58159 Procurement Packages with Methods and Time Schedule

advertisement
58159
Procurement Packages with Methods and Time Schedule, Component 1 for UBEDN investment, IDA46730-MN
1
Ref. No.
2
Contract
Description
LOT#1, Test van for 35 kV cables,
Package#1 LOT#2, Underground cable pulling
machine
LOT#1, Replacement of 22 Nos.35kV
obsolete oil filled circuit breakers by
Package#2 SF6 equipment, (29 cubicles)
LOT#2, Replacement of 177 Nos. 6 and
10 kV obsolete oil filled circuit breakers
by vacuum circuit breakers, (370
cubicles)
Augmentation and Rehabilitation of
"Esgiilekh", Uprating capacity to
Package#3 2x25mVA, new 35 kV(110kV size)
OHL from Power Plant “TETs-3”,
replacement of obsolete circuit breakers
(2 sets SF6 breaker, 30 sets VCB),
New 35/10kV substation “Khandgait”
around “Bayanbulag” summer camp and
Package#4 connect it by new double OHL about
7.5km from “Yargait” 35/10kV
substation
3
4
5
6
7
Estimated
Cost
Procure
ment
Method
Prequalifi
cation
(yes/no)
Domestic
Prefere
nce
(yes/no)
Review
by Bank
(Prior /
Post)
ICB
No
No
Prior
Supply of
Goods
Nov 01,
2010
Mar 15,
2011
ICB
No
No
Prior
Supply and
Installation
Jan 15,
2011
May 15,
2011
$1,720,000
ICB
No
No
Prior
Supply and
Installation
Dec 15,
2010
Apr 15,
2011
$1,070,000
ICB
No
No
Prior
Supply and
Installation
Dec 15,
2010
Apr 15,
2011
LOT#1
$220,000
LOT#2
$155,000
Total:
$375,000
LOT#1
$780,000
LOT#2
$2,100,000
Total:
$2,280,000
8
9
10
Type of
Contract
Expected
(Supply
BDs
and
Issuing
Installation
Date
/Procureme
nt of
Goods)
1
Expected
Contract
Signing
Date
(Eastern Distribution Network)
1. Installation of new 10kV double cable
line from 110/35/10kV substation
"Tuul" to a new switching station at the (1)$ 670,000
Package#5 "Zuun Selbe" Khoroolol
(2)$ 810,000
2. Installation of new 6kV double cable
Subtotal:
line from 35/6kV substation "4 Zam” to
$1,480,000
a new switching station around
substation No.114
(Eastern Distribution Network)
1. Installation of new 10kV double cable
line from 110/35/10kV substation
"Umnut" to a new switching station at
(1)$ 750,000
Package#6 the "Zaisan"
(2)$ 750,000
2. Installation of new 10kV double cable
Subtotal:
line from 110/35/10kV substation
$1,500,000
"Dornot-2" to a new switching station at
the "Ikh Zasag" University
(Western Distribution Network)
1. Installation of new 6kV double cable
line from Central cable line No.7 and 8
of 35/6kV substation “Esgiilekh” to a
new switching station around river
“Dund gol” (22 switchgear)
Package#7 2. Installation of new 6kV double cable
line from Central cable line No.5 and 6
of 35/6kV substation “Esgiilekh” to a
new switching station around substation
“Talkh” (13 switchgear)
3. Installation of new 10kV double cable
line from 110/10kV substation “Baruun”
to a new switching station around
substation “Nasos-6”
Total amount
(1)$ 480,000
(2)$ 380,000
(3)$ 820,000
Subtotal:
$1,680,000
ICB
No
No
Prior
Supply and
Installation
Dec 15,
2010
Apr 15,
2011
ICB
No
No
Prior
Supply and
Installation
Dec 15,
2010
Apr 15,
2011
ICB
No
No
Prior
Supply and
Installation
Dec 15,
2010
Apr 15,
2011
$10,680,000
6,780,000.00 SDR x 1.58USD=10,705,263.00 USD
2
Consultancy Assignments with Selection Methods and Time Schedule, Component 2 for Distribution Network Development
and Planning
1
2
3
4
Ref. No.
Description of Assignment
Estimated
Cost
Selection
Method
5
Review
by Bank
(Prior /
Post)
Package#8
Distribution network planning
software and associated training
$147,500
QCBS
Prior
Package#9
Transmission network planning
software and associated training
$147,500
QCBS
Prior
Package#10
Consultancy services for network
planning
$300,000
QCBS
Prior
Consultancy services for design and
$300,000
standard
Total amount
$895,000
566,000.00 SDR x 1.58USD=893,684.00 USD
QCBS
Prior
Package#11
6
Expected
Proposals
Submission
Date
7
Comments
EOI issuing date is December, 2010
Jan 20, 2011 TOR issuing date is December, 2010
Contract sign date is February, 2011
EOI issuing date is December, 2010
Jan 20, 2011 TOR issuing date is December, 2010
Contract sign date is February, 2011
TOR issuing date is February, 2011
Mar 01, 2011 Contract sign date is May, 2011
Contract completion date is after 12 months
TOR issuing date is February, 2011
Mar 01, 2011 Contract sign date is May, 2011
Contract completion date is after 12 months
Capacity building and Incremental financing, Component 3
Description
Study tours and short time courses for capacity building
Incremental cost for project administration
Total amount
Estimated Cost
$220,000
$180,000
$400,000
Comments
254,000.00 SDR x 1.58USD=401,053.00 USD
Grand Total Amount, US Dollars
$12,000,000
3
Download