(c) Identification of potential impacts
(d) Monitoring and evaluation
Day three:
(a) Fieldtrip to selected sub-projects sites
(b) Environmental and social screening checklist testing
(c) Proposal’s preparation and submission
The focus of this proposed training will mainly be selected farmers, associations and
extension officers who will in turn train community members to implement components
of the ESMF at the community level.
10.3. Technical Assistance (TA)
Technical assistance will be provided for government officials, IIAM and communities in
order to prepare sub-projects proposals and implement the ESMF. Two types of technical
assistance will be provided:
1) General TA to ensure that local government authorities and extension teams receive,
on a reliable basis, experienced advice and mentoring to assist them in carrying out their
responsibilities. This component of the TA will also assess training effectiveness and
recommend further training needs, based on information gleaned from regular interaction
with project participants.
2) Specific TA to support IIAM, extension teams and communities in preparing
challenging sub-projects where specific technical knowledge is needed (e.g. the design of
a weir, a water supply system, IPM, monitoring) or where thorough ESMPs, PMPs, RAPs,
etc. may be required.
The General TA will be delivered on a regular, programmed monthly schedule by
professionals with strong training experience in environmental and social analysis and
management, as well as community-based development. The Specific TA will be
65
contracted on a "standing offer" basis so it can be mobilized quickly, as it is needed, by
professionals with the relevant technical skills and experience for preparation and/or
implementation of ESMPs, PMPs and RAPs, and other specialist inputs. General and
Specific TA service providers must keep detailed records for use in compiling the annual
reports and for undertaking annual reviews.
11. ESMF MONITORING REQUIREMENTS
This chapter also sets out requirements for monitoring of this ESMF implementation.
Monitoring of the indicators set out here will be mainstreamed into the overall
monitoring and evaluation (M&E) system for the project.
Indicators of ESMF implementation are:







Number of national, provincial, district level staff trained in implementation of
this ESMF;
Number staff attending training course in ESIA and ESMF implementation;
Number of sub-projects correctly submitted for approval;
Number of mitigation measures implemented;
Number of written warnings of violation of ESMPs issued to project proponents;
Number of recommendations from the Audit that have been implemented;
Number of performance contracts signed between IIAM and farmers/associations.
The indicators are deliberately very simple. Despite their simplicity, the integration of
these indicators into the APPSA M&E system provides a guarantee that the ESMF will
be implemented in full.
12. PROPOSED IMPLEMENTATION BUDGET
This Chapter presents the estimated budget needed to implement the ESMF. The budget
includes:





Institutional development activities;
The training program for communities, extension teams and IIAM to implement
their ESMF responsibilities;
Technical assistance to local authorities and extension teams;
Allowances for the preparation and/or implementation of sub-projects ESMPs,
RAPs, PMPs, etc. The costs of implementing these plans are included in the subprojects budgets. Sub-projects will only be approved as from year two;
Annual reviews and tri-annual audits;
The overall budget for implementation of the ESMF is estimated at USD$1,408,000 and
is presented in Table 9.
66
Table 9. Estimated implementation budget for APPSA
Component
ESIA
PMP
ESMF
implementation
Training
(includes
trainer fee,
course material
preparation,
implementation
of different
types of
training)
Activity
Preparation and
Implementation
Implementation and
monitoring
General technical
assistance
Specific technical
assistance
Monitoring
Inspection
Annual review
Tri-annual Audit
Central level Project
Management
Provincial level Project
Management
Annual amount (*USD$1000)
4
5
Total
(*USD$1000)
1
25
2
15
3
25
30
30
30
15
15
145
5
5
5
5
2.5
2.5
25
7
7
7
3.5
3.5
28
15
14
4
15
14
4
15
14
4
30
15
14
4
60
56
16
60
55
Notes
6
40
21
17
15
14
4
30
17
50
40
50
140
Extension
teams/selected farmers
20
15
20
55
IOs/leaders/Associations
25
20
25
70
Total
401
347
447
75
84
54
67
1,408
3 times a year during 3 years in-depth training and one
awareness training at kick-off
one per year during 3 years in-depth training and one
awareness training at kick-off and one awareness
refresher (in each province)
1 per year during three years in-depth training in each
district, 1 sensitization at the kick-off and 1
sensitization refresher
1 per year during three years in-depth training in each
district, one awareness training at kick-off , 1
sensitization at the kick-off and 1 sensitization
refresher
ANNEX I: ToR FOR A SIMPLIFIED ENVIRONMENTAL AND SOCIAL
IMPACT ASSESSMENT (ESIA)
Consultants are required to carry out a SESIA and prepare an EA report according to the
Mozambique’s legislation and World Bank standards (OP 4.01). The report should
include the sections:








Executive summary
Introduction
Policy, Legal, and Administrative Framework
Project Objectives and Description
Characterization (socio-economic and biophysical) of the reference area
Potential Environmental Impacts (follow Chapter 8)
Analysis of Alternatives
Environmental and Social Management Plan (Follow Annex VII)
Specific aspects under the above components of the ESIA that should be addressed in an
ESIA of a project are described below.
Project Objectives and Description: This section should describe the need for the
project in the context of the local and national agricultural strategy. The effect on
economic and social development goals of the project area, country and region when the
project influences transboundary rivers, aquifers, coastal zones or other issues, If the
project is an element of an overall irrigation and drainage or agricultural sector
development program in the area, then a description of the other program elements must
be presented.
A physical description of the project should be provided, including the physical location
and area of influence, the schedule of works and implementation program, the materials
and equipments needed, the source of irrigation water, the disposal strategy for drainage
waters and the projected effects including volume and flow of irrigation and drainage
water.
Characterization of the reference area: Key parameters for area characterization
include: hydrology and hydrogeology, water quality, demand and allocation, soils,
existing land-uses, ecology, ecologically sensitive habitats, protected areas, forested areas,
socio-economic environment, significant natural, cultural and historic sites.
Potential environmental and social impacts: A prediction of the changes on the
environment (social and biophysical) resulting from the project construction and
operation must be considered and an assessment of the effect on the surrounding physical,
biological and human systems should be considered. The engineering design plan should
reflect “best practices” in terms of construction and operation activities to ensure that
potential environmental impacts are minimized. Special attention should be given to
issues raised in Section 8.2 about potential impacts.
68
Analysis of alternatives: Alternatives should be clearly presented (including the
“alternative zero” of no-action). For irrigation projects, alternative sources of water and
demand reduction through conservation and re-use and project management and
monitoring should be considered. For drainage, alternative methods, overall project
concept, management and monitoring programs should be thoroughly analyzed.
Environmental and Social Management Plan: This section should include details of
the management initiatives to be implemented during both the construction and
operational phase of the project. The ESMP will need to account for monitoring of
environmental parameters and the influence of mitigation measures on environmental
impacts. It should include the following basic components:
Institutional Component
• Institutional responsibilities for management of the agricultural sector;
• Institutional responsibilities for health and socio-economic issues management;
• Responsibilities for monitoring, reporting and enforcement for water quality, water
balance and salt balance and related issue management;
• Identification of any needs for capacity building, training or equipment
Environmental and Social Mitigation Component
Chapter 8 presents key mitigation measures for agriculture project.
Environmental and Social Monitoring Component
Monitoring should address all potential issues listed in Section 8.2 and any others which
are considered relevant to the project and the location. For Bank-financed projects the
results of the monitoring and analysis including interpretation and recommendations, if
any, should be reported to the Bank on a quarterly basis during the construction phase
and annually during the operational phase for at least three consecutive years following
the completion of construction.
General monitoring parameters and their suggested monitoring frequency agriculture
projects are presented in Annex III.2. It is important to note that these parameters apply in
general to such projects and that it may be necessary to include additional parameters for
individual projects. The parameters listed do however provide a benchmark for the
environmental and social management plan, which will need to be geared toward the
specific project circumstances.
69
ANNEX II: CHECKLIST FOR ENVIRONMENTAL AND SOCIAL SCREENING
Name of the Project:
Sub-project Name:
Sub-project Location:
Community Representative and Address:
Extension Team Representative and Address:
Site Selection:
When considering the location of a sub-project, rate the sensitivity of the proposed site in
the following table according to the given criteria. Higher ratings do not necessarily
mean that a site is unsuitable. They do indicate a real risk of causing undesirable adverse
environmental and social effects, and that more substantial environmental and/or social
planning may be required to adequately avoid, mitigate or manage potential effects.
Issues
Natural
habitats
Water
quality and
water
resource
availability
and use
Natural
hazards
vulnerability,
floods, soil
stability/
erosion
Cultural
property
Low
No natural habitats
present of any kind
Water flows exceed
any existing
demand; low
intensity of water
use; potential water
use conflicts
expected to be low;
no potential water
quality issues
Flat terrain; no
potential
stability/erosion
problems; no known
volcanic/seismic/
flood risks
No known or
suspected cultural
heritage sites
Site Sensitivity
Medium
No critical natural
habitats; other natural
habitats occur
Medium intensity of
water use; multiple
water users; water
quality issues are
important
Medium slopes; some
erosion potential;
medium risks from
volcanic/seismic/ flood/
hurricanes
Suspected cultural
heritage sites; known
heritage sites in broader
area of influence
70
High
Critical natural
habitats present
Intensive water use;
multiple water
users; potential for
conflicts is high;
water quality issues
are important
Mountainous
terrain; steep slopes;
unstable soils; high
erosion potential;
volcanic, seismic or
flood risks
Known heritage
sites in project area
Rating
Issues
Involuntary
resettlement
Low
Low population
density; dispersed
population; legal
tenure is welldefined; welldefined water rights
Site Sensitivity
Medium
Medium population
density; mixed
ownership and land
tenure; well-defined
water rights
High
High population
density; major
towns and villages;
low-income families
and/or illegal
ownership of land;
communal
properties; unclear
water rights
Rating
Completeness of Sub-projects Application:
Does the sub-project application document contain, as appropriate, the following information?
Yes
Description of the proposed project and where it is located
Reasons for proposing the project
The estimated cost of construction and operation
Information about how the site was chosen, and what alternatives were
considered
A map or drawing showing the location and boundary of the project
including any land required temporarily during construction
The plan for any physical works (e.g. layout, buildings, other structures,
construction materials)
Any new access arrangements or changes to existing road layouts
Any land that needs to be acquired, as well as who owns it, lives on it or
has rights to use it
A work program for construction, operation and decommissioning the
physical works, as well as any site restoration needed afterwards
Construction methods
Resources used in construction and operation (e.g. materials, water,
energy)
Information about measures included in the sub-projects plan to avoid or
minimize adverse environmental and social impacts
Details of any permits required for the project
71
No
N/A
Environmental and Social Checklist
Yes
A
1
2
3
4
4
5
6
7
8
9
B
10
11
12
13
14
15
16
17
18
C
19
20
21
22
No
Type of activity – Will the sub-projects :
Involve the construction or rehabilitation of any small dams,
weirs or reservoirs?
Support irrigation schemes?
Build or rehabilitate any rural roads?
Build or rehabilitate any electric energy system?
Involve food processing?
Build or rehabilitate any structures or buildings?
Support agricultural activities?
Be located in or near an area where there is an important
historical, archaeological or cultural heritage site?
Be located within or adjacent to any areas that are or may be
protected by government (e.g. national park, national reserve,
world heritage site) or local tradition, or that might be a natural
habitat?
Depend on water supply from an existing dam, weir, or other
water diversion structure?
If the answer to any of questions 1-9 is “Yes”, please use the indicated
Resource Sheets or sections(s) of the ESMF for guidance on how to avoid or
minimize typical impacts and risks
Environment – Will the sub-projects :
Risk causing the contamination of drinking water?
Cause poor water drainage and increase the risk of water-related
diseases such as malaria or bilharzia?
Harvest or exploit a significant amount of natural resources such
as trees, soil or water?
Be located within or nearby environmentally sensitive areas (e.g.
intact natural forests, mangroves, wetlands) or threatened
species?
Create a risk of increased soil degradation or erosion?
Create a risk of increasing soil salinity?
Produce, or increase the production of, solid or liquid wastes
(e.g. water, medical, domestic or construction wastes)?
Affect the quantity or quality of surface waters (e.g. rivers,
streams, wetlands), or groundwater (e.g. wells)?
Result in the production of solid or liquid waste, or result in an
increase in waste production, during construction or operation?
If the answer to any of questions 10-18 is “Yes”, please include an
Environmental and social Management Plan (ESMP) with the sub-projects
application.
Land acquisition and access to resources – Will the sub-projects :
Require that land (public or private) be acquired (temporarily or
permanently) for its development?
Use land that is currently occupied or regularly used for
productive purposes (e.g. gardening, farming, pasture, fishing
locations, forests)
Displace individuals, families or businesses?
Result in the temporary or permanent loss of crops, fruit trees or
household infrastructure such as granaries, outside toilets and
72
ESMF
Guidance
Annex IV.1
Annex IV.2
Annex IV.3
Annex IV.4
Annex IV.5
RPF
Annex IV.1
Annex VII
Yes
23
D
24
F
25
26
No
kitchens?
Result in the involuntary restriction of access by people to
legally designated parks and protected areas?
It the answer to any of the questions 19-23 is “Yes”, please consult the ESMF
and, if needed, prepare an Resettlement Action Plan (RAP)
Pesticides and agricultural chemicals – Will the sub-projects :
Involve the use of pesticides or other agricultural chemicals, or
increase existing use?
If the answer to question 24 is “Yes”, please consult the ESMF and, if needed,
prepare a Pest Management Plan (PMP).
Dam safety – Will the sub-projects :
Involve the construction of a dam or weir?
Depend on water supplied from an existing dam or weir?
If the answer to question 25-26 is “Yes”, please consult the ESMF
ESMF
Guidance
RPF
and
Chapter 8
Chapter 10
and
PMP
document
Annex III.1
CERTIFICATION
We certify that we have thoroughly examined all the potential adverse effects of this sub-projects.
To the best of our knowledge, the sub-projects plan as described in the application and associated
planning reports (e.g. ESMP, RAP, PMP), if any, will be adequate to avoid or minimize all
adverse environmental and social impacts.
IIAM representative (signature):…………………………………………….
Community representative (signature): ………………………………………….……………
Extension team representative (signature): ……………………………………………………
Date: …………………………………………………
73
FOR OFFICIAL USE ONLY
Desk Appraisal by Review Authority:
 The sub-project can be considered for approval. The application is complete, all
significant environmental and social issues are resolved, and no further sub-project planning
is required.

A field appraisal is required.
Note: A field appraisal must be carried out if the sub-project:
 Needs to acquire land, or an individual or community’s access to land or available resources
is restricted or lost, or any individual or family is displaced
 May restrict the use of resources in a park or protected area by people living inside or
outside of it
 May affect a protected area or a critical natural habitat
 May encroach onto an important natural habitat, or have an impact on ecologically sensitive
ecosystems (e.g. rivers, streams, wetlands)
 May adversely affect or benefit an indigenous people
 Involves or introduces the use of pesticides
 Involves, or results in: a) diversion or use of surface waters; b) construction or rehabilitation
of latrines, septic or sewage systems; c) production of waste (e.g. slaughterhouse waste,
medical waste); d) new or rebuilt irrigation or drainage systems; or e) small dams, weirs,
reservoirs or water points.
The following issues need to be clarified at the sub-project site:
………………………………………………………………………………………………………
………………………………………………………………………………………………………
………………………………………………………………………………………………………
A Field Appraisal report will be completed and added to the sub-project file.
Name of desk appraisal officer (print): …………………………………………………………...
Signature: …………………………………………………
Date: ………………………………
74
ANNEX III: RESOURCES SHEET
ANNEX III.1. SMALL DAMS AND RESERVOIRS
Scope of Projects
Small dams and reservoirs can have many purposes, for example to provide water for
irrigation, water supply and aquaculture, to control erosion or floods, and to generate
micro-hydropower. They may involve relatively low structures (weirs) to divert water to
other uses without creating a reservoir. Higher structures raise water levels and flood land
upstream, and can significantly alter the timing and perhaps temperature of downstream
flows. The latter may require resettlement of people, land clearing, and the relocation of
roads. Structures that divert water to other uses reduce downstream flows with
consequent effects on surface and groundwater hydrology, aquatic habitats, and water
users. Even small dams can have complex and significant environmental effects. Planning
and design need to be comprehensive and thorough, and will likely involve specialists in
a variety of fields (e.g. engineering, hydrology, aquatic ecology, soil and water
conservation, sociology, economics).
Some of the environmental impacts and mitigation measures that can apply to the target
areas are presented in Table 1.
Table 1. Potential environmental impacts and mitigation measures for small dams and
reservoirs that may apply to APPSA target areas.
Potential environmental Adverse effects
Human Environment
* Loss of productive land (e.g. agriculture,
grazing and forestry)
* Displacement of people and families
* Loss of local livelihoods
* Reduction of water available to downstream
water users
Human Health
* Creating habitats for disease carriers such
as mosquitoes and snails
* Increases in water-related diseases such as
Mitigation measures
 Consider alternatives to a new dam and
reservoir for example: Upgrading and renovating
existing water supply and irrigation systems;
Alternate locations and/or dispersed smaller dams
in less sensitive areas; Watershed improvement
program to enhance retention of precipitation in
soils (see
below)
 Compensate for taken land and
structures, and resettlement (including rehousing, reestablishment of livelihood activities,
water and sanitation, training)
 Avoid areas of significant economic or
cultural value to local people
 Ensure that downstream water users
(e.g. water supply, irrigation, livestock watering)
are partners in planning the dam and
mitigation/compensation measures
 Assess the ecology of disease carriers in
the watershed
 Employ suitable prevention and
75
malaria, schistosomiasis (bilharzia),
onchocerciasis (river blindness), and
dysenteries, fevers and worms)
mitigation measures, including education of local
people, construction workers, e.g.: Ensure all
construction sites, borrow pits and quarries are
properly drained, Finish and manage reservoir
margins for proper drainage, Vary the reservoir
water level
Proper design and operation of dam spillways and gates
(timing and volume of discharges)
 Monitor disease and public health
indicators, during and after construction, and take
corrective measures (e.g. education, medical) as
needed
Natural Environment (General)
* Loss of natural areas, important habitats,
and number and variety of species
 Avoid: Protected natural areas
(biodiversity); Critical habitats or areas
with significant biodiversity (e.g. wetlands)
 Assess state of the watershed, and plan
the reservoir (e.g. siltation, evaporation losses) to
implement appropriate water conservation
program, perhaps including: Watershed
improvement measures (e.g.
revegetation, reforestation, afforestation,
controlled use) to reduce erosion and
increase infiltration of precipitation, Training to
ensure effective tending of
improvement measures (e.g. watering,
protection from grazing), Agricultural methods
that maximize soil moisture conservation (e.g.
mulching, terracing, contour cropping,
maintaining soil cover)
* Threatened water source(s) for the reservoir
(sedimentation)
Aquatic Environment - River/Stream
* Reduced or altered timing, quantity,
quality and temperature of downstream
water flows
* Altered rates and locations of bed and bank
erosion and deposition downstream
* Reduction in quantity and quality of
aquatic habitats and fish production
* Reduction/loss of downstream subsistence or
commercial fisheries
 Ensure thorough analysis and assessment of
potential impacts to develop and plan, as part of
the project, an acceptable combination of: water
releases required to sustain habitats and fish
production, habitat improvements to sustain
production and fisheries, development assistance
to people de pendent on reduced fisheries
* Consider alternate dam locations and possibility
of fish around dam
* Blockage of fish migration and access to
upstream spawning areas by dam; decreases in
fish populations downstream
Aquatic Environment - reservoir
* Conversion of aquatic species in reservoir from
those that require flowing water to those that need
still water, and resulting effects on fishing
activities
*Assess fish production potential of reservoir,
and implement feasible measures to enhance
production (e.g. habitat design, stocking,
aquaculture)
* Provide development assistance to local people
to benefit from reservoir fisheries
76
* Deterioration of reservoir water quality
* Provide areas for bathing, laundering, and
animal watering away from reservoir
* Ensure local sanitation facilities do not release
pollutants to surface or roundwaters reaching the
reservoir
* Prevent livestock access to reservoir
* Deterioration of reservoir water from:
- Decomposition of flooded vegetation flooding; Nutrients in eroded soils and agrochemicals
* Clear vegetation from reservoir area before
* Train farmers in soil and water conservation,
agricultural fertilizers and in appropriate use of
fertilizers
Terrestrial Environment
* Raised water table around the reservoir,
waterlogging and salinization of soils, and
lowered agricultural productivity
ENVIRONMENTAL STANDARDS
* National legislation on protected areas (natural
cultural and built environments)
* National legislation on protecting natural
resources (e.g. fish, wildlife, forest cover)
* International environmental conventions (e.g.
waters and heritage, wetlands)
* National water quality standards and controls
* National controls on use of fertilizers
* Health and safety standards for construction
activities
* Project support to improve agricultural land
drainage and production around reservoir
* Develop tolerant fodder and crop species
around reservoir
ENVIRONMENTAL QUALITY
INDICATORS
Pollution: Fish deaths, concentrations of
suspended sediments and contaminants (e.g.
pesticides) in surface reservoir, Reservoir oxygen
levels
Environmental Health: pesticides and
herbicides, Degree of biodiversity (numbers of
plant, fish, animal and bird species) in the
watershed, Extent of critical habitats
Human Wellbeing: Incidence of human and
animal illness or disease, Poverty levels
77
ANNEX III.2: SMALL IRRIGATION SCHEMES
Scope of projects
Small irrigation schemes can serve a few families or an entire community. They can
involve new irrigation for existing rain-fed agriculture, the development of uncultivated
areas, and changes or expansions to existing schemes. Water may be pumped from lakes,
ponds or underground, or be diverted from streams or rivers. Pipes, channels or ditches
carry the water to farmers' fields where it is distributed to crops by gravity on the soil
surface, by hand, or by other means.
Irrigated agriculture involves complex soil-water-plant relationships, and should not be
undertaken without thorough informed planning, even at a small-scale. While the benefits
of irrigation can be obvious and impressive, the adverse environmental effects can be
significant, long-term, and perhaps permanent.
The most significant environmental issues with small irrigation schemes concern threats
to human health and soil productivity. Health effects arise from stagnant water in canals,
ditches or fields that provide habitats for water-borne disease carriers. Losses of soil
productivity result from over-irrigation or poor soil drainage. These lead to waterlogging
and salinization of the soils, and a reduction or complete loss of their usefulness for
cropping. Salinization is the build-up of mineral salts in the soil as water evaporates from
the soil surface.
Some of the environmental impacts and mitigation measures that can apply to the target
areas are presented in Table 1.
Table 1. Potential environmental impacts and mitigation measures for small irrigation
schemes that may apply to APPSA target areas.
Potential environmental Adverse effects
Human Environment
* Upsetting existing social and economic
community management relationships, land
tenure system, security of livelihoods and gender
division of labor
* Conflicting demands on surface or
groundwater supplies
Human Health
* Creating habitats in canals and ditches for
disease carriers such as mosquitoes and
Mitigation measures
* Avoid sites that require: Resettlement,
Displacement of other important land uses, or
Encroachment on historical, cultural, or
traditional use areas.
* Locate and size irrigation schemes:
- Where water supplies are adequate and the
scheme will not conflict with existing
human, livestock, wildlife or aquatic
water uses, especially during dry seasons
- So that withdrawals do not exceed "safe
yield" from groundwater resources
* Encourage crops with lower water demands
* Ensure effective community organization for
equitable distribution of water
* Assess ecology of disease carriers in the project
area, and employ suitable prevention and
78
snails responsible for spreading diseases
such as malaria and schistosomiasis
(bilharzia)
* Spreading infection and disease through
the inappropriate use of irrigation canals
for water supply, bathing or human waste
disposal
* Health effects from improper storage,
handling, use or disposal of agro-chemicals
(pesticides and herbicides)
Soils
* Waterlogging
mitigation measures, e.g.: - Site and orient water
works, fields and furrows to ensure adequate
natural drainage of surface water, - Use lined
canals and pipes to discourage vectors - Avoid
unsuitable gradients, and creating stagnant or
slowly moving water, - Construct straight or only
slightly curved
canals, - Install gates at canal ends to allow
complete flushing, - Ensure adequate sub-surface
drainage of fields, - Avoid over-irrigation, Maintain water works, and clear sediment and
weeds regularly
* Provide/ensure alternate facilities for
domestic water supply, bathing and human
waste disposal
* Provide education and training for farmers and
other community members on:
- Irrigation health risks, - Efficient use of
irrigation water, - Maintenance of irrigation and
drainage works, - Proper storage, handling, use
and disposal of agro-chemicals, - Integrated pest
management
* Monitor disease/infection occurrence and
public health indicators, and take corrective
measures (e.g. physical changes to irrigation
scheme, education, medical) as needed
* Thoroughly assess project soils and their
management needs under irrigated agriculture
* Apply water efficiently. Consider drip or
dawn/evening sprinkler irrigation.
* Install and maintain adequate surface and
subsurface drainage
* Use lined canals or pipes to prevent seepage
* Salinization
* Avoid waterlogging (above)
* Mulch exposed soil surfaces to reduce
evaporation
* Flush irrigated land regularly
* Cultivate crops having high tolerance to
salinity
* Erosion
* Design and layout of furrows appropriately
* Avoid unsuitable gradients
* Avoid over-irrigation
* Install sediment traps in fields and canals to
capture sediment for return to fields
* Minimum tillage, contour cropping, terracing
and other methods of conserving soil moisture
Water Bodies and Aquatic Ecosystems
* Loss or damage to wetlands and their
environmental services, biodiversity, and
ecological productivity
* Avoid: - Locating irrigation schemes on or near
important wetlands (Special attention should be
given to Marromeu), - Developing irrigation
79
water sources that may reduce wetland water
supply, - Draining irrigated fields into wetlands
* Reduced quality of surface and
groundwaters receiving excess irrigation
water or drainage (nutrients, agro- salinization
chemicals, salts and minerals)
ENVIRONMENTAL STANDARDS
National legislation on protected areas (natural,
cultural and built environments)
National legislation on protecting natural
resources (e.g. fish, wildlife, forest cover)
International environmental protection
conventions (e.g. RAMSAR, Biodiversity)
National water quality standards and controls
National controls on storage, handling, use and
disposal of agro-chemicals
* Follow Soils mitigation measures (above) to
minimize risks of waterlogging and
* Use agro-chemicals appropriately (see Human
Health above)
* Prevent surface drainage of fields into nearby
water bodies (streams, ponds, etc.)
ENVIRONMENTAL QUALITY
INDICATORS
Pollution: Water quality (nutrients, agrochemicals, pH, Conductivity, turbidity, Sodium
Absorption Rate -SAR) in water supply and
drainage canals, and wells; Physical and chemical
properties of irrigated soils; Environmental
Health: Water table levels in project area
(including wetlands); Rate of extinction of
existing resources (e.g. fish, wildlife, forest
cover); Rate of occurrence of disease carriers
Human Wellbeing: Incidence of human and
animal illness or disease; Poverty levels
80
ANNEX III.3. RURAL ROADS
Scope of Projects
Rural roads can have substantial economic and social benefits as well as have significant
negative and long-term impacts. Many of these impacts can be avoided or minimized
through careful and comprehensive planning and design. Roads that involve relocation of
existing routes, or new access into previously inaccessible areas, can create particularly
difficult impacts on communities and land use, both directly and indirectly.
Indirect impacts include the economic, social and environmental effects, whether planned
or spontaneous, induced by the improved access and lower transportation costs a road
creates. Such new roads and relocations are large projects beyond the scope of this
resources sheet.
APPSA-supported rural roads will involve upgrading existing roads or tracks to improve
access to markets. They will be built with local labor, unpaved, and will be narrower and
can have tighter curves and steeper grades than highways. They may be all-weather or
seasonal. Close management of construction work is important to avoiding most
construction impacts. Adequate road maintenance is essential to avoid environmental
problems, and is often inadequate due to lack of funds or well-trained personnel.
The most important direct impact of rural roads is typically erosion -- during construction
and then operation. Because traffic intensity is low, air and water pollution and noise are
generally not significant problems. Indirect impacts need to be considered, but are
unlikely to be as significant as those caused by new roads or relocations.
Some of the environmental impacts and mitigation measures that can apply to the target
areas are presented in Table 1.
Table 1. Potential environmental impacts and mitigation measures for Rural Roads that
may apply to APPSA target areas.
Potential environmental Adverse effects
Human Environment
* Negative social and economic effects on
local people and communities, such as:
- Unplanned commercial development
- Demand for local public infrastructure
and services increases beyond capacities
- Disruption of traditional lifestyles
* Induced population movements and natural
resource exploitation activities, due to improved
access (e.g. conversion of forest to pasture, or of
sustainable land use to unsustainable, short-cycle
cropping; illegal or unsustainable hunting).
Human Health
* Social disruption during construction (e.g.
enhanced transmission of STDs, HIV/AIDS and
TB)
Mitigation measures
* Work with affected communities to anticipate
and plan for enhanced access to and demand on
local public infrastructure and services
* Provide project funds to strengthen local public
existing infrastructure and services (e.g. health
clinics, markets, schools)
* Avoid creating congested and unsafe road
conditions at intersections, and in villages and
towns
* Comprehensive community participation in
construction planning and management
* Education on avoiding communicable diseases
81
* Creation of stagnant water in construction
borrow pits and quarries, and on road sides, that
breed disease carriers
* Assess ecology of disease carriers in road
corridor, and employ suitable mitigation
measures (e.g. proper drainage of construction
areas and road sides, effective
road maintenance)
* Minimize use of road-side herbicides
* Health risks during road use due to
herbicides used to control road-side weeds
Soil and Vegetation
* Loss of natural areas, important habitats,
biodiversity
* Landslides, slumps and slips
* Increased soil erosion leading to sediment in
runoff and, possibly, gully formation from:
- Construction activities such as grading,
excavations, and borrowing/quarrying
- Inadequate design of culverts and drainage
controls flows
- Inadequate maintenance of road surface,
ditches, burrow/quarry sites and, drainage and
erosion control measures
Surface and Groundwater
* Disruption of natural surface and subsoil
drainage patterns, especially in flood-prone
or wetland areas
* Increased runoff from road surface
* Contamination by spills oil, fuels and
lubricants from construction equipment
Aquatic Environments
Soil erosion leading to:
- Increase in the turbidity of water courses
- Temporary or permanent covering of
riverbed organisms and habitats
*Avoid infringing on: - Protected natural sites
and wilderness areas, - Critical habitats or areas
with significant biodiversity (e.g. wetlands).
* Avoid: - Areas of soil, slope or geological
instability, - Unstable river crossing sites
Design:
- Use surface drainage controls and mulch on
vulnerable surfaces and slopes
- Size and locate roadside drainage and culverts
to handle maximum anticipated flows
- Line receiving surfaces with stones or concrete
- Locate and design borrow/quarry sites for
erosion control during road construction
and future maintenance operations
Construction:
- Limit earth movement and soil exposure
to the dry season
- Balance cut and fill for minimum
deposition of earth
- Provide sedimentation basins
- Resurface and revegetate exposed
surfaces
- Ensure proper and timely maintenance of
erosion control and drainage measures along the
road and at borrow/quarry sites
* Minimize soil compaction and time that soil
surfaces are exposed
* Provide adequate surface drainage control for
both construction and operation
* Size and place culverts and bridges correctly
* Establish measures to avoid accidental spills,
and contain them if they do happen
* Collect and recycle used lubricants
* Follow Soil and Vegetation and Surface and
surface Groundwater mitigation measures above
* Install culverts and bridges in dry season
82
* Watercourse and drainage blockages at
culverts and bridges
* Erosion of embankments and roadside slopes
Animals and Wildlife
* Blocked animal and wildlife movements
* Animal/wildlife road kills
ENVIRONMENTAL STANDARDS
National legislation on protected areas (natural,
cultural and built environments)
International environmental protection
conventions (e.g. RAMSAR, Biodiversity)
National water quality standards and controls
Health and safety standards for road
construction and use
* Ensure adequate maintenance of: - Culverts and
bridges,- Roadside slopes, drainage control
measures and vegetation,
- Road surface
* Avoid fencing across known animal and
wildlife movement routes
* Animal/wildlife crossing warnings, night time
speed limitations or perhaps closures
ENVIRONMENTAL QUALITY
INDICATORS
Pollution: Concentrations of suspended
sediments in surface waters, water turbidity,
salinity and pH.
Environmental Health: Degree of biodiversity
(numbers of plant, fish, use animal and bird
species) in road vicinities;
Extent of critical habitats;
Human Wellbeing: Occurrence of illness or
disease, Frequency of traffic accidents involving
vehicles or pedestrians; Poverty levels
83
ANNEX III.4. FOOD PROCESSING
Scope of Projects
Small-scale food processing may be home-based or small enterprises that use a wide
variety of processes and technologies to convert animal and plant products into human
food.
Food processing of all kinds can create environmental problems if not managed properly.
Solid and/or liquid wastes can be highly polluting and create offensive odors. Water use
can place excessive demands on local supplies. Wastewater containing organic and other
wastes can degrade streams and rivers, and contaminate groundwater. Stagnant pools of
polluted water can be highly odorous and provide breeding grounds for mosquitoes.
Some of the environmental impacts and mitigation measures that can apply to the target
areas are presented in Table 1.
Table 1. Potential environmental impacts and mitigation measures for food processing that
may apply to APPSA target areas.
Potential environmental Adverse effects
Human Environment
* Water supply conflicts:
- Negative social and economic effects
on existing community water management
practices relationships
- Conflicting demands on surface or
groundwater supplies
Human Health
* Illness or disease due to pollution of water
sources from food processing wastes
Mitigation measures
* Minimize water use by use "dry cleanup" (e.g.
sweeping, wiping down) of solid wastes before
washing, regulate water flows (e.g. valves, high
pressure nozzles) and reuse water
* Develop supply sources: - Where water
quantities are adequate and the project will not
conflict with existing human, livestock, wildlife
or aquatic water uses, especially during dry
seasons; - So that withdrawals do not exceed
"safe yield" from groundwater resources
* Follow General Measures above to minimize
water use and provide good management of solid
and liquid wastes
* Damaging worker health
* Provide/strengthen health and safety training,
accident prevention and equipment (e.g. face
masks, rubber gloves, boots, ear plugs, good
ventilation)
* Practice good housekeeping (e.g. clean floors
regularly, install drip trays)
* Repair and maintain machinery for safe and
quiet operation
Water Quality
* Degradation of groundwater, streams and
rivers from solid and liquid wastes; and
consequent
* Deterioration and contamination of aquatic
habitats and resident species from waste
discharges
* Follow General Measures above to minimize
water use and solid and liquid wastes
* Screen waste liquids to remove solids
* Install grease traps and skim tanks.
* Locate waste disposal sites away from surface
and groundwater sources, watercourses, housing
84
and town centers
* Ensure receiving waters for liquid wastes are
able to absorb and naturally decompose the
effluent
* Ensure waste that is stored before transport to
treatment facility or landfill cannot leak into the
ground
ENVIRONMENTAL STANDARDS
National/local standards and regulations for the
discharge of industrial wastewater to i) sewers
and ii) streams and rivers
National water quality standards and controls
Workplace health and safety regulations
ENVIRONMENTAL QUALITY
INDICATORS Pollution
Quality (nutrients, chemicals, salinity) of liquid
effluent and receiving waters
Environmental Health
Surface water flows and groundwater table levels
in project area
Productivity of aquatic environments receiving
liquid waste
Human Wellbeing
Incidence of human illness or disease
85
ANNEX III.5. STRUCTURES AND BUILDINGS
Scope of Projects
Sub-projects may include the construction of buildings notably markets and grain storage
facilities. Markets will include ancillary facilities such as sanitation, drainage, and access.
Although the envisaged construction is small-scale and likely to have localized
environmental impact, there are some precautionary measures requiring consideration in
the planning, construction and operational phases of the project cycle.
Some of the environmental impacts and mitigation measures that can apply to the target
areas are presented in Table 1.
Table 1. Potential environmental impacts and mitigation measures for structures and
buildings that may apply to APPSA target areas.
POTENTIAL
MITIGATION MEASURE
PHASE
ENVIRONMENTAL
IMPACTS
Loss of indigenous vegetation
Locate site in order to avoid
Planning Phase
or sensitive habitats
destruction of indigenous
vegetation or sensitive habitats.
Loss of productive inhabited
* Locate site on uninhabited
land and/or assets due to
land when possible. If
location of site
inhabited, follow guidelines
found in Resettlement Policy
Framework and in Operational
Manual.
* Locate site on least productive
or degraded land
Loss, of vacant or unused
Locate project on least
productive land resources and
productive or degraded land
other assets on any site
Loss of inhabited or used land,
When possible locate site on
resources and assets, by people vacant or unused land with no
without officially
usage rights issues OR affected
recognized usage rights for the
people may
site
voluntarily give up land and
assets on the site and be
provided with replacement or
restoration of losses (see RPF
and Operational Manual)
Loss of rights and used or
When possible locate site on
unused land, resources and
vacant or unused land with no
assets by people without
or fewer usage rights issues OR
officially recognized usage
affected people may voluntarily
rights for the site
give up rights, land and assets
on the site and be provided with
replacement or restoration of
losses (see RPF
and Operational Manual)
Soil erosion (note steep areas,
Locate site on level ground
Construction Phase
lack of vegetation cover and
86
high rainfall)
Removal of intact vegetation
such as trees, stream bank
vegetation etc.
Unforeseen damage to
neighboring property (e.g.
damage to vegetable garden)
Localized soil/water pollution
from incorrect storage and
handling of diesel fuel.
Localized soil/water pollution
from used engine oil.
Accumulation of solid wastes
creating health risks and
negative aesthetic impact.
Operational phase
Accumulation of non-hazardous
solid wastes creating health
risks and negative aesthetic
impacts..
poorly maintained latrines and
drainage channels drainage
Lack of shade
87
Wherever possible avoid
removal of trees or other intact
vegetation
Ensure that construction
workers vehicles and materials
do not enter neighboring
property
Carefully selected storage area
for handling of fuels to prevent
localized pollution of soils
Used engine oil should be
properly stored in drums and
returned to the supplier for
recycling or should be disposed
of in proper disposal sites.
(i)Remove and dispose of solid
waste in pits and cover with top
soil on closure; (ii)
recommended: mount
awareness campaigns for the
workforce. (iii) where possible
use building debris for backfilling and construction of
drains, soak-aways and paved
walk ways
(i) Remove and dispose of solid
waste in dedicated land fill site
or dig pits and cover with top
soil (ii) Design,
promote & conduct public
hygiene awareness campaigns
focusing on adverse health
impacts arising as a
consequence of indiscriminate
disposal of solid wastes
Establish a routine maintenance
& cleaning service through
caretaker or community action.
Through public health education
campaigns, raise awareness
about the dangers of exposed
sewage and blocked channels
Plant shade trees and shrubs
ANNEX III.6. ELECTRIC ENERGY
Scope of projects
Some sub-projects may include the rehabilitation and/or establishment of electric energy
to feed electric pumps. This would be performed most likely through the national electric
system. This will not only feed in electric pumps for irrigation schemes but can also
provide energy for local population.
Although the envisaged sub-projects are of small-scale and likely to have localized
environmental impact, there are some precautionary measures requiring consideration
especially during construction/rehabilitation and operation of the electric energy system.
Some of the environmental impacts and mitigation measures that can apply to the target
areas are presented in Table 1.
Table 1. Potential environmental impacts and mitigation measures for electric energy
systems.
Potential environmental Adverse effects
Human Environment
Risks of accidents for local population
(electrocution)
Mitigation measures
delimitation and signalization of the risk area
Awareness regarding to the risks
Biophysic Environment
Landscape modification
Ecosystem loss and fragmentation
Fauna perturbation
Increased erosion due to vegetation removal
*Vegetation removal only in justified situations;
*Vegetation recuperation whenever the risk of
erosion is high;
*Avoid ecological sensitive areas;
*Establish the system along the existing roads to
Avoid further ecosystem/vegetation loss;
*Design the system according to the local
topography
ENVIRONMENTAL STANDARDS
ENVIRONMENTAL QUALITY
INDICATORS
Land Law (areas of partial protection and
compensations due to construction)
extension of protected area and/or ecosystem
crossed or removed
Roads Law
Number of species (fauna and flora) lost
National legislation on protected areas (natural,
cultural and built environments)
Number of properties lost and compensation
Amount of soil loss due to erosion
Electric Energy Law
88
ANNEX IV: ENVIRONMENTAL AND SOCIAL FIELD APPRAISAL FORM
NAME OF PROJECT
Application Number:
(APPSA Project)
PART 1: IDENTIFICATION
1. Project Name: (for example: Rehabilitation of the Sussundenga road, Sussundenga
District)
2. Project Location: (for example: Sussundenga District, Manica Province)
3. Reason for Field Appraisal: Summarize the issues from the ESMF Checklist that
determine the need for a Field Appraisal.
4. Date(s) of Field Appraisal:
5. Field Appraisal Officer and Address:
6. Extension Team Representative and Address:
7. Community Representative and Address:
PART 2: DESCRIPTION OF THE PROJECT
8. Project Details: Provide details that are not adequately presented in the sub-project
application. If needed to clarify sub-project details, attach sketches of the sub-project
component(s) in relation to the community and to existing facilities.
PART 3: ENVIRONMENTAL AND SOCIAL ISSUES
9. Will the project:
Yes
No
* Need to acquire land?
* Affect an individual or the community's access to land or available resources?
* Displace or result in the involuntary resettlement of an individual or family?
If "Yes", tick one of the following boxes:
 The Resettlement Action Plan (RAP) included in the sub-project application is
adequate. No further action required.
 The RAP included in the sub-project application must be improved before the
application can be considered further.
 A RAP must be prepared and approved before the application can be considered
further.
10. Will the project:
Yes
89
No
* Encroach onto an important natural habitat?
* Negatively affect ecologically sensitive ecosystems?
If "Yes", tick one of the following boxes:
 The Environmental and Social Management Plan (ESMP) included in the sub-project
application is adequate. No further action required.
 The ESMP included in the sub-project application must be improved before the
application can be considered further.
 An ESMP must be prepared and approved before the application can be considered
further.
11. Will this project involve or introduce pesticides?
No
Yes
If "Yes", tick one of the following boxes:
 The Pest Management Plan (PMP) included in the sub-project application is adequate.
No further action is required.
 The PMP included in the sub-project application must be improved before the
application can be considered further.
 A PMP must be prepared and approved before the application can be considered
further.
12. Will this project involve or result in:
Yes
No
* Diversion or use of surface waters?
* Production of waste (e.g. slaughterhouse waste)?
* New or rebuilt irrigation or drainage systems?
If "Yes", tick one of the following boxes:
 The application describes suitable measures for managing the potential adverse
environmental effects of these activities. No further action required.
 The application does not describe suitable measures for managing the potential
adverse environmental effects of these activities. An ESMP must be prepared and
approved before the application is considered further.
13. Will this project require the construction of a small dam or weir? Yes No
If "Yes", tick one of the following boxes:
 The application demonstrates that the structure(s) will be designed by qualified
engineers, and will be built by qualified and adequately supervised contractors. No
further action is required.
 The application does not demonstrate that the structure(s) will be designed by
qualified engineers, and will be built by qualified and adequately supervised
contractors. The application needs to be amended before it can be considered further.
14. Will this project rely on water supplied from an existing dam or weir?
No
If "Yes", tick one of the following boxes:
90
Yes
 The application demonstrates that a dam safety report has been prepared, the dam is
safe, and no remedial work is required. No further action is required.
 The application does not demonstrate that a dam safety report has been prepared, the
dam is safe, and no remedial work is required. A dam safety report must be prepared
and approved before the application is considered further.
15. Are there any other environmental or social issues that have not been adequately
addressed?
Yes No
If "Yes", summarize them:
and tick one of the following boxes:
 Before it is considered further, the application needs to be amended to include
suitable measures for addressing these environmental or social issues.
 An ESMP needs to be prepared and approved before the application is considered
further.
PART 4: FIELD APPRAISAL DECISION

The sub-project can be considered for approval. Based on a site visit and
consultations with both interested and affected parties, the field appraisal
determined that the community and its proposed project adequately address
environmental and/or social issues as required by the ESMF.

Further sub-project preparation work is required before the application can
be considered further. The field appraisal has identified environmental and/or
social issues that have not been adequately addressed. The following work needs
to be undertaken before further consideration of the application:
All required documentation such as an amended application, ESMP, RAP, or PMP
will be added to the sub-projects file before the sub-projects is considered further.
Name of field appraisal officer (print): .....................................................................
Signature: ................................................Date: ……………………………………
91
ANNEX V: GUIDELINES FOR ANNUAL REPORT
Name of the Project:
(APPSA Project)
Application Number:
1.
Name of District or Local Government:
2.
Name and Position of Review Authority Completing the Annual Report:
3.
Reporting Year:
4.
Date of Report:
5.
Community Sub-project (s):
Water Supply
Water point rehabilitation
Earth dam rehabilitation
Community reservoirs
Small dams
Water harvesting facility
Gravity water schemes
Roads and Energy
Tertiary/secondary roads
Tertiary/secondary
road
culverts/bridges
Footpaths
Rural electrical distribution
Agriculture and markets
Terracing
Agro-processing facilities
Post harvest handling facilities
Market places
Mechanization
Natural resources management
Anti-erosion interventions and
soil fertility restoration
92
Specific TA
RAP/ARAP
PMP
EMP
Field Appraisal
Application included an
ESMF checklist
Types of Activities
Approved this year
Please enter the numbers of sub-projects in the following table.
Specific TA
RAP/ARAP
PMP
EMP
Field Appraisal
Application included an
ESMF checklist
Approved this year
Types of Activities
Demonstration/nutrition gardens
Stream and river bank protection
Wetland development
6. Were there any unforeseen environmental or social problems associated with any
sub-project approved and implemented this year? If so, please identify the subproject (s) and summarize the problem (s) and what was or will be done to solve the
problem (s). Use a summary table like the one below.
Sub-project
Problem(s)
Actions taken
Actions to be taken
7. Have any other environmental or social analyses been carried out by other public or
private agencies in your district/province? If so, please describe them briefly.
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
……………………….
8. Have you noticed any particular problems with implementing the ESMF in the past
year (e.g. administrative, communications, forms, capacity)? If so, please describe
them briefly.
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………
9. Training: Please summarize the training received in your district/province in the
past year, as well as key areas of further training you think is needed.
93
Group
Review Authority
Training Received
Approval Authority
Extension Teams
Selected
farmers/Associations
94
Training Needed
ANNEX VI: GUIDELINES FOR ANNUAL REVIEWS
Objectives: The objectives of annual reviews of ESMF implementation are two-fold:
a) To assess Project performance in complying with ESMF procedures, learn lessons,
and improve future performance; and
b) To assess the occurrence of, and potential for, cumulative impacts due to APPSAfunded and other development activities.
The annual reviews are intended to be used by APPSA management (Consultative Forum)
to improve procedures and capacity for integrating natural resources and
environmental/social management into project operations. They will also be a principal
source of information to Bank supervision missions.
Scope of Work: ESMF Performance Assessment
The overall scope of the performance assessment work is to:
a) Assess the adequacy of the sub-project approval process and procedures based on
interviews with project participants, project records, and the environmental and social
performance of a sample of approved sub-projects;
b) Assess the adequacy of ESMF roles and responsibilities, procedures, forms,
information resource materials, etc.;
c) Assess the needs for further training and capacity building;
d) Identify key risks to the environmental and social sustainability of sub-projects; and
e) Recommend appropriate measures for improving ESMF performance.
The following tasks will be typical:
a) Review provincial and district records of sub-projects preparation and approval (e.g.
applications; screening checklists; ESMPs, RAP and PMPs appraisal forms; approval
documents), monitoring reports as well as related studies or reports on wider issues of
natural resources and environmental management in the country;
b) On the basis of this review, conduct field visits of a sample of approved sub-projects to
assess the completeness of planning and implementation work, the adequacy of
environmental/social design, and compliance with proposed mitigation measures. The
sample should be large enough to be representative and include a substantial proportion
of sub-projects that had (or should have had) a field appraisal according to established
ESMF criteria (see Section 9.2 Appraisal and Approval). Sub-projects in sensitive natural
or social environments should especially be included.
c) Interview project and district officials responsible for sub-projects appraisal and
approval to determine their experience with ESMF implementation, their views on the
strengths and weaknesses of the ESMF process, and what should be done to improve
performance. Improvements may concern, for example, the process itself, the available
tools (e.g.guidelines, forms, and information sheets), the extent and kind of training
available, and the amount of financial resources available.
d) Develop recommendations for improving ESMF performance.
95
Cumulative Impacts Assessment
This part of the annual review assesses the actual or potential cumulative impacts of subprojects with other sub-projects or development initiatives on the environment, natural
resources and community groups. Cumulative impacts result from a number of individual
small-scale activities that, on their own, have minimal impacts, but over time and in
combination generate a significant impact. For example:
* Decline in groundwater levels or quality due to the construction of numerous wells and
the introduction of numerous small-scale irrigation works;
* Overwhelmed or illegal waste and dumping sites due to the inappropriate disposal of
increasing amounts of waste materials;
* Illegal poaching of wildlife due to expansion of land under cultivation or increased
proximity and access to protected areas through construction of small access roads; and
* Attraction of large migrant populations to communities that have successfully
introduced improve social infrastructure (such as schools, health centers or water sources)
resulting in overcrowding, depletion of resources (e.g. space, supplies, water), etc.
The function of this assessment is primarily as an "early warning" system for potential
cumulative impacts that might otherwise go undetected and unattended to. It will be
largely based on the observations of people interviewed during the field work, and trends
that may be noticed by district or regional officials. Where cumulative impacts are
detected or suspected, recommendations will be made to address the issue, perhaps
through more detailed study to clarify matters and what should or can be done about them.
Qualifications for Undertaking Annual Reviews:
The reviews should be undertaken by an individual or small team with training and
experience relevant to the likely issues to be encountered (e.g. environmental and natural
resources management and land acquisition and resettlement). They should also be
familiar with the methods and practices of effective community consultation, and with
typical methods and processes for preparing, appraising, approving and implementing
small-scale community development projects.
Timing:
Annual reviews should be undertaken after the annual monitoring report has been
prepared and before Bank supervision of the project, at the closing of each year of the
project. It is expected that each review would require 3-4 weeks of field work (interviews,
examination of sub-projects), and that the review report would be completed within 2
weeks of completing the field work.
Outputs:
The principal output is an annual review report that documents the review methodology,
summarizes the results, and provides practical recommendations. Distinct sections should
address: a) ESMF performance and b) cumulative impacts. Annexes should provide the
detailed results of the field work, and summarize the number of approved sub-projects by
district and their characteristics according to the annual report format (see Annex V).
96
Copies of the annual review report should be delivered to APPSA Consultation Forum, to
each district/provincial office responsible for appraisal, approval and implementation of
sub-projects, and to the World Bank. The Provincial Review Panel may also want to host
national or district workshops to review and discuss the review findings and
recommendations.
97
ANNEX VII: GUIDELINES FOR AN ESMP
When a sub-project includes distinct mitigation measures (physical works or management
activities), an Environmental and Social Management Plan (ESMP) needs to be included
with the sub-project application.
ESMP Contents:
An ESMP usually includes the following components:
 Description of adverse effects: The anticipated effects are identified and summarized.
 Description of mitigation measures: Each measure is described with reference to the
effect(s) it is intended to deal with. As needed, detailed plans, designs, equipment
descriptions, and operating procedures are described.
 Description of monitoring program: Monitoring provides information on the
occurrence of environmental effects. It helps identify how well mitigation measures
are working, and where better mitigation may be needed. The monitoring program
should identify what information will be collected, how, where and how often. It
should also indicate at what level of effect there will be a need for further mitigation.
How environmental effects are monitored is discussed below.
 Responsibilities: The people, groups, or organizations that will carry out the
mitigation and monitoring activities are defined, as well as to whom they report and
are responsible. There may be a need to train people to carry out these
responsibilities, and to provide them with equipment and supplies.
 Implementation schedule: The timing, frequency and duration of mitigation measures
and monitoring are specified in an implementation schedule, and linked to the overall
sub-project schedule.
 Cost estimates and sources of funds: These are specified for the initial sub-project
investment and for the mitigation and monitoring activities as a sub-project are
implemented. Funds to implement the EMP may come from the sub-project grant,
from the community, or both. Government agencies and NGOs may be able to assist
with monitoring.
Monitoring Methods:
Methods for monitoring the implementation of mitigation measures or environmental
effects should be as simple as possible, consistent with collecting useful information (see
example below) and that community members can apply themselves. For example, they
could just be regular observations of sub-project activities or sites during construction
and then use. Are fences and gates being maintained and properly used around a new
water point?; does a stream look muddier than it should and, if so, where is the mud
coming from and why?; are pesticides being properly stored and used? Most observations
of inappropriate behavior or adverse effects should lead to commonsense solutions. In
some cases (e.g. unexplainable increases in illness or declines in fish numbers), there may
be a need to require investigation by a technically qualified person.
98
Table 1. Example of monitoring water quality from a drainage project
Item
Operation Phase
Ground
water
quality
Monitoring
Parameter
Sampling
Frequency
Monitoring
Location
pH
salinity
Alkalinity
conductivity
ammonia
Total nitrates
Phosphorus
Pesticide scans
BOD
COD
Monthly
tube wells, tile
drain
outfalls
and/or monitoring
wells
Surface
water
quality
–
receiving water
pH
salinity
Alkalinity
conductivity
ammonia
Total nitrates
Phosphorus
Pesticide scans
BOD
COD
Coliforms
weekly
Drainage quality
pH
salinity
Alkalinity
conductivity
ammonia
Total nitrates
Phosphorus
Pesticide scans
BOD
COD
Coliforms
Weekly
above and below
project influence
and at strategic
stations
below
and
above
drainage outfalls
at minimum 500
meters; if the river
exceeds 3 meters
depth, samples at
all stations should
be at surface and
60-80% of depth
At
point
of
discharge
99
ANNEX VIII: VISITED SITES, CONSULTED STAKEHOLDERS AND KEY
OBSERVATIONS
Site visits to the agrarian research stations were carried out between 10th December 2012
and 8th of January 2013. In general, there are several environmental concerns in the target
areas and the contacted stakeholders in each site are presented in Table 1.
Umbelúzi Agrarian Station
The Umbelú Agrarian Station was founded in 1909 and is Located in Umbelúzi, Boane
District in Maputo Province. The area of 60 ha belongs to IIAM (with the DUAT) where
several experiments on legumes, roots, maize and rice are taking place.
The main problem in this station is related with the irrigation scheme which is from the
colonial period and has never received a profound maintenance. According to the head of
the station, the main needs associated with the system are: two electro-bombs,
maintenance of the main dike (full of grass, sand and other detritus), and rehabilitation of
main walls, among others. As a result of these problems the water drainage is insufficient
and thus soils have become saline. During site visit it was observed at thin salt layer over
the soils, in an area that will probably be used as the APPSA experimental area (Figure 1).
No problems were reported in terms of either water quality or quantity. Water quantity is
sometimes a stress specially when different crops are in the field at the same time, but
with an accurate irrigation schedule, water is enough for all experiments.
100
Figure 1. Salt layer over the soils in the Umbelúzi Agrarian Station.
Nicoadala Research Station
Nicoadala Research Station was founded in 2006 and is located in Nicoadala District
about 15 km north of Quelimane. The experimental fields, of about 85 ha, are located in
Mucelo along the EN1 road, in the right hand side of the Mucelo River an affluent of the
Bons Sinais River, at approximately 273541 E and 8045596 S. IIAM has the land rights
(DUAT) of the area. In the area there are several small (100x50m) rice fields belonging
to local communities. Some temporary houses are found in the area and these belong to
farmers that are only present in the zone during the rice campaign (November/December
to March/April). A power line crosses the area (Figure 2).
101
Figure 2. IIAM’s experimental fields in Nicoadala (Mucelo).
Main environmental and social problems in this area are related with water salinity
(electrical conductivity of Rio Mucelo is 6.638 μS/m and the pH of 5.8), but the soils do
not present major salinity or other problems (electrical conductivity of 211.3 to 683.3.
μS/m and a pH of 4.4.3 and 4.86). Water salinity is higher during the dry season when
river flow is lower and saline waters from the ocean enter the river through the Bons
Sinais River. Socially, the area is being cultivated for rice by around 100 farmers and
several conflicts with IIAM were reported during the site visit such as farmers not
allowing IIAM to cultivate the area, which resulted in the need for police interference.
During the site visit, famers were very renitent in talking to the consultant and inquired
the reasons for her presence.
APPSA will not develop any activity in this area, given the high salinity of the water
from the Mucelo River and thus, an area belonging to DPA in Namacurra District was
selected for APPSA.
Namacurra DPA’s area
The visited site in Namacurra District is located at about 105 km north of Quelimane,
along the EN1 road. The site belongs to DPA where a rice processing facility exists and a
seed laboratory infrastructure is being built. The area for rice cultivation is located in the
low lying area in the margin of the Nadobe River at about 272920 E e 8046086 S. The
area belongs to the Maulati (ou Dualia) community. Presently there are a bit over 100
farmers cultivating the area (small farms of 100 x 50 m) and they reported having bought
the land from an individual.
APPSA will develop the RCoL for rice in an area of 50 ha. Probable project’s activities in
this area include: resettlement (of existing farms), construction of an irrigation scheme
and mechanization of the area.
No major environmental problems were found in this area (soil electric conductivity of
589 μS/m and pH of 5.71; water electric conductivity of 13.40 μS/m and pH of
6.39). Major social problems in this area are related with resettlement of rice farms (over
100 small farms). However during conversations in the field people willing to move their
farms to other places, but they reported not knowing any free areas for cultivation nearby.
102
Table 1. List of visited sites and consulted stakeholders.
Province
Research Station
Maputo
Umbelúzi
Gaza
Chóckwe
Manica
Sussundenga
Zambézia
Nicoadala
(Mucelo)/Namucurra
(Dualia,Maulate)
Nampula
Nampula
Consulted stakeholders
Enga. Paciência Banze (Head of the RS)
103
IIAM- Eng. Hideraldo Duarte (Researh
Station)
DPA – Eng. Ilidio Afonso José Bande
SDAE (Nicoadala) – Sr. Nel da Graça
Bartolomeu
DPCAEng.
António
Osvaldo
Paqueleque
Download