Metrics Methodology

advertisement
Extremely Expensive Program (XXP)
Metrics Methodology
June 17, 2015
Dr. Jennifer Booker
XYZ Corporation, Inc., PLC, GmBH
TABLE OF CONTENTS
1
2
3
4
5
Introduction ............................................................................................................................ 1
1.1 Background........................................................................................................................ 1
1.2 Scope and Assumptions..................................................................................................... 1
1.3 Objectives .......................................................................................................................... 1
1.4 Constraints ......................................................................................................................... 1
References ............................................................................................................................... 2
2.1 CMM Traceability ............................................................................................................. 2
2.1.1 Software CMM ............................................................................................................ 2
2.1.2 Systems Engineering CMM......................................................................................... 3
2.2 Terminology ...................................................................................................................... 3
Measurement Basics ............................................................................................................... 4
3.1 Why Measure? ................................................................................................................... 4
3.2 How do we Measure? ........................................................................................................ 5
3.3 What can be Measured? .................................................................................................... 6
3.3.1 Fundamental Measurement Types ............................................................................... 6
3.3.2 Complex Measurements .............................................................................................. 8
3.3.3 Before and After Measurements .................................................................................. 8
How do we Choose What to Measure? ................................................................................. 9
4.1 Identify Your Business Goals ............................................................................................ 9
4.2 Identify What You Want to Know or Learn ...................................................................... 9
4.3 Identify Your Subgoals .................................................................................................... 10
4.4 Identify the Entities and Attributes .................................................................................. 11
4.5 Formalize Your Measurement Goals............................................................................... 11
4.6 Identify Quantifiable Questions and Indicators ............................................................... 12
4.7 Define Your Measures ..................................................................................................... 13
4.8 Identify the Data Elements .............................................................................................. 14
4.9 Identify the Actions Needed to Implement Your Measures ............................................ 14
4.10 Prepare a Plan .................................................................................................................. 15
How can we Present Measures? .......................................................................................... 16
5.1 Graphing Conventions ..................................................................................................... 16
5.1.1 Graph Terminology ................................................................................................... 16
5.1.2 Units .......................................................................................................................... 17
5.1.3 How Much Data Fits? ................................................................................................ 17
5.2 Pie Chart .......................................................................................................................... 19
5.3 Check Sheet ..................................................................................................................... 19
5.4 Pareto Diagram ................................................................................................................ 19
5.5 Histogram (Bar Chart) ..................................................................................................... 20
5.6 Run Chart (Line Chart) .................................................................................................... 22
5.7 Scatter Diagram ............................................................................................................... 23
5.8 Control Chart ................................................................................................................... 24
5.9 Cause and Effect Diagram (Fishbone)............................................................................. 25
XXP Metrics Methodology
1
Introduction
This Metrics Methodology describes a recommended methodology for identifying and describing
measures, and deciding how they can be presented. [This was adapted from a real document,
which was cleaned up to alleviate any proprietary issues.]
1.1
Background
This document was written for a particular contract, though the methodology described is widely
applicable.
1.2
Scope and Assumptions
All projects within XXP are responsible for using this methodology to identify relevant metrics,
then collect, analyze, and report them on a regular basis (e.g. at least monthly). Guidance for
performing these activities is provided in sections 3 through 5 of this document.
1.3
Objectives
This methodology needs to support basic measurement objectives for the XXP contract:

Help identify measures which demonstrably support the program’s needs

Clearly define how those measures will be calculated and graphically presented
More generally, this methodology helps the XXP measurement program meet the following
objectives:

To meet the measurement and reporting requirements of the XXP contract

To meet project management requirements

To support meeting Software CMM Level 3 process maturity requirements, and establish a
sound quantitative framework for higher maturity levels (e.g. Continuous Process
Improvement, Defect Prevention, etc.)
1.4
Constraints
The measures must be consistent with the following constraints on how they may be defined,
collected, and/or used.
Process Constraints
 Processes must be consistent with organization’s Standard Engineering Processes.
 The SEI Capability Maturity Model (CMM) for Software, version 1.1, dated 1993
(CMU/SEI-93-TR-024).
Tool Constraints
 The existing methodology for program management
 The major COTS products used in the modernized system
Page 1
XXP Metrics Methodology
Contractual Constraint
 The XXP contract for development and implementation of the modernized system
(see References, section 2.2). The contract includes the Statement of Work (SOW),
Performance Requirements, and Performance Bonus Plan.
2
References
This methodology supports industry best practices for software development and maintenance,
such as those practices identified by IEEE standards, SEI, STSC, SPMN, PMI, and the NIST.
Specific industry references include:

2.1
Booker, Jennifer, “Statistics for Software Process Improvement,”
http://cci.drexel.edu/faculty/gbooker/INFO630/statistics.pdf, 2015.

Brassard, Michael, and Ritter, Diane, “The Memory Jogger II,” Goal/QPC, First Ed.,
1994 (http://www.goalpqc.com)

Capability Maturity Model (CMM) for Software, version 1.1, dated 1993
(CMU/SEI-93-TR-024).

Fagley, Kara, “Basic Seven Tools of Quality,” http://www.freequality.org/beta
freequal/fq web site/training/Basic7ToolsofQuality[1].ppt

IEEE-1045, “IEEE Standard for Software Productivity Measures,” 1992.

IEEE-1061, “IEEE Standard for a Software Quality Measures Methodology,” 1988.

IEEE-982.1, “IEEE Standard Dictionary of Measures to Produce Reliable
Software,” 1988.

Ishikawa, Kaoru, “Guide to Quality Control,” ISBN 92-833-1036-5, Productivity Press,
1986. Source for Ishikawa’s seven tools.

Kan, Stephen H., “Measures and Models in Software Quality Engineering,”
Addison-Wesley Pub Co; ISBN: 0201633396, 1995. This also describes Ishikawa’s
seven basic tools for presenting measures, which are summarized here in section 5.

Park, Robert E., “Goal-Driven Software Measurement — A Guidebook,”
CMU/SEI-96-HB-002, 1996. This describes the GQ(I)M approach summarized here in
section 4.

Systems Engineering Capability Maturity Model (SE-CMM), CMU/SEI-95-MM-003
CMM Traceability
2.1.1 Software CMM
This Plan supports the common feature of "Measurement and Analysis" for all Key Process
Areas (KPA’s) of the Software CMM, and will eventually support the Quantitative Process
Management KPA.
Page 2
XXP Metrics Methodology
2.1.2 Systems Engineering CMM
This Plan also supports the Systems Engineering CMM's generic practice "Track with
Measurement," and will eventually support the common feature "Establishing Measurable
Quality Goals."
2.2
Terminology
General XXP terminology is described in the XXP Quality Management Terminology document.
Some specific measurement concepts of interest include the following.
Term
Definition
Data
Element
Some quantity needed to calculate the value of a measure.
Data Source
The repository from which a data element is measured.
Goal
A high level business objective
Indicator
A means of graphically presenting one or more measures
Information
The result of comparing a measure to an internal or external measurement
standard.
KLOC
Thousand lines of source code; a commonly used measure for software size.
Measure
A specific characteristic used to quantify an attribute of something.
Metric
A means of measuring something.
Subgoal
An objective which supports meeting a goal; here, subgoals are defined by each
project organization within the program.
Page 3
XXP Metrics Methodology
3
Measurement Basics
This section describes the reasons for measuring a project, how measurements are made, and the
types of characteristics which can be measured.
3.1
Why Measure?
There are four major reasons for measuring software development processes, products, and
resources: to Characterize existing processes, to Evaluate program status, to Predict the future
status of this and other programs, and to Improve the processes used. These reasons are described
in more detail in Table 1.
Table 1. Reasons for Collecting and Using Measures
Reason
Characterize
Evaluate
Description
Allows XXP to gain an understanding of the processes, products, resources, and
environments, and to establish baselines for comparisons with future assessments.
 What types of defects are common?
 What is our current defect rate?
Allows XXP to determine a program’s status with respect to plans, assess
achievement of quality goals, and assess the impacts of technology and process
improvements on products and processes
 What is the reliability of the product after delivery?
 Does the product provide the needed functionality and is it easy to use?
 Does functional testing minimize certain types of faults?
Predict
Allows XXP to plan. Measuring for prediction involves gaining understandings of
relationships among processes & products, and building models of these
relationships. The models allow one to focus on the values observed for the
characteristics of processes, products; resources; constraints; etc., which provide a
mechanism for predicting:
 How can we refine our Basis of Estimates (BOE)?
 How can we estimate our budget?
Improve
Allows XXP to improve our processes and procedures, by collecting a repository of
data for evaluating our weaknesses and process bottlenecks. This will help answer:
 How can we do it better?
 What new techniques may improve our capabilities?
Hence the Characterize step is when we make measurements to describe how we’re currently
performing. The Evaluate step is comparing those measurements to our goals. Based on the
trends observed over time, we can then Predict future performance. Finally, we strive for ways to
Page 4
XXP Metrics Methodology
Improve our organization so that we can do even better than earlier predictions would have
allowed.
3.2
How do we Measure?
Measures are used to understand our activities, and to eliminate bias in making decisions. As
shown in Figure 1, measures are derived from data elements, and are used to produce useful
information for our project. This information often forms the basis for making decisions, such as
deciding when to proceed to the next life cycle phase, or when to accept a new software into the
system.
To implement this concept, we often start by identifying the information we want to understand,
and then work backwards to determine what measures and data elements are needed to get that
information.
Data
Source
Data
Elements
Measures
Information
Figure 1. Calculation and Analysis of Measures
The Information is derived from comparing a measure to an internal (e.g. project-defined)
standard, and/or to an external (such as industry-based) standard. For example, if we want to
know whether the quality of our custom-developed software is “good,” that’s a piece of
information based on comparing our defect rate (a measure) to our project’s own history of defect
rate (an internal standard), and/or to an industry standard for “good quality” software (an external
standard).
Each Measure is calculated from one or more data elements. For example, the defect rate is often
defined as the number of defects divided by the number of thousand lines of code (KLOC).
Defect Rate = (# defects) / (# of KLOC)
Hence in order to calculate this measure, we need two data elements; the number of defects, and
the number of thousand lines of code.
We obtain each Data Element from a Data Source. This usually means taking particular pieces
of data from the data source which are needed to calculate our measure. Notice that different data
elements may come from completely different data sources.
The Data Source is where each Data Element comes from. A data source can be electronic (such
as a database or spreadsheet) or manual (a pile of paper sales receipts). In this example, we might
get the number of defects from a problem reporting database, and the number of KLOC might
come from a tool to analyze our source code.
Page 5
XXP Metrics Methodology
It is critical to define very precisely how measures are calculated, and how data elements are
extracted from their data sources, so that measures from several years ago can be meaningfully
compared to measures made yesterday.
It’s possible for some data elements also to be used as measures in another context. The number
of lines of source code (# of KLOC) is a data element in the above example, because it’s used to
calculate the defect rate. However it’s also possible to track the # of KLOC by itself over time to
monitor the growth of the product; in that context, # of KLOC is a measure because it’s the
quantity being plotted and analyzed.
3.3
What can be Measured?
This section describes the most fundamental types of measurements, then combines them to
produce more complex measures, and describes how they can be measured before and after some
significant event.
3.3.1 Fundamental Measurement Types
Measurements may be collected for the work products, and for the resources, tools, and processes
needed to generate those work products. These are the most fundamental measures.
As shown in Figure 2, the objective of a project is to create some sort of work Products. Products
could be software, documentation, plans – in short, creation of any thing which is needed to
ultimately fulfill the project’s needs. In order to do so, we need Resources, such as people, to be
able to create the product. But Resources can’t work in a vacuum, they need Tools to do their
work, such as a software development environment. And finally, to produce a consistently high
quality product, we need to follow a defined Process.
Resources
Tools
Products
Processes
Figure 2. Need Resources, Tools, and Processes to produce Products
Hence fundamental measurements can be defined for any or all of these aspects of our business
environment, as shown in Table 2.
Page 6
XXP Metrics Methodology
The precise distinction whether a particular measure relates to process, tool, resource, or product
isn’t critical – this is merely a method for understanding where the focus of our measurement
attention needs to be placed. For example, if you have low product quality, and know that the
tools aren’t a problem for your staff, then you can focus on resource or process measures to help
identify why the product quality is low.
Table 2. Types of Fundamental Measures
Type
Definition
Examples
Products
Any final or interim work product
Product measures are often the easiest to collect, and
can even be done long after the product has been
created. Basic product measures can include aspects
such as size (LOC, pages, etc.), complexity, and
number of components (e.g. modules, scripts,
classes, etc.). The number of defects in a product are
also a key measurement.
Resources
The people who create the
products, including their training
and skills. Labor cost to use those
resources also belongs in this
type.
Resource measures are often the most important
project management tool. How much staff effort
was required to perform task X? How much does it
cost to fix a defect? More advanced resource
measures may include the amount of training needed
to maintain or improve staff qualifications.
Tools
The equipment used by the
resources to produce the products.
May include hardware, software,
and third party components. All
non-labor costs generally belong
to this type.
Tool measures are relatively rare, but can include
measures such as utilization (what percent of time
are tools being used?), cost, and capacity (what
percent of available bandwidth is being used? Or of
available storage?)
Processes
Generally refers to a defined set
of processes and procedures,
which describe the tasks and
activities performed in order to
create the products.
Process measures often focus on duration (how long
does it take to perform process X?) or frequency
(how often is Process X performed?). Notice that
process measures focus on calendar time to perform
tasks, while Resource measures focus on staff effort.
Page 7
XXP Metrics Methodology
3.3.2 Complex Measurements
The fundamental measures can be combined to yield more complex measurements, as shown in
Table 3.
Table 3. Typical Complex Measurements
Defect Rate
Based on two product measurement (defects and size), the defect rate is typically
given in defects per thousand lines of code.
Earned
Value
Earned value measurements compare the cost, effort, and amount of product
created to define dozens of measures. See
http://users.snip.net/~gbooker/Reference/measures/evalue.htm for examples and
further references.
Productivity Productivity measures are based on the amount of product produced, divided by
the time needed to produce them. Typical software productivity is defined by the
number of LOC per staff month needed to design, write, and validate them.
Thousands of complex measures can be defined to meet specific needs; see the book by Kan for
more examples.
3.3.3 Before and After Measurements
A common technique is to measure the same quantity at two times to allow comparisons. This is
the foundation of being able to Predict or Improve any aspect of our organization (see section
3.1).
Predict - The most common technique is to compare the planned and actual values for a
measure, such as the planned and actual effort required to perform a task. This type of beforeand-after measurement is primarily used for project management, to allow prediction of the cost
and schedule needed to produce some product.
Improve - The other variation on this is to compare measures before and after some change in
the environment. For example, the process duration before a deliberate change to the tools, may
be compared to the duration after the tools are in use, to determine if there was a significant
improvement. Hence this type of before-and-after measurement is primarily used for process
improvement, to quantify improvements in processes.
Page 8
XXP Metrics Methodology
4
How do we Choose What to Measure?
This section tells how to identify which measurements are best for your environment, using the
GQ(I)M method.
There are thousands of possible measures which can be defined from even fairly simple project
data. To help ensure we’re finding the right measures to meet our goals, we need a method to
help choose the best measures for our project.
The GQ(I)M method (per Park, et al) is used to support the definition of measures, in order to
ensure traceability from goals to individual data elements. The method is called "GQ(I)M" for
Goal, Question, Indicator, and Measurement. It is based on the GQM method by Victor Basili,
first developed circa 1988-89.
GQ(I)M is a ten-step top-down approach to definition of measures which focuses on tracing
measures from high level business goals (objectives) down to their exact definition, and
collection of the data elements needed to calculate them. The reasons for using this method
include:

To ensure that measures are clearly defined.

To avoid overcollection of data

To ensure that there is a defined reason (management purpose) for collecting each piece
of data.
To understand why the data are being collected. The “why” is important- it affects how
the data will be interpreted, and provides a basis for reusing measurement plans and
procedures for other projects.

There is nothing magical about using a top-down approach for defining measures. The key is to
fill out all of the GQ(I)M parameters for every measure, regardless of whether you started near
the top (goal), bottom (data elements), or somewhere inbetween. One could start with the
existing data sources and determine what measures and goals could be addressed with them; or
pick measurements which seem relevant, then work up to goals and down to data elements to
clarify their purpose.
4.1
Identify Your Business Goals
The top level business goals for XXP are defined in the sites’ Metrics Plans. Typical high level
goals are to ensure compliance with contractual obligations, and meet corporate standards for
process maturity and process improvement.
4.2
Identify What You Want to Know or Learn
Each XXP Project Manager needs to identify what information they would like to know in order
to understand, assess, predict, or improve their activities to help meet our collective business
goals.
Consider your organization; and ask:

How do we receive inputs?
Page 9
XXP Metrics Methodology

What temporary or internal products do we create?

What work products do we generate?

What resources and tools do we use?

What processes do we use?
Ask what basic information you know quantitatively about your activities:

Cost: How much does it cost to perform each type of activity?

Schedule: How long does it take?

Effort: How much effort does it require?

Scope: How much product is created?
If you’re already comfortable answering those questions, try these:

Is the process stable?

How is it performing now?

What limits our capability?

What determines quality?

What determines success?

What things can we control?

What do our customers want?

What limits our performance?

What could go wrong? How can we tell if it does?

What might signal early warnings?

How big is our backlog?

Where is backlog occurring?
The net result from this step should be an idea of what aspects of your activities are most in need
of better understanding.
4.3
Identify Your Subgoals
Translate the top-level goals from step 1 & and the questions from step 2 into sub-goals that
specifically relate to each Project Manager’s area (e.g. Deployment, Sustainment, Data, etc.).
Each subgoal should support the overall project goals from section 3.4.1, but more specifically
address issues relevant to each project area. Subgoals might include issues like:

Improve emergency fix responsiveness

Improve customer satisfaction

Understand scope of external interfaces
Page 10
XXP Metrics Methodology
4.4

Reduce dependency on subcontractor expertise

Or whatever might be appropriate for each project area
Identify the Entities and Attributes
For each subgoal, identify the products and activities which relate to that subgoal – these are
called the entities of interest. Then for each entity, determine which attributes (characteristics) of
that entity are most important to fulfilling the subgoal. This is to identify what attributes or
combination of attributes can be measured to see if the subgoal has been reached.
4.5
Formalize Your Measurement Goals
Based on the analysis in the first three steps, we now want to formulate specific measurement
goals to address each subgoal. There may be multiple measurement goals for one subgoal,
depending on the complexity of the subgoal.
Each measurement goal is a sentence of the form:
Verb measure frequency
The verb is an action verb chosen based on whether the measurement goal is “active” or
“passive.”

Passive (strategic) measurement goals are meant to enable basic learning or understanding of
the measure (e.g. identify capabilities & trends; identify root causes; etc.). Passive goals are
better suited to lower levels of process maturity, when the baseline performance hasn’t yet
been fully defined. Verbs used with passive goals are focused on developing an
understanding of the current situation, such as “track,” “determine,” “assess,” “observe,”
“identify,” or “monitor.”

Active (tactical) measurement goals are used when you already have a good understanding of
the entity you’re trying to measure. Active goals are better suited to high levels of process
maturity, when process improvement is the norm. Verbs used with active goals are focused
on causing change from the existing state, such as “improve,” “increase,” “decrease,” or
“reduce.”
The measure is a written description of the specific measure(s) which will be used to address this
particular subgoal. Be as specific as possible about exactly what is being measured; this will help
make defining the measure easier. Measures can be calculated, so it’s okay to cite the number of
things, a difference between two things, or the average value of something. Examples of
“measures” could include:

“the number of open Problem Reports”

“the cost and schedule variance”

“the number of known major defects”

“the number of approved system requirements”

“the average number of people charging to the project”
Page 11
XXP Metrics Methodology
The frequency is used to define how often the measure is collected. Frequencies may be on a
fixed schedule (e.g. daily, weekly) or event-driven (per release). Examples of frequency phrases
include:

at the end of each day

at the end of each week

at the end of each month

for each release

for each life cycle phase

after each contract modification
Table 4 puts all of this into a menu format. To generate a measurement goal, pick one entry from
column A, one from column B, and one from Column C. Notice that both passive and active
verbs are shown.
Table 4. Menu for Defining Measurement Goals
These lists are not comprehensive - they are examples only!
Verb
Measure

Track
the number of open Problem Reports

at the end of each day.

Determine 
the cost and schedule variance

at the end of each week.

Assess

the number of known major defects

at the end of each month.

Observe

the number of approved system requirements

for each release.

Identify


for each life cycle phase.

Monitor
the average number of people charging to the
project


Improve
after each contract
modification.

Increase

Decrease

Reduce
4.6

Frequency
Identify Quantifiable Questions and Indicators
Another way to understand measurement goals is to formulate them in terms of a question which
will address the subgoal’s needs. Sometimes this is a starting point for defining measures,
because a question may arise which prompts defining some measure to answer it. Common
measurement questions may include:

Have our requirements stabilized?
Page 12
XXP Metrics Methodology

What is the quality of our software?

Has testing been thorough?

Is the customer happy with our product and services?

When do we need to upgrade our servers?
Indicators are needed to display measures in a meaningful manner. In this context, indicators
refers to the way in which measures are graphically displayed or captured, such as:

Pie Chart

Check Sheet

Pareto Diagram

Histogram (Bar Chart)

Run Chart (Line Chart)

Scatter Diagram

Control Chart

Cause and Effect Diagram (Fishbone)
These indicators are discussed in detail in section 5.
4.7
Define Your Measures
Note: In this document, steps 7 and 8 are switched from the original GQ(I)M approach.
Based on the measurement goals, define each measure to be used. Definitions of measures must
be consistently repeatable. Give each measure a brief name, show an equation for calculating the
measure, and give a written description of the measure.
The written description should communicate what is being measured, how it is measured, and
what has been included or excluded from its definition.
For example, the Defect Rate might be defined as:
Defect Rate = (number of defects) / (number of KLOC)
The Defect Rate is used to assess the quality of software by measuring the number of
known defects per thousand lines of source code (KLOC). Defect severity and status are
not considerations – major and minor defects count equally.
This sets the stage for definition of the data elements in the next step.
Page 13
XXP Metrics Methodology
4.8
Identify the Data Elements
Based on the definitions of each measure, collect a single list of all data elements needed to
calculate all measures. (A particular data element may appear in several measures; hence this
avoids repetition.) Describe how each data element is defined and obtained, so that it may be
consistently collected.
“Number of defects” is the number of defects, of any severity or status, which apply to the
current developmental build, which are in the Problem Reporting Database. They are
collected by running the script “find-all-defects.sql”.
Each data element should generally be collected at one time, so that one measure isn’t, for
example, using the number of defects as of last Friday, and another similar measure is using the
number of defects as of the end of last month. This could lead to confusion in interpretation.
4.9
Identify the Actions Needed to Implement Your Measures
In order to implement these measures, we need to identify where, when, and by whom each
measure will be collected.
A common (shared) location needs to be identified for collection and dissemination of measures
and data elements. This location generally needs to be public for the entire project team. The
main exception to this is sensitive data, such as financial data, which may need more restricted
access.
The following information needs to be identified for every measure:

Goal (a general statement of the subject of interest)

Subgoal (a.k.a. objective)

Question (what is the specific question answered by this measure, if any)

Indicator (how to display measure; e.g. line chart, histogram, etc.)

Measure (the actual measure, including how it is calculated and its definition)

Assignee (who is responsible for collecting and analyzing each measure, and when)
And the following information needs to be defined for each data element:

Data Element name (used to calculate measure)

Source (of each data element - what report, script, survey, etc will be used to gather it?)

Assignee (who is responsible for collecting each data element)
Page 14
XXP Metrics Methodology
4.10
Prepare a Plan
Each project needs to prepare a Plan to define and implement new measures. This activity
has five major elements:
1. Identify existing measures, and document them using the format described in section 4.9.
2. Define desired measures and data elements needed to meet their subgoals, using sections 4.2
to 4.9.
3. Determine the difference between the existing measures, and the desired measures.
Determine the priority of each new measure (e.g. High, Medium, Low).
4. Plan implementation of the new measures. Most projects will want to phase in new measures
over time, such as one set of measures implemented immediately, another set implemented in
six months, and so on. Phased implementation of measures supports the human need for
gradual cultural change, and supports Continuous Process Improvement.
5. Implement the new measures according to the Plan, and report on measures periodically
(e.g. weekly or monthly).
Page 15
XXP Metrics Methodology
5
How can we Present Measures?
This section describes how measurements can be presented graphically (called Indicators in the
GQ(I)M method).
The first two subsections (5.1 and 5.2) describe common terminology for presenting measures,
and discuss a common tool for presenting data, the pie chart.
The next seven subsections (5.3 through 5.9) discuss what are also known as “Ishikawa’s seven
tools.” They are, respectively:
o Check Sheet
o Pareto Diagram
o Histogram (Bar Chart)
o Run Chart (Line Chart)
o Scatter Diagram
o Control Chart
o Cause and Effect Diagram (Fishbone)
Note: Some sources cite the Flow Chart as one of Ishikawa’s tools, instead of the
Check Sheet. However his book Guide to Quality Control discusses Check Sheets.
These collectively cover all of the most commonly used methods for presenting measures
graphically.
5.1
Graphing Conventions
Once a measure has been selected, and its collection frequency determined, it’s possible to define
how it will be presented graphically. Various graphs can show from two data points up to a
million on one chart. The challenge is to determine which type of chart is best for a particular
measure or set of measures.
5.1.1 Graph Terminology
Most graphs are presented in a two-dimensional format, with some horizontal axis (usually called
‘X’ in math classes) and a vertical axis (‘Y’), as shown in Figure 3.
The X axis is also called the independent variable. Here it usually represents when data was
collected for one set of measurements. It is independent because you could choose any value of
X, and look up what corresponding value of Y was measured.
The Y axis is called the dependent variable, because the value of Y depends solely on the X
value. You can’t pick a value of Y and be guaranteed that there will be a corresponding data
point.
Page 16
XXP Metrics Methodology
Y
Sample (Line) Graph
9
8
7
6
5
4
3
2
1
0
0
1
2
3
4
5
X
Figure 3. Definition of X and Y Axes
5.1.2 Units
It is important to remember that most measures have units. These units should be shown with
each graph to help ensure the reader understands the data being presented. The units for each X
or Y axis of a graph should be included in the axis label. Typical units may include:

Effort is in staff hours

Defect Rate is in defects/KLOC

A single date has no other units (May 2002), but differences between dates need to
specify units (hours, days, etc.)

Many Earned Vaue measures are in money ($) or percent (%).
5.1.3 How Much Data Fits?
As various methods for presenting measures are discussed, keep in mind two key factors which
will help determine the best method for presenting the data.
1. Amount of Data per Interval: Each graph may show one or more measures for each data
collection opportunity.
2. Number of Intervals Shown: The number of data collection opportunities, or intervals,
shown on each graph may also range from one to several. Since many measures are repeated
over time, that is the most frequent kind of interval of interest. Hence the analyst typically
needs to decide how many time intervals need to be presented on the graph.
A very rough guide to the amount of data which may be shown on each type of graph is given in
Table 5. The actual amount of data which fits depends on the size of the graph, font size, length
of data labels, and other factors.
Page 17
XXP Metrics Methodology
Table 5. Allowable Data Amounts by Graph Type
Graph Type
Control Chart
Amount of Data per Interval Number of Intervals Shown
(Number of Y values per X)
(Number of X values)
1-6
2-100
Histogram (Bar Chart) –
simple
1
2-15
Histogram (Bar Chart) –
stacked or clustered
2-6
2-10
1
2-15
Pie Chart
1-10
1
Run Chart (Line Chart)
1-6
2-100
Scatter Diagram
1-6
2-100
Pareto Diagram
Page 18
XXP Metrics Methodology
5.2
Pie Chart
The pie chart is the simplest type of graph (see Figure 4). It is used to show the distribution (or
relative amounts) of up to about ten data points at one moment in time, generally now. It is good
for showing percentages, since the pie slices visually add up to 100% for the complete “pie.”
Sales ($M)
1.2
West
4.6
2.4
Northeast
South
Midwest
East
1.1
1.7
Figure 4. Pie Chart
5.3
Check Sheet
The Check Sheet is not a graphic display device; it is used to gather data easily, consistently, and
in a standard format. A check sheet used to help control the quality of a process or product is a
“checklist.” The main purpose of a check sheet is that it helps to define key parts of a process, so
that nothing gets left out. Examples include a code inspection checklist and detailed test
procedures.
5.4
Pareto Diagram
A Pareto Diagram is a special type of bar chart (see Figure 5), used to identify problem areas what do we need to fix first? What are the biggest fires to put out?
It is useful in a software environment because defects tend to cluster in portions of code, so if we
can identify where a lot of defects have already been found, we can probably find more defects in
those same areas.
Here we would typically find the defect rate for all major software components, and then plot the
defect rate (Y axis) for each component (X axis). To be a Pareto diagram, we must list the
components in descending order of defect rate, which automatically puts the most defect-ridden
components on the left of the graph.
Page 19
XXP Metrics Methodology
There is an optional line on a Pareto diagram, which shows the cumulative percent of all cases
for each component, going from left to right. Hence the line always reaches 100% by the rightmost X value, and strictly increases going from left to right. In the context of defect rate analysis,
this line would not have much meaning since defect rates cannot be added. A sample Pareto
diagram, without the cumulative percent line, is shown in Figure 5.
Defect Rate (defects/KLOC)
Pareto Diagram of Component Defect Rate
25
22.3
20
15.6
13.3
15
11.1
8.9
10
5.6
5
0
Interface
Query
Core
Import
Export
Reports
Component
Figure 5. Pareto Diagram
5.5
Histogram (Bar Chart)
There are many variations possible on the histogram.

The bars can be oriented vertically (a.k.a. a column chart), or horizontally. Usually
vertical bars are preferred.

A histogram can contain one measure (a simple bar chart) or more than one. The latter is
a stacked bar chart if the bars are placed on top of each other, or a clustered bar chart if
the bars are sitting next to each other.

The bars can represent the actual value of each measure (e.g. the number of problem
reports in various statuses), or they can show the percent each measure contributes to the
total (e.g. the percent of problem reports which are in each status).
A third possibility, for real-valued data (as opposed to integer data), is that each bar can
represent “the number of data points within a specific range of values.” So a histogram
could show the distribution of problem report closure times, where one bar might be the
“the number of problem reports which closed in 2 or 3 days,” and another bar might be
the “the number of problem reports which closed in 1 day or less,” and so on.
This gives at least eighteen possible types of histogram (vertical vs horizontal, simple vs. stacked
vs. clustered, and actual values vs percentages vs. data ranges). Figures 6, 7, and 8 show
Page 20
XXP Metrics Methodology
examples of the simple, stacked, and clustered bar charts. Notice that the data in Figure 6 is the
first cluster (leftmost) in Figure 8.
No. of Problem Reports
No. of Problem Reports by Status
234
250
200
150
100
50
23
34
15
50
8
0
New
Closed
Pending Withdrawn Analysis
Testing
Status
Figure 6. Simple Bar Chart
Problem Reports in each Status over Time
Number of Problem
Reports
500
Testing
400
Analysis
300
Withdrawn
200
Pending
Closed
100
New
0
Jan-02
Feb-02
Mar-02
Apr-02
May-02
Time
Figure 7. Stacked Bar Chart
Page 21
XXP Metrics Methodology
Problem Reports in each Status over Time
Number of Problem
Reports
300
250
New
200
Closed
Pending
150
Withdrawn
100
Analysis
50
Testing
0
Jan-02
Feb-02
Mar-02
Apr-02
May-02
Time
Figure 8. Clustered Bar Chart
Same data as Figure 7.
5.6
Run Chart (Line Chart)
A run chart, by definition, graphs one or measures over time. Hence the X axis for a run chart is
always some form of date measure. By using straight lines to connect data points for each
measure, the line chart allows more data to be presented than could easily fit on a histogram.
Note: In Microsoft Excel, a “Line Chart” uses the same format data as a bar
chart – only the representation of each data point is different. In order to use a
line chart with real-valued time data (e.g. if you have specific data points at May
1, May 5, and May 6, 2002 instead of just a generic category May 02), then you
have to use a scatter plot instead and use straight lines to connect the data points.
A sample run chart is shown in Figure 9.
Page 22
XXP Metrics Methodology
Number of Defects Found
Number of Defects Found by Severity
45
40
35
30
25
20
15
10
5
0
Minor
Major
Total
Jan-02
Feb-02
Mar-02
Apr-02
May-02
Time
Figure 9. Run Chart
5.7
Scatter Diagram
Scatter diagrams are used to graph two measures against each other. They are generally used to
determine if there is a correlation between the two measures, e.g. “does testing time decrease
when more time is spent doing review?”
In a scatter diagram the Y axis is the measure we wish to predict or understand more fully, and
the X axis is the measure which affects the value of the Y axis. So in the example, the testing
time would be the Y axis, and review time would be the X axis.
A scatter diagram can be used to plot data points initially. Then, based on the type of
relationship which appears to exist between the measures, a regression analysis is done to
determine if that relationship is statistically meaningful. See “Statistics for Software Process
Improvement” for more information on the statistical aspects of analyzing a scatter diagram’s
data.
A sample scatter diagram is shown in Figure 10. Notice that there does appear to be a correlation
between salary and employee’s educational level. This graph was generated from a fictitious
school employee database, using the program called SPSS.
Page 23
XXP Metrics Methodology
Current Salary vs. Educational Level
60000
50000
40000
CURRENT SALARY
30000
20000
10000
0
6
8
10
12
14
16
18
20
22
EDUCATIONAL LEVEL
Figure 10. Scatter Diagram
5.8
Control Chart
The control chart is a special kind of line graph used to monitor performance of a measure. The
main purpose of using a control chart is to provide statistically sound basis for determining if a
measure is under control.
The main feature of a control chart is that there are three lines in addition to the measure itself.
These three are the mean, the Upper Control Limit (UCL) and Lower Control Limit (LCL). There
are a set of rules for determining if your measure is “out of control” based on its behavior relative
to the mean, UCL and LCL. (See Memory Jogger II or Ishikawa’s book for details.)
There are many kinds of control charts to meet a wide range of measure types.

Variable Data control charts apply when the measure is a continuous (real-valued)
quantity, such as temperature, pressure, cost, etc. The control charts for variable data are
based on the mean value of the measure and some measure of its standard error.

Attribute Data control charts apply when the measure is a discrete event, such as a
defective part, an absent employee, or some other measure based on integer variables.
Of those, software tends to focus on defect-oriented measures, so Attribute Data control charts
apply most often here. Within Attribute Data control charts, there are different methods based on
whether each defect is counted separately (called Defect data), or whether entire units are passed
or failed (Defective data). Then the type of control chart is selected based on whether the samples
are constant size (rare in software), or variable size. Assuming the latter applies, the choice of
control chart becomes this:
Page 24
XXP Metrics Methodology

If each defect is counted separately (Defect data), and the sample size may vary, use the
‘u’ type of control chart. This is the ‘number of defects per unit’ type of control chart.

If each unit is passed or failed as a whole (Defective data), and the sample size may vary,
use the ‘p’ type of control chart. This is the ‘fraction defective’ type of control chart.
After selecting the type of control chart, there are formulas for calculating the UCL and LCL.
Hence every data point for the measure also results in calculation of the control limits. (If the
sample sizes vary by less than +/- 20%, then the control limits can be fixed, which makes the
chart easier to read.) A sample control chart is shown in Figure 11.
Control Chart: Percent Passed
93.000
89.000
85.000
Percent Passed
81.000
UCL = 92.3343
Average = 85.0833
77.000
LCL = 77.8324
1
2
3
4
5
6
7
8
9
10
11
12
Sigma level: 3
Figure 11. Control Chart (‘p’ type)
5.9
Cause and Effect Diagram (Fishbone)
A cause and effect diagram isn’t a method for presenting measures graphically. It is a tool for
analysis of the causes of some undesired effect (problem). It’s called a fishbone diagram because
it resembles the skeleton of a fish. A sample cause and effect diagram is shown in Figure 12.
Cause and effect diagrams are generally generated in a meeting setting, by brainstorming about
some problem. The diagram is a way of capturing everyone’s thoughts.
The ‘head’ of the diagram is a box containing the effect you wish to cure. A horizontal line from
the head forms the backbone of the ‘fish.’ The lines at 45 degrees to the backbone are the major
types of causes of the effect. Some common choices for major causes are:

Machines (Plant, or equipment)

Methods (or Processes)

Materials (raw materials for the product)

People (staffing)
Page 25
XXP Metrics Methodology

Policies (high level rules)

Procedures (steps in a task)

Environment (facilities)

Measurement (data collection)
The choices for major causes need to be customized for each problem. Generally at least four
major causes are selected.
Specific possible causes of the effect are shown by horizontal lines which point to each major
cause. Each possible cause can be elaborated upon by adding more lines to show the causes of
the possible cause. This process can continue to any desired level of detail.
The main questions being asked to generate the cause and effect diagram are:

Why does that happen?

What causes that?

What influences that?
The fishbone diagram can be used to support causal (root cause) analysis.
Figure 12. Cause and Effect Diagram
(from Kara Fagley‘s overview of Ishikawa’s tools)
Page 26