MCM-10AUG09 - Indico

advertisement
Muon Commissioning Meeting 10 August 2009
Present: Antonio, Davide, Fernando, Giovanni and Burkhard
Online:
Roberta
Muon System Status – week 32
•
Due to network problems the online cluster, DBs etc. were not
operational from Monday to Thursday. Therefore work resumed only
on Friday. As a consequence not much progress has been made with
the timing tests etc.
•
Due to missing pieces the progress with the turbine was very
slow. Only today we received 2 turbines for re-installation. M25C
should be complete4d this week, M1 next week.
Issues related to the LHCb general planning (Burkhard):
•
The re-installation of the access structures on the bunker
extension for A- and C-side is scheduled for the 2nd part of
August and should be completed by August 31. The accessstructures should be sufficient for the remaining interventions
planned on the chambers.
•
The LHC TED run is now scheduled for September 26/27 without LHCb
participation (due to the Florence LHCb week). A TED run with
LHCb participation has been requested for a weekend in October.
No date fixed yet. Therefore there is no urgent need any longer
to close M1 and the rest of detector in the week of August 31.
•
We should aim at completing our interventions by September 11, so
that we can close M1 (and subsequently the calorimeters) in the
week of September 14, the week prior to the LHCb week. Like that
we are ready for the Global commissioning week scheduled for the
week of September 28.
Moving control for M1:
•
According to the present planning of LNF, this should be
completed in the week of September 7. A delay should be avoided,
so the system can be commissioned and used in the week of
September 14.
DSS issues (Burkhard):
•
The thresholds for water leak detection, mainly on M25 C-side,
need to be raised to avoid the frequent DSS alarms we get at
present. To be done when Laurent and Nikolai are back from
vacation.
PVSS for HV system and GEM HV system (Giovanni):
•
Michela Lenzi comes on August 14 to CERN and will work on the
upgrade of the projects to PVSS 3.8 and the integration of the
GEM HV in the overall PVSS HV project.
•
Powering of the GEMs with HV foreseen for the week of August 24
with Farbizio et al. Two channels of the GEM gas system don’t
work at present should be investigated before HV is put on.
Continuation of timing tests (Antonio/Dimtry/Fernando):
•
•
First round of connectivity and phase tests has been completed
for A- and C-side:
A-side: 17/24 are ok;
C-side: 20/24 are ok.
Time alignment has been done for 14 HUs (which passed
successfully the first round) on the A-side and for 9 (good) HUs
on the C-side.
ECS activities (Davide):
•
Davide summarized the plans for optimizing the threshold and HV
settings of the Muon system (for details have a look at the
slides uploaded to the agenda page).
•
The plans are as follows (updated with respect to the slides):
–
Week 10/08-14/08 (Davide + Giovanni + Lukas):
debugging and threshold scan at 110 r.u.
–
Week 17/08-21/08 (Giacomo + Antonio + Lukas):
noise runs
–
Week 24/08-28/08 (Giacomo + Antonio + Lukas):
cosmics at HV= 2650V. A Muon stand-alone trigger (M3 in
AND) will have to be used because the calorimeters will be
still open to allow M1 interventions.
–
Week 31/08-04/09 Global Commissioning week
–
Week 14/09-25/09 :
cosmics at HV=2550V and HV=2450V
–
Week 28/08-02/10 Global Commissioning week
–
Week 05/10-09/10 :
cosmics at optimal HV/thresholds a la Walter
–
–
Week 12/10-16/10 :
cosmics at optimal HV/thresholds a la Anatoli
A.o.B.
Next muon commissioning meeting will take place Monday August 31 at
14:30 at the pit – unless Fernando sees the need to call for a meeting
also on August 24, in two weeks from now.
Download