An Introduction to Agile Estimation

advertisement
Inflectra Corporation
8121 Georgia Ave, Suite 504
Silver Spring. MD 20910-4957
+1 202.558.6885
www.inflectra.com
An Introduction to Agile Estimation
Background Topic
August 2014
An Introduction to Agile Estimation
Abstract
Traditional software development estimating techniques are slow, long lasting exercises and as such are
totally unsuited to Agile processes. New methods of estimating have emerged which fit the Agile model,
requiring minimal effort to provide ‘just enough’ information to support prioritization and decision making.
This paper offers an introduction to the most popular of these techniques, as well as a look at how such
practices work in larger, multi-team projects in which normalization has become the subject of
disagreement.
Introduction
Traditional estimating techniques used in predictive, phased projects are meant to produce time
estimates for tasks or related sets of requirements. Those of us who have sat through such estimation
meetings, (often under the misnomer ‘planning’ meetings) will know what a painful experience this can
be. There are often endless discussions about how complex ‘X’ really is and how long it will take to code.
The problem is that each task is considered independently of the others. It doesn’t help that each person
tends to think about the problem from the perspective of doing the work themselves and naturally,
degrees of (perceived and real) expertise vary from one individual to another.
Story Points
The human brain is far better at making comparisons than it is at making individual value judgments. You
can usually identify the longer of two books, but accurately estimating how many pages either has is
extremely difficult. This principle is the basis of the deceptively simple and yet highly successful device
known as story points.
Story points are an abstract measure; they have no units. All we know is that 2 story points take twice as
long to code and test as 1 story point, and 4 story points take twice as long as 2, and so on. That begs
the question: How can we estimate something on the basis of an abstract measure? Further, how can we
overcome the problem of individuals estimating based on their own individual abilities?
Estimation Methods
There are two popular estimating methods, both of which overcome these difficulties. Both share three
key characteristics:
1. All team members must participate,
2. Only relative judgments will be made, and
© Copyright 2014, Inflectra Corporation
Page 2 of 8
This document contains Inflectra proprietary information
3. Each method is carried out as a game.
Planning Poker
The first method is referred to as ‘planning poker’ and was originally described by James Grenning (2002)
and popularized by Mike Cohn in, ‘Agile Estimating and Planning’ (2005). The game goes something like
this:
1. A user story is read to the entire team, whereupon each team member estimates the number of
story points without revealing his/her educated guess,
2. All estimates are revealed at the same time,
3. High and low estimates are explained by their proponents, with subsequent discussion,
4. The secret estimation process is then repeated before returning to step 2.
Estimates usually converge quickly, but if one or two team members are unable to concur after repeated
discussions, the majority view is taken. One other critical element of planning poker is the permissible
values of the estimates, which can only be a number in the Fibonacci i series: 1, 2, 3, 5, 8 or something
similar to it such as 1, 2, 4, 8. This is because accurate value judgments are more difficult when things
get larger. For example, when using only whole numbers, a 20% divergence from 1 is still 1; which is
quick and easy. However, a 20% divergence from 8 is either 7 or 9, which becomes more difficult.
Eliminating 7 or 9 as options makes the answer 8, which is again, quick and easy.
Figure 1: Fibonacci Series
This process ignores one key element. When the team estimates the very first story, how does each team
member know what constitutes a single story point? There is no point (pun intended) of reference for
them to use. Remember, we are using comparative methods, and with the very first story, there is nothing
to compare it to. This catch-22 is solved by using a reference story. The team as a whole finds the
smallest user story, (ignoring those requiring almost zero effort) and agrees to call that 1 story point. All
subsequent estimates will be relative to that story. Occasional reminders of the reference story are a
good idea to achieve consistency.
Two-Stage Estimating
The second estimation method avoids this problem by starting the process with the second story, not the
first, thus making possible an immediate comparison. This method has two stages. In the first stage, the
initial user story is placed in plain view, on a wall or table, for example. The first team member takes the
next user story and places it:
© Copyright 2014, Inflectra Corporation
Page 3 of 8
This document contains Inflectra proprietary information

To the left of the first story, indicating that it requires less work than the first story,

To the right, indicating that it requires more work, or

Underneath another story, indicating that it requires about the same amount of work.
Each team member takes a turn placing a new user story relative to the others. Team members have one
other option during their turn: they may move a previously placed story to another location if they disagree
with the original placement. Play goes on until there are no more stories and nobody wants to rearrange
the order. At this point, the stories have a relative order, but are not yet assigned story points. This is
done in stage two.
Figure 1: Relative sizing
Stage two also requires a Fibonacci sequence, or something similar. The number 1 is placed above the
leftmost story column, representing the smallest user story. The first team member takes the next
number, 2, and places it above the stories he/she believes to be twice the work of the first column. This
does not have to be the adjacent column of stories. The next player takes the next number and assigns it
to a column of stories in the same way. Each player has one other option, which is to replace the previous
number with theirs, e.g. they may feel that the stories assigned 5 may in fact be 8 and that there are no
5s and so 5 is not used. Optionally, the rules may allow a player to also move a user story after it has
been assigned a number if it is now apparent that its position is wrong. Once all numbers have been
placed and agreed, stories not located beneath numbers are collected beneath the previous number; they
are effectively rounded down, not up.
© Copyright 2014, Inflectra Corporation
Page 4 of 8
This document contains Inflectra proprietary information
Figure 3: Assigning story points
In both games, the value zero can also be used in the case where the smallest user stories are really
considered to be 30 minute tasks and can be rolled into others at little or no cost. Be aware that only a
limited number of zero story point items will really be free. Too many and they will add up to one or more
story points.
These estimation methods can be used before a project is in full swing when estimates are required for
the backlog, (in Scrum terms) and when new stories are identified or existing stories change.
The next question is, how do we know how many story points we can assign to any iteration? This is
where velocity comes in.
Velocity
Velocity is a measure of how many story points a team can implement in one iteration, based on previous
performance. It is essential that story points and velocity remain abstract to avoid teams falling back into
the old habits of absolute, time-based estimating. But by inference, velocity does assign an absolute time
value to a story point in the following way: take the number of days available to the entire team in an
iteration, subtract non-coding/testing duties such as vacation, meetings, etc., and divide by the velocity.
The result is the number of team person days per story point. For example:

A team of 5 people potentially has 50 team days available per 2-week iteration,

Each person spends, on average, 1 day per week in meetings, on vacation, or unavailable for
other reasons, which is 2 days per iteration,

Their velocity is 46.5.
50 – (5 x 2) / 46.5 = 0.86 team person days per story point
It is important to realize that the value ‘team person days’ is an average of all team members and that all
team members must be participating in the iteration for the velocity to be meaningful. If 3 experienced
coders are replaced with junior team members for an iteration, the expected velocity for that iteration
must be reassessed.
While a story point time estimate can be easily calculated, it is not helpful to do so. In fact, it undermines
the entire concept of story points because it leads back to the temptation to estimate based on the time
required to complete a story, and as we shall see, there are many reasons why this is not good practice.
© Copyright 2014, Inflectra Corporation
Page 5 of 8
This document contains Inflectra proprietary information
The temptation is greatest for engineers new to Agile practices, and for managers who, despite working
with Agile principles, feel rather uncomfortable without estimates of ‘man-days’ appearing somewhere in
their plans.
Relating Story Points to Time
So, why don’t we relate story points directly to time so that we know how long each story point, and
therefore each story, will take to complete? There are two major reasons, and both are related to velocity.
The first reason we don’t want to relate story points directly to time is that velocity is not constant, at least
it shouldn’t be. As team members become more familiar with the project, the process, the environment
and with each other, their productivity should go up. In other words, a team should show an increase in
velocity as the project progresses. If we were directly relating story points to time, we could only ever
assign the same number of story points for each iteration because the time available remains constant,
whereas a variable and increasing velocity means the team is working faster and so we can assign more
story points per iteration.
The second reason is critical on projects with multiple teams. Teams are not always the same size which,
along with differing experience and expertise, affects how much work a team can do in one iteration.
Thus, team velocities are rarely the same. A team with a greater velocity will complete more story points
than one with a lower velocity. The differing velocities tell us how many story points we can assign to
each team per iteration. If stories were measured by time, each story would need a separate time
estimate for each team, each estimate being different, which is clearly absurd.
Having recognized that different teams have different velocities, we should also be able to conclude that
the size of a story point may also vary from one team to another. Each team may have a consistent view
of what a story point means to them, but across teams, story points may not be the same. This leaves us
with a project reporting problem because it will not be possible to aggregate story points completed or
planned across teams; they are using the same terminology, but not the same measures. It also means
that velocities are not comparable across teams. A velocity of 7.5 might, in fact, be lower than one of 6.2
simply because the size of the first team’s story point is far smaller. All of this is fine provided each team
has its own backlog and does its own estimates. Aside from reporting, teams operating entirely
independently will not have a problem. But is this what we want?
© Copyright 2014, Inflectra Corporation
Page 6 of 8
This document contains Inflectra proprietary information
Figure 4: Story point size may differ across teams
To Normalize or not to Normalize?
Having totally autonomous teams reduces the flexibility that should exist in Agile projects to
accommodate change and new user stories. Change may dictate that stories be transferred from one
team to another. In fact, the job of the product owner would be far easier if he/she were able to allocate
stories to teams dynamically as the project progresses, rather than dealing all the stories out to the teams
at the start. To harmonize the teams and get them using the same estimation values they must have the
same definition of a story point, which is achieved by a process called normalization.
There is no firm agreement within the Agile community as to whether normalization is a good or bad
thing. Some say it is a waste of time and that up-front story allocation works perfectly well. Others say that
teams need to be on the same page in order to achieve full agility and easier status reporting. While the
debate continues, it is worth examining the methods of normalization.
Normalization Methods
To normalize estimation, the temptation is to yet again fall back on time; we all know what 1 day is, so
why not use that as a common unit of measurement instead of story points? As soon as we do that, we
lose all the benefits of relative estimating which we discussed earlier. However, without resorting to time
estimation, we can still use the one-day-of-effort measure to bring a degree of consistency to the
reference stories used by each team, against which they will compare the others.

First, in a cross-team meeting, the definition of 1 day of effort is agreed by all, (accounting for
vacations, administrative duties, meetings, etc.). This is sometimes called an Ideal Developer
Day, or simply, Developer Day.

Next, a 1 developer day reference story which fits the agreed definition is chosen by each team
from stories they know well.

Finally, the fact that this 1 story point reference was estimated as taking 1 day is forgotten and
the story point once again becomes an abstract measure.
This process will not give perfect story point symmetry, but it will be close enough for stories to be
transferable across teams and for aggregate reporting to be meaningful. It can also help individuals new
to Agile processes to initially think of a story point as 1-day of effort, although the temptation to continue
indefinitely with this way of thinking should be resisted.
If greater consistency is required, another normalization technique can be used which involves team
representatives gathering for a common estimation meeting to identify stories for which they have an
agreed understanding. They then estimate each story using the method chosen for the project, assigning
story points to each. Optionally, each representative can first take the set of stories back to their team for
estimation after which those results are used for estimating in the higher level meeting. This set of stories
now provides a baseline of agreed estimates which is used by each team to calibrate their own estimating
process. This meeting of the minds should occur before even the first iteration; before estimating begins,
and then occasionally throughout the project to re-synchronize.
Remember, normalization is not mandatory and the effort required should only be expended if there is a
belief that the benefits are worth it for the project: after all, in the end it’s all about return on investment
(ROI.)
One final word about normalization. Some people think they are normalizing velocity across teams so that
team performance can be compared. This is totally invalid. As we have shown, team sizes, experience
and environments may vary greatly, so velocity should, and does, vary across teams and even for the
same team over time, whether story points are normalized or not.
© Copyright 2014, Inflectra Corporation
Page 7 of 8
This document contains Inflectra proprietary information
Summing Up
It must be remembered throughout all of these processes that estimation is not an end in itself and
therefore under an Agile philosophy, as little effort as possible should be used in order to get the job
done. Estimates are necessary for prioritization of the backlog and to achieve meaningful allocations for
each iteration, but digging deep in an attempt to increase accuracy is wasteful. By doing so the user story
begins to undergo analysis which should be part of implementation, not estimating and planning. As with
many activities, the law of diminishing returns also applies to estimating; “don’t take too long, you’re not
going to get significantly better results.”
Finally, the best estimates come from collective views of the entire team. Using only your managers or
experts will tend to result in optimistic estimates. Conversely, using mostly individuals new to the team is
likely to result in estimates larger than necessary. Include everyone; after all, it’s the Agile way.
Bibliography
http://scrummethodology.com/scrum-effort-estimation-and-story-points/
http://scaledagileframework.com
Cohn, Mike. Agile Estimating and Planning. Prentice-Hall, 2005.
Chris Sims & Hillary Louise Johnson. The Elements of Scrum. Dymaxicon, 2011
Dean Leffingwell. Agile Software Requirements. Addison-Wesley, 2011
i
The Fibonacci series is the sequence of numbers in which the next number is a sum of the previous 2 numbers.