PROJECT NAME PRE-WIRE INSPECTION SIGN-OFF

advertisement
PROJECT NAME
PRE-WIRE INSPECTION SIGN-OFF
EATON’S COOPER CONTROLS
LIGHTING MANAGEMENT SYSTEM
September 2014
Version 1.3
LIGHTING MANAGEMENT SYSTEM
PRE-WIRE INSPECTION SIGN-OFF
1. Review DALI wiring protocol and wiring fundamentals
CHECK
DETAILS
1.1
Control wire length
limitations
1000 Feet Maximum
1.2
Control Wire Class
Only Class 1 and Class 2 wiring
1.3
Bus device limitations


1.4
Topology
1.5
Polarity Free

DONE
()
COMMENTS
DONE
()
COMMENTS
64 DALI Devices
o 8 DALI Sensors
Fixtures can be connected via
o T-Tap
o Star Tap
o Daisy Chain
DALI loops are all polarity free
when connecting 2 conductor
wires
2. Network
CHECK
DETAILS

2.1
CAT5 Network Length
2.2
Building Network
2.3
IP Address Range


No CAT5 cable shall exceed
300ft in length. If runs that
exceed 300ft are required,
either a fiber network is
needed or a CAT5 repeater.
Will the lighting network be
dedicated or connected to the
client network?
Inquire about the IP Range
which the lighting network will
reside in.
__________________________
Page 2/7
LIGHTING MANAGEMENT SYSTEM
PRE-WIRE INSPECTION SIGN-OFF
3. Review drawing submittal package with EC
CHECK
3.1
Confirm Eaton Title Block is on
drawings used by EC.
3.2
Ensure the DALI design
revision matches the latest
submitted by Eaton.
3.3
3.4
3.5
Change Requests
MWS Wiring
User Input Forms/Sequence of
Operations
DETAILS
Ensure the EC is working
from our DALI design. They
will often work directly from
ENG drawings which do not
have all the necessary
details.
When multiple revisions are
required, it is critical that
the latest version is being
used for the install.
Ensure there have been no
change orders which have
been issued to EC but not
incorporated in the latest
DALI design.
Review modular wiring
system (if applicable) with
EC to ensure correct
installation.
Discuss the user input forms
that have been provided to
ensure design team receives
the most up to date
requirements regarding
schedules and sequences of
operation.
Page 3/7
DONE
()
COMMENTS
LIGHTING MANAGEMENT SYSTEM
PRE-WIRE INSPECTION SIGN-OFF
4. Review Install Sign-off Process
CHECK
4.1 Review the use of the DALI
Tester/DBC and provide the
appropriate instructions and
check sheet.
4.2 Ensure EC is aware of lead
times.
DETAILS
Each project will have a
specific check sheet listing all
busses with the associated
devices.
There is a standard 3 week
lead-time required from when
the sign off is received and
techs are onsite.
Page 4/7
DONE
()
COMMENTS
LIGHTING MANAGEMENT SYSTEM
PRE-WIRE INSPECTION SIGN-OFF
5. Review Post Installation Phase (Commissioning, Training, Close Out)
CHECK
DETAILS

5.1 Commissioning Process
Review
5.2 End User/Client Training
5.3 Close out/Commissioning Sign-
off
Address DALI busses
completed and signed-off
 Turn over list of any
deficiencies to EC
 Launch server after
deficiencies rectified
 Full functional check of all
devices, schedules, scenes
Training is typically planned
for after startup in order to
demo the live system.
Once all functional checks are
complete and the client is
content with operation and
training material presented,
commissioning sign off is
obtained.
A full documentation package
is provided after all sign-offs
are complete. Documentation
package includes:
5.4 Eaton Documentation Package






Control intent
Network Details
Design drawings
Datasheets/Manuals
All Sign-offs
Warranty Card
Page 5/7
DONE
()
COMMENTS
LIGHTING MANAGEMENT SYSTEM
PRE-WIRE INSPECTION SIGN-OFF
6. Site Tour
CHECK
6.1 Walkthrough entire site
DETAILS
Visual checks by technician.
(depending on access)
6.2 Discuss timelines to ensure
most accurate dates are with
PM.
Expected Install Completion
date:
___________________
Expected Commissioning Start
date:
___________________
Excellent opportunity to
ensure dates currently with
PM are accurate.
Expected Customer hand-off
date:
___________________
Page 6/7
DONE
()
COMMENTS
LIGHTING MANAGEMENT SYSTEM
PRE-WIRE INSPECTION SIGN-OFF
I acknowledge that a qualified Eaton employee has reviewed all pre-wire checks described
above and detailed the process in which commissioning and start-up will be executed.
NAME:
SIGNATURE:
DATE:
ROLE:
COMPANY: