BILLS OF QUANTITIES
PROJECT NAME : DOEHLER Egypt S.A.E.
5 Engineering Square-Plot#4 of North Expansions
6th October City-Egypt
DIVISION - 15 - Mech. Works (Fire Fighting)
FIRE FIGHTING SYSTEM
Ref.
.1
DESCRIPTION
DRAWING REF. : 02-01-DD-FF
Unit Price Amount
L.E
L.E
Quantity
Unit
20
set
0
1
1
set
set
0
0
24
24
18
24
36
12
24
6
36
mt
mt
mt
mt
mt
mt
mt
mt
mt
0
0
0
0
0
0
0
0
0
3
set
0
5
Set
0
0
Sprinkle Head:
Supplying, installing, connecting and testing of Quick
Response / ESFFR Sprinkler heads type, UL/FM
approved as shown on drawings and specifications.
. 1-2 Upright sprinklers heads K 8 rating temp 74 C NonStorage
2
Zone Control Station
Supplying, installing, connecting and testing of Zone
control station (Z) consist of (OS&Y) gate valve and
check valve with tamper switch and flow switch both
wired to fire alarm, pressure gauge, and 1.5 inch
inspector test and drain (assembly with sight glass),
Pressure relife valve, complete with all fittings as per
FM Stander and as shown on drawings and
specifications.
2-1 6 inch Zone control station
2-2 3 inch Zone control station
3
Fire Water Line:
3-1
3-2
3-3
3-4
3-5
3-6
3-7
3-8
3-9
Supply, lift into position, install, test, set to work, and
commission Above ground pipes, Seamless black
Steel ASTM A 53 Schedule 40 category including,
grooved fittings expansion joints, galvanized hangers
and supports, and all pipes are painted with two
coats of red oxide primer and two coats of fire red
Diameter 150 mm (6 Inch)
Diameter 150 mm (6 Inch) Underground
Diameter 100 mm (4 Inch)
Diameter 75 mm (3 Inch)
Diameter 65 mm (2 ½ Inch)
Diameter 65 mm (2 Inch)
Diameter 40 mm (1 ½ Inch)
Diameter 25 mm (1 Inch)
Diameter 20 mm (3/4 Inch)
4
Automatic Direct Fire Detection And Suppression System:
For electric panels Supplying, installing, connecting,
testing and commissioning The FM-200 gaseous fireextinguishing agent Automatic Systems, as per
"NFPA-2001 Standard on Clean Agent" Fire
Extinguishing Systems complete with but not limited to
Cylinder Mounting Bracket, Flexible Detector,
Actuation and Discharge Tubing, Pressure Switch,
Recharge Adapter, FM-200 Cylinder, all necessary
accessories and ancillary works required for interlock
with (fire detection system) and as shown on details
drawing and as specified.
4-1 Extinguisher Charged with 12.0 Lbs. of FM-200
5
5.1
Fire Hose cabinet:
Supply, lift into position, install, test, set to work, and
commission Fire Hose cabinet with 30 meters length,
40 mm (1.5 Inch) diameter fire hose cabinet assembly
complete with bronze adjustable spray nozzle, (multipurpose dry chemical powder fire extinguisher 6-Kg
capacity), as per drawings.
BILL SUMMARY
DOEHLER Egypt S.A.E.
FIREFIGHTING
INTEGRATED MECHANICAL ENGINEERING OFFICE
BILLS OF QUANTITIES
PROJECT NAME : DOEHLER Egypt S.A.E.
5 Engineering Square-Plot#4 of North Expansions
6th October City-Egypt
DIVISION - 15 - Mech. Works (Fire Fighting)
FIRE FIGHTING SYSTEM
Notes:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
DOEHLER Egypt S.A.E.
DRAWING REF. : 02-01-DD-FF
Prices including lifting tools, scissor lift and all equipments needed to complete the work.
Material given in the drawing and/or spec's not necessarily repeated in the Bill of Quantities. The
Technical
Specification
forms an
partnumber
of the Bill
Quantities.
include
dismantlingand
The Tenderer
is committed
to integral
check the
of ofthe
pages ofPrices
the Bill
of Quantities
should any be found missing or duplicated or the figures or writing indistinct, the Tenderer must notify
The Tenderer is deemed to have visited the site and fully acquainted himself as to the location of each
of the
pipesto each of the roads in which the pipes will be installed.
Access
Access for the plant, equipment and materials.
Surface conditions
All safety regulations and employer site safety procedures.
Installation methods according to site condition
Quantities will surveyed according to actual quantities which will be installed, and all material need to
complete
works
according to
FMequipments
standards should
to be
included
on BOQ prices
All
materials,
components
and
used are
FM
approved.
All materials used are the best new available, guaranteed and subject to the consultant approval.
Execution is subject to approval of project consultant.
Materials or products are to be taken as samples of what will be required. Subject to the consultant
approval.
The unit prices include wall opening and repair any damage may happened during installation.
The unit price shall cover all costs, without being limited to, all charges for additional supervision, labor,
transportation
supply
materials
all72,
temporary
worksaccording
and all services
and the fulfillment
of all
All installationsand
should
be of
according
toand
NFPA
FM Standard,
to site conditions
and
according
to safety
consultant
approval.
safety, food
and plant
operation requirements should to apply by contractor during installation.
Water or/and Electricity required for completion of the work shall be coordinated with the owner as per
owner
capability,
otherwise
willrequested
provide bybycontractor.
Contractor
committed
by tests
project consultant.
The tests and measurement required by the consultant obligated to the contractor
The contract price includes the submissions of all user manuals, catalogues, software’s and
other
related and data sheets should to submit to review by consultant for approval before installations
Shop drawing,
as built drawing should to submit by contractor to review.
FIREFIGHTING
INTEGRATED MECHANICAL ENGINEERING OFFICE