Defending a Beach from Bacteria
Stormwater Treatment at Venice Beach
2016 Florida Stormwater Association Annual Conference
Presented by
James Clinch, P. E., City of Venice
Gary Serviss, VHB
June 15, 2016
PROJECT
LOCATION
PROJECT
LOCATION
BEACH STORMWATER OUTFALLS
Safety
Maintenance
Public Perception
Stormwater Discharges
VENICE BEACH
Popular Public Recreational Beach
Directly adjacent to Stormwater Outfall 1
Recurring Bacteria Issues
Dry Season (Dec. – May)
VENICE BEACH
Numerous “No Swim” Advisories Issued
2011 – 34 days of “No Swim”
Spring Break
Media Blitz, Tourism, Property Values, Political
BACTERIA SOURCE TRACKING
Upstream Pipe & Manhole Inspections
Abandoned Pipe Removal
Sanitary Sewer Inspections
Bacteria & DNA Sampling
PROJECT OBJECTIVES
Minimize the Bacteria
Loads to the Gulf
Reduce Nutrient &
Sediment Loads
Integrate into Existing
Stormwater System &
Surrounding
Neighborhood
#1
#2
ALTERNATIVES ANALYSIS
Traditional Treatment
– Limited Space
Deep Water Discharge
#1
– Hard Bottom, $$$
Ultra-Violet Treatment
– Expensive O&M
Sanitary Sewer Diversion
– Low Flows, Sewer Fees
#2
ALTERNATIVES ANALYSIS
Traditional Treatment
– Limited Space
Deep Water Discharge
#1
– Hard Bottom, $$$
Ultra-Violet Treatment
– Expensive O&M
Sanitary Sewer Diversion
– Low Flows, Sewer Fees
In Dune Treatment
#2
DESIGN – DUNE TREATMENT
City Owned Right-of-Way
Project Budget of $500,000
DESIGN – DUNE TREATMENT
Diversion Pump at Outfall #1 into Treatment System
DESIGN – DUNE TREATMENT
Exfiltration Trench – 500 LF
DESIGN – DUNE TREATMENT
Planted Bio-Swale – 500 LF
Diversion Pump at Outfall #2
PROJECT GRANTS
SWFWMD COOPERATIVE FUNDING GRANT
EPA SECTION 319 GRANT
PROJECT CHALLENGES
Permitting
– FDEP Coastal Construction Control Line
– SWFWMD ERP
Intense Public Opposition
–
–
–
–
–
–
–
Aesthetics – Ugly Stormwater Ponds
Beach View Obstructions
Beach Access Obstructions
Pump Noise
Odor from Standing Water
Mosquitos
Environmental Impacts
PROJECT CHALLENGES
Media Opposition
– SWFWMD Permit Legally Challenged
– City Ownership Legally Challenged
PR STRATEGY
Minor Adjustments to Design
Numerous Community Workshops
One-on-One Meetings
Successful: 8 Month Project Delay
– Attorney Fees & Staff Time
CONSTRUCTION!
Broke Ground December 2014
CONSTRUCTION!
Bio-swale Installation
CONSTRUCTION!
Exfiltration Trench Installation
CONSTRUCTION!
Exfiltration Trench Installation
CONSTRUCTION!
Pump Station #1 Installation
CONSTRUCTION!
Pump Station #1 Installation
CONSTRUCTION CHALLENGES
PEAK TOURIST SEASON
BEACH NOURISHMENT & UTILITY PROJECTS
ABANDONED SEWER LIFT STATION
PROJECT COMPLETION
Lift Station #1
PROJECT COMPLETION
Completed Lift Station #1
PROJECT COMPLETION
Completed Lift Station #2
PROJECT COMPLETION
Completed Bio-Swale w/Plantings
PROJECT COMPLETION
Completed Exfiltration Trench
SYSTEM OPERATION
Placed into Operation May 2015
SYSTEM OPERATION
Bio-Swales in Action
SYSTEM OPERATION
Bio-Swales in Action
Monitoring Program
Quality Assurance Project Plan (QAPP)
Storm Event Monitoring (10)
Rainfall Threshold (0.2”)
Sample Inflow and Outflow
EMC and Volume
Monitoring
Station
Locations
Inflow
Station
Outflow
Station
Technical Challenges
Small Watershed
Short Sampling
Window
Enclosed System
Limited
Stage/discharge
relationship
Duals pumps
Solution
Pace based on pump
duration
Tie into electric panel
Program Volume
Equipment
Design
Equipment Design
Equipment Design
Outflow
Design
Remote Communication
Web access
Real time data - Rainfall, pump activation, ISCO
subsamples
Manipulate programming
Rainfall
Figure 3-1. Average Total Daily Rainfall
3.00
Site Rainfall
Local Weather*
2.50
Precipitation (in)
2.00
1.50
1.00
0.50
0.00
Discharge
Figure 3-3. Daily Discharge from Station 1
30.0
Volume (thousands of cubic feet)
25.0
20.0
15.0
[CELLRANGE]
[CELLRANGE]
[CELLRANGE]
[CELLRANGE]
[CELLRANGE]
[CELLRANGE]
10.0
5.0
0.0
[CELLRANGE]
[CELLRANGE]
[CELLRANGE] [CELLRANGE] [CELLRANGE]
[CELLRANGE]
[CELLRANGE]
Water Quality Results
Parameter
Total Nitrogen
Total Phosphorus
Total Suspended Solids
Fecal Coliform
Enterococci
Average EMC
Inflow Outflow Change
0.778
0.150
21.8
3,430
30
0.496
0.561
1.2
2,145
<10
36%
-274%
94%
37%
83%
Loads and Load Removal
Parameter
Total Nitrogen (kg)
Total Phosphorus (kg)
Total Suspended Solids (kg)
Fecal Coliform (Mcol)
Enterococci (Mcol)
Inflow
5.79
1.12
162.1
2,556
1,598
Total Load
Outflow Removed
0.091
0.10
0.221
6
0.9
5.70
1.02
161.9
2,551
1597.1
Removal Efficiency
Parameter
Total Nitrogen
Total Phosphorus
Total Suspended Solids
Fecal Coliform
Enterococci
Removal Efficiency
98%
91%
100%
100%
100%
Recommendations
Evaluate the potential sources of
secondary pollutant loading.
Evaluate the potential to increase
the volume of water reaching the
BMP and/or the bioretention
swale.
OPERATION & MAINTENANCE
Over 1 Year of
Successful Operation
Maintenance Occurring
– Quarterly on Pump
Stations
– Bi-Annually on
Cleanout Manholes
PROJECT OBJECTIVES
Minimize the Bacteria Loads to the Gulf
– Achieved: High efficiency removal of
Enterococci Indicator Bacteria
– Bacteria diverted to treatment system,
reducing occurrence of “No Swim”
Advisory and Protecting Public Health
Reduce Nutrients & Sediment Loads
– Partially Achieved: High efficiency
removal, however diversion volume could
be increased to provide higher removal
PROJECT OBJECTIVES
Integrate into Existing Stormwater System
& Surrounding Neighborhood
– Achieved: Angry Mob has Dispersed!
– Final product very well received by local
community.
CONCLUSION
In-Dune Stormwater Treatment very successful
for Venice Beach
We have not had a Beach Advisory since the
system has been operational
Never too early to get ahead of Public Opinion!
• PROJECT Q & A
James R. Clinch | jclinch@venicegov.com | 941.284.6990
www.vhb.com
Gary Serviss | gserviss@vhb.com | 941.256.7151
Offices located throughout the east coast