Airport Operations Thailand (AOT) report for MEE – Net

advertisement
Suvarnabhumi International
Airport
..WELCOME MEE Net..
MJTA Consortium
1
.
SUVARNABHUMI INTERNATIONAL AIRPORT
MJTA Consortium
2
SUVARNABHUMI AIR
CONDITIONING SYSTEM
SUVARNABHUMI AIR CONDITIONING SYSTEM
BUILDING CONFIGURATION
The Terminal building requires to have large hall area without concrete
pole or with minimal concrete pole for passengers’ convenience. For maximum
passengers comfort with ease of traveling within the airport compound, the
building comprise of two sectors, the Terminal and Concourse building. The
Concourse building is for airplane connection to boarding bridges. The
Terminal building is for handling departure and arrival passengers.
 For energy saving purpose, the airconditioning will be provided only from
floor level to 3 or 4 meter above the floor since passengers will not stay higher
than 2 meters above the floor

MJTA Consortium
4
SUVARNABHUMI AIR CONDITIONING SYSTEM
BUILDING SIZE
 Concourse
Width 40.50 m. Length 3,123 m.
Hight 23.60 m.

Terminal
Width 108 m. Length 441 m. Hight 40 m.
MJTA Consortium
5
SUVARNABHUMI AIR CONDITIONING SYSTEM
AREA FOR AIR CONDITIONING
 Concourse
248,445 SQ.M.

Terminal
119,906 SQ.M.
TOTAL OF
368,351
MJTA Consortium
SQ.M.
6
CONCEPTUAL DESIGN FOR ENERGY SAVING OF
SUVARNABHUMI AIR CONDITIONING SYSTEM
1.
2.
3.
Usage of direct sun light with minimal electrical lamps during day time.
Air conditioning will be provided only from floor level to 3 or 4 meter
above the floor to reduce the air conditioning load by means of
Stratification technique. This technique use Radiant Floor Cooling
together with Recirculated Air Cooling System.
Control intake fresh air for continual changing number of passengers.
MJTA Consortium
7
CONCEPTUAL DESIGN FOR ENERGY SAVING OF
SUVARNABHUMI AIR CONDITIONING SYSTEM
4.
5.
6.
7.
Adjust Variable Chilled Water Volume for continual changing cooling
load.
Use Chilled Water Temperature Difference ( delta T ) larger than normal
conventional type which will require lesser pipe size and flow rate, thus
reduced the pump size and energy required.
Reduce make up water of Cooling Tower by way of water filter instead of
bleed-off
Reduce solar heat gain through glass by way of using Frit, a small
circular pad, spread evenly on glass which help reduce the Solar Factor
MJTA Consortium
8
CONCEPTUAL DESIGN FOR ENERGY SAVING OF
SUVARNABHUMI AIR CONDITIONING SYSTEM พลังงาน
8.
9.
10.
Reduce infrared radiation from ceiling and wall by way of applying LowE Infrared Hard Coating on ceiling and wall.
Reduce convective heat gain from electrical lamps since the heat gain will
be combined with hot air above stratification level which will cause no
effect to passengers.
Reduce radiation heat gain by way of using radiant floor cooling together
with conventional air conditioning system.
MJTA Consortium
9
Air Conditioning System
MJTA Consortium
10
Radiant Floor Cooling
Cooling
tube to
Diffuser
Header
Poly Etelene 1 header=10 loops
Diffuser
MJTA Consortium
11
SUVARNABHUMI INTERNATIONAL AIRPORT.
Radiant Floor Shop Drawing: Configuration Detail Drawing.
12
MJTA Consortium
12
SUVARNABHUMI INTERNATIONAL AIRPORT.
Radiant Floor Shop Drawing: Floor Plan
13
MJTA Consortium
13
SUVARNABHUMI INTERNATIONAL AIRPORT.
VAC System. Temperature Layer
14
MJTA Consortium
14
SUVARNABHUMI AIR CONDITIONING SYSTEM
Design Criteria
Ambient Temp.
35C db
28C wb
24C±1 db
55+5% RH
Circulation, Holdroom 10 W/m2
Office 15 W/m2
Retail 35 W/m2
Indoor Temp.
Relative Humidity
Lighting:
MJTA Consortium
15
SUVARNABHUMI AIR CONDITIONING SYSTEM
Design Criteria
Outside Air:
Passengers:
(Peak Hour)
Circulation, Holdroom 17 m3/hr/person
Office
34 m3/hr/person
Retail
26 m3/hr/person
Terminal + Concourse 22,879 persons (30 MAP)
27,379 persons (45 MAP)
OA total
506,011 m3/hr (30 MAP)
582,511 m3/hr (45 MAP)
MJTA Consortium
16
SUVARNABHUMI AIR CONDITIONING SYSTEM
Design Criteria
Total Cooling Capacity
41,666 KW
43,238 KW
=
=
MJTA Consortium
11,850 Tons (30 MAP)
12,297 Tons (45 MAP)
17
SUVARNABHUMI AIR CONDITIONING SYSTEM
AOT purchase chilled water from DCAP (Districted Cooling System
and Power Plant Company Limited). DCAP has installed 8
ABSORPTION CHILLERS at CENTRAL PLANT located within
Parking building next to the Terminal building. DCAP installed 4
ABSORPTION CHILLERS ( DOUBLE EFFECT TYPE ) on each
plant (EAST and WEST PLANT) and each absorption chiller has the
capacity of 2,100 TR (norminal) and can produce 706 m3/hr (196.11
L/S) chilled water at return temp. of 14 C and supply temp. of 5 C
MJTA Consortium
18
SUVARNABHUMI AIR CONDITIONING SYSTEM
4 Absorption Chiller Cooling capacity@2100 TR (7,386 kW)
=
8,400 TR
(29,544 kW)
4 Secondary chilled water pumps @ 706 m3/hr (196.11 L/S)
=
2,824 m3/hr (784.44 L/S)
Supply Temp.
5o C
Return Temp.
14o C
TOTAL COOLING CAPACITY OF EAST AND WEST PLANTS
=
16,800 TR (59,088 kW)
MJTA Consortium
19
SBIA : TERMINAL COMPLEX
30 MILLION ANNUAL PASSENGER
REDUCED CONCORSE WIDTH 4.35M
AND
REVISED MATERIAL OF CONSTRUCTION
MJTA Consortium
20
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP
A) Heat Transmission + Electrical Load at Peak Hour
• East Concourse Building
• West Concourse Building
• Terminal Building
• Jetbridge East Concourse
• Jetbridge West Concourse
Sub Total A)
MJTA Consortium
7,464
7,381
4,875
617
559
=
kW.
kW.
kW.
kW.
kW.
20,896 kW.
21
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP (Cont’d)
B) Occupancy and O.A Load
B.1 Officers + Employees +
Visitors + Meeters
=
Total Adjusted Heat Gain 130 W/Person;
13879 x 130/1000
=
13,879 Persons
1,804
kW.
Total O.A Supply 353,011 Cubic Meter Per Hour
Total O.A. Load
=
1.19 x 353,011/3.6 x (90-51)/1,000
=
4,551 kW.
MJTA Consortium
22
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP (Cont’d)
B) Occupancy and O.A Load (Cont’d)
B.2 TPHP of 30 Million Annual Flow as Recommended by
FAA is Equivalent to 9,000 persons
TPHP Load of Passenger =
9,000 x 130 / 1,000
=
1,170 kW.
O.A. Load for TPHP = 1.19 x 9,000 x 17 / 3.6 x (90-51) / 1,000
=
1,972 kW.
Sub Total B)
=
MJTA Consortium
9,497
kW.
23
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP (Cont’d)
C) Machine Room Cooling Load
6 sets AHU Capacity each 142 kW.
=
Sub Total C)
=
D) PCA. Chiller Heat Rejection
PCA. Chiller Capacity each 350 Ton, 525 HP Motor, Max
Heat Rejection is 1,621 kW. Per set, 6 sets x 1,621 =
Sub Total D)
=
E) Electrical Load
Heat Dissipated from Transformers and LVSB
=
Sub Total E)
=
MJTA Consortium
852
852
kW.
kW.
9,726
9,726
kW.
kW.
695
695
kW.
kW.
24
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP (Cont’d)
SUMMARY
Heat Transmission + Electrical Load at Peak Hour
Occupancy and O.A Load
Machine Room Cooling Load
PCA. Chiller Heat Rejection
Electrical Load
=
=
=
=
=
20,896
9,497
852
9,726
695
Total Peak Hour Chiller Cooling Capacity
=
41,666 kW
MJTA Consortium
kW
kW
kW
kW
kW
25
SBIA : TERMINAL COMPLEX
45 MILLION ANNUAL PASSENGER
REDUCED CONCORSE WIDTH 4.35M
AND
REVISED MATERIAL OF CONSTRUCTION
MJTA Consortium
26
WATER SIDE PEAK COOLING LOADS SUMMARY
45 MAP
A) Heat Transmission + Electrical Load at Peak Hour
• East Concourse Building
• West Concourse Building
• Terminal Building
• Jetbridge East Concourse
• Jetbridge West Concourse
Sub Total A)
MJTA Consortium
7,464
7,381
4,875
617
559
=
kW.
kW.
kW.
kW.
kW.
20,896 kW.
27
WATER SIDE PEAK COOLING LOADS SUMMARY
45 MAP (Cont’d)
B) Occupancy and O.A Load
B.1 Officers + Employees +
Visitors + Meeters
=
13,879 Persons
Total Adjusted Heat Gain 130 W/Person;
13879 x 130/1000
=
1,804
kW.
Total O.A Supply 353,011 Cubic Meter Per Hour
Total O.A. Load
=
1.19 x 353,011/3.6 x (90-51)/1,000
=
4,551 kW.
MJTA Consortium
28
WATER SIDE PEAK COOLING LOADS SUMMARY
45 MAP (Cont’d)
B) Occupancy and O.A Load (Cont’d)
B.2 TPHP of 45 Million Annual Flow as Recommended by
FAA is Equivalent to 13,500 persons
TPHP Load of Passenger =
13,500 x 130 / 1,000
=
1,755 kW.
O.A. Load for TPHP
Sub Total B)
= 1.19 x 13,500 x 17 / 3.6 x (90-51) / 1,000
=
2,959 kW.
=
MJTA Consortium
11,069 kW.
29
WATER SIDE PEAK COOLING LOADS SUMMARY
45 MAP (Cont’d)
C) Machine Room Cooling Load
6 sets AHU Capacity each 142 kW.
=
Sub Total C)
=
D) PCA. Chiller Heat Rejection
PCA. Chiller Capacity each 350 Ton, 525 HP Motor, Max
Heat Rejection is 1,621 kW. Per set, 6 sets x 1,621 = 9,726
Sub Total D)
=
E) Electrical Load
Heat Dissipated from Transformers and LVSB =
695
Sub Total E)
=
MJTA Consortium
852
852
kW.
kW.
kW.
9,726
kW.
kW.
695
kW.
30
WATER SIDE PEAK COOLING LOADS SUMMARY
45 MAP (Cont’d)
SUMMARY
Heat Transmission + Electrical Load at Peak Hour
Occupancy and O.A Load
Machine Room Cooling Load
PCA. Chiller Heat Rejection
Electrical Load
=
=
=
=
=
20,896
11,069
852
9,726
695
Total Peak Hour Chiller Cooling Capacity
=
43,238 kW
MJTA Consortium
kW
kW
kW
kW
kW
31
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP AND 45 MAP
DESCRIPTION
A)
30 MAP
kW.
Heat Transmission + Electrical Load
East Concourse Building
West Concourse Building
Terminal Building
Jetbridge East Concourse
Jetbridge West Concourse
Sub Total A)
MJTA Consortium
45 MAP
kW.
7,464
7,381
4,875
617
559
7,464
7,381
4,875
617
559
20,896
20,896
32
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP AND 45 MAP (Cont’d)
B)
Occupancy and O.A. Load
B.1 Officers + Employees + Visitors = 13,879 Persons
Total Heat Gain at 130 Watts/Person
Total Peak Hour Passengers 130 W x 9,000 for 30 MAP
and 130 W x 13500 for 45 MAP
B.2
1,804
1,804
1,170
1,755
Sub Total B.1
2,974
3,559
O.A. Load for Officers, Employees, Visitors
Total 353,011 CMH: 1.19 x 353,011/3.6x(90-51)/1,000
O.A. Load for 9,000 TPHP = 1.19x9,000x17/3.6x(90-51)/1,000
O.A. Load for 13,500 TPHP = 1.19x13,500x17/3.6x(90-51)/1,000
4,551
1,972
-
4,551
2,959
Sub Total B.2
6,523
7,510
Sub Total B)
9,497
11,069
MJTA Consortium
33
WATER SIDE PEAK COOLING LOADS SUMMARY
30 MAP AND 45 MAP (Cont’d)
C)
Machine Room Cooling Load
6 sets AHU Capacity Each 142 kW
852
852
852
852
9,726
9,726
9,726
9,726
695
695
Sub Total E)
695
695
TOTAL PEAK HOUR CHILLER COOLING CAPACITY
41,666
43,238
Sub Total C)
D)
PCA. Chiller Heat Rejection
6 sets PCA Chiller 350 TR each, 525 HP Motor Max Heat Rejection
6 x 1621 kW.
Sub Total D)
E)
Heat Dissipated from Electrical-Transformer and LVSB Rooms
MJTA Consortium
34
CHILLED WATER PIPE COOLING CAPACITY
CHILLED WATER PIPE SCH. 40 COOLING CAPACITY BASED ON
MAX VEL. 3.1 m/sec.
MAX FRICTION LOSS 5%
TEMPERATURE DIFFERENT 8.5C°
PIPE DIA.
MM.
50
65
80
100
125
150
200
250
300
350
400
450
500
600
750
900
MAX FLOW
L/S
3.5
5.2
9.5
20
35
55
100
160
220
280
370
450
580
820
1390
1950
MAX VEL.
M/S
1.5
1.7
2
2.4
2.7
3.1
3.1
3.1
3.1
3.1
3.1
3.1
3.1
3.1
3.0
3.0
MJTA Consortium
COOLING CAPACITY
TR AT 8.5 C° TD.
35
53
95
202
354
556
1010
1616
2222
2828
3737
4545
5858
8282
14040
19696
35
CHILLED WATER PIPE COOLING CAPACITY
CHILLED WATER FLOW RATE
L/S
=
0.239 x KW
Δ C°
TR = 3.517 KW
INLET WATER TEMP. = 5.5 C°
L/S
=
OUTLET WATER TEMP. = 14 C°
0.239 x 3.517
8.5
TEMP. DIFFERENT = 8.5 C°
WATER FLOW RATE FORONE TR. AT 8.5 C° TEMP. DIFF.
MJTA Consortium
=
0.098889 L/S
=
0.099 L/sec.
36
. Cooling System and Power Plant (DCSPP)
District
for Suvarnabhumi International Airport
MJTA Consortium
37
District Cooling System and Power Plant (DCSPP)
By using natural gas as fuel to generate electricity and use
excess heat to produce hot steam as a requirment for absorbtion
chiller to produce chilled water for air conditioning purpose. This
technology will increase efficiency in generating electricity and
chilled water and will also reduce energy required.
MJTA Consortium
38
Airport Electrical Power Distribution
MEA 115kV
Back Up
DCAP
115kV
6.9kV
DCAP Inhouse use
MTS
Airport Main
Transformer
24kV
All Area in Airport
MJTA Consortium
39
Chilled Water Distribution
StationCar Park
TrainTrain
Station??,
100RT
700RT
MTB&Concourse 12,600RT
AIMS
700RT
AIM 200RT
Chilled Water
Supply from
DCAP
to …..
DCAP
AOB 500RT
AOB
1500RT
Airport Hotel 700RT
Total
19,000RT
(29,860RT)
Installed
Airport Hotel 1,500RT
MJTA Consortium
TG Catering Facility
5,000RT
40
Steam Distribution
10barg/185C/8.6t/h
DCAP
DCAP
TG Catering
8barg/175C/3t/h
Airport Hotel
Airport Hotel
MJTA Consortium
41
ตำแหน่ งที่ตัง้ ของโครงกำร
POWER PLANT
CHILLER PLANT
FOR CATERING
CHILLER PLANT FOR
PASSENGER TERMINAL
MJTA Consortium
42
MJTA Consortium
43
Questions and Answers
Thank you for your attention
Download