NRC presentation

advertisement

Extension of Construction

Authorization for the Mixed Oxide

Fuel Fabrication Facility

David Tiktinsky

Senior Project Manager

Division of Fuel Cycle Safety, Safeguards and

Environmental Review, Office of Nuclear Material Safety and Safeguards

1

Background

• Construction Authorization (CA)

– Originally issued March 30, 2005 for a ten year period

• Nuclear construction commenced in 2007

– CA Condition 5 allows the Director of the

Office of Nuclear Material Safety and

Safeguards, to extend the CA in writing and for good cause, as shown by MOX

Services in writing

2

CA Extension Request

• MOX Services requested extension on May 12, 2014

• Basis for extension request

– First of a kind facility and first facility of this type to be licensed under 10 CFR Part 70

– Annual funding supporting construction have been less that had been projected

– Nuclear quality assurance requirements and shortage of qualified vendors (delayed delivery of components)

– Shortage of qualified construction workers (longer duration of construction activities)

– Two-year delay between issuance of NRC CA and start of construction

3

CA Extension Request (Continued)

• More time needed to complete construction of:

– Key structures including Emergency generator building and reagents processing building

– Completion of ventilation, fire detection and suppression, diesel generator and support systems, process units and gloveboxes.

4

CA Extension Request (cont)

• MOX Services stated that environmental impacts are still bounded by

MOX Services Environmental Report (no adverse environmental impacts)

• Requested extension did not authorize or result in significant environmental changes

• Construction progress reported by MOX Services

– Substantial progress has been made (60% complete)

– Significant progress made in construction of principle structures, systems and components.

– MOX Fuel Fabrication Building is substantially complete including roof and exterior structure

– 200,000 pounds of HVAC ductwork installed

– Seventy of 73 tanks installed

– Installation of fire dampers has commenced

– Non-PSSC cabling and other support

5

NRC Review of Request

• Environmental Assessment

• Issuance of Order

– Included time extension and other administrative changes

6

NRC Environmental Assessment

• Published in Federal Register (Vol. 79, No. 205, Page

43442) on October 23, 2014

• Environmental impacts of proposed action

– NRC previously evaluated environmental impacts and issued a

Final Environmental Impact Statement (NUREG-1767) in

January 2005

– MOX Services concluded in extension request that all activities conducted to date are still bounded by their Environmental

Report.

– Extension would not authorize or result in any new changes of significance as defined in 10 CFR Part 51.60(b)(2)

– Substantial progress on construction has already been made

7

NRC Environmental Assessment

(continued)

• Finding of No Significant Impact

– Proposed action does not involve any different impacts or a significant change to those analyzed in the original EIS.

– NRC determined that extending the CA completion date will not have a significant effect on the quality of the human environment.

– NRC determined that an EIS for the action need not be prepared.

8

NRC Confirmatory Order

• Published in Federal Register (FR Volume 79, No. 226,

Page 69886) dated November 24, 2014

– Extension of Construction Authorization completion date and administrative changes

• Safety Evaluation Report issued to MOX Services on

November 13, 2014

9

NRC Confirmatory Order

(continued)

• Extension of CA expiration date

– NRC staff concluded that MOX Services had demonstrated good cause to extend the CA

• Extension will not expand scope of work not already allowed in the existing

CA

• Licensees’ factors for needing an extension were beyond their control and are logical

• The time requested is reasonable based on the uncertainty of funding for construction

• The extension does not impact the staff’s previous finding that the design basis of the Principle Structures, Systems and Components and the quality assurance program provide reasonable assurance against natural phenomena and consequences of potential accidents.

10

NRC Confirmatory Order

(continued)

• Administrative Changes

– Name change from Shaw AREVA MOX Services to CB&I

AREVA MOX Services

• No direct or indirect change of control or any other change in management, operation or security

– Housekeeping change

• Removal of list of submittals incorporated by reference in Attachment A of the CA

– All commitments, representations and statements made in the referenced documents have been incorporated into the Construction Authorization

Request, Environmental Report, and License Application to possess and use radioactive material.

11

Summary

• NRC granted an extension of the CA via an order

– NRC staff EA found that the extension had no significant environmental impact

– MOX Services had demonstrated good cause for the CA extension

• NRC also made administrative changes to the CA in the order

12

Download