Update on the Davis-Woodland Water Supply Project Agency Board September 12, 2013 Discussion Topics • Recent Activities/Accomplishments • Upcoming Activities/Milestones • Project Schedule 2 Recent Activities/Accomplishments July - September 2013 PROGRAM MANAGEMENT- DBO PROPOSAL • Received priced DBO Proposal from CH2M Hill on July 30th • Based on review to date, Proposal appears to be responsive • Negotiations with CH2M Hill are continuing 3 Recent Activities/Accomplishments July - September 2013 (cont’) PROGRAM MANAGEMENT- GRANTS & LOANS • Continued pursuit of SRF Loans: – Clean Water SRF Application Submitted by the Agency for the regional facilities ($211M) – Safe Drinking Water SRF Application Submitted by Woodland for Woodland’s portion of regional and local facilities ($143M) Eligibility based on lost well capacity due to exceeding MCL’s (nitrate) Davis would be eligible upon consolidation of North Davis Meadows • Continued pursuit of state commitment for Intake funding • Westside IRWMP approved DWWSP highly-ranked project 4 Recent Activities/Accomplishments July - September 2013 (cont’) PROGRAM MANAGEMENT • Issued RFQ to solicit qualified construction quality assurance firms • TerraVerde energy analysis proceeding 5 Recent Activities/Accomplishments July - September 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Section 404 Permit: Biological Opinion received from USFWS Biological Opinion from NMFS pending • Microbial Aerosol Study: Six 24-hour sampling events completed; Draft Final Report pending • Working with RD 2035 re: WAPA power sharing at Joint Intake • Working with PG&E to define system improvements/costs to serve RWTF and Joint Intake • Agreement with Yolo County regarding Encroachment Permit requirements 6 Recent Activities/Accomplishments July - September 2013 (cont’) LAND AND ROW ACQUISITIONS • Agreements reached for following property rights/easements: Heidrick/McGinnis for Davis Finished Water Transmission Main easement Oates for 3 parcels near Intake Facility site and along Raw Water Pipeline alignment Alamar for property near Intake Facility site CPG for Intake Facility site & Conaway Ranch easements • Sierra Northern Railroad easements revised- transverse crossing only. CH2M Hill will keep tunnel pits in the road (close Road 22 for 60 days) 7 Recent Activities/Accomplishments July - September 2013 (cont’) PLANNING, DESIGN, AND CONSTRUCTION • Evaluated solids handling alternatives for RWTF • Reviewed contractor pre-qualifications document for Intake Facility • Provided MWH with design criteria for Agency equipment at Intake Facility 8 Upcoming Activities/Milestones PROGRAM MANAGEMENT • Continue to pursue SRF low interest loans from Safe Drinking Water Act SRF (CDPH) and Clean Water Act SRF (SWRCB) Offers from CW SRF and SDW SRF anticipated in early November • Obtain state commitment letter for remaining share of state grant funds (for joint intake - $6.7M) • Continue efforts to obtain WAPA power at Joint Intake • Continue development of ASR Program 9 Upcoming Activities/Milestones PROGRAM MANAGEMENT (cont’) • Complete “Value for Money” analysis • City of Davis to resolve water rate lawsuit or otherwise confirm ability to finance the project • Finalize agreements with RD2035: Operations Agreement Intake Cost Sharing Agreement 10 Upcoming Activities/Milestones ENVIRONMENTAL AND PERMITTING • Receive Biological Opinion from NMFS • Obtain Finding Of No Significant Impact (FONSI) from Bureau of Reclamation • Receive Section 404 Permit (US Army Corps of Engineers) • Obtain State 401 Water Quality Certification • Begin negotiations for purchase of environmental mitigation credits • Approve Air Quality CEQA Addendum • Complete Microbial Aerosol Study at RWTF Site 11 Upcoming Activities/Milestones LAND AND ROW ACQUISITIONS • Complete “condemnation” for Riverbank Road • Finalize escrow for RWTF site purchased from City of Woodland • Complete negotiations for final property easements: SNRR for transverse easement Lillard for Davis Treated Water Main 12 Upcoming Activities/Milestones PLANNING, DESIGN, AND CONSTRUCTION • Complete plan with the Yolo County Farm Bureau for Road 22 closure coordination • Shortlist construction quality assurance firms and solicit proposals • Seek approval to award DBO contract to CH2MHill on October 10 • Pre-qualify intake construction firms (RD 2035-October) 13 DBO Procurement Schedule Activity Issue Request for Qualifications Date January 27, 2011 Receive Statement of Qualifications April 15, 2011 Short list three DBO teams June 2, 2011 Davis and Woodland City Council authorization to proceed with project final engineering and construction March 2013 Issue Request for Proposals December 21, 2012 Receive Initial Concept Submittals & Proposal Phase Procurement Plans May 15, 2013 Priced proposal submittal by Proposer July 30, 2013 Board authorization to proceed with negotiations July 15, 2013 Board award of service contract October 10, 2013 Updated: 09/12/13 14 Project Schedule Milestones Task Completion By Complete RWTF Site Fill November 2012 Obtain water rights for 10 TAF purchased from CPG November 2012 Issue Final RFP for DBO Contract December 2012 Approval of Project Final Engineering and Construction by Each City March 2013 Authorization to Proceed with Bond Financing by Each City September 2013 Award DBO Contract October 2013 Secure Joint Intake Construction Funding October 2013 Obtain USACE 404 Permit November 2013 Advertise Joint Intake Construction Bid Documents November 2013 Joint Intake Construction and Testing Completion DWWSP Acceptance Testing Completion April 2016 September 2016 Updated: 9/12/13 15