16-009 - UC 304 Remodel Addendum No. 1

advertisement
Addendum No. 1
16-009 - UC 304 Remodel
Date:
Thursday, November 19, 2015
To:
All Bidders
From: University of Colorado at Colorado Springs
Facilities Planning and Construction
Clarifications:
1. Sheet CS: Schedule, Work Hours and Building Access: Hours of construction should be within schedule below
unless otherwise arranged with Project Manager.
Nov. 30-Dec 18
M-Th 7:00am – 10:30pm
F-Sat 7:00am - 11:30pm
Sun
12:00pm - 9:00pm
Dec. 19 – Jan. 18
M-F
7:30am – 7:00pm
Sat
8:00am - 6:00pm
Sun
closed
2. Ceiling tile to be used:
Armstrong Fine Fissured; 2x2 or 2x4 Angled Tegular
Facilities Services/Planning and Construction
1420 Austin Bluffs Pkwy • Colorado Springs, CO 80918
t 719-255-3505 • f 719-255-3222
3. Is a VAV required to control the air flow at each heat coil? System is a constant volume and a balancing
damper will be required at each new take off and installed between take off and new RHC.
4. Please provide a model # for the heat coils. Carrier is listed but they are saying they cannot provide. Carrier
provides the coils through a third party. A cutsheet of the coils selected during the design phase is
attached. Carrier contact is Doug Amerine; Inside Equipment Sales Office: (719) 444-0505.
5. Are the T- stats local or connected to a building controlled system? I would suggest that the new coil
control components (valves, actuators and balancing valves) and the room temperature sensor match the
existing control components. UCCS Existing control system is Setpoint.
Facilities Services/Planning and Construction
1420 Austin Bluffs Pkwy • Colorado Springs, CO 80918
t 719-255-3505 • f 719-255-3222