Addendum #1 New Residence Hall Site Package Alabama A & M University

advertisement
Addendum #1
New Residence Hall Site Package
Alabama A & M University
May 03, 2016
Prepared by 4Site (Civil Engineer) and Moody Nolan (Architect)
This revision forms a part of and modifies the Bidding Documents dated April 22, 2016, and is to
be acknowledged in the Proposal Form. This addendum consists of 2 pages and 12
attachments. The descriptions below are intended as a summary only of the changes to the
Drawings. Bidders are required to incorporate all clouded changes to the Drawings into their
Bid, regardless of whether or not the changes are listed below.
CHANGES TO DRAWINGS:
1. C101
a.
2. C102
a.
3. C103
a.
b.
Added “Materials Testing” notes to “General Notes”
Added notes clarifying the scope of demolition work for the site contractor
Added new pedestrian bridge to cross existing creek
Added new sidewalk to connect front door entrance (northern most door) to side
door entrance sidewalk on the north side of the building
c. Added notes clarifying the scope of site contractor versus building contractor
d. Relocated fire hydrants to curb islands
4. C104
a. Relocated fire hydrants to curb islands
b. Relocated “yard hydrant” to NW corner of the mechanical yard
c. Relocated water line connections (domestic and fire) to building
d. Added notes clarifying the scope of site contractor versus building contractor
e. Added new sidewalk to connect front door entrance (northern most door) to side
door entrance sidewalk on the north side of the building
5. C105
a. Added (3) benchmark locations
b. Added spot elevations in the pad to create “crown” for positive drainage
c. Reduced high point elevation in courtyard area
6. C106
a. Added note regarding stabilization of building pad
7. C107
a. Added notes clarifying the scope of site contractor versus building contractor
b. Added extents and details for grading the storm shelter pit
8. C108
a. Added orifice and stub pipe information to structure “C2A”
9. C109
a. Added standard curb and gutter detail
10. C110
a. Added straw wattle detail
11. C111
a. Added all sanitary sewer details
12. L101
a. Added irrigation sleeves to the landscape plan
b. Revised landscape beds at entrance of building, added shrubs and groundcover.
c. Updated the plant schedule
CHANGES TO THE SPECIFICATIONS:
1. Section 00 40 00 Notice and Instructions to Bidders—Replace the first page with the page
attached to this addendum.
2. 01 50 00 Temporary Facilities and Controls- Add Section 1.05 H, as follows:
Contractor will provide a location for Construction Manger to setup and occupy a single wide
trailer for the duration of the project. Contractor will provide temporary utility connections to
this trailer.
CLARIFICATIONS:
1. Construction fence to remain in place for the duration of the Sitework and the Building projects,
until the Owner occupies the Building.
2. ADEM fee will be paid by the Owner.
3. Geotechnical Report is included for reference.
4. 00 40 01 Proposal Form— Acknowledge all addenda received by listing each number in the box
next to “Addenda Received”
5. Davis Bacon Wage Rates- The University provides the following link
http://www.dol.gov/whd/regs/compliance/whdfs66.pdf
6. Attendance at Pre-Bid meeting is not mandatory.
ATTACHMENTS:
C101 – Project Notes
C102 – Demolition Plan
C103 – Site Development Plan
C104 – Utility Plan
C105 – Grading Plan
C106 – Erosion Control Plan
C107 – Storm Shelter Grading Plan
C108 – Storm Sewer Plan
C109 – Construction Details
C110 – Construction Details
C111 – Construction Details
16-0194 Subsurface Geo Exploration dated April 4, 2016
SP 00 40 00 --PAGE 1 ONLY--Addendum 1.pdf
END OF ADDENDUM # 1