Estimated award date

advertisement
PROJECT PORTFOLIO
PROJECTS IN
TRANSPORT
INFRASTRUCTURE
NEW INTERNATIONAL AIRPORT OF
CHINCHERO – CUSCO
CALLED
Location: Cusco.
Description: The project comprises the concession to
design, build, finance, operate and maintain the new
international airport of Chinchero – Cusco (AICC)
 Estimated investment*: US$ 658 million
 Type of concession: Co-financed
 Concession period: 40 years
Estimated award date: I QT 2014.
GENERAL SAN MARTÍN PORT
TERMINAL
CALLED
Location: Ica
Panamericana Sur highway
Road Network N° 6
BRAZIL
Description: The project comprises the concession to
design, build, finance, operate and maintain of the
General San Martín Port Terminal. Initial works:
Dredging
Multi-purpose dock
Yard for bulk cargo and other cargo
Support facilities
Electricity interconnection
2 mobile cranes
Yard equipment
Other equipment for general loading
 Estimated investment (VAT not included): US$ 103
million
 Type of concession : Self-sustaining
 Concession period: 30 years.
Estimated award date: I Quarter 2014.
THE AMAZON WATERWAY
CALLED
Location: Loreto and Ucayali.
BRAZIL
PACIFIC
OCEAN
Description: The project comprises the implementation of
works and actions to improve the navigability and transit of
pasenger and cargo on the Amazonas, Marañón, Huallaga
and Ucayali rivers.
 Dredging on critical areas (Malos Pasos) and on the access
to the Port of Iquitos.
 GPS information system on the route of the navigation
channel.
 Installation of level measuring stations with transmission
of information.
 System of monitoring of navigability conditions.
 Cleaning system.
• Estimated investment (VAT not included): US$ 65
million
• Type of concession : Co-financed
• Concession period: 20 years.
Estimated date of award: I Quarter 2014.
LINE 2 AND BRANCH LINE OF FAUCETT AV. - GAMBETTA AV.
OF THE BASIC NETWORK OF THE METRO OF LIMA AND
CALLAO
CALLED
Location: Lima and Callao.
Description: The project comprises the
concession to design, build, finance, supply of
electromechanical equipment, acquire rolling
equipment, operate and maintain Line 2 of the
electric mass transportation system, it will
have an approximated extension of 35 km and
will cross 13 districts of Metropolitan Lima.
 Estimated investment (VAT not included):
US$ 5.701 million (1, 2 and 3 stage)
 Type of concession: Co-financed
Estimated award date : I Quarter 2014.
LINES 3 AND 4 OF THE BASIC NETWORK OF
THE METRO OF LIMA AND CALLAO
TO BE CALLED
Location: Lima and Callao.
Description: The project comprises the concession to
design, finance, build, provision of electromechanical
equipment, purchase of rolling stock, operation and
maintenance of Line 3 and Line 4.
 Estimated investment:
Under evaluation
 Type of concession :
Co-financed
 Concession Period:
35 years
Line 3
Line 4
Approximate
length
32 Km
30 Km
Estimated award
date
2015
2015
HUANCAYO - HUANCAVELICA RAILWAY
Location: Junín and Huancavelica.
TO BE CALLED
Description: Project oriented to the transportation of passengers
and cargo, which comprises the execution of the following works
along the 128 Km of the existing railway:





Railway upgrade
Changes to the tracks in critical sectors
Purchase of rolling stock
Reinforcement of 15 railway bridges
Extension of 38 tunnels for standard gauge rolling stock
(1,435 mm)
 Upgrades to the signaling and telecommunication systems
 Draining works
The project includes the interoperability with Ferrocarril Central
(railway service with standard gauge of 25 ton per axle) for the
connection of high Andes regions with the port of Callao and the
Santa Anita market.
LEYENDA
Ferrocarril Central
Ferrocarril Huancayo Huancavelica
Ferrocarril Sur
Estimated investment:
Type of concession :
Concession Period:
Under evaluation
Co-financed
30 years
Estimated award date:
I Quarter 2015
FAST MONORAIL MASS TRANSPORTATION
SYSTEM - AREQUIPA
Location: Arequipa
Description: A private initiative for the design,
construction, electromagnetic equipment, systems,
rolling stock, financing, operation and maintenance of
a 14 Km fast mass transportation system on an
elevated track.
• Estimated Investment: Studies in progress
• Type of concession : Co-financed
• Estimated award date: IV Quarter 2014
LONGITUDINAL DE LA SIERRA HIGHWAY, SECTION 4
TO BE CALLED
Location: Junín, Huancavelica, Ayacucho and Apurímac.
Description: The project comprises the execution of
upgrade and rehabilitation works (117 km), initial
periodic maintenance (160 km); and subsequent
maintenance and operation of 651 Km, in order to
reach and maintain the established service levels on
the railway route.
Estimated investment: The sector is conducting the
final engineering studies.
Type of concession : Co-financed
Concession period: 25 years
Estimated date of award: I Quarter 2015.
LONGITUDINAL DE LA SIERRA HIGHWAY, SECTION 5
TO BE CALLED
Location: Cusco and Puno.
Description: The project comprises the regular initial
maintenance, and operation and maintenance of all the
Section (422 km), in order to obtain the required level of
service.
 Estimated Investment: The sector is updating the
upgrading and improvement costs
 Type of concession: Co-financed
 Concession period: 25 years.
Estimated award date : II Quarter 2015.
PANAMERICANA SUR HIGHWAY: SECTION ICA- DV.
QUILCA
TO BE CALLED
Location: Ica and Arequipa
Description: Private initiative for the concession to
build, operate and maintain the following
infrastructure: Vía de Evitamiento de Ica, Second road
Ev. Ica - Ov. Ocucaje, Vía de Evitamiento de Palpa, Vía
de Evitamiento de Nazca and section Nazca - DV.
Quilca.
 Estimated investment: Under Evaluation.
Type of concession: Self sustaining
Estimated award date: 2015
CONCESSIONS IN URBAN AREAS
PERIPHERAL RING ROAD
TO BE CALLED
Location: Lima and Callao
Description:
Private
initiative
for
the
construction,
financing,
operation
and
maintenance of a highway from Av. Elmer
Faucett to Av. Circunvalación (approx. 33 Km),
according to the technical parameters and
service levels established.
• Estimated Investment: Studies in progress
• Type of concession : Co-financed
• Estimated award date: IV Quarter 2014
Ring road
PROJECTS IN
ENERGY
220 kV MOYOBAMBA -IQUITOS TRANSMISSION LINE AND
ASSOCIATED SUB STATIONS
CALLED
Location: Loreto and San Martín.
Iquitos
600 Km
Moyobamba
BRAZIL
PACIFIC
OCEAN
Description: The project comprises the concession to
design, finance, build, operate, and maintain a
transmission line with an approximated length of 600
km and capacity of 145 MVA, in order to incorporate
the city of Iquitos to the National Interconnected
System.
 Estimated Investment (VAT not included): US$
434 million
 Type of concession: Self-sustaining
 Concession period: 30 years
construction period (52 months)
Estimated award date: II Quarter 2014.
plus
the
220 KV LA PLANICIE INDUSTRIALES TRANSMISSION
LINE AND ASSOCIATED SUBSTATIONS
TO BE CALLED
Location: Lima
Description: The project comprises the concession to
design, finance, build, operate, and maintain the
transmission line with a length of 16.6 km and two circuits
with 400 MVA capacity each. The last 5 km of the line will be
underground.
Estimated investment (VAT not included): US$ 56.6 million
Type of concession : Self-sustaining
Concession period: 30 years plus the construction period
(22 months approximately).
Estimated award date: II Quarter 2014
220 KV FRIASPATA - MOLLEPATA TRANSMISSION LINE AND
220/60 KV ORCOTUNA SUBSTATION
CALLED
Location: Huancavelica, Ayacucho, Junín.
Description: The project comprises the concession to
design, finance, build, operate and maintain of the
following projects:
a) Mollepata – Friaspata transmission line of 90.5 k.m.
and 192 MVA capacity and associated sub stations.
b) 220/60 kV new Orcotuna substation with 50 MVA
capacity.
SE Orcotuna
Friaspata
Mollepata
Both projects will allow to meet the energy demand in
the regions involved.
 Estimated investment (VAT not included): US$ 43.5
million
 Type of concession : Self-sustained.
 Concession period: 30 years plus the construction
period (25 months approximately)
 Estimated award date: II Quarter 2014
1100 Mw ELECTRICITY SUPPLY
TO BE CALLED
Location: Nationwide.
Description: Supply of power and energy to the National
Interconnected Power System (SEIN) through several
generators that guarantee the promised supply by building
new hydroelectric power stations that will be commissioned
from 2016 on.
•
•
Estimated investment: Under evaluation
Type of concession : Self-sustaining
Estimated date of award: IV Quarter 2014
ENERGY SECURITY AND SOUTHERN GAS
PIPELINE
Location: Cusco, Arequipa and Moquegua.
CALLED
Description: The project comprises the concession to
design, finance, build, operate, maintain and transfer of
a natural gas distribution system. The project includes 2
sections:
Camisea
Malvinas
PC
Quillabamba
Chiquintirca
CUSCO
PUNO
AREQUIPA
Mollendo
MOQUEGUA
Ilo
TACNA
a) Construction of natural gas pipelines and liquid gas
pipelines from Malvinas plant to the Connection point
(CP) and then to the Chinquintirca plant.
b) Construction of the Southern region gas pipeline from
the Connection Point (CP) to south coast of the
country. This comprises the following works:
 Route 1: natural gas pipeline from the CP to Cusco
 Route 2: Continuance of the gas pipeline to Ilo
and Mollendo.
Estimated Investment (VAT not included): US$ 3,722
million
Type of concession: Self - sustaining
Estimated award date: I QT 2014
SUPPLY SYSTEM OF LNG FOR
DOMESTIC MARKET
CALLED
Location: Lima.
Description: The project comprises the concession to
design, finance, build, operate and maintain a supply system
of liquid natural gas with a capacity of 130,000 M3 in
emergency situations for up to 7 days.
 Estimated Investment (VAT not included): US$ 250
million.

Type of concession: Self-sustaining.

Concession term: 20 years plus the build period (30
months).

Estimated award date: IV Quarter 2014
PROJECTS IN
SANITATION
AND HEALTH
CHILLÓN RIVER WATER SUPPLY
WORKS
TO BE CALLED
POR CONVOCAR
Location: Lima.
Description: The project comprises the concession to design,
finance, build, operate and maintain of dam works
(approximately 40 MM cubic meters) of Chillón river basin.
Estimated investment (VAT not included):US$ 45 million
Type of concession: Self- sustaining
Concession term: 20 to 30 years
Canta
Ancón
Matucana
Estimated award date: III Quarter 2014.
MAIN WORKS AND CONDUCTION OF DRINKABLE
WATER SUPPLY FOR LIMA
Location: Junín and Lima.
TO BE CALLED
POR CONVOCAR
Description: The project comprises the concession to
design, finance, build, operate and maintain of the
following infrastructure works:
 Extension capacity of Pomacocha and Huallacocha
Bajo dams (approx. 100 MM cubic meters ).
 Diversion works of Pomacocha – River Blanco (approx.
10 km of trans Andean tunnel).
P
H
Trans Andean tunnel
Water
Purificatio
n Plant
Rimac
River
Blanco River
Southern conduction line
 Water purification plant (5 m3/s), and
 Southern conduction line Ramal Sur (approx. 25,6 km)
from Huachipa to Villa del Triunfo districts, three
tunnels of 4.2 k.m., 4.5 k.m., and 2.5 k.m.; and 6
support reservoirs of 24,000 cubic meters.
Estimated Investment (VAT not included): US$ 400
million
Type of concession: Self -sustained
Concession term: 20 to 30 years
Estimated award date: IV Quarter 2014.
MANAGEMENT OF THE INSTITUTO NACIONAL DE SALUD
DEL NIÑO – SAN BORJA
CALLED
Location: Lima.
Description: The project comprises in the provision, by a
private operator, of the following services:
 Maintenance
of
buildings,
facilities
and
electromechanical equipment associated with
infrastructure, landscaping and parking
 Maintenance of the clinical and not-clinical
equipment
 General services (laundry, kitchen, cleaning service
and security and hospital waste management)
 Support to the diagnose (Laboratory, clinical
pathology, blood bank and sterilization center)
 Technical assistance services for acquisition
 Type of concession: Co-financed
 Contract term: 10 years.
Estimated award date: I Quarter 2014.
BUILD, EQUIP AND COMPLEMENTARY SERVICES IN
ESSALUD AND MINSA HOSPITALS
TO BE CALLED
Location: Lima, Piura, Lambayeque, Arequipa and Huaraz.
Description: The project comprises the concession to
design, build, equip, operate, maintain complementary
services in the following hospitals:
1. Sergio Bernales MINSA
2. Dos de Mayo MINSA
3. Hospital Piura Essalud
4. Hospital Chiclayo Essalud
5. Hospital Arequipa Essalud
6. Hospital Chimbote Essalud
 Estimated investment: Studies in progess
Estimated award date: 2015
INTEGRAL MANAGEMENT OF SOLID WASTE FROM
HOSPITALS IN METROPOLITAN LIMA AND CALLAO
TO BE CALLED
Location: Lima and Callao
Description: A private initiative involving the construction,
operation and maintenance of a modern hospital waste
treatment plant for the appropriate management of this
type of waste (hazardous-biocontaminated/specialhazardous/regular) from hospitals and institutes of the
Ministry of Health in Lima and Callao.
The project will be executed on the basis of other existing
infrastructure public works owned by the Peruvian
Government.
 Estimated Investment: Studies in progress
 Type of concession: Co-financed
 Estimated award date: 2015
PROJECTS IN
TOURISM AND
CULTURE
CABLECAR TO KUELAP
CALLED
Location: Amazonas.
Description: The project comprises the concession to
design, finance, build, operate and maintain a cableway
system for a fast, safe and easy access to Kuelap Fortress.
The cable cars route will be 4,400 meters aimed to
overcome the distance of 965 meters between Tingo
Nuevo town and Kuelap fortress.
 Estimated investment (VAT not included): US$ 17.6
million
 Type of concession: Co- financed
 Concession term: 20 – 25 years
Estimated award date: II Quarter 2014.
CHOQUEQUIRAO CABLE RAILWAY
TO BE CALLED
Location: Apurímac and Cusco
Description: Concession of the design, financing,
construction, equipment, operation and maintenance of
a cable railway system to access the Choquequirao
Archaeological Park in a fast and comfortable way.
It will cross the Apurimac Canyon and will have 5.4 Km
long, divided in 2 sections (3.4 Km and 1.99 Km), and
capacity for 400 passengers/hour.
 Estimated investment (VAT not included): US$ 55
million
 Type of concession : Co-financed
 Concession period: 20-25 years
Estimated date of award: IV Quarter 2014
PROJECTS IN
PENAL
FACILITITES
PROVISION OF TECHNOLOGICAL SECURITY
SERVICES IN PRISONS
Location: 33 Correctional Facilities nationwide
Description: A private initiative declared to be of interest,
created to upgrade the security in correctional facilities
through the application of the following technologies:
 Blockers of mobile phone signals and WiFi networks.
 Public use telephones under established security
conditions.
• Estimated Investment (VAT not included): US $ 4.1
million
• Type of concession : Self-sustaining
• Concession term: 25 years
Deadline for the presentation of interested parties: January
17, 2014
Estimated award date: I Quarter 2014 (If third parties do
not appear)
ELECTRONIC PERSONAL MONITORING
TO BE CALLED
Location: Lima and Callao
Description: A private initiative for the provision of
Electronic Personal Monitoring services aiming at
decongesting the Peruvian correctional facilities through
the use of electronic tagging devices on prosecuted or
sentenced inmates that may have access to this benefit,
in their places of residence or under restricted transit
conditions.
 Estimated Investment: Under evaluation
 Type of concession : Self-sustaining
 Estimated award date: IV Quarter 2014
RELOCATION OF PENAL FACILITIES
TO BE CALLED
Location: Lima and Cusco
Description: Relocation of 4 penal facilities located in urban areas
of Metropolitan Lima and Cusco, fulfilling the necessary
conditions for the treatment process of the inmates.
Penal facilities considered are:
• Mujeres Chorrillos (Common) and Annex.
• Lurigancho
• Miguel Castro Castro.
• Cusco and EP Cusco Women
Estimated Investment: Under evaluation
Estimated award date: I Quarter 2015
PENAL INFRASTRUCTURE AND URBAN RENEWAL
“TINKUY PLAZA PROJECT”
TO BE CALLED
Location: Lima
Description: The project proposes the construction of a
commercial center, housing, warehouses and parking lots in
the land of the current San Jorge Prison (Metropolitan Lima).
It also includes the construction and equipment of a new
prison for the transfer of inmates of San Jorge Prison into a
state owned property – to be defined.
 Estimated investment : Under evaluation
 Concession type: Self sustaining
Estimated award date: 2015
PROJECTS IN
MINING
HUAYDAY AMBARA MINING PROSPECT
TO BE CALLED
LA LIBERTAD
Location: La Libertad.
LUCMA
Description: The project involves a mining
concession with a total area of 2992 ha . There are
coal stratums identified as “clean anthracite” with
probable estimated reserves of 1.8 million MT that
offers a high potential for exploration.
Estimated award date: II Quarter 2014
COMPREHENSIVE AGRICULTURAL, WATER AND
MINING PROJECT IN PIURA
TO BE CALLED
Location: Piura
Description: This project will be performed in two
stages :
Location of the
ore benefit plant
Operations
area of
informal
mining
PACIFIC OCEAN
 First stage: Design, financing, construction,
operation and maintenance of an ore benefit
Plant which shall process the gold ore extracted
by formal miners and miners under formalization
process who operate within the Piura region.
 Second stage: Promotion of a portfolio of
agriculture and livestock development projects
and others that are intended to solve problems
related to water for domestic and agriculture
purposes in the influence area of the formal
mining operations.
Estimated award date : IV Quarter 2014
Download