Federal Government Cost Overruns

advertisement
No. 72 • September 2015
Federal Government Cost Overruns
Chris Edwards and Nicole Kaeding, Cato Institute
The federal government has hundreds of agencies and
thousands of programs, and it now spends almost $4
trillion a year. The government has grown too large to
manage efficiently. Agencies have little incentive to
control costs or improve quality, and Congress does a poor
job of overseeing the executive branch to ensure good
performance. As a result, many federal agencies suffer
from wasteful spending practices.1
One aspect of federal waste is frequent cost overruns
on major projects, such as weapon systems and
infrastructure. If a government project is initially estimated
to cost $1 billion, it may end up costing $2 billion by the
time it is finished. This essay looks at the causes of cost
overruns, and examines some of the budget areas that have
the most serious problems, including defense, energy, and
transportation.
Scope of the Problem
The federal government proceeds with large projects
on the basis of estimated costs, but once projects get
underway officials often revise the costs upward. Cost
overruns have plagued the federal government since the
beginning. Way back in 1836, for example, a Ways and
Means Committee report criticized infrastructure spending
by the Army Corps of Engineers. All 25 projects reviewed
by the committee that year were overbudget, and “many”
had cost overruns of 50 percent or more.2
Economists Stanley Engerman and Kenneth Sokoloff
studied a sample of major government infrastructure
projects in U.S. history and found that most had substantial
cost overruns.3 The construction of the Erie Canal between
1817 and 1825, for example, went 46 percent overbudget,
while the canal’s later expansion went 142 percent
overbudget.
In recent years, many federal projects have had large
cost overruns. The cost to create the Healthcare.gov
website launched in 2013 grew from $464 million to $824
million.4 The International Space Station more than
quadrupled in cost from $17 billion to $74 billion.5 The
Capitol Visitor Center in Washington soared in cost from
an initial $265 million to $621 million by the time it was
completed in 2008.6
Cost overruns have plagued hospital construction by
the Department of Veterans Affairs.7 A hospital currently
being built in Orlando has more than doubled in cost from
$254 million to $616 million. And a hospital being built
near Denver has quintupled in cost from $328 million to
$1.7 billion.
Cost overruns on government projects are a global
phenomenon.8 For example, construction costs for
Olympic Games often escalate, with the 2012 London
Olympics doubling in cost, and the 1992 Barcelona
Olympics quadrupling in cost.9 Describing government
infrastructure, the World Bank concluded, “studies show a
history of extensive cost and time overruns in construction
projects across the sectors and in countries around the
world. . . . The rising expense can be crippling for
governments, particularly in developing countries as they
try to improve basic services.”10
A leading expert on cost overruns is Bent Flyvbjerg, a
Danish professor of planning. His co-authored 2003 book,
Megaprojects and Risk, concluded that “cost overruns of
50 percent to 100 percent in real terms are common in
megaprojects.”11 In one of his studies, Flyvbjerg looked at
258 large transportation projects across 20 countries.12 He
found that 90 percent went overbudget.
Another study by a team at Oxford University looked
at 245 dam projects across 65 countries.13 The study found
that average construction costs were 96 percent higher than
originally budgeted, in constant dollars. Thus, real dam
costs have typically doubled from the original estimates.
This issue is important because the true costs of
projects determine whether or not they make economic
sense. On the Oxford study, for example, the average
projected benefits of the dams was just 40 percent higher
than the originally estimated costs. Since the costs, on
average, rose 96 percent, the study concluded that large
dams are not economically viable in most cases.
Unfortunately, government policymakers and planners
do not seem to learn from past mistakes. Flyvbjerg finds
that the magnitude of cost overruns on major projects has
not declined over time.14 Engerman and Sokoloff come to
similar conclusions.15 So there appear to be systematic
factors that induce governments to either consistently
mismanage projects, low-ball initial cost estimates, or
both.
Causes of Cost Overruns
There are technical reasons why cost overruns may
occur on major projects. The costs of materials, labor, or
other inputs may change in unexpected ways. Projects may
face delays for reasons not envisioned. Project planners
may have “optimism bias,” meaning that they are eager for
a positive result and overlook possible problems.
However, expert planners and engineers should
consider contingencies and include leeway in their initial
cost estimates. They should study prior projects, consider
risk factors, and construct conservative estimates.
Optimism should be tempered by experience in dealing
with problems on previous projects. If planners did make
realistic projections based on experience, one would
expect that, in a sample of projects, the errors in cost
estimating would go both ways—some projects would be
underbudget and some would be overbudget.
However, that is not what happens with large
government projects. In studying hundreds of projects,
Flyvbjerg and his colleagues conclude that the differences
in initial and final cost figures “are too consistent and too
one-sided for this.”16 Projects generally run overbudget,
not underbudget.
The cost overrun problem has not diminished over
time. Yet, as Flyvbjerg notes, “it seems unlikely that a
whole profession of forecasting experts would continue to
make the same mistakes decade after decade instead of
learning from their actions.”17 So he concludes that project
promoters purposely low-ball initial cost estimates to
increase the likelihood of project approval. Flyvbjerg calls
this “strategic misrepresentation.”
With the federal government, there are structural
incentives that encourage both low-balled estimates and a
lack of cost control on projects once they are underway.
Unlike businesses, federal agencies do not have to earn
profits, so they have little reason to restrain costs. A 2014
Government Accountability Office (GAO) report on
Department of Defense (DoD) contracting noted:
In DoD, there can be few consequences if funds
are not used efficiently. For example, as has
often been the case in the past, agency budgets
generally do not fluctuate much year to year and,
programs that experience problems tend to
eventually receive more funding to get well.18
Another problem in the government is that
disciplining managers is difficult because of strong civil
service and union protections. Just 0.5 percent of federal
workers get fired each year, which is just one-sixth the
private-sector firing rate.19 Also, federal pay is generally
tied to longevity, not performance. As a result, federal
managers do not have strong incentives to ensure that
projects are executed on time and on budget.
Now consider the incentives in Congress. Members
are inclined to support expensive federal projects that
benefit voters in their districts and states, even when
projects make no sense for the overall nation. Cost
overruns may generate some negative publicity, but they
also create benefits for politicians because they mean more
spending in affected congressional districts.
Alan Stern, a former associate administrator of the
National Aeronautics and Space Administration (NASA),
pointed to numerous bureaucratic and political reasons for
chronic cost overruns:
Endemic project cost increases at NASA begin
when scientists and engineers (and sometimes
Congress) burden missions with features beyond
what is affordable in the stated budget. The
problem continues with managers and
contractors who accept or encourage such
assignments, expecting to eventually be bailed
out. It is worsened by managers who disguise
the size of cost increases that missions incur.
Finally, it culminates with scientists who won’t
cut their costs and members of Congress who
accept steep increases to protect local jobs.20
Flyvbjerg and his colleagues conclude that “project
promoters routinely ignore, hide, or otherwise leave out
important project costs and risks in order to make total
costs appear low.”21 Put another way, politicians, officials,
and contractors use “salami tactics.” They present
artificially low costs up front to gain initial funding, and
then higher costs are revealed later on one slice at a time
when projects are too far along to be canceled.
Martin Wachs, an infrastructure expert at RAND
Corporation, has come to similar conclusions about the
causes of cost overruns:
I have interviewed public officials, consultants,
and planners who have been involved [in transit
projects and ridership forecasting] and I am
absolutely convinced that the cost overruns and
patronage overestimates were not the result of
technical errors, honest mistakes, or inadequate
methods. In case after case, planners, engineers,
and economists have told me that they had to
‘revise’ their forecasts many times because they
failed to satisfy their superiors. The forecasts
had to be ‘cooked’ in order to produce numbers
that were dramatic enough to gain federal
support for projects whether or not they could
be fully justified on technical grounds.22
William Ibbs, a professor of construction management
at the University of California, Berkeley, concurs that
governments often lowball initial cost estimates to help get
projects underway: “I’m not saying they’re committing
fraud, but let’s say they’re overly optimistic. . . . They’ll
get the work going and then the public will be reluctant to
cancel a project because they’ve spent all this money so
far.”23
Former San Francisco mayor Willie Brown has been
even more blunt than Ibbs or Wachs. In a 2013 opinion
piece, he described the sources of cost overruns on projects
in his city:
News that the Transbay Terminal is something
like $300 million over budget should not come
as a shock to anyone. We always knew the
initial estimate was way under the real cost. Just
like we never had a real cost for the Central
Subway or the Bay Bridge or any other massive
construction project. So get off it. In the world
of civic projects, the first budget is really just a
down payment. If people knew the real cost
from the start, nothing would ever be approved.
The idea is to get going. Start digging a hole and
make it so big, there’s no alternative to coming
up with the money to fill it in.24
Brown was in the California assembly for 30 years and
mayor of San Francisco for 8 years, so he knows how the
government works. He is saying that officials provide the
public with fake initial estimates to get projects approved,
and then projects are moved ahead before the truth is
known so that there is no turning back. Note that major
shares of funding for San Francisco’s Transbay Transit
Terminal and Central Subway came from the federal
government.25
Defense Projects
The Department of Defense has long struggled with
cost overruns. As one of the first major procurements
under the Constitution, the government bought six Navy
frigates in 1794. The ships were projected to cost
$688,889, but a myriad of problems pushed the ultimate
cost up 70 percent to $1,176,721.26
Over the decades, that pattern has been repeated many
times. The Pentagon building itself, constructed in
Virginia in the 1940s, “was built upon a foundation of lies,
secrecy, and cost overruns.”27 The Pentagon building
ending up costing $75 million to build, more than double
the original estimate of $35 million.
In 2006 Comptroller General David Walker said that
the Pentagon has “a long-standing track record of overpromising and under-delivering with virtual impunity.”28
In 2008 the GAO found, “DoD’s major weapon system
programs continue to take longer, cost more, and deliver
fewer quantities and capabilities than originally
planned.”29 And in 2014 the GAO noted, “Weapon
systems acquisition has been on GAO’s high risk list since
1990. . . . While some progress has been made on this
front, too often we report on the same kinds of problems
today that we did over 20 years ago.”30
Congress has made some reforms to help reduce
defense cost overruns, but the problem does not seem to
have diminished. For 91 major programs the GAO
examined in 2005, R&D costs were 33 percent overbudget,
on average, and procurement costs were 18 percent
overbudget.31 For 78 major programs examined in 2014,
R&D costs were 53 percent overbudget, and procurement
costs were 46 percent overbudget.32 These overruns are
measured in constant dollars.
Policymakers often blame the Pentagon’s use of costplus or cost-reimbursement contracts—rather than fixedprice contracts—as a key problem. Cost-plus contracts
seem to give a “blank check” to contractors because they
allow costs to rise over time. And, indeed, studies find that
cost-plus contracts typically have more cost growth than
do fixed-price contracts.33
However, some experts argue that a greater use of
fixed-price contracts would not necessarily reduce overall
procurement costs.34 Producing advanced weapons is a
complex activity, which makes it difficult to set tight upfront parameters. As a result, fixed-price contracts are
often modified to add new capabilities, which tends to
push up overall costs.35 So finding the best solution for
Pentagon contracting is not easy, and different types of
contracts are likely appropriate for different types of
procurement.
Nonetheless, there is wide agreement that current DoD
procurement suffers from a bloated bureaucracy and
excess paperwork, and it moves far too slowly.36 The
system produces results biased strongly toward cost
overruns. Consider the Joint Strike Fighter, or F-35, which
is the Pentagon’s largest acquisition program at almost
$400 billion. Real, per-unit costs of the fighters have
soared 75 percent since 2001, as shown in Table 1.37
Another high-profile cost overrun was the purchase of
new Marine One helicopters for the president. The VH-71
project began in 2002, and then estimated costs began to
rise, eventually doubling from $6.5 billion to $13 billion.38
The GAO pinned the blame on DoD mismanagement.39
Fortunately, the DoD scrapped the VH-71 program in
2009, but after $3.2 billion had already been spent.40
In sum, the Pentagon and Congress share the blame for
ongoing problems in defense procurement. The GAO says
that the military branches “overpromise capabilities and
underestimate costs to capture the funding needed to start
and sustain development programs.”41
As for Congress, many members fight attempts to
restrain spending in their districts, including spending on
weapons that the Pentagon does not want. As defense
analyst Winslow Wheeler noted in his book about the
dysfunction in military budgeting, gaining parochial
advantage “has become a full-time preoccupation that
permeates Congress’s activities and members’
decisionmaking processes.”42
Table 1. Sampling of Defense Cost Overruns
Cost Estimate and
Defense Projects43
Date of Estimate
Original
Recent or
Final
Littoral Combat Ship
$360m
$667m
(2004)
(2014)
Evolved Expendable
$102m
$376m
Launch Vehicle
(1998)
(2013)
Joint Strike Fighter
$79m
$138m
(2001)
(2013)
JPALS Landing System
$29m
$77m
(2008)
(2014)
G/ATOR Radar
$24m
$61m
(2005)
(2014)
Notes: Costs in this table are per-unit in constant 2015 dollars.
By contrast, Tables 2 and 3 show total costs in nominal dollars.
m=million.
Energy Projects
Mismanagement is pervasive in the Department of
Energy (DOE). The largest part of DOE’s budget is
spending on the National Nuclear Security Administration
(NNSA), which handles the safety of America’s nuclear
weapons stockpile. NNSA activities are plagued with cost
overruns.44 For example, “costs have skyrocketed for the
Mixed Oxide Fuel Fabrication Facility at the Savannah
River plant in South Carolina.”45 When the NNSA began
this program in 2002, it was expected to cost $1 billion,
but by 2014 costs had soared more than seven-fold to $7.8
billion. The project has already consumed $5 billion in
taxpayer funding, and a group of outside experts is now
calling for it to be cancelled.46
The second largest part of DOE’s budget is spending
to clean up federal nuclear weapon sites. This activity has
cost a remarkable $150 billion or more since 1990.47
Unfortunately, “efforts to treat and dispose of high-level
waste have been plagued with false starts and failures,
resulting in steadily growing estimates of the program’s
total cost,” noted GAO.48
In 2008 GAO found that “nine of 10 cleanup projects
we reviewed have experienced cost increases and schedule
delays in their life cycle baseline, ranging from $139
million for one project to more than $9 billion for another,
and schedule delays ranging from 2 years to 15 years.”49
The largest nuclear site cleanup is at Hanford in
Washington State. A key waste treatment plant at Hanford
ballooned in cost from $4.3 billion in 2000 to $13.4 billion
by 2012, as shown in Table 2.50
Federal energy research has been another black hole
for taxpayer dollars. One boondoggle was the Illinoisbased FutureGen. It was launched in 2003 to build a lowemission coal power plant and demonstrate carbon capture
technologies. It was originally estimated to cost $950
million, but by 2008 the cost had ballooned to $1.8
billion.51 The George W. Bush administration wisely
cancelled it. But in 2010, the Obama administration
revived the project, which it dubbed FutureGen 2.0. This
version of the project also went overbudget, and was
eventually cancelled in 2015.52 The project made no
economic sense, but was sustained for years by the dogged
efforts of Illinois members of Congress.
Table 2. Sampling of Energy Cost Overruns
Energy Projects
Cost Estimate and
Date of Estimate
Original
Recent or
Final
Hanford waste site53
$4.3b
$13.4b
(2000)
(2012)
Superconducting
$4.4b
$11.8b
Supercollider54
(1987)
(1993)
NNSA-Savannah River55
$1.0b
$7.8b
(2002)
(2014)
56
National Ignition Facility
$2.1b
$5.3b
(1995)
(2014)
Clinch River Reactor57
$400m
$4.0b
(1971)
(1983)
58
FutureGen clean coal
$950m
$1.8b
(2003)
(2008)
Note: m=million, b=billion.
Transportation Projects
Cost overruns on transportation projects have plagued
American governments since at least the 19th century. The
Erie Canal, which opened in 1825, suffered a large cost
overrun, as noted, but in the end it turned out to be an
economic success. The problem was what happened next:
the Erie’s success prompted politicians in Michigan,
Pennsylvania, Ohio, Indiana, Maryland, and Illinois to
spend lavishly on their own, often dubious, canal
schemes.59 The states overestimated the demand for canals
and underestimated the construction costs. Routes were
often chosen for political reasons, not to maximize
economic benefits. It turned out that the Erie Canal was a
uniquely high-return route, while nearly all the rest of the
state-sponsored canals in the 19th century were
boondoggles that created large taxpayer losses.
Today’s equivalent of boondoggle canals is urban rail
systems, which cost federal taxpayers $13 billion a year.60
Federally funded rail projects have long been prone to cost
overruns and inflated ridership projections. A 1990
Department of Transportation (DOT) report examined the
costs of 10 large rail projects.61 Nine of the projects had
cost overruns, and the average overrun was 50 percent.
Little has changed since that study. Martin Wachs, the
RAND infrastructure expert, says, “of 35 public transit
projects I have studied in the U.S., 33 overestimated
patronage [ridership] and 28 underestimated costs.”62 A
recent study by Randal O’Toole and Michelangelo
Landgrave looked at the costs of 45 urban rail projects
across the nation since the 1980s.63 They found that, on
average, rail projects doubled in cost between when they
were approved and when they were completed.
Looking internationally at a sample of 58 rail projects,
Flyvbjerg and colleagues found that the average cost
overrun, in constant dollars, was 45 percent.64 On the
benefits of rail projects, they found that ridership was 51
percent less, on average, than originally estimated.
O’Toole and Landgrave find a similar overestimate of
ridership.
Both studies found that cost overruns on rail projects
have not diminished over time. Looking at transportation
projects overall, Flyvbjerg and colleagues concluded, “The
use of deception and lying as tactics aimed at getting
projects started appears to best explain why costs are
highly and systematically underestimated and benefits
overestimated in transport infrastructure projects.”65
One current project with a large cost overrun is the
East Side Access train tunnel in New York City between
Queens and Manhattan. The original proposal in 1999 put
the cost at $4.3 billion and completion by 2009. But now
the project is expected to cost $10.8 billion and be
completed by 2023, as shown in Table 3.66 Federal
taxpayers will pay $2.7 billion of the project’s bill.
Another troubled project is the World Trade Center
rail station in New York. When completed this year, the
station will have cost about $4 billion, double the original
estimate of $2 billion.67 The Wall Street Journal found that
political infighting and the conflicting demands of
numerous government agencies pushed up the costs. It
concluded that the station is “a project sunk in a morass of
politics and government.”68
The morass of transportation bureaucracy is made
worse by federal involvement in state and local projects.
GAO points to the “fragmented approach as five DOT
agencies with 6,000 employees administer over 100
separate programs with separate funding streams for
highways, transit, rail, and safety functions. This
fragmented approach impedes effective decision making
and limits the ability of decisionmakers to devise
comprehensive solutions to complex challenges.”69 By
adding more officials and more paperwork, federal
involvement in state projects reduces accountability and
encourages cost overruns.
Table 3. Sampling of Transportation Cost Overruns
Transportation
Projects
Boston Big Dig70
NYC East Side
Access71
San Francisco Bay
Bridge72
Denver International
Airport73
NYC WTC Rail
Station74
Denver West Light
Rail75
VA-Springfield
Interchange76
Cost Estimate and
Date of Estimate
Original
Recent or
Final
$2.6b
$14.6b
(1985)
(2005)
$4.3b
$10.8b
(1999)
(2014)
$1.4b
$6.3b
(1996)
(2013)
$2.1b
$4.8b
(1990)
(1995)
$2.0b
$4.0b
(2004)
(2015)
$250m
$707m
(1997)
(2013)
$241m
$676m
(1994)
(2003)
Note: m=million, b=billion.
Conclusions
Cost overruns on large government projects are
pervasive. The problem appears to stem from a mixture of
deception and mismanagement, and it has not diminished
over time. One of the consequences is that taxpayers are
likely footing the bill for many projects that cost more than
the benefits delivered. Flyvbjerg argues that cost overruns
result in the “survival of the unfittest,” meaning that
projects with the most exaggerated benefits and low-balled
costs get approved, rather than the most worthy ones. 77
To help cure the cost overrun disease, the federal
government should increase transparency in major
contracting. Agencies should release details about
proposed projects early in the process, and they should
actively solicit critiques of projects from independent
engineers and economists.
Federal agencies should also benchmark the costs and
schedules of proposed projects against similar past projects
to inject more realism into planning.78 And agencies
should perform detailed evaluations of projects after they
are completed, so that policymakers and contractors can
learn from them and avoid mistakes in the future.
The gains from such improved efficiencies would be
large. A McKinsey Global Institute study looked at
hundreds of infrastructure projects worldwide, and found
that productivity could be improved by up to 60 percent by
better project selection, more efficient permitting and
construction, and better use of existing assets.79
In the United States, productivity would be improved
by decentralizing funding and decisionmaking for projects
out of Washington whenever possible. Energy research
should be left to the private sector. Urban transit should be
left to local governments and the private sector. Highway
funding should be left to state governments and the private
sector.
It is true that cost overruns and other inefficiencies are
a risk on all types of large projects, whoever undertakes
them. But the federal government’s track record on major
project management is particularly poor, and many federal
agencies do not learn from past mistakes. By using their
own funding, state and local governments and the private
sector would have stronger incentives to minimize costs
and reduce delays on major investment projects.
1
These issues are discussed in Chris Edwards, “Why the
Federal Government Fails,” Cato Institute Policy Analysis
no. 777, July 27, 2015.
2
The report is excerpted in Chester Collins Maxey, “LogRolling,” Thesis for Master of Arts, University of
Wisconsin, 1914, p. 38. And see Todd Shallat, “Success
through Failure,” Water Resources Impact, American
Water Resources Association, January 2003.
3
Stanley L. Engerman and Kenneth L. Sokoloff, “Digging
the Dirt at Public Expense: Governance in the Building of
the Erie Canal and Other Public Works,” National Bureau
of Economic Research, Working Paper 10965, December
2004, Table 1.
4
Department of Health and Human Services, Office of the
Inspector General, “Federal Marketplace: Inadequacies in
Contract Planning and Procurement,” January 2015, p. 18.
5
A NASA report found, “The final configuration of the
ISS cost more, took longer to complete, and is less capable
than NASA and its partners envisioned. NASA originally
estimated assembly of the station would be complete by
2002 at a total cost to the agency of $17.4 billion.
However, construction was not completed until 2011, and
through fiscal year (FY) 2013 the agency has spent
approximately $74.4 billion.” National Aeronautics and
Space Administration, Office of Inspector General,
“Extending the Operational Life of the International Space
Station Until 2024,” September 18, 2014.
6
Ashley Halsey III, “6 Years Later, Capitol Visitor Center
Puts Out Long-Awaited Welcome Mat,” Washington Post,
December 1, 2008.
7
Government Accountability Office, “VA Construction:
Actions to Address Cost Increases and Schedule Delays at
Denver and Other VA Major Medical-Facility Projects,”
GAO-15-564T, April 24, 2015, p. 4.
8
In Britain, a think tank examined 240 large U.K.
government projects and found an average cost overrun of
38 percent. See Taxpayers’ Alliance, “Out of Control:
How the Government Overspends on Capital Projects,”
November 20, 2009.
9
Bent Flyvbjerg and Allison Stewart, “Olympic
Proportions: Cost and Cost Overrun at the Olympics 1960–
2012,” Saïd Business School Working Papers, University
of Oxford, June 2012.
10
The World Bank, News, “Construction Sector
Transparency Program Goes Global,” November 8, 2012.
11
Bent Flyvbjerg, Nils Bruzelius, and Werner
Rothengatter, Megaprojects and Risk: An Anatomy of
Ambition (Cambridge, UK: Cambridge University Press,
2003), p. 136. The authors discuss some private projects,
but their main focus is government projects.
12
Bent Flyvbjerg, Mette Skamris Holm, and Soren Buhl,
“Underestimating Costs in Public Works Projects: Error or
Lie?” Journal of the American Planning Association 68,
no. 3 (2002).
13
Atif Ansar et al., “Should We Build More Large Dams?
The Actual Costs of Hydropower Megaproject
Development,” Energy Policy 69 (2014).
14
Bent Flyvbjerg, Nils Bruzelius, and Werner
Rothengatter, Megaprojects and Risk: An Anatomy of
Ambition (Cambridge, UK: Cambridge University Press,
2003), p. 16.
15
Stanley L. Engerman and Kenneth L Sokoloff, “Digging
the Dirt at Public Expense: Governance in the Building of
the Erie Canal and Other Public Works,” National Bureau
of Economic Research, Working Paper 10965, December
2004, p. 31.
16
Bent Flyvbjerg, Nils Bruzelius, and Werner
Rothengatter, Megaprojects and Risk: An Anatomy of
Ambition (Cambridge, UK: Cambridge University Press,
2003), p. 45.
17
Bent Flyvbjerg, “Survival of the Unfittest: Why the
Worst Infrastructure Gets Built, and What We Can Do
about It,” Oxford Review of Economic Policy 25, no. 3
(2009), p. 351.
18
Government Accountability Office, “Defense
Acquisitions: Addressing Incentives Is Key to Further
Reform Efforts,” GAO-14-563T, April 30, 2014, p. 8.
19
Andy Medici, “Federal Employee Firings Hit Record
Low in 2014,” www.federaltimes.com, February 24, 2015.
And see Chris Edwards, “Federal Firing Rate by
Department,” Cato@Liberty, Cato Institute, June 6, 2014.
20
Alan Stern, “NASA’s Black Hole Budgets,” New York
Times, November 23, 2008.
21
Bent Flyvbjerg, Mette Skamris Holm, and Soren Buhl,
“Underestimating Costs in Public Works Projects: Error or
Lie?” Journal of the American Planning Association 68,
no. 3 (2002).
22
Quoted in Stanley L. Engerman and Kenneth L.
Sokoloff, “Digging the Dirt at Public Expense:
Governance in the Building of the Erie Canal and Other
Public Works,” National Bureau of Economic Research,
Working Paper 10965, December 2004, p. 29.
23
Antonio Olivo and Katherine Shaver, “Why Costs Often
Creep on Public-Works Projects,” Washington Post, May
14, 2014.
24
Willie L. Brown, Jr, “When Warriors Travel to China,
Ed Lee Will Follow,” San Francisco Chronicle, July 27,
2013.
25
Transbay Transit Center, “FAQs,”
http://transbaycenter.org/project/faqs. And see Central
Subway, “Project Funding/Budget,”
www.centralsubwaysf.com/content/project-fundingbudget.
26
Joseph Fordham, U.S. Naval Institute,
“#PlatformsMatter—The Rebirth of the U.S. Navy: A
Fleet of Frigates to Equal None,” Naval History Blog,
March 27, 2014.
27
James Mann, “The House That War Built,” Washington
Post, June 17, 2007.
28
R. Jeffrey Smith, “Tanker Inquiry Finds Rumsfeld’s
Attention Was Elsewhere,” Washington Post, June 20,
2006.
29
Government Accountability Office, “Defense
Acquisitions: Better Weapon Program Outcomes Require
Discipline, Accountability, and Fundamental Changes in
the Acquisition Environment,” GAO-08-782T, June 3,
2008, p. 1.
30
Government Accountability Office, “Defense
Acquisitions: Addressing Incentives Is Key to Further
Reform Efforts,” GAO-14-563T, April 2014, p. 1.
31
Government Accountability Office, “Defense
Acquisitions: Better Weapon Program Outcomes Require
Discipline, Accountability, and Fundamental Changes in
the Acquisition Environment,” GAO-08-782T, June 3,
2008, p. 5.
32
Government Accountability Office, “Defense
Acquisitions: Assessments of Selected Weapon
Programs,” GAO-15-342SP, March 2015, p. 170.
33
Joachim Hofbauer, Gregory Sanders, Jesse Ellman, and
David Morrow, “Cost and Time Overruns for Major
Defense Acquisition Programs,” Center for Strategic and
International Studies, April 2011.
34
Chong Wang and Joseph San Miguel, “Unintended
Consequences of Advocating Use of Fixed-Price Contracts
in Defense Acquisition Practice,” Naval Postgraduate
School Acquisition Research Symposium, April 30, 2011.
35
Department of Defense, “Performance of the Defense
Acquisition System: 2014 Annual Report,” June 13, 2014.
36
Charles Josef Duch, “Pentagon Purchasing Is Overdue
for an Overhaul,” op-ed, Wall Street Journal, July 23,
2015.
37
Government Accountability Office, “Defense
Acquisitions: Assessments of Selected Weapon
Programs,” GAO-15-342SP, March 2015.
38
Government Accountability Office, “Defense
Acquisitions: Applications of Lessons Learned and Best
Practices in the Presidential Helicopter Program,” GAO11-380R, March 2011.
39
Ibid.
40
Christopher Drew, “Work Halted on Helicopter for
President,” New York Times, May 15, 2009.
41
Government Accountability Office, “Defense
Acquisitions: Better Weapon Program Outcomes Require
Discipline, Accountability, and Fundamental Changes in
the Acquisition Environment,” GAO-08-782T, June 3,
2008, highlights page.
42
Winslow T. Wheeler, The Wastrels of Defense
(Annapolis: Naval Institute Press, 2004), p. 83.
43
These projects were selected from Government
Accountability Office, “Defense Acquisitions:
Assessments of Selected Weapon Programs,” GAO-15342SP, March 2015.
44
For example, see Hans M. Kristensen, “B61-12:
NNSA’s Gold-Plated Nuclear Bomb Project,” Federation
of American Scientists, July 26, 2012.
45
Walter Pincus, “The Explosive Cost of Disposing of
Nuclear Weapons,” Washington Post, July 3, 2013.
46
Steven Mufson, “Energy Secretary is Urged to Halt
Nuclear Fuel Program,” Washington Post, September 9,
2015.
47
Author’s calculations based on Budget of the U.S.
Government, Fiscal Year 2016 (Washington: Government
Printing Office, 2015), Public Budget Database.
48
Government Accountability Office, “Nuclear Waste:
Challenges to Achieving Potential Savings in DOE’s
High-Level Waste Cleanup Program,” GAO-03-593, June
2003, p. 17.
49
Government Accountability Office, “Nuclear Waste:
Action Needed to Improve Accountability and
Management of DOE’s Major Cleanup Projects,” GAO08-1081, September 2008, p. 5.
50
Government Accountability Office, “Hanford Waste
Treatment: DOE Needs to Take Action to Resolve
Technical and Management Challenges,” GAO-13-38,
December 2012, p. 14.
51
Matthew L. Wald, “Higher Costs Cited as U.S. Shuts
Down Coal Project,” New York Times, January 31, 2008.
52
Peter Folger, “FutureGen: A Brief History and Issues for
Congress,” Congressional Research Service, R43028,
April 3, 2013, p. 3.
53
Government Accountability Office, “Hanford Waste
Treatment Plant: DOE Needs to Take Action to Resolve
Technical and Management Challenges,” GAO-13-38,
December 2012, p. 14.
54
Robert Lee Hotz and Lianne Hart, “A Costly Monument
to 'Big Science' Difficulties,” Los Angeles Times, October
21, 1993.
55
Walter Pincus, “The Explosive Cost of Disposing of
Nuclear Weapons,” Washington Post, July 3, 2013.
56
Kenneth Chang and William J. Broad, “Giant Laser
Complex Makes Fusion Advance, Finally,” New York
Times, February 12, 2014.
57
Congressional Budget Office, “Comparative Analysis of
Alternative Financing Plans for the Clinch River Breeder
Reactor Project,” September 20, 1983. The $400 million
initial estimate was from the Atomic Energy Commission.
58
Matthew L. Wald, “Higher Costs Cited as U.S. Shuts
Down Coal Project,” New York Times, January 31, 2008.
59
Burton W. Folsom, Jr. and Anita Folsom, Uncle Sam
Can’t Count (New York: Broadside Books, April 2014),
Chapter 3.
60
Budget of the U.S. Government, FY2016, Analytical
Perspectives (Washington: Government Printing Office,
2015), Table 29-1.
61
Don H. Pickrell, “Urban Rail Transit Projects: Forecast
Versus Actual Ridership and Costs,” U.S. Department of
Transportation, DOT-T-91-04, October 1990.
62
Martin Wachs, RAND Corporation, “Political Aspects
of Forecasting: Explaining and Controlling ‘Optimism
Bias’ in Transportation Forecasts,” U.S. Department of
Transportation Workshop for Transportation Forecasters,
September 2009.
63
Randal O’Toole and Michelangelo Landgrave, “Rails
and Reauthorization,” Cato Institute Policy Analysis no.
772, April 21, 2015.
64
Bent Flyvbjerg, “Survival of the Unfittest: Why the
Worst Infrastructure Gets Built, and What We Can Do
about It,” Oxford Review of Economic Policy 25, no. 3
(2009), p. 346.
65
Bent Flyvbjerg, Nils Bruzelius, and Werner
Rothengatter, Megaprojects and Risk: An Anatomy of
Ambition (Cambridge, UK: Cambridge University Press,
2003), p. 47.
66
Alfonso A. Castillo, “East Side Access Completion Date
Extended—Again,” Newsday, January 27, 2014. And see
Federal Transit Administration, “PMOC Monthly
Report—East Side Access Project,” January 2015, p. 12.
67
Eliot Brown, “Complex Design, Political Disputes Send
World Trade Center Rail Hub Cost Soaring,” Wall Street
Journal, September 3, 2014.
68
Eliot Brown, “Complex Design, Political Disputes Send
World Trade Center Rail Hub Cost Soaring,” Wall Street
Journal, September 3, 2014.
69
Government Accountability Office, “Opportunities to
Reduce Potential Duplication in Government Programs,
Save Tax Dollars, and Enhance Revenue,” GAO-11318SP, March 2011, p. 48.
70
Boston Globe’s “Easy Pass” series of reports by Raphael
Lewis and Sean Murphy,
www.boston.com/globe/metro/packages/bechtel.
71
Alfonso A. Castillo, “East Side Access Completion Date
Extended—Again,” Newsday, January 27, 2014.
72
News to the Next Power, Prepared for the California
Senate Transportation and Housing Committee, “The San
Francisco-Oakland Bay Bridge: Basic Reforms for the
Future,” July 2014, p. 4.
73
Government Accountability Office, “Denver
International Airport,” GAO/T-RCED/AIMD-95-184,
May 11, 1995, p. 6.
74
David Dunlap, “How Cost of Train Station at World
Trade Center Swelled to $4 Billion,” New York Times,
December 2, 2014.
75
Randal O’Toole, “Has RTD’s FasTracks Been Worth It?
No,” Denver Post, op-ed, April 28, 2013.
76
Michael Shear, “Springfield Interchange Project Is
Defended,” Washington Post, November 26, 2002.
77
Bent Flyvbjerg, “Survival of the Unfittest: Why the
Worst Infrastructure Gets Built, and What We Can Do
about It,” Oxford Review of Economic Policy 25, no. 3
(2009).
78
This is called “reference class forecasting.” See Bent
Flyvbjerg, “Survival of the Unfittest: Why the Worst
Infrastructure Gets Built, and What We Can Do about It,”
Oxford Review of Economic Policy 25, no. 3 (2009).
79
McKinsey Global Institute, “Infrastructure Productivity:
How to Save $1 Trillion a Year,” January 2013.
Download