SCATS 6.10.1 Release Review

advertisement
SCATS 6.10 Release Review
SMUG, March 2013
Sydney
SCATS 6.10 Release Review
This presentation describes the new features
and changes introduced in
SCATS 6.10 Commercial Release.
SMUG 2013
2
Corporate Delivery Plan (2012-2013)
• Improve the efficiency of the road network during peak times on
Sydney’s road corridors, including supporting road based public
transport.
 Develop an Intelligent Transport System Strategy to drive the
ongoing development of the SCATS and associated traffic
management systems.
 Develop the Smart Managed Motorways concept for the M4
Motorway to improve travel flow efficiency and road user safety.
SMUG 2013
3
SCATS 6.10: Objectives
• Improvement of traffic management capabilities through the addition
of new features as well as enhancements of existing SCATS
functionality.
• Provide a better interface to external ITS applications.
• Lay down the foundation for future SCATS technologies (i.e. new
TRAFF protocol support).
• Improve existing Ramp Metering management within SCATS.
SMUG 2013
4
SCATS 6.10: Scope
• Improve traffic management: re-engineer adaptive SCATS
• Improve intersection diagnostics: New History File & Walks
• Introduce robust repository: Site Inventory
• Improve interoperability: New ITS messages
• Enhanced monitoring: New Picture & Tablet Interface
• Continuity: New TRAFF protocol
SMUG 2013
5
Improve Adaptive SCATS
• Commence the re-engineering of some of the SCATS adaptive
operations that are handled via variation routines which limit us to
modify, enhance or add new features such as supporting more than 4
phases in ISS operations.
• Three variation routines will be enhanced in the next release:
- VR35 - Incremental Split Selection (ISS)
- VR43 - Diamond Overlap phase control
- VR59 - SD control of a diamond phase
• New operations will be optional in 6.10 – trial & feedback
SMUG 2013
6
Improve Adaptive SCATS – cont’d
• VR35 (ISS) limitations
- Intersections with 2, 3 and 4
phases
- ISS table do not contain all
possible combinations
- Maximum increment split value
is limited to +/- 4
• Introduce all possible
combinations for all
phases and configure max
split value for each phase
SMUG 2013
7
Improve Adaptive SCATS – cont’d
• VR43 - Diamond Overlap phase control
• Two modes of operation
- Introduce trailing turn
• if it’s in the selected split plan
- Introduce trailing turn
• Based on voting result
• Simple thresholds
- Cycle length
- Bay time
SMUG 2013
8
Improve Adaptive SCATS – cont’d
• Improved Strategic Approach
- VR59 - SD control of a diamond phase
- VR83 - Test an SA for congestion
- Configurable voting
SMUG 2013
9
Improve Adaptive SCATS – cont’d
• Allow SA specific options
- Instead of setting these options from
subsystem options
• Allow SA voting based on DS
or volume, and conditional
voting (VR59)
• Allow SA gating/congestion
control (VR83)
SMUG 2013
10
Improve Adaptive SCATS – cont’d
SMUG 2013
11
SCATS 6.10: New History File
• Combine the information already logged by HIST and IDM files as
well as log additional new information
• One daily file per Region for ALL intersections, incrementally sent to
Central Manager, similar to SM and VS
• Additional information that will be stored in the new history file
- All Walks (including Secret)
- External I/O (XSF, MSS)
- Alarms to be recorded as state changes
SMUG 2013
12
SCATS 6.10: Walk Definitions
• Provide ability to define all walks in SCATS
- Option to chose SCATS or controller managed
• Allow empty walks
- remove sequential walks definition
• Visibility of ALL walk states
- New history file to include start/termination request/ended
SMUG 2013
13
SCATS 6.10: Site Inventory
• Provide configurable data storage and report mechanism
• Import existing Site Details
- Line, Names, Camera etc
• Capture equipment details
- Log changes
• Add new information
- Power Supplier, Network Provider
- In Service/Out Service
SMUG 2013
14
SCATS 6.10: New ITS messages
• Keep existing ITS as it is
• Introduce new port/protocol that allows new paradigm – extendable
& authenticated
• Closer integration with SRMS
- Provide access to more Central Manager functionalities – special dates
• Interoperability
SMUG 2013
15
SCATS 6.10: New Picture
• Provide real-world layout for intersections
- Support new requirements
• Design and implement SCATS Spatial Data
- Easier to integrate other systems
• ITS extension to manage intersection pictures
- Import/Export spatial attributes
SMUG 2013
16
SCATS 6.10: New TRAFF Protocol
• Open paths to improve intersection efficiency, responsiveness and
provide data reporting to improve network coordination
- Plan-based operation
• Increase number of phases, approach timers etc.
• Allow phase order to be variable
- Supporting mechanism to repeat any phase in the sequence
• Send all signal group colours to SCATS
- Green, Yellow, Red, and flashing state
SMUG 2013
17
Download