Suvarnabhumi International Airport ..WELCOME MEE Net.. MJTA Consortium 1 . SUVARNABHUMI INTERNATIONAL AIRPORT MJTA Consortium 2 SUVARNABHUMI AIR CONDITIONING SYSTEM SUVARNABHUMI AIR CONDITIONING SYSTEM BUILDING CONFIGURATION The Terminal building requires to have large hall area without concrete pole or with minimal concrete pole for passengers’ convenience. For maximum passengers comfort with ease of traveling within the airport compound, the building comprise of two sectors, the Terminal and Concourse building. The Concourse building is for airplane connection to boarding bridges. The Terminal building is for handling departure and arrival passengers. For energy saving purpose, the airconditioning will be provided only from floor level to 3 or 4 meter above the floor since passengers will not stay higher than 2 meters above the floor MJTA Consortium 4 SUVARNABHUMI AIR CONDITIONING SYSTEM BUILDING SIZE Concourse Width 40.50 m. Length 3,123 m. Hight 23.60 m. Terminal Width 108 m. Length 441 m. Hight 40 m. MJTA Consortium 5 SUVARNABHUMI AIR CONDITIONING SYSTEM AREA FOR AIR CONDITIONING Concourse 248,445 SQ.M. Terminal 119,906 SQ.M. TOTAL OF 368,351 MJTA Consortium SQ.M. 6 CONCEPTUAL DESIGN FOR ENERGY SAVING OF SUVARNABHUMI AIR CONDITIONING SYSTEM 1. 2. 3. Usage of direct sun light with minimal electrical lamps during day time. Air conditioning will be provided only from floor level to 3 or 4 meter above the floor to reduce the air conditioning load by means of Stratification technique. This technique use Radiant Floor Cooling together with Recirculated Air Cooling System. Control intake fresh air for continual changing number of passengers. MJTA Consortium 7 CONCEPTUAL DESIGN FOR ENERGY SAVING OF SUVARNABHUMI AIR CONDITIONING SYSTEM 4. 5. 6. 7. Adjust Variable Chilled Water Volume for continual changing cooling load. Use Chilled Water Temperature Difference ( delta T ) larger than normal conventional type which will require lesser pipe size and flow rate, thus reduced the pump size and energy required. Reduce make up water of Cooling Tower by way of water filter instead of bleed-off Reduce solar heat gain through glass by way of using Frit, a small circular pad, spread evenly on glass which help reduce the Solar Factor MJTA Consortium 8 CONCEPTUAL DESIGN FOR ENERGY SAVING OF SUVARNABHUMI AIR CONDITIONING SYSTEM พลังงาน 8. 9. 10. Reduce infrared radiation from ceiling and wall by way of applying LowE Infrared Hard Coating on ceiling and wall. Reduce convective heat gain from electrical lamps since the heat gain will be combined with hot air above stratification level which will cause no effect to passengers. Reduce radiation heat gain by way of using radiant floor cooling together with conventional air conditioning system. MJTA Consortium 9 Air Conditioning System MJTA Consortium 10 Radiant Floor Cooling Cooling tube to Diffuser Header Poly Etelene 1 header=10 loops Diffuser MJTA Consortium 11 SUVARNABHUMI INTERNATIONAL AIRPORT. Radiant Floor Shop Drawing: Configuration Detail Drawing. 12 MJTA Consortium 12 SUVARNABHUMI INTERNATIONAL AIRPORT. Radiant Floor Shop Drawing: Floor Plan 13 MJTA Consortium 13 SUVARNABHUMI INTERNATIONAL AIRPORT. VAC System. Temperature Layer 14 MJTA Consortium 14 SUVARNABHUMI AIR CONDITIONING SYSTEM Design Criteria Ambient Temp. 35C db 28C wb 24C±1 db 55+5% RH Circulation, Holdroom 10 W/m2 Office 15 W/m2 Retail 35 W/m2 Indoor Temp. Relative Humidity Lighting: MJTA Consortium 15 SUVARNABHUMI AIR CONDITIONING SYSTEM Design Criteria Outside Air: Passengers: (Peak Hour) Circulation, Holdroom 17 m3/hr/person Office 34 m3/hr/person Retail 26 m3/hr/person Terminal + Concourse 22,879 persons (30 MAP) 27,379 persons (45 MAP) OA total 506,011 m3/hr (30 MAP) 582,511 m3/hr (45 MAP) MJTA Consortium 16 SUVARNABHUMI AIR CONDITIONING SYSTEM Design Criteria Total Cooling Capacity 41,666 KW 43,238 KW = = MJTA Consortium 11,850 Tons (30 MAP) 12,297 Tons (45 MAP) 17 SUVARNABHUMI AIR CONDITIONING SYSTEM AOT purchase chilled water from DCAP (Districted Cooling System and Power Plant Company Limited). DCAP has installed 8 ABSORPTION CHILLERS at CENTRAL PLANT located within Parking building next to the Terminal building. DCAP installed 4 ABSORPTION CHILLERS ( DOUBLE EFFECT TYPE ) on each plant (EAST and WEST PLANT) and each absorption chiller has the capacity of 2,100 TR (norminal) and can produce 706 m3/hr (196.11 L/S) chilled water at return temp. of 14 C and supply temp. of 5 C MJTA Consortium 18 SUVARNABHUMI AIR CONDITIONING SYSTEM 4 Absorption Chiller Cooling capacity@2100 TR (7,386 kW) = 8,400 TR (29,544 kW) 4 Secondary chilled water pumps @ 706 m3/hr (196.11 L/S) = 2,824 m3/hr (784.44 L/S) Supply Temp. 5o C Return Temp. 14o C TOTAL COOLING CAPACITY OF EAST AND WEST PLANTS = 16,800 TR (59,088 kW) MJTA Consortium 19 SBIA : TERMINAL COMPLEX 30 MILLION ANNUAL PASSENGER REDUCED CONCORSE WIDTH 4.35M AND REVISED MATERIAL OF CONSTRUCTION MJTA Consortium 20 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP A) Heat Transmission + Electrical Load at Peak Hour • East Concourse Building • West Concourse Building • Terminal Building • Jetbridge East Concourse • Jetbridge West Concourse Sub Total A) MJTA Consortium 7,464 7,381 4,875 617 559 = kW. kW. kW. kW. kW. 20,896 kW. 21 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d) B) Occupancy and O.A Load B.1 Officers + Employees + Visitors + Meeters = Total Adjusted Heat Gain 130 W/Person; 13879 x 130/1000 = 13,879 Persons 1,804 kW. Total O.A Supply 353,011 Cubic Meter Per Hour Total O.A. Load = 1.19 x 353,011/3.6 x (90-51)/1,000 = 4,551 kW. MJTA Consortium 22 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d) B) Occupancy and O.A Load (Cont’d) B.2 TPHP of 30 Million Annual Flow as Recommended by FAA is Equivalent to 9,000 persons TPHP Load of Passenger = 9,000 x 130 / 1,000 = 1,170 kW. O.A. Load for TPHP = 1.19 x 9,000 x 17 / 3.6 x (90-51) / 1,000 = 1,972 kW. Sub Total B) = MJTA Consortium 9,497 kW. 23 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d) C) Machine Room Cooling Load 6 sets AHU Capacity each 142 kW. = Sub Total C) = D) PCA. Chiller Heat Rejection PCA. Chiller Capacity each 350 Ton, 525 HP Motor, Max Heat Rejection is 1,621 kW. Per set, 6 sets x 1,621 = Sub Total D) = E) Electrical Load Heat Dissipated from Transformers and LVSB = Sub Total E) = MJTA Consortium 852 852 kW. kW. 9,726 9,726 kW. kW. 695 695 kW. kW. 24 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d) SUMMARY Heat Transmission + Electrical Load at Peak Hour Occupancy and O.A Load Machine Room Cooling Load PCA. Chiller Heat Rejection Electrical Load = = = = = 20,896 9,497 852 9,726 695 Total Peak Hour Chiller Cooling Capacity = 41,666 kW MJTA Consortium kW kW kW kW kW 25 SBIA : TERMINAL COMPLEX 45 MILLION ANNUAL PASSENGER REDUCED CONCORSE WIDTH 4.35M AND REVISED MATERIAL OF CONSTRUCTION MJTA Consortium 26 WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP A) Heat Transmission + Electrical Load at Peak Hour • East Concourse Building • West Concourse Building • Terminal Building • Jetbridge East Concourse • Jetbridge West Concourse Sub Total A) MJTA Consortium 7,464 7,381 4,875 617 559 = kW. kW. kW. kW. kW. 20,896 kW. 27 WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d) B) Occupancy and O.A Load B.1 Officers + Employees + Visitors + Meeters = 13,879 Persons Total Adjusted Heat Gain 130 W/Person; 13879 x 130/1000 = 1,804 kW. Total O.A Supply 353,011 Cubic Meter Per Hour Total O.A. Load = 1.19 x 353,011/3.6 x (90-51)/1,000 = 4,551 kW. MJTA Consortium 28 WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d) B) Occupancy and O.A Load (Cont’d) B.2 TPHP of 45 Million Annual Flow as Recommended by FAA is Equivalent to 13,500 persons TPHP Load of Passenger = 13,500 x 130 / 1,000 = 1,755 kW. O.A. Load for TPHP Sub Total B) = 1.19 x 13,500 x 17 / 3.6 x (90-51) / 1,000 = 2,959 kW. = MJTA Consortium 11,069 kW. 29 WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d) C) Machine Room Cooling Load 6 sets AHU Capacity each 142 kW. = Sub Total C) = D) PCA. Chiller Heat Rejection PCA. Chiller Capacity each 350 Ton, 525 HP Motor, Max Heat Rejection is 1,621 kW. Per set, 6 sets x 1,621 = 9,726 Sub Total D) = E) Electrical Load Heat Dissipated from Transformers and LVSB = 695 Sub Total E) = MJTA Consortium 852 852 kW. kW. kW. 9,726 kW. kW. 695 kW. 30 WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d) SUMMARY Heat Transmission + Electrical Load at Peak Hour Occupancy and O.A Load Machine Room Cooling Load PCA. Chiller Heat Rejection Electrical Load = = = = = 20,896 11,069 852 9,726 695 Total Peak Hour Chiller Cooling Capacity = 43,238 kW MJTA Consortium kW kW kW kW kW 31 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP AND 45 MAP DESCRIPTION A) 30 MAP kW. Heat Transmission + Electrical Load East Concourse Building West Concourse Building Terminal Building Jetbridge East Concourse Jetbridge West Concourse Sub Total A) MJTA Consortium 45 MAP kW. 7,464 7,381 4,875 617 559 7,464 7,381 4,875 617 559 20,896 20,896 32 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP AND 45 MAP (Cont’d) B) Occupancy and O.A. Load B.1 Officers + Employees + Visitors = 13,879 Persons Total Heat Gain at 130 Watts/Person Total Peak Hour Passengers 130 W x 9,000 for 30 MAP and 130 W x 13500 for 45 MAP B.2 1,804 1,804 1,170 1,755 Sub Total B.1 2,974 3,559 O.A. Load for Officers, Employees, Visitors Total 353,011 CMH: 1.19 x 353,011/3.6x(90-51)/1,000 O.A. Load for 9,000 TPHP = 1.19x9,000x17/3.6x(90-51)/1,000 O.A. Load for 13,500 TPHP = 1.19x13,500x17/3.6x(90-51)/1,000 4,551 1,972 - 4,551 2,959 Sub Total B.2 6,523 7,510 Sub Total B) 9,497 11,069 MJTA Consortium 33 WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP AND 45 MAP (Cont’d) C) Machine Room Cooling Load 6 sets AHU Capacity Each 142 kW 852 852 852 852 9,726 9,726 9,726 9,726 695 695 Sub Total E) 695 695 TOTAL PEAK HOUR CHILLER COOLING CAPACITY 41,666 43,238 Sub Total C) D) PCA. Chiller Heat Rejection 6 sets PCA Chiller 350 TR each, 525 HP Motor Max Heat Rejection 6 x 1621 kW. Sub Total D) E) Heat Dissipated from Electrical-Transformer and LVSB Rooms MJTA Consortium 34 CHILLED WATER PIPE COOLING CAPACITY CHILLED WATER PIPE SCH. 40 COOLING CAPACITY BASED ON MAX VEL. 3.1 m/sec. MAX FRICTION LOSS 5% TEMPERATURE DIFFERENT 8.5C° PIPE DIA. MM. 50 65 80 100 125 150 200 250 300 350 400 450 500 600 750 900 MAX FLOW L/S 3.5 5.2 9.5 20 35 55 100 160 220 280 370 450 580 820 1390 1950 MAX VEL. M/S 1.5 1.7 2 2.4 2.7 3.1 3.1 3.1 3.1 3.1 3.1 3.1 3.1 3.1 3.0 3.0 MJTA Consortium COOLING CAPACITY TR AT 8.5 C° TD. 35 53 95 202 354 556 1010 1616 2222 2828 3737 4545 5858 8282 14040 19696 35 CHILLED WATER PIPE COOLING CAPACITY CHILLED WATER FLOW RATE L/S = 0.239 x KW Δ C° TR = 3.517 KW INLET WATER TEMP. = 5.5 C° L/S = OUTLET WATER TEMP. = 14 C° 0.239 x 3.517 8.5 TEMP. DIFFERENT = 8.5 C° WATER FLOW RATE FORONE TR. AT 8.5 C° TEMP. DIFF. MJTA Consortium = 0.098889 L/S = 0.099 L/sec. 36 . Cooling System and Power Plant (DCSPP) District for Suvarnabhumi International Airport MJTA Consortium 37 District Cooling System and Power Plant (DCSPP) By using natural gas as fuel to generate electricity and use excess heat to produce hot steam as a requirment for absorbtion chiller to produce chilled water for air conditioning purpose. This technology will increase efficiency in generating electricity and chilled water and will also reduce energy required. MJTA Consortium 38 Airport Electrical Power Distribution MEA 115kV Back Up DCAP 115kV 6.9kV DCAP Inhouse use MTS Airport Main Transformer 24kV All Area in Airport MJTA Consortium 39 Chilled Water Distribution StationCar Park TrainTrain Station??, 100RT 700RT MTB&Concourse 12,600RT AIMS 700RT AIM 200RT Chilled Water Supply from DCAP to ….. DCAP AOB 500RT AOB 1500RT Airport Hotel 700RT Total 19,000RT (29,860RT) Installed Airport Hotel 1,500RT MJTA Consortium TG Catering Facility 5,000RT 40 Steam Distribution 10barg/185C/8.6t/h DCAP DCAP TG Catering 8barg/175C/3t/h Airport Hotel Airport Hotel MJTA Consortium 41 ตำแหน่ งที่ตัง้ ของโครงกำร POWER PLANT CHILLER PLANT FOR CATERING CHILLER PLANT FOR PASSENGER TERMINAL MJTA Consortium 42 MJTA Consortium 43 Questions and Answers Thank you for your attention