SECTION 27 08 00
COMMISSIONING OF COMMUNICATIONS SYSTEMS
SPEC WRITER NOTES:
1. Edit this specification section
between //____//, to fit project, or
delete if not applicable.
2. Contact VA’s AHJ, Spectrum Management
and COMSEC Service (SMCS 005OP2H3),
(202-461-5310), for all technical
assistance.
3. Included throughout this specification
are references to system’s interface
capability and various related
features. System designer must verify
availability of this system and
coordinate associated requirements and
subsequent interfaces.
4. Spec writer must review the Physical
Security Design Manual for VA
Facilities to determine and include in
this section any Mission Critical or
Life Safety requirements called out.
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section includes requirements for commissioning facility
communications systems, related subsystems and related equipment.
This
Section supplements general requirements specified in Section 01 91 00,
GENERAL COMMISSIONING REQUIREMENTS.
B. Complete list of equipment and systems to be commissioned is specified
in Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS and
Specification 27 05 11, REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS.
C. Commissioned Systems:
1. Commissioning of systems specified in Division 27 // and 28 // is
part of project’s construction process including documentation and
proof of performance testing of these systems, as well as training
of VA’s Operation and Maintenance personnel in accordance with
requirements of Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS
and Division 27, in cooperation with Government and Commissioning
Agent.
2. The facility exterior closure systems commissioning includes
communications systems listed in Section 01 19 00 GENERAL
COMMISSIONING REQUIRMENTS and 27 05 11, REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS.
1.2 RELATED WORK
A. System tests: Section 01 00 00, GENERAL REQUIREMENTS.
27 08 00 - 1
06-01-15
B. Commissioning process requires review of selected submittals that
pertain to systems to be commissioned: Section 01 33 23, SHOP DRAWINGS,
PRODUCT DATA AND SAMPLES.
C. Construction phase commissioning process and procedures including roles
and responsibilities of commissioning team members and user training:
Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.
1.3 COORDINATION
A. Commissioning Agent will provide a list of submittals that must be
reviewed by Commissioning Agent simultaneously with engineering review;
do not proceed with work of sections identified without engineering and
Commissioning Agent’s review completed.
B. Commissioning of communications systems require inspection of
individual elements of communications system construction throughout
construction period. Coordinate with Commissioning Agent in accordance
with Section 01 19 00, GENERAL COMMISSIONING REQUIREMENTS and
commissioning plan to schedule communications systems inspections as
required to support the commissioning process.
1.4 CLOSEOUT SUBMITTALS
A. Refer to Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS for
submittal requirements for pre-functional checklists, equipment startup
reports, and other commissioning documents.
B. Pre-Functional Checklists:
1. Complete pre-functional checklists provided by commissioning agent
to verify systems, subsystems, and equipment installation is
complete and systems are ready for Systems Functional Performance
Testing.
2. Submit completed checklists to COR and to Commissioning Agent.
Commissioning Agent can spot check a sample of completed checklists.
If Commissioning Agent determines that information provided on the
checklist is not accurate, Commissioning Agent then returns the
marked-up checklist to Contractor for correction and resubmission.
3. If Commissioning Agent determines that a significant number of
completed checklists for similar equipment are not accurate,
Commissioning Agent can select a broader sample of checklists for
review.
4. If Commissioning Agent determines that a significant number of
broader sample of checklists is also inaccurate, all checklists for
27 08 00 - 2
06-01-15
the type of equipment will be returned to Contractor for correction
and resubmission.
C. Submit training agendas and trainer resumes in accordance with
requirements of Section 01 19 00, GENERAL COMMISSIONING REQUIREMENTS.
PART 2 - PRODUCTS - NOT USED
PART 3 - EXECUTION
3.1 FIELD QUALITY CONTROL
A. Contractor's Tests:
1. Scheduled tests required by other sections of Division 27 must be
documented in accordance with Section 01 00 00, GENERAL
REQUIREMENTS.
2. Incorporate all testing into project schedule. Provide minimum seven
calendar days' notice of testing for Commissioning Agent to witness
selected Contractor tests at sole discretion of Commissioning Agent.
3. Complete tests prior to scheduling Systems Functional Performance
Testing.
B. Systems Functional Performance Testing:
1. Commissioning process includes Systems Functional Performance
Testing that is intended to test systems functional performance
under steady state conditions, to test system reaction to changes in
operating conditions, and system performance under emergency
conditions.
2. Commissioning Agent prepares detailed Systems Functional Performance
Test procedures for review and acceptance by COR.
3. Provide required labor, materials, and test equipment identified in
test procedure to perform tests.
4. Commissioning Agent must witness and document the testing.
a. Provide test reports to Commissioning Agent. Commissioning Agent
will sign test reports to verify tests were performed.
3.2 TRAINING
A. Training of Government's operation and maintenance personnel is
required in cooperation with COR and Commissioning Agent.
B. Provide competent, factory authorized personnel to provide instruction
to operation and maintenance personnel concerning location, operation,
and troubleshooting of installed systems.
C. Schedule instruction in coordination with COR after submission and
approval of formal training plans.
- - - E N D - - -